Atalaya Mining Copper, S.A. (ATYM) Earnings Call Transcript & Summary
August 12, 2025
Earnings Call Speaker Segments
Operator
operatorHello, everyone, and welcome to the Atalaya Mining Q2 and H1 2025 results call. Right now, everyone is in listen-only mode. Afterward, we'll hold a question-and-answer session over the phone lines, and instructions for it will come at that point. I'd like to remind everyone that this call is being recorded. I'll now pass things to Atalaya Mining's CEO, Alberto Lavandeira, who will open the presentation. Please go ahead.
Alberto Lavandeira
executiveGood morning, everyone. It's great to be here presenting our second-quarter results, which I'd describe as excellent. Joining me is Pesar Sanchez, our CFO. I'll walk straight through the presentation, which I hope you can see on the screens. We delivered two very strong quarters. Production was already pre-released, and because of that, our financial results came in excellent. Copper production currently stands at a range of 27.5 thousand tons for the half year. Our cash costs are far below what the market expected, and all-in sustaining costs are declining. The first half came in at roughly $2.78 to under $2.80 per pound. Thanks to that, we've raised our guidance, with slightly higher production and basically a somewhat lower all-in sustaining cost. One could argue we might bring this down a bit further, but we'd rather stay conservative. Given this excellent production and these economic results, we posted a record EBITDA — a new record for both a quarter and for half of a year.
Alberto Lavandeira
executiveLooking at things from a corporate standpoint, quite a lot else has taken place during this year. A number of those items, for instance, keep helping us make our management team stronger, and there we brought in Fernando Díaz-Riopa as Project Manager at Toro, which will be a mixed mine. We made a few other adjustments as well. One involved naming Fernando Louth as General Manager of Rio Tinto. He has spent a good number of years with us, and 11 years ago he also played a key part in securing the permits. He took over from Enrique Dorado, who stays with the business as a Senior Advisor and handles some other corporate matters. On top of that, the board — we kept up some renewal there too. Hussein Barma had served the company for over 10 years. He was judged not to be independent, and so we made that change. He went on to a very important company in Canada. We truly thank him for his service. Then we had the appointment of Corie Gonzalez. Corie Gonzalez is a woman with board experience in Spain and very strong connections. Also Hennie Fo, who joins us from Anglo-American, brings high-caliber experience in the copper sector. We are very happy to welcome both of them to the board.
Alberto Lavandeira
executiveSo those are, I'd say, the main takeaways from this first slide. Now I'll go into the details a bit more. Turning to the details, it's pretty evident from the production results we saw — we had announced them at the plant — that the plant is performing very well. It's running at a throughput of more than 4 million tons per year, an annualized rate of 16 million tons per year. As a reminder, this plant was designed for 15 million tons per year. The grades were good as well. Grades came in at 0.43%, so higher than previously. Even though we had some lower recoveries because of the complex material being blended from San Luis, the upshot is that we had much better production, and that's what drives the exit revenues. On the next slide, you'll see that the records were very strong once again, thanks to the concentrate rates, a good copper price, and low offsite costs. Cost performance was very good. On-site cost was lower, both in mining and at the plant, on a unit per ton basis. We also had lower offsite costs. In the end, that produced a record EBITDA of EUR 55 million, a new record.
Alberto Lavandeira
executiveThat actually came in above what we saw during the first quarter of 2025. Taking all of that together, operating cash flow came in excellent — EUR 52 million. Once we had put EUR 19.4 million into investments, free cash flow remained very strong at almost EUR 33 million, which is also excellent for a quarter. The main investments we carried during the quarter were the capitalized stripping at Cerro Colorado, some tailings expansion, and some stripping in some. As a result of all that, our cash position — and you will see it in the last part of the slide — has been excellent. We increased the net cash position to plus EUR 70 million, which is also very high. In the next slide, you will see the economic results with good operating costs, excellent profits of EUR 60 million for the half of the year. We are looking at an EBITDA during the first half of the year 100 and almost EUR 108 million. This was possible due to the combination of the strong production and sales, good copper prices, good cost control, and so on. As usual, we would like to give the breakdown of what are our costs, and we do have that in slide 10.
Alberto Lavandeira
executiveSo at that point you'll notice that mining, processing, G&As, and costs have been declining versus earlier years, mainly—let's say—because production is bigger. Site cash costs came in at roughly $2.30 for the quarter and about $2.20 across the first half. What matters more, I'd argue, is that offsite costs—the cost of selling—have fallen sharply. The first factor: as all of you are aware, treatment charges and refining charges from benchmarks and spot sales have been quite low, so they're actually roughly half of what they were previously. On top of that, the strong silver price and the solid silver output we achieved pushed our by-product credits into negative territory, meaning total offsite costs were in fact negative over the quarter. For the year overall, they've been neutral. And this comes despite rather unfavorable U.S. dollar movements. As all of you are aware, our operating costs sit mostly in euros, apart from offsite costs, which are largely in dollars. Even though the euro/dollar has moved against us, good cost controls have let us keep the impact of these costs on our accounts very limited.
Alberto Lavandeira
executiveAs usual, we typically provide the breakdown of all-in sustaining costs. In that breakdown, we include corporate costs, sustaining capital, capitalized stripping costs, and other costs. Taking all of these all-in sustaining costs together, our AC costs come to roughly $280 per pound, and that is again about $0.40 per pound below where they were in earlier quarters and earlier years. As usual, we like to benchmark our costs against other peers, and we present that on slide 11. We keep demonstrating that our cost control is delivering good results. We are holding our all-in costs on that downward trend quite nicely. I think we remain able to fight inflation and low rates nicely. We were essentially staying quite competitive, keeping our all-in costs well below the all-in sustaining costs of $3.50, which, as we can see, is quite standard in the industry, and that also tells us that for future projects, we will really need much higher copper prices for them to get sanctioned and to get approved. With all that, what are we doing with guidance? Because we had a very good, strong performance during the first half, we decided to — and now there are some revisions — we tried to be a little bit conservative and not to jump.
Alberto Lavandeira
executiveOur guidance has been raised slightly, to between 49,000 and 52,000. What we did, essentially, was lift the lower end of that range a modest amount, since we feel confident there will be no problem holding to that guidance. On all-in cost, we have likewise trimmed our guidance by roughly $0.10. All of this takes into account that we still anticipate a heavy euro exchange rate during the year's second half. Our euro costs may stay stable, yet from the dollar standpoint we could encounter somewhat higher costs over the next half of the year. As for CapEx guidance, certain items have been shifted into next year — partly because time won't allow them, partly because our understanding of the situation has improved. We are guiding between EUR 29 million and EUR 37 million in non-sustainable CapEx. That represents a reduction from EUR 58 million to EUR 82 million. The chief reason is that a portion of those capital costs consisted of the San Luis expansion, the associated prescription. We are now reclassifying that into all-in sustaining costs. It's a big difference, given that we obtained the permits. Those are running through P&L.
Alberto Lavandeira
executiveOn the other projects side, certain ones have been pushed back to 2026 — for instance the road relocation, because of the permitting delay at San Venancio, and the Massawa ramp, where access to the portal and the ground also ran into delays. On exploration, we nudged our guidance upward a little to EUR 8 million-EUR 12 million, perhaps even a bit better than that. Most likely it will land near EUR 10 million, purely because we are seeing some strong infill results at Massawa and we intend to keep that going. There are other activities underway that give us confidence we can comfortably put money into exploration. Given all these strong results, the board has stated and approved that the dividend needs to go up. That aligns with our yearly payout of 30%-50% of free cash flow, which is typically distributed in two installments. The first one was just paid a couple of weeks ago. We have chosen to raise the interim dividend to EUR 0.044 per share, a 21% increase compared with the equivalent interim dividend of EUR 0.0362. We will keep doing so even with the knowledge that some investments are coming at Toro.
Alberto Lavandeira
executiveOur dividend policy is going to stay in place, since we see it as evidence of discipline. If a company is unable to afford a dividend, that tells you something is wrong with it. Where will our attention be in 2025? Our attention will be on San Luis, and we will keep going there. On slide 15, you can see that part of the hill at San Luis Obispo is already being moved down. Several benches have already been taken. The plan is to gain access while we keep mining the oxidized zone in the deeper section of the pit. We are already pre-stripping the hill at San Luis. Road relocation work continues. The bulk of this work will be finished at the very end of the year. Mining is not being affected by this at all. Our partner, Alex, Lane, will also keep treating material through their plant. That operation is running well, but at this point they still lack sufficient operating capacity for us to say it delivers economic cash flow to the company. We have strong confidence that this will bring us improved recoveries in certain deposits that we own.
Alberto Lavandeira
executiveOur focus is going to remain on continuing and drilling at Marshall Valverde, and you can see that on slide 18. As I said earlier, we got excellent results that we put out one month ago, with very good intercepts — some of them 25 meters at 2.9 or 26 meters at 2.8, and so forth — and with very clean copper mineralization, which is mostly stockwork or remobilized material, grain material, with very low zinc levels. That's assumed based on our test results. It's going to work very well in our plant. The plan is to keep infilling this area in the north part of the deposit so that we can justify having some of the material going through the middle. It will raise production and extend the life of the Tinto district. To mine here, we have approved a ramp. We have all the approvals. It's subject to board approval regarding starting this second half of the year. The ramp will be built in a couple of three straight lines so that in the future, belts can be installed, but it will use truck haulage. At first, the ramp will access the high-grade deposit, but this is a polymetallic deposit with high zinc content that requires a separate circuit at Tinto.
Alberto Lavandeira
executiveIt goes straight into the copper-only zone, which sits in the Northeast, roughly beneath the Massawa border polymetallic deposit. Our focus will remain on Togo. As all of you are aware, Toro represents this company's main growth driver. Roughly EUR 250 million of CapEx will be needed for this project. Its strip ratio is very low, with rates that are higher than Rio Tinto's. You can see that, with average rates of about 42%, you can see what is achievable in terms of cash flows at Rio Tinto. That's a good example. Better recoveries and better concentrate rates are expected from this deposit, which means higher payability. In fact, this deposit's cash cost ought to be below what we see at Rio Tinto — roughly $0.40-$0.50 per pound lower than Rio Tinto. Capital intensity for this project will come in at about $10,000 per ton, which is half to one-third of the cost of most new projects built around the world. That stems from where the project is located, the lowest prescription, particularly location and infrastructure. So what are we doing there, and where is our focus? Permitting is where our attention is. The bulk of our team is focused on answering the questions that the authorities raise.
Alberto Lavandeira
executiveThis is a fairly intricate project that the local government has labeled strategic, which means the permitting phases ought to be accelerated. Positive reports have already come in from the majority of the Xunta de departments. Even though we're in a somewhat quiet stretch of the year right now, I should note that meetings are still going on. Our teams are at work. The Xunta de teams are at work finishing every report needed so an environmental impact statement can be issued, likely in September or October. Naturally, we anticipate that environmental impact statement will be favorable, and that essentially paves the way for development to begin right away, which will take roughly one year and a half. To sum up, with initial development activities ongoing, Basal Alberde drilling, total permits, and Alix working to debottleneck, wrap up, and confirm the ability, we are beginning to drill at a location known as San Antonio, a satellite deposit situated just one kilometer east of Cerro Corallo. Thirty holes had already confirmed what we have there. We keep conducting some exploration both within our company and at our sites near Rio Tinto and also on other projects such as in Sweden.
Alberto Lavandeira
executiveTo sum up, the company and guidance of roughly 50,000 tons got better, with the possibility of reaching 200,000 tons of copper and copper equivalent over the coming 3 years, low risk, good rates, quick production, a team that has kept delivering, a solid enterprise value equal to $16,000 per ton. In fact, the shares right now appear to be rising. It's growing. A strong, healthy balance sheet with no royalties or streams or anything of that kind. No debt. We have been paying dividends, $84 million, nearly $100 million since 4 years back, which means that on top of producing and on top of development and on top of building new product, we are highly disciplined with the money. As we all know, we are situated in Spain, a stable, modern jurisdiction whose people are excellent operators and explorers with building experience. Lastly, I think a very key point that I skipped earlier and didn't mention is that we were added to the FTSE 250 index in May. We are one of the pure copper companies listed in London. With that, I think I'll end my presentation and be ready for any questions you might have for me or for Cesar.
Operator
operatorWe’re going to start the questions from the conference line now. Just a reminder that participants can send written questions by using the Ask a Question button on the webcast page. If you’d like to ask a question on the phone line, press star then one on your telephone keypad. We’ll pause briefly while the questions come in. Our first question comes from Jason Fairclough at Bank of America. Your line is open now.
Jason Fairclough
analystMorning, everyone. Buenos días. The market appears to be reacting well to your results. On my screen, I see you up 7.3% — that's EUR 5.13 per share. Folks, just a couple of questions, I suppose, that are related. Clearly, the surprise this year — the positive one — has been the robust production, all those strong by-product credits, and ultimately the higher revenue per ton of rock. So my question is, how should we think about grades over the coming couple of years? And when might we begin to see the Maca de Valverde ore actually heading into your mill?
Alberto Lavandeira
executiveThat's a great question, Jason, thank you. The by-product grades aren't going to be — hold on a second. I can't tell whether the screen is sharing or not. Either way, it doesn't matter. The by-product grades will keep going this year and a bit into the following year as well — I mean the silver grades. They'll return to typical levels, roughly half of where we sit at present. At present, we're running about double what we had before. Getting the new Massa Alverde input up to speed will take us 2 years. You'll begin to see solid copper grades arriving in 2 years — let's say 2 years and a half, to be conservative, by the point you start bringing material in. This rate is climbing too.
Jason Fairclough
analystApologies — regarding the board approval, Alberto, when does that come? Is it now? Like it should be happening any day now, is that the kind of thing?
Alberto Lavandeira
executiveIt's very likely — very likely — that this comes up at the upcoming board meeting, since we already have everything in hand. What we're waiting on is, let's say, some confirmation of our final capital cost, so that it's serious and everything is known. What does this capital cost come to, and how does the capital cost profile look for the company over the coming five years, so that we can manage it? We expect approval of this item certainly within this quarter — at the September board meeting or the October board meeting, yes. As soon as you feed grades of around 2%, it's a no-brainer. The payback on the ramp is one year, a year and a half. We're quite sure this item is going to get approved. Regarding the higher grades coming from San Dionysio, we are stripping, as you can see, quite fast. We're trying to get quickly to the normal grades, which are fresh material containing around 7.7% copper. It's fresh material, so recoveries can return to the +80s. This will be there for, I'd say, the next five, six, seven years continuously. That's something we should be enjoying under normal circumstances. There is a certain limitation on feeding this type of material into the plant.
Alberto Lavandeira
executiveYou can’t simply introduce that 0.7% over extended periods, given the delicate balance between copper and sulfide content. There’s more pyrite present, and though fluorides are there too, this isn’t your standard stockwork. My view is that you need to blend it cautiously, with between 10% and 20% of the feed coming from Southern Issuer and the remainder from Theragorella. Looking a bit ahead — and we haven’t discussed this here, of course — you can clearly see we hold substantial polymetallic resources, and considerable test work has been carried out on this kind of material. We’re already collaborating with a highly regarded international firm on designing — the design is in fact complete — but the final call on layouts and the approach for a polymetallics plant, which will be configured so it can separate zinc alongside copper, is still pending. That will probably be announced at some point in the first part of 2026. Construction is also expected in late 2026 and 2027. It won’t be anything massive. Its purpose is simply to add zinc flotation, thickening, filtering, plus a summary grind within the existing server. Those represent the three grade components you should expect to see over the coming three years, in addition to total, obviously.
Jason Fairclough
analystI want to press you a bit here, Alberto — if I'm trying to decide what figure to plug into my model for Rio Tinto over the next two, three, four years, would it be somewhere above 0.4, below 0.6? Or will it actually come in under 0.5?
Alberto Lavandeira
executiveMy guess is higher than 4, under 0.5. No — 0.6 is not a level you can exceed.
Jason Fairclough
analystAlright.
Alberto Lavandeira
executiveNo, 0.5 is the maximum you're allowed to exceed.
Jason Fairclough
analystAlright, thanks.
Alberto Lavandeira
executiveOur grade is low, yet we still produce.
Operator
operatorDavid Radclyffe from Global Mining Research has the next question. Your line is open now.
David Radclyffe
analystMorning, Alberto. To pick up on San Inicio — under the previous guidance, capital was EUR 32 million to EUR 46 million. Can you confirm what portion of that capital now sits inside production costs, in euro millions, and what amount has been pushed out to 2026?
Alberto Lavandeira
executiveCesar, are those figures right there with you? Since.
César Sánchez
executiveYes. We’ve got approximate figures. A portion of the capital expenditure moved into 2026 relates to Massimo — that isn’t tied to Sandinisia — plus the road relocation, correct? Those two items together come to roughly EUR 16 million, which is now anticipated in 2026. Previously, it was expected in 2025. As for Sandianasia, a substantial part of it, now that the permit is in hand, will be recorded as an item within the P&L. It simply follows an accounting rule under which stripping costs — essentially, anything above the life-of-mine average goes onto the balance sheet, while anything below that average goes into the P&L. A small share of the Sandianasia amount will shift into 2026, but most of it will merely be classified as a P&L item.
David Radclyffe
analystOkay, thanks. If I could squeeze in one quick follow-up: could you give us a bit more detail on Elix and that third-party review you're starting up? What's driving the timing on it now, and how long do you figure it will run? Given that EUR 55 million has gone in, is there still actually funding available on your side for this project?
Alberto Lavandeira
executiveThat is a really good question. For sure, we won't keep funding it the same way we've been doing. The bulk of the funding so far has come through loans and convertible loans. Given the delays a startup runs into — and we all know this is a new technology — those terms will definitely need to be revisited. As of right now, we haven't put in any additional money since last year. They're basically, let's say, running off our latest injection, which came in the second quarter of 2024. This matter is being reviewed. What we're seeing is that the process does work. It would be quite compelling if the copper TCs and RCs weren't so low or even negative, because obviously you can't compete under those conditions. At the moment, Elix is focused on taking the zinc out of certain complex bulk concentrates containing copper-zinc or copper and something like zinc. Once the zinc is removed, the copper grade rises. That is working pretty well. Of course, because zinc prices sit substantially below copper, the economics aren't all that clear. At present, it's very near breaking even. It genuinely isn't costing us money. For sure, we'll need to review how we engage going forward.
Alberto Lavandeira
executiveWe still believe this will bring significant benefits to us and to the parent belt, since the worth won't stem from the tiny operation currently in place—it's simply too small, and the fixed cost portion runs quite high. The value is going to come from enabling deposits to be mined that otherwise would require pressure leaching or those high-alveolum, high-oxygen, high-energy, high-everything processes used around the world, all of which are well known yet very rarely installed because of the steep capital costs. That, I believe, is where we see the value. We see the worth of the process we own and possess—without it, recoveries would be quite low and the economics wouldn't be so attractive. That's the reason we keep pushing.
David Radclyffe
analystExcellent. Thanks. I’ll get back into the queue.
Operator
operatorThe next question is from Alex Bagwini at Canaccord Genuity. Alex, your line is open.
Alex Bedwany
analystYeah, thanks guys for taking my question. So the first one, going back to San Luis — when do you expect to break through into that fresh material with the higher grades? And how much of the ore that's being mined right now is actually making its way to the plant?
Alberto Lavandeira
executiveAs I recall, based on the previous meeting, we've been putting through roughly 0.5 million tons, or 600,000 tons, of material that didn't originate from the fresh zone. It was sourced from the oxidized old mining area, where grades sit at about 1%, though the recoveries we're getting are quite low. That's the material going in at present.
Alex Bedwany
analystAlberto, was that figure for the most recent quarter?
Alberto Lavandeira
executiveNo, I'd say that's on a year-to-date basis.
Alex Bedwany
analystThe past six months.
Alberto Lavandeira
executiveAround the July figures — I believe it was the July figures. I'm just recalling what was in the report on July; I don't have it with me right now. At the top of the hill, we haven't yet gotten into the fresh material. We're beginning to make contact with it, but it's heavily oxidized. Its grade is roughly 0.3, yet it's very oxidized. That material doesn't go to the plant, since it holds a lot of oxide material. Exactly when we'll hit the fresh material, I honestly don't know. If I had to guess, I'd say the end of this year. Before then, I don't believe we'll have it. Just glancing at the top — I'm thinking out loud here, because I know it ought to be that way across all the plants, but judging by the hill and so forth, my assumption is it won't be fresh until we're down at the hill level.
Alex Bedwany
analystThat’s clear. As a quick follow-up on the polymetallic zone: when do you expect to decide on expanding the recovery circuit at the plant? And do you feel you need a firm answer on how Elix looks before you can make that call?
Alberto Lavandeira
executiveMy view is that we’ll move straight ahead with sulfides, using a standard differential rotation. There’s still room at Elix for recovery improvement. That gives us sufficient flexibility to produce some mixed bulk concentrates that, if that plant is operating, we would upgrade. We can’t sit around and push our decision back for years, or for one year or two, because the polymetallic material will certainly be available to them in Marsa Albano. Alongside copper, we have polymetallic. In Majalales, we also have very good polymetallic. At San Antonio, where the grades are 1.6% copper, 1.8% copper, and 3.5% zinc, and those are only one kilometer away. We can’t rely on it entirely. In the future, we will likely be using Elix, but right now we are proceeding. When will this happen? I believe in the first part of 2026 we’ll have a complete budget and flow sheet and so forth. By first part, I mean probably the first quarter or thereabouts.
Alex Bedwany
analystAll right, thanks a lot, everyone.
César Sánchez
executiveThanks, Alex. Just to go over again what Alberto mentioned, so far this year we've mined 0.5 million tons out of San Diego, and the rest is coming from Southern Colorado.
Alex Bedwany
analystAll right, that's great. Thank you.
Operator
operatorOur following question is from Alexander Pierce at BMO. Your line is open now.
Alexander Pearce
analystGood morning, Alberto. You still appear confident about securing the Toro permit before year-end, but could you remind us of the other key stages for this project, and how soon after the permitting process do you believe you can begin work on the ground?
Alberto Lavandeira
executiveHonestly, getting started on site is going to move very quickly. Our teams are in place. For the big-ticket items with long lead times, we already have quotes and final quotes in hand. Essentially, everything is ready for us to begin. At this point, the one thing I'd say could likely hold us up is the weather. Starting in autumn wouldn't be my preference. It looks like we won't have every permit by autumn, since that's when the rain comes. Usually there's a really good window in January and February — cold yet dry. My sense is that's when we'll be clearing the grass, the topsoil and all of that. Permits should certainly come in by the end of this third quarter or the start of the fourth quarter. Things are progressing quite quickly. No special permits are needed beyond that. What I mean is, when you go through the strategic process, once the environmental permit is in hand, approval is nearly automatic. How long finalizing all the paperwork takes, I can't say — one month or two, whatever it is. The reality is that it's essentially a road of no return. Because this sits on the strategic route, we already have automatic access to land, water, roads, electricity, and any urbanistic land change.
Alberto Lavandeira
executiveYou skip the, let's say, lengthy process where a change in land use at the municipality is still required. Beyond that, there's a water discharge permit, as has occurred at other well-known operations in the paravel. Everything comes at once, and that's the key aspect of these matters. I foresee considerable development occurring during 2026. Hopefully that happens if the permits come through, and I assume they will, since I see no indications otherwise. Activity will be quite brisk in 2026. Incidentally, I didn't bring this up in the presentation. This project's financing is at a very advanced stage. We have written interest and are essentially set to visit the notary and sign with three Spanish banks, plus another two waiting in line, but three Spanish banks. We also hold a formal proposal from traders, offtakers, and smelters, or some combination of those, to finance up to basically 100% of the project. This is because all of Toro's offtakes will be very clean, free of any issues with any type of material, since they'll be premium concentrates for blending.
Alberto Lavandeira
executiveAnd there's also the point that concentrates will be available to Rio Tinto starting essentially this year and next year, because every offtake agreement we have in place at the moment with the offtakers is coming to an end — which means we'll be free.
Operator
operatorThanks a lot. That wraps up the questions from the conference line — we have no more. At this point I'll turn things over to management for the closing remarks.
Alberto Lavandeira
executiveJust want to say thanks for joining us. We appreciate your ongoing backing. It's been quite a long road, and our hope is that this positive path keeps going through the remainder of the year and in the years to come. Many thanks for your ongoing backing.
Operator
operatorI appreciate everyone joining us on today’s call. You’re welcome to hang up at this point. Take care.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Atalaya Mining Copper, S.A. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Atalaya Mining Copper, S.A. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Atalaya Mining Copper, S.A. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.