American Electric Power Company, Inc. (AEP) Earnings Call Transcript & Summary

October 28, 2026

NASDAQ US Utilities Electric Utilities earnings 61 min

What were the key takeaways from American Electric Power Company, Inc.'s October 28, 2026 earnings call?

In the third quarter of 2026, American Electric Power (AEP) reported operating earnings of $2.23 per share, a significant increase from $1.80 per share in the same quarter last year, driven by strong demand growth and constructive regulatory outcomes. The company raised its full-year operating earnings guidance to be at or above the high end of the previously increased range of $6.25 to $6.55 per share. AEP also introduced a new long-term expected annual operating EPS growth rate of 9% to 11% for 2027 through 2031, supported by a robust $100 billion capital plan aimed at enhancing the reliability and resilience of its electric service.

What topics did American Electric Power Company, Inc. cover?

  • Increased Earnings Guidance: AEP now expects full-year operating earnings to be at or above the high end of the guidance range of '$6.25 to $6.55 per share'. This reflects strong year-to-date performance and confidence in execution plans.
  • Long-Term Growth Outlook: The company introduced a new expected annual operating EPS growth rate of '9% to 11%' for 2027 through 2031, an increase from the previous range of 7% to 9%. This indicates a stronger growth trajectory supported by a substantial capital plan.
  • Capital Investment Strategy: AEP announced a $100 billion 5-year capital plan, which is one of the largest in the industry, aimed at enhancing system safety, reliability, and resilience. This plan is expected to nearly double the rate base from '$87 billion in 2026 to $162 billion by 2031'.
  • Contracted Load Growth: The company reported an increase in contracted load to '84 gigawatts', up from 69 gigawatts, driven by projects like the Piketon project. This growth is expected to support future capital investments and earnings.
  • Customer Affordability Initiatives: AEP highlighted that fully executed take-or-pay ESAs are expected to generate up to '$21 billion' in benefits for existing residential customers, up from $16 billion previously discussed. This illustrates the company's commitment to balancing growth with affordability.

What were American Electric Power Company, Inc.'s October 28, 2026 results?

  • Operating Earnings Per Share: $2.23 (compared to $1.80 per share in the third quarter of 2025)
  • Rate Base Increase: $162 billion (up from $87 billion in 2026 by 2031)
  • Contracted Load: 84 gigawatts
  • Benefits for Residential Customers: $21 billion

AEP's strong earnings performance and robust growth outlook position it favorably within the utility sector. The substantial capital plan and increased contracted load provide a solid foundation for future earnings growth. Investors should monitor the execution of the capital plan and the regulatory environment, particularly in Texas, as potential catalysts for continued performance.

Earnings Call Speaker Segments

Andy Gurgol

executive
#1

Good morning, everyone, and thank you for joining us for American Electric Power's Third Quarter 2026 Earnings Call. You can access a live webcast of this teleconference along with the slide presentation on our website, in the Events and Presentations section. With me today are Bill Fehrman, our Chairman, President and Chief Executive Officer, and Trevor Mihalik, our Chief Financial Officer. We also have other members of our management team here in the room, including Kate Dixon, Senior Vice President, Controller and Chief Accounting Officer, and Darcy Reese, Vice President, Investor Relations. During the call we'll be making forward-looking statements. Actual results could differ materially from those projected in any forward-looking statements we make today. The factors that could cause our actual results to differ materially are discussed in the company's most recent SEC filings. Please refer to the presentation slides accompanying this call for a reconciliation to GAAP measures. We'll take your questions after the opening remarks. Please turn to Slide 5 as I hand the call over to Bill.

Bill Fehrman

executive
#2

Much appreciated, Andy, and hello everyone—glad you could join our Q3 2026 earnings call. I'll begin by briefly walking through how we performed in the third quarter, after which I'll highlight what sets AEP's portfolio apart and explain how those strengths are driving continued above-market growth and unique value for both customers and shareholders. Slides 5 and 6 lay out our refreshed strategic outlook along with the financial plan. Let me be clear: AEP is in a very strong position to seize what lies ahead. I'd call our leadership team best-in-class, we have solid ties with state lawmakers and regulators, we're sharply focused on financial performance, our balance sheet is strong, and accountability driven by execution runs across the whole organization. Add to that the size, scale and diversification of our portfolio, and AEP delivers dependable, affordable electric service, makes the growth investments our customers require, and builds significant long-term value for shareholders. Today we're glad to share a new long-term target: expected yearly operating EPS growth of 9% to 11% for 2027 through 2031. We also anticipate a compound yearly growth rate above 10% out to 2031, measured off the midpoint of our initial 2026 guidance. That projection rests on a five-year capital program totaling $100 billion—among the biggest in our sector—and it is grounded in substantial, lasting spending on making our system safer, more reliable and more resilient, especially in generation and transmission. To help enable that expansion, during the quarter just ended we completed commercial contracts for the Wyoming fuel cell project as well as the 765 kV transmission build at Piketon, Ohio, which lets us fold both into the revised capital plan. Work is progressing steadily on the Wyoming fuel cell project, backed by a 20-year power purchase agreement with Google. The Piketon project has a 20-year offtake agreement with SB Energy behind it—that agreement will cover the project cost, and it's backed by a counterparty with a high rating and investment-grade status. Construction is expected to start in the first quarter of 2027; we've secured substantially all of the rights of way and intend to submit the required regulatory filing shortly. We're also glad to report that AEP posted third quarter 2026 operating earnings of $2.23 per share, or $1.2 billion. With that, we now feel confident in expecting full year operating earnings at or above the top end of the 2026 guidance range we recently raised to $6.25 to $6.55 per share. With the visibility we have into our growth and the confidence we hold in our execution plans, we're excited to share operating earnings guidance ranges for 2027 and 2028 of $6.75 to $7.05 per share and $7.40 to $7.70 per share, respectively. Compared with the prior year, the midpoints of these ranges imply an increase of roughly 9.5% based on the original 2026 guidance midpoint. Later in the call, Trevor will walk through the drivers of third quarter performance and provide additional details regarding our updated financial plan and long-term outlook. Please turn to Slide 7. The U.S. utility sector is seeing an electric demand surge unlike anything before, and AEP sits squarely at the heart of that opportunity. With the amount of contracted and committed load across our service territory, we anticipate demand on our system will more than triple by 2031, driven by considerable economic development activity throughout our footprint. What distinguishes AEP isn't just how large that growth is, but where it's happening. The 11 states where we operate produce about 1/4 of U.S. GDP and are drawing major investment from data centers, manufacturing activity and energy infrastructure; these trends are producing a durable rise in electricity demand and generating substantial opportunities for long-term infrastructure investment. Importantly, the states AEP serves combine robust business fundamentals with backing from state political leadership, constructive regulation and strong investment recovery mechanisms. Solid demand growth, sensible regulation, and clear cost-recovery structures all combine to position AEP well for seizing this growth opportunity, and they mirror the traits investors continue to reward with premium valuations. Turning to Slide 8. AEP's size, know-how, and transmission leadership—particularly in 765 kV infrastructure—deliver a durable and steadily more valuable strategic edge. We own and run the nation's biggest transmission network, which lets us pursue substantial organic growth while giving customers a distinctive single-provider solution spanning several RTOs and states. AEP was the first to develop the 765 transmission system in North America and has invested more than 6 decades honing the capabilities, expertise, and institutional knowledge required to operate and expand this infrastructure efficiently at scale. That background continues to fuel innovation now. As an illustration, our engineers lately came up with fresh proprietary designs that meaningfully reduce tower height as well as right-of-way needs, enabling 765 kV infrastructure to go in with physical traits mostly comparable to 345 kV transmission yet carrying 6x the electricity. Such innovations strengthen our capacity to provide transmission solutions with greater efficiency, serve rising customer demand and generate differentiated value for our customers, communities and shareholders. Kindly turn to Slide 9. A key strength of our growth plan is that it simultaneously enables investment and keeps things affordable: when new large load customers join our system, the added revenue they bring helps cover fixed costs that existing residential customers would otherwise bear. With fully executed take-or-pay ESAs in hand, we now project as much as $21 billion in benefits to existing residential customers at our vertically integrated utilities over the contracts' full term. That figure is higher than the $16 billion mentioned on AEP's previous earnings call. The result is a strong virtuous cycle in which economic development and load growth help make service more affordable for customers—and we are already witnessing that dynamic unfold in real time. Indiana saw significant new large load expansion, which let us submit a second rate reduction filing during the quarter just ended. Put simply, responsible handling of growth can deliver gains for customers and shareholders alike. Next I want to touch briefly on AEP's nuclear strategy at its early stage. During the last week, we disclosed a development agreement with 2 exceptional companies, X Energy and Amazon, to evaluate a potential small modular reactor project sited in Indiana — the only early-stage nuclear effort we are advancing right now. Worth emphasizing: our pact with X Energy and Amazon encompasses development and feasibility work alone, requiring only minimal investment on AEP's part. Before any final investment decision gets made, a prospective project would have to pass successfully through a number of stage gates. That decision could come no sooner than some point in 2030, assuming we meet explicit strategic and financial goals. And as we have said all along about how we pursue nuclear development, we stay highly disciplined so that our existing customers, shareholders and balance sheet are protected. Kindly go to Slide 10. For AEP, this year has been exceptionally productive up to now, as we keep acting with urgency to serve our customers and seize what we see as a growth opportunity that comes once in a generation. With our scale, diversification and presence in several of the most attractive growth markets across the country, AEP is positioned exceptionally well to generate sustainable long-term value for customers and shareholders alike.

Bill Fehrman

executive
#3

To fulfill what we've promised, we're moving projects forward using standardized designs, buying long-lead equipment early, drawing on long-standing key relationships with industry leaders including <<inaudible>>, GE Renova and Mitsubishi, and a formalized partnership with Quanta, backed by decades of experience in designing, building and operating large-scale infrastructure; these key suppliers are supplying the top craft labor teams, manufacturing capacity and technical expertise required to carry out our plan with speed and certainty. One of the main ways we deliver results is by partnering with our states to secure favorable regulatory rulings and better cost recovery across the portfolio. In Texas, a unanimous settlement—constructive in nature—was submitted in SWEPCO's base rate case, featuring a proposed ROE of 9.53%, an increase from 9.25%, along with a proposed equity layer of 51.98%, up from 49.4%. This positions SWEPCO well to advance its growth plans and to bolster electric service that is safe, reliable, and affordable for customers. Over in Virginia, APCO submitted a constructive settlement in its rate case, with a proposed ROE of 9.8%, a slight increase from 9.75%. There are two main elements to this settlement. First, a significant share of operating costs—vegetation management among them—would move out of base rates and into annual riders, which cuts down on earnings lag. Second, base rates should decline during the first year after an order, which further backs the push to keep service affordable for customers. To sum up, the main point is straightforward: we're not preparing to put this plan into action—we're already far along in carrying it out. Our experience, our partnerships and our operational capabilities are all in place, so we can deliver this plan at the speed customers require and generate distinctive long-term value for shareholders. My confidence in the group we've brought together, the plan we're carrying out, the progress we've achieved, and the prospects in front of us couldn't be stronger. On that note, I'll hand things over to Trevor, who'll take you through how we did financially in the third quarter and share more specifics about our long-term growth and financial outlook. Trevor?

Trevor Mihalik

executive
#4

Thank you, Bill. I'll start by walking through our financial results, and then I'll go over our updated financial plan, beginning with the higher long-term earnings growth rate. I'll also cover specifics on the capital plan, rate base growth and financing strategy, and I'll close by explaining why we think AEP is positioned unlike any other to seize the substantial growth opportunities throughout our footprint. Please turn to Slides 12 and 13 in the presentation. In the third quarter of 2026, AEP posted operating earnings of $2.23 per share, versus $1.80 per share in the third quarter of 2025. Every segment delivered higher earnings than a year earlier, fueled by constructive regulatory outcomes, robust demand growth across our footprint, and ongoing transmission and generation buildout. And as Bill mentioned, because of our strong performance year-to-date, we anticipate full year operating earnings at or above the top end of our 2026 guidance range of $6.25 to $6.55 per share. Looking toward 2027, you'll see that our operating earnings guidance on Page 22 in the appendix now includes a new segment, AEP infrastructure. That reflects how the generation and marketing business has evolved toward infrastructure investments backed by contracted and highly predictable cash flows. A solid example is the fuel cell project in Wyoming announced recently, which is supported by a 20-year take-or-pay PPA with Google. The new AEP infrastructure business combines our contracted generation assets, legacy PPAs and other infrastructure investments into one reporting segment. Looking forward, we expect this business to gravitate toward projects backed by high-quality, long-term contracts. Moving to Slide 14. The key takeaway from today's update is that we're embarking on the next chapter of AEP's growth story with more confidence than ever in both the size and the durability of our long-term growth opportunity. In the past, we provided only the prompt year of earnings guidance. Today, we're giving you more visibility into our expected financial performance, with guidance ranges for 2027 and 2028 alike. That confidence extends well past the near term. We are now raising our expected annual operating EPS growth rate to 9% to 11% through 2031, an increase from our earlier 7% to 9% range. We're also lifting our expected 5-year operating earnings CAGR to greater than 10% through 2031. The breadth and durability of opportunities throughout our portfolio give us confidence that our growth continues well beyond the 5-year plan. So we are likewise projecting a 10% operating earnings CAGR through 2033, measured off the original 2026 guidance midpoint. Today's update marks a meaningful step change in AEP's growth profile. We're growing faster, and with more visibility, than at any point before, which further underscores AEP's position as one of the premier high-growth companies in the utility sector. And we're accomplishing this while staying focused on improved reliability and affordability. Please turn to Slides 15 through 17. As Bill pointed out, we're excited to introduce our $100 billion 5-year capital plan through 2021, one of the largest investment programs in the utility industry. Under this updated capital plan, we anticipate rate base rising from $87 billion in 2026 to $162 billion by 2031, which is close to a doubling across the next 5 years. That works out to a rate base CAGR above 13%, compared with 11% under our earlier 2026 through 2030 capital plan. This anticipated acceleration in growth is especially apparent starting in 2028 and 2029, when major generation and transmission projects enter service. Transmission continues to be among AEP's most appealing investment opportunities, given the scale and strategic benefit of running the country's largest transmission business. Our transmission capital plan has grown to $37 billion through 2031 and now incorporates the Piketon project in Ohio. We anticipate transmission rate base almost doubling across the next 5 years, reaching close to $70 billion by 2031. Now on generation. Our revised plan includes $36 billion of investment through 2031. Regulated gas generation is the biggest opportunity, rising by $7 billion compared with the earlier 5-year capital plan. The logic is straightforward: contracted customer demand is expanding more quickly than the operating output of our current fleet, which creates an obvious and lasting need for new baseload dispatchable generation. Importantly, these generation investments are backed by fully executed take-or-pay ESAs within the VI us, giving us a higher level of confidence in the underlying demand. They also gain from constructive regulatory and cost recovery frameworks, such as Oklahoma's generation pre-approval mechanism, which permits concurrent rider and construction work in progress recovery. Lastly, distribution investment has risen to $22 billion over the next 5 years, concentrated on grid modernization, reliability, resiliency and infrastructure replacement. These are foundational investments needed to strengthen the system and serve customers efficiently. Equally important is the quality of investment recovery. About 90% of planned utility investments is expected to be recovered through reduced lag mechanisms, including riders, trackers and 4 test year rate cases; these constructive frameworks give greater cash flow and earnings visibility while enabling more timely recovery of invested capital. All together, this $100 billion 5-year capital plan represents a substantial expansion of our investment opportunity, backed by contracted customer demand, highly visible transmission investments and essential distribution infrastructure needs. Moving to Slide 18; we now have 84 gigawatts of incremental contracted load through 2031. That is a 15 gigawatt increase over the 69 gigawatt contracted load we described on our second quarter earnings call. This step change comes from adding Piketon and other ESAs signed since late July. Altogether, we now have 35 gigawatts of incremental contracted load backed by firm take-or-pay ESAs; that leaves just 3 gigawatts not under take-or-pay ESAs in PJM and SPP, which we expect to be converted in the near term. And in our view, our entire 46 gigawatts of contracted load is backed by fully executed SP6 compliant letters of agreement. Tying it back to the new financial outlook. The contracted load we have signed in PJM and SBP is largely reflected in the capital plan. When it comes to AEP Texas, we keep seeing substantial opportunities for investment. That said, we're being deliberate about adding capital into the plan while the batch process and wider transmission planning work continues. So the bulk of our Texas plan centers on system reliability and resiliency, and only part of the transmission buildout that Texas needs is included, among which is the recently approved Howard <<inaudible>> line. As those processes move forward, we anticipate securing further capital opportunities in Texas. We also expect incremental generation investment opportunities, thanks to strong customer demand along with ongoing growth in organic and competitive transmission. All together, these upside opportunities give us a long runway for capital investment and earnings growth down the road. Moving to Slide 19. Strong operating cash flow and a disciplined financing strategy underpinned our expanded capital plan. As the slide notes, across the 5-year forecast period we expect to produce roughly $55 billion of cash from operations. That cash flow, strong and growing, is a significant funding source for our investment program and covers more than half of our $100 billion capital plan. Beyond that, we stay committed to returning capital to shareholders via consistent dividend growth. One key differentiator of our financing plan is the comparatively modest incremental equity requirement.

Trevor Mihalik

executive
#5

Since we've been proactive in raising equity during the past several years, we've built considerable financing flexibility, and we expect to fund growth with substantially less equity than the industry's typical 30% to 40%. To be specific, we've increased our capital plan by $22 billion while adding just $5.2 billion in equity funding. What that means is that 24% of the incremental investment is anticipated to come from new accretive growth equity. It's also worth pointing out that $2.5 billion of the incremental equity assumption is tied to marketed growth equity across the next 2 years of the plan. Put simply, we're funding a much bigger investment opportunity with only modest equity needs in order to maximize shareholder value. We enter this period financially strong. At both Moody's and S&P, our FFO to debt sits within the 14% to 15% target range and well above the 13% downgrade threshold — a reflection of the substantial progress we've made over the past several years. Combined with robust operating cash flow, that gives us a solid footing to carry out our plan while maintaining a strong balance sheet. Now please turn to Slide 20, where I'll close with a quick recap of today's messages: First, you heard that the business is performing exceptionally well. The solid results we posted for the third quarter show what disciplined execution, favorable regulatory outcomes, rising customer demand and ongoing investment throughout the business can deliver. In fact, the momentum we see companywide gives us confidence that 2026 operating earnings will land at or above the top of the guidance range. Next, you heard about our continued expansion of the investment opportunity. With our new $100 billion 5-year capital plan, we expect rate base to almost double, reaching $162 billion by 2031. And third, you heard that this new update represents a meaningful uplift in AEP's growth profile. For the 2027 through 2031 period, we're lifting our projected yearly operating EPS growth rate to a range of 9% to 11%, and over that same stretch we're also raising our anticipated long-term operating earnings per share CAGR to above 10%. On top of that, because of the strong growth we're seeing throughout our portfolio, we anticipate that growth carrying on well into the next decade — we're projecting a 10% operating earnings CAGR through 2033, measured from the midpoint of the original 2026 guidance. And finally, as you heard, we're still dedicated to striking a balance between growth and affordability. By way of large low tariffs, infrastructure arrangements funded by customers, and other creative structures, we're working to let new growth help pay for the investments we need while also producing meaningful affordability gains for our existing customers. We now expect the fully executed take-or-pay ESAs in the vertically integrated utilities to produce as much as $21 billion in fixed cost offsets for existing residential customers over the life of the contracts, up from the $16 billion we announced previously. Stepping back, the investment thesis is simple. Among utility companies, AEP stands out as one of the largest and most prominent growth opportunities, supported by enduring capital plans, favorable regulatory structures, strong execution capabilities, and a disciplined financial approach. In our view, these strengths position us to deliver top-tier growth, generate a 12% to 14% annual total shareholder return through 2031, and create substantial long-term value for our customers and our shareholders alike. With that said, I'll turn things over to the operator now so we can open the lines and take your questions.

Shahriar Pourreza

analyst
#6

Congratulations—these are tremendous results. Bill, $100 billion in CapEx is obviously a very large figure. Your guidance now points to a CAGR of 10-plus percent through '31. Could you help paint a clearer picture of what could drive that "plus"? In other words, does Texas take you beyond 10% or extend the 10% runway, and why should I assume the CAGR drops to 10% through '33, given this strong plan? Is that the law of large numbers, or simply near-term caution?

Bill Fehrman

executive
#7

Yes. I really appreciate that question. Clearly, we see a very substantial pipeline of potential investment opportunities out there that exceeds the capital plan we just discussed. Particularly in transmission and generation. To address what you raised: regarding transmission, there's more 765 kV coming in Texas, plus projects coming out of SPP's integrated transmission plan. We're heavily involved in the competitive RFPs, and beyond that, organic growth continues throughout the system. On generation, extremely strong load growth combined with upcoming plant retirements we have ahead creates a substantial and highly visible requirement for new gas plants. So when you put it all together, our long-term investment pipeline stays exceptionally strong well into the next decade. Teaming up with Trevor and the group here, and with the clarity we now have plus our determination to get this done, I feel very confident we can hit that 10% EPS CAGR all the way through 2033. Naturally, we'll keep sharpening that figure as things move along; our aim is to promise conservatively and then beat expectations. So I'm glad to offer you that kind of forward visibility, and I'm genuinely confident about the position we're in.

Shahriar Pourreza

analyst
#8

Then there's the 300 basis points of lag between rate base and the EPS CAGR. Clearly, financing plays a key role in that. Could you give us some sense of the timing around equity, and whether any equity is needed in '26? I'd have to think the cash flow profile that comes with these large load customers makes things easier and gives you more flexibility, particularly if they're paying some upfront. So I'm just curious about the timing of equity.

Trevor Mihalik

executive
#9

Yes, Shar, it's Trevor. I'll handle that question. Look, one thing we've done — and we talked about it in the prepared remarks — is that we've been very forward leaning on the equity side, and we currently have more than $5 billion of equity forwards in place supporting this capital plan; doing that has given us a great deal of flexibility. What we're looking at right now is keeping the ATM option available to us. And then we sort of layered in that $2.5 billion, which we'll do at some point over the next 2 years in support of this plan. But what you'll probably see us do is bring some of that equity forward that had gone out all the way to '28 — we'll utilize those equity forwards. And then at some point over the next 2 years, we will either go to the market and do a block equity or equity-linked securities, or we'll keep running the ATM. When you looked at us this last year, we said we'd do $1 billion of ATM, and we got that $1 billion done well before the end of the third quarter. So there's plenty of opportunity for us to obtain that equity through multiple different structures. And again, I think we've been very conservative in making sure that the equity we do issue is done in a very shareholder-friendly way. So given how proactive we've been, it's given us a great deal of flexibility.

Steve Fleishman

analyst
#10

First off, regarding the generation builds in Indiana and at APCO, will those sit within the regulated businesses? Or are they still being looked at for something like the Genco structure?

Bill Fehrman

executive
#11

We still see the Genco concept as quite favorable, and we are actively assessing where it can deliver the most value for customers. We are also finishing a detailed evaluation of which jurisdictions would be best suited for a Genco structure from a regulatory standpoint. We are making sure to socialize this with our regulators and our state policy makers, but given how urgent it is to meet growing customer demand, our focus right now has been on securing the load and moving forward with generation investments needed to support that growth in the vertically integrated utilities, and the financial plan we laid out today also preserves that flexibility; and so should the Genco structure emerge as a viable pathway in any given state, particularly West Virginia and Indiana, we could ultimately look to house a portion of the planned or future gas plants in that framework. And so continuing to work at continuing to socialize and making sure we have the proper regulatory and other support in the states where we view these as most interesting.

Steve Fleishman

analyst
#12

All right, great. And then perhaps just regarding — I think if I read it correctly, of the 84 gigawatts of load you have locked up, only 35 of that is kind of baked into your plan. Is that right?

Trevor Mihalik

executive
#13

Yes, Steve. So what you have watched us do is grow contracted load from 69 to 84. Most of that is really the Piketon project, which accounts for 9 gigs, and then there are an additional 2 gigs in Ohio and 2 gigs in APCO, plus a gig in PSO; so what we are seeing is strong growth there. But what you are really looking at, and I think the heart of your question is, is when we look at Texas, what is really kind of in the plan tied to the 45 gigs or the 46 gigs we have under LOAs. And generally, what we are seeing there.

Steve Fleishman

analyst
#14

That is the question.

Trevor Mihalik

executive
#15

Yes, yes. So what we are seeing there is a chance to keep putting money into Texas. At present, most of that is really the Texas Capital plan, which is $17 billion, and it has been built and centered on boosting the reliability and resiliency of the system, so there is really incremental investment to grow around the ERCOT 765 system, like the Panhandle RPG initiative, and that spending is not part of the plan. So I would say what you are looking at is probably a fairly conservative capital plan in Texas, particularly when it comes to the incremental LOAs that we have tied to Texas.

Julien Dumoulin-Smith

analyst
#16

I have to agree with what's been said so far—all in all, this is a pretty impressive result. As you put it, you truly delivered high quality. That said, let me actually take up where Steve stopped there, okay? To begin with, how do you view recutting that Texas discussion with respect to Batch 0 versus Batch 1, given that a portion of the upside you just referred to—what's included versus excluded from the plan—could genuinely come in when you look at those Batch 1 filings as early as next year, and that would fall inside the 5 years, definitely inside the 7-year window. Would you speak a bit about the timing for when some of this additional load might begin to solidify, if you follow what I mean. I don't want to get too far ahead of myself. But at the same time, I want to be sure I'm understanding you correctly and how you're characterizing it.

Bill Fehrman

executive
#17

Yes. Thank you, Julien; on the timing of Batch 0, as we understand it, ERCOT anticipates filing its data center audit report on December 10, and that will then be taken up at the PUCT open meeting the week after. ERCOT had originally intended to wrap up the Batch 0 process in April. So although this is slipping, we don't anticipate it being pushed out much further in any meaningful way; and then, naturally, I want to restate that our signed load in ERCOT is genuine; we've gathered more than $2 billion in cash or collateral for Texas alone. And out of the 45 gigawatts we submitted in that Batch 0 filing, 16 gigawatts were classified as baseload while the remaining 29 gigawatts were study load. So the conditional load classifications ERCOT communicated in early September really line up broadly with what we filed. So we feel quite strong and positive about that. That said, we do see these classifications as being somewhat administrative in nature as they move through the full process. And obviously, we'll have greater clarity over the coming months; but our customers, based on the discussions we've had with them, stay very committed to connecting to our system, and we remain very excited about our business opportunities in Texas.

Julien Dumoulin-Smith

analyst
#18

Great, and now on the more substantive EPS question, there's that 10% figure you have for the later years. In your final year, thinking about that role, since you clearly give us some more discrete rate base numbers, if you roll 2030 forward to '31, for example, you get roughly 7% growth in that last year. How are you thinking about what's baked into rate base in what you're presenting here versus what's sort of baked into your EPS numbers and the commitments here for the 9 to 11, or 10, or however you'd like to characterize it in those later years.

Bill Fehrman

executive
#19

Yes. Julien, this is <<inaudible>>. So look, what we wanted to accomplish here was really to give a view just a little beyond the 5-year plan. And so what we did was roll out that 7-year look on that 10%. What I don't want people to assume is that we're walking down or stepping back from what we see as robust growth across the system; we really just haven't put the capital into those years and the associated financing; but I think you've seen us continue to show that this capital plan has a long runway for increased growth and we're very confident about sustaining that 10% over the long-term period; and when you get 7 years out into the plan and can still say we're growing at a 10% CAGR. Yes, you may be right, if you actually run the calculation you see a slight drop off; but what I'm saying is that we don't even have a lot of these incremental growth opportunities baked into the plan at this point yet; so this, I would say, is really a conservative look around the corner and we feel very, very good about where things are going, especially within the historical 5-year window. And then in the 7-year window, as we continue to update that, I think you'll see it continue to show strong robust growth like we're seeing in that '29, '30 and '31 time frame.

Julien Dumoulin-Smith

analyst
#20

Yes, absolutely. And as you figure we've turned the corner here, are there any lumpy items in those final years that you'd be watching for, ones that could move the needle? You've made some pretty big moves here of late. I'm just curious whether anything stands out that you'd be watching as you think about lumping into that, call it, that '31 rate base?

Bill Fehrman

executive
#21

Yes. Julien, I would say what you'd want to watch for is the build-out in Texas continuing. I think in the Texas Capital plan we've been fairly conservative, especially around 765 build-out. I think you can also take a look at the generation needs as we lean into the incremental generation opportunities across the VIUs; and so from that perspective, both transmission and generation are going to be big projects coming in, and incremental projects, as we continue to roll out the capital plan in subsequent years; and then we also, on the transmission side, also have the competitive transmission projects. And you've seen us pretty active in MISO with the projects that we announced up in Wisconsin. And so I think this will be very much a continuation of the under-promised <<inaudible>> deliver mantra that this management team is doing.

Nick Amicucci

analyst
#22

I want to start by congratulating Darcy and thanking you for all your support through the years. Still, I'd like to ask about the $37 billion for transmission: $17 billion comes from RTOs, $11 billion from reliability, and $9 billion from individual customers. When we consider the RTO portion specifically, how much has actually been awarded, and how much is still pending regional planning or competitive bids?

Kate Dixon

executive
#23

Nick, this is Kate. When we included that in the plan, it had already been through a regional transmission planning process. So that's work where the needs have already been identified, whether through an SPMS or PJM. All of it has gone through that process. Most of it is now ready to construct, and we're still working through the final stages of the regulatory process on the remaining items in there. But I want to reiterate that all of it has gone through what you could call the regional needs process; none of the upside Bill mentioned that we may see in the future as these planning processes continue is included in that.

Nick Amicucci

analyst
#24

Great, that makes sense. So when we look at the new segment, AEP infrastructure, I suppose with the fuel cell project, I mean, it isn't slated to enter service until 2028. I guess what is behind that 26% accretion from contracted assets compared with retail and wholesale?

Trevor Mihalik

executive
#25

Yeah. So Nick, what we're seeing is that the Wyoming fuel cell project will come online in stages. There are, I believe, 5 or 7 distinct stages for when those fuel cells come online. So we're actually seeing earnings contributions in '27. And by December of 2028 the whole project would be fully in service, and then in 2029 it would be at a full run rate. So that's really what you're seeing in that step-up on the AEP infrastructure. Kate, anything you'd like to add?

Kate Dixon

executive
#26

Yeah, I believe that's correct, and once we have your EEI, we'll give you the full breakout of the earnings drivers. So Trevor is absolutely right.

David Arcaro

analyst
#27

Perhaps I could pick up a bit further on that question regarding the infrastructure side. I was simply curious about how you think through capital allocation for the AEP infrastructure side, since a relatively small amount of CapEx is going there at present. And I wonder whether that will mostly be shaped by some of those individual big project opportunities you point to, or perhaps by more of a generation business in West Virginia and Kentucky. I suppose what determines that? And maybe what timeframe do you have in mind when you consider further CapEx opportunities there?

Trevor Mihalik

executive
#28

Yes. So David, once again, we have followed a rather conservative path when it comes to putting capital into that business. And Greg has done a solid job of steadily growing that business, as we have seen with the Bloom fuel cells, but what we are really focused on, and I believe the core of your question about capital allocation, is that the dollars going into that unregulated business must compete at a return higher than what a regulated business earns. And so from that angle, as Greg examines opportunities across his business. We are looking at, again, returns substantially higher than those we would earn on the regulated side to justify allocating capital there. And we certainly witnessed that with the fuel cell project in Wyoming. Another thing that matters quite a bit, and that is why we have really now moved toward this new segment and labeled it AEP infrastructure, is that we are seeing more long-term contracted infrastructure with counterparties of high credit quality, and that is what we are really after. This is not about us simply trying to go out and find merchant generation. It is about where we can augment our existing footprint and where we can augment our existing capabilities to deliver incremental shareholder value at a size and at a return fitting for that unregulated business.

Ross Fowler

analyst
#29

I've got a couple of things I'd like to ask. First, a quick one about incremental equity, which right now sits at about 24% of CapEx — and sorry if this was already addressed in an earlier answer, because 3 earnings calls were going on simultaneously. But Trevor, should I keep that kind of expectation in mind going forward whenever I model new incremental CapEx? You've talked a fair amount about CapEx upside beyond the $100 billion. What's the right way to think about that ratio?

Bill Fehrman

executive
#30

Yes. Ross, we've said publicly enough times that, industry-wide, you typically see somewhere around 30% to 40% of incremental equity for incremental capital. Considering how robust our cash generation is, this plan is expected to produce $5 billion in free cash flow from the business; and with the way we've addressed our earlier equity requirements and directed a substantial portion of that $5.2 billion into forward contracts, we now have considerable flexibility. At this stage, I wouldn't want to lock ourselves into saying that every bit of additional capital will be raised below 5%, but you will see us act in a very shareholder-friendly manner. We understand how valuable shareholder capital is and how valuable that equity is. So issuing it isn't something we do casually. Still, any equity we bring to market has to boost earnings and support the plan. From that standpoint, we will always look for the most efficient ways to finance and fund this business's growth. So as we keep rolling out revisions to the capital plan in later years, you can expect us to examine various equity or equity-linked instruments, and also to see the substantial cash these existing businesses generate, which will help fund future growth. But again, we want to be as conservative as we possibly can with shareholder equity.

Ross Fowler

analyst
#31

No, I'd expect nothing less, ever. Maybe I don't want to flog a dead horse here, but maybe going back to Texas and continuing on to Julien and Steve's question. If I look at what you're showing in Texas right now, and I turn to Slide 17, roughly $6.4 billion that adds distribution, right? Then they get around $7.4 billion of transmission. Now, some of that transmission is Howard Solstice, I believe, that's included in there, right?

Bill Fehrman

executive
#32

That's right.

Ross Fowler

analyst
#33

That's the first one in. Then the next question is what remains after Howard <<inaudible>> from that 74. Can you give me any sense of how we get to a pretty small number within the context of your $100 billion plan? But what is in there for Batch 0? Is there anything? Is it a very small proportion of what's left? I think you sort of touched on that, but I'm just trying to scope out for the LSAs what's left in that remainder.

Bill Fehrman

executive
#34

Yes. So I'll let Kate get into the detail on this. But I will say, first, that the Howard Solstice line is included in the plan right now. That $765 million is in there; but Kate, why don't you walk through a little bit regarding what's in and what's not in and why we believe the Texas Capital plan is actually fairly conservative at this point.

Kate Dixon

executive
#35

Ross, so as Trevor mentioned, we’ve taken a fairly conservative approach in this update to the AEP Texas capital plan. That’s partly while we wait for the Batch 0 process to unfold and for broader transmission planning to move forward. If you look at AEP Texas’s capital plan, roughly 85% is currently allocated to system reliability, resiliency, replacing infrastructure, and modernizing the grid—and to Trevor’s point, that does include approved lines like the Hotels is lying. But I’d think about most of the AEP Texas plan as having been tied to resiliency and reliability at this point. Looking ahead, as Batch 0 progresses and as the broader transmission planning process progresses, there is absolutely upside, and as that becomes—as that crystallizes through the process, we’ll think about when to add it to the plan at the appropriate time.

Richard Sunderland

analyst
#36

We devoted much of the Q&A to transmission, yet you pointed to generation as another opening. If my memory serves me from 2Q, I think you outlined part of the gas turbine situation, on both a 5-year view and further out. Could you go over that again and just address what sits inside the plan versus outside it at present on a secured or reservation basis? And have you seen any activity since 2Q? And any other thinking about how things are positioned toward the middle of next decade with respect to Gas Gen.

Bill Fehrman

executive
#37

Yes. Richard, thanks for the question about generation. Clearly, we've been extremely aggressive here and have really been very proactive about locking in turbine slots, and that has put us in an exceptionally strong position to serve the load growth happening throughout the footprint. And really, that is also enabling us to deliver value beyond that for the customers and, of course, for our shareholders. we keep seeing truly, truly robust customer demand throughout the footprint. And we keep finding opportunities for additional generation. It's genuinely just a question of time before these turbines get allocated to specific projects. And we keep having more arriving. Trevor will provide you a bit more detail on this; but again, this is an area where we've been very forward-looking and it has genuinely placed us well to pursue these customers and give them what they want when they want it. So Trevor.

Trevor Mihalik

executive
#38

Absolutely, Bill — and Richard, here's the situation as we've described it pretty transparently. Inside VIU, we've secured approximately 15 gigs of load by way of firm, long-term take-or-pay ESAs, and that expansion in load is what really provides the groundwork for investing capital in new baseload generation. So the demand exists, and at this stage we truly require the generation to support it. I'd note that framework agreements are already in place with blue-chip turbine suppliers and with craft labor companies, and that has genuinely put us in position to construct the generation needed to serve this load. A bunch of gas plants already have filings in or have received approval, and we've said plainly that we can move the rest ahead, thanks to the resource need and a supportive regulatory framework. Take I&M and PSO as an example — combined, they account for 10 gigs of ESAs, and lawmakers in both Indiana and Oklahoma recently enacted measures that accelerate new generation resources with favorable cost recovery. So in the end, I'd say our confidence is high regarding both the necessity of these projects and our capacity to get them done. And demand is unmistakably there, with wide local backing. Looking at the generation included in the plan, we feel really confident about what's in it and what we're able to deliver.

Richard Sunderland

analyst
#39

Got it. Now, coming back to AEP infrastructure — you obviously get the idea of how the market is shifting toward long-term contracts. How do you expect that to unfold when it comes to the opportunities on your radar and the timing for capturing them? Do you think there's a chance to push more solutions forward there over the coming year or 2? Or is it more a matter of locating the right spots on a 5-year horizon? Given how high profile the revamp of that segment has been, I suppose, how are you framing the real opportunity to add dollars there versus the conceptual shift you're seeing in what counterparties want?

Bill Fehrman

executive
#40

Yes. The way I'd describe how we view this segment is that, as you said, we've seen plenty of growth opportunity there. That team has been quite proactive about spotting opportunities that will add value. Still, we want to be careful not to grow that segment at a pace that creates any kind of heartburn for us when it comes to the reg versus the unreg side of the business; so we'll be very opportunistic as we identify new projects that can deliver a meaningful boost to overall earnings per share while we manage the overall balance between the regulated and unregulated sides of the business. But again, I think you've hit the nail on the head. This is a business that really will have long-term contracted cash flows with highly creditworthy counterparties, and it's something that, given what we're seeing in the marketplace for these kinds of solutions, I think we're very well positioned to capitalize on.

Jeremy Tonet

analyst
#41

Apologies if this came up before, but could you specify the large load figure that's actually included in the plan? I just want to be certain about how many gigawatts are assumed in there.

Kate Dixon

executive
#42

Yes. So I'd frame it this way — let's take Texas first and then the remainder of the plan; the bulk of the large load and the rest of the plant is now built into the capital. In Texas specifically, we've noted that we've taken a fairly conservative approach with the AEP Texas Capital plan. 85% of that rests on system reliability and resiliency; so a portion of the wider Texas load and the infrastructure required to serve it isn't in the plan right now, and that would amount to incremental upside.

Jeremy Tonet

analyst
#43

Got it. One last quick question. I understand that keeping cash on hand is pretty valuable given how fast the company is growing at the moment; but I was just curious whether you could bring us up to date, I guess, on the target, how should we think about dividend growth going forward?

Bill Fehrman

executive
#44

Yeah. So Jeremy, I think we are — first, I would always begin by saying that the dividend is always at our Board's discretion, and we make recommendations to our Board. But what we're aiming to do is keep delivering value to our shareholders, and a major part of that comes through a growing dividend. Over the past year, we've slowed how much we raise the dividend, and we expect that same kind of restrained increase—around 2% across the four- to five-year horizon. We'll keep revisiting this and bringing recommendations to our Board. And as before, you'll see us committing capital toward dividend growth. Yet with a capital plan of this magnitude, there's substantial value in making sure we're executing a $100 billion five-year capital plan while keeping dividend growth modest. So it's approximately that 2% per year that you could see us raising the dividend debt.

Bill Fehrman

executive
#45

Yes. Thanks to everyone for being with us today. Clearly, we are quite enthusiastic about what lies ahead for AEP and the major opportunities in front of us as we move this remarkable growth strategy forward, improve affordability, and build long-term value for shareholders. I am also very proud of the whole AEP workforce and the tremendous backing we receive from our Board of Directors. We remain sharply focused on carrying out this $100 billion 5-year capital plan and on meeting every commitment we have made to our customers, our communities, shareholders, and all our other stakeholders. So <<inaudible>>, if there are any further follow-up items you would like to discuss, please contact the IR team with your questions, and we hope to see many of you at EEI in a couple of weeks; that brings our call to a close. Once more, thank you for your ongoing interest in AEP.

Operator

operator
#46

That brings us to the end of today's call. A replay by telephone of this call can be accessed through November 3. To listen to the telephone replay, please dial, in the U.S., toll-free 1 833 309 to 1852 and then enter the meeting ID 222192844. Thank you for joining us. You may disconnect at this time.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete American Electric Power Company, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to American Electric Power Company, Inc. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in American Electric Power Company, Inc. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.