Algoma Steel Group Inc. (ASTL) Earnings Call Transcript & Summary

August 14, 2024

NASDAQ US Materials Metals and Mining earnings 37 min

Earnings Call Speaker Segments

Mike Moraca

executive
#1

Hello, everyone, and thanks for joining the First Quarter Fiscal 2025 Earnings Conference Call for Algoma Steel Group Inc. this morning. Today's speakers are Michael Garcia, who serves as our Chief Executive Officer, and Rajat Marwah, our Chief Financial Officer. Please be aware that this call is being recorded and a replay will be accessible later today in the Investors section of the Algoma Steel website. I'd also like to note that remarks shared during this call might include forward-looking statements under applicable securities laws, and those involve assumptions along with inherent risks and uncertainties. Results that actually occur could differ materially from what is stated today. Furthermore, our financial statements are put together in accordance with IFRS, which is not the same as U.S. GAAP, and during this discussion we will reference certain non-IFRS financial measures. Yesterday evening, we posted an earnings presentation that goes along with today's prepared remarks. You can locate the slides for this call in the Investors section of our corporate website. With all of that said, I'd ask that each person on today's call review the legal disclaimers found on Slide 2 of the accompanying earnings presentation, and also look at the risks and assumptions described in Algoma Steel's first quarter fiscal 2025 management's discussion and analysis. Keep in mind that our financial statements use the U.S. dollar as our functional currency, while the Canadian dollar serves as our presentation currency. Our fiscal year goes from April 1 to March 31, and the financial statements were prepared for the quarters that ended June 30, 2024 and June 30, 2023. Be advised that unless otherwise noted, all amounts mentioned on today's call are in Canadian dollars. After our prepared remarks, we'll hold a question-and-answer session. I'll now hand the call over to Michael Garcia, our Chief Executive Officer. Mike?

Mike Garcia

executive
#2

Thanks, Mike. Hello, everyone, and I appreciate you being here as we go through what happened in our first fiscal quarter of 2025. Keeping our people safe stays a fundamental value and our number one priority as a company. That steadfast dedication produced meaningful gains in how we performed on lost time injuries throughout fiscal 2024, and we're carrying that emphasis forward into the present fiscal year. Paying attention to safety matters even more now, given that our site is buzzing with work as the EAF project moves ahead; that commitment also gets highlighted in Algoma's second annual ESG report, which came out this past Monday and explores a broad set of subjects spanning environmental, social and governance matters in more depth. The report showcases what we're continually doing to uphold safety standards and also to push forward our wider ESG obligations, underscoring how we stand as a leader when it comes to sustainable and responsible business practices. Up next, I'll walk through the major events and milestones from our fiscal first quarter, plus provide an update on how the transformative EAF project is progressing. After that, I'll hand things to Rajat, who will dig deeper into the figures and talk about our solid liquidity and balance sheet, and then I'll wrap up with a look at market conditions. There are several key themes I want to convey on today's call. To start, our quarterly results mirrored the broader situation in steel markets, which meant reduced volumes and realized prices. Shipping volumes came in weaker too, which mirrored the scheduled outage at our plate and strip facility during April; once the outage ended, we put plate production first and anticipate that we'll keep increasing volumes across the coming quarters. Secondly, our balance sheet and liquidity sit in a strong position, having gotten a boost from our USD 350 million notes offering in April, which left us with cash at quarter end of nearly $500 million and total liquidity exceeding $800 million. We have ample funding to finish our EAF project. And last, the EAF project stands on the verge of a genuinely thrilling milestone, getting close to the scheduled start of commissioning for Unit 1 in our calendar fourth quarter. Each passing day lowers the project's risk and moves us one more step toward becoming one of the greenest steel producers in North America. Now, let me add some further detail on those key themes. Our results for the fiscal first quarter of 2025 matched the guidance we had previously disclosed for both shipments and adjusted EBITDA. They showed a continuation of the difficult market conditions we've encountered this year when it comes to steel pricing; we remain intensely focused on making sure our existing legacy facilities, several of which are more than 70 years old, operate safely as we shift toward EAF steelmaking. In the end, the mix of reduced shipments and weaker realized steel prices drove an overall drop in revenues, adjusted EBITDA and cash flow generation compared with the prior year period. Like we mentioned on the previous call, over the quarter we wrapped up essentially all the outstanding improvements tied to the plate mill modernization. That work means putting in new machinery throughout the site, which has lifted product quality and is driving a consistent increase in plate shipments. Even though the site was down for 3 weeks, plate shipments during the first fiscal quarter of 2025 came in at roughly 61,000 tonnes. The second phase of our 2-part plate mill modernization project had initially planned a final multi-week outage for later this year, but our team managed to pull forward extra work into this outage, meaning the bulk of the modernization effort at the site is now essentially finished. Anything left over, we anticipate handling alongside other scheduled maintenance in the year ahead. For our fiscal second quarter, we anticipate plate production near 90,000 tonnes as we carry out a steady ramp through the rest of the fiscal year toward our anticipated annual run rate capacity of more than 650,000 net tonnes; given the exit from the wide coil market we announced earlier, happening in our 2025 fiscal year, we can now focus on plate production and sales, capitalizing on our standing as Canada's only discrete producer of plate products. That ought to deliver a better product mix, which we expect to generate meaningful margin improvement. Now that the blast furnace maintenance outages and the plate mill upgrade are behind us, operations are running as normal, and we still anticipate strong production levels during the second half of calendar 2024. In April, we closed a USD 350 million note offering, which gave our liquidity a substantial boost as we head into the final stretch of building our EAF project. Cash on hand when the quarter ended stood at nearly $0.5 billion. Paired with our undrawn credit facility, that provides excellent flexibility and security for carrying out our strategic growth strategy. Let me now update you on how our electric arc furnace project progressed during the quarter. It's genuinely an exciting moment in Sault Ste. Marie as the skyline at the EAF site keeps transforming, with exterior sheeting sealing the building ahead of commissioning activities set to begin by the end of this year. With EAF steel production anticipated by the close of the calendar first quarter of next year, we'll start ramping toward a shipping capacity of roughly 3 million tonnes per year. Cumulative investment in the EAF project hit $611 million during the quarter. So far, we've committed contracts worth approximately $850 million, and over 90% of that is tied to fixed price contracts. The progress made so far on both construction and the contracted work still outstanding has meaningfully derisked the project budget; we anticipate that all remaining contracted work will be settled in the current quarter. Just to remind everyone, during calendar 2025 our start-up plant will still have the usual output coming from the steelmaking facility we already operate, even as we increase steel production from our EAF, and after that we move entirely to EAF production. To sum up, the market was extremely difficult, so during the quarter we concentrated on the things we could influence: running the facilities we already have in a safe manner, finishing the significant upgrades at our plate mill, and keeping the EAF project moving forward both on schedule and on budget. The softness in pricing over the near term cannot reduce how excited we are about what is taking place at our company and the enormous leap forward this means for Algoma Steel and for our community. Once again, I want to express thanks to every one of our employees for the hard work, the dedication and the professionalism they show. At this point I will hand the call to Rajat so he can review our financial results for the quarter. Rajat?

Rajat Marwah

executive
#3

Thanks, Mike. Good morning, everyone, and I appreciate you all being on the call today. Just a quick note that every figure we discuss is in Canadian dollars unless we say otherwise. For the first quarter, adjusted EBITDA came in at $37.7 million, which works out to an adjusted EBITDA margin of 5.8%, and cash from operating activities was $12.5 million; we closed the quarter with a solid balance sheet, with $493 million in cash and $351 million of availability under our revolving credit facility; let me now walk through what drove our performance. Steel revenue for the quarter reached $597 million, a decline of 20.8% from the same period a year earlier. We shipped 503,000 net tonnes during the quarter, which was 11.6% lower than the prior year quarter. That shipment decline was mostly due to the planned maintenance outage at our plate and strip facility as we finish the last phases of the plate mill modernization project. Net sales realization came in at an average of $1,187 per tonne, a drop of 10.4% from the prior year period. That year-over-year decrease reflects softer market conditions, partly offset by a better value-added product mix as a share of steel sales; turning to costs, Algoma's cost per tonne of steel products sold averaged $1,069 for the quarter, which is 12.5% higher than the prior year period. The primary factors behind that year-over-year rise are lower volume, the expense of substituting purchased coke for internally produced coke, and higher natural gas. Cash flow from operations came to $12.5 million for the quarter, versus $163.9 million in the prior year period. The principal reason cash flow declined in the quarter was lower operating income. Inventories stood at $800 million at quarter end, a slight decrease from $808 million at the close of the 2024 fiscal year. We're still focused on reducing working capital levels and continue to expect a release of no less than $100 million in fiscal 2025. Now let me remind you about the financing activity we wrapped up in early April. Our wholly owned subsidiary, ASI, issued and aggregated USD 350 million of 9.125% senior secured second lien notes due April 2029; that step strengthened and added flexibility to our balance sheet and shows the favorable view credit investors hold of our company, along with their confidence in our strategic direction and financial stability. In total, the company had $493 million of cash and $351 million of unused availability under the revolving credit facility, which represents roughly $845 million of liquidity plus about $45 million available on our strategic innovation fund loan supporting the EAF project. One more item regarding the insurance recovery tied to the coke-making corridor collapse in January. We're continuing to work closely with our insurance providers and adjusters as they finish their assessments. Although a claim like this calls for a thorough adjudication effort, we've moved forward on the property damage piece and anticipate an advance of $25 million during the quarter we're in, even as we continue working through what remains of both the business interruption and property damage claims. At this point, I'll hand the call back to our CEO, Mike Garcia, for some closing comments.

Mike Garcia

executive
#4

Thanks, Rajat. If we look at where the North American steel market stands, pricing has mostly come under pressure from the spring through the summer. Prices have appeared to be leveling off to some degree since late July, but we still anticipate that they'll create headwinds for earnings results in the near term. The softer conditions seen over the past few months are a reflection of plentiful spot supply, brief lead times, uncertainty in the economy and careful purchasing throughout what is normally a slower summer buying period. While we await relief from these headwinds, our attention will stay on the things within our control: running our facilities safely and putting ourselves in the best position to seize market opportunities when they emerge. For nearly 5 years now, we've been working toward bringing electric arc furnace steelmaking to Sault Ste. Marie. Our whole company feels a sense of excitement as this major milestone draws near. Over the coming months, we'll keep up our unrelenting focus on safely operating the facilities we have today as we carry out commissioning of our transformative EAF project. By pursuing this endeavor, our strategic vision should unlock meaningful shareholder value and also deliver some of the greenest steel available in North America. Many thanks for your ongoing interest in Algoma Steel. With that, we'd be glad to take your questions. Operator, could you please provide the instructions for the Q&A session.

David Ocampo

analyst
#5

Perhaps the first thing here is for Rajat. The EAF is getting closer to starting up. Could you help us get a handle on the duplicate costs you'll be taking on while in the hybrid phase? And the second half of that is, what do unit economics look like after we're operating fully as an EAF? Is it scrap plus $200 to $220 of conversion cost? That's a figure I believe you've referenced before. So we were just hoping you could bring us up to date on those metrics.

Rajat Marwah

executive
#6

Certainly, David, and thank you for asking. So as we make the transition through the EAF, the biggest cost shift that occurs while we're operating in the transformative mode is the labor cost, seen from a fixed cost standpoint. And then the gap — the delta between buying scrap or generating hot iron in-house. The way we look at it is that in the coming year, when we begin producing from both furnaces — that's the blast furnaces operating at the capacity they have now, plus the EAF contributing tonnes as we ramp up — our cost per tonne will decline, since volume will be greater. Yet in absolute terms, the cost will be — on a fixed basis will be quite comparable. Variable, will move around depending on some of the index contracts we hold for scrap purchasing. But on a fixed cost basis, it will be quite comparable to what we currently have, since the headcount required to run the furnace is already embedded in the cost you're seeing now; they're being trained, they're drafting SOPs and so forth; so our cost, on a per tonne basis, will decline as we produce more and ship more through the transformative period; and once we reach the point where we shut the blast furnace and move to only electric arc furnace, there will be meaningful savings on the fixed cost side as people exit to align with the operational capabilities. We will target scrap plus $200 to $220 in much the same range, as I said before, from our full cost standpoint.

David Ocampo

analyst
#7

All right. And I believe, if I recall correctly, that the workforce cut was roughly 1,000 people. Could you bring us up to date on the way that will be accomplished? Or will there be significant transition expenses connected to cutting staff?

Mike Garcia

executive
#8

David, Mike here. Yeah, I'd say the biggest savings or shifts on the staffing side will come once we stop running the blast furnace and coke ovens. Some lesser tweaks will occur in certain support functions, like maintenance and a few of the infrastructure support groups. Still, your figure for headcount is roughly correct. And as far as execution goes, it's fairly simple once you quit operating an asset or a department, since the CBA spells out clearly what happens to those workers when they depart the company; they keep certain recall rights inside the collective bargaining unit for some period, and the expense of achieving that staffing cut is laid out quite clearly in the CBAs, and we can see it well.

David Ocampo

analyst
#9

All right, that helps. And Michael, since I've got you, regarding that $25 million still needing to be contracted out — how likely is it that you folks end up exceeding the budget? I just want a sense of the worst case, whether that's in terms of order of magnitude or simply what might go sideways.

Mike Garcia

executive
#10

Absolutely. So commitments are in place, and we've signed contracts amounting to CAD 850 million. Our aim and expectation is that the rest of the commitments and contracts required to finish the project get placed inside what remains of the budget — that's $25 million; there are a handful of contracts left for us to award, and those will wrap up essentially the installation and the construction of the facility. The equipment has all been delivered to site. It's all being installed as we speak. This is a very busy stretch for us when it comes to construction and installation on the project. As for the building — its exterior is mostly done, and the tie-in with the neighboring operations is mostly done. In the first EAF furnace, the transformers have been installed. That's 9 transformers featuring Q1 technology. When it comes to the cranes, many of them are already in the commissioning stage right now. So the team's goal is to award those final installation and construction contracts while staying inside the budget. Roughly under 10% of the overall budget consists of commitments or contracts that are time and material. That means there's invariably some execution risk with time and material contracts — should you end up using additional time or additional materials, you then face the possibility of blowing the budget. That's why we're watching it very carefully. It's also a key area of attention for the project team. Once more, that likely falls within the overall budget's scope. It amounts to somewhere between $60 million and $70 million of the total cost. So that's where the exposure sits. So at this stage, I'd say we're in the home stretch on this project; execution is our focus. Our focus is on awarding those remaining contracts for installation and construction. And we intend to complete it inside that $875 million figure. So putting a specific measure on the risk is difficult, but our attention is squarely on getting this project done at CAD $875 million.

David Ocampo

analyst
#11

All right. From what you're saying, it seems the time and materials work is coming in about where you figured it would at this stage. Right?

Mike Garcia

executive
#12

That's right. That's right. We also added a project coordinator, EllisDon, who assists us in handling that time and material component, plus the broader scheduling and pacing of every construction and installation activity taking place across the project site. They have now been with us for more than 1.5 years, so they have proven a wonderful addition to the team.

Katja Jancic

analyst
#13

Perhaps we could begin with the plate ramp-up. For Q2, you're anticipating 90,000 tonnes. What's the right way to view the ramp-up over the remaining months of the year?

Mike Garcia

executive
#14

From the perspective of both production and capability, we're feeling quite confident about our position. The mill emerged from the April outage — I believe that was a 22-day outage. It came back up quite smoothly following that downtime. We're extremely pleased with what the mill can do and how it's performing. There's still some work on the shear line pacing to ensure that line is running well, though that isn't constraining our actual shipments or production, since we haven't yet taken the gas cutting line down; so on the production side, we're quite happy with where things stand. Honestly, the biggest issue at the moment is the market. We're dealing with a soft market, and while the commercial team is getting excellent feedback regarding our plate's quality and our plate mill's delivery performance, demand isn't particularly strong at present. Plate pricing still carries a spread of more than $300 compared with coil. So that's something we feel good about. Still, we're up against a somewhat soft market at the moment. So I'd say our existing expectation for that 90,000 tonne quarter holds. As for the ramp-up toward year-end, we'll likely see a bit less in the quarter that follows this one, because we're doing a small maintenance outage at the mill. That's how we're currently viewing our plate business.

Katja Jancic

analyst
#15

Could you also refresh our memory on what share of your plate volume is shipped to the U.S. market?

Mike Garcia

executive
#16

Roughly 30%. That figure isn't exactly 30% each month, but it stays near 30% across the entire year.

Katja Jancic

analyst
#17

And so, Mike, perhaps at the start you said the pricing landscape is weak; right now we're in a period where demand is seasonally slower. What's the right way to think about total shipments in the near term? During the prior quarter, you were partly affected by the plate maintenance or upgrade. What about the current quarter? How should shipments be viewed?

Mike Garcia

executive
#18

Yeah, Katja, thanks. My sense is they will move higher directionally. Operations are doing well. Our commercial group is putting in a lot of effort to keep customers supplied. I believe we aren't seeing — we're aware of where pricing stands at present. Over the rest of the year, I don't anticipate any near-term catalyst that would push pricing up, and demand will likely follow the same pattern, though it will definitely be directionally higher in the upcoming quarter; and in this current market environment, this is a moment when our focus is on finishing the EAF project, and even under present market conditions we possess all the liquidity required to finish that project on schedule and within budget.

Katja Jancic

analyst
#19

And perhaps, just to wrap up, one final question. You said the NCIB is being brought back. Considering how sizable the available liquidity is at the moment, would you be open to drawing on some of it? Or will this instead be linked more closely to the free cash flow we generate?

Mike Garcia

executive
#20

Well, I believe we — our aim in putting the — in reinstating the NCIB was to give ourselves room to do either of those things, to buy — to give capital back to shareholders, to purchase company shares at moments we judge favorable for buying. We stay conscious of where our liquidity stands; we still have to complete the EAF project and keep carrying out our strategic transformation, yet our capital allocation strategy is always on our minds; so having the NCIB in place, we believe, provides us that flexibility to pursue it.

Ian Gillies

analyst
#21

When you consider deploying the NCIB and take the share price—whether it's costly or cheap—as your reference point, do you use a baseline of 2.2 million tonnes of output, 2.7 million tonnes, or closer to 3 million tonnes to determine that valuation, deciding if the stock is cheap enough to act on?

Mike Garcia

executive
#22

Well, I mean — that's a great question. I think we are building this company to be a 3 million plus — 3 million finished goods steel company of plate and DSPC; and that's the value we are creating, and that's going to be enabled by completing these EAF furnaces and starting them up successfully in 2025 and then reaching 2.4 million tonnes of EAF production sometime in 2026. We've got the power secured to do that; so there's no limitations from the power. And so that's how we kind of think of the value we're creating and our view of the value of the company; now we aren't there yet. We've got to complete the project and get it started up; but I think where we've gotten to over the last 5 years that we've been on this journey, we are in a really exciting place right now and we'll be making EAF steel in another — just over 6 months.

Rajat Marwah

executive
#23

Ian, one more thing from me. In my view, the market is undervaluing us, and that isn't shocking at all. Once the EAF is finished, that should change, and it lines up with how peers typically trade. So to me that's fairly obvious, yet as Mike noted, our priority remains getting this project done and ensuring we've got the funds needed to finish it.

Ian Gillies

analyst
#24

Got it. So when we get into calendar year 2025, Rajat, could you walk us through what tax advantages might come from firing up the EAF? My assumption is that there are substantial capital cost allowances and similar items involved. Does that mean the cash tax effect ought to be pretty minimal in the coming year, or perhaps even reduced?

Rajat Marwah

executive
#25

That's exactly correct. Once we bring it into commission and capitalize it, Canada offers accelerated depreciation, which lets us claim the bulk of it within a 2-year window. So our cash taxes are certainly going to be reduced, and that benefit will be realized across 2 or 3 years, depending on the state of the economy, but the taxes we owe will come down.

Ian Gillies

analyst
#26

All right; and the final one from me relates to EAF and power. Could you give any kind of thorough update regarding where things stand with the public utility commission and securing the last sign-off needed to construct that power line? My understanding was that this was expected to arrive between this summer and the fall.

Mike Garcia

executive
#27

Yeah. So the final decision — formal approval from the Ontario Energy Board for PUCs leave to construct application — is what we're anticipating either at the close of August or in early September. All the — we have stayed in extremely close touch with PUC while they put the application together with OEB while it undergoes review. We have been monitoring it. No problems have arisen — OEB or interveners have raised no additional questions, and nobody has come forward opposing the project; so — even so, a full review of the application by OEB and the issuing of their positive finding does require time. After that is in hand, that essentially sets in motion the work for the physical build, which we expect to finish during 2027. At that point, if you consider what finishing the power line here in the community of Sault Ste. Marie will accomplish, it's this: we will have sufficient power to produce 2.4 million tonnes of EAF steel through cold charging, 100% without supplementing any hot iron from our blast furnaces. Once that local line wraps up in 2027, we'll have sufficient power to turn out 3 million tonnes of EAF steel. That figure would come from combining the greater grid power made available to us with continued operation of our Lake Superior power plant. The last phase, then, would be finishing the grid — the transmission lines across the Ontario province — which would let us, once more, produce 3 million tonnes, though this time without operating our captive power plant, and that would substantially reduce both our cost and our carbon emissions profile; so really, once that local power line is done in 2027, we'll be at full production based on how much steel our EAF and our downstream can turn out. Beyond that, any further power changes would only work to bring down our cost and our carbon emissions profile.

Ian Gillies

analyst
#28

Got it. And perhaps one quick follow-up, if that's all right. So would that suggest that at some stage — maybe this is something further out on the timeline — LSP turns into a possible monetization chance to provide some additional value?

Mike Garcia

executive
#29

I believe that's right. I believe it's going to be — it's going to hinge on what condition the Ontario grid is in overall and on how the system operator along with the OEB look at that power plant, in terms of whether it contributes grid stability, whether it holds value from a peaker standpoint for making sure power is available, and if those conversations are taking place at that point, I believe there's going to be value in keeping that power plant running and keeping it within the province's broader generation footprint so it can produce 110 megawatts of power at the moments the system operator needs it.

Mike Moraca

executive
#30

Thank you. I appreciate everyone joining us for this earnings conference call covering the first quarter of fiscal 2025, and I'm grateful for the ongoing interest you've shown in Algoma Steel. We're eager to share our results and progress with you when we present our fiscal second quarter results, which are scheduled for November. Thanks so much. Enjoy the rest of your day.

Operator

operator
#31

That brings an end to the conference call for today. You're free to disconnect your lines at this point. We appreciate you taking part.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Algoma Steel Group Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to Algoma Steel Group Inc. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Algoma Steel Group Inc. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.