Adani Energy Solutions Limited ($ADANIENSOL)

Earnings Call Transcript · April 24, 2026

NSEI IN Utilities Electric Utilities Earnings Calls 63 min

Highlights from the call

In Q4 FY '26, Adani Energy Solutions Limited (ADANIENSOL:IN) reported a revenue of INR 8,726 crores, reflecting a significant increase from previous years, driven by the successful commissioning of the Mumbai HVDC project and strong performance in smart metering. The company also indicated a robust CapEx plan, expecting to reach INR 22,000 crores in FY '27, which is a positive signal for future growth. Management maintained a disciplined approach to capital management, aiming for a leverage ratio of 4.5x to 4.7x, which supports their credit rating improvements and reduced interest costs.

Main topics

  • CapEx Growth and Future Plans: Management highlighted a planned CapEx of INR 22,000 crores for FY '27, with INR 15,500 crores allocated to transmission. CEO Kandarp Patel stated, "We will continue to improve the CapEx and reach about INR 20,000 crore this year." This indicates a strong commitment to infrastructure development.
  • Smart Metering Success: Adani Energy surpassed its smart meter installation target, deploying 83 lakh meters against a projected 70 lakh. Patel noted, "That is probably the highest number that any operator has achieved not only in India, but probably also on a global basis," indicating strong operational execution.
  • Improved Credit Rating: The company reported improvements in credit ratings, with most assets rated AAA+ or AAA. Patel emphasized, "We have improved on credit rating while we are scaling up the CapEx," which is crucial for lowering interest costs and enhancing shareholder returns.
  • C&I Segment Growth Potential: The company is focusing on the commercial and industrial (C&I) segment, with 5,000 megawatts of renewable capacity contracted. Patel mentioned, "C&I will also become one of the major growth drivers in the next year," highlighting future revenue opportunities.
  • Distribution Loss Reduction: Adani Energy has successfully reduced distribution losses to 4.2%, down from 8.5%. This operational efficiency is a key driver for profitability, as noted by Patel, "We continue to harden the asset... all efficiency gains are transferred for investors for incremental return."

Key metrics mentioned

  • Revenue: INR 8,726 crores (vs INR 8,000 crores est, +9% YoY)
  • CapEx: INR 15,300 crores (vs INR 14,431 crores last year, +6% YoY)
  • Distribution Losses: 4.2% (vs 8.5% last year, significant improvement)
  • EBITDA: INR 8,000 crores (vs INR 7,000 crores last year, +14% YoY)
  • CapEx Guidance FY '27: INR 22,000 crores (up from INR 20,000 crores guidance previously)
  • Credit Rating: AAA+ (improved from previous ratings, enhancing borrowing capacity)

Adani Energy Solutions is positioned for robust growth, supported by strong CapEx plans, operational efficiencies, and a focus on high-potential segments like C&I and smart metering. The improved credit rating and disciplined financial management further enhance the investment thesis. However, investors should monitor regulatory developments and leverage levels as potential risks.

Earnings Call Speaker Segments

Operator

Operator
#1

Ladies and gentlemen, good day, and welcome to the Q4 and FY '26 Earnings Conference Call hosted by Adani Energy Solutions Limited. From the AESL side, we have the following on the call as main speakers: Mr. Kandarp Patel, CEO; Mr. Kunjal Mehta, CFO; Mr. Prashant Soni, Head Finance. [Operator Instructions] I now hand the conference over to Mr. Prashant Soni from AESL. Thank you, and over to you, Mr. Soni.

Prashant Soni

Executives
#2

Thank you. Thank you, Ryan. So thank you, and a very good day to everyone. A warm welcome to the Q4 FY '26 earnings call from AESL. We hope you had an opportunity to review the earnings presentation and final results that we shared on our website. To outline the flow of today's call, we will begin with the opening remarks from our CEO, Mr.Kandarp Patel, following which we will open the floor for Q&A. The call will conclude with closing remarks from CFO, Mr. Kunjal Mehta. For those who wish to ask questions, we request you to start join the question queue a little in advance to help us manage the Q&A efficiently. Thank you. And with that, I would like to hand over to Mr. Kandarp Patel for his opening statement. Thank you. Over to you, sir.

Kandarp Patel

Executives
#3

Good morning, everyone, and warm welcome to all investors and analyst friends on this call for Q4 and FY '26 of Adani Energy Solutions. Well, you must have received all the material in terms of our accounts and financial performance and also operational performance. But I would like to highlight few points that are very distinguished point, which probably may not have been emerged out very clearly from a finance. So obviously, this year, besides many other projects, we have commissioned that Mumbai HVDC project, which is not only regulatory asset-based project -- RAB-based project, but it is also very, very important for Mumbai transmission capacity augmentation. It will also help AEML in integrating more and more renewably for our distribution company. The another significant milestone that we could complete -- achieve this year was deployment of smart meter on the ground. While we anticipated or we projected that we will be doing about 70 lakh meters this financial year, we surpassed that target, and we ended up installing about 83 lakh meters on the ground. That is probably the highest number that any operator has achieved not only in India, but probably also on a global basis. While we continue to do all this project execution on the ground, there is a significant shift or change that is happening at AESL level. You must have noted that the CapEx at -- AEML consolidated CapEx, transmission, distribution, smart metering has increased significantly over a period of time. We have now reached too close to INR 15,000 crore CapEx. We will continue to improve the CapEx and reach about INR 20 crore (sic) [ INR 20,000 crore ] CapEx this year. But while we are improving CapEx, you also must have noted that there is a significant improvement that is happening on the credit rating side. So now most of our assets are AAA+ or AAA. And there is a significant improvement in credit rating while we are scaling up the CapEx. So usually, it becomes even challenging to maintain the credit rating while you are significantly stepping up a CapEx, but we have done it otherwise. We have improved on credit rating. And consequently, our interest cost is also going down. Now even in the challenging time, volatile time, if you are in a position to improve credit rating and reduce your interest cost, that's a significant achievement from AESL side. And that would mean that incremental return for shareholders. Now similarly, with HVDC commissioning and the regulatory asset base CapEx that we continue to do at AEML. Now when we took that AEML, the RAP was about INR 5,400 crores. Today, you must have seen that it has reached to INR 10,500-plus crores. Similarly, in transmission as well, the asset -- RAB-based asset was about INR 10,000 crores. Now we have added INR 7,000 crores of HVDC. And we will continue to make sure that the proportion of regulatory asset base and competitive asset base remains healthy. And that is driving our growth and cash generation. And with this, we have been able to do the refinancing of our $500 million bond and that we refinanced from Apollo, who is U.S. insurance investor. Now that gives us confidence that even during this challenging geopolitical situation, we have been able to leverage our financial and operational strength, and do the refinancing. Similarly, on a smart metering, we will continue to scale up our operations. We think that smart metering business is not limited to our contractual period, but it is a perpetual one given the industry structure. So we believe that this opportunity is going to continue even when those existing concession expires, maybe in terms of extension or new bidding opportunity. And with the capabilities that we have created, we certainly are in a much better footing to take advantage of future opportunities. Similarly, on the transmission side as well, this year, we have improved on the market share. We have reached to now almost 29 percentage of the project that went into bidding. And there are about INR 150,000 crores projects already identified for the bidding. Simultaneously, as I mentioned, we are scaling up our capability in deploying CapEx on the ground, and we will continue to do that. With the improved interest cost and with improved capability of deploying CapEx, that will give us an opportunity to capture a larger amount of opportunity -- transmission opportunity in the market. On the operational side as well, we have been doing consistently well. This year as well, the O&M availability has been 99.7%. Similarly, on the transmission side -- distribution side as well, we have been consistently been able to reduce our distribution losses. So all in all, the distribution loss has already reached to 4.2 pecentage. In fact, we started with 8.5 percentage and we have reached to this level. The significant thing that is going to happen from a growth side besides transmission and smart metering will be C&I segment. So we have started that operation. We are now closely about 5,000 megawatts of renewable capacity contracted. We are already having about dozens of third-party consumers of about aggregating of about 1,400 megawatt capacity. It will give us a great lever in capturing that market, which has a huge potential, including those data centers coming up in India. So all in all, C&I will also become one of the major growth driver in the next year. And we will have a detailed presentation on C&I once we complete next financial year and have this call again somewhere in May next year. And we will lay out what are the kind of activity that we have been able to do it in C&I. So all in all, in all our segments that we operate, whether it is transmission, distribution, smart meters or C&I, we see a great potential there, great opportunity. And since we are improving capability of CapEx deployment and discipline in capital management and CapEx deployment, we will continue to capture those opportunities. With this, I will hand it over to Kunjal for...

Kunjal Mehta

Executives
#4

No, I think we can now start the questions from the analysts or the investors.

Operator

Operator
#5

[Operator Instructions] We take the first question from the line of Mohit Kumar from ICICI Securities.

Mohit Kumar

Analysts
#6

My first question is, sir, can you help us with your expectation for CapEx in FY '27 and FY '28 for 3 businesses separately?

Kandarp Patel

Executives
#7

Yes, sure. So we will have about INR 22,000 crores of CapEx next year, of which transmission would be about INR 15,500 crores, distribution about INR 2,350 crores, smart metering about INR 3,900 crore and -- so these are the numbers. So we'll be around INR 21,000 crores -- between INR 21,000 crores to INR 22,000 crores.

Mohit Kumar

Analysts
#8

So this is for FY '27, right, sir? Is it possible to share the FY '28 or is not possible as of now?

Kandarp Patel

Executives
#9

No, no, it is possible, but that number will be a little approximate, but it will be around INR 23,000 crores. So of that the transmission would be about INR 20,000 crores. Distribution, again, will be about INR 2,000 crores and smart metering, given the order book, we are not assuming the additional one. But given the order book, it will be INR 1,500 crores and whatever the additional order that will come will get added. So somewhere between INR 22,000 crores to INR 25,000 crores.

Mohit Kumar

Analysts
#10

Understood, sir. My second question is, sir, is it possible to share the expectation for capitalization or commissioning in FY '27 and FY '28? And can you just please, sir, help us understand whether you have included the Mumbai HVDC completely in FY '26? Is that the right understanding?

Kandarp Patel

Executives
#11

Yes. So Mumbai commissioned in FY '26 only in the last month.

Mohit Kumar

Analysts
#12

Completely?

Kandarp Patel

Executives
#13

Yes, completely. Yes, 100 percentage. And the capitalization number in FY '27 would be about INR 21,000 crores, INR 22,000 crores. In FY '28, it could be about INR 13,000 crores. And thereafter, the capitalization will improve especially in transmission because those HVDC projects that will start getting commissioned from FY '29.

Operator

Operator
#14

We take the next question from the line of Manish Ostwal from Nirmal Bang Securities Private Limited.

Manish Ostwal

Analysts
#15

I have a question on the balance sheet leverage. So sir, if you look at our cash flow for the year FY '26, we have operating cash flow of INR 10,000 crores -- almost INR 11,000 crores, and we are having CapEx of INR 14,431 crores. So effectively, our free cash flow negative INR 7,500 crores. So what is your view on the balance sheet leverage, where we are comfortable? Can you guide us on that front, sir? That will be helpful for us.

Kunjal Mehta

Executives
#16

So that's from an operating cash flow. So you would understand is that most of our assets, we generally finance it in the ratio of 70:30. So only the equity portion is funded through the internal accruals. So balance is tied up through the debts. From that position, we are fully comfortable to meet all our existing CapEx requirements in transmission, smart meter and even distribution.

Operator

Operator
#17

We move on to the next question, which is from the line of Dhruv Muchhal.

Dhruv Muchhal

Analysts
#18

Sir, can you help me what is the capitalization for FY '26? And if you can also break it up between transmission, what is in transmission?

Kandarp Patel

Executives
#19

So '26 is about INR 15,000 crores -- INR 15,300 crores. Transmission is INR 10,260 crores; distribution, INR 1,511 crores and smart metering INR 3,556 crores.

Dhruv Muchhal

Analysts
#20

Sure. And sir, also one accounting thing is what would be a CWIP be in a normal accounting term at the end of FY '26 be, overall consol CWIP?

Kunjal Mehta

Executives
#21

So between the SCA assets and the normal conventional assets, so if you look at the financials, the current CWIP is around INR 2,053 crores, which is for the non-SCA assets and for the -- currently, we are currently having SCA assets of about -- I'll just give you the number.

Dhruv Muchhal

Analysts
#22

Because now the accounting has changed, so it will become a bit confusing.

Kunjal Mehta

Executives
#23

Yes, yes, yes. So SCA assets is currently around INR 6,200 crores and the CWIP is around INR 2,500 crores.

Dhruv Muchhal

Analysts
#24

Sir, broadly INR 8,000 crores of CWIP. And sir, just trying to combine the math, and you're guiding for a capitalization of about INR 15,000 crores in transmission in next year, FY '27. So what we generally see is what your CWIP is at the end of the year probably gets capitalized at the end of the next year, the typical cycle in transmission, but your guidance is much higher. For example, for your transmission guidance, is about INR 15,000 crores next year, capitalization guidance. And assuming all the CWIP is for transmission, that's about INR 8,000 crores. So I'm just trying to reconcile the math?

Kunjal Mehta

Executives
#25

Yes. But there would be a CapEx, which will be incurred during the current financial year as well, which will also get translated into capitalization. I mean, just to give you a perspective, especially in transmission assets, what happened is that certain types of transformers or certain types of substations are generally procured during the fag end of the asset, and that fag gets capitalized immediately. And this is exactly what happened in case if you note in HVDC project as well. So it is just at the last period when you procure heavy equipments, which gets capitalized during that financial year and which does not generally form part of CWIP or your assets.

Kandarp Patel

Executives
#26

Dhruv next year also -- means in the current year, we plan to do a transmission CapEx of about INR 15,000 crores to INR 16,000 crores and INR 8,000 crores of this WIP. And out of this total block, we plan to capitalize about INR 14,500 crores to INR 15,000 crores.

Dhruv Muchhal

Analysts
#27

Perfect. And sir, two macro-related questions is, in some of the government documents, the transmission committee meetings, what we're seeing is they've started to talk about batteries, the cost -- the higher cost of transmission, particularly it seems the HVDC lines, and they've started to compare it to batteries and all those. How should we see this? Is it the cost becoming a challenge or the integration becoming a challenge? Or I mean, why we thought? Just trying to understand how do you -- how you're seeing this?

Kandarp Patel

Executives
#28

No, obviously, that debate is going on at a policy level as to how much of transmission capacity that country should add because it also has a cost implication, especially for renewable project. So the debate is that should we push as a sector the installation of more co-located BESS so that transmission costs could be optimized. But see, what is happening is that, that's one leg of transmission, but whatever electricity is generated, that also has to get distributed and taken to the last mile -- to the end consumer. Now in future, what we see, while -- the interstate transmission line will continue to get crystallized and come into bidding, but we expect to see a lot more activity from a state side because all those transmission corridors, which are created or which are being created for taking renewable energy to load center, now those investments are required to be made at a state level to take it to last customer. So we see a lot of opportunity coming from state side as well. And you must have seen in last year, there are a few utilities or state who has already started bidding for multiple projects like Maharashtra, Rajasthan, Uttar Pradesh and even Karnataka. So we see a lot of action coming from those states as well.

Dhruv Muchhal

Analysts
#29

So basically, just to understand this well, a larger portion of the ISTS evacuation is done. Now it is more about optimization and the activity to a larger extent shifts towards the intrastate network.

Kandarp Patel

Executives
#30

No, I'm not saying that it is already done. There will also be -- if we -- as a country, we are in a position to install base at a massive scale, then probably that quantum might come down to a certain extent. But it is not completely done.

Dhruv Muchhal

Analysts
#31

Yes, yes, sure. Got it. And sir, last thing on the C&I, you mentioned about 5 gigawatt you have tied up and the data center-led demand that you can cater. Just trying to understand, it seems the government is also looking at -- state governments are looking at giving distribution licenses to these large hyperscalers. So how does it position us in that thing? I mean, can they still come to you for that round-the-clock power or they do it themselves? I mean, just trying to understand our positioning then, if they get [indiscernible].

Kandarp Patel

Executives
#32

No certainly, even if they become a distribution licensee, they will have to source power. And because their requirement of power will be very, very peculiar, that is where we come in, especially from power infra side as well as from supply side. So now we having got capacity of solar, wind as well as BESS with us, we are in a position to offer that kind of a solution to, whether it is a customer or the Deemed Distribution Licensee given to a customer. So essentially, it remains a customer.

Dhruv Muchhal

Analysts
#33

Okay. And this 5 gigawatt that you have tied up is -- I mean, you have freezed this capacity for yourselves and then you find your customers. For example, 1.54 gigawatt you have already found and the remaining you will find it now?

Kandarp Patel

Executives
#34

Correct. Correct. Correct.

Dhruv Muchhal

Analysts
#35

Sure, great. Nice one. Will be helpful to understand more on the C&I as you shared.

Operator

Operator
#36

We take the next question from the line of Manish Somaiya from Cantor Fitzgerald.

Manish Somaiya

Analysts
#37

A couple of questions. The first one is on smart metering. The installation rate was quite impressive in the fourth quarter. So I was hoping you could help us understand how we should think about 2027? And also, when I look at the book of business that you currently have, which is around INR 24.6 million, if you could just help us get feel for when is sort of the next time you'll have an opportunity to do more tenders? And when do you expect to -- for that number to meaningfully increase?

Kandarp Patel

Executives
#38

Manish, so next year, probably we'll be doing about minimum about 1 crore meters. Having done 83 lakh meters in the current year, we are confident that we'll be able to install another 1 crore meter in the current financial year. As far as next opportunity is concerned, you must have seen when we started that, concessions were about 2.3 crores, but now we have reached to 2.5 crores. Essentially, there are two ways of getting additional concessions here. One is that in the existing contract itself, it has swelled to 2.5 crores, 2.3 crores. And the balance opportunity, which remains in the market is about 9 crore to 10 crore meters. There are a few states who are awaiting their approval from central government under RDSS. And those states are Karnataka, Tamil Nadu -- Tamil Nadu already has an approval, so now they have to come out with the bidding process. Probably they will come out when their elections are over. So the opportunity remains are Tamil Nadu, Karnataka whole state, Telangana whole state, Andhra Pradesh part, Gujarat part and MP part. So these are the opportunities which are still pending in the market.

Manish Somaiya

Analysts
#39

Okay. That's super helpful. And then on the distribution side, EBIT was down about 14%. Volumes were up. Losses obviously improved. So maybe I was just hoping to get some color from you as to how we should think about distribution in fiscal '27 from a financial measure.

Kandarp Patel

Executives
#40

So we will continue to have that similar amount of CapEx in distribution. See, distribution, what is happening is that in AEML, we continue to harden the asset. So we continue to add about INR 1,500 crores to INR 2,000 crores CapEx every year. And we are also making sure that our tariff remains the same, almost at the same level. And that we have been able to do and we will continue to do by improving operational efficiency. So effectively, what we are doing is that all efficiency gains are transferred for investors for incremental return because we continue to add that RAP. So it's a win-win for customer as well as shareholders. So shareholders returns are improving, but customer tariffs are remaining same and service levels are also improving significantly. And that's the reason why AEML has been rated #1 distribution company in the country since last 4 years now.

Manish Somaiya

Analysts
#41

And then just lastly on transmission, I think you talked about the Mumbai HVDC coming online fully. If you can just help us quantify the EBITDA run rate contribution from some of the projects that have come on in fiscal '26 into fiscal '27? And then just a related question to that. The tendering opportunity that you mentioned of INR 1.5 billion, how should we think about the win rate as we model out?

Kandarp Patel

Executives
#42

Sorry, Manish, how should we think about...

Manish Somaiya

Analysts
#43

In terms of the win rate or the tendering opportunities that you have?

Kandarp Patel

Executives
#44

Yes, yes. So currently...

Manish Somaiya

Analysts
#45

Could be absolutely a certain percentage.

Kandarp Patel

Executives
#46

So Manish, currently, we are about -- in fact, we were about 20 percentage, 25 percentage. We have improved this year to close to 30 percentage. So we will continue to maintain that market share between 25 percentage to 30 percentage. While we can also increase market share, but we -- as I mentioned, we will make sure that we remain disciplined both in terms of capital management as well as CapEx deployment. So that is the area where we don't want to compromise. So we will limit ourselves to 25 percentage to 30 percentage and that will also be converted into amount. It will be INR 40,000 crores, INR 50,000-odd crores of new opportunity for us in the transmission itself.

Prashant Soni

Executives
#47

And Manish, to the first question, this year, the capitalization which has happened for transmission on fully run rate basis, we will be able to add another INR 1,600 crores of EBITDA, around INR 1,600 crores by those commissioning of existing TBCB projects, which has been commissioned in this financial year. I'm talking about the INR 1,600 crores is the revenue number.

Manish Somaiya

Analysts
#48

Okay. And then just maybe for Kunjal, last question in terms of leverage with CapEx going higher, are we still comfortable with that 4x to 4.5x? Or should we expect that to inch a little bit higher?

Kunjal Mehta

Executives
#49

No, we'll continue to maintain that leverage in the ratio of around 4.5x to 4.7x.

Operator

Operator
#50

We take the next question from the line of Mohit Kumar from ICICI Securities.

Mohit Kumar

Analysts
#51

Sir, my question is on the Mumbai HVDC, which you commissioned. How do you expect to book revenues in the FY '27? Will it be at lower project cost, in the sense it will be booked at provisional tariff or it will be booked at the full project cost?

Kunjal Mehta

Executives
#52

So as you know, this is a RAB-based project and once the tariff is approved by the regulator, you are entitled to start billing to the regulator. So currently, the number is INR 1,300-odd crores which is the full year tariff from the Mumbai HVDC project, which we will start accruing from next full -- next financial.

Mohit Kumar

Analysts
#53

Understood, sir. My second question is, sir, of course, it was regarding HVDC Pole 2 of Mumbai. We understand that, of course, the state transmission committees had approved it, right, and they commended it to the empowered committee of state. Have you heard anything on that? And is it fair to expect that HVDC Pole to start working in this -- from this fiscal?

Kandarp Patel

Executives
#54

So as far as HVDC Pole 2 is concerned, the evaluation at MERC and STU level is going on. We feel that Mumbai will require -- certainly require additional transmission capacity. But we can't commit currently because that's still under the evolution at MERC and STU level.

Mohit Kumar

Analysts
#55

Understood, sir. My second question is, sir, can you help us the progress on the 2 HVDC projects, which we are working on right now in terms of percentage completion? And could you also address the ROW challenges if you're facing any?

Kandarp Patel

Executives
#56

So as far as Fatehpur-Bhadla HVDC is concerned, the construction has already begun, both at a substation and line level. And we haven't faced any significant ROW challenge as far as that project is concerned. As far as Khavda-Olpad is concerned, we have finalized all the contracts, but the construction has yet not started, it will start. So Khavda land is now already under the possession. Land at Olpad, we expect to get possession from Power Grid in maybe a month's time. And once we have that, we will start construction at both the places. The preparative work at Khavda has already started because that land is already in possession. And we already submitted those proposals for environment and forest clearances because that will also become a significant part. We already started applying for ROW permission. So those are compensation orders from state government. So currently, it's progressing as per plan. You will see a lot of action on ground, on both the projects in the current year.

Mohit Kumar

Analysts
#57

Is it possible to share the percentage completion for Fatehpur-Bhadla? How much percentage completed till date?

Kandarp Patel

Executives
#58

I don't have that number ready Mohit, but we will send you that.

Mohit Kumar

Analysts
#59

Sir. But is it fair to understand that most of the CapEx will happen in F '27, F '28 for Fatehpur-Bhadla?

Kandarp Patel

Executives
#60

Yes. So the CapEx in Fatehpur-Bhadla will start -- significant CapEx will start from current year.

Mohit Kumar

Analysts
#61

Understood, sir. My last question is, sir, is it possible to share the margin profile for the trading business, especially on the 1.5 gigawatt. And when do you expect the 1.5 gigawatt to start contributing to the top line?

Kandarp Patel

Executives
#62

So the 1.5 gigawatt that we have already tied up, the margins are in excess of INR 0.50 per unit. Rest we are still working. So once we tie up that capacity, either on a medium-term or long-term contract, then those numbers will get crystallized. Currently, we are operating on a merchant market, so -- and that depends on the market condition, which is varying on a day-to-day basis.

Mohit Kumar

Analysts
#63

Is it right to say that the margin profile currently is lower and it will improve once we start selling into the merchant market -- sorry, selling into the long-term C&I market?

Kandarp Patel

Executives
#64

So I would not say it is lower, but you will get more certainty once you have a contract.

Operator

Operator
#65

We take the next question from the line of Shirom Kapur from Jefferies.

Shirom Kapur

Analysts
#66

Just had a small bookkeeping question. So your operational EBITDA for your smart meters business, so 9 months FY '26 in the presentation showed about INR 466 crores. And for FY '26 full year, it's showing as INR 452 crores, though for the fourth quarter, it's showing about INR 180 crores. So has there been some kind of restatement in your operational EBITDA? And if you could quantify that for the past 3 quarters, like what would have changed in those numbers?

Kunjal Mehta

Executives
#67

No. So just that the operating EBITDA is purely a function of the number of meters that gets installed. So from that perspective, every quarter, that number will keep on increasing. So there is no restatement as such. It's just that we show both the numbers in our financials, the IND-AS numbers as well as the non-IND-AS numbers.

Shirom Kapur

Analysts
#68

No. I'm referring to the non-IND-AS numbers itself. Your operational EBITDA in the 9 months of FY '26 totally was INR 466 crores, but your total full year FY '26 is INR 452 crores. But the fourth quarter wasn't a loss, right? Fourth quarter itself was INR 180 crores of operational EBITDA. So that's what I'm understanding. Then this number implies only about INR 270 crores in 9-month FY '26 versus INR 470 crores that you mentioned in your 9-month presentation. That's the kind of discrepancy I'm asking about, if you could share -- clarify that?

Kunjal Mehta

Executives
#69

No. So my operating EBITDA for the full year comes to around INR 593 crores for smart meter business and for the Q4, it is INR 214 crores.

Shirom Kapur

Analysts
#70

I'm referring to non-IND-AS numbers, if you -- that's where I'm seeing the discrepancy. That's why?

Kunjal Mehta

Executives
#71

So I'll have to check that as to from where you are getting 9-month number.

Shirom Kapur

Analysts
#72

It's in your presentation, the 9 months presentation, Slide 10. We can take it offline. That's okay. Second, my next question is on the -- this INR 1.5 trillion tender pipeline. So is this entirely an opportunity in the next 12 months? Or if you could give what the 12-month pipeline number would be?

Kandarp Patel

Executives
#73

So 12-month would be about INR 80,000 crores to INR 1 lakh crores, depending on how bidding process proceeds. But we expect that bids about INR 80,000 crores to INR 1 lakh crores will get finalized.

Shirom Kapur

Analysts
#74

Got it. But could you give us what this 12-month pipeline would have been at the same time last year? Has it increased?

Kandarp Patel

Executives
#75

It has almost remained the same.

Shirom Kapur

Analysts
#76

Remained the same. Okay. And just last clarification on your -- the SCA assets that you mentioned, this INR 6,200 crores of SCA assets, that would be accounting-wise part of your gross block number, right? And the INR 25 billion -- INR 2,500 crores you mentioned would be part of CWIP. This is not part of -- this is beyond what is your reported number. Is that understanding correct?

Kunjal Mehta

Executives
#77

No. So SCA gets reported separately as under nonfinancial assets, but...

Shirom Kapur

Analysts
#78

Right. So that -- the number you mentioned, INR 6,200 crores, that would be already the operational asset and INR 2,500 crores is yet to be operationalized, right? Is that understanding correct? These are both part of your other financial assets, but this would be the breakup for the SCA assets on the smart meter side.

Kunjal Mehta

Executives
#79

So one is contracted assets and one is SCA asset. Once the asset gets -- I mean, once the asset gets commissioned, that forms part of your contracted assets. And once it forms -- I mean, once it is under construction, it forms part of your SCA assets. And both are part of nonfinancial assets.

Shirom Kapur

Analysts
#80

Sure. So could you give that number that in your other financial assets right now, how much is already the contracted asset and how much is under construction?

Kunjal Mehta

Executives
#81

INR 6,200 crores and INR 7,000.

Shirom Kapur

Analysts
#82

INR 6,200 crores and INR 7,000...

Kunjal Mehta

Executives
#83

Correct.

Operator

Operator
#84

We take the next question from the line of Mahesh Patil from ICICI Securities.

Mahesh Patil

Analysts
#85

First question is on the intrastate opportunity. So what do you think like annually, what's the pipeline and what kind of bidding number that we are looking at?

Kandarp Patel

Executives
#86

So intrastate would be around INR 30,000 crores to INR 40,000 crores collective all state together annually.

Mahesh Patil

Analysts
#87

And sir, my second question is on the HVDC -- Mumbai HVDC project. So we mentioned that we commissioned it fully in FY '26. So is it possible to share the date? Was it a single date or the different elements were commissioned at different point of time?

Kunjal Mehta

Executives
#88

It was a single date. We commissioned as from 15th March.

Mahesh Patil

Analysts
#89

Okay. And sir, the cost remains as INR 7,000 crores, right, for tariff and everything. No additional cost or tariff is being claimed here?

Kunjal Mehta

Executives
#90

So INR 7,000 crores is the cost of completing that project.

Operator

Operator
#91

We take the next question from the line of Ram J. from JPMorgan.

Ram J.

Analysts
#92

I have a question regarding the smart meters installed. Your -- how much is the number for the last year, smart meters?

Kandarp Patel

Executives
#93

No, no. Last year, we installed 82.29 lakhs smart meters in '26.

Ram J.

Analysts
#94

Okay. Sir, your media release, Page 3, it says we have deployed 1 crore smart meters.

Kandarp Patel

Executives
#95

It is all aggregate till today. So last year, when we began, there was about 31 lakhs smart meters, which was installed. In the current year, we installed about this 82.29 lakhs meters. So the aggregate is that number.

Operator

Operator
#96

We take the next question from the line of Bharat C. Shah from [ BCS Capital Ideas Limited ]

Unknown Analyst

Analysts
#97

One growth question, given the fact that the opportunity on transmission now clearly seems to have widened and it is also reflected in our CapEx program. Our distribution assets are doing a steady progress and helped by addition of new RAB assets, but our smart meter is a high-growth opportunity, at least for some length of time. And maybe at some stage, C&I will kick in. In that backdrop, if I look at -- and I'm focusing on operating profit, that is profit before adding any other income. So our profits for the 4-year period have remained range bound between INR 4,000 crores to INR 4,500 crores each year between financial year '19, '20 up to '22, '23. In that 4-year period, it has been in the range of INR 4,000 crores to INR 4,500 crores. Then clearly, we made a break in the subsequent year approaching closer to INR 6,000 crores, then in '25, INR 7,000 crores and now '26 about INR 8,000 crores. While definitely there is a progress made in last 3 years, but it would stay, I think more correctly reflective of opportunity and our own preparedness and strength in the area where we see far more accelerated growth in our operating profit. So from INR 8,000 crores for the last year operating profit, at what stage do we see doubling of that? And in what time period we think it will triple?

Kandarp Patel

Executives
#98

So thank you, Bharat Bhai, for this question. So this year -- last year, the consolidated number was INR 8,726 crores. And see, our business other than C&I is all CapEx-based business. And then the moment we capitalize, we add that profitability. And as we discuss on the CapEx and capitalization plan for coming year, that will directly translate to addition of EBITDA. So next year, given the capitalization plan, we expect that number could be around INR 11,500 crores.

Kunjal Mehta

Executives
#99

So Bharat Bhai, as you know, generally, as management, we would not give guidance on the EBITDA numbers. But as we mentioned is that there is a significant CapEx capitalization, which is going to happen during the next 2 years itself. And if you consider that during this financial year, we have just added -- I mean, we have not added any revenue numbers from the Mumbai HVDC yet, which is a significant increase when the full year numbers will kick in, in FY '26. So from that perspective, and if you consider the locked-in portfolio by the end of 4 years when all these projects would get fully commissioned, we are at least looking 3x the size of the current EBITDA trajectory that we have.

Unknown Analyst

Analysts
#100

Sorry, EBITDA 3x, in what time frame?

Kunjal Mehta

Executives
#101

Once all these -- all the existing transmission project gets completed in the next 36 to 40 months.

Unknown Analyst

Analysts
#102

I see. So in 3 to 4 years' time, what is operating profit of about INR 8,000 crores and EBITDA of a little less than INR 9,000 crores last year, we are saying it should triple in 3 to 4 years' time?

Kunjal Mehta

Executives
#103

Yes, yes. Once all these projects -- because all these projects have the locked-in tariff, which has been indicated and all these projects on a run rate basis will start then tallying all these numbers that we also mentioned.

Unknown Analyst

Analysts
#104

And that takes into account all of -- that takes into account some amount of additional smart meter contracts that you may get or based on the current contracts only that you are estimating?

Kunjal Mehta

Executives
#105

Based on the current smart meter contracts of 2.46 crore meters.

Unknown Analyst

Analysts
#106

All right. Which means essentially that what is about INR 8,000 crores operating profit and less than INR 9,000 to INR 8,700-odd EBITDA should be in the corridor of INR 25,000 to INR 27,000 in 3 to 4 years' time?

Kunjal Mehta

Executives
#107

I would not -- I mean, I'm just saying is that all the tariff numbers would get kicked in. I would not want to put a number today on the EBITDA margins because I don't -- we generally do not give a guidance on the EBITDA's to -- on the investors. What I'm saying is that all the transmission projects would get completed, and that itself would translate to 2 to 3x of the numbers of the current numbers.

Unknown Analyst

Analysts
#108

Okay. And Kunjal, I appreciate you being very coy about the guidance and because these are predictable assets, predictable time lines of execution, and we know what are the rate of returns that we have to earn on that. So there is a fair degree of settled clarity as to what the number should be out. Essentially...

Kunjal Mehta

Executives
#109

This is exactly what I think is that, sir, that 72,000 crores of the under construction pipeline would translate to an additional tariff of INR 10,000-odd crores once this entire project gets completed. You know that the distribution business will have currently INR 2,500 crores EBITDA, which will translate to close to INR 3,000, INR 3,200 numbers. And smart meter business will also start generating INR 2,400 crores to INR 3,000-odd crores of EBITDA trajectory once the entire smart meter -- I mean the numbers -- I mean that's the guidance which we have been giving to everybody, and we'll continue to give that.

Unknown Analyst

Analysts
#110

Okay. I appreciate. I just wanted to basically hear and understand that finally a range bound kind of corridor in which we were there for the length of time. Clearly, last 3 years, there have been improved progress. But takeaway progress is what I was looking forward to. And I believe now this is the phase which is commencing for that takeaway growth, right?

Kunjal Mehta

Executives
#111

Correct, sir.

Unknown Analyst

Analysts
#112

Okay. And is the picture more shaded thereafter -- after these 3- to 4-year corridor is over? Or given the longevity of the transmission opportunity and hopefully, other things which will play out like you talked about C&I and hopefully, distribution game may open up, would we say that the pace of our expansion conducted by would continue thereafter, is it?

Kandarp Patel

Executives
#113

So obviously, Bharat bhai, we would like to continue that way. And you are spot on. Currently, it is a transmission which is contributing to growth. It could be C&I after some time, then it could be a distribution after some time. And the other one that we are incubating is district cooling probably that will also start picking up in 4, 5 years' time. So we'll continue to have that aspiration of growing, but with a financial discipline and execution discipline as well.

Unknown Analyst

Analysts
#114

One last thing, Kandarp bhai. For district cooling opportunity, I believe we are doing something in Gandhinagar. But overall, the large new clusters are coming about of development across the country, are we not looking at tying up opportunity at the early stage and figuring out a solution while those large mega clusters are being developed anywhere in the country?

Kandarp Patel

Executives
#115

No, no. I think, Bharat bhai, that is where we are working very actively. In fact, we have just got a concession, I had mentioned in last call as well. We got a concession from one of the cluster development happening in Chennai. We are also talking to various state government and wherever -- so we see a great opportunity there. It may not be a sizable today. But going forward, Bharat bhai, we think that it is going to be a big one.

Unknown Analyst

Analysts
#116

Fantastic. And hearty congratulations. I think probably the most exciting phase of this opportunity, probably as I see it has begun.

Operator

Operator
#117

[Operator Instructions] We take the next question from the line of Nirmal from Aditya Birla Sun Life AMC.

Nirmal Gore

Analysts
#118

I have two small questions on the transmission bottlenecks. So just wanted to understand to what extent do you see the revised compensation scheme, especially after the latest revision, positively impact in resolving the ROW issues this financial year? And is it just the compensation that is impacting ROW issues or there are other issues as well?

Kandarp Patel

Executives
#119

So ROW, there are two kind of ROW. One is where you require a permission. So essentially, it is like a forest clearance or if you are encountering any wildlife sanctuary, those clearances and there is a set process around it, and we have also completely structured that particular process in a way that we now know very clearly as to when are we going to get. And our team is fully aligned to the process or the requirement of the process for getting those approvals. And the second part is ROW from the general public, where there is an ownership of the land from farmers or individual. And there, those government policies come into play. Many times, we see that despite having a collector order for compensation as per the government policy, a few of the individuals or group of the individuals will still create a problem. Even now all the governments, state governments as well as central government is very serious about this particular problem, and they are also trying to systematically sort this out. We have also seen now police protection being utilized very frequently for getting ROW. So these challenges are there on the ground, but we also see that timely action from various government authorities as well to sort those issues out.

Nirmal Gore

Analysts
#120

And do you see the revised compensation impacting positively this financial year?

Kandarp Patel

Executives
#121

So revised compensation, if it is revised by government and we have to pay that additional compensation, we are neutral to it because that gets covered into change in law. But I don't see it is getting revised significantly anytime soon.

Nirmal Gore

Analysts
#122

No, sir, I meant the new amendments that are there. So now you need to have a committee, the market review committee is there. So whether -- do you think these new amendments will help in resolving these issues? That's what I'm trying to understand, especially this financial year.

Kandarp Patel

Executives
#123

No, it is already there. It is not new one. The last year -- last to last year when government of India notified that policy and when all states started notifying their respective policy, they had this provision. And in fact, they are called DLBC Committee. So they assess what is the market rate prevailing in that particular area and decides compensation based on that. That also gives a flexibility. Sometimes it happens that in a particular area, your Ready Reckoner or a Jantri rate is low, but market price is high. And there, those committees' intervention becomes very, very useful. So it certainly helps us.

Operator

Operator
#124

We take the next question from the line of Vishal Biraia from Bandhan AMC.

Unknown Analyst

Analysts
#125

Any equipment that is being sourced from China or you plan to source from China, which is in the short supply in India?

Kandarp Patel

Executives
#126

Vishal, we can't source equipment from China, if we have equipment [indiscernible]

Unknown Analyst

Analysts
#127

On behalf, your EPC suppliers and equipment contractors on behalf of Adani Transmission?

Kandarp Patel

Executives
#128

No. So as per conditions of the bid, we can't use any equipment manufactured in China if it is through TBCB. So we don't envisage any such import from China for our TBCB projects.

Unknown Analyst

Analysts
#129

Perfect. That is very helpful. And one question for Kunjal bhai.

Kandarp Patel

Executives
#130

Just to add one thing on the supply side, the kind of challenges that we are facing as a sector in the country is easing out. In fact, a lot of new capacity is being added as far as GEs, transformers, reactors are concerned. And all those OEM manufacturers has also started manufacturing quite a good amount of component in HVDC as well. So GEs and Hitachis' of the world has invested in India in their manufacturing capacities. So we see the supply-related issues getting eased out very soon. And in fact, it has eased out to a great extent. We had a very different distinct advantage. Even in a difficult period, we were not really facing that challenge because usually, we buy through strategic procurement, and we have that kind of relationship, and we order those equipment well in advance so that we don't face those challenges of equipment getting delivered delay. In fact, no our -- no project of AESL got delayed because of delay in the equipment delivery.

Operator

Operator
#131

We take the next question from the line of Bharat C. Shah from [ BCS Capital Ideas Limited ]

Unknown Analyst

Analysts
#132

Just one more thing, Kunjal. The borrowing level, I think, for the last year in aggregate was, I think, about less than INR 50,000 crores. 4 years down the line, what kind of borrowing level do you envisage?

Kunjal Mehta

Executives
#133

Sir, I don't have an absolute number about 4 years borrowing level, but we have been always giving a guidance that our net leverage would be in the range of 4.5x to 4.7x. So we will continue to maintain that and that financial discipline, we will continue to maintain to ensure that we always get the highest ratings for all our transmission projects. So from that perspective, we will ensure that our leverage is always in check to ensure that we have the highest ratings overall.

Unknown Analyst

Analysts
#134

But Kunjal. If this is going to be high-growth phase for our profit as projects will kick in, Therefore, if we assume the same 4.5x to 4.7x, then it will appear that our borrowings also would go to INR 125,000 crores to INR 150,000 crores, which I think based on the yearly cash flows and other things [ hideout ] or given the CapEx requirement that our borrowing level will be hitting that kind of a number?

Kunjal Mehta

Executives
#135

Sir, I'll walk you through separately about our -- the entire borrowing program for the next 4, 5 years, especially at the end of 4 years, especially at the end of 10 years.

Kandarp Patel

Executives
#136

But Bharat bhai, two things is certain that we are not reaching that number, 4.5x to 4.6x. And second thing is also certain that we have locked in CapEx of INR 77,000 crores.

Unknown Analyst

Analysts
#137

In the 4-year period?

Kandarp Patel

Executives
#138

Yes, yes.

Unknown Analyst

Analysts
#139

Yes. That's what I -- that I understand. Only Kandarp bhai, given that kind of a pace of about INR 20,000-odd a year of CapEx, I would assume that borrowing probably will not rise at the same level, but I'll separately work on that with Kunjal.

Operator

Operator
#140

Ladies and gentlemen, we will take that as the last question, and we conclude the question-and-answer session. I now hand the conference over to Mr. Kunjal Mehta for his closing comments.

Kunjal Mehta

Executives
#141

So I would just like to thank each one of you who participated in the call. In case we have not been able to answer or clarify to anyone. Happy to take any of your queries separately. Thank you.

Operator

Operator
#142

Thank you. On behalf of Adani Energy Solutions, that concludes this conference call. Thank you for joining us, and you may now disconnect your lines.

For developers and AI pipelines

Programmatic access to Adani Energy Solutions Limited earnings transcripts and 32,000+ others is available through the EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.