Leila Dillon

executive
#1

Thanks, Michelle, and good afternoon to all of you. We're glad you could be with us on today's call. Here with me are George Sakellaris, who serves as Ameresco's Chairman, President and Chief Executive Officer; Doran Hole, our Executive Vice President and Chief Financial Officer; and Mark Chiplock, Senior Vice President and Chief Accounting Officer. Before handing things over to George, I want to offer a short note about forward-looking remarks. The earnings materials we released today include forward-looking statements, among them statements about what we expect. Every forward-looking statement carries risks and uncertainties. For a discussion of the major risk factors that might cause our actual results to differ from those in our forward-looking statements, please see today's earnings materials, the safe harbor language found on Slide 2, and our SEC filings; furthermore, when presenting our financial results we rely on several non-GAAP measures. Reconciliations to these measures appear in our supplemental financial information. I'll now hand the call over to George. George?

George Sakellaris

executive
#2

Thanks, Leila. Hello, everyone, and good afternoon. We kicked off 2022 with outstanding quarterly results, since the team delivered against the backlog we had under contract, and we're also securing substantial upcoming work across every one of our business lines. The way our employees carried this out, alongside our customers, is even more remarkable when you consider the supply chain problems and inflationary pressures that have been widely reported throughout our sector. At this point, I'd like to spend a few moments discussing our Southern California Edison project. To begin, let me remind you that this Southern California Edison project is in fact 3 distinct contracts, and we carry them out separately with regard to each one's budget, procured goods, and completion timeline. Next, Ameresco has demonstrated a strong history of finishing some of the toughest energy projects this industry has. The engineering and building work on these battery projects is far less complicated than what we have already accomplished elsewhere, for instance the Savannah River biomass plant and the different green gas plants we've been building and running since 2001. I continue to have confidence that we can hand over these 3 battery projects to our customer in a way that is both satisfactory and profitable. Third, at the time we signed the contract last year, we understood we were working within a difficult COVID setting where supply chain interruptions were possible. And as we do on every project, we remove as much risk as we can from materials and labor prior to signing; still, because of how large the Southern California Edison battery projects are, we went further with precautions: we bargained for contractual safeguards covering possible COVID delays, and we put a suitable contingency into our budget. Regarding the battery supply, we went back to the table and secured firm terms for battery supply, with priority slots at the factory tied to our bid. Most of these customer batteries are already built and paid for, and the first shipment is already underway as of this call. Importantly, the COVID delays we're seeing in China on the remaining batteries have nothing to do with the battery sales, since all of those have already been produced for us. We're actively engaged with Southern California Edison concerning the COVID, the effect of the delays tied to COVID. Our agreement with them provides for financial and schedule relief when force majeure events like COVID occur, and we're currently in talks with Southern California Edison. Taking that into account, along with the contingencies we built into the projects, we don't anticipate any material effect on our margin from these delays. As we said in the April 10 press release and as our quarterly results show, numerous important milestones across the Southern California Edison projects moved forward during the quarter, which pushed Q1 revenue past what we had expected. Key equipment has been obtained, and construction-related work is moving ahead at every site as we get ready for battery delivery. Ameresco keeps working hard with the suppliers and Southern California Edison to prevent or lessen possible delays, which includes coordinating with West Coast ports on faster ship and container processing. Beyond the battery deliveries, for the 3 projects we anticipate finishing every other construction element by the initial August 1 target, which covers installing the batteries now being shipped; we expect as much as 300 megawatts of capacity to come online in August 2022, with the rest online during this year. Although recent developments could move our anticipated core revenue guidance, our confidence in the annual guidance stands. Finally, I want to spend a moment acknowledging Southern California Edison as a genuine partner. Their assistance with the design and execution of the whole project has been tremendous. We thank them, along with the state of California, for their cooperation. Returning to our Q1 highlights. Strong first quarter revenue growth came primarily from our projects business, since we keep executing the Southern California Edison contracts. Just as important, though, we delivered solid growth and profitability throughout every one of our business lines. And we have both excellent quarterly results and continued progress in strengthening our multiyear visibility. We brought 60 megawatts of energy into assets in development, among them a 50-megawatt battery asset and a fresh RNG opportunity, while our O&M business signed more than $100 million in added multiyear contracts. In the quarter, we also brought in more than $400 million of new project awards, as customers keep pursuing solutions for their rising energy costs, resilience requirements and carbon reduction objectives. Among those awards, one I want to call attention to is our already announced partnership with the City of Bristol in the U.K.; in fact, this project ranks as the second largest award in Ameresco's history, trailing only the Southern California Edison contract. When contracted, this distinctive 20-year partnership will cover a complete array of advanced technologies, energy efficiency and renewable solutions spanning project work, O&M and energy asset ownership. The Bristol City Leap project aims at a bold 2030 carbon neutrality goal and is built to draw roughly GBP 1 billion of inward investment that might be split between our partner, Vattenfall, and us. We expect this project to act as a model for other cities, campuses and corporations throughout the U.S. and Europe as they craft their own net 0 and cost savings initiatives. We are especially enthusiastic about comparable opportunities in Europe, because of the high energy prices there, continuing geopolitical risks and the push toward net 0. As 1 of the biggest energy services companies in the U.K., Ameresco is extremely well placed to keep winning and carrying out such transformative projects. I will now hand the call to Doran for some remarks on our financial performance. Doran?

Spencer Hole

executive
#3

Thanks, George, and good afternoon to all of you. If you'd like more financial detail, take a look at the press release and the supplemental slides, which we posted on our website once the market closed today. As George mentioned, the Ameresco team pushed past ongoing supply chain and inflationary headwinds across the industry to turn in outstanding results. And although the growth on the top line was led in a very impressive way by our projects business, it's worth pointing out that each of our 4 lines of business posted solid growth in the quarter. Also important, we saw continued strength in new business wins, and that allowed our overall project backlog to grow at the same time we turned an all-time-high level of backlog into revenue in the quarter. If you add together our total project backlog and the revenue we anticipate later on from our energy assets and O&M operations, that gives us visibility into more than $5.3 billion in revenue. The biggest driver of the notable increase in Q1 total revenue was our projects segment. Some parts of the SoCal Ed project's customized procurement and construction milestones progressed more quickly than anticipated, and that generated higher revenue in the quarter. Adjusted cash from operations declined as a result of the working capital needs tied to the SoCal Ed project. Even so, once the quarter had closed, we gathered $99 million from invoices we'd already issued. Broadly speaking, we anticipated these short-term cash demands right from the start of the contract, and I'm glad to share that during the quarter we revised our senior credit facility to bolster near-term liquidity and provide added financial room to continue expanding the business. Through that amendment, $262 million was added, lifting Ameresco's credit facility to $495 million in total. As has been the pattern in recent quarters, the rise in year-over-year revenue for our energy asset business stemmed from improved results at operating assets we already had, additional new assets coming online, and higher RIN prices. Despite the dip in total gross margins tied to the SoCal Ed project, we achieved strong adjusted EBITDA growth compared to last year. This contract perfectly demonstrates how powerful our operating leverage can be—it shows we're able to grow gross profit dollars while keeping direct incremental operating expenses flat. Moving on to our project backlog: we're pleased to report it reached a record high of $3.1 billion, which is a 1% increase from the prior quarter and a 34% jump from the same time last year. Both customer interest and bidding activity are robust, and we're actively pursuing and securing numerous large, complex projects—including the Bristol City collaboration in the U.K. that we announced recently. In the course of the quarter, 10 megawatts' worth of assets were brought online by us, and at the same time we replenished the pipeline of projects under development, which stands at 464 megawatts as of now. A few remarks would be worthwhile regarding the widely discussed problems of supply chains and inflation that are hitting the entire sector, and regarding the way Ameresco has succeeded in getting past a great number of those obstacles. The enormous adaptability designed into how we run our varied operations comes first and matters most. Our investors know that to meet what each individual customer requires, Ameresco draws on the most sophisticated technologies available from every supplier; because of this, our vulnerability to any single maker or type of technology is reduced. Scope tends to be wide for every project we install, involving dozens or perhaps a larger number of separate technologies. That means when one kind of product shows up late, crews can usually keep progressing on the remaining portions of the job. In the same way, since we have active work spread across the entire country, along with Europe and Canada, during each quarter we could shift products and personnel where they were needed most to get the best possible execution efficiency. Beyond that, our agreements typically include force majeure-style safeguards whenever we run into interruptions such as the shipping hold-ups triggered by COVID-related closures in Shanghai. Ameresco takes a proactive stance, locking in and contracting a substantial share of the products and labor a project will require long before it transitions from an award into a contract, which helps us reduce unexpected cost overruns. We further take advantage of our size and balance sheet to buy critical components for our projects and assets in volume. As one illustration, Ameresco made proactive purchases of a big quantity of solar panels during earlier years, and in the U.S. we continue to hold a stock of those panels to cover our near-term requirements. Before I wrap up, I want to remind everyone that somewhere between 60% and 70% of our EBITDA usually comes from business lines with contracted recurring revenue, and that really demonstrates the resiliency we've built into our business model. George brought this up earlier, and I'll repeat it: COVID-related restrictions in China have created delays in getting some batteries delivered to the SoCal Ed sites. I want to be very clear about this — this is strictly a timing issue. When it comes to force majeure situations such as COVID, we have contractual protections in place, and we believe they apply here. One more thing worth noting: even though raw material prices for battery cells have gone up broadly across the market recently, that has not changed the battery pricing for the SoCal Ed project. To reiterate, we don't anticipate these projects will meaningfully impact our margins. So even though we're definitely seeing and dealing with certain of these worldwide challenges, the varied business structure we've created, the procedures we've put in place, and our exceptional group of experts have all contributed to keeping the consequences for the company's performance in check. That's why I'm pleased to restate our full-year 2022 guidance and to provide our latest view on how the quarters will play out from here. For Q2, we're now looking at revenue roughly 10% to 15% above Q1, while gross margins should remain around 14%. We're anticipating that revenue in the third quarter will come in a bit above what we see for the fourth quarter, and for each of those two periods, gross margins should land right around 18%. At this point, I'll hand things back to George so he can wrap us up.

George Sakellaris

executive
#4

Thanks, Doran. Before we wrap up, I'd like once more to pause and express appreciation to everyone at Ameresco for how committed they are and how well they deliver. We'd also like to acknowledge the continued backing we receive from our clients and from those who hold our shares over the long term. During our Investor Day held not long ago, as we talked about then, we keep gaining from a sizable market opportunity that is only expanding. When you pair our collection of creative offerings with the know-how we bring on both the technical and financial sides, Ameresco stands out as the partner of choice for advanced clean tech solutions that are the most intricate and wide-ranging. Operator, at this point I'd like to turn the call over for questions.

Joseph Osha

analyst
#5

I'd like to ask about something in your press release — that sentence mentioning that talks with SCE are ongoing. As far as these force majeure matters go, when do you think we'll have some clarity on where SCE stands?

George Sakellaris

executive
#6

Honestly, pinpointing exactly when that situation will be fully resolved is quite difficult. That said, discussions with them are happening. Our belief is that we're dealing with a COVID situation, and the contract does allow for release; if you asked me to give my best guess, I'd say it will most likely be during the third quarter that we find out. We have a clear indication of where we send.

Noah Kaye

analyst
#7

I've got 1 question about the SCE contract and then 1 that isn't. It's basically about the ins and outs of the guidance. With a portion of the revenue tied to the battery storage project moving to 2H, and the gross margin guidance staying at 14%, is there anything else we should be thinking about for the second quarter regarding mix, other revenue streams starting up, or seasonality?

Mark Chiplock

executive
#8

Noah, it's Mark. No, I don't believe there is. Q2 is still going to be — the SoCal Ed project will still have a major effect, but beyond that, there's nothing significant that would move the margins. That's why we felt fairly confident putting that guidance back out there.

Stephen Gengaro

analyst
#9

Thank you. Hello, everyone. I know you touched on this during your prepared remarks, but I'd like to hear a bit more detail so we can better grasp the City of Bristol contract and agreement, and how that partnership is likely to unfold. Also, does it show up in backlog? If it does, how much is it right now?

George Sakellaris

executive
#10

Sure. Roughly 50% of the awards we referenced in our press release and our scripts stem from that contract. It's essentially a concession agreement, with Vattenfall as our partners. They are extremely knowledgeable — they bring strong expertise when it comes to the steam distribution system; so most likely a significant portion of the work will flow through them. As for the projects we've identified so far, which we reported as awards, those are ones we pinpointed or coordinated with them, confirming they'll be completed — and that's the effort we'd be carrying out in connection with what we reported. We also have essentially a plan spanning 10 years to bring them to carbon neutrality.

Eric Stine

analyst
#11

Staying on the City of Bristol topic — I'm just wondering whether you'd say that was a win against competition. And then, when you consider the possibility of this spreading into other parts of Europe, maybe you could share your thoughts on what that pipeline could look like?

George Sakellaris

executive
#12

Sure. Sure. That was an extremely competitive contest — 2 years of work went into it. Their work in bringing on consultants and assessing all the proposals they received was outstanding. The fact that we've built Ameresco up to the point where, in the U.K., we're counted among the leading energy services companies — depending on which analysis you consult, we're ranked number 1 or 2 or 3 — gave us an enormous boost, along with having grown the company so it can deliver what I'd call a holistic approach to the specific solutions, whether that's for a City, a university, or one particular industrial customer: not just energy efficiency, but all the renewables tied to today's advanced technologies. That combination really helped us land this project. As I mentioned in my commentary, I believe what's happening in the industry is only getting started. My view is this becomes a model for other major cities and towns. And here's something worth noting: once we won, we brought it up with a couple of mayors in the United States; they told us they love the concept; but institutional momentum among those folks takes time to build. Some time will be needed, yet ultimately it's going to happen. Over in Europe, given where energy prices stand at the moment, I'm not sure the shape would be identical, but you'll see additional projects emerge from Europe. And that region is getting a good amount of our attention.

Greg Wasikowski

analyst
#13

I had some concern here — could you break down those 300 megawatts that are supposed to be operational in August? Will that be a single complete site, or more like partial completion across all 3?

George Sakellaris

executive
#14

Ultimately, it comes down to what the customer prefers; and we have been collaborating very, very closely with Southern California. In fact, we already addressed that, and they have not yet settled on precisely how they will distribute the specific container for the battery storage, which sites; but as I noted in my remarks, every site will be prepared to accept whatever quantity of batteries we have on hand.

Sam Kusswurm

analyst
#15

Sam Kusswurm here, sitting in for Tim. Given that component parts are getting more expensive across numerous projects — take batteries or solar panels, for example — I wanted to ask whether you could share your thoughts on just how price-sensitive your customers tend to be. For most of the projects you handle, is the essential nature of the work such that buyers are ready to bite the bullet? Or might they instead look at pushing projects out to a later date?

Spencer Hole

executive
#16

Absolutely. That's one I'll field, Sam. I'd be lying if I said customers aren't sensitive to pricing — those without a pressing timeline might move projects along at a slower pace. That said, broadly, our business centers on public procurements, where a substantial time component is baked into both the award and the contracting stages; and as I mentioned, our habit is to remove risk prior to signing — prior to putting pen to a contract. So as that contract date draws near, we collaborate with our customers so they fully grasp how the pricing is shaping up, and I believe that holds true equally in the project side of the business and in the energy asset side. With energy prices climbing the way they are, naturally you'd expect there to be several revisions to those pro formas as the contract gets closer. So we feel confident in our rhythm for managing the price increases you brought up.

Chris Souther

analyst
#17

Let me ask a bit more about SCE. If we suppose they didn't raise any objection regarding force majeure, could you help us understand what schedule you would have to meet so that penalties on the project are avoided? What would that look like? And I'm assuming — is it fair to assume that the gross margin profile you're reiterating contains no penalties tied to 1 out of the 3 projects not being completed? Is that a reasonable way to view it at this point? And — and then, as a follow-up to that, given the delay here, are you noticing any slowing in your pipeline of new opportunities, or are customers fairly understanding that this situation is beyond your control?

Spencer Hole

executive
#18

So let me speak to SCE first. Beyond what's in the press release and what's in the prepared remarks, I don't believe we can offer any additional details; so I think that's where we'll have to leave it. As for slowdowns, and I'm certain George will say the same, we aren't seeing anything of that kind.

George Sakellaris

executive
#19

That's the reason we were after a battery asset of 50 megawatts. Plus, we've got a number of additional ones lined up. It's worth pointing out that up until the close of March, when <<inaudible>> sent us word that they'd be late with the batteries, we were running ahead of plan on those specific Southern California projects. So, as we've said, we'll stay on schedule, except that certain batteries won't be in place.

Chip Moore

analyst
#20

To start, I’d say the execution here was genuinely impressive, especially given how tough conditions are. Could you give us an update on where things stand with the RNG development pipeline, and maybe where those projects are now? I believe one of them is moving past development megawatts?

George Sakellaris

executive
#21

As we’ve said previously, by the time this year ends, 3 RNG plants will be mechanically complete. Then, based on how our business plan is currently structured, we’d expect 5 to 6 each year after that, as things look today. That said, we intend to push hard to grow that capacity over time, because, as some of our other remarks have shown, we currently have roughly 18 of these in the development asset pipeline.

Ben Kallo

analyst
#22

I have two brief items. First, regarding Europe. George, you mentioned expanding operations over there. I'm aware you run facilities in the U.K., yet when it comes to the Continent, how can we feel confident that your team can grow at scale and replicate all the positive outcomes you deliver back here in America? Then, for my second item, aside from batteries — I caught your remark that you're at ease with that — what's the story on emerging technologies, possibly fuel cells, or whatever else deserves our attention?

George Sakellaris

executive
#23

Sure. To address your initial item about Europe. My view is we're in a really, really solid position, with scale established in no fewer than 3 nations, whose names I'd rather hold back for now, and those are precisely the markets we'd go after. On top of that, we're pursuing a few possible buyouts, modest in size. Also, we'll lean heavily on our regional allies over there. Take Vattenfall — the firm we partnered with; it's a superb, superb organization, and their strengths fit beautifully alongside our own efforts. There are also one or two additional markets where things aren't ready for us to make an announcement, but we've aligned with a few more businesses; my expectation is you'll notice developments surfacing related to that.

Pavel Molchanov

analyst
#24

Regarding M&A, suppose certain U.S. solar developers are struggling due to AD/CVD and a shortage of modules. From an acquisitions standpoint, would you consider those opportunities?

George Sakellaris

executive
#25

Absolutely, without a doubt. I believe I've addressed this previously. Several months back—or, shall we say, 1 year ago—what several of those folks sought was extremely steep pricing, which is why we held off. I consistently advise our team, let's be patient; pricing could shift and decline. We do have some—so yes, we're evaluating a few, absolutely; and Doran isn't permitting much, correct, perhaps you could grant him additional time.

Spencer Hole

executive
#26

Yes, Pavel, on the whole, when it comes to M&A, we tend to look for chances wherever they arise, whether that's within solar or beyond it. And like George said, should pricing or valuations come down as a result of this investigation, then perhaps a few of those — perhaps a few of those opportunities would look more appealing to us.

Luke Tilkens

analyst
#27

Luke Tilkens here, sitting in for Kashi. We'd like to ask about how you source solar panels, plus whatever insight you can share regarding supply and what prices look like right now in the market?

Spencer Hole

executive
#28

Sure — for competitive reasons, I believe we're limited in how deeply we can discuss supply and pricing. Naturally, our tendency is to concentrate on suppliers we view as extremely dependable and top-tier in quality. Regarding procuring modules, like I said during my prepared remarks, we brought in certain inventory during earlier years; we keep pushing to get through it, and that benefit is on our side, I suppose, along with the reality that Ameresco isn't exclusively a solar business. So the effect on us is not what it could be for some rivals operating in that arena.

Anya Shelekhin

analyst
#29

Anya here, filling in for Julien. I wanted to ask — could you give us an update on the RNG hedging strategy? What are your expectations for D3 RIN prices, if you're able to discuss that, perhaps over the coming year or so?

George Sakellaris

executive
#30

We're going to place 3 plants since August mechanical complete this year, and then 5 to 6 thereafter.

Spencer Hole

executive
#31

Broadly, the way we've described before, roughly half the output from these projects gets contracted once they come online, and then throughout the year we hedge the rest of the RIN and LCFS credits those projects produce. We keep watching where RIN prices are at all times, and depending on RIN pricing we treat that somewhat dynamically across the year. I don't believe we'd want to sit here and offer any forecasts about where we think that's headed, other than to say that as we assess projects and as we're building them out, we adopt fairly conservative assumptions on RIN pricing — both for setting our 2022 guidance, for instance, and for the target returns a given project would need to hit when we look at risk-adjusted returns. We lean conservative. That's really all I can offer on that.

Joseph Osha

analyst
#32

I'd like to dig a bit into how you set sell pricing and how you think about it in relation to your customers. At this stage, can you put together an agreement that lets you, for instance, hand along any swings in something like lithium carbonate pricing or cobalt pricing? What's your approach to shielding yourself from the ups and downs in the inputs for those products?

Spencer Hole

executive
#33

Joe, my sense is that we've got flexibility in how we structure deals with our buyers. That's a risk our buyers want to take on, since they figure it might move in a direction that benefits them, and we're open to that kind of arrangement. For reasons of competition, I probably shouldn't get into precisely what we do or how much falls under each model. What I can say is that we — as with any kind of project, we usually negotiate those prices ahead of time and secure them prior to signing a customer contract, so we aren't exposed to price swings, particularly for raw materials and batteries.

George Sakellaris

executive
#34

Also, we need to keep in mind what our contracts offer in terms of value, and that's already shown up in a few cases, since energy prices are climbing at a much quicker pace than materials — a lot of the projects, in fact — one of them. As an illustration, with the contract group, after we entered the updated energy prices against the project costs, those costs are rising as well. Yet the simple payback came in below what it had been previously. The same logic applies to interest rates, which rise. However, when energy prices increase more rapidly, the project performs considerably better.

Stephen Gengaro

analyst
#35

Just a quick follow-up there. I found myself considering how this looks over a longer horizon — specifically the Bristol project — and when the income statement starts reflecting it. Does it ramp up? What's the right way to frame that effect?

George Sakellaris

executive
#36

For that particular one, it begins appearing next year. My expectation is that nothing will show up in this year's figures. Next year, though, without question, we will see something. In fact, that roughly $200 million — give or take half of what has been booked so far — I believe spans more than 4 or 5 years. That said, it covers every project we've identified up to now, since the following phase involves actually securing the contract, after which we run more detailed energy orientations and carry out development of the plan. At that point, all of those figures along with the schedule get fine-tuned, which means we can offer you improved color before this year ends regarding how that project shapes up. Even so, it represents over 1 billion pounds in possible project value, if you want to call it that. What portion of it gets funded through a third party? What portion do they fund themselves? On the first page, incidentally, the funding already comes from a third party and they have already identified it.

Greg Wasikowski

analyst
#37

Since the SoCal Edison delay came after the Analyst Day, does your view of the $300 million 2024 adjusted EBITDA guidance still hold the same way? And might you say approximately what portion of that $300 million is expected to come from larger-scale, more traditional EPC-type contracts, such as the SoCal Edison project?

George Sakellaris

executive
#38

Yes, the $300 million — there's no doubt in my mind — we remain on track, and regarding where we stand, we feel quite good. This year the SoCal project does contribute, but as far as that specific target goes, that's essentially all, from my perspective. When it comes to how much is generated by projects versus how much is generated by the asset business or the recurring line of business, here's what I'd say. Somewhere between 60% and 70%, and at times perhaps 75%, will be produced by the asset business or the recurring business lines, while the remainder will come from projects. Conversely, our visibility on the projects is excellent, since today we hold the $3 billion total backlog. And as I noted, and as Doran noted in his remarks, the level of activity is increasing; and the fact that we've only just started having face-to-face meetings is benefiting the company. And naturally, with energy prices as they are and continuing to rise, that is extremely, extremely favorable for our business.

Operator

operator
#39

Appreciate it. That brings our Q&A portion to a close. Thanks for joining us on today's call. You're free to hang up at this point. Have a wonderful day, everybody.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Ameresco, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Ameresco, Inc. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ameresco, Inc. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.