executiveHello, everyone, and thanks for joining us on Algoma Steel Group Inc.'s conference call covering our Full Year Fiscal 2024 results. With us this morning are Michael Garcia, our Chief Executive Officer, and Rajat Marwah, our Chief Financial Officer. Please be aware that this call is being recorded and a replay will be accessible later today through the Investors section on Algoma Steel's site, www.algoma.com. I want to note that remarks shared during this call could include forward-looking statements under applicable securities laws, and those statements carry assumptions along with inherent risks and uncertainties. Actual outcomes might differ materially from what is stated today; furthermore, our financial statements are put together under IFRS, which is not the same as U.S. GAAP, and during this discussion we will reference certain non-IFRS financial measures. Yesterday evening, we posted an earnings presentation that goes along with today's prepared remarks. You can locate the slides for this call in the Investors section of our corporate website. With that said, I'd ask all participants on today's call to review the legal disclaimers on slide two of the accompanying earnings presentation, and also to look at the risks and assumptions described in Algoma Steel's fourth quarter fiscal 2024 management's discussion and analysis. Kindly note that our financial statements use the U.S. dollar as our functional currency and the Canadian dollar as our presentation currency. Our fiscal year spans April 1st through March 31st, and our statements cover the years ended March 31st, 2024, and March 31st, 2023. Please also note that unless otherwise indicated, all amounts discussed on today's call are in Canadian dollars. After our prepared remarks, we will hold a question-and-answer session. At this point, I'd like to hand the call over to our Chief Executive Officer, Michael Garcia. Mike?
Michael Garcia
executiveThanks, Mike. Good morning, everyone, and I appreciate you being here as we go over what we achieved in the fourth quarter of fiscal 2024 and across the entire year. Keeping our employees safe is a fundamental value and the number one priority for this company; because of that steadfast dedication, we achieved meaningful gains in our lost time injury results in fiscal 2024. With our site remaining a busy place, particularly as more contractors get involved in our EAF project, keeping the focus on safety matters more than it ever has. We're happy to share that Erin Oliver is joining us as the new Vice President of Health and Safety. This role is newly created on our leadership team, and it reports straight to me. A native of Sault Ste. Marie, Erin comes with extensive experience and a solid record of advancing health and safety efforts throughout Canada. Her knowledge will play a key part as we work toward zero injuries in the workplace. Up next, I'll walk through the major events and milestones from our fiscal fourth quarter and what happened after it ended, plus provide an update on how things are progressing with our transformational EAF project. After that, I'll hand things over to Rajit, who will take a closer look at the figures and talk about our solid liquidity and balance sheet, and then I'll wrap up with a market conditions update. There are several important themes I want to convey on this call. Our quarterly results took a hit from the operational difficulties we'd already disclosed — the coke-making utility structure collapse and the blast furnace outage that followed in January, which we resolved and which cost us roughly 150,000 tons of production. After the quarter closed, we finished the scheduled upgrade tied to the plate mill modernization project. The mill upgrades are now essentially done, and the plate mill is already producing as we anticipated, with our operations and commercial teams concentrating on ramping up output and sales of plate products. Our core operations are back to normal now that we've recovered from the utilities corridor collapse and wrapped up the plate mill work, and we anticipate this will lead to sequentially higher shipments in fiscal Q1 of 2025, with additional gains in the quarters that follow. And lastly, our long-term strategy hasn't changed and remains on track, as we work to successfully deliver our electric arc furnace project and become one of North America's leading green steel producers. Now, let me offer a bit more detail on those key themes. Our fiscal fourth quarter of 2024 results matched the guidance we'd previously shared for both shipments and Adjusted EBITDA. They accounted for about 3 weeks of lost production stemming from the utilities corridor collapse at our coke-making facility and the blast furnace outage connected to it. That outage made clear how challenging it is to run facilities that, in certain cases, are more than 70 years old, but it also showcased the professionalism and skill of our workforce and how quickly they could bounce back from that incident. This likewise underscores the advantages we anticipate gaining when we move away from traditional blast furnace steel production toward cutting-edge electric arc furnace operations beginning in the next year. Partially counterbalancing the volume we lost during the quarter was stronger pricing. Because our order book lags, the pricing we actually realized in the quarter mirrored the elevated index prices from the close of calendar 2023, making their way through our contractual order book... After the quarter ended, we wrapped up successfully the scheduled outage tied to upgrading our plate mill. Our crew managed to install new machinery throughout the site, and that has delivered improved product quality while opening the door to greater plate shipments. Even though the facility was down for 3 weeks, plate output during the fiscal first quarter of 2025 should come in at roughly 65,000 tons. That figure would match prior quarters in which no maintenance shutdown occurred, and it signals the stronger run rate we anticipate moving forward. On a highly encouraging note, the team managed to speed up extra work while the outage was underway, and the bulk of the modernization effort at the site is now essentially finished. We anticipate that whatever items remain will be handled alongside other scheduled maintenance work during the next year, which delivers considerable savings on downtime; so what does that translate to in terms of results? For the quarter ahead, we anticipate plate mill output hitting around 90,000 tons. Our operations and commercial groups are concentrated on increasing production and sales of plate products through the rest of the fiscal year, which positions us toward our projected yearly run rate capacity exceeding 650,000 net tons. As we said earlier, we have started pulling out of the wide coil market, and that exit will wrap up across the remainder of the fiscal year; this strategic pivot lets us put plate production and sales first, capitalizing on our standing as Canada's sole discrete producer of plate products, producing a better product mix that should deliver substantial margin improvement. Now that the blast furnace has bounced back from the unplanned outage earlier in the quarter and the plate mill upgrade is finished, our operations are running as they should, and we anticipate strong production figures during the second half of calendar 2024. Now I'll provide an update on how far we've come this quarter with our transformative electric arc furnace, or EAF, project. Once complete, the EAFs will boost our throughput capacity by about a third, enabling us to hit a shipping capacity of roughly 3 million tons, drawing on our two cutting-edge electric arc furnaces. That greater volume will align with our enlarged downstream finishing capacity, which includes added capacity at our upgraded plate mill. Making the switch to EAF steelmaking will better our overall product mix and cut our carbon emissions by roughly 70% once fully up and running. Once we account for how our power supply is generated, shifting to EAF operations should position us among the greenest steel producers in North America. Throughout the quarter, the total amount invested in the EAF project hit $563 million. As of now, we've signed contracts worth roughly CAD 800 million, and about 93% of those are fixed-price agreements. The headway we've made so far on building the project, plus the portion of contracted work that still needs completing, has meaningfully lowered the risk attached to the project budget as we move toward the anticipated beginning of commissioning in late calendar 2024. Just to repeat, our startup strategy still calls for regular output from the steelmaking facility we already operate, alongside gradually increasing steel production from our EAF during calendar 2025, and after that a full transition to EAF production. All told, this quarter proved difficult from an operations standpoint, and market conditions over the past several weeks have demonstrated near-term weakness. Even so, our attention remains on the things within our control: running our current facilities safely, finishing the significant upgrades at our plate mill, and keeping the EAF project moving forward on schedule and on budget. Once more, I want to express gratitude to every one of our employees for their hard work, dedication, and professionalism — especially their capacity to quickly and safely restore our facilities to normal production levels throughout a challenging stretch. At this point, I'll hand the call to Rajit so he can walk us through our financial results for the quarter. Rajit?
Rajat Marwah
executiveThanks, Mike. Good morning, everyone, and I appreciate you joining the call. Just a reminder that unless we say otherwise, every figure we discuss is in Canadian dollars. In our fourth quarter, Adjusted EBITDA came in at CAD 41.5 million, representing a 6.7% Adjusted EBITDA margin, and we generated CAD 121.2 million in cash from operating activities. We closed out the quarter with a solid balance sheet, which included CAD 98 million in cash along with CAD 347 million of available capacity under our revolving credit facility. After the quarter ended, we issued $350 million of high-yield bonds carrying a 9.125% interest rate. Mike already walked through the coke-making corridor collapse in detail. Financially speaking, we figure the outage that followed hurt hot metal production during the quarter by roughly 150,000 tons and cut Adjusted EBITDA by somewhere around $120 million-$130 million; we've been collaborating closely with our insurance providers and adjusters while they finish their assessments. Although we do anticipate recovering a substantial portion of those losses, how much we recover and when remains uncertain. Now let me get into the main factors behind our performance; during the quarter we shipped 451,000 tons, a decline of 21.1% compared to the same quarter last year. The decrease in shipments can be attributed largely to the utility corridor failure at our coke-making plant, which resulted in a blast furnace being taken offline, as Mike mentioned previously; we managed to counter some of that impact by producing and shipping specific product from our existing slab and finished goods stockpiles. On average, our net sales realization reached CAD 1,260 per ton, representing an 18.2% increase compared to the same period last year. This year-over-year improvement captures the delayed effect of our order book as well as robust pricing as the calendar year drew to a close. Throughout the quarter, plate pricing continued to gain from a significant premium relative to hot-rolled coil, underpinned by steady demand. Steel revenue for the quarter came in at CAD 568 million, which was down 6.7% compared with the same period a year earlier. On the cost side, Algoma's average cost per ton of steel products sold was CAD 1,182 for the quarter, up 21.1% versus the prior year period. That year-over-year increase was mainly driven by three things: lower volumes, the cost of using purchased coke instead of coke we produced ourselves, and higher natural gas prices. Cash flow from operations for the quarter was CAD 121 million, which is above the CAD 95 million recorded in the prior year period. The main driver of cash flow this quarter was a net change in non-cash working capital. At the close of the fiscal year, we had CAD 808 million in inventories, down from CAD 886 million at the end of the third quarter of fiscal 2024. Now looking at our results for the full fiscal year, we shipped 2.1 million tons, an increase of 4.1% compared with the year before. Our average net sales realization was CAD 1,220 per ton, which represents a 4.1% decrease versus the prior year, and that reflects generally soft market conditions across the fiscal year. Steel revenue came in at $2.5 billion as a result, basically unchanged from the previous year. On the cost side, the average selling price for steel products at Algoma was $1,018 per ton for the year, up 1.5% from the year before. What drove that increase were greater usage of purchased coke, more natural gas consumption, and labor expenses, and those factors outweighed the benefit of increased shipments. Full-year adjusted EBITDA reached $313 million, which works out to an adjusted EBITDA margin of 11.2%, versus $452 million of adjusted EBITDA and a 16.3% adjusted EBITDA margin in fiscal 2023. Lower price realizations and elevated costs were the main reasons for the decline, and those more than canceled out the gain from higher shipments. For fiscal 2024, cash flow generated by operating activities came in at CAD 295 million, an improvement from CAD 177 million in fiscal 2023. The year-over-year gain was mostly the result of the net change in Non-Cash Working Capital, partly offset by reduced operating income. Working capital went from CAD 875 million at the close of fiscal 2023 down to CAD 830 million at the close of fiscal 2024. Our original expectation was that we would free up a larger amount of working capital during that period. But, as I noted during the previous call, the unplanned outage in the quarter meant we released smaller amounts. Driving working capital levels lower remains our focus, and we still anticipate a release of no less than 100 million in fiscal 2025. I'll now discuss the financing activity that we wrapped up in early April. A subsidiary we own entirely, ASI, which we don't consolidate directly, put out $350 million total in senior secured second lien notes carrying a 9.15% rate and maturing in April 2029. Through that move, our balance sheet gained both strength and flexibility. The smooth completion of this offering demonstrates how positively credit investors view our business, as well as the trust they place in where we're heading strategically and in our financial soundness. Altogether, the cash we held, the unused portion accessible under our ABL revolver when the fiscal year closed, and the money brought in from selling these notes add up to more than $900 million in liquidity; with that said, let's shift to what we expect for the first quarter of fiscal 2025. Taking into account how business has gone so far this quarter, the orders we've booked, and what we anticipate shipping before the month wraps up, we're looking at a healthy Adjusted EBITDA for the fiscal first quarter, somewhere between CAD 30 million and CAD 40 million, along with steel shipments totaling 500,000 to 510,000 tons. At this point I'll hand things back to Michael Garcia, our CEO, for some final remarks. Mike?
Michael Garcia
executiveAppreciate that, Rajit. If we look at where the North American steel market stands right now, pricing has swung around quite a bit so far this year. From the start of January through today, the index price for U.S. Midwest domestic hot-rolled coil has dropped by roughly $400 per ton. What we're seeing in the market at present—this softness—comes down to plenty of spot supply being available, short lead times, broader economic uncertainty, and purchasers holding back as we head into the summer months, which are seasonally slower for buying. Like I've mentioned before, our attention stays on the things within our control, which means running our facilities in a safe manner so we can best seize market opportunities whenever they show up. There's support for our results in the fact that plate pricing is still showing a sizable premium, since demand for plate products overall stays elevated. That, in turn, keeps helping our average price realizations, particularly now that we're seeing greater production volumes out of the plate mill after the planned outage and upgrade we most recently completed. Over the coming several quarters, there's an exciting chapter ahead in the Algoma story, because we keep pushing forward on the work needed to begin commissioning our transformative EAF project before the year is out. That brings us into the next phase of our company—one that shapes what lies ahead for Algoma, lays the groundwork for creating long-term value for our stakeholders, and cements our standing as a leader at the very front of green steel production in North America. Many thanks for the ongoing interest you've shown in Algoma Steel. With that, we'd be glad to take your questions. Operator, could you please provide the instructions for the Q&A session.
David Ocampo
analystThanks, everybody, for allowing me to ask. My initial question concerns shipments in the June quarter. That figure is under the typical run rate, despite plate shipments looking quite strong at 65,000 tons. I'm just wondering what's behind those reduced volumes. Is it mostly softer industry conditions, or are additional elements playing a role?
Rajat Marwah
executiveHello, David. Good to speak with you. You're completely correct that it's slightly lower. Typically, though, whenever we have outages of this type — specifically the 20-day outage we took at the plate mill — plus the ramp-up, we generally lose roughly 50,000 tons to 60,000 tons, from both the plate mill and the strip mill tied to it. So ordinarily our shipment ought to be under 500, yet the plate mill genuinely bounced back well following the outage and made up part of those losses. As a result, we'll land in the 500 to 510 range, though the primary cause is that outage we took, which usually lasts 20 days, with the ramp-up requiring somewhat more time.
David Ocampo
analystOnce more, that's quite useful, Rajit. Then perhaps also for you, regarding the capital expenditures during the quarter, I believe the figure was near CAD 120 million, with 50 of that allocated to the EAF. I'm wondering what the remaining CAD 70 million could be traced back to. Did a portion of those expenditures spill over into the coke ovens that you had to fix?
Rajat Marwah
executiveYes, you're completely correct. That is the CapEx tied to the coke oven along with a few of the blast furnace problems. The reason for all of it is the coke oven collapse, the utility corridor, and, as you know, we're in discussions with the insurance providers about that matter too, so it will be recovered once it's settled, and it will likely arrive in the next quarter, the next year, this year, fiscal 2025.
David Ocampo
analystAll right, so when it comes to capital expenditures, the possible reimbursement coming from insurance companies—does that sit on top of the $120 million to $130 million in EBITDA you're aiming to recover?
Rajat Marwah
executiveThat's right.
David Ocampo
analystAll right, and the final question from me before I pass it along. You're getting close to wrapping up your EAF project, so I'm wondering — when we consider how the total cost might land, what risks remain that could take you past the upper bound of your guidance? And conversely, what might bring you in nearer to that $825 million figure, since eight hundred million already looks locked in at contract prices?
Michael Garcia
executiveHello, David, Mike here. Given where we stand today, we've taken a great deal of risk out of this project on both schedule and budget. Weather delays and labor disruptions are the kinds of things that can always crop up. At present, none of those worry us. A modest portion of the work — likely below 10%, likely below 8% — is being performed on time and materials. So in theory, there's a chance those time and materials costs come in above the placeholders we currently carry, our assumptions about where they'll land. Still, that represents under 10% of the total spend we intend, so we don't view it as a major risk. Turning to the possibility of finishing below that range, between $825 and $875, once more, since the bulk of the work is contracted, there isn't much upside available to capture. We might spot some efficiencies letting us pick up a little on certain time and material work; beyond that, a handful of contracts remain to be awarded for the rest of the scope. Only about two contracts are of moderate to significant size — one is the material handling system, and the other is the fire protection system. So the team is putting in considerable effort alongside the contractor base, giving them the proper engineering package so they can bid on both of those pieces of work; we're optimistic about where they'll land, though we won't know for certain until those contracts are actually awarded. Does that answer your question?
David Ocampo
analystRight, so about those two contract pieces still waiting to be handed out — are we talking $25 million, or is it $50 million? What size are we looking at that still has to be contracted?
Michael Garcia
executiveI don't have that figure on hand at the moment. Let me check with the team, and perhaps I can get you something.
David Ocampo
analystAlright, that's useful. I'll pass the call along now. Many thanks.
Michael Garcia
executiveThanks.
Ian Gillies
analystGood morning, everyone.
Michael Garcia
executiveMorning, Ian.
Rajat Marwah
executiveGood morning.
Ian Gillies
analystWith the EAF start-up getting nearer, can you give us any news on the scrap plan and where things stand there, since that might turn into a bottleneck?
Michael Garcia
executiveCertainly. As we've said in the past, the way we'll obtain scrap for the EAFs is via the joint venture we set up with Triple M Metal when this project began. That venture is now up and running. It has staff, the folks from Triple M or ATM — Algoma Triple M is what it's called. They've been active in the market, talking with scrap suppliers, both those we'll use later and those we use now. So they've put in plenty of effort in the market. We know which suppliers we'll purchase scrap from. We know the way we'll transport it into Sault Ste. Marie. We've devoted substantial time to the supply chain, ensuring we have efficient logistics by rail, truck, and throughout the Great Lakes. At present the joint venture is purchasing scrap for our existing operations; that's not anywhere close to the volume we'll purchase later, but we do purchase scrap today for our Basic Oxygen Furnace, our steelmaking shop. So we're confident about our grasp of the scrap market and who our suppliers will be. Still, we won't purchase those bigger volumes until later in the ramp-up curve, in the second half of calendar year 2025. That makes it tough to say precisely how the market will look or feel then.
Ian Gillies
analystAll right, that's useful. Regarding the plate side, those ramps clearly have the potential to be fairly significant across what you might call the coming 4 to 6 quarters. Could you elaborate a bit on the way your commercial team is winning market share, and how it typically goes about winning market share in that area? Since, I mean, plate pricing has been rather soft during recent weeks.
Michael Garcia
executiveCertainly. So, you know, everyone on the team is genuinely thrilled with what we now offer in plate; we've achieved considerable gains in surface quality, flatness, and dimensional tolerance thanks to the upgrades we completed at the plate mill across the past 2 years; we've achieved considerable gains in how well we deliver our plate over roughly the past 18 months. And I believe that combination of the two gives the commercial team a more compelling pitch to both our existing plate mill customers and prospective ones. In fact, we held a grand opening for the modernization of our plate mill right here in Sault Ste. Marie earlier this week, and about 25 plate customers joined us at the mill. We walked them through the new facility; they had the chance to meet the crews, to view the product, to see the new assets installed and operating. And so, you know, going forward from here, it comes down to having those one-on-one conversations with our plate customer base and with potential plate customers, a number of whom were, honestly, plate customers historically, and for one reason or another, you know, we haven't held a major position with over the past 5 or 10 years. So it's that kind of selling, grasping the customer's needs, grasping what the customer is after and how they succeed in their marketplace and with their own customers, and simply carrying out that kind of work alongside the customers to either expand our share of wallet among existing customers or build a position with customers where we don't yet have one.
Ian Gillies
analystAlright, that's, that's useful; given that, I'll hand it back over.
Michael Garcia
executiveThanks, Ian.
Katja Jancic
analystHello, and thanks for taking my questions. Perhaps to begin with CapEx for fiscal year 2025, could you give an update on what total expected CapEx will be?
Rajat Marwah
executiveCertainly. So, as always, our typical maintenance CapEx is going to fall between CAD 100 million and CAD 120 million, likely toward the upper end, given where the legacy assets stand. Our EAF CapEx should come in at approximately CAD 250 million to CAD 270 million for fiscal 2025. And all of this is without any recovery from the government. And, yes, I believe those are the two significant ones that you will see in fiscal 2025.
Katja Jancic
analystIs there still anything additional from the coke ovens that will carry over into—
Rajat Marwah
executiveYes, there will be additional on the—
Katja Jancic
analystwhat about the upcoming quarters?
Rajat Marwah
executiveYes, there's going to be some additional spending tied to the coke oven, though recovery we anticipate over the course of the year should counter that, plus a bit more to make up for what we've already laid out this year. So once everything's settled, those should balance each other out; however, none of this has been wrapped up yet. What we'll likely be putting out is somewhere around $30-odd million, so $30 million to $40 million on the coke side across the year. If nothing recovers, that's the extra you'd be looking at; still, talks with the insurers continue on that front.
Katja Jancic
analystAll right, turning to the volume question, then. At present, what amount of normalized volume do you believe you can get to each quarter in an environment that's more normalized?
Rajat Marwah
executiveYeah. As we've consistently stated, $550 represents a normal level that we will get to, and that's the figure we use for benchmarking. Once the EAF settles down, improvement ought to begin. And once more, all of that takes into account where our primary operations sit. So over the coming couple of quarters, that's what strikes us as more normal; and like I mentioned, as the EAF stabilizes, we'll begin to observe that increase taking place.
Katja Jancic
analystPerhaps regarding that point, what's your expected speed for bringing the EAF up to capacity, or how fast could it reach a steady state?
Michael Garcia
executiveYes, Katja, Mike here. The first EAF, EAF steel will start being produced during the initial calendar quarter of 2025. Commissioning will in fact kick off prior to this year's conclusion, yet we don't anticipate striking an arc and producing heats until that initial calendar quarter of 2025. As with any startup, it will be methodical and require considerable effort from the startup team, but all our crews have been identified. Training is underway. A production plan exists, and we anticipate volume across those EAFs will build up over the rest of 2025. However, we will share that at the right moment. Yet honestly, it's... We aren't hesitant about over-committing or overstretching concerning precisely how much metal we'll produce from those EAFs, particularly during the first half of 2025. That's the reason we intend to keep operating our existing steelmaking assets and flow path at maximum output as we progress into 2025 and throughout the remainder of that year.
Katja Jancic
analystAll right, then, just so I'm clear, while that startup is happening, the blast furnace is essentially going to run the way it always does, meaning it ought to get up to its typical output — that is, 550, say, each quarter.
Michael Garcia
executiveThat's right; we, we have no desire for any big, for any falloff in shipments on a quarterly basis across that startup year, since it is a startup year.
Katja Jancic
analystAll right, perhaps just one additional question, if that's okay. Mike, I believe you mentioned that during this quarter, or in Q1, plate output came to roughly 65,000 tons. Did I get that right that in the following quarter it ought to reach 90?
Michael Garcia
executiveThat's right.
Katja Jancic
analystAll right, thanks.
Michael Garcia
executiveOnce more, we appreciate everyone joining this call covering our Fiscal 2024 full-year earnings, and we're grateful for your ongoing interest in Algoma Steel. We're eager to share updates on our performance and headway when we present results for the fiscal first quarter, which is set for August. Thanks.
Operator
operatorThanks, everyone — that wraps up the call for today. At this point you're free to drop off the lines, and we appreciate you joining us.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Algoma Steel Group Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Algoma Steel Group Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Algoma Steel Group Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.