Ameresco, Inc. (AMRC) Earnings Call Transcript & Summary
November 6, 2023
Earnings Call Speaker Segments
Leila Dillon
executiveThanks, Howard, and hello everyone on this afternoon's call. We're glad you could be with us today. On the line with me are George Sakellaris, who serves as Ameresco's Chairman, President, and Chief Executive Officer, along with Doran Hole, our Executive Vice President and Chief Financial Officer, and Mark Chiplock, Senior Vice President and Chief Accounting Officer. Before handing things over to George, I want to offer a short remark about forward-looking remarks. Within today's earnings materials, you'll find forward-looking statements, among them statements about what we expect. Risks and uncertainties apply to all forward-looking statements. For a discussion of the major risk factors that might cause our actual results to differ from those in our forward-looking statements, please see today's earnings materials, the safe harbor language on slide two, and our SEC filings. Beyond that, when presenting our financial results, we rely on several non-GAAP measures. Reconciliations to these measures appear in our supplemental financial information. At this point, I'll hand the call over to George. George?
George P. Sakellaris
executiveAppreciate that, Leila, and good afternoon everyone. We finished the quarter with total project backlog reaching an all-time high of $3.7 billion — up 14% from the prior quarter and 41% higher than a year ago. New project awards booked during the quarter came to a strong $700 million, bringing our awards for the year so far to $1.7 billion, which is over twice what we saw a year earlier. With proposal activity running 35% above last year's mark, we anticipate continued growth in new awards. When you add the insight we have on energy assets and maintenance operations, that pipeline gives us more than $7.2 billion in multiyear visibility toward profitable revenue, and it's what grounds our belief in Ameresco's growth over the long term. Even so, several challenges hit us in the third quarter — some affecting the whole industry, others specific to our company — and they dragged down our results. That leaves us deeply disappointed. Still, we take encouragement from how far we've come in strengthening the foundation for future growth. During Q3, we brought more than 50 megawatts of assets into development, so the period closed with close to 600 megawatts across development and construction. Compared with the 460 megawatts on hand when last year ended, that's a 30% gain. Even though the future looks extremely bright for us over the long haul, I wanted to address a few of the difficulties the industry has run into lately. In our projects business, the process of turning projects we've won into signed backlog is taking more time. Some clients are moving more slowly when it comes to kicking off the actual work, which pushes these contracts back. I should point out that nothing has been cancelled — what we're seeing is simply a longer sales cycle between winning an award and getting a contract signed. And just like other companies in our space, we're still dealing with supply chain holdups on particular components, plus a labor market that remains tight. We've run into difficulties in our energy asset division, stemming from outages at certain biogas facilities and from holdups in developing and building some of our properties — particularly the bigger, more intricate ones like RNG. Some level of asset downtime is inevitable, but what we've experienced across the past several quarters has exceeded what we planned for by a wide margin, caused by a number of circumstances beyond our influence, such as severe weather and disruptions from utilities. Timelines for constructing these assets have been drawn out because of shortages affecting components and workers throughout the industry, along with administrative logjams. Once more, though these setbacks are aggravating, we should remember that every one of these profitable assets is going to get built. The timeline has stretched beyond what we initially expected. Ameresco keeps expanding, so we're refining how our operations are organized to create greater consistency and scalability throughout every region and business segment; these adjustments are meant to sharpen our responsiveness to shifting market dynamics and to boost overall corporate efficiency; and given the enormous backlog of projects we hold, we've sharpened our attention on carrying out projects and producing cash flow. Because of the ongoing sector-wide difficulties that affect how long conversions take and how execution unfolds, we're reexamining certain assumptions underlying our guidance. Doran will delve into the figures more thoroughly during his financial review. Even so, despite these difficulties, our optimism regarding what lies ahead could not be stronger. Ameresco is a very profitable company, and we still anticipate considerable growth in 2024 and afterward. At this point I'll hand the call to Doran so he can speak about our financial results and outlook. Doran?
Doran Hole
executiveThanks, George, and good afternoon to all of you. For more financial detail, take a look at the press release and the supplemental slides we posted on our website once the market closed today. Second quarter total revenue came in at $335 million, which fell short of what we expected, since project delays and asset downtime weighed on revenue. Project revenue took a particularly heavy hit from a longer cycle for converting awarded backlog into contracted backlog, plus ongoing supply chain problems across the industry that keep stretching out our construction timelines. Energy asset revenue rose 6%, mostly because we had more operating assets than we did last year, and also because RIN prices were higher. Those gains helped offset downtime at our biogas facilities that was worse than anticipated, along with delays in getting some new assets up and running. Our O&M business turned in another steady quarter, growing 4%, while our other line of business saw revenue dip slightly, due to softness in end markets at our off-grid solar business. Gross margin widened to 19%, though that still fell short of our expectations, since the downtime I just referred to and project mix weighed on our results. I want to stress that we've seen no fundamental shift in our overall project gross margins, because the margin we expect within our backlog has held quite steady for at least two years. We produced adjusted EBITDA of $43.3 million this quarter. Our GAAP results for the quarter include a discrete tax benefit of $7.2 million tied to a prior year's Section 179D tax deduction allocated from a customer. To maximize our earnings, we'll keep taking advantage of every benefit available to us and to our customers under the IRA and other favorable legislation. Our long-term revenue visibility stays as strong as ever. As George noted, we closed the quarter with a record total project backlog of $3.7 billion. That's an impressive 41% increase versus last year and a 14% sequential increase, fueled by winning over $700 million in new project awards during this quarter alone. Our operating energy asset visibility sits at approximately $2.3 billion, which represents both contracted revenue and a conservative estimate of lifetime uncontracted RNG revenues. Along with our O&M backlog, these metrics give Ameresco visibility into more than $7.2 billion of future revenue. Importantly, that figure excludes any revenue contribution from the 596 megawatts of energy assets in development and construction. The timing for placing these assets into operation can range from under a year for small, simpler assets to 4+ years for more complex ones, such as RNG facilities. Unfortunately, that timeframe has been growing lately because of labor and equipment availability, as well as permitting delays; even so, we maintained our high conversion rate, with approximately 90%+ of our energy assets either successfully placed into service on our balance sheet or monetized through a sale to a third party. We keep getting lots of questions about how higher interest rates will affect Ameresco, especially when it comes to our energy asset business. Unlike a lot of others in this sector, the natural variety built into how we operate lets us pivot when conditions shift. We retain the choice to build assets that generate profit and then keep them on our books as operating energy assets, or divest them to a third party and book project revenue when those assets fail to meet the risk-adjusted Levered IRR thresholds we require. Even though certain assets might fall short of our own thresholds, they still sit comfortably inside the return expectations of numerous energy asset purchasers and aggregators eager to grow their holdings. A transaction like that typically includes an O&M contract tied to it; this approach isn't a new one at Ameresco, since cycling our cash flow via asset divestitures has formed part of how we've done business for multiple years. Ultimately, we think our adaptable corporate structure, spanning project O&M plus asset business lines, lets us keep capitalizing on the swift expansion of clean technology deployment, even when interest rates are elevated. Our capacity to fund our growth continues to be outstanding. Over the quarter, we obtained more than $500 million in financing commitments, lifting our year-to-date figure past $1 billion. Although the broader clean tech sector has seen credit conditions tighten and spreads widen, we take particular satisfaction that in our latest financing, credit spreads tied to Ameresco's top-quality asset portfolio have remained steady. We possess numerous appealing avenues for funding our growth, such as non-recourse project-level debt, tax equity, and capital recycling via asset sales; we are revising our 2023 guidance because of the matters we outlined previously; at the midpoints, we now foresee full year 2023 revenue, Adjusted EBITDA and EPS of roughly $1.35 billion, $165 million, and $1.20, as spelled out in our press release. For all of 2023, we now anticipate bringing between 120 and 130 megawatts of energy assets into service, counting the recently acquired Los Alamitos microgrid project along with our second 5-megawatt RNG plant. A third RNG plant should reach mechanical completion before the year ends and be fully commissioned during early 2024. Though we'll offer detailed full year 2024 guidance at the time we report our fourth quarter and full year results, we'd like to use this moment to address our 2024 Adjusted EBITDA target of $300 million, first shared back in early 2022. Because sales and construction cycles have grown longer in our project and energy asset businesses, we now think 2024 Adjusted EBITDA might land at approximately $250 million. Let me be clear that no portion of this Adjusted EBITDA opportunity has vanished. It has merely been pushed back, and this revised Adjusted EBITDA figure still amounts to remarkable growth relative to our anticipated 2023 results, and it remains consistent with our long-term 20%+ Adjusted EBITDA growth target. We are still keeping a close eye on operating leverage, staying disciplined about OpEx, and that's helped even more by the improvements we've made internally. At this point, I want to hand things back to George so he can give the closing remarks.
George P. Sakellaris
executiveThanks, Doran. As we've gone over thoroughly on this call, even though we're still up against certain headwinds, the chances for growth over the long term have never looked stronger. Our firm is stepping up its emphasis on executing profitably and on generating cash flow, and we're eager to share how that goes in quarters ahead. To wrap up, I want to express gratitude one more time to the people who work here, the clients we serve, and the shareholders who keep backing us. Operator, let's take questions from callers at this point.
Noah Kaye
analystThanks for taking my questions. To kick things off, I'd like to understand how we get from the earlier guidance to the updated one. There's roughly a $50 million gap in EBITDA. Could you break down the key pieces for us, as specifically as possible? You did mention both the projects and the energy assets, but it would really help if you could give us a sense of that bridge.
Doran Hole
executiveJust to make sure I understand, Noah — you mean 2024?
Noah Kaye
analystNo, it was 2023, in fact. Appreciate you clearing that up.
Doran Hole
executiveAll right, thank you; so to start, the main thing here is that our 2023 ramp depended heavily on strong execution plus turning awards into contracts during Q3. That never came together as we had anticipated, so because of that, we've more or less revised this guidance to shift items later, as you'd likely expect, and as you've probably watched us do previously. So, through Q2, we're carrying out work on our contracted backlog, and as you saw, revenue performance came in above expectations. Yet we also carried, you know, a fairly substantial portion of second half 2023 guidance within that awarded and contracted backlog; and with those conversions slipping, several big projects, I believe that was among the factors that simply led to the delay. I'm not sure we'd benefit from digging into further specifics past that.
George P. Sakellaris
executiveSo, yes, the
George P. Sakellaris
executive... how those assets were run played a part in that too.
Doran Hole
executiveYes. Asset operation. Yeah.
Noah Kaye
analystRight. Right, right. So it's not feasible to say if it was split evenly between projects and assets — that's a detail you won't be able to give us? I suppose, I suppose that's confirmed. Okay, got it. Got it. Earlier you brought up, or one of the model's advantages is being able to stay flexible when it comes to capital. Could you speak a bit about what you're planning for capital recycling here and what your thinking is regarding — leverage and financing. You said you've already locked in a solid amount of capital this quarter, but I just want to grasp how you're viewing capital recycling levels, and how quickly that could happen.
Doran Hole
executiveSo, look, I believe that was really meant to serve as a reminder that this forms part of the business model, that we will seek to sell assets. I think, as I discussed last quarter, with interest rates higher, we're beginning to encounter a bit of, you know, a bit of difficulty with the levered IRR targets we hold; and as you're aware, certain of these assets take time to sort of work their way through the asset and development metric and become something in operation. So if we see some strain from the interest rate, what we've discovered is that a market still remains for those assets at return hurdles below ours, and we will routinely focus on kind of pivoting and signing sales agreements for those assets pre-construction, so while they're still in development, which effectively turns it into a project business for us, rather than viewing it as a separate kind of business line. I'd say it's fair to say it will be consistently kind of dynamic, if that works as a good oxymoron for you, as we move forward.
Noah Kaye
analystAll right. Perhaps a final question. Pardon me, go forward, George.
George P. Sakellaris
executiveNo, even so, we still have a great number of projects being developed, assets under development, so this presents a chance for us to turn those development assets into cash while continuing to meet our goals for the ones we keep — roughly no less than 20% growth each year on those we retain; and with the current interest rate conditions, I believe there's a solid opening to recycle part of that cash. That also explains my earlier remark: on the project side, the backlog keeps expanding to such a big, such a large extent that we shifted our focus toward producing, toward constructing additional projects as we move ahead so we can create more cash from within instead of seeking it externally.
Doran Hole
executiveYes. What I mean is, this lets us keep up the pace of expansion we've been projecting, and it also lets us stay at our target IRR in the mid-teens.
George P. Sakellaris
executiveRight.
Doran Hole
executiveAnd simultaneously, keep ourselves ahead of the people we serve, correct?
George P. Sakellaris
executiveCorrect.
Doran Hole
executiveYou know, for the assets we intend to hold onto, we keep working to secure the appropriate non-recourse financing.
George P. Sakellaris
executiveRight.
Doran Hole
executiveAs you're aware, should those returns fail to materialize, the upside is that we remain active in the market and keep ourselves visible to our customers. On top of that, we continue to build out a solid volume of assets.
George P. Sakellaris
executiveThat way, Noah, we don't overstress our balance sheet. You know?
Noah Kaye
analystUnderstood. There's plenty more I'd like to ask, though I'll save those for later. Plenty of analysts are waiting on you.
George P. Sakellaris
executiveRight.
Noah Kaye
analystThank you.
Doran Hole
executiveThank you, Noah.
Stephen Gengaro
analystHello there. Hope everyone's having a good afternoon. Am I coming through clearly?
Doran Hole
executiveYes, indeed.
George P. Sakellaris
executiveRight.
Stephen Gengaro
analystOh, excellent. Thanks. So, you know, I suppose my main, my broad question is when we consider, you know, the quarter, and clearly you, you have described the difficulties you have encountered and you sort of provided this early glimpse at 2024. When we consider your grasp of the problems and what sort of gives you assurance that you begin to gain, you know, kind of extra momentum traction into 2024, which makes those targets realistic?
George P. Sakellaris
executiveWell, we factored in what took place for us during this particular quarter, and essentially we extrapolated. We presume that these conditions will persist for the foreseeable future. And honestly, among ourselves, that's a mistake we made. We kind of dropped our guard because we'd done so well in Q1 and Q2, even though we were starting to notice that a few of those awards weren't converting into contracts as quickly as we'd expected. But then it spread across a whole lot of projects, not only the ones we could see. And the other thing that caught us off guard big time is how much the implementation timelines stretched out. We ended up stalled on a good number of projects during execution since we couldn't source certain materials. With a few of them, we couldn't secure the right labor quickly enough. Regarding those administrative hurdles I brought up, it's honestly hard to fathom. In the past, certain permits might have been secured within roughly fourteen days. Now, over three to four months go by since no one turns up to evaluate the submissions. That leaves us feeling quite optimistic, which explains the situation with our project segment and its backlog—things have reached a stage where we're confident about delivering in 2024. Particularly given the standard we're able to offer a client right now. That's the reason I believe — and once the year wraps up, when we discuss the 2024 figures, we'll share additional specifics and add a bit more nuance and background. Still, at this moment we're feeling fairly confident about our position, having factored in the conditions of the marketplace.
Stephen Gengaro
analystThank you, George. What I took away is something along these lines: your sense is that those projections take into account the factors within your control, as opposed to the ones beyond your control, as we head into next year. Would that be a fair characterization?
George P. Sakellaris
executiveYes, that's right.
Stephen Gengaro
analystAll right.
George P. Sakellaris
executiveSo that's the reason, in what I wrote, I mentioned that our confidence in what's ahead is extremely high, given where the business trend stands. Things look really strong. It's simply that carrying it out is taking somewhat more time than we — Look, this industry has been our home for many years, and the metrics we believed we had fully mastered. And frankly, folks, I expected the supply chain problem to be resolved by this point. What I believe is going on, though, and this is why the electrical side keeps tripping us up, particularly around equipment, with the whole shift toward everything being electric. There are bottlenecks, and not just when it comes to what the different manufacturers are able to do in producing transformers, control panels, and similar items. The wonderful part is that not one of our projects has disappeared. Every single one remains, and the pace we're going at is just somewhat slower.
Mark A. Chiplock
executiveMm-hmm.
Doran Hole
executiveSteve, this is why managing operating expenses matters so much in this situation.
George P. Sakellaris
executiveYeah.
Doran Hole
executiveSo, since our emphasis is on producing earnings, we will keep operating expenses in check and, as you know, keep delivering the EBITDA we anticipate delivering. To be honest, before we sign any customer agreement, we are still trying to get contracts finalized with our vendors and suppliers so that margin risk is reduced. That effort is ongoing; the thing is, a handful of these adjustments have arisen on certain projects that sat in the backlog for some time, given how the cycle has lengthened.
Stephen Gengaro
analystGot it. I see. Well, thanks to both of you. That's a big help.
George P. Sakellaris
executiveThanks.
Doran Hole
executiveThanks.
Eric Stine
analystHi, everybody. I'd like to explore this a bit further, simply to get a clearer picture. So, obviously, challenges around the supply chain, plus labor, have remained fairly persistent, I realize. What I'm wondering is whether you observed that getting worse, or is it more that you simply had several bigger projects—work you expected would add to results in the latter half of the year—and the blow from those headwinds was just larger?
George P. Sakellaris
executiveExcellent, excellent question. And in particular, that is precisely what took place, above all with certain bigger projects. They had already been placed on the schedule, and you tell them this specific contract, so at this point it will perform XYZ, and then unexpectedly, that contract appeared. Alternatively—and this matters most—you were unable to get qualified workers to arrive at the job site, at the site. As for some of them, we previously would issue an RFP to 12 to 16 vendors, and at times only one or two would reply. Then you discover that a single one among them isn't even qualified. Therefore, the labor problem has turned into an enormous worry.
Eric Stine
analystUnderstood. And beyond that — I mean, your project business has grown really well. You brought up permitting and things like that, but would you say this is the part of your operations where it's fair to claim that higher interest rates are genuinely making a negative difference?
Doran Hole
executiveNot truly. No, no.
Eric Stine
analystNo.
Doran Hole
executiveOn the project side of things, that isn't something we've truly observed.
Eric Stine
analystOkay.
Doran Hole
executiveI think-
Doran Hole
executiveEric Stine asking, and Doran Hole responding: I believe that it's, well, you go first.
Eric Stine
analystNo, what I meant to say is this: regarding that $250 figure you mentioned as a preliminary view of 2024, I just want to verify — you aren't actually counting on any betterment in those segments, correct? What you're basically assuming is that things stay as they are right now, carrying that forward across 2024, instead of expecting that some of these segments will get better.
George P. Sakellaris
executiveThat is what we did, and Mark performed excellent due diligence on it. Feel free to add something, but that is precisely our aim, and we believe our representation of it is quite accurate.
Eric Stine
analystAll right, thanks.
Tim Mulrooney
analystI wanted to ask about the 2023 guidance you gave. Based on the midpoint, it looks like you're still pointing to a solid sequential increase in Q4 revenue — from Q3 to Q4, at that midpoint, growth of over 20%, as I understand it. Could you walk through what's mainly driving that step-up? Is it things like collecting unbilled revenue at SCE, or is there something else?
Mark A. Chiplock
executiveYes, Tim — Mark here. Sure. For the most part, it comes down to solid performance against the contracted backlog we have. It bakes in almost no revenue from awards. After reviewing that, we also have to factor in the slippage we are observing. Still, given the projects that are underway right now, we believe the contracted revenue figure is one we can hit in Q4.
Tim Mulrooney
analystAll right. Thanks, Mark. For my next question, I wanted to inquire about those administrative bottlenecks you mentioned as something affecting the third quarter results. Could you go into a bit more depth on what exactly they involved? Were they tied to just one or two particular projects, or is this a wider problem that you anticipate continuing into the fourth quarter and past that? Thanks.
George P. Sakellaris
executiveWell, I'm aware of a few of the assets that got held up due to — whether it's solar plants that weren't hooked up because of the utility. We weren't able to get out there and connect the project, or some of the renewable gas plants that we had built; things got pushed back since I believe it was 3 months before anyone showed up to look over the applications. So that held up that specific project by roughly 3 months.
Mark A. Chiplock
executiveYes. And I believe those administrative holdups that are affecting when awards turn into contracts — that's something we honestly began noticing somewhat near the close of Q2, with certain awards we thought would convert. We truly felt the effect during Q3. So, regarding what you asked, yes, we anticipate that persisting, carrying on into Q4; and since all of these are essentially just shifting further to the right, well, we've factored that into the guidance we updated.
George P. Sakellaris
executiveLook, the reality that not everyone has returned to their jobs — that does have an effect on how our work gets carried out, and I believe it affects plenty of others too.
Mark A. Chiplock
executiveUnderstood, thanks.
Joseph Osha
analystHey, everyone. I thought this might be a good moment to change direction somewhat. Looking at where we are during this quarter, and in the presentation you mention that much of the business is non-recourse; however, if Q3 is annualized, we're currently at roughly 8.3 times debt EBITDA. And based on your updated guidance, it's around 8 times likely debt EBITDA for 2024. The business hasn't produced any free cash flow since 2020, even including ESPC, and since the start of 2019 it has generated $80 million. So I suppose what I'm asking is, we can discuss the expansion in the energy assets business, but when does this business start generating cash? And how are you approaching that as we head into 2024?
Mark A. Chiplock
executiveYeah.
Doran Hole
executiveJoe, what I'd start with is this: our adjusted cash from operations came in positive, correct? Like we've discussed before, you know, we've got the flexibility to, you know, adjust how quickly we invest in assets when needed, so that it lines up properly with the cash our operations bring in. I get it — those higher leverage figures you're referring to, as you yourself noted, EBITDA multiples aren't something that gets applied when setting advance rates for non-recourse debt. I believe we're all basically on the same page there, on that topic, and because of that, those numbers are going to appear elevated compared to what you'd expect from a typical corporate credit facility. When it comes to cash flow, I believe that's an area — and we've talked about this — that we're going to examine, looking at how we can begin discussing the company's track record for producing cash and how that stacks up against how much is going into assets; that said, at a high level, the one other thing I'd mention regarding leverage in general is that it's still somewhat inflated because of the delayed SoCal Ed projects and finishing those up, bringing that cash in. We've actually put a fair amount of our own operating cash flow toward paying down the debt — the corporate debt — and so we have a substantial amount of unbilled sitting there that you'll see, you know, reverse around roughly Q1, to sort of reveal the cash emerging from the SCE project. So that's going to assist us when it comes to delevering the corporate facility. You know, at this point, I'm not sure what more I can offer to answer your-
Joseph Osha
analystSure.
Doran Hole
executiveYour question.
Joseph Osha
analystAbsolutely; and so, following up on that, this is really the latter half of that very same question; and listen, a lot of discussion around this has been happening at certain businesses somewhat similar to yours, such as, you know, a few of those residential solar, you know, companies. Yeah, the issue really comes down to the way you, you strike a balance between expansion and, and producing cash flow. So I suppose I'll simply put it to you or George or whoever else, you know, is there some threshold at which it becomes a $2 billion-dollar company or a $3 billion-dollar company or whatever, where you'd say, "Alright, perhaps we're going to adopt a somewhat different perspective on how we view growth as opposed to generating cash flow and perhaps in the end returning capital to shareholders?" I'm only attempting to get a feel for the philosophy at work here that supports, you know, the way these choices get made. Thank you.
Doran Hole
executiveYeah.
George P. Sakellaris
executiveOkay, so that’s the reasoning — the way we think about it, particularly when rates are elevated, is that we aim to turn a solid portion of the assets we hold and build into revenue, and then put more emphasis on the project side of the business, since that throws off fairly strong cash flow. And really, instead of putting out fresh equity to fund possible assets that are already ours, the money comes entirely from cash flow we generate ourselves; beyond that, the approach we’ll follow moving forward is that we won’t reinvest every bit of that cash flow coming from projects, existing assets, and O&M — we’ll hold some back to bring down leverage at the company.
Joseph Osha
analystAll right. Thanks so much.
Julien Dumoulin-Smith
analystHi there, good afternoon, everyone. Thanks, folks, I really appreciate that. I just want to follow up on a few items here. To start, what's your thinking on how long it will take for these projects to get, as people say, back on track? Clearly, you're taking 2023 and 2024 down by about 50. I mean, should we expect some catch-up in 2025, or do you believe that, you know, in a categorical sense, we're pushing it out through the four, through the forward look here? When do we get that sort of view on 2025? And then, when you think about, you know, sort of catching back up here, does a piece of higher OpEx need to come into play for things to get back on track? Or, you know, is there any other risk sitting in the SG&A? And then maybe, just to tidy up on that last one about payments and cash, could you just clarify a bit more regarding, you know, the payments on the batteries here and the timeline for that?
George P. Sakellaris
executiveSure.
Julien Dumoulin-Smith
analystBut that will support 25.
George P. Sakellaris
executiveTo start with the first part — no, regarding OpEx. Our operating expenses are going to stay in check. Growing the business doesn't require us to increase OpEx. This quarter, we brought in $700 million of new awards, and for the full year, $1.7 billion. Growth is coming for this business. When I look at 2025 and past that, I wouldn't really characterize this as playing catch-up. Sure, we don't get into granular discussion of periods that far out, but what we're seeing is that timelines are extending — both on the sales cycle side and the construction cycle side, correct? On the macro side, everybody is aware of the labor shortage problems present in the market; we have to keep monitoring those. That said, with the IRA and the volume of awards flowing in, you know, the business's overall growth potential remains intact. It doesn't automatically follow that those timelines must shorten for us to keep expanding at our, you know, roughly 20% per year EBITDA goal. That's the target we're, that's the target we're working, you know, working toward; so that answers the first two items. As for SoCal, you know, essentially once we reach substantial completion, you know, the payment terms are 60 days; that's written into the contract, it's public, anyone can look it up; so you can take it that, you know, we're discussing two of the projects finishing in Q4, and then a third one during the first half of the year, kind of extrapolate forward from there. We won't be providing deep detail on those cash flows, Julian.
Julien Dumoulin-Smith
analystOkay, so about the schedule — do we feel sure that you folks truly know when the revised dates land for this project slip? What I mean is, it appears this came together fairly recently. So, comparing one quarter to the next, I'm just wondering, how can you be certain about how deep these holdups go? If you could get a bit more granular on that, given that certain bigger efforts, RNG included, tend to be pretty uneven.
George P. Sakellaris
executiveWell, I'd say — based on what we've observed up to now — take the RNG project: roughly a 6 to 8 month delay, more or less. Then with the other projects that are in construction, you know, we used to talk about a construction schedule of 1 to 2 years. At this point it appears to be longer than that — 1.5 to nearly 3 years of construction for some of those $100 million-plus projects. And, I mean, let me share something with you that took place. We had jobs that were being built, and we send the gear out to that specific air base. Then, because we're working up at the North Pole, in some way or another, the items never made it onto the aircraft, which pushes that project back by half a year. We missed out on $12 million in revenue there, and it ended up as a loss. Situations like this keep cropping up everywhere, which is exactly why we decided it made sense to fold as much of this as possible into our projections. Even so, that work hasn't disappeared—it remains out there and will get completed. As for our five-year growth plan and the 20% EBITDA goal within it, our level of confidence there is quite high.
Julien Dumoulin-Smith
analystThanks, guys.
George Gianarikas
analystHey there, I appreciate you fielding my questions. So I just wanted to touch on those same topics. You brought up that contract conversions have been delayed, and I believe during the call I heard you say that in your view, none of that slowdown stems from shifts in the interest rate environment. Did I get that right? Is that what came across on the call?
George P. Sakellaris
executiveThat's right, yes.
Julien Dumoulin-Smith
analystYeah, you've got it right.
George P. Sakellaris
executiveThat is correct.
George Gianarikas
analystCan you then explain-
George P. Sakellaris
executiveA portion of these are purely administrative matters, you know. Either the boards aren't convening, or individuals fail to appear, or there's bureaucratic hell with certain federal contracts. Yet conversely, you know, those awards total $700 million. Federal contracts make up one third of that amount. Obtaining them is happening, but advancing them to the following stage is proving harder, and then actually executing them is proving harder still.
George Gianarikas
analystSo starting right at the beginning of the funnel — with that awarded project backlog, which has now stretched, you know, to $2.5 billion — it's simply about turning that into contracted work. Is it purely a matter of administrative holdups, and then in some way project delays are also affecting that conversion? Is that... Is this just the point where the administrative problems are turning up?
Doran Hole
executiveNope, that piece George just brought up is essentially the administrative angle. Once the contract has been executed, that's when the project delays come in.
George Gianarikas
analystRight.
Doran Hole
executiveActually, the construction timelines-
George Gianarikas
analystThe schedule.
Doran Hole
executiveThe timelines for putting things in place, along with the schedules, are extending somewhat—
George Gianarikas
analystRight.
Doran Hole
executive-based on labor and material availability.
George Gianarikas
analystTherefore, regarding what appears on one of your slides — that 12 to 24 month period for contracting — I believe your comment was that it's closer to 18 to 36 months at present, and that's for the contract, correct?
George P. Sakellaris
executiveI will let Mark answer the question better than me.
Mark A. Chiplock
executiveRight, so we continue to observe that same band, though it isn't hitting each of our awards. What we've mentioned before is that a number of bigger awards sit at more advanced points in the contracting cycle, yet administrative holdups keep stretching them out. Consequently, on average we remain inside that band, but the lag has really come from a handful of sizable projects we thought would move into the following phase of active construction. Then, as we've also noted, after contracting happens, that implementation window begins to run a bit longer — we have to get the workforce labor mobilized and bring materials to the work site. All of that consumes time, so everything is essentially being stretched between the conversion and the subsequent ramp up in implementation, and that's driving much of the pushouts.
George Gianarikas
analystAll right, and this might be the last thing we cover. You brought up that higher RIN prices are making up for a portion of the unexpected outages at your RNG plants; so once those are brought back to full operation, how do you see things playing out? Is there anything you can tell us about the recent jump in D3 RINs, and what your approach will be for turning those into revenue? Given the downtime, did you lose a chance to cash in on some of your RINs? Thanks.
George P. Sakellaris
executiveOkay, so we're always looking to capitalize on what the market gives us. At the start of the year, we had roughly 50% merchant in. But at this point, what remains for us this year is likely just output from the past 2 months. We've essentially been selling on a monthly basis, and I'd say we secured fairly strong pricing. That has shown up in our guidance. For 2024 and also for 2025. One more thing I should highlight — I believe I brought this up on one of the calls previously for 2024 — we were consistently bullish on RIN prices, and the figure we had used in that earlier projection was basically where RIN prices sit today, at this moment.
George Gianarikas
analystThanks.
Moses Sutton
analystYou're fielding my questions, and to start, for whatever it's worth, my view is that you shouldn't decelerate growth the way one of my peers mentioned, just to hand back cash while genuine growth is available. Yeah, so, I suppose the first thing I'd ask is, what's your thinking on Adjusted EBITDA margins in the project business? You know, it's 4% for the nine months year-to-date. Typically I'd picture this nearer to 10%. Is that, is that because of inflation? Is it because of some mismatches related to delay? How, how should we think about that for the project side when it comes to Adjusted EBITDA?
Mark A. Chiplock
executiveWell, sure — 10% does seem somewhat elevated. But my view is that this usually comes down to mix, correct? So if you look at it on a year-over-year basis, what drives it is which projects happen to be underway at that moment and how they affect the margin. I'd say historically we've run nearer to 6%, so the gap isn't all that large. And once more, lately we've had certain parts of our mix carry a somewhat lower margin profile, despite the fact that margins in general have been widening; so I'd say we're pretty close to where our margins have sat through history.
Moses Sutton
analystUnderstood, that makes sense. So returning to the D3 RIN subject — given that spot RIN prices are hovering around their 2021 highs, I recall you usually mention something like a 50% spot exposure, or spot versus hedges, with 50% under contract. Does the slowdown in RNG projects actually give you room to lock in a larger share of the future RINs you anticipate once projects come online next year, at a better contracted rate than you could have gotten before? Is that already reflected in the 250-
George P. Sakellaris
executiveYeah, no, that's a really, really solid point. In fact, we're currently in discussions with a couple of companies. We've got a few offers sitting in front of us. That's the reason we aren't providing forecasts for RIN prices for the coming year and such. We could potentially sign a few long-term agreements at prices that are much higher than, say, the ones we signed two or three — what was it, three years ago; so no, we're definitely examining this, and there's no doubt about it; and once we're feeling a bit more at ease with where prices stand, we'll go ahead and finalize them.
Moses Sutton
analystThat's quite useful, thanks. And at this point, when we talk about long term, what tenure does that mean — how many years?
George P. Sakellaris
executiveYou know, we have... Oh, my God, up to 15 years.
Moses Sutton
analystExcellent. Thank you. I'll get back in the queue.
George P. Sakellaris
executiveYeah.
Griffin Smith
analystExcellent, many thanks. For my first one, I was simply wondering whether you might offer a bit more detail regarding the RNG financing that you announced not long ago alongside HASI. From what I gather, that arrangement has some flexibility, and there may be a profit-sharing element tied to the true expenses associated with that funding. Could you possibly go into further detail on that?
Analyst
analyst... Hi there, everyone, Josh Baribeau speaking. So there is nothing variable about it. The way it functions is that a fixed cash piece of interest applies up until the point the loan has been amortized. Following that, Hannon receives something of a cash sweep until such time as they reach an IRR, meaning internal rate of return, based on the amount they put in at the start.
Pavel Molchanov
analystAll right. Would you be in a position to reveal the real, I suppose, the initial rate that applies to you, the rate that ends up being effective for you, on that financing?
Analyst
analystRight, that figure appears in the 8-K, and the accrual is being done using that IRR rate.
Pavel Molchanov
analystUnderstood. Okay, many thanks.
Chris Souther
analystI appreciate you fielding my questions. Since the timeline has stretched out for both awarding contracts and carrying them out, this past year ended up weighted much more toward the back half given what you'd be able to see. So I'm simply wondering how you view that visibility right now, and once you provide complete guidance for 2024, should we figure that far more clarity will exist around awarded contracted backlog as we move into the year? Or am I perhaps hoping for too much? How exactly do you regard the visibility surrounding that 250?
George P. Sakellaris
executiveOur visibility strikes me as quite strong, and we lean more heavily on contracted work than on what we put in where we'll stand at year's end regarding the contracted side, which carries greater weight than anything else, rather than depending as much... Unlike what happened this year across the final couple of quarters, particularly given our position, we won't see a large hockey stick.
Chris Souther
analystAll right. Then perhaps regarding the project — you know, those possible development project sales — is there a specific sector you're watching that you'd concentrate on for possible sales? Is it solar, batteries, RNG? What particular areas would you sort of be examining there, or is it sort of all of the above?
Doran Hole
executiveNot really RNG, I'd say. I think we're-
Chris Souther
analystNope.
Doran Hole
executive— largely regarding solar, definitely, and after that the hybrid-
George P. Sakellaris
executiveBatteries, correct.
Doran Hole
executiveSolar plus battery. Honestly, I wouldn't rule out us considering certain standalone battery opportunities, since, as I mentioned, we keep developing across multiple markets. A number of those markets could carry more merchant risk than we'd prefer, so because of that, we'll pursue, you know, an NTP sale for projects of that type; so my sense is it leans more in that direction rather than the RNG.
George P. Sakellaris
executiveRight, so listen everyone, I'd like all of you to grasp this: when it comes to assets we develop — solar ones, battery ones — and afterward turning them into revenue, that process isn't any different from what we do with energy savings and performance contracts. Essentially, we offload the receivable, we collect the funds, then comes the financing, and ultimately we stand behind the guaranteed savings. Honestly, this is an even easier thing to do, it just requires somewhat more time; and after that, we can choose to retain whichever ones offer stronger returns, meaning they surpass our required rate of return. As for RNG projects, on the whole those tend to be more involved, there's no denying that, yet right now, they deliver stronger returns compared to solar.
Chris Souther
analystAll right.
Pavel Molchanov
analystYes, I appreciate you fielding this. There's been plenty of discussion regarding the main U.S. operations. I have a couple of inquiries concerning Europe. To start, do any of the challenges around permits and difficulties in the supply chain have an impact on whatever projects you're handling across the Atlantic?
Doran Hole
executiveTo start with the initial portion of that, I want to share something since I was present at one of the locations last week — one of the bigger ones. There has been a small amount, you know, but it hasn't reached the level that we've witnessed here in the United States.
George P. Sakellaris
executiveYeah.
Doran Hole
executive...regarding the supply of workers and supplies. In our case, particularly for that Delfini facility in Greece, which has a capacity of 100 megawatts, things continue moving forward according to schedule; the only shifts we've seen relate to timing, and they've been minor. And as I see it, for a lot of the fresh contracts we've secured within the awarded group — a number of them being in Europe on the engineering, procurement, and construction side — our outlook remains solid when it comes to getting both supplies and workers in the areas where those projects are being won.
George P. Sakellaris
executiveYes, and this holds true even over in the U.K. The single case that stood apart was our contract with Bristol City. We fell short of the figures by quite a bit there — not due to a lack of projects, but, and this is something we learned from, securing approval for those projects via the city council and all the other parties—
George P. Sakellaris
executiveMm-hmm — the body that needs to give the green light to those specific projects, that process ended up taking a lot more time than we had anticipated. So what we've done now is set up meetings every month, sitting down with the board to figure out which projects we'll be pursuing, and getting them more or less cleared before this year wraps up for whatever we're going to construct the following year. That particular one, then, we missed the boat regarding our expectations of what could be done versus what actually took place. Yeah, once more, it comes down to administration, not due to any reluctance on their part or anything of that nature, but — Yeah, administrative, and that pretty much covers the cycle of simply converting awards into contracts.
Pavel Molchanov
analystYeah.
Doran Hole
executiveNot anything about actual construction activity.
Pavel Molchanov
analystRight.
Doran Hole
executiveFurthermore, it's a push to the right.
Pavel Molchanov
analystYeah.
Doran Hole
executiveThis isn't about altering what any of those awards cover; our pace has just been reduced.
Julien Dumoulin-Smith
analystYeah.
Pavel Molchanov
analystGot it, that's clear. Oh, still on the subject of Europe — this year, I'd have to think that given, you know, certain macroeconomic challenges, the multiples attached to prospective M&A have declined. With that in mind, are you finding additional chances to expand your operations over there through M&A?
Doran Hole
executiveRight. There isn't anything particular we can share at the moment, though we'd share your view, and we are observing... Once more, we stay quite opportunistic; we continue to focus on our core criteria regarding what we seek — management compatibility, financial valuation, and things of that nature. Still, yes, the count of opportunities appearing attractive has gone up.
Pavel Molchanov
analystVery good. Thank you, guys.
Mark A. Chiplock
executiveThank you.
Doran Hole
executiveThanks.
Davis Sunderland
analystHi, everyone. I really appreciate you squeezing me in at the close. Most of what I had has already been covered. I just wanted to ask, could there be any chance to recoup costs tied to certain of these projects sitting in the contracted stage that have been stretched out, like SoCal or other transactions you've completed before? And then my second question: with so little visibility into shortages of labor and components, how are you now approaching those variables in contracts moving forward? Thank you.
Doran Hole
executiveYeah, absolutely. So, apologies, Davis, your line is coming through a bit garbled, but I believe I caught it, I believe I caught the question. So-
Davis Sunderland
analystI did.
Doran Hole
executiveRegarding the initial item — when a force majeure circumstance genuinely brings something into existence, then certainly, as you're aware, it's possible for us to recover expenses tied to particular postponements, and that remains a matter of contract in every case. I can't offer you any specific stories about that, nor do I have figures to share, yet broadly speaking, agreements typically aim at force majeure, not always a broad deceleration or workforce availability, mind you; as for examining what's left of this year and discussing, or pondering, that figure of $250 for the coming year, we have in practice factored in the current situation while weighing how construction will proceed from here. As we've mentioned, losing business from our awarded backlog or contracted backlog isn't something we normally do, and definitely not from the contracted backlog. Even so, should decelerations occur, matters simply get deferred further down the line. Consequently, we've revised our projections regarding that cadence, and the figures we've laid out for all of you today rest on that foundation.
Greg Wasikowski
analystYeah. Hey, thanks, everybody. Just a single question from me. I want to dig a bit deeper into the idea of divesting certain assets and the development side, since I get the feeling I may not be fully following it, or perhaps I heard it wrong. It sounds like doing that would let you remain in front of customers and keep business going across projects and O&M, which is a positive. But if you're swapping an energy assets business for a projects and O&M business, isn't that essentially swapping a business with high EBIT margin for one with low EBIT margin? I guess what I'm asking is whether it's less about pushing things out to a later date and more about accepting some shrinking of margins just to keep things running without interruption. Does that sound like a fair characterization, or have I got it wrong?
Doran Hole
executiveYeah. Let me lay out for you the way we approach this kind of analysis. When we look at assets that stop producing EBITDA and stop delivering levered equity IRR, two measures really matter to us: cash generation and net income. So actually, with certain of these assets — for instance, anything that could carry a merchant tail, or others where the unlevered IRR sits fairly narrow relative to the cost of funding — our focus shifts to this: from the standpoint of total cash flow generation, we're likely better off, given how the market is currently pricing some of those assets, to perform the EPC and secure the O&M contract, which lets us create more cash flow and redeploy it into something that genuinely shapes up more favorably for us in terms of cash flow and net income over the longer haul. That's really the sole tweak I'd offer there.
Greg Wasikowski
analystAlright, so there are layers to this. Got it. Thanks, Doran. I appreciate it. That's all.
Operator
operatorWe appreciate it. That wraps up the question-and-answer portion, folks, and that also brings an end to the conference call for today. Thanks for joining us. You're free to hang up now. Have a great day, everybody.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Ameresco, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Ameresco, Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ameresco, Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.