Hello, everybody, and thank you for joining us on the Algoma Steel Group, Inc. Second Quarter Fiscal 2024 Earnings Conference Call. Michael Garcia, our Chief Executive Officer, and Rajat Marwah, our Chief Financial Officer, are the speakers heading up today's session. Just a note that we are recording this call, and a replay will be accessible later today through the Investors section on Algoma Steel's corporate site, www.algoma.com. I want to point out that anything said during this call could include forward-looking statements under applicable securities laws, and those come with assumptions along with inherent risks and uncertainties. It's possible actual results will differ materially from what is stated today. Also, our financial statements follow IFRS, which is not the same as U.S. GAAP, and during this discussion we will reference certain non-IFRS financial measures. Yesterday evening, we posted an earnings presentation that goes along with today's prepared remarks. You can find the slides for this call in the Investors section of our corporate website; so with that said, I'd ask all of you on the call to review the legal disclaimers on Slide 2 of the accompanying earnings presentation and also to look at the risks and assumptions laid out in Algoma Steel's Second Quarter Fiscal 2024 Management's Discussion and Analysis. Please be aware that our financial statements use the U.S. dollar as our functional currency and the Canadian dollar as our presentation currency. Our fiscal year goes from April 1 to March 31, and our financial statements have been prepared for the 3 and 6 months ended September 30, 2023. Please note, all amounts referred to on today's call are in Canadian dollars unless otherwise noted. After our prepared remarks, we'll hold a question-and-answer session. I'll now hand things over to our Chief Executive Officer, Michael Garcia. Mike?

Mike Garcia

executive
#2

Thanks, Mike. Good morning, everyone, and I appreciate you being here as we go over what we achieved in the second quarter of our fiscal year. As I always do, I'll start with the thing that matters most of all — keeping every one of our employees safe. Here at Algoma, we hold to the principle that safety admits no compromise, and because we've kept at it, our lost time injury frequency rate has gotten considerably better across the last 10 years. On top of that, we apply that very same care and vigilance to safety as we keep moving forward with the biggest capital undertaking in the company's history — the EAF transformation project. I'd like to give the team credit for putting in 420,000 hours without any lost time injuries so far, and I want to stress how much safety counts, particularly with the winter season approaching; we'll keep at it diligently as we chase, without letting up, our objective of 0 workplace injuries. Moving on, I'll go through the notable events and milestones from our fiscal second quarter and what has happened since it closed, and also bring you up to date on how our transformative EAF project is coming along. After that, I'll hand things over to Rajat, who will take a closer look at the figures and talk about our solid liquidity and balance sheet, and then I'll wrap up with a look at where the market stands. For the fiscal second quarter of 2024, our results matched the guidance we had already shared for both shipments and adjusted EBITDA. What these results show is dependable operating performance set against a tough environment in steel markets, in which the UAW strike at a number of U.S. auto making facilities — recently settled — weighed on demand and pricing. Through the quarter, we kept advancing Phase 2 of the plate mill modernization project, which included commissioning and testing the inline shear. Later this month, we anticipate that the shear will be online, and plate production should ramp up through the end of the year; with that higher output, we'll be positioned to seize market opportunities and to build inventory before the planned outages tied to implementing the final phase of the modernization budget. The project team has gone through the detailed implementation steps and found ways to further derisk this phase. Our original plan called for a single outage lasting 40 days; even so, we've spotted benefits in breaking the outages into 2 shorter ones, each lasting up to 20 days, which we believe will soften the effect on our customer base while also lowering commissioning risk. April of next year is when the first outage will take place, and the second one will be set for later in the calendar year so that it lines up with our planned maintenance outages, which brings additional advantages. We continue to expect the same gain in production volume across the year, with far less disruption for our customers. Now to other strategic initiatives. We made substantial headway on locking in critical raw material inputs during the quarter. We signed a 2-year extension to our existing iron ore purchase contract with U.S. Steel, along with an option for a third year that we may exercise at our sole discretion. With this contract extension in place, we expect that all the iron ore we require for the shift to electric arc furnace steel production is now secured, which provides us with supply certainty and continuous availability. Turning to coking coal, we have finalized what we need for calendar 2024, and pricing for that raw material should decline by a low double-digit percentage during calendar 2024. So with labor certainty from the 5-year union agreement we signed last year, the iron ore contract covering our needs for the coming years, and our coking coal arrangements for calendar 2024, we have firmed up our inputs and gained improved visibility into our cost structure across the next several quarters, which puts us in position to grow margins, particularly as steel prices keep recovering from the recent softness caused by the strike. We feel optimistic, since forward prices for hot-rolled coil have recently been sitting at roughly USD 1,000 per ton, which reflects pent-up demand along with low inventory levels among certain customers. Now I want to bring you up to date on what we accomplished this quarter on our transformational EAF project. Once finished, it will raise our throughput capacity by about a 1/3, moving from 2.8 million tons per year of liquid steelmaking capacity through conventional methods today to 3.7 million tons using dual EAF furnaces. That greater output will align with our enlarged downstream finishing capacity as we boost throughput at our plate mill. Just as importantly, it will enhance our overall product mix while at the same time cutting our carbon emissions by roughly 70% once fully running. Taking into account the composition of our electricity supply once we convert to EAF operations, we anticipate ranking among the greenest steel producers in North America. Over the quarter, cumulative investment in the EAF project hit $456 million, which equals 54% of the expected total project cost at the midpoint of our project budget. Since the quarter closed, we have achieved meaningful progress in locking down the uncontracted portions of expected project cost; and as of today, about 80% of the total project budget is under contract; we anticipate having the rest of the project budget under contract by the end of March 2024. Also, it is worth highlighting that right now, just 5% of the total contracted amount is exposed to time and material adjustments, which means the large majority carries fixed price terms. That shows how much the EAF project has been derisked over the past several months as we move toward beginning commissioning in late calendar 2024. As a reminder, our start-up plan still calls for normal production from our current steelmaking facility while we ramp up steel output from our EAFs in calendar 2025, after which we will switch entirely to EAF production. Earlier I mentioned our successful work to lock in coal and iron ore inputs for our current operations. And when you consider what EAF steelmaking requires, power stands out as one of the most important inputs. Like we said earlier, the electricity we need to operate the electric arc furnaces is already in place at our present shipment pace of 2.2 million to 2.4 million tons, and we don't have to depend on the blast furnace for it — we draw on our on-site generation plus the existing grid. Hot metal from the blast furnace can be used when it makes sense, and that would give us additional upside beyond what we can currently produce. During this quarter, a system impact assessment came through for phase two of our project, so once the local 230 cable line is in place, we'll be able to operate either EAF unit without needing to run our on-site power plant. On top of that, after the quarter closed, the Ontario government made an announcement and issued an order in council aimed at speeding up regional power infrastructure upgrades, which gives us even more confidence about meeting our long-term electricity needs for the EAF project. Taking everything together, we've made considerable progress, and the risk around both the availability and the cost of power for our new EAF has been reduced substantially; it's an exciting period in Sault Ste. Marie, with our existing facilities running as usual and EAF construction picking up speed. Once again, I want to express my thanks to every one of our employees, whose execution keeps producing strong operational and financial results safely while at the same time pushing the EAF project ahead. At this point I'll hand the call to Rajat, who will walk through our financial results for the quarter and provide more detail on how we expect to fund our capital expenditures. Rajat?

Rajat Marwah

executive
#3

Appreciate it, Mike. Morning everyone, and thanks for being on the call. For the second quarter, adjusted EBITDA came in at $81 million, equal to an adjusted EBITDA margin of 11.1%. Operating activities produced $57.2 million in cash; at quarter end we held $213.6 million in unrestricted cash, and the USD 300 million revolving credit facility is still undrawn, which puts total liquidity above $500 million. On earlier calls we've noted, and it's part of our strategic direction, that financial discipline is a priority for us. Our balance sheet is arranged so the sole long-term debt consists of government loans tied to our capital projects, and we've kept leverage very low with plenty of liquidity to ride out market swings and finish our capital initiatives. Now let me get into the main drivers behind our performance this quarter. Shipments for the quarter reached 549,000 net tons, a rise of 26.1% from the same period a year ago. Plate and strip operations keep performing well, and our usual seasonal maintenance is taking place on schedule, which includes the annual reline of our steelmaking vessel. Keep in mind that this routine seasonal maintenance usually cuts production by 20,000 to 30,000 tons. Consequently, we'd anticipate fiscal third quarter production declining on a sequential basis relative to the fiscal second quarter. Net sales realizations came to an average of $1,213 per ton, a decline of 4.3% from the prior year period. That year-over-year drop mostly mirrors softer overall market conditions during the quarter. Plate pricing kept commanding a sizable premium over hot-rolled coil throughout the quarter, supported by resilient demand, especially from infrastructure project spending and durable goods. As a reminder, we're the sole discrete plate mill in Canada, and we anticipate incremental tons from the plate mill in the calendar fourth quarter and afterward thanks to the new share installation. Steel revenue for the quarter was $665.8 million, an increase of 20.7% over last year's same quarter, which mirrors higher shipments that were more than offset by a lower average realization per ton of steel; turning to costs, Algoma's cost per ton of steel products sold averaged $1,021 for the quarter, a drop of 1.6% from the prior year period. The primary reasons for that year-over-year reduction include the favorable effect of greater volumes. Compared with the prior quarter, our cost of steel products sold ran roughly 7% higher, which we attribute to lower volumes plus increased costs for various raw materials and utility inputs, natural gas and purchased coke among them. Cash flow from operations for the quarter was $57.2 million, versus a use of $66.1 million in the prior year period. At the close of the quarter, our inventory stood at $822.7 million, which was an 8.3% increase across the quarter, reflecting the usual seasonal buildup; we anticipate additional inventory growth in the calendar fourth quarter before winter, just as we normally do at this time of year, and then a release of inventories across the first half of calendar 2024, with the heaviest portion falling in the first calendar quarter; at this point I want to give some extra detail regarding how we intend to fund the EAF project. As we've said before, we still expect the project's total cost to fall within $825 million to $875 million. By the close of the quarter, $456 million had been spent, equivalent to 54% of the anticipated total cost, which leaves $394 million still to be spent. Looking at where we expect the money to come from for those outlays, we're in a solid position today. We hold more than $200 million in cash, plus $93 million of remaining capacity under our federal SIF loan, and roughly $150 million in cash expected to be produced by pulling down excess working capital, with about 70% of that arriving in the fourth fiscal quarter and the rest in the fiscal year that follows. Taken together, that is more than the capital still needed to finish the project. With that, I'll hand the call back to Mike Garcia for closing comments. Mike?

Mike Garcia

executive
#4

Thank you, Rajat. If we look at how things stand in the North American steel sector, index pricing for hot-rolled coil dropped roughly 25% during the calendar third quarter, since both worries about and the actual occurrence of a UAW strike pressed down on the market. As a consequence, capacity was reduced at a number of mills across North America, and distributor inventories were depleted. We do anticipate a meaningful hit to EBITDA in the fiscal quarter we are currently in, given that we are feeling lower prices along with reduced shipments stemming from our scheduled maintenance outages. Turning to the longer term, with labor agreements having been finalized during the past few days, pricing has risen quickly, and forward curve pricing has been observed climbing to close to $1,000 per ton, which should deliver considerable upside in the fourth fiscal quarter. Another factor supporting us is that plate pricing keeps showing a substantial premium, since demand for plate products overall remains elevated, and that in turn keeps helping our average price realizations. No matter how volatile our end markets become, we will keep our primary focus firmly on operational excellence and on preserving prudent financial discipline. That will safeguard our capacity to carry out our EAF project, bringing in the next chapter for our company that defines Algoma's future, secures long-term value creation for our stakeholders, and cements our leadership position at the forefront of green steel production in North America. Many thanks for your ongoing interest in Algoma Steel. With that, we would be glad to take your questions. Operator, kindly provide the instructions for the Q&A session.

David Ocampo

analyst
#5

My first question is for Rajat, I think. Given your yearly purchases of raw materials and the new iron ore agreement you've signed, do you believe raw material prices have topped out? And what direction should that take as we move into next year?

Rajat Marwah

executive
#6

Yeah, so on coal, it certainly declines, and I'm not sure how you're tracking the way that index moves around. That has some impact, since at present we're operating 2 contracts. Still, I'd agree with you that costs ought to head lower going forward. Typically, the winter season brings certain difficulties, mostly tied to expensive utilities, natural gas, and power. But other raw materials ought to begin declining as we head into the coming year.

David Ocampo

analyst
#7

All right. And I suppose, Rajat, staying on this topic with you. If I look at where your inventory stands, it's still somewhat high. In fact, there was a rise during the quarter. Could you take us through how those raw materials, or perhaps finished goods, start to come down? And what amount of cash might be freed up over the coming quarters?

Rajat Marwah

executive
#8

Certainly. We typically build in December, which is normal, then we release in March, and we follow the same pattern the next year; however, if you compare March to March, or the end of March to the end of March, roughly $100 million in working capital ought to be released. When I mention working capital, that covers inventories plus certain items on the payables side, since those move together. So that's what you'll observe. Then an additional $50-odd million is what we expect in the year after. So that $150 million should be coming down. It's taking somewhat longer, as I said previously too, because we hold inventories that will require a bit more time to draw down, and that's mainly on the raw material side. Regarding finished goods and WIP, as cost declines, we ought to see improvement there. From a tonnage standpoint, though, some optimization should be occurring.

David Ocampo

analyst
#9

Understood. Moving to my final question, and anyone can field this one. Normally, you finalize those yearly agreements near this point in the calendar — at minimum the portion, roughly 10%, that you generally leave unresolved. Did that get finished prior to the UAW strike being settled, or afterward, once pricing conditions had improved considerably?

Mike Garcia

executive
#10

David, Mike here. My sense is that it's been taking place the whole way through. It's ongoing even at this moment. So the answer really hinges on which customer you mean and what the typical timeline looks like. That said, we certainly kicked it off right as the strike was beginning, and it keeps moving forward while we're on this call.

Katja Jancic

analyst
#11

Let's start with the plate side, perhaps. You said, I believe, that demand conditions are still solid and pricing is high, yet in the U.S. we're observing that a competitor of yours has come out saying they're cutting prices, and demand appears to be weakening. Could you elaborate a little — are you encountering a different situation in Canada? And what portion of your sales goes into the U.S. market?

Mike Garcia

executive
#12

Thanks, Katja. Mike here. When you look at our plate book of business, most of it sits in Canada; the breakdown is about 70 to 30, Canada versus the U.S. And once more, as the spread shows, it's still wide and in fact widened somewhat this week, we continue to witness fairly strong demand for our plate business. Certain portions of the plate market may be facing somewhat greater pressure than others. I'm certain you noticed the wind tower projects being cancelled, but that isn't a segment we participate in. So we remain reasonably confident regarding the plate spread and the position of our book of business. Does that answer your question?

Katja Jancic

analyst
#13

All right, perhaps — yeah. No, that's really useful. And then regarding the short-term expense side, since output will be reduced during this quarter, what's the right way to view cost per ton? Would those be elevated? Or which factors are pushing and pulling there?

Rajat Marwah

executive
#14

Yeah. Katja, it's going to be elevated purely as a result of the volume; so if you examine the pluses and minuses for upcoming quarters, let's say, or at minimum the quarter ahead, is that the wall is certainly going to have an effect. The remaining costs are pretty much the same. Utilities could keep going, meaning natural gas plus power, with a bit of strain from increased pricing; so that's the way the following quarter will unfold before returning to typical output levels, since the outages are finished, and after that you still face utility strain, and then you move into summer, when conditions become far more typical. So that's the way we expect costs to develop across the next few quarters.

Ian Gillies

analyst
#15

Regarding the plate mill modernization and that new shear line going in, if my memory serves me, I believe it was meant to wrap up sometime in the quarter we just finished, and from what I'm hearing, work is still underway. Has something caused a hold-up that cut into volumes? Or am I getting the picture wrong?

Mike Garcia

executive
#16

No. What we'd said earlier, I believe, was that hot commissioning would kick off during this quarter, and that project remains essentially on schedule; the hot commissioning effort involved here is quite extensive. So we continue to be on track as we ramp that shear toward more typical output in November, then afterward in December, and on through the first quarter of next year.

Ian Gillies

analyst
#17

All right, that's useful. And when you consider — after you're through those 2 short outages next year, do you feel confident about where volumes will land after that? Or does that figure remain somewhat uncertain, based on what might occur? And should you have a solid view, would you be ready to put a number on it for us?

Mike Garcia

executive
#18

Well, before the first outage arrives in April, what we're targeting is to bring in a 10% to 15% gain in our plate business, then grow from that point; the plate business is a highly significant market segment for us. We're investing a great deal of time with customers at present regarding — and it truly breaks into 2 parts; one is restoring our standing with certain plate customers we've had historically; we faced some difficult periods last year tied to commissioning of the — and the start-up of Phase 1 of the project; so we had a bit of space to bounce back, if you will; yet we've delivered the kinds of gains in quality and promised performance that we think customers expect from us; and moving forward, as additional capacity comes online in a steady manner throughout next year, we'll expand our business through those quality and promised performance gains, along with the added flow path to manage it.

Ian Gillies

analyst
#19

All right, that's useful. If I can fit in just one additional question. Regarding what your customers are currently experiencing and in relation to the increase in HRC prices, what portion of this run do you attribute to demand that is structurally stronger? And what portion do you believe is connected to restocking of inventories, since I'm aware purchasing has been rather soft? I realize this is a difficult question to respond to, but any thoughts on it would be beneficial, I think.

Mike Garcia

executive
#20

Yes, that's a hard one to field. Certainly, there's a component of it, and likely a considerable component in the initial period, the first several weeks, a couple of months, that relates more to bouncing back from the situations people found themselves in during the strike. Inventories stood at, I believe, 2 months, which is fairly low. Lead times at the mills were extended to 8 weeks in most cases. So I believe the earliest phase of this has been a rebound from the anxiety and the particular disruptions connected to the UAW strike. I believe moving ahead is when it will truly sort of show whether the remainder of it, any additional pricing past where we're arriving at now will, I believe, be tied more to underlying demand and economic activity.

Lucas Pipes

analyst
#21

First question returns to the topic of yearly agreements. Given that raw material prices dropped during 2024, do you think margins on those annual contracts will rise, remain flat, or fall? I'd like to hear how you see it.

Rajat Marwah

executive
#22

Certainly. The majority of agreements we sign are tied to an index, while only a tiny portion uses a set price — that's where you'd notice this dynamic. Still, on the whole, we ought to see margins get better, since expenses should become more efficient. Should pricing stay where it is or drop further, we'd expect improved margins; thus, comparatively speaking, margins will look stronger as costs decline. That said, since index-linked deals make up most of our contracts, the outcome depends heavily on how prices shift across the year.

Lucas Pipes

analyst
#23

Understood. Could you give us a rough reminder of the split between fixed and floating?

Rajat Marwah

executive
#24

Typically, roughly 5% of our overall book is fixed, and contracts generally account for about 50% to 60%. So 5% sits in fixed, while everything remaining is floating, tied to monthly and quarterly contracts.

Lucas Pipes

analyst
#25

That's quite useful. My follow-up concerns how you'll secure coke while shifting over. Could you restate the approach you're taking? What blend should we anticipate? Plus, are there any capital-related cost reductions tied to this transition?

Mike Garcia

executive
#26

Absolutely, Lucas. What we do is keep pushing output as high as possible from the coke batteries we own. We also keep directing capital that's absolutely necessary toward keeping those batteries running safely. Even so, the reality is that despite excellent operation, we still come up short on coke, so buying from outside suppliers will carry on just as it has before. Our aim is always to hold that figure down, yet we foresee it continuing ahead. Lately we've enjoyed a modest gain since coke's market price has fallen quite a bit. Nonetheless, our method hasn't changed. Those batteries must be kept up, despite the fact that they won't serve us long, or serve us at all once we complete the move to EAF output, yet we still devote a certain level of mandatory sustaining capital so they stay secure and run profit — correctly. Is that clear enough?

Lucas Pipes

analyst
#27

That answers it. Now I've got one more thing to ask. People are saying some blast furnace coke production capability could sit unused during 2024 — wait, I mean blast furnace capability itself. So my thinking is that on a merchant basis, there would be a larger supply of coke out there. Does that make it appealing, or — you just addressed this earlier, saying you'd prefer to get as much as possible from your own sources, but could there come a moment when that flips and purchasing additional coke from merchants becomes the smarter move?

Mike Garcia

executive
#28

Right. Ultimately, economics drive this. We need a solid grasp of what it costs us to make coke ourselves, factoring in the yield loss incurred once you purchase coke from outside and ship it to this location. That said, the economics definitely shifted a lot when weighing self-production against buying from others, and that's a factor we'll monitor, stay conscious of, and be ready to respond to.

Lucas Pipes

analyst
#29

Also, how fast might you be able to change that choice you need to sort of make annually? Or is it possible to stay flexible as the year goes on and supply-demand shifts?

Rajat Marwah

executive
#30

Yeah. No, we're able to do that quite quickly. It isn't a matter of days, though likely within months, we can make the switch. There's no need to hold off a whole year, since what happens is we enter contracts according to what we can produce most efficiently in-house. And should we need to change that because of an opportunity in the market to purchase at a price that makes up for our own output, then you have — then we've got that flexibility, and we're able to act fast within months.

Ahmad Shaath

analyst
#31

Perhaps just a fast question from my side regarding the EAF project. Did I understand correctly that the hybrid scenario has been dropped from the plan, and that you will begin commissioning the two EAFs based on your views about the connectivity?

Mike Garcia

executive
#32

No. Hybrid remains very much an option, I'd say. What we did say was that we wished to stress that we can achieve the same output we have now by operating EAFs solely on cold charge, using the electricity that is accessible at present, together with the recent rulings from IESO and the finished system impact study. So the grid operator in Ontario now has a complete grasp of how our power demand behaves and what it involves, and conclusions have been released by them on that basis. That said, we retain the choice of keeping our blast furnaces running and using hot metal from them, at a lower blast furnace rate, to supplement what the EAFs produce, should we decide to raise the overall volume of steel made. Once more, that comes down to the economics and what that choice looks like economically.

Ahmad Shaath

analyst
#33

Understood. That’s quite useful, and perhaps somewhat connected to that point. Regarding the carbon tax credits, I noticed the figure appeared slightly larger — at least when looking at the income statement — yet it doesn’t seem to have significantly affected cash flow. So that might be something for Rajat. Could you take us through, going forward, how we should view this as the blast furnaces keep running?

Rajat Marwah

executive
#34

Pardon me, Ahmad, could you say the question again?

Ahmad Shaath

analyst
#35

Yeah. I'm just trying to get a handle on what the carbon tax payment could do to your cash flow, since it was pretty sizeable this quarter — around $12 million. That figure hasn't shown up in a while. So maybe you can walk us through why it's a bit larger. From a cash flow standpoint, though, it doesn't appear to have hit operating cash flow. So I'm just trying to figure out how you reconcile those 2 numbers.

Rajat Marwah

executive
#36

Understood. I was thinking government tax. So yes, carbon tax — the way to think about carbon taxes is, we have roughly — we pay on about 5% of our emissions, which comes to roughly 200,000 tons, and the price for last year is — for this year it's $50 million, and next year it rises by another $15 million. So that's how the total cash out comes about, and typically the cash goes out in November. From an accounting standpoint, it was — based on the estimates that come out until the point they're finalized, those estimates get reviewed and the accounting takes place. And that's how you end up seeing a big number in this quarter, which is the September quarter. But for — from a cash out standpoint and a total expense standpoint, it still comes down to simple math of roughly 200,000 tons on average and the price that gets published every year on what we need to pay it on.

Ahmad Shaath

analyst
#37

That's quite useful. And one final question from my side. If I understood your remarks correctly, you are indeed anticipating that margins will get better, but given the volume circumstances in fiscal Q3, we ought to anticipate a slight decline, and after that, past 2024, margins should begin to improve?

Rajat Marwah

executive
#38

That's right.

Mike Garcia

executive
#39

We appreciate you joining us once more for this call about our results in the second quarter of fiscal 2024, and we’re grateful for the ongoing attention you show toward Algoma Steel. We’re eager to share our performance and the strides we’ve made when we release figures for the fiscal third quarter, which is set for February.

Operator

operator
#40

That brings us to the end of today's call, so you're free to hang up whenever you like. We appreciate you taking part.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Algoma Steel Group Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to Algoma Steel Group Inc. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Algoma Steel Group Inc. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.