Adani Energy Solutions Limited (ADANIENSOL) Earnings Call Transcript & Summary

October 23, 2026

National Stock Exchange of India IN Utilities Electric Utilities earnings 66 min

Earnings Call Speaker Segments

Operator

operator
#1

Good day, ladies and gentlemen, and welcome to the Q2 and H1 FY27 Earnings Conference Call, hosted by Adani Energy Solutions Limited. Joining us from AESL as our main speakers are Mr. Kandarp Patel, CEO, AESL; Mr. Ashok Jagetiya, CFO, AESL; Mr. Raj Kumar Jain, Business Head, Energy Solutions Platform; and Mr. Prashant Soni, Head, Finance, AESL. As a reminder, all participant lines will be in listen-only mode, and you'll have a chance to ask questions once the presentation wraps up. <<operator_script>> Please be aware that this conference is being recorded. I'll now hand the conference over to Mr. Prashant Soni from AESL. Thank you. Mr. Soni, over to you.

Prashant Soni

executive
#2

Thank you, and a very good day to everyone. I'd like to welcome all of you to the Q2 and H1 FY27 earnings call of AESL. We hope you've had a chance to go through the earnings presentation and financial results, which we shared on our website. To give you a sense of how today's call will proceed, we'll start with opening remarks from our CEO, Mr. Kandarp Patel, and after that we'll open the floor for Q&A. The call will wrap up with closing remarks from CFO, Mr. Ashok Jagetiya. If you'd like to ask a question, we'd ask that you begin joining the question queue somewhat ahead of time so we can keep the Q&A running efficiently. Thank you. With that, I'll hand things over to Mr. Kandarp Patel for his opening remarks. Sir, over to you.

Kandarp Patel

executive
#3

Good morning, everyone, and thanks for being on the Q2 FY27 call today. This quarter represents yet another significant milestone in AESL's evolution. What we delivered this quarter shows that AESL is maturing into India's top integrated infrastructure platform and utility, with support from all four of our businesses, each of which is growing: transmission, distribution, smart metering, and energy solution. Our attention, clearly, stays on creating utility assets built to last. Right now our asset base stands at roughly INR83,000 crore, and we have already secured capex exceeding INR1 lakh crore, which we intend to deliver over the coming four to five years. So over the next five years, assets will expand by almost 1.3, 1.4 times compared with today's level. In fact, because we have kept our focus steadily on executing capex on the ground, we are now seeing the results come through. Capex during this first half of the year is the highest ever. Across all our businesses, we deployed approximately INR7,850 crores of capex. Turning to transmission, we added two more projects in this quarter: one at Vizag Pendurthi and the other at Satara. With those two projects included, our order book stands at around INR87,000 crore.

Kandarp Patel

executive
#4

As we mentioned before, our focus has been on the key transmission assets through which we integrate substantial renewable generation and consumption. These 2 projects are clearly very, very significant — Satara's development matters for PSP Projects' development, and Pendurthi serves the data centers coming up in the Vizag region — and we will keep concentrating on those large, critical projects such as HVDC and projects of this type, where we are enabling renewable integration into the grid as well as rapid consumption in our economy. On the distribution side, at both AEML and MUL, we have continued to deliver outstanding operational performance. Distribution losses in Mumbai came down further to 4.29% in the first half, and that is despite consumption rising by more than 10% as well. We also remain focused on reliability, customer service, and operational excellence when it comes to distribution. On smart metering, we have delivered roughly 14.8 million meters to date, which is around 60% of our order book delivered, and the remaining portion we hope to finish within another 12 to 14-month period. When it comes to the C&I and energy solution platform, we are steadily moving from incubation to scale now.

Kandarp Patel

executive
#5

For this quarter, the platform brought in more than INR2,000 crore in revenue along with EBITDA exceeding INR800 crore. We also have a tie-up in place for 4 gigawatt of renewable capacity and 3.5 gigawatt of base capacity. So while we are securing things on the supply side, we have now also begun tying up on the consumer side. In that vein, we executed the 2,500 megawatt RE-RTC contract with MSEDCL. And looking ahead, we expect to scale up considerably on both sides — our supply side as well as our consumer side. On the financial front too, we posted another strong quarter, with total income up over 50%; EBITDA rising close to 67% and PAT growing 145%. As we made a commitment and remain focused on the governance and ESG piece, we are glad to report that in the S&P global electric utility category we now rank number one worldwide, with a score of 90 out of 100, whereas the industry average sits at about 40, and we will keep focusing on those areas going forward as well. On the funding and balance sheet side, a significant portion of our debt is fixed-rate or appropriately hedged. So we don’t anticipate much volatility from foreign exchange or interest rate movements hitting our P&L or balance sheet. Overall, across all segments — whether transmission, distribution, smart metering, or C&I — we see great opportunities ahead.

Kandarp Patel

executive
#6

That opportunity pipeline is still strong, and we're in a good position to capitalize on the opportunities in front of us across all the segments. And beyond CSG, as I mentioned, we'll keep concentrating on capex delivery. So that's it in a nutshell, and I trust you've gotten all the details and materials on our financials. So thank you, everyone, and now we'll be glad to take questions from all of you. Thank you.

Operator

operator
#7

Thanks. <<operator_script>> Our first question is from Manish Somaiya at Cantor. Go ahead, please.

Manish Somaiya

analyst
#8

Morning, and well done on a solid quarter and first half. I’ve got a few questions. To start things off, on IntelliSmart, when do you expect that deal to close?

Kandarp Patel

executive
#9

Thank you, Manish bhai, for that question. Regarding IntelliSmart, we're still waiting on the CCI's approval, and we anticipate receiving it quite soon. As a matter of fact, we've had a few meetings with them, and they requested various details concerning the transactions as well as the market. We've supplied all of that information. We've also obtained approval from every utility where IntelliSmart holds a concession. So their approval is something we're required to secure as well. All of those approvals are now in hand. And we anticipate the CCI's approval very soon. Once that CCI approval comes through, we'll close the transaction right away. So we expect that to take place within the next one month.

Manish Somaiya

analyst
#10

Alright, that’s really useful. Then regarding the legacy smart meter business, you had roughly 1.3 million installations during the second quarter. It did indicate that deployment was somewhat slower in that quarter. Could you perhaps help us understand how we ought to think about deployment in the second half, and maybe what’s actually happening on the ground that could potentially accelerate deployment during the second half.

Kandarp Patel

executive
#11

Yes. So — right, clearly the rollout during the first half came in below even what we had expected, and the causes were mostly extended, but we’re addressing them, and those causes are, of course, in registers <<inaudible>> from people for a smart meter where we have now stepped up our campaign to educate those customers. The second one was that a few of the distribution companies wanted to concentrate on one particular kind of smart meter installation. So a case in point was that Maharashtra expected us to install mainly in ST consumer meters. And once you target a very specific consumer, obviously, your speed will drop because you won’t be able to cover that entire geography, and they were wanting to do it for a right reason because they wanted to complete that energy accounting at least for real-time energy accounting for ST consumer. So we supported them as well, but now that they have asked us to deploy all and every meter, which is pending. So we expect that speed to — will increase significantly. And similarly, in Bihar, they wanted us to do the tagging of all the customers before we installed that meter, and we also have completed those activities now in Bihar, and Maharashtra where the pace was slow.

Kandarp Patel

executive
#12

We anticipate that rising considerably.

Manish Somaiya

analyst
#13

All right, and finally, on transmission — if I could squeeze in one more question. I believe you mentioned that capitalization in the second half ought to be considerably stronger than in the first half, and maybe you could help us get a handle on the two or three projects that could really step up in the second half compared with the first half. Thanks a lot.

Kandarp Patel

executive
#14

Looking at our track record, or how things went over the past few years, CapEx in the first two quarters is clearly somewhat lower than in the last two quarters, largely due to weather — a great deal of transmission CapEx gets held up during monsoon and summer. So for transmission we expect total CapEx of roughly INR14,000 crore. That means we will be doing somewhere between INR8,000 crores and INR9,000 crore of CapEx in the other — in the second half. And we are completely lined up for that. Every contract has been awarded, teams have been mobilized, the contractor has been mobilized, and we — you will be seeing plenty of execution activity on the ground ramping up in the second half.

Manish Somaiya

analyst
#15

Thanks a lot. I’ll rejoin the queue. Many thanks.

Operator

operator
#16

Thanks. Our following question is from Rohan Mehta at StratEasy. Your line is open.

Rohan Mehta

analyst
#17

I appreciate the chance to speak, sir, and good morning to everyone. I have a couple of questions about the energy solutions platform. First, from what I understand, we were selling into the merchant market during the prior quarter, and now we'll be partnering with MSEDCL. So does that mean margins will decline? And second, how should we view how this segment progresses, let's say in H2 and FY28? Thank you.

Kandarp Patel

executive
#18

Rohan, our strategy over the long term is to ensure we've got substantial capacity locked in over a long-term basis on both sides. Obviously, as far as the AESL platform goes, we wouldn't want large exposure to the market. So when we began and scaled this activity up, obviously we started by tying up generating capacity, and now we've begun tying up on the consumer side as well. And you must have noticed that we've done this long-term PPA with MSEDCL, which starts operating from the last quarter of this year, and we were fortunate that during this period when we start our long-term supply, the market was good, and we've been able to earn a good margin, but over the long run, we wanted a stabilized revenue profile rather than creating volatility based on a market in our P&L.

Rohan Mehta

analyst
#19

All right, so what’s the plan for the long term, sir?

Kandarp Patel

executive
#20

So that's…

Rohan Mehta

analyst
#21

When it comes to volumes.

Kandarp Patel

executive
#22

When it comes to volume, we will definitely keep scaling this up. And right now we have roughly that 2,500 megawatt of MSEDCL PPA. We'll be entering into another PPA with AEML, for which regulatory approval has already been secured. So that PPA is something we will do. So we'll keep growing this volume, and over a three to four year span we will get to a total aggregate capacity on both sides of about 7,000 to 8,000 megawatt of tie-up.

Shirom Kapoor

analyst
#23

Alright, thanks a lot.

Operator

operator
#24

Thanks. Our next question is from Mahesh Patil at ICICI Securities. You have the floor.

Mahesh Patil

analyst
#25

Yeah. Hi, sir. Sir, my first question concerns our transmission order book. We reported work in hand of roughly 870 billion. So I assume that figure doesn’t take in the Apta project we won recently, which comes to about 120 billion.

Ashok Jagetiya

executive
#26

That covers Vizag as well as Satara, which is a deal we won not long ago.

Mahesh Patil

analyst
#27

Alright. And sir, regarding transmission commissioning, in H1 I believe we haven't brought any meaningful capacity online. From what I see in CEA data, that's largely because of ROW issues, some clearances and so on, including certain capacity at Khavda. So do we expect these three or four projects that slipped in H1 to be commissioned in H2, or what steps are we taking to speed them up?

Kandarp Patel

executive
#28

Mahesh, we recently brought one part of Phase 4 online — that's the Khavda project <<inaudible>> Hello. Hello.

Vivek Rajamani

analyst
#29

Yes, sir. We can hear you clearly.

Kandarp Patel

executive
#30

Yeah. Yeah. So we've recently commissioned one element of Phase 4K Khavda, Bhuj. Work is also continuing on Khavda-Lakadia and Khavda-Halvad. Halvad has been held up because of this ROW problem, and we expect it to be resolved very soon. In fact, it's being discussed at the government of Gujarat level as well as the government of India level very frequently. The other project we expect to commission would be WRSR this year also — this year — and we're probably going to complete it; we're trying to push that project. We might complete the Navinal project in the current year, or maybe it spills over into the first half of next year. We will be commissioning WRSR and Khavda Phase 4 Halvad. So these three projects are the sure shot, and Navinal, we probably might be able to commission. And in Mahan as well, Phase 1 will get commissioned. Phase 2 will be in the second — next year first quarter. So as you must have seen, despite these ROW challenges, we've been able to scale up our CapEx deployment as far as transmission is concerned. And with this ROW in Gujarat resolved, we're hopeful that we'll be able to scale up even further.

Mahesh Patil

analyst
#31

Understood, sir, and thanks. Sir, my second question concerns the energy solutions segment. This quarter we sold roughly 12.2 billion units. Could you break that down for us — how much was sold under our long-term contracts, and how much was on a short-term basis?

Kandarp Patel

executive
#32

In quarter two, we sold roughly 14,500 million units. Of that 14,500 million, around 3,500 million is the volume where we take a position and sell into the market, either to a third party or on the exchange. There we have a long-term tie-up for supply and sell it into the market. That accounts for 3,500 million. The second volume, approximately 9,500 million units, is where we do power trading. We sell on behalf of someone else, which is 9,500 million, and there are about 1,500 million units where we manage or provide power management services, so adding up that 3,500 million, 9,500 million, and 1,500 million. So the total volume we handled this quarter comes to 14,500 million units.

Mahesh Patil

analyst
#33

Alright, sir, but for this quarter I was simply reviewing the figures. So from the 25 BU we reported in H1, right? And during Q1, we had reported 13 — roughly 13 BU. Therefore I believed that this quarter we had sold approximately 12 BU, but I think that figure isn't…

Kandarp Patel

executive
#34

The H1 figure comes to 28,540 million, while for Q2 it stands at 14,583 million.

Mahesh Patil

analyst
#35

All right, sir, understood. And sir, one last item: on the P&L we've recorded certain assets — deferred assets of roughly 17 billion. Could you shed some light on precisely what that is?

Ashok Jagetiya

executive
#36

Two companies are involved here, MEGPTCL and ATIL. In one of them, the company has <<inaudible>> to move to the new tax regime and has recognized the past paid MAT <<inaudible>> assets in its books of account amounting to roughly INR1,500 crore. Because these qualify as Section 62 assets, a matching adjustable recoverable asset has also been — a liability has also been set up. And to that extent, the P&L sees no impact.

Mahesh Patil

analyst
#37

Understood, sir. Understood. Understood. Many thanks.

Operator

operator
#38

Thanks. Our next question is from Nikhil Nigania at Bernstein. Please go ahead.

Nikhil Nigania

analyst
#39

Hello, and thanks for taking my question. I have a couple of questions about the energy solutions business. Earlier, you mentioned a plan to scale that up to 7,000, 8,000 megawatts within a few years. I just wanted to clarify that. Did you mean on the sourcing side, or on the power sales side, that you wanted to grow it to that level?

Raj Kumar Jain

executive
#40

Nikhil, Raj here. So this mostly concerns the supply stack — the consumer stack side, that is. Clearly, capacities would be needed to meet that demand. So that figure would be higher, but yes, we're talking about the consumer stack side. That's what we're aiming at.

Nikhil Nigania

analyst
#41

Got it, Raj. Regarding the entities you're going after, you brought up that Maharashtra contract. Aside from that, are small C&I customers also in our sights, or is our selling effort mainly directed at the large data center type of opportunities?

Raj Kumar Jain

executive
#42

We already have quite a varied consumer stack today. First, there's the 2,500 megawatt MSEDCL piece, plus 750 megawatt AEML — that adds up to 3.25. We're going after several data center customers and are in advanced discussions with them. Beyond that, we have nearly 400 megawatts of C&I clients, both smaller ones, and we also handle some of the other demand, supplying our services to various internal consumers at competitive power. So we're diversifying the mix to make sure margins capture the full solutions.

Nikhil Nigania

analyst
#43

Understood, Raj. Then when it comes to sourcing, are we also looking at coal-based generation and pumped storage, or would we mostly stay with renewables — solar plus BESS types of arrangements? Solar, wind, BESS?

Raj Kumar Jain

executive
#44

The sourcing would therefore mirror consumption itself, since our aim is to align over the long term on both sides. Clearly, demand from our consumers is diverse as well, as you can tell from the mix we are discussing. So it will draw on all sorts of sources, including thermal, PSP, renewables, BESS and the like. It will thus be fully diverse, covering third-party clients and market sourcing too.

Nikhil Nigania

analyst
#45

Great. And one final question. Once that Maharashtra PPA kicks in, what portion of the BESS we've already contracted, or are going to contract, would move over to this PPA?

Raj Kumar Jain

executive
#46

So I'd put it this way: inside Maharashtra, for that 2,500 megawatt, we've secured roughly 50% as of now through our sourcing efforts. And clearly, we're continuing — we're out in the market, holding discussions with a range of parties to source additional capacity of different kinds. That's where we stand at present.

Nikhil Nigania

analyst
#47

That's great. I really appreciate it, and best of luck to you. Thanks.

Raj Kumar Jain

executive
#48

That applies across the sources, and not just to the battery.

Nikhil Nigania

analyst
#49

All right, solar combined with BESS — understood. Fine. Thanks. Appreciate it.

Operator

operator
#50

Thanks, and our next question is from Shirom Kapur at Jefferies. Shirom, you have the floor.

Shirom Kapoor

analyst
#51

Hello, sir, and thanks for the chance to ask. My first question follows on from the energy trading business. You began by giving the volume breakups. Could you also share the revenue and EBITDA breakups the way you did last quarter for the three segments inside this long-term trading, C&I trading, and power management?

Ashok Jagetiya

executive
#52

So, when it comes to trading, the average realization is roughly INR5.75. And for what we sell on the exchange for other parties, we receive somewhere in the range of INR0.02 to INR0.03 for each unit.

Shirom Kapoor

analyst
#53

Understood, sir.

Kandarp Patel

executive
#54

Just to add a bit more on that, the total sell for H1 comes to roughly 3,800, and that figure represents purchase sale revenue. When it comes to the rest of the category, we account on a net basis, which means only the margin portion is captured. So the long-term sale we've completed — the sale from a long-term contract we've done — is about INR3,688 crore. And the balance in the other category — power trading, on those C&I customers, and power management — those revenues, which are margins, come to roughly INR52 crore, INR57 crore, and INR32 crore respectively.

Shirom Kapoor

analyst
#55

Understood, sir. And then just secondly on the — so the EBITDA you'd have made on the long-term trading would simply be — so what you're saying is that INR0.02 to INR0.03 is a reasonable estimate to apply to the power management and C&I trading, and everything else is coming from the long-term trading. Is that…

Kandarp Patel

executive
#56

Correct.

Shirom Kapoor

analyst
#57

Understood, understood, sir. And then second, regarding transmission, you said you expect to commission 3 projects in 2024, WRSR, Halvad and Khavda Phase 4. So previously you had provided guidance of roughly INR15,000 crores of capitalization. So are you lowering that guidance because perhaps certain projects have slipped into the following year?

Kandarp Patel

executive
#58

Not right away, since we still hold hope of finishing what we have planned during this year, because we now anticipate that the coming six months will be a decent stretch for work on transmission projects, and we expect that those constraints which existed around ROW in Gujarat will get resolved. In fact, we have begun tackling that and have begun work on the ground. As I said, we have already finished one element of Khavda Phase 4. The second element, Lakadia, is likewise moving ahead quite quickly. In Halvad, just 50 locations remain pending, and we expect that to be finished very soon too. The WRSR project is likewise at the fag end of commissioning. Both — the substation on each side is done. The line portion has a limited issue, or rather balance work, still pending, and at present we are also doing stringing — that last phase of stringing there at WRSR. We have begun using drones to avoid ROW problems for stringing. So we expect that to be completed within this year only. So we do not see a need right now, as of now, to revise the CapEx guideline, and we hope that we will manage to do it in the next six months of this year.

Shirom Kapoor

analyst
#59

Okay, sir. And finally, regarding your smart meters business — earlier you gave guidance of roughly 10 million installations. In the first half of this year alone, you've completed 3.4 million. So I'm just wondering whether you're still on track to hit the 10 million this year.

Kandarp Patel

executive
#60

Thus, our plan for this year is roughly 80 to 90 lakh meters, and the remaining portion, around 40 lakh — 40 lakh, 45 lakh — we hope to finish within the second half of the year.

Shirom Kapoor

analyst
#61

Understood, sir, and thank you. I’ll rejoin the queue for additional questions.

Kandarp Patel

executive
#62

Alright.

Operator

operator
#63

Thanks. Our next question is from Vishal Periwal at PL Capital. Please go ahead.

Vishal Periwal

analyst
#64

Yes, sir. Thank you for the chance to speak. Sir, regarding this energy solution platform, I believe that in the contract type where we take a position, we did roughly 3.3 billion units last quarter, which carries a wider spread and better margins. This time around, we have done 3.5 billion units. So could you offer some perspective? I mean, by the end of the year, perhaps on a quarterly basis, how might this ramp-up unfold for us in that particular portfolio?

Raj Kumar Jain

executive
#65

I think there are two relevant points here. First, as we said earlier, we're ramping up that portfolio beginning at the end of our — during the last quarter we'd have capacities coming online through Maharashtra. So that's where a great deal of the capacity we currently have available would be put to work, and the margins would mirror the PPAs, which is our long-term strategy. And you'd see that the volumes — what you see today — are expected only to rise as we bring on more capacity on the sourcing side. So that's broadly the business model you'll find with us: we line up the capacities before deployment. So that's what you'd reflect — you'd see in our results.

Vishal Periwal

analyst
#66

All right, so essentially with that quarterly run rate of 3.5 billion, we anticipate a rise in quarter four. And as for — I mean, since if you work out INR0.01, INR0.02 across the other portfolios we handle, then I mean, we're earning upwards of INR2.20 on this particular side of the business. Then for RE-RTC, the figures follow a comparable path. Is that the case for us on the Maharashtra one, or is it perhaps somewhat different?

Raj Kumar Jain

executive
#67

On the volume side, to address the first question: as I said, volumes should rise steadily as we add more tie-ups on both sides. So what you're seeing now obviously includes seasonal weather swings, but on a trajectory basis, we expect volumes to grow. As for margins, that comes down to what the underlying tie-ups are, both on supply and on the deployment side. Margins in the PPAs reflect the long-term return profile of those PPAs, and you will see that play out, but we believe we'll keep maintaining healthy margins across our businesses and our diversified consumer base, and that's what you would see.

Vishal Periwal

analyst
#68

Alright, alright, alright. Then perhaps just one final question regarding smart metering. I believe, though — as I mentioned, a clarification target has already been provided for this year and next year — but when it comes to further buildup of the order book, I mean, are you seeing activity on the ground, any tendering opportunities that are, I mean, probably scaling up, or where we are bidding? Any color that can be provided would be helpful, sir.

Raj Kumar Jain

executive
#69

Regarding smart metering, yes, at present that market remains untapped for the big volumes that will arrive through the auctions. We already have auctions running in the market today. We are taking part, and we believe the <<inaudible>> ramp-up will happen because the market is recognizing the benefits as it comes in, and we are fully positioned to tap that option.

Kandarp Patel

executive
#70

Beyond what we secure via bidding, there might also be an acquisition opportunity in the market.

Vishal Periwal

analyst
#71

All right, all right, understood. Certainly, sir. I believe that covers everything on my end, and thank you.

Operator

operator
#72

Thanks. Our next question is from Vivek Rajamani at Morgan Stanley. Go ahead. Mr. Rajamani, go ahead.

Vivek Rajamani

analyst
#73

Yeah. Thanks a lot for giving me the chance, and congratulations on…

Operator

operator
#74

Mr. Rajamani, I apologize for cutting in. Your voice is breaking up. Could you please get closer to the range and speak?

Vivek Rajamani

analyst
#75

Would you say that's an improvement?

Operator

operator
#76

No. Mr. Rajamani, we’re not able to hear you. Mr. Rajamani, would you mind speaking, please?

Vivek Rajamani

analyst
#77

Is this coming through more clearly now?

Operator

operator
#78

All right, that’s an improvement. Please continue.

Vivek Rajamani

analyst
#79

Yeah, sorry about that. My apologies. Thanks for the chance to ask, and congratulations on a solid set of numbers. Just to clarify the question from the previous participant: obviously, the new contracts you have will ramp up starting in 4Q of 2027, and the portfolio mix will clearly shift as we head into fiscal ’28. Could you give us a sense — given the very strong quarter we just saw, would it be fair to say there could be some softening as we move into a cooler period from a merchant standpoint, since you'll have more longer-term volumes once these <<inaudible>> really begin from fiscal ’28 onward? Is that a fair statement?

Rohan Mehta

analyst
#80

Yes, I think so — and as we mentioned in our earlier response too, we're increasingly moving merchant volumes that are currently available to us into long-term PPAs. Going forward, we'll likely again see timing mismatches, and we'll have volumes available for those mismatches as we secure capacities ahead of our deployment. Now, what we recognize there is that machine capacity depends on market conditions, and we obviously try to steer our strategy so that we can achieve healthy returns on those. Within that framework, there are clearly PPAs we want to lock in, and we already hold roughly 3.25 gigawatts of PPAs, which also carry very healthy returns. So as volumes pick up and all the PPAs come in, we expect to sustain a very good EBITDA margin in this business.

Kandarp Patel

executive
#81

As I mentioned before, Vivek, over the long term we wouldn’t want significant volatility in our C&I profitability, so we wouldn’t take on long-term exposure to the market or a large volume of it. We’ll keep tying up capacity on both sides on a long-term basis, which gives us stability in revenue as well as profitability. And clearly, to leverage the benefit of having this diverse portfolio on the supply side as well as the consumer side, we’ll leave some capacity open, but it won’t be a significant amount. So what you’ll see over the long run is steady, growing cash flow as well as volume and profitability.

Vivek Rajamani

analyst
#82

Thanks, sir — that's excellent. One quick follow-up question <<inaudible>>

Operator

operator
#83

Apologies for cutting in, Mr. Rajamani. Your voice is breaking up.

Vivek Rajamani

analyst
#84

My apologies. Does that work better?

Operator

operator
#85

Nope, nope. It's still breaking.

Vivek Rajamani

analyst
#86

Alright, my apologies.

Operator

operator
#87

Mr. Rajamani, please rejoin the queue if you have further questions. Thank you. Our next question is from Apoorva Bahadur of IIFL Capital. Go ahead.

Shirom Kapoor

analyst
#88

Hi, thanks. I’ve just got one question. Adani Green brought on more battery capacity during 2Q, so I’d like to know whether we will also take that over and run it for the remainder of the year.

Raj Kumar Jain

executive
#89

Look, I believe we're currently in active talks with several parties, and that includes Adani Green, for whatever capacity they end up deploying. If it looks attractive to them to partner with us independently, using the market benchmarks, then they'd go ahead with us. So obviously we're in touch with them too regarding these capacities, and you'd see some of that materializing in the near future — but strictly on the market benchmarks, where the value is there for both entities, if those transactions do happen at all.

Apoorva Bahadur

analyst
#90

So if we do take over, it won’t — it need not necessarily be at the INR4.85 tariff, I believe.

Raj Kumar Jain

executive
#91

Right. I wouldn't commit to one specific figure. That number comes out of where the market benchmarks sit. It might come in lower, it might come in higher, depending on how market costs are trending. What matters is whether I'm locking in at levels that reflect market benchmarks. So whether it's SECI, NTPC, or other bids available to me — or to similar players — when I go to the market and tie up with them, versus what opportunities they might have in their own folio. That's where I think a good meeting of minds is taking place, and we've managed to tie up large capacities — built on that understanding from the past, where they earn their market returns and we secure capacities at that level. And they can do this without carrying the risk of SECI PSA tie-ups or any of those things you see in the center. At the same time, we can tap large resources. So it's a mutual win-win. At the same time, both parties would decide based on how market benchmarks are moving for a similar trade profile, for similar long-term tie-ups, and similar terms and conditions.

Apoorva Bahadur

analyst
#92

All right, thank you.

Operator

operator
#93

Thanks. Our next question is from Vin C <<inaudible>> at PhillipCapital. Go ahead, please.

Analyst

analyst
#94

Yeah, hi. Thanks for the chance to ask. My question is about the industry. So China is currently banning exports of solar technology, and that could possibly cause a slowdown in solar in India. So if that happens, can you see a reduction in the need for transmission lines going forward?

Kandarp Patel

executive
#95

Apologies, Phillip. Your point was that a ban is being placed on solar.

Analyst

analyst
#96

No, no. It’s a ban on exporting solar technology. So India still isn’t fully integrated into the solar value chain. So if that causes a possible slowdown in solar capacity addition, do you think there would be less need to add new transmission lines?

Raj Kumar Jain

executive
#97

So, Phillip, on that point, we aren't really seeing equipment bans in China, because that mostly concerns the high-tech side, where there's been some reluctance to export technology outside China—mainly, I'd say, more toward ingot and wafer, or the earlier portion of the solar manufacturing value chain. That said, if you look at India itself, on the solar side—the manufacturing side—it's an overcapacity market today, and that capacity is available across 11 schedules and so on. All of that is available. So we don't really see any impact on solar, but I don't think that's how we should view transmission. The transmission opportunity arises from multiple facets, not just from solar deployment. There's a massive amount of pipeline right now coming from states upgrading their networks, since they need to absorb capacity for their rising demands; many cities are now seeking solutions to bring more power to their own consumption sectors. You can see considerable demand coming from China—from the Mumbai area as well, or the Maharashtra area too.

Raj Kumar Jain

executive
#98

Comparable developments are being duplicated across additional metro areas. Clearly, phase three is now also arriving, with over 100 gigawatt of thermal capacity being added. That whole dynamic is likewise driving transmission-side capacity needs and the associated requirement. In a similar vein, PSPs are entering on a very large scale. Solar, then, is a single piece of the picture. Yet we see no significant deceleration in solar, for the factors you just mentioned. Essentially, this is a market in which we can choose how much of the opportunity to pursue, rather than one where opportunity is scarce.

Analyst

analyst
#99

Sure. Thanks. To build on that point about thermal: of this 100 gigawatt of thermal, I believe most is brownfield expansion where transmission lines, I think, are already in place. So if we shift more toward thermal to offset any drop in solar, do you see the overall transmission pipeline ending up somewhat smaller than it would have been if it had been all renewables?

Kandarp Patel

executive
#100

No, that's not right. Even though this is a brownfield expansion, the transmission line plan was built for the original capacity, and clearly, adding that capacity will call for extra transmission capacity as well. So whether capacity is being added through a new project or a brownfield one, the transmission capacity needed would be about the same.

Analyst

analyst
#101

Right. But given that it's incremental transmission capacity that can come online, would it lean more toward the 400 kV line instead of a 765 kV or HVDC line?

Kandarp Patel

executive
#102

No, no, no, no. I don’t believe it would likewise be heading toward a 400 kV line, since those brownfield expansions are big as well. So if both units get added, that comes to 1,600 megawatt. And clearly, several thermal projects are being built nearby. So it likely would need a comparable type of solution, such as HVDC. You must have seen recently one mega project that the Government of India has approved, which on its own exceeds 80,000 crore, right, Raj? That one is the East to North transmission corridor. So, as Raj said, transmission demand is arriving from many sectors. And now you will see plenty of transmission opportunities arising from the project, which is targeted at system upgradation and also on the consumption side and mainly around city areas.

Analyst

analyst
#103

Yes, yes. Thanks a lot, sir. I appreciate the responses.

Operator

operator
#104

Thanks. Our next question is from Shirom Kapur at Jefferies. You have the floor.

Shirom Kapoor

analyst
#105

Hello, sir, and thank you for the chance to ask. I just want to clarify something. You said roughly 3.25 gigawatts of PPAs are already signed on the energy trading side. That would break down as 2.5 gigawatt MSEDCL plus 750 megawatt AEML, right? And on those two — has the AEML one started operating yet, or does it still need to be operationalized?

Raj Kumar Jain

executive
#106

On timelines and capacity: for the 2.5 gigawatt MSEDCL contract, deployment begins at the end of February this year with 1,000 megawatt, followed by another 1,000 megawatt starting at the end of April, and a further 500 megawatt at the end of July next year. Regarding the 750 megawatt, the regulator has already granted approval and all the processes are complete. We're now working on executing it and expect that to take place within the coming three to four weeks. Under that particular PPA, the capacity window runs two years from the signing date. That gives us flexibility on the deployment side. I hope that addresses your question.

Shirom Kapoor

analyst
#107

Understood, sir. Then, secondly, returning to transmission — if you could put a figure on it, a few weeks ago you also won an intrastate project recently. Could you quantify what that project's value would be, and what the pipeline looks like going forward? Of that 1.4 trillion tender pipeline you mention, how much is interstate as opposed to intrastate, and how do you see progress specifically on the intrastate side?

Kandarp Patel

executive
#108

Both of the projects we won last quarter — one is Satara and the second is Pendurthi — are interstate projects.

Raj Kumar Jain

executive
#109

And at this moment, look, I'd say the tender pipeline at the country level stands at roughly INR140,000 crores. So it's distributed between the states and the central side. Naturally, the central piece includes a fair number of — or some of the HVDCs too. So the weighting leans toward the center when it comes to the share of tenders already out there, but as we said earlier, there's a substantial amount of capacity buildout happening in the new GEC II category as well, which was approved recently and is aimed more at building out the intrastate network. So this split is a shifting split and will have its own distribution as we go forward. So naturally we pick where we — where it fits us best, which projects suit us better, and concentrate on those to make sure we deliver value on our bids and add value for our stakeholders <<inaudible>>.

Kandarp Patel

executive
#110

And on the directional side — yeah, directionally, you're going to see quite a bit of new projects and opportunities coming from stateside, like I mentioned earlier. So a lot of projects are going to need to be developed on the consumption side, particularly in those areas where enormous amounts of consumption are coming up when it comes to data centers or manufacturing, and also around those cities that are growing. For instance, this year we're seeing consumption in the city of Mumbai rise on the order of 11% to 12%. So that kind of consumption growth in cities will also drive the need for additional transmission capacity in those city areas.

Shirom Kapoor

analyst
#111

Okay, sir. But to pick up on the intrastate pipeline, you're saying there are — directionally, more opportunities will be coming up. How does the competitive landscape look on the intrastate side compared with interstate? And do you expect your typical project IRRs or ROEs to come in a little lower on the intrastate side than the typical interstate ROE?

Kandarp Patel

executive
#112

For intrastate projects, the returns tend to be somewhat stronger than what you see interstate, and the reason is clear: the developer is dealing with a state regulatory framework rather than the central one. So in state-level cases, the ROE usually comes out somewhat better.

Shirom Kapoor

analyst
#113

Understood, sir. Thanks very much.

Operator

operator
#114

Thanks. Our next question is from Vishal Biraia at Bandhan AMC. Vishal, please go ahead.

Vishal Biraia

analyst
#115

Hey there. So regarding the capital allocation target, for this year as well as next year, I missed…

Operator

operator
#116

Apologies for cutting in. Mr. Biraia, we’re not able to hear you. Could you speak a bit louder?

Vishal Biraia

analyst
#117

Right, right. Could you go over the capitalization target once more for FY27 and ’28 in the transmission business, please?

Ashok Jagetiya

executive
#118

As we mentioned in response to the earlier question, we do expect to incur INR8,000 <<inaudible>> crore of additional CapEx during the second half of this year, plus another INR18,000 crore to INR19,000 crore in FY28. That is the pipeline we are projecting on the transmission side.

Vishal Biraia

analyst
#119

And sir, does capitalization also apply to gross blocks?

Kandarp Patel

executive
#120

Capitalization would likewise land in the range of INR8,000 crores to INR9,000 crore. So when we look at WRSR, Khavda Phase 3, Halvad — that being the Halvad project — plus Khavda Phase 4, counting just those three, the figure comes to approximately INR9,000 crore.

Vishal Biraia

analyst
#121

And then next year, would we be nearer to INR10,000 crore, sir?

Kandarp Patel

executive
#122

When it comes to capitalization?

Vishal Biraia

analyst
#123

Yes, sir.

Kandarp Patel

executive
#124

Alternatively,

Vishal Biraia

analyst
#125

No, capitalization.

Kandarp Patel

executive
#126

For capitalization, it would be roughly — give me a minute. That figure will also come in around INR10,000 crore. Capitalization is going to jump following the subsequent — meaning after next year — on account of those HVDC projects being commissioned. That is going to add capitalization in a lump.

Vishal Biraia

analyst
#127

Yeah, I agree. Sir, I have a question about the borrowing side. Out of that total net debt of around INR41,000 crores, how much comes from ECB?

Ashok Jagetiya

executive
#128

Turning to borrowing, ECB accounts for roughly 10%. Of the total debt of INR51,000 crore, about 10% comes from the ECB.

Vishal Biraia

analyst
#129

So ECB accounts for 10%. All right. And for this year, as you mentioned earlier, the currency exposure is hedged — but has the interest rate also been locked in for a few years?

Ashok Jagetiya

executive
#130

Correct.

Vishal Biraia

analyst
#131

Or is that entirely variable?

Ashok Jagetiya

executive
#132

No, no, no. When it comes to USD bonds and ECBs, those all carry fixed interest rates. That means 75% to 80% of the debt portfolio sits on a fixed coupon basis.

Vishal Biraia

analyst
#133

Alright, fair enough, sir. That’s quite useful. Thanks.

Operator

operator
#134

Thanks. <<operator_script>> Our next question is from Anuj Upadhyay at Investec. Go ahead, please.

Anuj Upadhyay

analyst
#135

Yeah. Hello, sir. Thanks for the chance. Sir, just one point of clarification. The 4.6 gigawatt tie-up along with 3.5 gigawatt of battery storage, that all comes entirely from Adani Green, correct? As of now, there isn't any tie-up that includes Adani Power.

Kandarp Patel

executive
#136

Right now, there’s no tie-up with Adani Power, but of the total capacity, roughly 700 comes from third parties as well. 650.

Anuj Upadhyay

analyst
#137

All right. You said that out of the overall volume we traded under the energy solution, close to around 3.5 billion was on a merchant basis, and the remainder was on a trading basis where we earned roughly INR0.02 to INR0.03 as a margin. So you just said what the margin was on the merchant basis, sir?

Kandarp Patel

executive
#138

Sure, sure — somewhere in the range of INR1.70 to INR2.

Anuj Upadhyay

analyst
#139

Okay, and in our earlier discussion, sir, you said we'd be looking at roughly 10 gigawatts of PPAs with the C&I and data center segment, where the typical spread might land between INR0.80 and INR1. Now, on the supply-side PPAs — the ones we're signing on the obstacle side as of today — with AEML we've executed 700 megawatts. With MSEDCL, we've executed 2.5 gigawatts. So even across this 3.5 gigawatts, do we expect a similar kind of margin, or are the margins here more on a regulated basis, which would be much lower?

Kandarp Patel

executive
#140

No, no. It wouldn't be significantly lower, but it wouldn't be this high either, since the market conditions that prevailed during these two quarters are the reason. As we mentioned before, we expect <<inaudible>>.

Anuj Upadhyay

analyst
#141

Hello there.

Kandarp Patel

executive
#142

Hi there. I’m hearing a bit of background noise.

Anuj Upadhyay

analyst
#143

Yes, sir.

Kandarp Patel

executive
#144

Right. So we don’t anticipate — like I mentioned before, we wouldn’t want to see this type of market volatility in a particular quarter where, due to market conditions, you get a bumper margin, and then perhaps afterward, that significant margin may not be there. So we’ll lock things in on a long-term basis, where those margins will be around INR0.80 to INR1 consistently.

Anuj Upadhyay

analyst
#145

All right, that's fair, sir. And would it be reasonable to assume, sir, given the tie-up we currently have on the supply side — that is, from Adani Green plus the 600, 700 from the third party — that the volume available for us to trade on a merchant basis would fall in the range of 13 billion to 14 billion annually under the current contract? Because on a very simplistic calculation I did, at 4.6 gigawatt, that gives us close to around 10 billion units to be traded plus 3.5 gigawatt hour of battery. Assuming that battery is again charged through the power, if we take it from the grid at a very low rate during the solar hour, it comes to somewhere close to 14 billion of — in units. And just going by your quarterly run rate, this quarter we sold somewhere in the range of 3.3 billion on a merchant basis. So is it fair to assume, based on our current tie-ups, that we have this quarterly run rate of 3.3 billion or 3.5 billion units available to be traded on merchant until the time the PPA is added <<inaudible>>?

Kandarp Patel

executive
#146

That's true, though we should keep in mind that renewables — both wind and solar — will follow a seasonal pattern. Still, taken as a whole, it should come in around 3,500 million units per quarter.

Ashok Jagetiya

executive
#147

Regarding the MSEDCL PPA, supply of roughly 1,000 megawatt is set to begin near the end of February. A portion of that will be directed there.

Anuj Upadhyay

analyst
#148

Understood, understood, sir. Appreciate it. That's quite useful.

Operator

operator
#149

Much appreciated. Our following question is from Ishan with Antique. The floor is yours.

Ishan Verma

analyst
#150

Hello, sir. Thanks for taking my question. I just wanted to get some clarity: since our contracts with Adani Green operate on a take-or-pay basis, and curtailment is a bigger issue at the moment, if the power isn't scheduled onto the grid and gets backed down, who ends up bearing that cost?

Raj Kumar Jain

executive
#151

In essence, whenever they supply me with power, I pay for it — whatever the price of that power is. So on the generation side, clearly, the grid problem lies with the generator. Just like any other purchaser — for instance, those who hold PPAs with SECI or anyone else — we pay for the electricity that gets delivered.

Ishan Verma

analyst
#152

All right. So in the event that power isn't getting to you, then Adani Green would be the one footing the bill for the curtailment. Is that right?

Raj Kumar Jain

executive
#153

Yeah, that’s the risk they’re up against in their business.

Kandarp Patel

executive
#154

Basically, the way this works is that with any PPAs you might hold — whether those are with AESL or with any utility — it's the generator's job to schedule that power, and as soon as it's scheduled, taking it up and paying for it falls on you. Right now, they haven't managed to schedule in line with the curtailment being enforced. So our obligation kicks in the instant the power gets scheduled.

Ishan Verma

analyst
#155

Understood. Second, sir, you said there isn’t a PPA in place yet with Adani Power, but as I understand it, this MSEDCL PPA also has a thermal component in order to provide round-the-clock power. So if you could give us some sense of it: will there be a tie-up with Adani Power, or, say, how much thermal capacity do we need to secure under this particular contract?

Kandarp Patel

executive
#156

With the MSEDCL PPA, there's no requirement on our side to hold thermal capacity. We have complete flexibility here. It functions as an energy supply contract, not a standard PPA locked to one specific source. That means I'm free to put together any combination, though clearly thermal capacity will be needed, and we're looking at a range of other ways to secure capacity — thermal capacity — over the long term. That could be Adani Power, it could be others too, and we've also been in discussions with third parties regarding a thermal PPA.

Ishan Verma

analyst
#157

Right, so at this point we aren’t able to quantify how much thermal will be needed for this particular PPA.

Kandarp Patel

executive
#158

That's right. And we don't want to commit that kind of capacity in a manner that would cost us the full flexibility we want to keep on the supply side. That way I can draw on that whole supply stack as optimally as possible, both technically and commercially.

Ishan Verma

analyst
#159

Understood, sir. Appreciate it. That covers everything I wanted to ask.

Operator

operator
#160

Thank you. Since nobody has any more questions, ladies and gentlemen, that brings the question-and-answer portion to a close. At this point I'll turn the conference over to Mr. Ashok Jagetiya, who will offer some closing remarks.

Ashok Jagetiya

executive
#161

Thanks to all of you for making the time to be on this call. Should any further question remain unanswered, please reach out to us individually, and we'll gladly address it. Thank you.

Operator

operator
#162

Operator signoff.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Adani Energy Solutions Limited transcript — plus 131,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Adani Energy Solutions Limited earnings transcripts and 131,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Adani Energy Solutions Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.