Agnico Eagle Mines Limited (AEM) Earnings Call Transcript & Summary
February 12, 2021
Earnings Call Speaker Segments
Sean Boyd
executiveThanks, operator. Morning, everyone, and welcome to the call covering our fourth quarter and full-year 2020 results. Before we move into the slides, I want to remind everyone that forward-looking statements are part of this presentation, and that material is in the deck. To kick things off, regarding how we finished the year and how we're set up going forward over the coming several years, we delivered a record quarter on production, and that produced record cash flow. Even more significant, we achieved our strongest safety results ever. Even though we're moving more volume than at any point before, and we have more workers than at any point before, we're running more safely than at any time in our history. A huge thank you goes out to our employees. It speaks to their dedication and to the fact that they arrive at work each day wanting to contribute and caring about where they work and the colleagues beside them. Thanks to that operating performance, the business across full-year 2020 produced operating cash flow of $1.2 billion. That keeps strengthening our financial standing, solid liquidity, we declared our quarterly dividend of $0.35 per share, and we also brought on another credit rating agency to rate us investment grade. We recently got Moody's to do that. It simply demonstrates the strong financial position, which keeps getting stronger as we expand our production over the coming several years. We anticipate growing output by 24% off the 2020 level as we progress through 2024, and our record reserve position backs that up. Plenty of records as 2020 wrapped up. That reserve growth is underpinned by exploration results; this isn't only a story about growing production, but also about being able to enhance the quality of our asset base, expanding deposits at our current mines as we go forward. Because of that, we've raised our exploration budget by more than 40% to $160 million. Exploration remains very much a priority, and we'll discuss how it fits into the strategy shortly. It's a crucial piece of the story. The strategy will stay the same. It's consistent. It's essentially to grow production per share by concentrating on the geological potential of our asset base, by optimizing our current mines, as we mentioned, through exploration, and then developing our project pipeline; we have visibility at LaRonde, at Goldex, when it comes to further conversion of resource into reserves, which will extend the lives of those assets, along with bringing new projects into the company's production base with the announcement of Amaruq underground and Canadian Malartic underground. A major element of the strategy is keeping the business low risk, managing political risk, remaining in those jurisdictions we know well, but also continuing our leadership and excellence in ESG, which we keep doing. We're AA rating at MSCI. Corporate Knights placed us at number 73 globally, and that's across every industry, not only mining, when it comes to ESG; our leadership in that area keeps getting acknowledged. Now to the quarter's key points: as mentioned, for the first occasion in more than 60 years of our history, quarterly output exceeded 500,000 ounces; that lifted us past the upper end of our guidance range for 2020, reaching 1.736 million ounces. Our reserves, as noted, climbed to an all-time high of 24.1 million ounces. We'll get into the details shortly. Supporting that is more spending on exploration, as mentioned; the focus of that work is squarely on sites such as Canadian Malartic, where the budget shared with our partner comes to roughly $30 million; we'll cover that shortly. There are substantial budgets at LaRonde, where drifts are being extended across four separate zones so the entire felsic rock package can be opened up as we advance westward and also eastward. It's a major year for exploration. Yesterday, as mentioned, the board gave approval to proceed with the Odyssey and Amaruq underground projects. We'll discuss that shortly. Production keeps climbing steadily; during 2021, costs are set to be below 2020 levels as output rises. Over the coming four years, as mentioned, we anticipate production growth of 24%; during 2021, we ought to be more than 300,000 ounces above 2020, while unit costs decline roughly 6%. Looking ahead, somewhat greater costs are expected, which we've laid out in the press release. The main factor — almost the primary one — is elevated costs at our Amaruq deposit; cost performance remains very strong at several of our mines, especially those in the Abitibi, and we'll get into that. It's really Amaruq's high costs that have pulled the overall average up somewhat. On capital expenditures, we project roughly $800 million for 2021, given that two new projects received approval. Even at that figure, we'll still produce considerable net free cash flow. Regarding the project pipeline ahead, there's no rush on our part. They'll be staged, spaced out, and our CapEx will stay aligned with the level of the past couple of years going forward. We covered our gold reserves and mineral resources. Apart from Hammond Reef, every one of those reserves was calculated at $1,250. For Hammond Reef, the figure used was $1,350. As mentioned, it rose 12%; more than a million ounces were added across a number of our currently producing assets, with the remainder attributable to Hammond Reef. What isn't captured in that figure — and what these reserves and resources exclude — are the reserves and resources held at the recently acquired Hope Bay project. I'll address that shortly; we also kept a solid resource base, with measured and indicated at 15 million ounces and inferred at 23 million ounces. We have a solid foundation of reserves and resources that underpins our capacity to keep expanding production. When it comes to opportunities in the near term, there are a number of them. Kittila has enjoyed a strong year. They turned out record quantities of gold, and they keep increasing their yearly throughput. In the prior year, I believe the average was 1.85 million tons a year, heading to 2 million tons per year. The mill expansion wrapped up a bit ahead of schedule during Q4. They keep advancing that opportunity; they are also examining, given exploration success, as they drill the deposit while it plunges to the north, the possibility of raising yearly throughput from the 2 million tons per year figure by 20%-25% above that figure. That study is going to happen over the coming two to three years simply to keep optimizing the expanding size of that ore body. Malartic phase 2 is still on track. In January, we were at roughly 4,600 tons a day, and we will steadily raise that across the next few years to 6,000 tons a day; we discussed the Amaruq underground project receiving approval for construction. The aim is basically just to mine the higher grade underground sections of that deposit alongside the open pits.
Sean Boyd
executiveWe anticipate the first gold pour in 2022, when we start reaching ore via the underground ramp network. Across that 5-year stretch, the underground portion should average roughly 2,000 tons per day in mining rate. On the whole, we're looking at mining close to 3 million tons, averaging approximately 2.5 grams per ton. From the underground alone, that contributes around 100,000 ounces annually to Amaruq's output. In certain years, once you put the underground and the open pit together, Amaruq is going to rank as Agnico Eagle's biggest single gold producer. This is a top-tier asset that will throw off considerable cash flow down the road; those volumes will come because combining open-pit ore with underground ore gives our plant the ability to process roughly 12,000 tons per day. Building that underground will cost about $140 million in capital, plus close to $40 million for sustaining. At $1,550, the after-tax return comes to 28%. Now let me turn to Odyssey. Drilling and exploration there keep delivering success, which is what we anticipated, since we've been running a very busy drill program on site for the past 2 to 3 years. At East Gouldie, the resource grew by more than 130%, reaching 6.4 million ounces. Right now 11 drills are aimed at the East Gouldie zone, both to keep growing that deposit and to reduce the drill spacing, especially within the high-grade core of East Gouldie. Across the whole property in 2021, Agnico and Yamana will put roughly $30 million into drilling. That's a hefty budget. Of that, $24 million goes mostly toward East Gouldie. The remaining $6 million will fund drilling on regional targets, since it's fascinating — discovering East Gouldie has basically unlocked a completely new mining horizon with enormous potential, judging by what we're seeing there. That's another thing our 2021 drill program is focused on. The underground ramp keeps advancing. That matters, because as it goes deeper, drilling gets simpler; it provides us a better setup to test those underground targets, especially at Odyssey, East Malartic, and East Gouldie too. As for the Odyssey project at Canadian Malartic, the underground venture, it's genuinely a very large, low-risk, high-quality opportunity; we expect it to become Canada's biggest underground gold mine by yearly output. Once at full production, we figure it will yield around 550,000 ounces each year, based on processing about 19,000 tons daily; we can sustain that high rate because there are basically 4 underground sources of ore. Honestly, the moment everything shifted for this whole undertaking was the discovery of East Gouldie, because that deposit by itself opened up an additional ore source that's both bigger and richer. And once you combine it with Odyssey North, Odyssey South, and the historic East Malartic zone, you end up with scale. Scale is genuinely what allowed the underground footprint to reach the size it has. Once we're running at full capacity, we're looking at cash costs in the neighborhood of $650 per ounce. The operation should last a very long time, stretching to roughly 2040, and keep in mind that figure only reflects a current plan incorporating approximately 7 million ounces. We know that when we add everything up — I guess we're not supposed to add everything up — but when we do, reserves plus resources come to more than twice what's in the current economic plan and the mine plan going forward; these deposits remain wide open as we understand them, and the whole horizon is wide open. We think this will be a major part of the business for both Yamana and Agnico for many, many years. At $1,550, the after-tax rate of return is 17%-18%. We feel there's still room to optimize the study and optimize the plan. We'll keep working hard at that. CapEx — 100% CapEx — is $1.3 billion. Looking at the stretch between 2021 and 2028 — essentially the build-out period — we anticipate generating over 900,000 ounces, with cash costs sitting at about $800, which makes it nearly capable of funding itself, if you think about it. Within that $1.3 billion figure is a production shaft reaching 1,800 meters deep, designed to handle roughly 20,000 tons each day. Production will be brought on gradually across multiple years, as we've mentioned, with the ramp kicking things off in 2023 — late 2023, that is. As for the shaft, our target for commissioning it is 2027. Like we've mentioned, once we finish ramping up the underground mine — that includes East Gouldie, the deepest among the four ore sources — we anticipate hitting full production of roughly 19,000 tons per day by 2031. We've also said lately that moving ahead with this production decision right now, grounded in the resource, feels right to us, since the cost figures hold up well. A lot of the design criteria and parameters this study relies on closely mirror what Agnico Eagle already runs at its operations in the area. Pairing that level of confidence with the fact that we're working from live cost data and hands-on experience at Canadian Malartic, we feel good about both the production plan and the cost estimate. On the project pipeline side, we keep making it more efficient. Like we mentioned initially, there's no rush on our end to construct these. Our focus is simply on steadily enhancing the value of these assets via exploration, refreshed studies, and bringing in new approaches. When it comes to applying new approaches on particular projects, such as Hammond Reef, we're evaluating ore sorting. Before we commit capital there, additional work remains; over the past year, we've achieved considerable advancement on these projects. At Upper Beaver, the deposit keeps expanding. Due to the substantial copper credit, we anticipate it will eventually become a low-cost producer. The location sits in a favorable region, one known for mining. It's extremely close to what we operate in Quebec, so honestly you couldn't ask for a better position. As we've mentioned, we keep creating value by drilling, and drilling there will carry on, with the study refreshed around the close of this year. I'll cover Hammond Reef, and after that Hope Bay. Over at Hammond Reef, we've brought in 3.3 million into reserves. The whole mineralized envelope exceeds 5 million ounces. Our aim is to optimize that plan and pull more gold resources into the mine plan; this is kind of the initial pass at it; we began revisiting it roughly a year back. This location has always been appealing to us because it's well situated, the permitting process isn't complicated, and the community is supportive. What held it back was its low-grade nature, but we think there are approaches—ore sorting among them—that allow us to improve the economics. We'll continue advancing it and building value. And again, we haven't made any commitment to put substantial capital into it. Now, on Hope Bay, the deal closed on February 2nd. That project has reserves of 3.5 million ounces and resources of 3.8 million ounces. As we've said before, neither of those numbers is included in our current reserve and resource statement.
Sean Boyd
executiveAs a lot of you are aware, the land package is quite large. It's an 80 km greenstone belt containing three identified deposits: Doris, Madrid, and Boston. Like we've mentioned, exploration is the priority for this year, with a budget planned at roughly $16 million. Delineation drilling accounts for $5 million of that, while $11 million goes toward testing targets surrounding the three known deposits as well as other targets across that 80-kilometer greenstone belt. Right now the mine turns out somewhere between 18,000 and 20,000 ounces each quarter. Cash costs sit in the $950 to $975 range. Operations at the mill run three weeks on, then three weeks off; our projection is that Hope Bay reaches cash flow neutral during 2021, and none of our overall total Agnico cost guidance includes those production cost or CapEx figures. Alongside our work to grow the reserve and resource on the property, we'll be concentrating on optimizing the Doris mine as it stands and then assessing expansion scenarios; our belief is that the project could eventually yield 250,000 to 300,000 ounces. The study remains to be done, and the work remains to be done. We have confidence that a solid path forward exists as we apply our Nunavut expertise there. We don't expect to spend any meaningful expansion capital at that site during the next two years; when it comes to the individual assets and operating results, LaRonde is where I'll begin. More than 30 years on, it's still our biggest source of cash flow. Output exceeded 105,000 ounces, with cash cost of $434. Another robust quarter in Q4; across the entire year, it actually hit its initial budget even though operations halted in Q2 because of COVID's effects; something else notable in Q4 is that automated scoops mucked 28% of LaRonde's tonnage, while automated scoops mined 16% of the tonnage at LZ 5. That's the direction LaRonde is heading as we go deeper. According to our exploration work, there's additional mine life at depth, which makes automation critical — not only for efficiency and cost reasons, but for safety too; during Q4, that result was largely fueled by more tons coming out of the West Mine area at grades exceeding what we'd expected. The deposit keeps expanding. As we've noted, reserves are growing. Quality ounces are still being added. We continue to add substantial tons to the mine plan; we'll get into the exploration details before long. Over at Goldex, quarterly production set a record. Roughly 40,000 ounces with cash cost under $600 per ounce. We averaged more than 8,000 tons per day. That's the best daily tonnage since the mine was restarted back in 2013, so the teams there have performed exceptionally well. The thing that has genuinely driven them past 8,000 tons per day is outstanding results from the underground Rail-Veyor system. Our team evaluated that technology a few years back, committed the capital to install it, and it has proven to be a truly significant boost to how efficiently that mine runs. Consider this: we're pulling out roughly 1.5 grams per ton, and the mine remains highly profitable. Over at Canadian Malartic, we had our strongest full-year safety results ever. During Q4, we kept making small adjustments to increase plant throughput, and we set yet another quarterly record of more than 62,000 tons per day. If you total up the Abitibi, those 3 assets delivered more than 230,000 ounces in Q4 at a cash cost of about $540 per ounce. All 3 of those mines continue to be a very meaningful piece of our business. Even more significant, they're strong cash flow generators, especially when we consider chances to prolong LaRonde's mine life through our exploration wins at depth, and to prolong Goldex's mine life as well, since we're also seeing encouraging drill results at Goldex as we examine the Deep 2 zone. With Canadian Malartic underground now added, that will remain a key part of our business for many years. At Kittila, as we mentioned, record ore production for the year translated into record gold output in 2020. After many years, we're at last settling into a rhythm, so to speak, in which we can better align the large ore body with a production rate heading to 2 million tons per year. Additional work remains, since that deposit keeps expanding. We can see it through extra ore sources indicated by recent drilling that could let us push that up by another 20%-25%. Again, we're not rushing into that. Doing the work and thinking it through will require 2 to 3 years. There's still upside there, and the deposit keeps growing. At Meadowbank Amaruq, consistent gains; we've witnessed improvement quarter after quarter. Record open pit production for the quarter, with 3.8 million tons mined per month. They've performed well on equipment maintenance and availability, and the operation has been steadily getting better over time. Once higher-grade underground ore is added, it will turn into a far more substantial producer for us. We still have cost work to do. Costs run higher because of strip ratios as we head into the next couple of years. They'll come down once we reach 12,000 tons a day with more high grade as we move into 2024. We still need to put more effort into the cost side. At Meliadine, record quarterly safety performance, another solid quarter, another strong operating and production quarter, 90,000 ounces at roughly $650 per ounce cash cost, but a very good operating margin quarter and cash generating quarter at $108 million in the quarter. This is our number two producer behind LaRonde, and it actually outpaces Canadian Malartic. We'll keep growing it, so it remains a key piece of what we do moving ahead. In Mexico, things are running steadily, with solid cash generation carrying on from those operations. Let me briefly go over the financial side. What really stood out to me, after 36 years here, is the record cash from operating activities — more than $1.2 billion. Back 20 years ago, in the late 1990s, we brought in just $50 million of revenue. That shows how our approach works: bolt on smaller assets, grow them into significant contributors, and do so while holding our share count low, which lets us deliver per-share returns to shareholders. That kind of cash generation gives us greater financial flexibility and reinforces our investment grade credit rating — we've now added Moody's to the agencies that rate us. By the end of December, our cash balance had risen $400 million. Once more, a modest share count after more than 60 years in this industry, plus a debt maturity schedule that looks very manageable going forward. Dividends remain a vital element of our story — we've been paying them for 38 years.
Sean Boyd
executiveWith the output growth we have, with the way we can extend several of our key mines, and with the newly approved projects we just announced — including Amaruq underground, which has a very long life — we believe we are positioned to keep raising our dividends going forward while expanding production in this business. Let me give a quick wrap-up, and then we'll take your questions. Basically, 2020 ended strongly, just as we had expected. Because we came through the difficulties of Q2, we accomplished a great deal of significant work during that quarter to get the assets ready for the robust second half we ultimately achieved; that mattered not only for generating cash, but also for setting us up for ongoing growth over the coming four years, and for positioning projects past 2024 so we can keep growing and keep adding value. Our tolerance for geopolitical risk hasn't changed. We're at ease with roughly where we stand. We remain committed not merely to doing the right thing on ESG, but to leading on ESG. We haven't said much about how greatly we contributed to our communities throughout COVID, yet that is definitely getting acknowledged by federal governments in the nations where we operate. Let me wrap up with exploration, since our achievements there have genuinely pushed us to reconsider the 10 to 15 year production profile compared with where we stood roughly 3 years ago. Much of that relates to our constant strategy: we want to know what we own as early as possible. That's the reason we have a record of drilling deep holes to determine whether those deposits continue; that's how we come to be discussing Canadian Malartic Underground. There was a deep target that hadn't been in the budget, and we added it to the budget following a mine visit, saying, "Look, our experience at LaRonde teaches us that when you have a geological structure that's wide open, it's important to understand how deep it goes." We're seeing that at Kittila today. We're seeing it carry on at LaRonde, where after more than 30 years, we're producing more gold than ever before and generating more cash than ever before, and we're still finding more gold. Consequently, we're going to put money into four exploration drifts to move westward into the old Barrick ground, since that same felsic package of rocks that contains all the LaRonde world-class ore bodies also exists on that land package to the west; we're going to open it wide open to see what's there. We're also going to drill toward the east, where we have some high-value net smelter return drill holes on a zinc zone, the reappearance of the 20 North zinc zone. There's a great deal going on at LaRonde, and that's a positive sign for the future of the asset that generates the most cash for us. At Kirkland Lake, Upper Beaver keeps expanding. We feel good that it will become a mine at some point. Once more, we'll provide an updated study later in this year, and then we'll figure out the best way to slot it in. Down at Pinos Altos in Mexico, we keep encountering strong drill results at the satellite deposits and at Santa Gertrudis. Those will be folded into our production plan as we move ahead. Basically, looking at things strategically, our plan is simply to keep concentrating on the approach that has served us extremely well over many years, and to optimize and unlock the complete potential of the mines we already own, with a clear emphasis on exploration, since that is delivering genuinely strong value relative to the money we put into exploration. We intend to advance the project pipeline. We're lucky to have a robust project pipeline; Hope Bay was added to it. We're positive about it over the long term. In our view, it will expand considerably past the reserves and resources it currently holds. That pipeline will be advanced in a steady, consistent way. When it makes sense, we'll bring in high potential projects with outstanding geological prospects in regions of the world where our skills are strong. That's what we've been doing since 2005, when we began acquiring assets such as Kittila and Pinos Altos. It has served us well when it comes to building per share value, and that's what we'll keep doing. Operator, I'd be glad to open up the line. Our entire team is here with us virtually, and we're happy to take the questions that come in from the callers on the line.
Tyler Langton
analystGood morning. Thanks for taking my question.
Sean Boyd
executiveMorning.
Tyler Langton
analystI had one thing on Amaruq. In 2023, I believe your total Meadowbank production guidance is roughly 415,000 ounces, with about 100 coming from underground, and then roughly 300 from the open pit. And I think after 2023, you're guiding the underground to be a bit around 120,000. What does the open pit look like, I guess, in 2024 and past that? Does it remain near 300,000 ounces, or should it come down somewhat?
Sean Boyd
executiveDominique, could you assist us with how underground and open pit at Meadowbank split as we move past 2023?
Dominique Girard
executiveRight. The Amaruq underground will contribute 100,000 to 140,000 ounces; as a result, Meadowbank as a whole is expected to exceed 500,000 ounces, making it our largest operation during 2024 and 2025.
Tyler Langton
analystGreat. That's helpful, no doubt. So, I suppose this is my last one. Free cash flow in 2020 was quite robust, I'd say. As you look ahead to 2021, aside from earnings and CapEx, roughly speaking, are there any other things — taxes, for instance, or similar items — that might influence how free cash flow shapes up during this year?
Sean Boyd
executiveSure. Compared with 2020, cash taxes are going to come in somewhat higher, and the reason is those extra 300,000 ounces of production, which will be more profitable, or will boost overall profit. So cash taxes will rise a bit, though not by a large amount.
Tyler Langton
analystExcellent, thank you very much.
Fahad Tariq
analystGood morning there. Appreciate you fielding my pair of questions.
Sean Boyd
executiveMorning to you.
Fahad Tariq
analystRegarding Hope Bay, I understand you said that during the coming 2 years, you don't anticipate major CapEx spending. Past that window, when you compare Hope Bay with certain other projects, could you give us some insight into how you view what it's up against? Is it up against Upper Beaver and Hammond Reef, or is there already a ranking established among those projects, even prior to additional work being done at Hope Bay?
Sean Boyd
executiveNo, it's up against the 2 you named. Those are the ones we continue to evaluate. I'd say Upper Beaver holds the advantage, so to speak, because of our familiarity and because of where it sits. Hope Bay is still a work in progress. What appealed to us, I think, was that 80-kilometer greenstone belt. We've achieved significant success with geological belts when we're able to control them 100% in terms of adding ounces, so we're confident this will grow larger. Essentially, we need to take a step back on this one since everyone recognizes a new processing facility is required. What and where will be the question? The where will hinge on exploration results as we proceed. More work remains. That's the reason we're not rushing here. Our top crews were already up there lately. Our project development team, along with some of our senior team at Nunavut, spent a week there. We've started the process of assigning people from our technical service group to examine various expansion scenarios. Once again, the entire concept behind our strategy is to stage and spread these projects out over time. It will simply require us to apply some of our key project development teams, collaborating with our technical service group and the operating teams in those jurisdictions to optimize the project studies and compete for the capital.
Fahad Tariq
analystAlright, that makes a lot of sense. Just one more thing from me regarding Kittila — I'm trying to wrap my head around what's happening with the shaft sinking contract. Have I got it right that everything there is now going to be handled by our own team, or are we still using a contractor, just with extra people brought in locally? I'm basically just looking for a clearer picture of the situation.
Sean Boyd
executiveDominique?
Dominique Girard
executiveYes. We will keep reducing it. Naturally, at this point we're pursuing mitigation by bringing in additional local workers and providing training for people from the area. The shaft remains under a contracted construction phase for sinking. The real difficulties stem from the travel problem connected to COVID. Individuals have to be isolated and undergo testing, which creates certain complications when a Canadian contractor is sent there. The team is seeking ways to mitigate this by improving conditions for the workers and by training a greater number of local residents.
Fahad Tariq
analystAll right, understood; that differs from ending the underground development contract. Those are separate things, correct?
Dominique Girard
executiveYes, those are separate. Suppose the whole project stands at 80%, 90% finished, speaking of the rock line and every task needed so the shaft can be operated. The sole critical path — shaft sinking — is where we face difficulties, and certain delays exist. Ultimately, production won't be affected, since we can extract via the ramp. It simply costs more every month when we use the ramp rather than the shaft, yet the production rate at Kittilä will remain unaffected.
Fahad Tariq
analystAll right, that's all from me. Appreciate it.
Ralph Profiti
analystHello, everyone, and good morning. Sean, my question concerns exploration at Canadian Malartic, more precisely regarding open pit sources of ore as it relates to topping up the mill's capacity, correct? Particularly once we're past 2026. Has the moment arrived for this to be treated as a greater strategic priority?
Sean Boyd
executiveWhat I'd say is that ahead of that, the emphasis — and keep in mind this is the study's initial version — is simply on making that study as good as it can be, as opposed to examining extra ore sources from elsewhere. It's genuinely a matter of optimization, provided we're able to lessen the production decline across those years when the initial changeover happens, moving from the open pit into underground operations. What we won't be doing is hurrying the build-out; the life here extends beyond 17 years. There's no need to hurry it. Should production decline, then production declines; that isn't catastrophic; our approach will be to manage it and construct the project as effectively as possible. Guy, when it comes to exploration, or Dominique, regarding production sourcing within the pit, could either of you offer any additional detail on that?
Guy Gosselin
executiveYes, this is Guy speaking. In addition, we hold a sizable property in that area, and across the 20 kilometers of land under our control, we keep examining and reevaluating what other near-surface ore bodies might offer—whether to the west of the Canadian Malartic pit, involving the Western Porphyry, Fourax, and the former East End operation. Simultaneously, on the eastern side of the Odyssey project, we still hold another 10 kilometers extending eastward, which we are continuing to evaluate. That represents one of our initiatives: to keep testing for both shallow mineralization and extensions of East Gouldie, and to determine whether we can eventually fold them into the mine plan.
Ralph Profiti
analystYeah. All right, I appreciate that. Yeah, that's useful detail. Sean, things are beginning to look brighter at Hammond Reef, correct? We've got some solid preliminary figures. Based on this study, it appears it may not satisfy the technical investment criteria at present, as far as IRR goes. To start with, do you believe it could reach that point? Especially given the $1 billion CapEx figure, would you be willing to enter into a partnership on this?
Sean Boyd
executiveOr divesting it — our minds are open on that possibility. What appeals to us is that it came as a throw-in through the Osisko deal in 2014, and we acquired the remaining half for $12.5 million. The value we've added far exceeds what we originally paid. The sole issue at this point is, how do we unlock that value? Regarding Hammond Reef, we're keeping an open mind.
Ralph Profiti
analystUnderstood. That was well put. Many thanks.
Josh Wolfson
analystThank you. A few things to start with regarding the capital. I realize the figure that's been described is really only indicative of that $750-$800. In the release, we have certain details on Amaruq Underground and Malartic. The indicative guidance, I suppose, suggests approximately $400 million on the project side. Apologies, a greyhound is crying beside me. I guess I simply want to address the gap concerning where the remainder of that might originate. As the release stated, Hope Bay wasn't included in there either.
Sean Boyd
executiveWell, we've simply placed a hold on things since we anticipate that at some point we'll advance Upper Beaver. That is merely a sort of bookmark to let us move those projects forward that are in the pipeline in a very steady and staged manner.
Josh Wolfson
analystAll right, perhaps I'll ask a direct follow-up. The next thing I want to ask about is LaRonde. The outlook for this year appears a bit softer compared with what that operation has been delivering over the past couple of quarters. Is that simply a conservative approach that's been baked in, or does it reflect a shift in sequencing?
Sean Boyd
executiveIt isn't truly a shift. I'd say it's mostly just a conservative stance overall. During Q4, we received an upgrade in the West Mine area, so none of that has been fully included in our numbers. All right. Thanks so much.
Jackie Przybylowski
analystMany thanks for that. Morning to you all. So, I suppose I have a few things to ask. Let me begin with Hope Bay. From what it seems, your intention is to keep it operating throughout this year while also pursuing the more distant growth possibility. Does the strategy remain one of pulling back and shutting the site down for quite a while? Ought we to be looking for that type of news during 2022? Perhaps, if possible, could you provide at least some sense of the timeline you envision for the exploration work and everything related to it, plus when it might reappear in your output figures.
Sean Boyd
executiveYes, at this point it remains premature to-
Jackie Przybylowski
analystYes.
Sean Boyd
executiveWe need to reach a determination about whether to place it under care and maintenance. Like we mentioned, it isn't bleeding cash, which I believe matters; we're able to keep operating it, improving it, drilling it, and finishing the studies. By this same point next year, following completion of all the study work throughout 2021 as we keep going with the drilling effort, we will have a far clearer picture. Regarding how things look past 2022, that remains undecided, dependent on what the drilling program and the study turn up.
Jackie Przybylowski
analystUnderstood. We'll hold off and watch how things develop, and with any luck, by next February the situation will be a little clearer. That sounds excellent.
Sean Boyd
executiveYes.
Jackie Przybylowski
analystMaybe something comparable regarding the underground at Malartic. This study is something we have been anticipating. The specifics you provided struck me as quite useful and appear fairly encouraging. What comes next in terms of information, or which upcoming data point ought we to keep an eye on? It somewhat seems as though we will enter a stretch of drilling and ramp development, that sort of activity. Do you anticipate additional news flow being put out to the market during 2021?
Sean Boyd
executiveWell, as you put it, Jackie, I would anticipate it being further exploration specifics. Like we mentioned, the joint partnership's budget in that area totals $30 million, and $24 million of that is allocated to East Gouldie, which remains wide open. Our expectation is that news flow will center on those exploration findings at East Gouldie, and as we continue drilling the structure along the trend. We will keep working to always optimize and take another look at the study, seeking ways to enhance it and seeking ways that perhaps allow us to reduce the production dip across that transition from the open pit into the underground. No timeline exists for information flow on that front. There will be one concerning exploration, given how large the budget is and the reality that 11 drills are operating at the site.
Jackie Przybylowski
analystUnderstood, and many thanks. There's one last item I'd like to ask about. Obviously, COVID made 2020 a tough stretch for what you do. We're clearly still dealing with it, no question. From what you're saying, some aftereffects remain when it comes to limits on travel and that sort of thing. My guess is this mostly touches those more far-flung sites you have in Nunavut — so how are you handling COVID right now? Have you begun considering whether to bring back workers from the local area? Does the risk from COVID up in that region look higher today, or is the situation improving? Could you perhaps walk us through a general picture of how things are operating?
Sean Boyd
executiveThe vaccine has arrived in Nunavut at this point, I believe, and that matters.
Jackie Przybylowski
analystGreat.
Sean Boyd
executiveThat is a positive sign, and it will play a significant role in determining when we return our employees. We have taken our time on this matter, since the community faces dangers, and as we have stated since the beginning, we needed to ensure Agnico Eagle was not introducing or transporting the virus into Nunavut.
Jackie Przybylowski
analystYeah, sure.
Sean Boyd
executiveI ought to mention that up in Canada, we currently have 5 labs conducting tests. We began testing at an early stage, we've kept growing our capacity for testing, and we're leveraging that to assist us in handling COVID at this point.
Jackie Przybylowski
analystAll right, that works well. I'll stop here. Thanks a lot, Sean.
Sean Boyd
executiveAll right.
Greg Barnes
analystYeah, thanks. Sean, I'd like to get a better understanding of Amaruq and the Meadowbank complex. For the next 2 years, costs are going to stay elevated. As the underground starts up, they'll decline. In my understanding, mining at the underground wraps up in 2026. So what's the outlook for Amaruq in the near term, the medium term, and over a longer horizon, in terms of both output and costs?
Sean Boyd
executiveYeah. From a production perspective, I'd say it's still a fairly short-life mine relative to the rest of our operations, which explains why we're concentrating on exploration within and surrounding Meadowbank and Amaruq, seeking, ideally, more open pit material, since that would let us extend the underground through our capacity to blend. Dominique, perhaps on the cost side you could offer some insight into strip ratios and how they affect costs across what's left of the mine life.
Dominique Girard
executiveYes. Costs are going to move around somewhat, and a big part of that comes from the stripping ratio plus the grade across the sequence. For 2021, the strip ratio should land closer to roughly 7, which is an improvement over 2020, when it sat nearer 11; that should work in our favor. The way it works is that a lower strip ratio means you're adding to the stockpile, which is beneficial. A higher stripping ratio, on the other hand, forces you to draw down that stockpile. That feeds into the cost. On the whole, Amaruq underground is contributing something favorable. The material there carries a higher grade, and, so to speak, the fixed costs have all been covered already; that should bring site costs down. We've also kicked off a fresh optimization effort, which, shall we say, we've named the strategic optimization at the site. They've strengthened the team there to explore various approaches for making things better. Mostly around contractors, rentals, and logistics inventory. Nunavut, both divisions, went through a growth period over the past year. They're working on their units. That's step one. Once things settle down more, we're truly shifting toward an optimization site. My sense is there's opportunity to do better there; we'll find out; we simply need to give the team some space to optimize how they operate.
Greg Barnes
analystThere's a significant increase in output during 2024, 2025, and then 2026 after that. At this point, is Amaruq done after 2026?
Dominique Girard
executiveYes, right now, we're looking at 2026 as the endpoint. Like Sean said, we still have solid resources below ground, beneath the permafrost, since we're continuing to mine within the permafrost for what you'd call Amaruq phase 1, Amaruq underground phase 1. Exploration is still happening, and perhaps Guy could add some color on that, but the exploration work continues. The ideal scenario would be discovering another pit. We've got all the infrastructure in place to handle that and to keep mining with the higher grade that comes from underground. So far, that's what we've got — the resources reserved at Amaruq.
Greg Barnes
analystAll right. And then just a secondary point about Akasaba, Sean — from what you're saying, it really does seem as though that one is lined up for growth. In practice, it appears that it will become the operation that follows the Malartic Underground. What's the timing for studies, or for any sort of decision on it?
Sean Boyd
executiveWell, the study will come to us later this year. A decision would probably land around this same point next year, subject to what the study shows.
Greg Barnes
analystAll right, that's great. Thanks very much.
Carey MacRury
analystHello, and good morning to all of you. Sean, based on what you said, the PEA resource represents roughly 50% of the overall resource outlined at that site. Is that primarily driven by how closely the drilling is spaced, or by the economics tied to some other piece of detailed work, possibly?
Sean Boyd
executiveAre you talking about the underground portion at Canadian Malartic?
Carey MacRury
analystYes.
Sean Boyd
executiveYeah. So most of that comes from East Gouldie, while the rest is made up of East Malartic along with Odyssey North and South, which carry a lower grade. We're quite confident that when we optimize the plan, we'll manage to add some extra ounces to it. Beyond that, we'd also anticipate that East Gouldie keeps expanding. Like we mentioned, this represents what comes out of the first study, so to speak, and it still needs to be optimized as we examine bringing additional resources into the mine plan.
Carey MacRury
analystPerhaps once more, regarding the expansion of the open pit. I understand your reserves stand at 1,250, and looking ahead three years, should we find ourselves in an environment where the price is $2,000, might there be a larger pit shell at that open pit, or does it tend not to be especially responsive to the gold price?
Sean Boyd
executiveYou mean at Malartic?
Carey MacRury
analystYes.
Sean Boyd
executiveYeah. My sense is that there isn't a great deal of space in which the open pit can be grown. What lies ahead at that site is the underground operation. Of course, a stronger gold price is a positive sign for a portion of the lower grade material located in the old East Malartic area. We will definitely be examining that as drilling continues there and as we keep moving through the construction phase. The underground infrastructure, in my view, is going to matter a lot. What truly transformed LaRonde from a small mine into a large mine was exactly this: the underground ramp and shaft provided the ability to drill the deposit. In this case, I believe we will likely see improved access for drilling. That opens up the possibility of adding further resources and achieving more effective conversion of the resource into reserve. A portion of that resource has only been drilled at 150-meter spacings. As your question pointed out, one reason it isn't in the plan yet is that additional drilling is still required and the spacing needs to be tightened up.
Carey MacRury
analystPossibly just a single additional question from my side. How do processing costs appear when operating at 19,000 tons per day compared with the current level of 55,000 or 57,000 tons, and what about G&A per ton? Could you shed some light on those unit costs?
Sean Boyd
executiveDominique, is that breakdown available? Right now I don't have it with me — the processing cost per ton at 19,000 tons a day when we're running at full production.
Dominique Girard
executiveNo, the cash costs were provided, but I'm not able to give you the specifics. We can circle back to that.
Sean Boyd
executiveWe'll get that. Yeah, we'll get that for you.
Carey MacRury
analystAll right, that's helpful, thanks.
John Tumazos
analystI really appreciate the chance to ask something. Does the Gekko mill in its original state meet what Agnico expects? From what I understand, they didn't have the same financial backing that your group does. When it comes to the problems at that plant, how much relates to the 80-km trend and determining where the center of gravity sits?
Sean Boyd
executiveRight. No, that mill simply doesn't meet the bar we hold — nowhere near it. That was clear to us from the start. A new plant is genuinely required, and at this point the main issue is where to put it, given how large the geological belt is and how far apart the deposits sit. That's the thing we're truly working to pin down across the coming year or so while we keep examining it and evaluating it.
John Tumazos
analystIf I could squeeze in one more, apologies for this being a question about the whole company. That southern operation down in Mexico — while the other divisions up north keep expanding — is now approaching 10% of the prospective mix. Does it still make sense to hold onto, given what the heap leach brings, the low capital cost, the simpler mining, and the exposure to the Sonora, Sierra Madre southern belts, plus Latin America and heap leaching in the southwestern U.S.? Or has that plane flight gotten too long, such that the company would carry less admin and run tighter if it were only a northern business?
Sean Boyd
executiveOkay, that's a fair question, and it's one we frequently ask ourselves. The greatest strength we have in that location is our workforce and what they're capable of accomplishing commercially in that nation; given that expertise and, as you mentioned, how close it sits to those geological belts, we believe it's worth holding onto. We would prefer to give them another thing to construct. Santa Gertrudis, we continue to think, is a project that can be built. As for timing, once more, we have no idea. At present, we are simply extracting from satellite deposits and advancing satellite deposits to produce cash, and we have reasonable exploration budgets in place. Mexico remains appealing to us as a business environment. It continues to be a country that supports mining. Regardless of whatever you might observe or come across in news coverage, nothing has happened that alters our stance on wanting to put money into Mexico; competition there is intense, there's no arguing that, yet we believe we hold an edge purely because of the expertise located there; it remains significant to us, though it obviously lacks a pipeline, which the northern operation possesses. From a management standpoint, overseeing it isn't hard since it essentially runs itself. The leadership group in that region has performed remarkably well, and it isn't something that consumes much time from senior management.
John Tumazos
analystThank you. Congratulations. Paul Penna is up in heaven doing a backflip, Sean.
Sean Boyd
executiveOkay.
John Tumazos
analystGreat job.
Sean Boyd
executiveThanks. Thanks, John.
Anita Soni
analystHi, everybody. Morning to you. Only a handful of things I want to ask. First off, from what I gather, if the plan is to run a model with $750-$800 of CapEx across the coming three years, then Upper Beaver ought to be part of that modeling too — meaning the capital tied to it gets included, or at least a portion of it, clearly.
Sean Boyd
executiveCorrect, though we haven't nailed that down yet. What we're essentially telling you — and this doubles as something our teams are chewing over internally — is this: here's the ceiling on what we're willing to commit.
Anita Soni
analystAll right.
Sean Boyd
executiveYou run the numbers on those projects, and then we'll make the call on whether it clears our investment hurdles and fits the risk profile we're willing to take on. What we're really saying is that we've kept some capacity available in case we end up with a positive production decision on a project such as Upper Beaver.
Anita Soni
analystAll right, and I have one more item on the financial side — I just want to verify something: that figure also takes in your capitalized stripping amount, correct? My apologies — capitalized exploration. I always say the wrong one.
Sean Boyd
executiveThat's right.
Anita Soni
analystCapitalized exploration.
Sean Boyd
executiveYes.
Anita Soni
analystOkay.
Sean Boyd
executiveYes.
Anita Soni
analystOkay, so my next question concerns the grade at LaRonde. While working through my reserve study and depletion, I saw that you once more brought in grades that were even better, and on the whole, the mineral inventory increased at these richer grades. Could you explain precisely where at LaRonde that exploration win came from?
Sean Boyd
executiveSure. Guy?
Guy Gosselin
executiveYep.
Sean Boyd
executiveCan you help us with that?
Guy Gosselin
executiveRight. So, as we talked about across the past two quarters, there's the high-grading impact we've been observing at LaRonde. We looked into our reconciliation and essentially determined we had been somewhat overly cautious. The capping limit we applied to the high-grade assays coming out of the deposit was set too low. So we eased the capping somewhat, and even so — I believe we've been working with a few assumptions — and despite that approach of capping at higher assays, reconciliation still isn't achievable. The gold we're recovering exceeds what our predictive model shows. We've factored in a portion of that, and together with the success at LZ5, we've been pushing the resources deeper than the earlier boundary of roughly 400 meters. That boundary now reaches nearly 700 meters beneath surface at LZ5 thanks to those results. Those 2 adjustments at LaRonde mean we've more than replaced the amount mined this year, and as you've noticed, the grade for the LaRonde portion has gone up.
Anita Soni
analystAll right. That brings me to a small point regarding the byproducts. Have the same sorts of parameters been applied when it comes to the byproducts? What I've observed is that you folks consistently seem to perform slightly above the guidance you provide at the start of the year for byproducts, so I'm curious whether that same sort of capping is affecting them.
Guy Gosselin
executiveNo. There's been no adjustment to how byproducts are estimated, and none for any of them either. Gold was the sole item that changed.
Anita Soni
analystOkay, understood. Now regarding the Canadian Malartic royalty — I realize your partner presents its total cost, or its unit cost, somewhat differently. That 5.5% royalty ought to apply only to the Canadian Malartic underground, or rather the Odyssey project underground material, correct? If we looked solely at the Barnat and Canadian Malartic pit, we'd use the unit cost guidance you provided for that material, and no royalty would need to be factored in — is that right?
Sean Boyd
executiveYeah, I'm not certain I'm tracking that. That royalty sits within the cash cost for all of today's output, and it will also apply to the underground output.
Anita Soni
analystRight. So what I'm trying to get at is this — from what I understood, given how your unit costs get reported, the royalty is already baked into that unit cost figure?
Sean Boyd
executiveThat's correct.
Anita Soni
analystregarding the open pit. On the underground side, you separated the royalty, since Yamana doesn't really handle it the way you folks do.
Sean Boyd
executiveBrian. I'm not sure whether Brian can assist us with that.
Anita Soni
analystThat's fine. If he goes ahead with that, we can discuss it separately.
Sean Boyd
executiveRight.
Anita Soni
analystAlright, those were all the things I wanted to ask. I really appreciate it.
Sean Boyd
executiveOkay, thank you.
Matthew Murphy
analystHey there. I've got a question about costs, and specifically your AISC, which is going to land in the high 900s. I suppose a year ago around this time, it sounded like they would be dropping in the near term. At this point it sounds like they'll stay roughly flat. I think there are two parts to this question. First, what's changed that's holding it up at that level? Second, looking past 2024, with everything else staying the same, is there a range you're aiming for on AISC?
Sean Boyd
executiveYes, it's mostly Amaruq. There are 2 years at Amaruq with elevated costs, 2022 and 2023, and after that it decreases. That's essentially what pushed the all-in figure higher, since cash costs rise at that point. It also pushes all-in sustaining costs upward. Following that, they decline.
Matthew Murphy
analystDo you have a level that you can talk about for 2025?
Sean Boyd
executiveNo.
Matthew Murphy
analyst2026? No?
Sean Boyd
executiveNo, we're not guiding that far out.
Matthew Murphy
analystAll right. So perhaps, on a similar note, has what happened at Amaruq shifted your perspective regarding satellite possibilities up in Nunavut?
Sean Boyd
executiveI believe that comes down to how long that asset can last. It lacks the same lifespan as Meliadine. Thanks to our exploration wins at Amaruq, we've got access to higher grade underground ore. What really performs well there is volumes — volumes measured as tonnage that perform well. Adding trucking does bring extra expenses. Our hauling expenses are definitely somewhat elevated, reflecting equipment availability along with reliability. Unit cost has truly been shaped by grade. That grade has come in somewhat under our expectations.
Matthew Murphy
analystAll right, thanks, Sean.
Tanya Jakusconek
analystMorning, everyone. I'd like to return to Amaruq for a moment. Dominique, I recall we discussed that the mine will operate through 2026, and that additional underground potential exists at that site. From what I understand, it's simply not possible to operate the underground portion unless the open pit is also running. So, Guy, first question: is my understanding accurate? And second, something like 2,000 tons per day coming from underground won't be enough to sustain that complex.
Sean Boyd
executiveYes, that's right.
Tanya Jakusconek
analystYeah. Guy, could you perhaps discuss what the exploration is targeting when it comes to open pit material at this property?
Guy Gosselin
executiveYep; that's an effort we've been carrying on annually, looking into, particularly near the infrastructure, whether it's the road linking Baker Lake with Meadowbank, or the one running from Meadowbank over to Amaruq. Essentially, we keep up the work of identifying old targets and putting them to the test. Each year, we're coming up with solid targets. Sadly, a discovery comparable to Amaruq isn't something we make annually, yet that doesn't mean effort is missing, and our focus stays on creating fresh targets, putting them through testing, and we'll share an update the moment we find something.
Tanya Jakusconek
analystSorry, what's the budget for this year?
Guy Gosselin
executiveBroadly, for regional exploration we're putting between 20,000 and 30,000 meters toward both Meliadine and Amaruq. How it gets split up will hinge on how things play out. Figure roughly 20,000 meters on the regional side — the news release lays this out — with 20,000 meters being used to develop fresh targets in the vicinity of Meadowbank, Amaruq.
Tanya Jakusconek
analystAll right. Perhaps this one's for Sean or Dominique — stepping back to look at the wider picture. Suppose we ultimately come up empty here? Is there a chance that part of your infrastructure, a portion of your equipment, or your personnel could be deployed over at Hope Bay?
Sean Boyd
executiveThat's possible, yes. Possible.
Tanya Jakusconek
analystAll right, so perhaps the mill is relocatable, along with the trucks and such?
Sean Boyd
executiveThat would require examining the particulars involved. Of course, if you consider Hope Bay, with reserves totaling 3.5 million ounces, resources exceeding 3.5 million ounces, and still quite open, it will probably reach somewhere between 7 and 10 million ounces. Our acquisition was driven by where it sits, the geological potential, and our capabilities for working in that region. Should we be able to take advantage of the infrastructure already in place, since Amaruq has no remaining mine life, we will definitely pursue that option.
Tanya Jakusconek
analystAlright, understood. Fine, here's hoping additional mineralization turns up at Amaruq. Much appreciated, everyone.
Sean Boyd
executiveThanks.
Sean Boyd
executiveAppreciate it, operator, and thanks to all of you for your questions. Should you need any additional follow-up details, please reach out. We'd be glad to assist. Thanks.
Operator
operatorThis concludes today's conference call. You may now disconnect.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Agnico Eagle Mines Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Agnico Eagle Mines Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Agnico Eagle Mines Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.