Arihant Superstructures Limited (506194) Earnings Call Transcript & Summary

August 13, 2025

BSE Limited IN Real Estate Real Estate Management and Development earnings 33 min

Earnings Call Speaker Segments

operator

operator
#1

Good day, ladies and gentlemen, and welcome to the Arihan Superstructures Limited Q1FY26 earnings conference call. Please be reminded that every participant line is in listen-only mode, and once the presentation wraps up, you'll have a chance to ask questions. If you require any assistance during this call, just signal an operator by pressing Star then zero on your touchtone phone. Kindly note that this conference is being recorded. I'll now hand things over to Ms. Kunjal Agarwal from Aryan Capital Markets Limited. Thank you. And over to you, ma'am.

Kunjal Agarwal

analyst
#2

Good afternoon, everyone, and hello. I’m speaking on behalf of Aryan Capital Markets, and I want to thank all of you for taking part today in the Q1FY26 earnings conference call for Aryan Superstructure Limited. With us from management are Mr. Ashok Chajir, chairman and managing director; Mr. Pajal, whole time director; and Mr. Udit Kassera, the company’s CFO. So, with no further delay, I’ll pass the call to management for his opening remarks. Sir, over to you.

Parth Chhajer

executive
#3

Thanks, Kunjal. Good afternoon, everyone, and I appreciate you spending some time to be on this REM Superstructures Limited conference call, where we'll go over Q1FY26 results along with business updates. I think you've had a chance to look through our financials and the investor presentation that was filed with the exchanges. First, let me introduce our new CFO, Mr. Udit Kassera, who will walk you through the quarter's financial highlights.

Udit Kasera

executive
#4

To begin, allow me to walk you through the key financial figures for the quarter we're reviewing. Consolidated operating revenue came in at INR121 crores for Q1FY26, compared with Rupees 84 crores in Q1FY25. That works out to roughly a 45% rise year on year. EBITDA for Q1FY26 is INR37 crores, versus INR11 crores in Q1FY25, marking a 247% increase year on year. The EBITDA margin for Q1FY26 comes to 30.5%, compared with 12.6% a year earlier. Profit before tax for Q1FY26 is 21.2 crores, against 2.6 crores the prior year. Profit after tax for Q1FY26 is INR 15.9 crores, versus Rupees 2 crores in Q1FY25 — a yoy jump of about 695%. The company's net worth has risen to INR 421.9 crores from rupees 325.3 crores, which again is a year on year gain of 29.6%. With that, I'll pass the call to Mr. Path Chad, who will cover the operational highlights.

Parth Chhajer

executive
#5

Yes. Turning now to the main operational points for the quarter: the company posted sales bookings of 192 units, equivalent to 2.01 lakh square feet of area and amounting to 151 crores in value. The average price per square foot came in at around 7493 rupees per square foot, versus 5063 rupees per square foot a year earlier. That works out to price growth of 48%. The reason is a major contribution from the premium housing segment, which drove up the average price for the quarter. The average price per unit stood at 78 lakhs. Total collections for the quarter stood at 126 crores. During this quarter we also made significant delivery progress on the projects located at Kharger — namely Aryan Dalishan — and Aryanthanmol, which is at Badlapur. So, including the rental housing component, we have handed over 803 units for the quarter, spanning 7,23,000 square feet. In terms of area, unsold inventory at the end of the quarter now stands at 94 units, valued at 21 crores. On the business development front, the company expanded its development footprint by acquiring an additional 11 acres at Chowk Maniwali for the Town Villas project, and the total project size has now.

Parth Chhajer

executive
#6

We increased that to 88 acres. Beyond that, we picked up another 1.5 acres of land, and it's going to be used for the 5 star hotel currently being developed within our wholly owned subsidiary, Dwell Cons Private Limited. So as things stand, the hotel land totals roughly 10 acres. And the overall land for the World Villas project, taking in the Gymkhana and the hotel and retail, now comes to 90 acres. On top of that, we've bolstered our capital base by successfully completing the warrants that were issued back in 2023. They were fully converted into equity, which let us bring in 37.6 crores altogether. So that utilization is likewise going toward business development during the current quarter. Now, looking ahead and speaking about the markets, we think that across Mumbai MMR there's a solid amount of supply that has arrived, with plenty of projects beginning to get off the ground. And that could result in. That will result in intense competition and. Could result in somewhat thinner margins. Whereas at Ariant we function across 12 different geographies, 12 different micro markets. A nd in a few of those we've secured the first mover advantage. For instance, World Villas and Town Villas at Chowk, which sits close to Panvel.

Parth Chhajer

executive
#7

So in these kinds of micro markets, our premium development villa offering stands alone. There's no competition at a peer level. As of today, that's what's securing better margins for us. Together, Town Villas and World Villas will deliver roughly 1800-plus villa units, which works out to 3750. Crores in terms of GDP. That's more than 25% of our overall portfolio. So we feel we've protected ourselves and shifted somewhat away from the highly competitive market. And there, too, we're anticipating stronger margins that will produce good results. For the company going forward. That said, the Navi Mumbai region is set for significant growth. Because the Navi Mumbai International Airport is expected to begin operations by October 2025. And Atel C2, which has been a major game changer, is already operational. And with large infrastructure and industrial and corporate parks coming up, we foresee. 10 lakh new jobs being created. In this region over the next decade. Which will drive a lot of residential demand as well. So this section of the city still offers good catchment and good livability. No matter the heavy competition that has arrived.

Parth Chhajer

executive
#8

The whole Mumbai region and Arianes Land, plus Bank, together with the launches coming up, sit in a strong position across these corridors of high opportunity. And we stay committed to meeting the changing aspirations of home buyers throughout the entire NMR spectrum. So with that, I'll now open the floor for questions and answers. Thank you.

operator

operator
#9

Thanks a lot. We’re moving into the Q&A portion now. If you’d like to ask something, you can press star and one on your touchtone phone. Should you want to drop out of the question queue, press star and two; we ask participants to use handsets when posing a question. Ladies and gentlemen, we’ll hold for a moment while the queue is put together. Our first question comes from Devesh Shah, an individual investor. Please go ahead.

Analyst

analyst
#10

Appreciate you fitting in a question. Am I coming through okay?

operator

operator
#11

We can hear you, but your voice is cutting out. Could you move to a spot with better reception?

Analyst

analyst
#12

Hold on one moment. Does that come through more clearly at this point?

operator

operator
#13

That's an improvement, sir.

Analyst

analyst
#14

Yeah. Okay. Sir, so I would like to ask a question. So didn’t increase competition.

operator

operator
#15

My apologies for cutting in, sir, but your audio is still coming through.

Analyst

analyst
#16

I’ll get back into the queue. All right. One moment.

operator

operator
#17

Moving on. Our next question comes from Path Patel, an individual investor. Please go ahead.

Analyst

analyst
#18

Good afternoon, sir. Can you hear me?

operator

operator
#19

Yeah.

Analyst

analyst
#20

Right, sir, so could you tell us what the planned capex is for FY26 by category, and how does that line up with the 125 billion GDG tied to the 1800 square feet currently under development?

Parth Chhajer

executive
#21

Regarding planned construction capex for FY26, it comes to roughly 450 crore. That covers construction tied to residential development as well as the annuity side. In this financial year, we expect to spend somewhere in the neighborhood of 50 crores.

Analyst

analyst
#22

Second, with Q1 at 65 following 26, what operational factors — procurement efficiencies or vendor negotiations, for instance — played a part in that, and in this highly competitive market, how sustainable are they?

Parth Chhajer

executive
#23

We'd been saying we would be. Capable of reaching roughly 30, 33 and. An EBITDA margin, and in this quarter, since Arian Talishran was finished. So the estimates needed correcting. For the projected costs, and that has. Brought about improved margins this quarter.

Parth Patel

analyst
#24

Alright, sir. And sir, could you talk about how pricing, labor, and material costs affect the estimated balance cost to complete the INR1 12 billion for the projects currently underway, and are there any hedging mechanisms in clinics.

Parth Chhajer

executive
#25

Inflation is something we take into account when setting prices, including with our construction estimates. And I mean, over the last few months, we haven't really seen any meaningful price increases when it comes to construction or even labor contracts. And I think the total capex for our 12,500 crore GDV will come to around 6,300 crores, specifically the construction capex that's outlined.

Analyst

analyst
#26

And so, as my final question: what's the plan for managing the inventory of unfold units valued at roughly 24 billion — approximately 24 billion — across the projects currently underway, and in a competitive micro market such as Kanwid and Karmia, how will the pricing adjustments be carried out?

Parth Chhajer

executive
#27

On the pricing approach for Fargar and Pand, we’re selling at levels similar to what was seen over the last year. So we haven’t taken a significant price increase, because our focus is on getting more velocity over the next two to three months, so that the projects are in a smooth phase of completion. Aryan Dalishan, we have some ready inventory that is valued at around 7 and a half crores, and over the next couple of quarters we’ll be able to sell that out as well. As a company, we don’t have significant ready inventory — it’s hardly 21 crores in terms of value. So we feel comfortable on that front when compared with the total GDV that we are executing under construction inventory, like you highlighted, around 3000 odd crores which is there. Our strategy is that we keep selling, take significant huge price rises but still stagnantly take a 5% 7% price rise, as per the market situations, and yet not affect the velocity of the sales. So that’s the main goal for us as a company — that we want to do more pre sales this year so that it helps us in the coming months.

Analyst

analyst
#28

Thank you, sir.

operator

operator
#29

Thank you. Anyone who would like to ask a question can press Star and one now. To ask a question, please press Star and one now. Once again, those who want to pose a question may press Star and one at this time. To ask a question, please press Star and one now. Our next question comes from Amit at Robocapital. Please go ahead.

Amit Mehendale

analyst
#30

That's the goal for FY26 and FY27.

Parth Chhajer

executive
#31

Apologies — I didn’t catch your opening line. Could you say it again?

Amit Mehendale

analyst
#32

Right, I just wanted to verify. Regarding the sales target, what's our internal goal for sales — for pre-sales — for FY26 and 27?

Parth Chhajer

executive
#33

Yeah, for FY26 we're looking at roughly 1,100-odd crores. As for pre-sales, we've got a solid lineup of launches coming up. In Q2, Q3, Q4, and FY27, we'll be looking at about 1,500 crore in pre-sales.

Amit Mehendale

analyst
#34

And would you connect margins like that to what we saw previously, or…

Parth Chhajer

executive
#35

On a year-over-year basis, margins are going to improve. Compared with prior years. If we view it year over year. And since the new projects that have been taken on have yet to — some of them have not yet reached the point of revenue recognition, and those that have begun contributing are helping us. To achieve better margins.

Amit Mehendale

analyst
#36

Alright, so the final question concerns the debt level — how it stands.

Parth Chhajer

executive
#37

Over the next 1.5 to 2 years, that debt figure is going to rise. The reason is that most of the borrowing is being channeled into building up the annuity assets. So we're looking at roughly another 150 crore of debt being added, driven by the Gymkhana development as well as the hotel.

Amit Mehendale

analyst
#38

That's all I have.

operator

operator
#39

Thank you. Before we move on to the next question, we'd like to remind everyone on the call to press star and one if they'd like to ask something. Our next question comes from Devia Shah, an individual investor, on the line. Please go ahead. Hello sir. Your voice is still breaking, sir.

Devesh Shah

analyst
#40

Yeah. Okay. So, is that better now? Yes, sir. Yeah. So, what I'd like to ask is this: what is the realization across the different projects, and how much of a hike are we seeing? What does construction generally cost?

Parth Chhajer

executive
#41

It depends. Construction expenses shift depending on how tall the building is. For instance, a 7 storey structure runs roughly 18, 1900 rupees per square foot. A 15 storey one comes in near 2200 rupees square foot. Then a 25, 30 storey building lands at about 2600 rupees square foot. Any project that is 40 storey and taller costs 3000 rupees per square foot and above. So the pricing mostly hinges on the height of the building and how much parking you build, the podiums and so on. Relative to the overall selling price, though, our construction cost is mostly around 50% of total sale value. Your first question concerned micro market pricing, if I’m not mistaken.

Analyst

analyst
#42

Right, right. So what’s the realization across the different projects? Like, what kind of hike are we seeing there?

Parth Chhajer

executive
#43

Okay, so it does differ depending on the project. Ariant Alisha — at the moment we're selling at roughly 8 and a half thousand rupees per square foot. And our expectation there, since the product is finished, phase one has been delivered, and phase two is also close to being done — next year we should be wrapping that up as well with OC. So we think the price could rise to about 9,000 in that area. At another site, Advika for instance, current trading prices sit at roughly 13,400 rupees per square foot on saleable area. And as this project also nears its completion phase, we expect it could go up to somewhere around 14,000, 14,200 rupees over the coming year. So roughly a 7, 10% increase in prices is what can be expected across the mid income and premium luxury segment wherever a project is moving along at a good pace and getting close to completion. That's a fairly typical picture for the broader market, and I believe we're tracking in line with those trends. Certain areas might not experience that magnitude of price growth — mainly in affordable housing. Perhaps your first sale compared with your last sale over a stretch of three and a half, four years might show an increase of just 7 to 10% in some locations.

Parth Chhajer

executive
#44

Perhaps something along the lines of a Badlapur or a Karjat. Or Titwala or Kopoli, say. So it differs from one micro market to another. Apologies, your voice is cutting out.

operator

operator
#45

Hi sir, can you hear me? No sir, your voice is still cutting in and out.

Analyst

analyst
#46

Is that so?

operator

operator
#47

Yes, sir. Yeah.

Analyst

analyst
#48

How long does it take to finish World Villa?

Parth Chhajer

executive
#49

We kicked things off with the World. Villas project only a few months back. Construction is now in full swing, and we anticipate. That project will require roughly four and a half to five years. As for Town Villa. By April 2026, that's when we expect. Construction to begin, and from that point it will need five to six years to be finished.

Analyst

analyst
#50

That covers everything on my end.

operator

operator
#51

Thanks. Any participants who’d like to ask a question can press star and one at this time. Our next question comes from Amita Gija at HG Hawa — please go ahead.

Amit Agicha

analyst
#52

Yes, hi. Good afternoon, everyone. Can you hear me okay?

Parth Chhajer

executive
#53

Yes.

operator

operator
#54

Yes, sir.

Amit Agicha

analyst
#55

Appreciate the chance, sir — what’s the blended cost of borrowing at present?

Parth Chhajer

executive
#56

Our blended borrowing cost comes in at roughly 12.5%.

Amit Agicha

analyst
#57

Is there any room to refinance in a way that would lower the interest burden?

Parth Chhajer

executive
#58

No, I mean, most of our debt, like from HTC bank or SBI, is around 10%, so there’s no room for refinancing there. And even the debt from Tata Capital or STCI is also around 11–12%, in that range. So I mean, there’s no big opportunity for refinancing in this situation, and we don’t usually switch just to gain 50 basis points — we value the relationship with our lender as well.

Amit Agicha

analyst
#59

What are the FY26 projections for operating cash flow? Post debt servicing in Capex.

Parth Chhajer

executive
#60

Debt servicing is going to consume roughly 70-odd crores. So, on cash flow for this year, to answer your question, we’re expecting 600 crores. Customer receipts in FY26 should bring in that amount; about 70 crores of it will be used for that servicing. Then some amount will—around—maybe part of it goes to repayment, but since we’ll be adding on, that may net off in a similar way. Administration expenses would then come to roughly 45-odd crores. Marketing expenses should land at around 25 crores odd, and approximately 450-odd crores is what we’re anticipating for construction.

Amit Agicha

analyst
#61

Could you talk about what the market trend looks like for you? Are you the leader, or are you the second leader?

Parth Chhajer

executive
#62

No, I'd say we're among the leaders in this market. Our position is strong — we've got the widest geographic footprint and the finest selection of inventory, spanning from 20 lakhs up to 4 crores in value. We carry every product, from 1, 2, 3, and 4 BHK all the way to villas. So the breadth we offer, the portfolio we serve, and the scale we operate at are top-tier. We go up against the very best — our neighboring players and competitors — and in certain locations and micro markets we're able to outperform them too, whether on pricing, on sales, or on velocity. As a company, in the years to come, given this position we hold, we'll be able to capitalize on the brand equity and on the value for the company as well, which will deliver good results in the months and years ahead.

Amit Agicha

analyst
#63

When you look at our company, is the superstructure again Pan India, in your view?

Parth Chhajer

executive
#64

Nope. Over the past four, five years, our focus has been here, in this MMR region. And it will stay that way through the next four, five years as well. We have no plans to go beyond MMR, since with the capital we hold and the liquidity available, we can deploy it in MMR without difficulty. There's no need for us to look elsewhere in search of opportunities, because the world is coming to us. Every developer throughout India wants at least one project in this location of Navi Mumbai and around the airport area. And we are in the finest phase our company has ever seen. We are at our best. We sit at the best locations. Roughly 75% of our portfolio surrounds the airport, where the major infra development is on the verge of taking off and where big jobs are going to be created. Over the coming decade, about 10 lakh jobs are envisaged to be created. So we want to remain in this location. We want to hold a great position in this location going forward as well, and show our investors that we are capable of executing and delivering.

Amit Agicha

analyst
#65

Do you feel good about having enough workers, and what about the raw materials—things like where you source them and what they cost?

Parth Chhajer

executive
#66

Yes, we can carry out the work without any trouble. Of course, in April and May there’s a labor shortage throughout the whole industry, since most of them return to their home villages and towns. But our sites have recovered. Starting in June, execution has been moving along at a solid pace. So as a company we face no problems, because our vendors and contractors are very long-standing and have been with the business for 20 years, and we also maintain strong ties with them, which serves us very well.

Amit Agicha

analyst
#67

What are your long-term ROE and ROCE targets, and during policy?

Parth Chhajer

executive
#68

On ROE, we’d prefer that ROE make up 20% to 25% of the total. That’s the goal.

Amit Agicha

analyst
#69

That is a dividend policy.

Parth Chhajer

executive
#70

Last year, the dividend came to 15% of face value.

Amit Agicha

analyst
#71

Do you have any plans to expand the annuity income streams past hospitality at Gymkhana?

Parth Chhajer

executive
#72

Right now, our attention is on hospitality at Gymkhana, since those are the spots where we own substantial parcels of land and they work well. For hospitality, or this segment. Retail or offices isn’t something we can do at these sites at present. So should a new opportunity arise, we. Might consider it. But there aren’t major plans to move into. Any office leasing model at this point.

Amit Agicha

analyst
#73

Could you give us a bit more detail on that hotel project you're looking at?

Parth Chhajer

executive
#74

We're at the stage where we're finalizing the agreement. Once that agreement is finalized, we'll be glad to return to the markets and talk about it. The design work is complete. We've finished the approval process as well. Work gets underway starting in October, and we expect the asset to be ready in three and a half to four years.

Amit Agicha

analyst
#75

Regarding your final question on redevelopment, do you feel as though you'll be moving into that?

Parth Chhajer

executive
#76

Yeah, we're actively looking around and hunting for additional redevelopment chances under an asset-light approach. As we pointed out during the previous earnings call, we won't be making big acquisitions this year when it comes to buying land outright. Instead, our emphasis will be on getting into 3 to 4, or at minimum a couple, of redevelopment-model projects. So at the moment we're in the process of nearly wrapping up talks with a couple of societies, and as soon as that's settled we'll be glad to make an announcement.

Amit Agicha

analyst
#77

Thanks for taking every question, sir — I appreciate it. And I wish you all the best going forward.

Parth Chhajer

executive
#78

I appreciate that.

operator

operator
#79

Thank you. Anyone who wants to pose a question can press star and one right now. To submit a question, just press star and one. Our following question comes from Suyesh Bhave of Wealth Guardian. You may proceed.

Suyash Bhave

analyst
#80

Can everyone hear me?

Parth Chhajer

executive
#81

Yes.

Suyash Bhave

analyst
#82

Yeah, so about that court-related environment clearance matter — what's the latest on it, given that it's still holding back our operations?

Parth Chhajer

executive
#83

So, roughly a week ago, there was a really positive update regarding environmental clearance. The Supreme Court has now resolved the matter. And, as you know, the environmental clearance processes will begin from the end of this month, and we'll wait for our position in the queue. That should arrive within the next 2 to 4 months, depending on which project it is. So, safely, I think we can say that by December we ought to have all the environmental clearances for the projects — Aryan T. Avanti at Sri Fata, Ariant 7, Anaika at Taloja. I mean, before December 25th we should have those environmental clearances in hand, and from Q4 onward we'll be in a position to begin construction on those projects, which will then help us start recognizing revenues for them from the next financial year onward.

Suyash Bhave

analyst
#84

All right, got it. And regarding those 2 land buses we bought not long ago, how much did they cost to acquire?

Parth Chhajer

executive
#85

The figure comes to roughly 300 crores for the two of them.

Suyash Bhave

analyst
#86

No, not that figure — I mean the step-up. The 11 acres and the 1 1/2.

Parth Chhajer

executive
#87

Or the ones bought—which quarter was that?

Suyash Bhave

analyst
#88

The acreage is 1 1/2 acres. Yeah.

Parth Chhajer

executive
#89

So it's 1 1/2 acres, the land for the hotel. That comes to roughly 4.8 crores.

Suyash Bhave

analyst
#90

Alright.

Parth Chhajer

executive
#91

So for those 11 acres, I believe it'll come to roughly 35 crores — I'll just, yeah, verify that figure. But it should land somewhere near that amount.

Suyash Bhave

analyst
#92

Oh, okay. I see. Got it. Got it. Fair enough. I understand.

Parth Chhajer

executive
#93

No, sorry. At 11 meters, it'll average 1.5. That comes to roughly 17, 18 crores. My mistake.

Suyash Bhave

analyst
#94

Alright. Got it. Thanks. Appreciate you taking the question.

operator

operator
#95

Thank you. Anyone who would like to pose a question can press star and one at this point. To pose a question, please press star and one now. Once more: those who would like to pose a question can press star and one now. To pose a question, please press star and one now. Ladies and gentlemen, since no more questions have come in from the participants, I'll now turn the conference over to Ms. Kunjal Agarwal for closing comments.

Kunjal Agarwal

analyst
#96

Thanks to the management and everyone taking part for joining the Q1FY26 conference call of Aryan Superstition Infrastructure Limited. I'd now pass the call over to the management for their closing remarks.

Parth Chhajer

executive
#97

All right, thanks to all of you for being on this earnings call. I hope you managed to get. Satisfactory answers to every question you had. Should anything else come up, or if you'd like additional detail about the. Business, don't hesitate to get in touch with our investor relations team at Valorum Advisors. Alternatively, you can reach out to our finance department. Our CFO and the team will pick it up from there. We'd also like to thank Arian Capital for hosting. This call on our behalf too. Many thanks.

operator

operator
#98

Arihant Capital Markets Ltd. sends its thanks. That brings this conference to a close. We appreciate your participation. Your lines can be disconnected at this point.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Arihant Superstructures Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Arihant Superstructures Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Arihant Superstructures Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.