APA Group (APA) Earnings Call Transcript & Summary

August 20, 2026

Australian Securities Exchange AU Utilities Gas Utilities earnings 87 min

Earnings Call Speaker Segments

Adam Watson

executive
#1

Good morning, everyone, and thank you for joining us for today's FY '26 Results Presentation. With me are Garrick Rollason, our CFO, and our Investor Relations team. I want to acknowledge the Gadigal people of the Eora Nation, the traditional custodians of the land from which I'm speaking. For the past 60,000 years, First Nations people have cared for our lands and waterways. We acknowledge and pay our respects to their elders past and present. I'll begin today's presentation with the Safety share on Slide 4. APA is genuinely a national business, with assets and teams operating right across Australia. A big portion of the people on our front line are based in remote and regional locations, and being able to stay in touch via telecom and tech platforms is critical for keeping them safe. That's the reason we launched a body of work aimed at improving connectivity, which includes rolling out various platforms — Starlink among them — at 70 of the sites where we operate. Because of that investment, our staff now have stronger links to our integrated operations center. They also have stronger links to their families and coworkers, and they possess the tools needed to better plan and schedule how and when they perform their everyday tasks across our assets. On its own, this counts as a significant effort to bolster the safety and care of our workforce, yet it goes beyond that. Upgrading the tech systems at our far-flung locations lets our employees carry out the essential daily tasks they do safely and productively; Slide 5 shows three main points from today's results. First, the financial outcome we've posted is a robust one. Underlying EBITDA rose a noteworthy 8.3%, landing above the middle of our guidance range. We're extremely proud that EBITDA margins widened 370 basis points. Free cash flow climbed 3.2%, which likewise beat what had been expected; our FY '26 goal for cutting costs of $50 million has been surpassed, with enterprise-wide savings totaling $80 million for the year. That figure takes in a 20.6% decrease in corporate costs. We've achieved annualized savings of roughly $100 million. A portion of those cost reductions comes from making our business simpler, which involved selling off the Networks and GDI operations since they no longer aligned with our growth strategy. Second, our growth prospects are compelling, backed by favorable market fundamentals. It's now broadly acknowledged that gas plays a key role in the energy transition and in keeping energy reliable and affordable. During the past year, we finished the Sturt Plateau pipeline — our inaugural project in the Beetaloo Basin and a significant step toward realizing that major opportunity. We have secured a deal with CS Energy for the Brigalow Peaking Power Plant, which highlights how appealing our GPG strategy is. We also announced that our East Coast Gas Grid will expand further through compression and the Bulloo Interlink. Alongside that, we recently revealed plans to expand the South West Pipeline in Victoria. The third main point is that APA holds a robust balance sheet, giving us room to finance growth, increase distributions and keep credit metrics intact. Our organic growth pipeline for FY '27 to '29 has climbed from $3 billion to $3.5 billion, which shows the solid growth we're seeing in our target markets. We remain disciplined about pursuing the right opportunities that offer the strongest returns—returns comfortably exceeding our cost of capital—and our balance sheet gives us the capacity to fund them. On Slide 6, you'll find a fuller breakdown of our financial highlights. As I noted, underlying EBITDA grew 8.3%, and EBITDA margins widened by 370 basis points, thanks to solid performance of assets throughout the portfolio, plus contributions from new assets, inflation-linked tariff escalation, and cost reductions across the enterprise. We expect earnings growth to carry on into FY '27, and today we announced FY '27 underlying EBITDA guidance in the range of $2.26 billion to $2.34 billion. The middle of that range implies a 5.4% gain over FY '26, which would be yet another strong outcome. Across the whole of FY '26, our distributions came to $0.58 per security — our 22nd year in a row of distribution growth. We anticipate that growth carrying into FY '27, and today we're announcing distribution guidance of $0.59 per security for the coming year. On Slide 7, you'll see several performance highlights from our key non-financial metrics. We had 0 serious harm incidents, and we're extremely proud of that. Thanks to our methane abatement and compressor efficiency efforts, gross emissions fell 21% across our gas infrastructure portfolio versus our FY '21 baseline. It's worth noting we met our safeguard mechanism obligations in FY '26 without having to give up any carbon credits. Our Employee Experience score came in at a solid 68% amid a period of considerable change for our people. I want to thank every APA employee for their perseverance and resilience across the past 12 months, and for the continued uplift in how we focus on customer experience and service delivery. We keep making strides on gender representation, lifting our representation of women to 34.2%, which sits well ahead of industry benchmarks. And we kept delivering on our reconciliation action plan commitments, with ongoing progress on cultural awareness and First Nations supplier engagement. Turning to Slide 9, let's look at our strategy and the dynamics of the market. There's no change to our strategy. Our focus is on building networks by developing assets backed by long-term, capacity-based contracts that are indexed to inflation. We keep strengthening what we can do in our core growth markets — gas transmission and storage as well as contracted power generation. That includes competitive edges we've built through efforts like our strategic partnerships with Siemens Energy, GE Vernova and solar turbines for procuring turbines and the related power generation equipment. We're still confident that the business is concentrated on the right key markets, and that our diversification lets us create value in an energy market that's dynamic. All of our efforts are directed toward creating chances for our team, strengthening the communities we serve, generating value for customers, and protecting value for you, our security holders. Slide 10 shows that our organic growth pipeline for FY '27 to FY '29 is now $3.5 billion. Announced projects make up the bulk of this amount, among them the East Coast Gas Grid expansion, the South West Pipeline expansion, the Brigalow Peaking Power Plant and Lateral Pipeline, and the Sybella Solar and Battery Project, which we announced today. Past that $3.5 billion pipeline, we are also working to progress a number of appealing longer-term opportunities. We're concentrating specifically on chances in the Beetaloo Basin, on gas-fired power generation that backs the continuing addition of renewables to our grids, and on behind-the-meter offerings serving our remote mining clients along with our newer AI and data center clients. In the slides that follow, I'll walk you quickly through where several of our bigger projects stand, starting on Slide 11 with the East Coast Gas Grid expansion; in February 2026 we announced Stage 3 of that expansion plan, which lifts the East Coast network's capacity by roughly 30%.

Adam Watson

executive
#2

That comes on top of the 25% gain in North to South capacity we have already delivered since 2023. In February, our announcement featured a final investment decision of $260 million for Stage 3A, which will add 3 new compressors and raise North to South capacity for winter 2029. We are likewise putting $220 million into Stage 3B to carry on early works and to procure long lead items for the Bulloo Interlink. Environmental assessments are underway at this point. From the start, demand in the market for our Stage 3 expansion plan has been quite evident. It offers a prompt and economically attractive response to anticipated supply gaps in the southern market, and it also supports the continuing part gas will play in firming renewables as time goes on. With the Federal Government's proposed domestic gas reservation requirements now moving forward, we're seeing sentiment and appetite for this added capacity turn in a favorable direction. We hold strong confidence in APA's expansion plan and that it will produce benefits for our customers and security holders, just as our earlier expansions along this corridor have done. The AER's recent approval of APA's South West Pipeline expansion shows once more that demand for expansion exists. Turning to Slide 12. Our efforts to help bring the Beetaloo Basin to life have advanced considerably. Construction of the Sturt Plateau pipeline has finished Phase 1 of our Beetaloo development. Gas should begin flowing before long, benefiting Darwin's communities and industry. Phase 2 is moving ahead as we pursue work tied to possibly expanding the SPP through added compression. That work is meant to back the basin's continuing commercialization for our upstream customers and to deliver more energy security for Darwin. In the Beetaloo, our Phase 3 efforts center on linking that basin with LNG markets both domestic and regional. For APA, this represents a multibillion-dollar opportunity of real significance. Should APA build its proposed North to East Australian pipeline, gas would reach Australia's East Coast Gas Grid, and the project would underwrite extending Australia's Gladstone LNG export facilities past the 2030s. That proposal, as it's known, has moved into the formal Environmental Assessment stage. In a similar vein, we are advancing pipeline routes for APA's proposed Darwin to Beetaloo pipeline, which would carry added gas from the Beetaloo up to Darwin, running alongside APA's existing Amadeus Pipeline. Turning to Slide 13, putting money into GPG capacity matters a great deal if Australia's energy system is to stay affordable and dependable through the shift away from baseload coal toward intermittent renewables. Batteries still have a significant part to play in firming renewables, but they cannot deliver system strength the way GPG does when it comes to handling the inertia created by many intermittent renewable systems. APA was glad to announce, in December 2025, a partnership with CS Energy in Queensland aimed at developing the 400-megawatt Brigalow Peaking Power Plant. That agreement is now being finalized, and delivery is advancing well, covering civil and bulk earthworks, turbine procurement, and the awarding of major construction contracts. A new lateral transport and storage pipeline will connect the project to APA's Roma Brisbane Pipeline, with APA also handling delivery of that line. Turning to Slide 14, we've advanced our development pipeline for remote contracted power generation at a number of sites. We're pleased to announce today an agreement with Evolution Mining for development of the Sybella Solar and Battery Project in Mt Isa. Costing $259 million, that project will deliver low-cost, low-emissions energy supporting Evolution's Ernest Henry operations, and it will be firmed by APA's Diamantina Power Station. Sybella shows clearly how the know-how and expertise of the Pilbara Energy crew were drawn on to get this key project up and running in Mt Isa. Our Pilbara operation continues to deliver solid results; for our strategic locations in that area — including the Newman Renewable Energy Hub — planning and approvals work is progressing, so we can serve clients dedicated to cutting carbon from their operations. I'll hand things over now to Garrick, who will walk you through the specifics of how we performed financially.

Garrick Rollason

executive
#3

Adam, thank you, and good morning to all. FY '26 came in as a robust, tidy outcome while we continue to carry out our expansion plan. What particularly pleases me is that we managed to achieve savings sooner than planned while also increasing free cash flow. I'll start with the top-line figures from Slide 16. We posted solid improvement in underlying EBITDA, climbing 8.3% over the year, driven by gains from inflation-indexed tariffs, income from newly added assets, and expense cuts. The underlying EBITDA margin climbed 370 basis points, reaching 77.9%. Free cash flow advanced roughly at the pace of inflation, reflecting stronger earnings and lower costs, partially counterbalanced by higher financing expenses needed to fund growth along with cash tax outlays; and our savings landed ahead of the goal we had set. Moving to Slide 17, I'll explain what drove the 8.3% increase in underlying EBITDA. Earnings rose by $136 million thanks to inflation-linked tariff escalation and contributions from new assets. New earnings came from the Kurri Kurri Lateral and the Atlas to Reedy Creek pipeline, a full year of contribution from Port Hedland Solar and Battery, and inflation-linked tariff escalations throughout the portfolio. We were also pleased to deliver lasting company-wide cost savings of $80 million, which exceeded our $50 million target and included a 21% cut in corporate costs. I'll cover this in more detail on a later slide. Those gains were partly offset by the earnings we had anticipated losing when we divested the noncore Networks and GDI businesses as part of simplifying the company around our core strategy. In addition, milder winter weather this year reduced earnings at VTS, which was partly offset by strong results from our contracted power generation assets. On Slide 18, you'll find a summary of the drivers behind free cash flow, which increased 3.2% to slightly more than $1.1 billion. As we've noted before, the improvement in underlying EBITDA was partly offset by greater interest expense and cash taxes paid. The rise in interest costs reflects added net debt used to fund growth along with a slightly higher average cost of debt. Increased cash taxes stem from ongoing installment payments that started during last year’s second half. The working capital shift booked in our first half—largely tied to one-time timing effects from the divested Networks business—reversed during the year’s second half. Apart from that, we anticipate free cash flow expanding roughly at the inflation rate as earnings keep rising and taxes return to normal; turning now to Slide 19 for a CapEx summary. Our dedication to long-term growth remains through sustained project spending, strengthening our foundations and ensuring asset operations stay safe and reliable. Growth capex has gone toward early-stage work on expanding the East Coast Gas Grid, along with the Sturt Plateau and Brigalow Pipelines and the Brigalow Peaking Power Plant. As Adam noted earlier, we've raised our organic growth CapEx pipeline from $3 billion to approximately $3.5 billion over the coming 3 years. All of that spending fits within our capital allocation framework—it's laid out in the appendix—which targets returns at least 150 basis points above our post-tax WACC, meaning above our hurdle rate. Foundational CapEx ended up under guidance, largely due to project timing, as certain expenditures are moving into FY '27. Despite that, the overall total for foundational CapEx remains the same. Same business CapEx was in line with guidance. Turning to what's ahead, growth should track inflation. On the following slide I'll discuss funding. We can finance our $3.5 billion organic growth pipeline for FY '27 through FY '29 using capacity already on the balance sheet. That pipeline covers Inflight as well as identified growth projects in gas transmission and storage, GPG, remote grid, and other on-grid contracted power generation projects. Adam showed the breakdown of the $3.5 billion on a slide earlier. With this strong balance sheet, active capital management, and predictable capacity-based inflation-linked revenues, we're well-placed to deliver on our $3.5 billion of organic growth opportunities. Next, on Slide 21, I'll discuss the strong progress we've made on our cost reduction target. The main takeaway here is that our enterprise-wide cost reduction effort came in ahead of plan, with $80 million in reductions delivered during FY '26, which beat our $50 million target. That result came from building on the foundational investments we've made in the business over the past 3 years. In addition, we concentrated on simplifying operations by divesting the noncore Networks and GDI businesses, and 725 employees moved over to the new owner as part of that. Those asset sales brought in $101 million of cash proceeds in FY '26 and created value for security holders; with that done, the business is now positioned to deliver lasting, sustainable cost improvements going forward. We anticipate reaching a $100 million annualized run rate in savings for FY '27, which includes the $80 million already delivered during FY '26. On my last slide, I'll cover the guidance we're giving for FY '27. We are today issuing FY '27 underlying EBITDA guidance ranging from $2.26 billion to $2.34 billion. The main things driving earnings growth are tariff escalations tied to inflation along with contributions from new assets, among them the Sturt Plateau Pipeline and Basslink's shift to a regulated asset. Cost reduction efforts should add an incremental $20 million in FY '27, which works out to an annualized FY '27 run rate of $100 million as we keep pushing for sustainable cost and efficiency gains. At the midpoint, guidance implies 5.4% growth year-on-year. So with that, I’ll turn it back over to Adam.

Adam Watson

executive
#4

Thanks, Garrick. Turning to Slide 24, to sum up, we've posted yet another very strong result for FY '26. Our financial outcomes have been strong. Our growth outlook keeps getting better, and our balance sheet is strong, with room to fund both growth and distributions. The guidance we gave today for FY '27 is more proof of our strong momentum, which brings us to our investment thesis on Slide 25. We're in a good position to seize emerging opportunities in an addressable market of more than $100 billion. Our $3.5 billion organic growth pipeline for FY '27 to '29 centres on opportunities that will create value for our security holders, and we're able to fund that growth from our existing balance sheet. Our business model is strong, with inflation-linked revenues and high margins. Our distribution yield is still attractive and our outlook is still strong. I want to thank the whole APA team, who have all contributed to today's fantastic results and to our exciting future. Thanks for your time. Let's go now to Q&A.

Tom Allen

analyst
#5

Congrats on the year-on-year EBITDA margin improvement, which really caught the eye. APA has said it will proceed with this East Coast Grid expansion without firm underwriting, and we need confidence that, despite all the shifts we're currently seeing in the domestic market, there won't be contracting pressure. In today's results, several key East Coast assets in particular posted EBITDA that was either flat or lower in real terms versus a year earlier. Slide 29 shows that, within energy infrastructure, East Coast total EBITDA was flat, I believe, once you exclude WGP and the new Kurri Kurri asset. Tariffs may be rising with CPI, yet as volumes get recontracted, they simply don't seem to be producing nominal EBITDA growth. I think we saw that with Moomba Sydney, the Victorian Transmission System, the Roma Brisbane Pipeline and the Carpentaria Pipeline. So the question is: could you please address what we're seeing there and the main drivers behind those outcomes?

Adam Watson

executive
#6

Yes. Thanks, Simon. First, on your opening remarks, we're incredibly proud of today's results; momentum is strong and the outlook is really positive. I think we've put in a lot of hard yards over a number of years now, and we've positioned the business really well. The margins you mentioned are something we're particularly proud of. And as Garrick said, the cost reductions we've made are structural costs; we took no shortcuts; they are structural and permanent. We think we've got the business in a really strong position. On the East Coast Gas Grid, and I may get some questions on this afterwards, it matters that we keep seeing real strength in demand along the East Coast corridor. The AER's decision on the South West Pipeline to invest in that project is, again, just more evidence that demand in the Southern markets keeps strengthening. Intraday demand is very strong and will remain so, and we need to keep bringing supply from those Northern markets. Just as we did with Stages 1 and 2 with previous compression, Stage 3 will be no different, with compression in the Bulloo Interlink. We're very confident the demand is there. As you know, we don't underwrite those small components of a network through individual contracts; it's all about demand and supply, and demand is very strong. And I have to say that, with the National Gas Review becoming clearer, we've seen a really positive uptick in inquiries, and the conversations have been very productive. So we have a lot of confidence in that regard. But I'll hand it over to Garrick to take you through some of the detail on certain assets.

Garrick Rollason

executive
#7

Thanks, Adam, and thanks, Tom, for that question and for acknowledging the strong result we achieved on underlying EBITDA margin, which is something we take pride in over the past couple of years. I'll address a couple of the assets you brought up, and it's probably worth reminding everyone that in FY '25, regarding the movement of Sydney Pipeline, we did gain from one-off insurance proceeds of $13 million MSCP. So once you normalize for that, we've actually seen a strong performance in movement to Sydney Pipe during the year. As you mentioned, VTS was probably the one asset that underperformed relative to what we had expected over the course of the year. And that was mainly driven by 2 things. First, the milder winter, and second, very stable electricity markets with high coal availability. I suppose the benefit from an API perspective is that we run a portfolio of really strong operating assets; so when you look at the Board, at times, market events do occur, which drive positive earnings outcomes. And it was probably a year in which we didn't see many of those. So assets performed broadly in line with our expectations, probably with the exception of VTS.

Tom Allen

analyst
#8

Appreciate the color, Garrick and Adam. Moving on to my second question. The upside in the Northern Territory seems pretty compelling. That said, if Beetaloo's upstream outcome is more or less all-or-nothing, can you speak to how much medium-term EBITDA growth could come from elsewhere should Beetaloo fail to become the largest onshore upstream development in Australia since Queensland CSG? You've already flagged chances to back remote power, data centers, and gas-fired generation. I'd like to get a handle on how big those are, and if Beetaloo doesn't work out, do we have sufficient capacity to deliver roughly $500 million of EBITDA growth across the coming 5 years?

Adam Watson

executive
#9

Yeah, thanks Tom. Well, the first point I'd make is that if you look at the AEMO 2026 GSOO 2C 2P Reserves and Resources, there is a substantial amount of capacity already in place to serve the East Coast without Beetaloo. We're quite confident that Beetaloo keeps advancing very nicely. Absolutely, you’re right that we need to keep moving forward on that positive path, and I’d frame it as showing that momentum continuing across roughly the next 12 months and then making it tangible. So in our view Beetaloo will be excellent for the domestic market, and it will be extremely important for Australia’s LNG export market—which explains why there is such a strong imperative for that asset, or rather that basin, to perform well. At the same time, if you look at Surat, it has ample capacity in the market, and there are additional new basins such as the Taroom Trough that are also being explored. We aren't worried about gas supply over time. For decades we've operated in a market where you have to keep adding supply to keep up with demand, and we don't see that easing.

Uwan Minogue

analyst
#10

Great work on another solid quarter. To begin, now that Networks and GDI have been sold off, do you see anything else in the portfolio that isn't core and could unlock more balance sheet capacity?

Adam Watson

executive
#11

Thank you, Uwan. To start, we're very happy about the fantastic outcome we achieved for APA security holders, and also about how the people from the Networks and GDI operations have moved across to the new owner. Doing that in a manner that was highly measured and highly respectful is something we're extremely proud of, and we think it has been a positive, a real win-win for all involved. That's the first thing. That group of assets was plainly noncore for us. During the year, one of the initiatives we carried out—along with the cost reduction efforts—was a deliberate push to simplify the business, and that clearly made sense. As for the remainder of the portfolio, our usual approach is to develop Networks, and the East Coast Gas Grid we were just discussing illustrates that. What we're doing in the Pilbara, and the announcement made today with Sybella in Mt Isa, is all centered on establishing a starting position and then expanding the network, collaborating with our customers, and generating greater value as time goes on. We'll keep reviewing assets and examining our portfolio going forward. Definitely, that's among the options available to us for financing expansion past the $3.5 billion organic growth pipeline. That pipeline has all the funding it needs and is well supported. Past that point, clearly, it's a possible option for us. Still, we aren't able right now to divest anything, though we'll keep watching and weighing it so that if an asset would deliver greater value for our security holders under someone else's ownership and strategic upside is limited, we'd consider it.

Uwan Minogue

analyst
#12

Got it. You also had some remarks about the Domestic Gas Reservation Policy. Could you walk us through where things stand right now? And perhaps take us back over the sensitivities, I suppose in both the best case and the worst case, on volumes and earnings across the East Coast Network.

Adam Watson

executive
#13

Yeah. Well, first of all, without a Gas Reservation Policy, demand for gas is going to remain, and supply will always naturally satisfy that demand. What we consistently push for, though, is a market dynamic offering a high degree of certainty so producers can contract with the demand centers, which in the end are our customers; and that simply makes — it builds a more structured setting for the energy market to trade in. We've definitely witnessed, with the announcement made a while back that there would be a National Gas Review, that producers and customers were quite understandably, if you put yourself in their position, holding back and waiting to see how that would unfold; then came the Federal Government's recent announcements regarding the frameworks for how they see this moving forward. And once more, they've made — they gave notice that they intend to finish this by the end of the year. It appears to be going in the right direction. So for us, what matters most is making sure it truly delivers that degree of certainty. The single thing we've been concentrating on is ensuring there are no openings to effectively shift the goalposts down the track; and one of those has involved Ministerial interference. That concerns us. But then again, I believe the market has spoken out strongly on that, and what we've seen the government do, viewed positively, is listen as they've been engaging with the various stakeholders across recent months; so yes, we feel it's moving in the right direction, and we're seeing that through the positive uplift in the interactions we're having with our customers.

Uwan Minogue

analyst
#14

Got it — and let me just slip in one more quick question, this time for Garrick. You've clearly done an excellent job on the cost base through FY '26 and on into FY '27. Is there anything that will need to be added back into the business, likely in FY '28 and after, as you set yourselves up for the next stage of growth — or should we keep thinking in terms of annual savings over the longer term?

Garrick Rollason

executive
#15

Yes. Thanks. That's a really good question, and like you said, it's a fantastic result delivered right across the business: $80 million in savings, and $100 million for the full year in FY '27. On Page 22, we did highlight one point: our investment in growth-related operating expenses—or total growth spending—is still increasing. As a result, some of that will naturally carry over into OpEx. So in FY '27 we expect roughly a $10 million rise in growth operating expenditure, and that is partly offsetting certain savings we would otherwise have realized during FY '27. On the wider savings front, we keep hunting for ways to get leaner on costs, and we're steadily building out—especially in AI, data, process and systems—methods that let us achieve customer outcomes more efficiently. That work will carry on, and we'll of course inform the market whenever additional cost reductions are ready for us to disclose.

Nik Burns

analyst
#16

Nice work on those results, and that jump in free cash flow really stands out. First off, I want to ask about the three-year organic growth outlook that you've revised and broadened. Thanks for adding more detail on Slide 10 about how that growth splits up. That said, Adam, you know how it goes — when a chart shows up without a Y axis, all of us end up using imaginary rulers and making our best guesses. Maybe I'm reading it wrong, but the bar for Brigalow Peaking Power Plant appears to be around six times the size of the Sybella Creek Solar and Battery Project bar sitting above it. And you mentioned today that Sybella Creek comes in at roughly $259 million. Taking that as my reference point, I get a Brigalow number of roughly $1.5 billion to $1.6 billion for APA's share. I'm just checking whether that's the correct reading or whether I'm overinterpreting the chart.

Adam Watson

executive
#17

Yes. Appreciate the question. Let me be very explicit about what makes up that $3.5 billion. And I might as well address upfront a question I'm certain will come, namely why it shifted from $3 billion to $3.5 billion. Broadly speaking, we simply continue to observe demand for new infrastructure rising and accelerating. So, I mention that to highlight the bigger opportunities ahead of us over the longer term—we're quite confident there's substantial growth available to us in that area. And as you can well imagine, we've been extremely rigorous these past few years about selecting only projects that clear our hurdle rates and our other financial commitments, and we've done exactly that and take great pride in it. If I break down the components of the $3.5 billion—that essentially covers the Brigalow Pipeline, which we've already told the market about, roughly $150 million. On Brigalow Gas Peaking Power Plant, we haven't given an exact figure since FID hasn't been reached. What we've indicated, though, is a cost of roughly $1 billion for the project. That said, a significant caveat applies, since final negotiations are still underway. And clearly, things have been moving forward as we finalize construction contracts and other civil works. East Coast Gas Grid Stage 3A came in at $260 million, and East Coast Gas Grid Expansion 3B at approximately $800 million. As you mentioned, today we announced Sybella at $260 million and South West Pipeline at $213 million. And so, yes, one thing that gives us a lot of satisfaction, broadly speaking, is that if you look back and consider where things stood, let's say, 3 years ago, we had a pipeline worth $1.4 billion, and to be fair, plenty of work was happening behind the scenes, and there was evidence supporting it, but we hadn't actually reached FID on any of those projects. Over the last 3 years that has now grown by 150%, and we have a $3.5 billion pipeline, and I've been able to describe to you 80%, 90% of what it involves. So yes, we feel very positive about it, and it is all fully funded.

Nik Burns

analyst
#18

Got it. And regarding Brigalow, like you mentioned, you're handing out the major construction contracts right now. Sounds as though you're quite near to a final investment decision on that. Could you take us through what still has to happen before FID? And you have a <<inaudible>> around targeting operations from CY '28, but is there a chance it slips even more if FID isn't reached over the next few months?

Adam Watson

executive
#19

Yeah. Appreciate the question. The way we handle these large projects alongside our customers is that you go into early works or, in this instance, a joint development agreement, where you basically establish the parameters and agree on terms, the major commercial terms, so you can move ahead. And you have a solid degree of commitment and conviction that you'll carry it through to FID; that's precisely what we did with Brigalow; we signed up to a joint development agreement so we could work in lockstep with our customer, with CS Energy, to procure turbines, to advance site works, civil works, bridges, platforms, bulk earth moving, all those kinds of things, and at the same time, work through the various contracts for construction and delivery too. And as you'd understand, that always takes time. But importantly, you do it in a manner where your commitment is strong and you're operating in partnership. We're extremely pleased with how the Queensland Government has approached partnering with the private sector; it's been part of the Queensland Energy road map. And I think what we've announced today in Sybella is another great example of how the private sector can deliver on what the Queensland Government is setting out to achieve. So coming back to Brigalow, we keep working through that with our customer and we'd like to reach FID very shortly.

Gordon Ramsay

analyst
#20

Adam, Garrick, nice work on the solid numbers today. I want to ask about the Beetaloo. To start, congratulations on finishing Phase 1 of the Sturt Plateau Pipeline. You mentioned that adding compression might take that line from 40 terajoules per day up to 100 terajoules per day. What would it take to make that commitment? And can you give me a rough idea of what it would cost?

Adam Watson

executive
#21

Sure. Thanks, Gordon. We've long been a business that recognizes the role we play in helping particular upstream basins get developed. The Beetaloo is the same. Everyone is aware that Beetaloo's location ranks among its major advantages, since it lets us stay highly attentive to what the community needs and collaborate with traditional owners as well as government to make the project a reality. A difficulty stemming from such a remote setting is the considerable infrastructure required to turn everything into something real. We recognize that we have a significant role to fulfill in that regard; and — this resembles a point I made before regarding efforts such as Brigalow and operating in close alignment with your customer. One action we take is clearly examining things through a robust risk perspective, yet we are prepared — provided there is sufficient evidence — to have confidence in ourselves and in our customers so that progress continues. The Sturt Plateau Pipeline makes us genuinely proud, since it lets our customers bring that to market and supplies gas to Darwin and its customers, helping them sidestep flaring and similar measures in order to get it going. Stage 2 is essentially focused on scaling that up and allowing additional output as additional wells are drilled to make it a reality. But, Gordon, as you understand better than anybody, you eventually hit a point where the necessary scale exists. That's the reason we're putting in considerable effort—and have been for several years, as you're aware—to bring projects like the North East Pipeline into operation, to head north from the Beetaloo down to Darwin too, and to ensure we can offer choices to our customers. Yet infrastructure is an odd business. It takes a very long time. Then suddenly, as soon as those projects turn concrete, everyone's asking how fast we can get it done. So we believe the balance is where it should be, and once more the well results keep coming in really strong, and we'll continue supporting it until they stop being good — though we don't expect that to happen; we see the outlook as extremely strong, and several new participants, major ones in my view, are validating how appealing it is and their readiness to support the basin.

Gordon Ramsay

analyst
#22

Back on the Beetaloo — I found something quite interesting in remarks I heard in Adelaide from the Ichthys CEO — apologies, the INPEX CEO, speaking about Ichthys Train 3. He mentioned that he could envision Beetaloo underpinning a potential future development tied to an Ichthys Train 3 expansion. When you refer to that indicative pipeline to Darwin, is that roughly the sizing you mean? Might it potentially take in volumes for Ichthys LNG, or perhaps even a Darwin LNG expansion? Is that the sort of thinking you have in mind if this extra pipeline gets built down the track — it's clearly not imminent — but some indication of going up to Darwin — the pipeline to Darwin?

Adam Watson

executive
#23

Yes, that's a really good question, Gordon, and an important one too, because when you look at the basin, the scale is significant. We've heard it could be as big as the Permian or the Marcellus basins in the U.S; it could be very significant, and the people drilling there aren't doing it just to produce small amounts of gas. Supporting Darwin specifically over the near term is great, though their big priority is ensuring this can scale. So as we assess the pipeline, we're modeling several different cases for how large that pipe might be. Happily, there are excellent routes that let us lay our pipelines beside corridors that already exist. Why does that matter? Since we already know the landowners, have solid ties with local communities, and can get onto sites, we're able to speed up delivery. And broadly speaking, this is something we do very well. So that's definitely on our radar. Looking at the project's economics on a standalone basis, the pipeline itself is substantial. Yet when you weigh those economics — and consider the counterfactual of a higher-cost pipeline versus what you might see in other places, the U.S. for instance — you have to factor in this: on Australia's East Coast, take Gladstone, where 6 trains are operating. I'm told replacing a single train runs about $6 billion these days, so that's roughly $36 billion in assets sitting there that will essentially be idle from the beginning of the 2030s through the end of that decade. Also in Darwin, there are a pair of trains whose replacement would run roughly $12 billion. That means close to $50 billion in assets sit unused come the 2030s, so constructing a pipeline that lets that already-built infrastructure be put to work—avoiding the need for new LNG trains—is a genuinely compelling economic result for our customers, which explains why they are charging ahead with real determination and keeping such a close eye on it.

Rob Koh

analyst
#24

Can I ask a question regarding the new Sybella project? Congrats on the announcement. Once it's operational, should we expect a typical high single-digit EBITDA yield?

Adam Watson

executive
#25

In fact, looking back at the majority of projects we've finished lately — we covered this during the half results with the Pilbara investment — from an investment perspective, we're achieving low double-digit yields on those projects. So, we don't publicly provide specific figures for any individual project. We do aim for project returns that beat our cost of capital by a minimum of 150 basis points, and you can more or less work backward to figure out the yield on these projects where — with this one, a ramp-up isn't really a given. After delivery and commissioning there'll be a quite modest ramp-up, though clearly it scales up fast. So yes, we feel quite good about this. What matters a great deal, though, is that none of these projects would ever get moving unless your customer ends up with a cheaper levelized cost of energy. And what makes us genuinely proud is our ability to give that customer a solution that brings their costs down, delivers a truly appealing renewable result, and has it firmed up by the Diamantina Power Station — which, again, I'm certain you've looked into, but we're truly thrilled to be building projects in the area that can support Diamantina even further across the longer term.

Rob Koh

analyst
#26

All right. Yeah, I was just about to inquire about what part Diamantina plays in this project. Does Thomson and Diamantina have significantly more capacity available? I can't recall the details of the other asset you hold in that area when it comes to backing similar hybrid projects.

Adam Watson

executive
#27

Yeah, that's right; and as time goes on, those — we're all aware that Diamantina and the assets around it were, as time goes on through the 2040s, going to turn into more of a peaking asset. So this essentially just supports those projects across a longer stretch of time. So yeah, we're quite happy with that.

Garrick Rollason

executive
#28

Apologies, Rob — this is Garrick. One more thing I meant to mention: clearly this is a terrific result for both Evolution Mine and APA, yet putting the battery in at Mt Isa is likewise a terrific result for the residents of Mt Isa and the companies operating there, simply in terms of supply security. So it's a terrific result for APA and Evolution, and on top of that a terrific result for Mt Isa in a broader sense.

Rob Koh

analyst
#29

Yes, I see. Okay. Let me turn to one of the projects on your growth list, the BDP, the Beetaloo to Darwin Pipeline. I appreciate it's very early days, but could you give us some sense of the dimensions of that pipe so we can size it?

Adam Watson

executive
#30

Well, on dimensions — again, as we said earlier, and Gordon mentioned INPEX, which has trains up there that obviously this could backfill in the 2030s — this could be a large diameter pipe. But internally, and together with our customers, we're examining a range of scenarios. Still, yes, in short, it would be a large diameter pipe, roughly 600 kilometers to get there. Very importantly, we've got the existing Amadeus Pipeline, which offers one route where, again, as I mentioned, we could use that corridor and work with our existing landholders and stakeholders to bring that product up north to Darwin. There are a couple of other routes we're looking at as well. So yes, early days, but we're motoring ahead with planning and approvals and all the various pre-work that happens behind the scenes, because again, if we really think about it and Beetaloo meets the potential we're all hoping for, then it could be big, and we want to be ready for it.

Rob Koh

analyst
#31

Yeah. All right, that works for me. Sure. And on your NEAP Project, it seems like you're putting in a great deal of — still putting in a great deal of effort there. Could you maybe weigh in, yes, on the alternative path another firm is putting forward and on what makes yours superior?

Adam Watson

executive
#32

Well, there are — as with any pipeline, transmission line, or piece of energy infrastructure, several routes exist for making it a reality. What we gain from moving the gas out of the Beetaloo southward to the South West pipeline and even eastward over to Gladstone is this: first, it lets that gas reach the East Coast Gas Group for domestic supply in the most efficient way possible. That fits well with the rules on reserving gas for domestic use. The other option would be running that pipeline from the Beetaloo essentially straight east to Gladstone — yet after that, what's the route for moving the gas from Gladstone down to the East Coast market? So there are various methods for delivering it. Taking it down to the south too, and making use of the infrastructure already in place, since this ties back to the LNG trains — from an export standpoint, substantial capacity is going to be open, both at the trains and through the pipeline capacity with WGP, which we hold and which runs out in 2035, for instance. So in short, this simply gives you a highly efficient route for delivering domestic gas to market and leveraging existing infrastructure to move that gas to the LNG export facilities.

Rob Koh

analyst
#33

All right. Great. My following question concerns Slide 22, and I'm picking up on what Nik was asking regarding measurement. If on Slide 22 — that's your year-on-year EBITDA bridge — I take the green cost initiative as roughly $20 million, that would imply the new asset contribution lands somewhere around $50 million to $60 million; and I can sort of arrive at $20 million for Basslink and perhaps, I'm not sure, $5 million to $6 million for SPP. Could you perhaps just confirm whether the AI has measured that correctly, and give us some guidance on what else could be in there.

Garrick Rollason

executive
#34

Rob, I think the AI rules aren't functioning particularly well today. What we've observed is new assets adding approximately $40 million of incremental EBITDA. So, as you mention, most of that will come through the change to the regulated assets at Basslink. Relative to how things performed in '26, we anticipate roughly $33 million of incremental earnings from Basslink and then, as you say, the remainder from Sturt Plateau pipeline.

Adam Watson

executive
#35

All right, that’s clear. One last question from me, if you’ll permit it: could you give us a bit of detail on how you’ve reshaped the foundation CapEx? My impression is that you — for lack of a better way to put it — spent less than expected in FY ’26, but then you’ve moved the $100 million to $120 million out slightly. So I take it there isn’t any increase in the overall total, but could you give us a little more detail on what’s driving that?

Garrick Rollason

executive
#36

Rob, you're exactly right — it came down to timing, and that let us shift part of that spending out of '26 and into '27. The overall shape of it remains identical to what we laid out before. As shown on Slide 19, we anticipate that figure landing somewhere in the range of $100 million to $120 million each year across '27 and '28, easing to $80 million by '29, with further moderation expected after that.

Adam Watson

executive
#37

And the reason for the push, the delay?

Garrick Rollason

executive
#38

Mostly because we can, especially when it comes to the schedule for a few of the things tied to cutting emissions, since we were in fact doing better in other areas. So let me return to corporate finance: if you don't need to spend it, and you're achieving those emission reductions somewhere else, then clearly that's the sensible way to go.

Adam Watson

executive
#39

Yes, Rob, we did — and one of the achievements our team takes real pride in is that we managed to hit our targets without giving up a single carbon credit over the course of the year. That has played a major part, and I'm genuinely proud of what our people have accomplished in driving down emissions at our assets, and also in simply making those assets more efficient through the work they're doing. So we're constantly asking how we can make the best use of — how we put capital to work and how we use our people's time. And wherever we're able to postpone something, we'll postpone it.

Ian Myles

analyst
#40

Now, on your point about data centers, could you expand a bit on the strategy there? Data centers are increasingly expected to be market facing. I'd like to know where you think your competitive advantage lies relative to the AGLs, the Origins, the Iberdrolas, who are also providing these kinds of services.

Adam Watson

executive
#41

Certainly. In much the same way as our current business, this is a sizable market with a number of participants, and we're not the only player around. So to begin with, we see a very substantial market, not only for data centers but also for GPG, for example, to serve our power generation customers, and once again, we're firmly of the view that our remote grid strategy will keep on. Apologies—there was some background noise. Yes, our grid strategy will continue to unfold. Take our remote grid approach together with a new Sybella, which we announced today as an illustration: that is a purely behind-the-meter solution. As a result, we can deliver renewable generation into the market, pair it with a battery, and firm it using an existing facility. And I must say, doing all of that as one package may sound easy to describe, but it is extremely, extremely, extremely complex—and we possess genuine expertise and the capability to pull it together and run it efficiently and effectively over the long term for our customers. We have a number of locations that are highly appealing for behind-the-meter options. Once more, that power can serve either as generation supporting our power generation clients or for data centers; and we've put substantial effort into areas like our sourcing approaches aimed at becoming the preferred supplier for OEM manufacturers including Siemens, GE and solar turbines; we made an announcement quite recently with Siemens Energy, something we're extremely proud of, and it puts us in a good position to act quickly. So look, we believe we possess considerable strong capability. And that isn't to suggest others lack comparable capability too, but we believe the market is large enough for the opportunity to be appealing.

Ian Myles

analyst
#42

Thanks for the comment about multiple sites. I'm just a little bit confused, honestly. On data centers — do you mean you've actually found a parcel of land beside a data center that's already been approved, or a potential data center customer, or is this something entirely separate from the data centers themselves?

Adam Watson

executive
#43

No, no, no. What we're focused on is — take, for instance, the Federal Government's stance on data center development, especially for the hyperscalers, and the AEMC has confirmed this regarding the need to bring power, and they've been extremely clear on what that involves. It has to be renewables led, it has to be supported, it has to be able to support the grid, and it has to be firmed with batteries and gas-fired power generation. That's what we do. That is precisely what we do. So we believe we're incredibly well-positioned to deliver that. And we operate — take our Pipeline business, we have over 15,000 kilometers of pipelines across Australia, in remote regions and closer to the cities. So we're not trying to suggest we'll simply show up, build something, and connect you into the grid. What we're saying is that we have a lot of land where you've got the supply of gas and the supply of electricity running through. And yes, that could be attractive for a data center.

Ian Myles

analyst
#44

So really, you're hoping to have that data center built on property you own?

Adam Watson

executive
#45

Sure, that could be an opportunity.

Ian Myles

analyst
#46

Alright. This is just a quick question, and perhaps I've misunderstood. Your Alinta business — the whole thing rose by roughly $5 million. And on one of those slides, you mentioned that Port Hedland was up $14 million. I'm simply curious as to why the inland business declined by around $10 million. Maybe I've misread the figures.

Garrick Rollason

executive
#47

Ian, Garrick speaking. I'll handle that answer. Your reading is right. Basically, the sole meaningful variance between the periods came from the fact that Newman Power Station generated some safeguard mechanism credit revenue in FY '25, which we understood would not repeat in FY '26; in fact, we are above the safeguard mechanism target for '26. Looking ahead, customers will bear the impact in '26, yet it wasn't there in '26. That lines up completely with the modeling and business case at the time we bought the asset, so nothing caught us off guard. So that was essentially a one-time, let's say, negative in '26 compared with what we had in '25 and what lies ahead.

Ian Myles

analyst
#48

All right, that's excellent. Now regarding the battery at Sybella Solar Farm — when you kicked things off at Dugald Creek, as I recall, Diamantina's performance became less than optimal owing to how it interacted with the solar farm. Will you be able to realise the benefit of that better Diamantina performance once the battery is integrated, or does the customer share in that?

Adam Watson

executive
#49

No. Put briefly, the answer is yes. One takeaway we gained from the Dugald River Solar Farm was this: a battery should have been installed there. And although the gas-fired power generator clearly delivers strong firming solutions, it did not deliver certain stability benefits that a battery gives you in those areas, which explains why we have batteries at sites such as Port Hedland and Newman to back up our operations there too. So yes, look, we're delighted to be working with our customer, who requires a battery to support development of the Sybella Creek Solar Farm. But clearly that battery, as Garrick mentioned earlier, will also deliver stability for the wider network in Mt Isa.

Ian Myles

analyst
#50

All right. And regarding data centers on that other front, is it only aero-derivatives you mean, or do reciprocal engines come into it too?

Adam Watson

executive
#51

Ian, the customer leads us, so it truly hinges on what that customer requires, and we have know-how with both. We deploy aeros at several sites; we deploy frame machines at several sites; it really comes down to what the customer requires. There are cases in which both kinds of machine can sit on one site, based on what you need since, once more, if you consider what the federal government is aiming toward, you must also be able to feed power back to the grid. So you could combine that in multiple ways.

Ian Myles

analyst
#52

And regarding that, a few aero-derivatives are currently up for auction owing to a company that failed. Would you purchase them on a speculative basis, or does that kind of item need backing from a customer?

Adam Watson

executive
#53

When it comes to used equipment, we would be very...

Ian Myles

analyst
#54

Those have not been put to use at any point.

Adam Watson

executive
#55

Right. Well, that's true, though they do come with specifications. I probably shouldn't describe them as secondhand in the sense of used, but given how they're specified, it isn't simply a matter of handing you a fresh set of keys to a new car so you can go driving; you have to entirely — possibly entirely — reconfigure the equipment. So no, generally we purchase our equipment by working together with our partner, in situations where we're confident we have line of sight on how those assets will be deployed.

Ian Myles

analyst
#56

And one last question. In the past you mentioned possibly looking to extend the Wallumbilla Gladstone Pipeline. I'm just curious how that progress might be going?

Adam Watson

executive
#57

Talks about WGP will take place at a point when projects such as the Beetaloo and the Taroom Trough are confirmed. So really, as you're aware, the entire reason WGP was set up to expire in 2035 is that this matched the schedule for when the gas flows for Gladstone were also due to expire. So we've talked fairly openly about the dream — the panacea for us is that not only can we bring a new basin like the Beetaloo to life, and we're also working with our customers in the Taroom Trough. But to the point — if they reach a stage where they're prepared to contract for those new infrastructure assets to support those basins, then that would be the natural moment when you'd be looking to enter negotiations to extend that contract; but again, it's up to the customer to do that; we can dream as much as we like. But ultimately, our customers are going to want to do that with us. And obviously, we've had conversations ahead of whenever that may be to show our intent, and we're certainly there for our customers if and when they need us.

Cameron Needham

analyst
#58

Only one question from me. I believe the bulk of the important questions have already been covered. Given that the organic growth pipeline now sits at roughly $3.5 billion, and you're covering a far broader range of infrastructure classes, how do you think about the ideal breadth when it comes to deploying capital? And internally, I suppose, how are you assessing your capacity to execute, particularly in light of the larger growth pipeline and the sheer amount of activity you have going on?

Adam Watson

executive
#59

Yes, that's a good question, Cameron. And I believe it matters when we consider the opportunities in front of us. Once again, we truly want to be led by our customers. So we won't head out and speculatively attempt to develop things while hoping the customer turns up; and with that in mind, we'll keep working alongside our customers, and we have — we've stayed very focused on the key markets, and we've been quite transparent about the key projects we intend to pursue. You can see that projects such as the Beetaloo could be very significant; and clearly we want to make sure, internally, that we possess the right capability to develop, deliver and operate those projects, and we've done considerable work over the last few years to build our capability in that area; we mentioned earlier the work we've done with the OEMs to get strategic supply arrangements in place and also to make sure that we have, for instance, a suite of contractors we can partner with to bring those projects to life. On the balance sheet, we're always confident — if you deliver projects where you're disciplined, you allocate capital to projects that deliver strong returns, the capital will be there. But we have plenty of options. And Garrick, it's probably worth just reminding everyone of the funding options we look towards.

Garrick Rollason

executive
#60

Yes, absolutely — and thank you for asking, Cameron. It's clearly a strong situation for us, given the $3.5 billion in fully funded growth CapEx we've announced. Basically, we refer to our capital allocation framework, which appears in the appendix to the presentation, and we consider where opportunities exist to put capital to work in ways that add value for our security holders. That's essentially our approach, and we've discussed the target returns for every one of our projects. On the funding side, we're plainly in a very solid position from a balance sheet standpoint right now. Still, we have a variety of funding levers available to pull. These include additional hybrid issuances, partnering with others, structured equity and similar options that will let us support further growth. So from an infrastructure business standpoint, it's a great position to be in.

Suraj Nebhani

analyst
#61

Just a few quick questions, and these sort of follow on from what Ian asked about the data center side. I suppose I'd just like to dig into that a bit, Adam. Is what you're telling us that — if you look at the U.S., a number of your large energy peers are out there constructing gas-fired power grids on site, backed up by renewables, and that's what feeds the data center? Is that something you're looking to do, or is it more about building these possible behind-the-meter solutions in regional spots where there's grid connectivity?

Adam Watson

executive
#62

Yeah, Suraj — the short answer is yes. In that kind of scenario, we would work alongside a data center developer and a customer, teaming up with them at a location so that we can provide that behind-the-meter solution. And clearly, from where Australia sits — and I believe this applies globally as well — the direction of travel is this: a meaningful renewable energy share has to be there, and beyond that it has to be firmed. So generally you'll want a battery at the site, plus you'll need GPG for the times when there's no sun and no wind, and also to supply system strength — not only to the site, but so that system strength can be pushed back into the grid. When it comes to what governments and the AEMC describe as firming and system strength, a gas-fired power generator's spinning reserves deliver exactly that. I want to be clear: constructing sheds isn't something we're pursuing. The data center build is not our line of work. So I don't think anyone was given the impression that this is where our attention lies. That said, as seen for example in the U.S., we're confident in our strong ability to do it. Even so, we'll stay highly disciplined and sharply focused on deploying capital in ways that generate value. Looking at how we've broadened our operations — our approach may seem varied, yet it fits inside a pretty tight structure centered on gas pipelines, storage, and power generation. To complete that picture, Sybella keeps coming to mind. It's a strong illustration, even though here it serves a mining client in Mt Isa, but the same template applies. It's precisely that identical template of pairing renewable generation with a battery, firmed up by gas. Once more, we carry that out nationwide, and we believe we hold solid competitive edges there.

Suraj Nebhani

analyst
#63

Just so I'm clear, Adam, would that power be fed into the grid, or does it work only off-grid, the way Sybella does?

Adam Watson

executive
#64

Well, the government's position is that the grid needs strengthening, and they've made it pretty plain that they expect you to be able to sit behind the meter. So your — I suppose your — for lack of a better way to put it, your main aim is supplying the data center right there on site, yet at the same time you have to be hooked up to the grid, so that when the grid requires stability or reinforcement, you can send your power back to it.

Suraj Nebhani

analyst
#65

Understood. And I believe the other major question we're weighing among ourselves, and probably across the industry too, is this: with all these data center energy requirements, could coal remain in the system for a longer period? And what would that mean for your business and some of those opportunities?

Adam Watson

executive
#66

Yes, that's an interesting discussion, and the sort of factual argument is that if coal must keep running longer because of the demand being placed on the energy market from data center growth, then by the same logic, more gas-fired power generation should be needed to support the new developments; and again, I think AEMO has indicated that with their latest GSOO, particularly regarding the intraday volatility you observe; so again, that's why we feel very confident about the level of growth. It's not — for us, it isn't a matter of whether there's enough growth out there. It's 14 gigawatts of GPG that needs to be developed. The remote grid decarbonization journey is one you're very familiar with. And the demands from data centers could be anything. But what we know is that the grid is already constrained. There is some capacity, obviously, available, but it's being soaked up very, very quickly by the data center projects that are in flight. The question is what happens next. And I think that's where GPG, renewable power generation, the whole Sybella example, could become a potential growth leg for us and the industry more broadly.

Nathan Lead

analyst
#67

Adam, I'd like to pick up where we left off on the data center topic. As I remember it, you had a Melbourne location tied to a potential GPG project. Is that still in play? And could it eventually turn into a colocation opportunity for a data center?

Adam Watson

executive
#68

Yes, and thank you, Nathan. So, what we have is — around 12 sites, if I'm not mistaken, that were set aside two or three years back for GPG, meaning power generation locations nationwide. And, as I've said before, those locations are able to serve several kinds of customers. You can view a data center as a separate customer base. The product itself doesn't change — only the customer base does. So indeed, we hold one in Victoria. We do have a few in New South Wales, Queensland, and Western Australia. They're scattered across the country; and — don't get me wrong, it's not like we're actively trying to develop all 12. But the key point is that I think we hold some pretty appealing sites. And obviously, we possess a skill set that we consider unmatched, plus we have strategic partnerships in place covering certain critical long lead items too. And look, maybe just — it's obviously a subject people are interested in, and it connects to what Suraj asked about earlier and the point made regarding the wider general load on the energy market. We see that as beneficial for the assets we already have. I realize it's simple to fixate on the growth angle, yet we believe it additionally supports underwriting those existing assets across a lengthy horizon. And our stance has consistently been firm — with data backing it — that demand for these assets, and genuine necessity, will extend far past the 2050s; and bringing additional load from a sector like data centers, in my view, simply reinforces that further and highlights how important our assets are. So yes, it's a fascinating area and everyone's discussing it, without question, but clearly it represents a possible growth market.

Nathan Lead

analyst
#69

Yes, absolutely. And the second question: if I look at the work in progress account inside PPE, Note 11, it seems there was close to $1.6 billion of CapEx commissioned across the last 2 financial years. You mentioned FY '26 had $70 million of new asset EBITDA contribution, and then in FY '27 you're only going to get, I suppose, something like $6 million to $7 million coming through. Does that represent the full earnings power of the growth CapEx that sat in that $1.6 billion? And of that $1.6 billion, how much was actually growth CapEx, I suppose?

Garrick Rollason

executive
#70

Yes. Thanks, Nathan, for the question. So CWIP, obviously, what flows through it isn't only growth CapEx; SIB and foundational CapEx also go through there, so you need to be aware of that. When I look at the balance of '25, which I think was about $1 billion, and the balance of '26, which is about $800 million — call it $850-odd million — we've seen Port Hedland Solar and BESS move out of CWIP into PP&E, some spending on MSEP do the same, and then a shift toward projects we've started, things such as Sturt Plateau Pipeline, which I think still sits within CWIP at balance sheet date, some of the work around the East Coast Gas Grid, and some of the Brigalow Pipeline work as well. So that's the kind of detail around the movements period-on-period. But I think fundamentally your question is whether we're getting the returns we seek on the assets we've brought into operation and recognized the revenues on over the last couple of years. And we're really happy that we are hitting our target return hurdles that we've talked about a number of times, across the assets we're constructing now and the assets we've brought online as well. Some of them — there's obviously South West Pipeline, which is a regulated asset and gets a regulated return. We've talked in the past around the returns on Kurri Kurri Lateral Pipeline that reflected the time at which the deal was done. But certainly, the big projects, the growth projects that have come to life and are coming through both our balance sheet and our P&L now and into the future, are hitting and exceeding those target hurdle rates.

Nathan Lead

analyst
#71

Yeah. All right. So just so I'm clear, of that $1.6 billion, what portion counts as growth CapEx?

Garrick Rollason

executive
#72

I don't have that figure right in front of me, but let me dig it out and get back to you.

Nathan Lead

analyst
#73

All right. So, Adam, regarding that $3.5 billion growth CapEx pipeline spanning FY '27 to '29, what's the right way for us to think about how earnings ramp up in connection with that spending? At what point should we expect the earnings contribution from that spend to really reach full tilt?

Adam Watson

executive
#74

Yeah. Well, let me try to give you some directional help here. Obviously, Kurri Kurri Lateral, Port Hedland Solar and Battery, and Atlas to Reedy Creek have all come through during this year, which is very positive. The Sturt Plateau Pipeline, a $66 million project, will feed through for most of 2027, and it isn't really a ramp-up, since it's an asset dedicated to a particular customer. So it picks up quickly. On Brigalow Pipeline, we've said it will be available toward the end of 2027. The Brigalow asset itself will be in 2028. So you'd imagine that if the pipeline is '27 and the asset is '28, the two are going to be reasonably close together, though there's still a bit of water to go under the bridge there. East Coast Gas Grid projects, as we all know, take a couple of years to ramp up. You're trying to bring that product to meet demand, but it simply does take a couple of years to ramp up. Still, I think the evidence you have behind you from what you saw on Stages 1 and 2 gives you an indication of how that played out; and again, demand is there, and you've got some pretty big assets coming out, particularly in 2028 in Victoria. So that could ramp up reasonably quickly. Sybella will be a quick ramp-up, and we've said today that it will be mid-2028. And then the South West Pipeline becomes a regulated asset. So effectively, you're at 100% straightaway, and that's mid-2029.

Adam Watson

executive
#75

Thanks a lot for the questions today — I really appreciate them. Being able to bring such a strong result to life is helpful, and I think the opportunities have been well covered throughout the day, so it's been a great dialogue. Once more I'd like to leave you with the main takeaways from today's result. We've delivered another strong financial result, and in our view the outlook keeps showing strength, which encourages us a great deal. Our portfolio of assets is a great one, and from a growth perspective our outlook is compelling — and I think we've gone through that a lot today to evidence it for you. Importantly, the balance sheet is also incredibly strong, and it gives us the funding capacity we need in order to deliver. So again, we believe we're in a good space, and as always we appreciate your support. Thank you for your time, and enjoy the rest of the reporting season.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete APA Group transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to APA Group earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in APA Group or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.