Algoma Steel Group Inc. (ASTL) Earnings Call Transcript & Summary
February 11, 2022
Earnings Call Speaker Segments
Michael Moraca
executiveHello, everyone, and thanks for joining Algoma Steel Group Inc.'s conference call covering our third quarter fiscal 2022 earnings. Michael McQuade, our Chief Executive Officer, and Rajat Marwah, our Chief Financial Officer, will be guiding today's discussion. Just a note that we are recording this call, and a replay will be accessible later today in the Investor section of Algoma Steel's corporate website at www.algoma.com. I want to caution that remarks shared on this call could include forward-looking statements under applicable securities laws, and those involve assumptions along with inherent risks and uncertainties. Actual outcomes could differ materially from what is stated today. Furthermore, our financial statements are put together in accordance with IFRS, which is not the same as U.S. GAAP, and during our discussion today we will reference certain non-IFRS financial measures. Yesterday evening, we posted an earnings presentation that goes along with today's prepared remarks. Slides for today's call are available in the investor section of our corporate website. With that said, I'd ask all of you on today's call to review the legal disclaimer on slide two of the accompanying earnings presentation, and also to look at the risks and assumptions outlined in Algoma Steel's third quarter fiscal 2022 management's discussion and analysis. Please be aware that our financial statements use the U.S. dollar as our functional currency and the Canadian dollar as our presentation currency. Our fiscal year goes from April 1st to March 31st, and our financial statements have been prepared for the three and nine months ended December 31st, 2021. Please note all amounts referred to on today's call are in Canadian dollars unless otherwise noted. After our prepared remarks, we will hold a question-and-answer session. I will now hand the call over to our Chief Executive Officer, Mike McQuade. Mike?
Michael McQuade
executiveThanks, Mike. Hi, everybody, and thanks for joining us on Algoma's call about our third fiscal quarter results, which ended December 31st, 2021. This is the second quarterly earnings call we've held since returning to the public markets. As I usually do, I'll begin with what matters most to us: keeping our people safe. At Algoma Steel, we follow the principle of safety without compromise, and that consistent focus has produced significant improvements over the past 10 years in our lost-time injury frequency rate. I'm proud to say that calendar year 2021 was among the safest years in Algoma's history. Safety is our top priority at Algoma, and I want to acknowledge our entire team for what they've accomplished together and for remaining vigilant as we pursue our goal of zero workplace injuries. Before I go through the specifics of our strong quarterly results, let me spend a few minutes discussing the remarkable transformation currently underway, what it means for Algoma's position in the North American steel industry today, and how it will shape where we head next. Our focus is on creating long-term shareholder value by pairing disciplined financial stewardship with game-changing capital investment and operating our facilities safely and efficiently. Steel markets are cyclical, and prices can fluctuate dramatically, as the last several quarters have clearly demonstrated. Disciplined financial stewardship means we focus on the cash we already have rather than cash we hope to receive at some future point. A tremendous amount of work went into reaching the enviable balance sheet position we now hold. With the cash available at quarter end plus the CAD420 million in financing commitments obtained from the Canadian government, work on our transformative EAF project has started. Our primary objective is to preserve our ability to start up the EAF facility on time and on budget — a facility designed to modernize and expand our steel-making capacity while reducing our carbon intensity and enhancing long-term stakeholder value. Let me quickly remind you why the EAF project excites us so much. It features dual furnaces built for a combined annual raw steel production throughput of 3.7 million tonnes, which matches our downstream finishing capacity, while cutting our carbon emissions by approximately 70% once fully operational. A CO2 reduction of that magnitude would represent 11% of the federal and 100% of the provincial 2030 targets for industrial emitters as set under the Paris Accord. We expect the two EAFs to be online in 2024 following a 30-month construction phase; after that will come a transition away from blast furnace steel production as more power becomes available from the grid, supported by the provincial government. Essentially, this project will transform who we are and how we operate, establishing the company as a next-generation steel maker focused on sustainability and prepared to thrive through every phase of the steel market cycle. Our expectation is that construction and startup of that plant will take roughly the next 30 months, and we intend to complete this without any disruption to production at the facilities we already operate, because we plan to continue running safely and capitalizing on the robust steel prices currently in front of us. A $420 million investment underpins that work. Later in the deck, we'll spend some time examining our thinking on capital allocation and how that philosophy could evolve over time. But before reaching that section, I'll pass the floor to Rajat, who will take you through the record financial results for the quarter.
Rajat Marwah
executiveThanks, Mike. Hi, everyone — I appreciate you joining this call. Once again, what we delivered in the fiscal third quarter made clear just how powerful Algoma's cash-generating capacity really is. Just to remind you: all figures we discuss are in Canadian dollars unless we note otherwise. This quarter really stood out, with net income of CAD123 million and adjusted EBITDA of CAD457 million — a 43% adjusted EBITDA margin — while cash from operating activities reached CAD318 million, and that was achieved even as we were accumulating our normal seasonal inventories of raw materials. We ended the quarter with CAD588 million of cash on hand, and our revolving credit facility remained completely undrawn. Beyond that, we restructured our balance sheet this quarter by fully retiring all $358 million of senior secured long-term debt that had been outstanding. As a result, government loans associated with our capital projects now represent the only long-term debt remaining on our balance sheet. As for what powered our results, shipments totaled 553,000 net tons in the quarter — down 6% from the prior quarter, but up 1% versus the same period a year ago. As we noted previously, shipments fell short of what we expected owing to several factors outside our operations, including additional customers idling for the holidays, constraints in supply chains and logistics, and COVID-related challenges. Consequently, we carried more steel inventory through the quarter, which we expect to ship during the first half of calendar 2022 at prices we had already locked in. Our net sales realization averaged CAD1,827 per ton — an increase of 15% quarter over quarter and 161% versus the prior year period. That improvement stems from the favorable impact of our contract order book, as higher lagged prices flow through into our revenue. This produced steel revenue of $1.01 billion for the quarter, up 8% from the previous quarter and 163% above the year-ago quarter. On the cost side, Algoma's cost of goods sold averaged $946 per ton in the quarter — up roughly 10% sequentially and 46% higher than the prior year quarter. The main drivers behind that increase are elevated commodity prices for certain raw materials, a larger workforce for profit sharing reflecting our historical performance, and higher SG&A expenses related to our public listing. All things considered, this third fiscal quarter delivered our second consecutive record for adjusted EBITDA — a milestone in Algoma's history. It reflected the dedication and hard work of the entire Algoma team and what we accomplished across a year: moving from adjusted EBITDA near breakeven just 12 months earlier to generating in excess of $1.34 billion in calendar 2021. So as a result of that, we can now share some good news: our Board of Directors has signed off on the earnout adjusted EBITDA figure for the calendar year that closed on December 31st, 2021, and that figure landed above the $900 million threshold required to trigger the full earnout, which means 37.5 million common shares are going to be issued to the holders of eligible earnout rights along with management. That works out to roughly $1,827 per share when you look at the $1.01 billion total value involved against the $1.34 billion figure we'd cited, with about $946 million of that tied to the non-management portion. Our expectation is that the non-management shares get issued in about five business days. With that, I'll turn it back to Mike, who can give you more color on what the market looks like at the moment and take everyone through our thinking on deploying capital in that balanced, disciplined manner. Mike?
Michael McQuade
executiveThank you, Rajat. If we examine where the North American steel market stands right now, it's evident that pricing has flattened out compared to the peaks reached only a few months back. Even so, prices continue to sit above any level seen before 2021 on a historical basis, and they're roughly twice what mid-cycle pricing looks like; our expectation is that pricing will settle into a near-term equilibrium, and we feel good about the level at which that will ultimately land. The fundamentals visible in the market and in our order book back this up; our customer base is diverse, which opens up selling opportunities throughout Canada and the U.S., and in a typical calendar year we serve as many as 150 customers. We deliberately aim for a larger share of contract sales, and at present about 65% of our steel is sold on contract; those volume commitments bring stability to our order book and our operations, and the lagging price mechanics helped us smooth out some of the volatility that comes when prices move quickly in either direction. Our offerings span a broad range, including plate products, which right now carry a price premium exceeding $685 per ton relative to hot-rolled coil. Our long-held view has been that spending on our plate mill ought to serve us well, since we are the sole Canadian producer and heat treater of discrete plate products. The modernization project is still on schedule, and we just finished assembling the new hot leveler and put our automated 3D surface inspection unit into commission, which is built to further boost our capabilities. We anticipate wrapping up this project over the remainder of calendar 2022. There are multiple reasons for optimism that pricing over the near and intermediate term will land at appealing levels. Among these possible positive drivers are solid underlying demand coming from automotive and other steel-intensive sectors, along with supply considerations tied to imports. Operationally, we're positioned well to capitalize on these favorable market conditions, even while we carry out development and construction of the EAF project, which delivers a genuine one-two punch of long-term value creation for our shareholders. Now, I'd like to go into a bit more detail on our capital allocation policy. Our main priority is generating long-term shareholder value through disciplined financial management and operational excellence, so that we can be sure of executing the EAF project, which brings in the next chapter of our company's history. In the interim, the actions we've taken to shore up the balance sheet and to ready our operations to take advantage of strong market pricing have given us room to start a regular quarterly dividend of $0.05 per share. Last, we've launched a normal course issuer bid program, which provides flexibility to act opportunistically and permits buying our shares on the open market from time-to-time. It's thrilling to have arrived at a moment in our history when we can generate attractive results from existing operations, develop and build transformative new assets, kick off dividends, and consider buying back our shares from time-to-time — quite a shift from only a few short quarters ago. Together with the Board, we'll keep reassessing how we deploy capital, since over the longer term we anticipate it will throw off substantial free cash. That said, let me repeat: our priority is staying within our means and not spending funds we don't have yet. So, to wrap up, during our fiscal third quarter we hit several significant milestones across our 120-year history — going back to the public markets, paying off our senior secured debt, deciding to move ahead with our transformational EAF development project, delivering historically strong financial results, and continuing our legacy of safety for our employees. We're now entering a stage focused on developing and building new projects with the dual EAF facilities — a generational investment meant to forever change how steel is made in Sault Ste. Marie — and Algoma is well-capitalized and ready to execute. Both operationally and financially, our team is concentrated on this crucial investment, which will make our business greener, more competitive, and more resilient. We believe this transformation will deliver a compelling value proposition for every one of our stakeholders. Many thanks for your ongoing interest in Algoma Steel. We're eager to see what lies ahead. With that, we'd be glad to answer your questions. Operator, kindly provide the instructions for the Q&A session.
David Gagliano
analystHello, and good morning. I appreciate you taking my questions. I'll begin with what's likely the most predictable one. We've observed that this earnings release presentation, the MD&A, and your prepared remarks this quarter contain no commentary on the near-term outlook; so, I was hoping you might share a few thoughts regarding the current quarter, since we're roughly midway through it, considering the pricing lags, considering the volume difficulties and the buyer strike that distributors are telling us about, could you give us an idea of what you're thinking when it comes to volumes, and lagged pricing if you have it? Thank you.
Michael McQuade
executiveGood morning, David; so, I'd like to begin by saying we are returning to industry practices with guidance that will arrive later in the quarter. Our aim is to make every effort to reduce the uncertainty that this sector's volatility introduces into guidance estimates. As you note, pricing under our lagging contracts is fairly well understood and modeled; the volume is truly what stays variable. And with over half the quarter still remaining and the near-term supply chain problems that are occurring, we believed it was essential that our guidance be given in a way that it can build confidence in what we say.
David Gagliano
analystAll right, so normally, from a volume standpoint, this tends to be a pretty significant bounce-back. Given the near-term pressures we're facing, does it still make sense to expect volumes to recover, even if that rebound is softer than what we'd usually see quarter over quarter?
Michael McQuade
executiveI'd say that's a reasonable way to look at it. When we gave guidance near the start of the year, we noted that some production hadn't reached the market during our fiscal Q3, and that output is going to be available in the quarters that follow. Our fourth fiscal quarter falls in the winter, and that's generally a stretch when we avoid major outages. So once again, our production levels are fairly elevated, meaning we have a couple of quite favorable factors on the supply side. The real issue is demand, which is shifting on a daily basis because of things such as the blockades at the bridges linking Windsor and Detroit.
David Gagliano
analystAll right, I get it. Let me move away from this topic quickly. There's one more aspect to it, though — the quantity. Could you help us understand how much volume was, well, not just sort of, actually pushed back into the quarter we're in now compared with the one before, and from a timing standpoint, at what point was that volume priced?
Rajat Marwah
executiveYes, David, Rajat here. The volume we accumulated, approximately 40,000 tons, came in the quarter prior, and it will move through during the first six months. Pricing for it was set in the earlier quarter, the December quarter. That's the way pricing carries over for those 40,000 tons that are going to be shipped.
David Gagliano
analystAll right, and — all right, great, that's useful; and now let's shift topics to the buyback. Clearly, you took the NCIB approach, which I believe limits how much could potentially be repurchased to roughly 5%. Are you considering further repurchases via other methods as the year goes on?
Michael McQuade
executiveYes, you're exactly right, the normal course issuer bid — its size is set by legislation. What it does give us is the ability to deploy cash across the coming year, and that comes after we've generated it and after we've safeguarded finishing the electric arc so we can purchase our own shares. That investment choice, together with any others, will be measured against other options available that would eventually boost shareholder value. I'd point you to slide number eight in our presentation. And although I take pride in what our team has achieved over the last three years, there remain additional opportunities to add more building blocks, so to speak, that will deliver long-term sustainable value for shareholders. Investing to further leverage our strengths, investing in opportunities that would be accretive to the value proposition, investing to bolster any weaknesses we've identified or investing to reduce threats to our business. So, every one of those investment choices, including further chances to do things with the shares, will be assessed through the lens of what generates the greatest long-term value for our shareholders.
David Gagliano
analystAll right. And as we have observed other publicly traded firms dealing with this "good problem to have" work their way through such a situation, a number of them have given ranges — kind of a range for distributions following capital requirements, a range of free cash flow intended to be handed back to shareholders across time. If Algoma were to give that sort of disclosure, what would a sensible range look like for that type of approach, from our perspective — what should we expect for Algoma?
Michael McQuade
executiveDavid, that is a wonderful question, and my view is simply that it is too early right now. Once more, our principles involve using the cash we possess. I understand you want some guidance regarding what that distribution of future cash might be; and as I said, it truly is premature, since we will assess the chances to look at expanding on our strengths and pursuing certain opportunities, as I mentioned; and to respond to the earlier question, so it is too early to offer any sort of split regarding cash allocation for any of those buckets until we actually see them. Yet the guiding principle is going to be generating long-term value for our shareholders, whichever route delivers the highest return.
David Gagliano
analystAlright, that's useful. I fully grasp the limitations right now, and I won't blame you for being the one who has to field these questions. It comes with the territory. Regarding CapEx, could you provide some indication for the 2022 calendar year, or looking out over the next 12 months, what CapEx looks like? And separately, have any adjustments occurred in what the EAF project will require in total capital spending, or in what the plate modernization project will need?
Rajat Marwah
executiveSure. So CapEx excluding EAF, which does include plate modernization, will fall in the — let's call it CAD100 million to CAD120 million range; and that aligns pretty closely with the figures we've given during our roadshow presentations. When it comes to maintenance CapEx, that will stay in the CAD60 odd million range, and after that, there's the plate modernization CapEx we'll be incurring next year. So that covers the whole picture. As far as EAF CapEx goes, and the plate mill as well, nothing meaningful has shifted compared with what we previously announced.
David Gagliano
analystAlright, that's my final item. I just want to get some clarity on that CAD100 million to CAD120 million — does that figure — was it — does it represent capital expenditure for fiscal year 2022? Is that the correct reading?
Rajat Marwah
executiveNo, that amount applies to the year ahead, and it wraps up the plate mill modernization. So the plate mill modernization is what we're funding in the coming year. Therefore, you could say it belongs to the next fiscal period.
David Gagliano
analystThe next fiscal year — sorry about that. Okay, that makes sense. All right, thanks.
David Ocampo
analystHello, everybody.
Michael McQuade
executiveHello.
David Ocampo
analystI simply wanted to build on what David asked regarding possible shareholder returns, though perhaps from a different angle. Is there a floor amount of cash you'd prefer to maintain on the balance sheet, and from there we could run the modeling and determine how the potential returns might shape up?
Michael McQuade
executiveWell, David, here's how I thought about it: when we got close to, or assessed, December 31st, we examined the cash we held, then we considered what's needed to finish the electric arc, taking into account the government financing we have access to; we also brought in two more considerations — a buffer meant to handle the swings we observe in the steel market. And beyond that, accounting for the fluctuations that happen — or the seasonal swings tied to our working capital — and built from that point. So, as we move through every month and every quarter, we'll keep assessing how much remains to be spent to enable the electric arc implementation, check our position on that seasonal working capital, and ensure we have cash available too, which lets us truly shield ourselves amid the steel sector's volatility.
David Ocampo
analystNo, that's quite logical. Then you mentioned — you briefly discussed how plate prices sit roughly CAD600 above sheet. Given that, ought we to expect your plate offerings to track a comparable trend to your broader operation, where 65% is contracted and 35% is — meaning, should we anticipate that you folks will take part in plate price gains here?
Rajat Marwah
executiveRight, so the contracted order book we hold for plate differs somewhat. It'll be approximately 50 to 50 when looking at contract against spot. Therefore, we ought to see that coming through, and going from monthly to quarterly, at a high level you can apply that same split, and it should make its way into the books in line with that.
David Ocampo
analystRaj, when it comes to the contracted piece of that, is it not the case that it breaks down in a comparable way — a quarterly lag, a monthly lag, and after that a set yearly rate?
Rajat Marwah
executiveThat's right. And as a rule, those plates don't carry a set price. So it's going to be monthly and quarterly. So there's no fixed pricing.
David Ocampo
analystGreat. Then, considering all the talk about worker shortages and getting parts, how confident are you folks still feeling regarding that 30-month build schedule for your EAF mills? Also, could you remind us whether there's any wiggle room there when it comes to cost overruns on that CAD700 million figure? Two parts to that question, and the response is that the 30-month construction phase does include a critical path, with some cushion incorporated at the front end. So we continue to feel confident about delivering that project by really this second calendar quarter of 2024; and a meaningful cost cushion was included as well. For the remaining pieces that haven't been contracted yet, the cushion now accounts for more than roughly 25% of the total cost. So we believe there's enough lead-time cushion along with financial cushion to get that project done on-time and on budget at this point. All right, great; that's all from me.
Michael McQuade
executiveThanks, David.
Anoop Prihar
analystMorning. I have a few things I'd like to ask. To start, with all the ups and downs we've been seeing in HRC, could you share your take on what's behind that swing and where you expect it to go across the coming 2 quarters?
Michael McQuade
executiveHello Anoop, I appreciate the question. To be sure, this kind of swing isn't anything new for the steel industry — in fact, in lots of instances it feeds on itself. We've seen record-breaking peaks in pricing, or hot-rolled coil sat at roughly 3x the cycle's midpoint, give or take. It definitely reached a top and still, as of today, sits higher than the earlier peaks, which were probably around the August of 2008 period. A large portion of the buyer base and the supply chain across North America consists of parties holding inventory, and the index-based pricing present in the market is in fact what pushes both the way prices are set and the way demand behaves. As a result, whenever people expect prices to decline, those inventories lead to orders being cut back, and that alone keeps lower demand going; so the balance between supply and demand is thrown off until some sort of equilibrium gets reached. Where exactly that lands is truly anyone's guess. What I'd argue matters more is that our view remains that the fundamentals are extremely, extremely robust — the demand and supply fundamentals in the North American market — and those will underpin a solid steel industry for some time from here.
Anoop Prihar
analystGiven the current gap between plate and HRC, which I believe is nearing CAD700, are customers switching from outer plate to HRC? And how feasible is that, really?
Michael McQuade
executiveNo, I'd say those are two quite separate markets with quite different uses. So I don't see buyers moving back and forth between them.
Anoop Prihar
analystOkay, understood. And while reading the MD&A, I saw that regarding your discussion of the plate mill modernization, the initial phase appears to have fallen behind somewhat. What I mean is, I believe March was the original timeframe, and at this point we're, in a sense, shifting it to May or June. Could you give us some detail on what's happening with that delay?
Michael McQuade
executiveSome of the components had a supply chain problem; beyond that, the environmental conditions here in Sault Ste. Marie were more favorable, I should say, and that was the case back last fall. My aim was to ensure we could carry it out — confirm that all items would arrive on schedule. And considering the market along with pricing, it was logical for us to shift it by four to six weeks.
Anoop Prihar
analystAll right. And for my final question, considering what you said about input costs going up, would it be fair to think our unit costs in Q4 will be greater than they were in the prior quarter?
Rajat Marwah
executiveSo that — no, they ought to begin moving lower, and like I mentioned previously, we also observe a delay when it comes to iron ore pricing making its way into cost, typically a lag of 6 months. So, since the iron ore price fell to below CAD100 on the index and has since recovered to CAD150, that movement ought to work its way into our cost during the fourth quarter and then carry into the second calendar quarter, which is the first fiscal quarter of the coming year. So our cost should level out and head in a favorable direction. There is certainly inflation affecting other cost components, be it alloys, be it gas, power — how that unfolds remains to be seen — but when it comes to the main raw material cost, that is what we'll observe. One more thing I'd add, which I brought up previously: coal will be greater year-over-year. It's roughly CAD100 per ton more year-over-year, and that will work its way into cost this year starting in April, when new coal supplies begin arriving at Sault Ste. Marie.
Anoop Prihar
analystAll right. So to make sure I have a handle on the pluses and minuses for Q4 compared with the prior quarter, our expenses ought to be declining and heading the proper way. Would that be accurate to say?
Rajat Marwah
executiveCorrect.
Anoop Prihar
analystAll right, excellent, thanks.
Kirk Ludtke
analystHi, everybody, is my voice coming through?
Michael McQuade
executiveYes, Kirk, we hear you. Good morning.
Kirk Ludtke
analystGreat. Well, congratulations on the quarter. Thanks for the call. Just a couple follow-ups. On the guidance, you mentioned that input costs will be coming down sequentially, that's super helpful. Thank you; and you also mentioned that pricing for the March quarter is already well known. I'm — I just want to confirm everything else being equal, realized pricing should be up sequentially, correct?
Rajat Marwah
executiveSo, I think you should look at from the construct of pricing perspective; so, we do have the monthly — the quarterly lagging contracts, which definitely will be up when you look at quarter-over-quarter because they are flowing from last quarter. Monthly contracts are tied to the prior month's settlement, so once prices began dropping in January and continued through February, that decline will feed into how those contracts get priced. Now, looking at spot business — it makes up about 35% to 40% of what we do — lead times have shortened, and for HRC in particular they're mostly at four weeks or less. That's the way the picture comes together. Plate works differently, though. It moves the other way: contract prices will sit below spot, while spot keeps selling at higher levels. That's how the shift plays out. Once you've worked it out, you'll arrive at that figure — roughly $60-odd million. We aren't providing formal guidance per se, though that's the direction it will take.
Kirk Ludtke
analystOkay, there are a number of moving pieces in that. Fine, I'll try to reason backward to get to an answer. I appreciate the information; and on the EAF, it's encouraging to hear that those buffers have already been baked in — is there a checkpoint we should — or a checkpoint coming up that we should mark on our calendars and look for on a particular date so that we remain on track?
Michael McQuade
executiveThat's a tough one to answer. If you look at the Gantt chart, it has hundreds and hundreds of separate line items. Our practice is to put out press releases and other communications whenever the mill's significant milestones are achieved. You've seen the equipment contracts awarded to Danieli. You've seen the transformer contract given to PTI, GE for upgrading our LSP. What I would anticipate next would be deals connected to the buildings, we keep preparing the site, driving piles <<inaudible>>. So, there isn't one huge one. If you're asking about the next one, it would be picking our partner for erecting the buildings.
Kirk Ludtke
analystAll right, what's the timing you're looking at for making that announcement?
Michael McQuade
executiveMy best guess would be a week or two out. The procurement folks on our team are handling the contracts and that side of things. Still, a reasonable expectation is that timeframe.
Kirk Ludtke
analystThat milestone looks like it carries fairly little risk.
Michael McQuade
executiveTrue, though the key thing is that this piece accounts for a sizable share of the expense. And once more, it would leave the remaining contingency, so to speak, in a considerably stronger position for the rest of the build.
Kirk Ludtke
analystUnderstood. All right, that's excellent. Thank you for that. And finally, regarding the earnout shares, I believe you mentioned that 37.5 million shares are going to be issued within the next five days.
Rajat Marwah
executiveCorrect, that will be the non-management portion of the shares, which comes in at slightly under that 35.9 million or so. Those shares are going to be issued within the next five days.
Kirk Ludtke
analystThat's great, really fantastic. And then one final thing — by that point, will the buyback program be up and running?
Rajat Marwah
executiveYes. Getting all the paperwork finished takes — NASDAQ isn't that involved, but where TSX is concerned and so on, it requires about two weeks. So it ought to be finished by the time the earnout shares get issued.
Kirk Ludtke
analystAll right, so it will be ready so that no matter what comes up, you're able to react.
Rajat Marwah
executiveThat's right.
Kirk Ludtke
analystGreat. I appreciate. Thank you guys.
Michael McQuade
executiveThank you.
Rajat Marwah
executiveThanks.
David Gagliano
analystHello, apologies. A brief additional question, if I may. Earlier you provided the CapEx figures for everything apart from the EAF for fiscal year 2023. My recollection is you mentioned CAD100 million to CAD120 million. That sounds correct to me. For fiscal year 2023, what CapEx do you expect for the EAF project?
Rajat Marwah
executiveThat figure — I'm able to provide a range — somewhat wider, since at present we're in the midst of finalizing contracts covering structural work and other segments. So, if we look at, say, net cash outflow terms, and if we assume a certain share of the government funds will come through, the figure ought to land somewhere between, say, CAD160 million and CAD220 million in Canadian dollars. So the range I'm providing is wider; however, many items remain in motion, which makes a precise figure hard to give, though it will fall within those bounds.
David Gagliano
analystFor the government funding piece, what is being assumed within that CAD160 million to CAD220 million?
Rajat Marwah
executiveWell, it's net of that. So what's assumed here is that the government funding has been taken in by me. So the CapEx — total CapEx will fall in the — spending will land somewhere between CAD300 million and CAD400 million. And government funding will come our way, with the remainder being the cash that leaves the company.
David Gagliano
analystAll right, and regarding the public funding — my apologies if somebody already covered this — could you remind me once more whether any limits exist? Once you begin drawing on those government funds, are there caps or other kinds of constraints tied to returning capital to shareholders? If that's the case, what do they look like?
Michael McQuade
executiveYes, there are. It concerns the piece coming from the infrastructure bank, and there are 2 separate stages. Throughout the construction stage — and here the government is trying to make sure we can finish the project — on capital allocations, there is a one-third claw-back against the availability. We would draw in the end, but it turns into secured funds, and at completion that would call for repayments. So think of it this way: while construction is underway, one-third of distributions effectively lowers the availability of the government financing.
David Gagliano
analystAlright, that's useful, thank you. Now regarding this government funding, I suppose it suggests something like $140 million or $180 million has been accessed, I think, going by the approximate range you provided — clearly, we don't have certainty. But that approximate range — inside that combination of $140 million and $180 million — how does it divide up? Could you perhaps give us the split? As I understand it, there are two buckets, and will this be drawn from one of the two, or from both of them, or is that still unknown?
Rajat Marwah
executiveIt draws from both buckets together; that's the situation as it stands. And it depends on how the spending unfolds. Another point concerns capital allocation — should there be adjustments to capital allocation down the road, then the amounts we pull from the government will also shift. To be specific, the CAD220 million that Mike referenced regarding the CIB, the infrastructure bank — that CAD220 million carries claw-back provisions or limits. So that figure will move around as capital allocation plans get worked out across the years.
David Gagliano
analystOkay, that helps, I appreciate it.
Michael McQuade
executiveSo, once again, thank you for being with us on this earnings call for the third quarter of fiscal 2022, and for the continued attention you give to Algoma Steel; we look forward to updating you on our performance and accomplishments when we report our fourth quarter results later this year, a period in which we expect to generate between $300 million and $400 million in adjusted EBITDA. Stay well, and we'll be talking with you again soon. Thanks.
Rajat Marwah
executiveThank you, guys.
Operator
operatorThat brings us to the end of today's call, and you're welcome to hang up your phones now. We appreciate everyone for joining in.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Algoma Steel Group Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Algoma Steel Group Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Algoma Steel Group Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.