Thanks, Catherine, and hello to everyone this afternoon. We’re glad you could be with us on today’s call. With me are George Sakellaris, who serves as Ameresco’s Chairman, President, and Chief Executive Officer; Doran Hole, our Executive Vice President and Chief Financial Officer; and Mark Chiplock, Senior Vice President and Chief Accounting Officer. Before handing things over to George, I want to offer a quick note about forward-looking remarks. In today’s earnings materials, you’ll find forward-looking statements, which include our expectations. Risks and uncertainties apply to all such statements. For a discussion of the major risk factors that might cause our actual results to differ from what those forward-looking statements indicate, please see today’s earnings materials, the Safe Harbor language on slide two, and our SEC filings. We also present several non-GAAP measures when reporting our financial results. Reconciliations to those measures appear in our supplemental financial information. At this point, I’ll pass the call to George. George?

George Sakellaris

executive
#2

Thank you, Leila, and hello everyone this afternoon. We delivered another solid quarter, and I'm particularly encouraged that our favorable trajectory continued, with significant growth in our project backlog and assets under development, which supports the 2023 outlook we provided as well as our longer-term financial objectives. Second-quarter revenue significantly exceeded our guidance, and adjusted EBITDA finished at the top of our range. Notably, we ended the quarter with an all-time high total project backlog of $3.2 billion, up 9% from the prior quarter. During the quarter we secured $493 million in new project awards, bringing total additions for the first six months of the year to nearly $1 billion. That increase is especially notable because our backlog has now surpassed the level it hit back at the close of 2021, when we signed the SCE battery contracts worth nearly $1 billion. On top of that, during Q2 we added 113 megawatts of assets in development — no other quarter in the company's history has seen a larger addition. That translates to a strong 26% quarter-over-quarter rise in assets in development, and as these get up and running, we anticipate they will generate meaningful EBITDA contributions across many years. All told, the projects and assets we've won continue to extend how far out we can see profitable revenues, and they strengthen how confident we are in Ameresco's growth over the long term. Big wins on large-scale battery energy storage contracts drove a significant share of the growth this quarter, in terms of both our project backlog and assets in development. If you look at our supplemental slides, you'll notice that battery assets represent 41% of our assets in development, compared with under 5% for our current operating assets. When it comes to replacing electricity generated from fossil fuels, large battery storage systems are essential, and they're also crucial for storing renewable energy when production peaks. Above all, batteries make the grid much more resilient and flexible, delivering power rapidly when it's required due to heavy demand, weather-related occurrences and various other unplanned outages. A number of forces are behind the enormous expansion we're seeing in battery storage. The widespread commercialization of battery technology is one of them, and it has played a part in bringing costs down. Within the U.S., a major catalyst for swift uptake of this technology has been the Inflation Reduction Act. Under the rules that applied prior to the IRA's passage, a federal tax credit for battery storage was offered only in cases where the system was combined with a renewable generation technology like solar or wind. Today, thanks to the IRA — along with comparable incentives in Canada — standalone battery storage systems are eligible for an investment tax credit of 30% or more. That makes these systems considerably more valuable from our customers' standpoint, which in turn is producing higher levels of adoption. The ITC certainly helps in North America, but on top of that, we're putting forward and securing independent battery ventures in Europe, where demand is every bit as strong. Thanks to how much technical know-how we hold, our engineering capabilities, and the ties we've built with suppliers, Ameresco is now viewed as a leading player when it comes to deploying battery systems. It began with those game-changing Southern California Edison projects, and continued through the wins we've more recently shared involving United Power, Middle River Power, and the Atura Power Joint Venture — and with that expertise plus a business model that flexes financially, we're able to chase battery project and asset possibilities well into the future. This quarter brought another highly promising long-term milestone for Ameresco: the EPA's decision on Renewable Fuel Standard targets covering 2023 through 2025. The EPA significantly increased the required volumes for RNG in that final rule. This immediately impacted D3 RIN pricing tied to the RNG our operations produce, with values quickly rising from around two dollars to over three dollars. Equally significant, the agency changed its method for determining the industry-wide growth rate for RNG, potentially allowing volume computations to extend beyond the three-year span covered by this decision. We felt very positive about this ruling, as it enhances our ability to see further ahead in this key business segment. Additionally, we anticipate upcoming EPA direction regarding eRINs, which may also provide favorable momentum for our current projects converting biogas into electricity. Prior to passing things over to Doran, I'd like to call attention to something we've just released: our ESG report for the third year running, which carries the title "Doing Well by Doing Good — Transformation and Purpose". There's real pride on our side in how much good our business has done for the planet worldwide, because when you add up our renewable energy assets alongside our customer projects, the total carbon emission reduction they've achieved comes to more than 95 million metric tons ever since our 2010 IPO. As our assets and projects continue to expand, that figure — an important one — will only climb further. And going forward, we've established an objective of reaching net zero across our internal operations, covering Scope 1 and Scope 2 emissions, no later than 2040. To help reach that goal, we've committed to setting targets for cutting emissions via the Science-Based Targets initiative by 2025. At this point, I'll hand things over to Doran, who will discuss how we performed financially and what we expect ahead. Doran?

Doran Hole

executive
#3

Thanks, George, and good afternoon, everybody. If you want more detailed financials, take a look at the press release and the supplemental slides we put up on our site once trading wrapped up today. Revenue for the second quarter came in at $327.1 million in total, which is roughly $37 million higher than the midpoint of the guidance we gave, thanks to quicker-than-anticipated progress on a few projects. Energy Asset revenue climbed 17%, mostly reflecting a larger count of assets in operation compared with a year earlier, and our O&M business turned in yet another strong quarter, growing 9%. On top of that, our other business line rose 4%, fueled by stronger demand across our utility, SaaS, and consulting operations. Gross margin widened to 17.9%, since the lower-margin SoCal Ed contract made up a smaller share of overall revenue. Adjusted EBITDA for the quarter reached $37.4 million, landing at the upper end of the range we had guided to. We closed out the quarter holding about $49 million in unrestricted cash, all while carrying out a record $285 million of financing activity. As George noted, we finished the quarter with project backlog hitting an all-time high of $3.2 billion, up 9% from the prior quarter, after booking close to $0.5 billion in new project awards over the period. Our energy asset visibility stands at roughly $2.3 billion — an operating asset revenue backlog measure that captures contracted revenue along with a conservative projection of lifetime uncontracted RNG revenues. Taken alongside our O&M backlog, these figures provide Ameresco with line of sight to more than $6.5 billion in future revenue. That measure leaves out any contribution from the 545 megawatts of energy assets currently in development and construction. As George pointed out, we set a record by adding 113 megawatts in the quarter, and since our assets in development and construction still far exceed the energy assets we currently operate, we have extra visibility into our growth over the long term. How long it takes to bring these assets online ranges from less than a year for smaller, simpler ones to more than four years for complex assets like RNG facilities. Those listening will recall that an asset must satisfy very stringent criteria before it can be counted in this metric — far more stringent than what most companies would call a pipeline. Over time, around 90%+ of our energy assets in development and construction get placed into service and are either kept on our balance sheet as an operating asset, mostly through non-recourse financing, or monetized via a sale to a third party; given the shifting interest rate landscape, we've been getting a lot of questions about how rising rates affect our Energy Asset business and what we expect for how that business may develop. For those of you who have been following us, a risk-adjusted levered internal rate of return serves as a crucial yardstick in our assessment of energy asset possibilities. Our goal remains a mid-teens risk-adjusted levered IRR across our assets. Achieving this elevated return in solar and batteries has come from handpicking assets tied to returning or first-time clients who appreciate our adaptable financing structures, in-house integration, and engineering know-how — meaning price alone isn't always what we compete on. Alternatively, it comes from building bigger, more technically demanding assets like RNG, where Ameresco's more than 20 years of experience provides a major edge in securing and delivering those opportunities. We're seeing a substantial uptick in asset development prospects, some of which might fall short of our risk-adjusted return thresholds or add little to net income. Even so, they remain top-tier assets, so we can create value for Ameresco by building them and then selling to third parties whose yield requirements are lower. When that happens, we redeploy capital and turn a profit via an EPC contract, with those assets becoming projects at the point of sale. We'll also pursue extra value by pairing those converted projects with an O&M agreement. While keeping our long-standing mid-teens IRR hurdle rates, we see plenty of room to keep expanding owned assets by roughly 20% annually on average — a growth goal we've mentioned previously — while selectively cashing in on origination work through other avenues. This approach isn't a departure for Ameresco, though in today's conditions it could take on greater significance. Ultimately, we think our adaptable corporate structure spanning both Project and Asset business lines lets us keep capitalizing on renewables' swift expansion, either by creating assets that still meet the mid-teens IRR target noted before or by developing and selling them as profitable projects. Turning back to operating assets: these are supported by fixed or hedged debt, so climbing interest rates exert minimal to no real effect on that segment. Consequently, even when rates are rising, Ameresco's nimble business model and our opportunistic stance toward the asset side ought to let us keep gaining from enormous appetite for renewable energy solutions. We're glad to restate our 2023 guidance, calling for adjusted EBITDA growth of 5% at the midpoint — notable given the tough year-over-year comparisons stemming from winding down and finishing the sizable SCE projects. We've also laid out a more granular mix of anticipated Q3 and Q4 results in the press release. Our expectation stays at bringing 80 to 100 megawatts of energy assets online during 2023, among them two RNG plants. A third plant, which we'd initially expected to bring online in 2023, should reach mechanical completion by year-end and be fully commissioned in Q1 2024. We've got a number of other RNG projects that are pretty far along in development and being built, and our expectation remains that 4 or 5 of them will start operating in 2024. At this point, I'll hand things back to George so he can wrap up.

George Sakellaris

executive
#4

Thanks, Doran. During this call we've gone over the details, and we've kept widening our long-range view toward major growth, finishing the second quarter with revenue visibility above $6.7 billion along with 545 megawatts of assets under development and construction. What we achieved in the first half, plus our backlog and the pipeline from business development, backs up the confidence we hold in our long-term growth targets. It's a thrilling moment to be a top clean tech solution provider, and I'm certain we possess the technical talent and business acumen needed to support the energy transition and drive meaningful change. To wrap up, I want to express thanks once more to our employees, customers, and stockholders for their continued support. Operator, let's open the call to questions.

Noah Kaye

analyst
#5

Hello, and thanks for fielding the questions. I also appreciate the detailed back-half outlook you provided. This marks, I believe, a second straight quarter where revenue has converted more quickly than anticipated, so for my first question, I'm simply attempting to square that outlook with the full year. If you just average the midpoints for 3Q and 4Q, that would put you at the top of the full-year revenue range. Essentially, you're lifting the bottom end of the full-year revenue guidance without saying so. Is there a detail I've overlooked, or a step I'm getting wrong? Or is my read accurate?

Mark Chiplock

executive
#6

Yes. Hey Noah, this is Mark Chiplock — doing well, thanks. I wouldn't say we're — our intention wasn't to revise the overall guidance. What I'd say is that topline results have been somewhat stronger because that acceleration has shown up, yet we're simultaneously seeing movement in certain awards and in when those get signed into contracts. So yes, it isn't an exact science. We're doing our best to assemble these ranges. Our expectation remains that we land inside the original ranges. Might we outperform? Absolutely; however, we're relying on the clearest visibility available to us, especially regarding the project side, to inform Q3 and Q4. The encouraging part about the second half, given that visibility, is that more than 90% of that project revenue stems from work already awarded and contracted. So once more, visibility is solid. As we've noted previously, timing tends to be the wildcard that can move things on a quarter-to-quarter basis.

Noah Kaye

analyst
#7

Right. I'd like to ask about how project margins looked during the quarter. They came in somewhat soft. Was it purely a mix issue? And related to that, what's behind the better operating leverage expected in the back half, and the stronger operating leverage in the back half on a seasonal basis — I mean specifically an improvement in operating leverage that's better than what you'd normally see, which is what's reflected in the guidance.

Mark Chiplock

executive
#8

Yeah, I'd say when you look at those net income and EBITDA margins, the issue is that, again, going back to last year, you clearly had more revenue and more net income coming from the SCE projects; we report by line of business, and keep in mind, corporate expenses get allocated according to revenue share. So our project margins compared to a year ago, they were going to come down as a result of how those corporate expenses get allocated — basically a big fixed cost allocation spread across revenue that was significantly lower than a year ago. Certain projects did have some cost overruns this quarter, which hurt our gross margins somewhat, but we are — we'd anticipate margins will keep expanding in the year's second half, especially once SCE cycles out, and we'd expect to keep seeing that trend of growing gross margins through the back half of the year.

Noah Kaye

analyst
#9

Great. Could I slip in one final question? That RFS ruling is clearly a good development for RNG assets, and I'm wondering how much the elevated RINs we're currently observing played into your decision to reaffirm guidance. Also, there was no effect — perhaps you could clarify whether that stems from hedging or simply from a cautious stance in your second-half assumptions?

Mark Chiplock

executive
#10

Yeah, absolutely, we're happy to watch RIN prices climb. It does have a bit of an effect in — during the latter portion of our figures, though I wouldn't describe it as significant or material. What I mean is, we've consistently aimed to keep our assumptions aligned with where the market is headed and where we expect it to head. So although there's a modest gain, nothing there would — nothing that would have led us to feel we should revise the guidance we gave.

George Sakellaris

executive
#11

Also keep in mind that, at this moment, we're actually sitting at 55% hedged rather than waiting until the quarter wraps up. That leaves 45% of upcoming output able to pick up some advantage from stronger pricing; however, for the volumes we plug into our projection, it's roughly in line with where the market stands at present.

Noah Kaye

analyst
#12

That's quite useful. I appreciate it.

Stephen Gengaro

analyst
#13

Thank you. Hello everyone, good afternoon.

George Sakellaris

executive
#14

Good afternoon, Steve.

Stephen Gengaro

analyst
#15

I've got two questions. First off, regarding the projects, the bidding going on, plus the orders and how the backlog is building — do you have any perspective on what the pricing environment looks like right now? And what should we expect in terms of how that affects project margins down the road?

George Sakellaris

executive
#16

The activity level is extremely strong, and that's the reason our awards and backlog are coming along quite well, which is exactly what we want to see — and it's also why I went on a bit longer during my remarks. Projects really are becoming somewhat bigger. When it comes to margins, for an EPC design-build type of project, as we've mentioned previously, those are below what we get from performance contracts. That said, they actually add more to profitability, because typically we benefit from the leverage within the company. There's another factor that's come into play somewhat, and this explains why OpEx is running a bit higher. Following COVID, we made a decision to drive the organization forward and invest somewhat more in development so we could build a solid pipeline and grab a healthy market share. And I'm pleased to report that proposal activity along with our win rate is extremely strong. So I'd characterize the environment as favorable, including over the last couple of quarters.

Stephen Gengaro

analyst
#17

Great, thank you. And to build on that, is there anything yet regarding orders coming in from Europe? And what's the brief update on how well you're gaining ground over there?

George Sakellaris

executive
#18

Things are going extremely well. Business is strong; it's tough for us to keep pace. That's the reason we're putting in somewhat more money. As a business expands, controlling our OpEx can occasionally prove quite difficult. Yet at the same time, the chances available are huge. The Italian company we bought — we couldn't be happier with how things have worked out. They're performing excellently. Over in Greece, a few projects are finished, and I'd say the odds are quite strong that we'll soon have a presence there. In the UK, once more, several items are in the works that should provide significant help to us; so, the level of business there — and Doran, if you'd like, feel free to add a few comments, since I've been going back and forth. It's — the amount of activity in that market has genuinely caught me off guard in a good way.

Doran Hole

executive
#19

Yeah, the only thing I'd add is that this is happening across every technology. And much of the project side of things, naturally, involves utility-scale EPC opportunities, and as George mentioned, Greece is performing very well for us; over in the UK, we've delivered some excellent wins in advanced technologies, which is letting that business expand past traditional energy efficiency and into advanced technologies, exactly as we've accomplished here in the United States.

Stephen Gengaro

analyst
#20

Great. Thank you for the color gentlemen.

Doran Hole

executive
#21

Yes.

Joseph Osha

analyst
#22

Hi there everybody.

George Sakellaris

executive
#23

Hi.

Joseph Osha

analyst
#24

I've got a few things to ask about the storage segment, which is expanding so strongly. To begin with, I'm curious whether you could spend a moment describing what the experience of managing cell sourcing has been like. I'm aware that SCE provided some lessons, so I'd like to hear how those lessons are shaping the way you run purchasing for all these additional storage products — projects? And then I've got one more question after that.

Doran Hole

executive
#25

Sure, Joe, I'll take the first one. On procurement, we keep adding to the roster of battery suppliers we work with. That market, as you're aware, is still fragmented, which means we have to be extremely careful about which partners we choose, both on the integration side and on the software side. Cells alone aren't the whole picture — it's genuinely all of it. So even though we examined things closely and ran a competitive bidding effort while assembling the SCE project, the schedule pressure meant we selected whoever could hit the delivery date. These days, I'd say it's reasonable to claim we're able to be choosier, and we're conducting competitive processes for pretty much every project George mentioned in his script; we're also making sure our suppliers rise to the occasion regarding price, quality, degradation, whatever you can think of, timing, delivery schedules, all of it. The market has me enthusiastic, since an increasing number of firms are joining the competition. True, battery cell makers are still few in number. Even so, they keep providing cells to a wider variety of companies. And the capabilities that matter — executing, delivering promptly, commissioning projects, the whole thing from start to finish — those aren't limited to the batteries.

Joseph Osha

analyst
#26

Of course. Alright. Given what you just said, I'll take my follow-up in a different direction. So would it be accurate to say that once you bring on board businesses such as STEM or FlexGen or anyone else, locating cells becomes their responsibility, or do you continue to play a part in that sourcing effort? I'm simply trying to get a clear picture of what this looks like at present.

Doran Hole

executive
#27

Yes, we are involved firsthand, to be completely candid. What I mean is that a few of them prefer partnering with particular makers over others, yet a number of them are in fact somewhat more adaptable, as we are, and aim to secure the optimal option for the customers. So we stay deeply engaged in that effort.

Joseph Osha

analyst
#28

Alright, thanks. I'll rejoin the queue.

George Sakellaris

executive
#29

Appreciate it, Joe.

George Gianarikas

analyst
#30

Hi everybody. Afternoon, and I appreciate you taking my question. What I want to ask about is the emphasis you place on generating free cash flow. I realize your guidance only covers 2024 EBITDA, though there was plenty of conversation regarding possibly divesting assets or leaning somewhat more toward projects. What I'm wondering is whether that turns into a bigger priority as we head into 2025 and 2026, along with free cash flow?

Doran Hole

executive
#31

George, let me give that a shot. My immediate reaction, when you look beyond 2024 toward 2025, is that we don't have some prescribed strategic step aimed at shifting toward project revenue and cash flow. We keep that flexibility when we engage with customers; therefore, should customers wind up wanting more project business, that's where our company will head to serve the customer. Should they want more asset business, that's where we'll head. Like we mentioned, on the Asset side, there's somewhat of a regulator for us, letting us truly monetize the development pipeline and turn those into projects as required, depending on either return criteria or the risk adjustments that factor into determining the return of criteria, yet we aren't making a strategic shift toward or away from the project business.

George Sakellaris

executive
#32

No, we're going to keep pushing the project side of things as hard as we can. And I'm not sure whether you caught it, but in today's paper the international energy agency said the cheapest route to net zero is energy efficiency. First, clean fuel means no energy cost; so we'll stay with that. But we aim to capitalize on every part of the clean tech sector, and I believe that's a big help to us. Then regarding the asset, some assets are being sold, and we're quite happy that what we're signing up for far exceeds what we can handle; that's the reason we'll take on certain ones that might not deliver the return we'd want, yet someone else finds them attractive. So we say, fine, we'll flip those over to them. But no, we aren't abandoning the business — in fact, we'll concentrate on it to the greatest extent we can.

George Gianarikas

analyst
#33

Thank you. Then, for a second question, I want to inquire about that RNG facility, which has now shifted into full commissioning status during Q1 of 2024. You repeated the point about the 4 or 5 units scheduled to begin operating in 2024. Do those sit alongside the separate one that has been delayed until the first quarter?

Doran Hole

executive
#34

Please continue. Correct.

George Sakellaris

executive
#35

So, what went wrong with that particular project? Initially, the plan was for certain equipment to be handed over during April, after that it slipped to June, and later it became the end of July, and now we've delivered — it has only just arrived. Because of that, a number of projects shift either because of weather conditions or the timing of deliveries. That is the main chokepoint we're seeing; beyond that, we've encountered issues with transformers, electrical switch gear, and similar items; yet ultimately, what matters is the RNG business itself. We've now spent roughly 20 years involved in it. In my view, the team we've assembled ranks as the strongest in this industry, and while we may fall short in a quarter or two occasionally, on the whole, we'll bring top quality projects in on time.

George Gianarikas

analyst
#36

Thanks.

William Grippin

analyst
#37

Okay, thanks a lot, and good evening. What I wanted to ask first is simply how you're viewing your RIN monetization strategy at this point, now that we've got the final EPA RVO and three years of visibility, and pricing clearly has improved quite a bit. So what's your thinking when it comes to hedging against selling on the open market?

George Sakellaris

executive
#38

The approach we've followed previously — hedging 50% of the output and putting the remainder into the open market — is, I believe, the one we'll stay with. Given that we now can see three years out, we actually feel considerably more confident about that approach. That said, from the start we've always had a very optimistic view of the RNG market, since it isn't only the RINs that carry substantial value. Over the long run, I'd say the voluntary market for renewable natural gas offers us a strong position. By the way, with the 3 to 5-year contracts we've signed covering 50% of the output, we've watched the prices climb. So it wouldn't shock me if, as we build out more and more of these RNG facilities, we end up with less exposure, so to speak, further out. You'd likely see us signing longer-term contracts. That holds so long as the economics support it, and by the way, each year we run an analysis for the Board. Through that analysis we reach a solid determination of what the cost would be to us if we hedged beyond what we've done historically. But look, this is an extremely important piece of our business line, and we devote a great deal of attention to it. We believe we build excellent assets, and we want to get the most value we can out of them.

Doran Hole

executive
#39

Okay, apologies — I just want to address this. If we're looking closely at the period from today through December 31, the way hedging and holding off interact — we're sort of monitoring the marketplace; once that RVO was released, we anticipated what would follow. A large number of participants would be looking to offload. Because of that, we chose not to immediately dump everything we held. We'll keep listening carefully regarding output forecasts and form a view about where the market is headed. We have contacts gathering intelligence across every corner of this sector, so for the remainder of 2023, we'll keep hedging in a flexible, chance-taking manner on those barrels tied to 2023 output; and I realize you haven't been following us for very long. As a rule, we typically cap things below 90% for the year underway, broadly speaking, so there's some room left for swings in output.

William Grippin

analyst
#40

Understood. Now for my second question. Regarding the anticipated earnings increase for the fourth quarter that the guidance implies, that falls beyond the seasonal pattern we've observed across the past several years — might you explain what's driving that? Is it simply projects going live during Q4 that are adding to it?

Mark Chiplock

executive
#41

I'd say a significant portion of the revenue stems from typical seasonality, though we do have somewhat of a change in when awards land; so, as I said earlier, we possess quite strong visibility into revenue arising from our project backlog, spanning both awarded and contracted work; however, I believe part of the timing we're observing that may be shifting certain things from Q3 over to Q4 relates to when we expect some awards to turn into contracts. What matters to keep in mind there, I think, is that we're capitalizing on projects while they're in the awarded stage, and we're capitalizing the development costs tied to those projects. The moment one becomes a contract, revenue jumps right away as those costs get moved into the construction phase and into that cost budget, since our revenue is recognized using percentage of completion. So Q4 appears somewhat heavier than it typically would, and a portion of that comes down to merely shifting a handful of items as contracts get converted. The remainder is simply the visibility we gain from our contracted backlog. Naturally, we still have to execute against it, yet we feel fairly confident given that visibility. Yes.

Kashy Harrison

analyst
#42

Good afternoon, and I appreciate you answering my questions. So perhaps this is simply a continuation of what was just asked. Mark, it seemed as though you were hinting that perhaps the conversion of awarded work was taking somewhat more time than anticipated — could you explain what might be causing that? Then I have another question to ask.

Mark Chiplock

executive
#43

Yeah, that's a fair question, since honestly speaking, what we appear to be experiencing is that our awards are in fact moving through conversion somewhat more quickly, especially when it comes to design build; normally those need somewhere between 12 and 24 months before converting, yet we're actually observing something closer to the faster end. The only issue is a handful of bigger projects that have needed somewhat more time, which we see slipping later; that situation might change and could come back in. Still, when it comes to giving guidance, our approach is to stay somewhat cautious about the timing of those conversions, while at the same time keeping our confidence that we can hit the numbers for the entire year.

Kashy Harrison

analyst
#44

Understood. Thanks. Moving to the RNG side for my follow-up. Could you talk about where things stand with the 4, 5 RNG projects slated to come online in 2024 — how is construction tracking against what was expected? What's the chance of slippage on those 4 or 5 projects? And then, given the RVO ruling, could you share any sensitivities for 2024 tied to higher D3 RIN pricing?

Doran Hole

executive
#45

Let's begin with construction progress — on the development side, honestly we feel quite good about the 4 to 5. As we've mentioned, they sit at fairly late development stages, or they're already being built; so a couple of them give us strong confidence on timing, and the rest are proceeding at the speed we anticipated, correct? So I'd say we feel quite good about that portion. Turning to the RIN and 2024, the key point is we aren't selling our 2024 RINs, correct? We're monitoring where that market stands relative to what we anticipate production will be across the market as a whole. That lands squarely in the category I mentioned earlier — we're keeping our ear to the ground. We'll watch where those figures land regarding supply, what we see finishing in the market versus what doesn't finish, and then we'll hedge as appropriate. Still, I don't believe we're ready to begin giving sensitivities for the whole business, since as you know we're highly diversified. RNG is just one component. I don't think we're ready to start offering sensitivities on RIN prices for 2024.

Kashy Harrison

analyst
#46

All right, I've got nothing further. Appreciate it.

Doran Hole

executive
#47

Thank you, Kashy.

Julien Dumoulin-Smith

analyst
#48

Hi there, good afternoon everyone. We really appreciate you making the time for us. Thanks so much. So, I was hoping to dig into a few points — hello again, folks. I just wanted to highlight a few items; regarding 2023, let's revisit that briefly, if we could. There are a few signals I'm picking up from all of you. To begin, could we discuss SCE and get a handle on just how big the effect really is? There was some discussion in the Edison 10-Q regarding certain time line adjustments. I simply want to confirm our understanding, and that all of you possess what amounts to a distinct, firm perspective regarding the size of that monetary consequence? And then, regarding 2023 as a whole, based on what we're hearing about how 3Q and 4Q are shaping up, which we touched on when this call began, it appears you remain, all things considered, rather at ease with 2023, and the explanation you're not lifting 2023 has more to do with a matter of timing, where certain items might drift into 1Q. Would that be the correct way to read it?

Doran Hole

executive
#49

Julien, I'll begin with SoCal, and then perhaps hand the remaining topic over to Mark. When it comes to SoCal, since that project is more than 95% finished, the monetary consequence tied to the shift in the substantial completion dates isn't something that worries us at all for 2023. Naturally, as you'd imagine, our attention is squarely on wrapping up the projects, and as a result, we have nothing new to share concerning talks over unresolved items with SoCal, though the revenue figures are essentially right at the finish line, and we're currently in the last stages of commissioning for two of the three projects, just as our disclosure noted. Mark, perhaps I'll pass it over to you regarding the — .

Mark Chiplock

executive
#50

Yeah, absolutely. Regarding what you asked — yes, I'd say our visibility into the back half of the year on the revenue side feels quite strong, since a big share of it comes from backlog we've already been awarded and contracted, meaning project backlog. There's still some portion we'd have to, I'd say, book and burn, though that piece is fairly small. And yes, I think the — as we've said, timing can hit the projects business hard, so I think certain awards we expect to sign in Q4, since the schedule definitely shifted. Still, I think as things stand, given what we can see, we're keeping confidence in the — in our initial projections for the year.

Julien Dumoulin-Smith

analyst
#51

Understood. Then regarding 2024 as such — just so I follow — with the mark-to-market bump in RINs pricing, and so on, and the open position you all mentioned earlier, if I recall, 45% — why take a less positive view of 2024? Once more, I recognize timing problems clearly appear to be a piece of this. But could you walk through the puts and takes a bit further regarding why it wouldn't be more positive on the whole? Or is this simply you all being conservative, so to speak, in certain ways?

Doran Hole

executive
#52

Julien, that's precisely it. Full year 2024 guidance is going to arrive once we put out Q4 at the start of the year. That's — and we will — right then, we'd be glad to discuss it further.

Julien Dumoulin-Smith

analyst
#53

Understood. However, regarding that $300 million, there isn't any other offsetting or mitigating item, nor a starting point assumption, that we ought to know about, correct? Obviously, all of us see this elevated price. My only aim is to confirm we aren't overlooking anything here. On a dollar move, it appears to come to $15 million in EBITDA.

Doran Hole

executive
#54

Right. Julien, I appreciate how you worked the numbers. Concerning the $300 million, we truly will not provide any comment. That figure has been public for quite a while. My sense is we'll set it aside and take it up early next year, once the full year has been reported.

Julien Dumoulin-Smith

analyst
#55

Okay, that's reasonable. Alright, thanks so much, everyone. I appreciate that.

Tim Mulrooney

analyst
#56

Yeah, thank you. By now, almost everything I wanted to ask has been covered. Let me just take a broader view for a moment. I think all of us have noticed a big jump in the dollar amount of the work you're competing for and securing lately. Could you give us some color on whether that reflects more big projects coming to market, or whether Ameresco is deliberately going after bigger jobs that maybe you wouldn't have pursued before?

George Sakellaris

executive
#57

A bit of both, I'd say, but the typical project size we're putting forward today is nearly — tell me if I've got this wrong — 50% larger? Right. And that's out of necessity, since these efforts have grown more intricate and now bring in not just energy efficiency, but also solar, battery storage, microgrids, and similar things — they keep getting bigger; and naturally, I'd say the Southern California projects have given us a big lift; so, as you noticed, we landed three solid wins in battery storage, and those are quite sizable projects.

Tim Mulrooney

analyst
#58

All right. Thank you, George. As a follow-up, switching topics, could you share your view on where the M&A landscape stands, what your pipeline looks like, and how hungry you are at this moment in mid-2023?

George Sakellaris

executive
#59

Our appetite remains strong; we keep evaluating opportunities. At present we're examining Europe, naturally, somewhat more aggressively, yet the United States too. However, they must be accretive, and we stay disciplined. Conversely, to expand your footprint, particularly when going abroad, it's far simpler to bring on 30, 50 or 75 or 100 people one at a time. So, given what we paid, it's worth doing it.

Tim Mulrooney

analyst
#60

Understood. Many thanks.

Pavel Molchanov

analyst
#61

I appreciate you fielding this. I'd like to ask about CapEx. Taking your first-half CapEx and scaling it to a full year, the total would land considerably above $500 million. Should we approach the arithmetic that way? Or did the CapEx come in somewhat heavily weighted toward the early part of the year?

Doran Hole

executive
#62

Yeah, Pavel, I'd say it's reasonable to describe it as having been quite significantly weighted to the front, given the RNG plants we have arriving during this year and also the one set to reach mechanical completion before the year is out, with sizable portions of CapEx already disbursed on those. And as you'd expect, we've secured an enormous amount of non-recourse financing, which we also covered in the script. So my view is it isn't — a straight fifty-fifty split across the two halves of the year.

George Sakellaris

executive
#63

Not really, since when these bigger projects, RNG and the rest, actually got rolled out made the difference compared with how things stood previously. To secure the equipment when you need it, you end up having to pay deposits far sooner than would normally be the case for transformers and every other kind of equipment requiring those advance payments. That is the reason they lean somewhat toward the first half of the year.

Pavel Molchanov

analyst
#64

All right. Now let's discuss Europe. Only a bit more than 12 months have passed since you announced that Bristol initiative, and if I'm not mistaken, purely in nominal dollar figures, it stands as the biggest undertaking Ameresco has ever taken on. Could you give us an update on how that first year has gone?

George Sakellaris

executive
#65

We're actively working on those. I'd say their approval of projects has been somewhat slower than we expected, though you'll notice a significant acceleration in the coming year, plus in Q4 of the current year and the following year. Even so, we've pinpointed at minimum — I believe we brought this up earlier — $400 million worth of projects for which we've also secured the related financing. That said, when you're working with the government, things move slowly. On the flip side, they're extremely pleased with our work. They've connected us with a number of additional UK cities that may want to pursue something comparable.

Pavel Molchanov

analyst
#66

All right, thank you very much.

Chris Souther

analyst
#67

Hey everyone. I wanted to ask about the United Power and Middle River Power <<inaudible>> wins — did those show up in the project-win awards for the quarter? I couldn't tell whether that press release came out in July, and I just wanted to make clear that those were projects rather than assets in development wins, correct?

Doran Hole

executive
#68

Sorry, Chris — did you say United Power and Middle River?

Chris Souther

analyst
#69

Yes, Middle River.

Doran Hole

executive
#70

All right. So United Power is in fact an asset — that is right; accordingly, it shows up within the battery section, which you can check in the supplemental slides. After that, Middle River is a project.

Chris Souther

analyst
#71

Understood. All right.

Doran Hole

executive
#72

That item, then, would sit in the backlog of projects.

Chris Souther

analyst
#73

All right, that tracks. So, as I see it, it looks like you folks intend to go after some of those bigger, lower-IRR opportunities, mainly in storage. I'm wondering, at which point in development would you plan to offload those? What amount of capital do you figure you'd require for whatever sits in the backlog or the development pipeline for the ones you expect you'll eventually sell while they're under construction? And what portion of that development pipeline consists of bigger projects that don't necessarily match the IRR you're targeting?

Doran Hole

executive
#74

Yes. So, I wouldn't say there's a CapEx figure I'd assign to that particular category. Once again, we'll be fairly opportunistic here to make sure we achieve the right outcomes and what we believe delivers the greatest value for Ameresco. I'd say the ideal moment is likely preconstruction, though we've also deviated from that approach regarding when we'd make a sale.

George Sakellaris

executive
#75

Regarding Middle River Power, the batteries aren't being purchased by us — the customer handles that purchase — and for that specific project, it's simply a design-build arrangement. That project, I'd say, will likely break ground within the coming 2 months.

Chris Souther

analyst
#76

Alright, that's quite useful. Congratulations, everyone.

George Sakellaris

executive
#77

Yeah. As for United Power, development there is fairly far along.

Eric Stine

analyst
#78

Hello everybody. I'll slip a question in right at the close regarding energy storage. Since it appears you'll be owning a few of these moving forward, could you discuss the rationale, or perhaps describe what an optimal project would look like, given that these assets generate various value streams compared with others of yours? And possibly several value streams rather than just selling the power or selling the gas. Any details you can offer on that front would be wonderful.

Doran Hole

executive
#79

We'll be brief; capacity contracts appeal to us — the fuel merchant revenue stream actually suits us better; fixed capacity contracts are what we prefer. And should we be able to get the numbers to work by examining CapEx, examining transportation, and the implementation speed at which we can get these things underway with a capacity contract, that looks better to us. We're securing long-term service agreements from our battery manufacturers that assist us with managing degradation and/or augmentation. And when you have a fixed long-term capacity contract, that genuinely helps keep us comfortable. So that, I think, is the ideal.

George Sakellaris

executive
#80

And the profit — solid profit.

Doran Hole

executive
#81

Naturally, clearing the thresholds we've set for returns.

Eric Stine

analyst
#82

Correct. And regarding that return — it isn't really about scale. What I mean is, provided everything lines up and you have the capacity contract in place, a project's particular size alone wouldn't make you walk away.

Doran Hole

executive
#83

Exactly. In our asset and development metric, whether it's solar paired with storage or storage on its own, you'll see projects spanning many different sizes, correct? Take some of these — a few of the battery systems we're acquiring for our behind-the-meter solar plus storage come in at a megawatt or under; whereas, as United Power showed, it's considerably bigger. So the range works fine for us. The metrics matter more.

Eric Stine

analyst
#84

Understood, thanks.

Joseph Osha

analyst
#85

Hello, thanks. I had another question. We discussed eRINs somewhat and whether or not something will occur. Based on how things turn out, this will become a fresh RIN marketplace. I'm curious whether you believe there will be sufficient liquidity in that market to hedge against it at the start? Or will it essentially be a situation where you simply monetize those credits once they're generated? I'm just curious about how you expect that marketplace to develop, if we assume EPA delivers what we're hoping for?

Doran Hole

executive
#86

Joe, in my view there's still plenty of work for the EPA to do on that front, but what we understand is that such RINs are going to function as RINs. They'll be D3 RINs, and they will need to add a greater RVO volume tied to that component; however, I'm not certain right now whether they will establish a distinct marketplace for eRINs as opposed to D3 RINs. That's unknown to us, we don't. Still, I'd say we lack sufficient clarity at this moment, indeed.

George Sakellaris

executive
#87

One thing we're certain they'll follow through on is this. They mean business when it comes to it; and the further along they get, the more they intend to electrify pretty much all of it. And our position is excellent, excellent, since we hold plenty of assets at their landfill gas to electricity operations. So that should give us a nice tailwind.

Joseph Osha

analyst
#88

And if I — apologies, please continue.

George Sakellaris

executive
#89

Plus, their claim is that completion will arrive earlier than most expect, since you'll hear some folks suggest it might slip to late next year or around then, but our expectation is that it wraps up well before that point.

Joseph Osha

analyst
#90

Still, I suppose if I — what I'm attempting to get at is, once the — how much time do you figure separates the announcement from the point where you actually have a working market, considering all these extra questions?

George Sakellaris

executive
#91

Well, based on what we know at this moment, that's 2025.

Doran Hole

executive
#92

Yeah, Joe, my sense is that this is going to require a while, since they will have to line it up with the calendar's cycle.

George Sakellaris

executive
#93

We wouldn't see anything until at least 2025.

Joseph Osha

analyst
#94

Okay. Thank you.

Operator

operator
#95

Appreciate it. That brings today's conference call to a close. Thanks for joining us. You're free to disconnect at this point.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Ameresco, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Ameresco, Inc. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ameresco, Inc. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.