Neil Woodyer
executiveThanks, operator, and welcome everyone to the Q3 2026 earnings call for Aris Mining. With me on the call today are Doug, Oliver, Cam, Dustin, Corné, and Alejandro. Our forward-looking and non-GAAP disclosures can be found on slide two. If you turn to slide three, during Q3 we produced 69,000 ounces of gold, and on a trailing 12-month basis we've now generated over $700 million in adjusted EBITDA. Our Q3 investments totaled $144 million, which brings the year-to-date figure to $341 million, and roughly 60% of that went toward the Marmato expansion. Across the portfolio, we have clear near-term milestones. At Segovia, owner mining keeps growing, and we anticipate Contract Mining Partner production will improve now that the new government has given appropriate access to explosives. At Marmato, the Bulk Mining Zone is up and running. The new tailings facility has been commissioned, construction of the CIP plant is in its final stages, and we expect the first gold pour in December. At Toroparu, we anticipate the pre-feasibility study later this month. At Soto Norte, we keep moving the permitting process forward. I'll now turn things over to Cam, who will walk you through the financial results.
Cam Paterson
executiveThanks, Neil. If we move to slide four, Q3 revenue came in at $287 million, while adjusted EBITDA was $144 million, which lifts our trailing 12-month adjusted EBITDA above $700 million. Adjusted net earnings stood at $73 million, equal to $0.35 per share. One thing worth noting: that $144 million of adjusted EBITDA was roughly the same as what we invested in capital for the quarter overall, which included $86 million at Marmato and $41 million at Segovia. Even with that capital spending, we closed the quarter holding $419 million in cash, compared with $392 million at the end of 2025. Now on slide five, you can see our strong year-to-date results. Revenue for the nine months came to $972 million. Adjusted EBITDA was $535 million, and adjusted earnings per share came in at $1.42. What this year-to-date trend tells us is clear. Record year-to-date results are being driven by higher gold sales and realized gold prices. Moving to slide six. The main takeaway here is cash generation. Through September, adjusted operating cash flow after taxes totaled $294 million, which covered roughly 86% of the capital investments we made year-to-date. We also collected the final two installments under the Marmato precious metal stream, for aggregate proceeds of $82 million across the first nine months; that leaves us with a solid financial base to complete the Marmato expansion, keep investing at Segovia, and move our development projects forward. With that, I'll pass it to Dustin for an operations update.
Dustin VanDoorselaere
executiveAppreciate that, Cam. If we move to slide seven: third-quarter output came in at 69,000 ounces, which puts us at 217,000 ounces for the year so far. Looking at the whole year, we're aiming at the bottom end of our 300,000-ounce to 350,000-ounce guidance range. Getting there means producing roughly 83,000 ounces during Q4. Two things held back output in the quarter just ended: short-term limits on explosives supply that hit our Contract Mining Partners at Segovia, plus the scheduled shutdown of the flotation plant at Marmato while we brought the new Cascabel 3 tailings facility into service. That downtime also let us carry out required maintenance and install some upgrades at the flotation plant. Both issues are now resolved — the explosives permits were settled in September with backing from the new Colombian administration, and Marmato's flotation plant is running again at slightly higher capacity thanks to the new Cascabel 3 tailings facility. We anticipate stronger output in Q4 as owner mining production keeps growing and we pour first gold at the Marmato CIP plant. On slide eight, I'll go deeper into how Segovia performed operationally. Segovia's production for the year to date reached 194,000 ounces, an 18% gain over last year. Owner mine output rose 32%. Contract mining output fell 3%, though with explosives access back in place we look for Q4 to improve. We remain focused on lifting mining rates and haulage capacity via underground development and fleet growth, so we can make fuller use of our expanded processing capacity. New mobile equipment begins arriving late in Q3, with the rest coming in Q4. Upcoming milestones include a refreshed mineral reserve and resource statement in November and finishing the new El Silencio service ramp in December. Now slide nine. At Marmato, Q3 brought a significant milestone as we commissioned the new Cascabel 3 filtered tailings facility. Doing so meant a planned four-week shutdown of the existing flotation plant, which weighed on Q3 production; during that downtime we finished maintenance and upgrades, among them refurbishing the primary ball mill and integrating a new regrind mill and Knelson concentrator. Consequently, the flotation plant's processing capacity now stands at roughly 1,200 tons per day. Notably, mining carried on through the shutdown, which let us build stockpiles to feed both the expanded flotation plant and the commissioning of the new CIP plant. With these improvements done, we anticipate a stronger production profile in Q4 as we get ready for Marmato's next growth phase. I'll now pass things to Corné for updates on the Marmato expansion and Toroparu.
Corné Lourens
executiveThanks, Dustin. We’re close to turning Marmato into a significantly bigger operation. At the new CIP plant, construction is in its last phase, and commissioning work has begun. The new Bulk Mining Zone is running nicely. We’re stockpiling ore to support ramp-up, and we’ve moved over to the new filtered tailings facility. We anticipate the first gold pour in December, with a staged production ramp-up during 2027, reaching the full design capacity of 5,000 tons per day by the end of 2027. We also intend to publish an updated NI 43 to 101 technical report in the first quarter of 2027, with fresh mineral reserve and resource estimates for Marmato. Turning to slide 10. At Toroparu, we’re completing the PFS for release later this month; it will contain our initial mineral reserve estimate for the project. Importantly, we’re treating this study as a team getting ready to build a mine. We’re focused on a practical, executable plan, with special emphasis on cost certainty, operational reliability, and managing construction and operating risks; that mindset shows up in several key elements of the study. Contract mining: we’re relying on competitive quotations from experienced international mining contractors instead of assuming an owner-operated mining fleet. Project delivery: our plan combines a tailored mix of engineering and construction contracting models with self-performed work, choosing the most suitable delivery approach for each project area. Our project delivery approach is meant to strengthen cost and schedule control while managing execution risk. Mine design: we’re taking a conservative approach to mine planning, including staged pit development and dual-access ramps to support reliable operations. The project is still based on a conventional open-pit mining operation with a 7 million ton per year processing plant. On the ground, construction of the 109 meter Puruni River Bridge is underway, with completion targeted for December. The bridge will provide permanent access to the Toroparu project and allow heavy equipment and materials to move. We’ve also submitted our large-scale mining license application and continue working closely with the government of Guyana to move the permitting process forward; with that, I’ll hand it back to Neil to discuss Soto Norte and close the presentation.
Neil Woodyer
executiveNow on slide 11. At Soto Norte, we're seeing encouraging movement on the environmental permitting front; back in July, Colombia's National Mining Agency gave the green light to our updated technical mine plan. We've finished getting the environmental and social impact assessment ready as well. The next thing for us is formal consultation with the community, and after that we'll finalize the ESIA and file our application for the environmental license. We've also had some positive regulatory news, with the incoming government rolling back a number of restrictions that the prior administration had put in place. Those decisions give us more clarity on the path to permitting for this project. Soto Norte is still a key piece of our long-term growth strategy, and the progress we're seeing has us encouraged. That said, Colombia's political and regulatory landscape is shifting fast. We're proceeding carefully, cooperating closely with communities and government authorities, and moving the project forward at an appropriate pace as things develop. On slide 12, our growth strategy comes in two stages. First, as we finish ramping up the expansions at Segovia and Marmato, those two have combined steady state production targets of roughly 500,000 ounces per year. Farther out, our development projects at Toroparu and Soto Norte could add another 500,000 ounces per year, based on their technical studies and subject to permitting. At Toroparu, we're aiming to wrap up the pre-feasibility study in November, with a possible construction decision in the first quarter of 2027, after the first gold pour happens at Marmato's new CIP plant. At Soto Norte, the backing of the new Colombian administration is encouraging to us, and we're pushing the environmental licensing process ahead. Taken together, these four assets offer a possible route to a million ounces of gold production each year. Our near-term priority is still execution — growing output at Segovia, achieving the first gold pour at the new Marmato plant, finishing the Toroparu study, and moving Soto Norte's permitting forward. Thanks for being with us today. Operator, please open the line for questions.
Carey MacRury
analystHi there, good afternoon, everyone. Perhaps to begin, regarding Segovia, I was just wondering whether you could put a number on how much the explosives problem in Q3 affected production.
Oliver Dachsel
executiveCarey, Oliver speaking. At Segovia, we anticipate gold output rising substantially during Q4, on the scale of roughly 70,000 ounces to 75,000 ounces. Part of that comes from increased mining rates on the owner mining side, along with better output from the CMPs.
Carey MacRury
analystAll right, that's excellent. Perhaps regarding the mining rate, how ought we to think about the exit rate as we head toward 2027?
Dustin VanDoorselaere
executiveI can handle that question, Carey. This is Dustin speaking. Essentially, the explosives had an impact on both Aris and CMPs during the first portion of the year. Aris fixed things somewhat faster than the CMPs did, and since then we've been steadily raising the mining rates. We had always intended a significant Q4 progression, so to speak, and we're staying on that course. In December we'll be hooking up our El Silencio ramp, which will boost productivity there, and we remain on track for roughly 70,000 ounces-75,000 ounces during Q4, with a very strong reaching of nameplate capacity anticipated in 2027.
Carey MacRury
analystAll right, so perhaps we can move on to Marmato. Clearly you're ramping things up in 2027. As I understand it, the CIP plant is still in progress. I was just wondering whether there's a capital estimate we ought to have in mind for Marmato in 2027.
Dustin VanDoorselaere
executiveI might hand that question over to Corné, since he's handling what's left of the CIP plant.
Corné Lourens
executiveYes. Thanks, Dustin. At the moment our spending runs at $25 million each month through Q4 of 2026; we anticipate only modest capital expenditure until roughly July 2027, when the last equipment components arrive and get installed. That figure is estimated at about $40 million.
Carey MacRury
analystCould you go over the first part again? Those figures for 2026 went past me.
Corné Lourens
executiveFor 2026, under the present—
Carey MacRury
analystYeah.
Corné Lourens
executiveFor 2026 — the current figure — Q4 spending sits at roughly $75 million. That works out to an average of $25 million each month. So, since expenditure for the first nine months of 2026 comes to $175 million, we anticipate construction spending for 2026 will land at about $250 million. That puts us $30 million above the original budget of $220 million. The projected $30 million rise stems mainly from FX — a stronger Colombian peso over the course of 2026.
Carey MacRury
analystAll right, that's great. Many thanks.
Neil Woodyer
executiveThanks a lot, everyone. We're grateful that all of you joined us, and we're anticipating a solid year ahead. Thank you so much, truly.
Operator
operatorThat wraps up the conference call for today. Your lines can now be disconnected. We appreciate you joining us, and we hope the rest of your day goes well.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Aris Mining Corporation transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Aris Mining Corporation earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Aris Mining Corporation or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.