Aurelia Metals Limited (AMI) Earnings Call Transcript & Summary

October 23, 2024

Australian Securities Exchange AU Materials Metals and Mining earnings 51 min

Earnings Call Speaker Segments

Operator

operator
#1

We appreciate everyone being on the line, and we're glad to have you join the September 2024 quarterly conference call for Aurelia Metals Limited. <<operator_script>> At this point, I'll turn the call over to Mr. Bryan Quinn, our Managing Director and CEO. Please proceed.

Bryan Quinn

executive
#2

Appreciate everyone being here for today's September quarterly update. Joining me are Martin Cummings, our Chief Financial Officer; Andrew Graham, Chief Technical and Business Development Officer; and Angus Wyllie, Cobar Regional General Manager. During this meeting, we'll walk through the slides, so feel free to follow along with those issued alongside the release, and we'd welcome your questions toward the end of our presentation, which the adjudicator will coordinate for us. Beginning on Slide 3, I'd like to point out that, in effect, we've kept a robust cash position, with our operations once more financing our growth. To sort of flag a few of the quarter's key points, it matters that -- clearly, Peak has kept delivering consistent with our guidance. I'll go through some slides on that shortly. But in effect, the operation was set up with a somewhat softer quarter among our targets, very much consistent with our full-year guidance, and we're still seeing really solid operational performance come from Peak, and that clearly produces the cash that is in fact backing our growth ambitions.

Bryan Quinn

executive
#3

Regarding Federation, it was a genuinely thrilling quarter for us. Our first stope ore was fired and brought up to surface. We also held our official opening, which the Minister's office for the Honorable Courtney Houssos backed very strongly. Council members from the region were there as well. Community members from the consultative committees attended. Landowners and a few other general managers from the region also came along to the session for our Federation grand opening. It was a truly fantastic day, and it reinforces our conviction that we have a Tier 1 jurisdiction with solid regional backing to genuinely carry us forward with our growth aspirations. Dargues also reached a conclusion during this last quarter. Naturally, we had laid out some aspirations around safely maximizing cash for Dargues. As some of today's results show, we have delivered against that. We have clearly made sure we did the right thing by our people, and maximizing cash stands out as a real highlight for this quarter. And finally, the Cobar optimization scoping study has been finalized. We have been talking about that over previous quarters, offering some sense of the concepts for where we are heading with it. And today we will go into it in a bit more detail, in line with the release that also came out today.

Bryan Quinn

executive
#4

Every one of those present operational efforts, projects, studies, and even the shutdown of Dargues reflects great credit on the management team; there is a great deal happening within a small organization, yet it truly demonstrates that we have achieved a degree of stability and are genuinely moving the organization forward. Moving to Slide 4, I want to discuss group production and costs. As you can see, costs were somewhat lower in the first quarter compared with the prior quarter. Certain of these costs include Dargues costs for the last quarter. Those costs are clearly decreasing and will fall away as we go forward or become much smaller. All-in sustaining costs came in at $2,321, which is very much in line with what we expected for quarter 1. And obviously, we are guiding against it this year. But in effect, our focus at present is on transitioning our business into a base metals producer in FY '25. And so we will obviously continue reporting the metrics we have on the table, and we have set out the guidance above. Regarding what we produced, essentially all those metrics there for quarter 1 FY '25 are pretty much in line with our expectations.

Bryan Quinn

executive
#5

And regarding how we're set up and the order of things for the remainder of the year, we're right where we want to be on that. Looking at Slide 5 and the sustainability side, clearly our emphasis is on avoiding injuries and safeguarding the environment. That absolutely stays a priority for us, along with engaging the community and being a good neighbor, and along with ensuring our people's health meets the highest standard every day. We have in fact seen some gains in safety performance. We're still getting slips, trips and hand injuries. And clearly management is placing a big emphasis right now on genuinely being out in the field, leading our people, genuinely examining controls and hazards and kind of helping our people, coaching our people to stay ahead of the game and making sure we can stop these from happening. As you can kind of see from the environmental graph, we had a couple of environmental incidents that we reported under our recordable environmental incident frequency rate. One involved some substance at Dargues, related to some old workings at the top of the mine that we have in fact rectified. And the second involved a water leak at Federation, which was rectified, and stayed on the roadway actually inside the lease.

Bryan Quinn

executive
#6

But again, we did report it. So it's nothing major, yet clearly we're strongly committed to getting both of those metrics under control and lifting our results as a result. On the bright side, we are certainly seeing better reporting each quarter, since we want people to increase their awareness and report incidents — safety, health, environmental and community-related ones alike — so that we can clearly put controls in place and stop them happening again. A survey was recently finished by our employees, and we're also genuinely seeing an increase in people calling out or speaking up about issues within the organization, which is great, and that's exactly where we want the organization to head too. So our teams are engaged sustainably and are truly, in a sense, part of and taking ownership of our organization going forward on these various metrics as well as performance. So moving to Slide 6 for Peak. Look, regarding where we stand in the first quarter, we are certainly still delivering in line with our guidance. It has been a very consistent quarter-on-quarter on development performance. Going forward, we do expect that to ramp up with the extra equipment and setup we've put in place, particularly with some equipment arriving from Dargues — a production drilling jumbo has been taken to Peak mine and is being set up for additional operational areas.

Bryan Quinn

executive
#7

So really, you can kind of see that we've stayed consistent, and that's exactly what we're aiming for. And moving forward now, we'll have some higher targets, and we'll be pursuing that same consistency at the elevated number too. Ore mined, as I mentioned, was a touch softer than the prior quarter. But essentially, that formed part of the sequence in our mine plan, and it will certainly be heading in the right direction consistent with our guidance across the remaining quarters. Costs, obviously, cost per tonne does have an effect, clearly, on how many tonnes we mine. But clearly, we're comfortable with that when we look at our full year numbers too. What I've actually included in the graph for this quarter is additional detail on our recoveries. I suppose it's genuinely worth pointing out that we've truly been maximizing plant recoveries each quarter. That's really a major focus for our operational team right now. Essentially, as we bring Federation ore into the Peak processing facility this quarter, we obviously want our recoveries running and performing at a very high level. And so the focus has been on continuing to push all of those various commodities.

Bryan Quinn

executive
#8

These two charts focus solely on lead and zinc, both essential to the ore we receive from Federation. That small anomaly you'll notice we've boxed off corresponds to the quarter in which our online analyzer was out of service for over half of that month. Naturally, that did have an effect on recoveries during that quarter. Yet, as you can observe, there is clearly some ongoing enhancement occurring quarter over quarter in those recovery figures. We remain very much focused on our development work so we can stay ahead of stoping, and as I mentioned, we are certainly on track with full-year guidance for ore mining to supply our processing facility too. Let me now turn to the following slide on Federation. Progress there is clearly advancing well, consistent with reducing risk to our future at Federation and to the volumes we feed into the Peak processing facility. The first stope ore has in fact been fired, and it went very successfully. And the mine was open, as I noted, at the outset. What matters about that, in terms of securing genuine backing from the government — at both the local state level and among local community members who are involved — is that it truly reinforces our organization's position that we will expand within this region, and we have the right backing behind us.

Bryan Quinn

executive
#9

For any organization, having that license to operate is essential. So those two items represented a major celebration for us during the quarter just ended. When it comes to development, that's clearly a core value driver for us at present. Development is in fact running ahead of budget as we head toward the close of this quarter and keeps progressing very, very well, and infill drilling is doing the same. Infill drilling matters, clearly, for us to establish platforms, get them down, drill them out to design our future stopes and essentially ready ourselves for the future design as we advance downward into the mine, which is a new mine. So those two areas are performing well, particularly following the stretch we emerged from when rain hit us during the last quarter of FY '24. One more piece of exciting news was that we signed a fresh 3-year mining contract with Redpath. That has been an excellent outcome for us. Our partnership with them has been really good. They have essentially stood beside us in handling some of these water issues and been very proactive in helping us set up for success. That new term and agreement aligns very much with the economics from our feasibility study.

Bryan Quinn

executive
#10

We’re really happy that we’ve secured a solid agreement, a strong working relationship, and a contract with Redpath moving forward. At this point, most of the surface work for the ROM stockpile has been finished. The preparation for the paste plant, the haulage road, and the different dams around the Federation surface area is complete, and demobilization for the Stage 2 surface works is more or less done as well. The water management infrastructure we installed to handle the heavy rainfall is now up and running. There are still a couple of minor tasks remaining related to mining some of the dam areas. But in the end, I have to say we’ve substantially reduced the risk on the surface works now, and the emphasis is on underground development and infill drilling to position the mine for the future as we keep preparing ourselves to ramp up operations through the rest of FY ’25. Regarding Dargues, as I said earlier, having operations finished is a huge milestone—really maximizing the cash and doing it safely as we bring Dargues to a close. I think it’s a real credit to the team that they’ve handled it in such a positive way, looking after people and making sure we’ve either redeployed them to the Cobar region or kept some staff on care and maintenance/closure.

Bryan Quinn

executive
#11

So then, clearly, we released the rest of the workforce — the contracting partners as well as the employees — and did it in a really positive manner. I mentioned I was fortunate enough to be there at their farewell, which was really positive and deeply emotional for those people. But in effect, I believe closing the operation at this stage was the correct call, and we've returned home with a strong cash position, just as we promised. The sale of the plant and equipment is still underway. We held an auction not long ago and will of course report on how that went next quarter, at the close of this quarter, and we're in the last stages of putting contracts in place for some of the bigger pieces of equipment too. At the end of this quarter we'll report on how those things turned out and how the proceeds from those sales will be applied toward paying future bills. And clearly, the priority at the moment is mine closure. So with a compact care and maintenance crew plus a set of consultants carrying out the closure work, we're really focused on how we plan that going forward and ensure it's positioned for success, so that we can carry it out across the years ahead and then wind that process down as we reach completion over the next several years.

Bryan Quinn

executive
#12

Look, before I turn things over to Andrew to walk through the optimization study, I just want to reinforce one quick point. As I said, it's exciting news that we're discussing this Cobar Basin optimization study and its conclusions. But the timing is also right for us. It's important to keep in mind that over the last 18 months we've delivered results consistently when it comes to how operations perform, generating cash, preserving cash, and maintaining a strong balance sheet. We've definitely placed a lot of focus on getting our development and our operations at Peak under control, ramping down Dargues in a controlled manner, maximizing cash while also building Federation in a controlled way, regardless of some of the unexpected headwinds from rainfall. So delivering this project comes at a good time for us. We believe the organization is in the right state of mind and has the right kind of control to move forward with this. So we have the infrastructure to leverage off this, we have the geological prospectivity ahead of us, and we've now got some great talent that we're bringing into our teams to really set us up for success in the Cobar region.

Bryan Quinn

executive
#13

I'll pass things over to Andrew now, and he might briefly cover some exploration matters as well as discuss the study, and then he'll hand things to Martin. Thanks. Andrew?

Andrew Graham

executive
#14

Thanks, Bryan. As Bryan mentioned, I'd usually walk you through an exploration slide at this point. I haven't included one today, since I want to keep the focus squarely on that Cobar optimization study, which I'm sure is top of mind for all of you too. Still, before we get into that, let me say a few words on exploration. It's been a busy quarter, with some drilling on the surface, although we did retender our surface drilling contract, and that meant we weren't drilling during the early part of the quarter. Deepcore won that contract for the remainder of this year and mobilized at the back end of the quarter. Importantly, they mobilized a rig to Nymagee, where we're drilling right now, and I'll come back to that in a little while as well; they also sent a rig to Chesney to focus on infill, specifically the Chesney East Gold Lens. Underground drilling has continued without interruption at Peak, targeting Hercules, Kairos Deeps, Jubilee North and New Cobar Deeps. You can find information on that in the quarterly release, and we'll obviously provide results once we have them all together. We've also completed a bunch of soil work, soils in the Nymagee region. And it's all part of building out the program we've discussed previously, stepping through those stages of exploration.

Andrew Graham

executive
#15

Turning now to the Cobar optimization study — it's on Slide 9 of the pack if you're following along. That study has helped us pinpoint a route that genuinely unlocks meaningful extra value for shareholders, and it does that while lowering risk across our business and giving us a genuine option for a step change in production. So let's walk through it. As you'll remember, we laid out a plan earlier in which we preferentially fed ore from Federation Mine into the Peak processing plant. Then, once that plant reached full capacity, we restarted Hera and ran the remaining lower-grade Federation ore through Hera. When we put that out, it marked quite a shift from constructing a brand-new plant. Having a base plant that we could finance also matters, and that's what we were doing at that point. It was achievable. It was permitted. It relied on plants that were already in place. But as you're also aware, we always believed we could do better. That's the reason we launched this Cobar Basin optimization study. The aim of the study was to establish the optimal configuration for the mines and plants across that Cobar Basin. And the study pinpointed — and this is a key piece — and quantified substantial latent capacity inside the Peak processing plant.

Andrew Graham

executive
#16

And you have to remember that we batch feed Peak with lead zinc ore or copper ore, and the latent capacity and the constraint shift depending on what we're feeding it. So while we're feeding lead zinc ore, the constraint sits at the back end, particularly in flotation. While we're feeding copper ore, the constraint sits at the front end in grinding. And when we looked into that, relieving that constraint on grinding — so on copper ore — was a much cheaper exercise. So through the study we moved very quickly toward how do we get more copper ore through the plant, use that latent capacity within the plant to process at a higher rate and, in doing so, allow us to process all of the Federation ore through that Peak plant as well. So the study determined that the key plant upgrades required were quite minimal — in effect, crushing and a bit of materials handling ahead of the existing feeders and the existing SAG mill, as well as a ball mill to give us additional grinding capacity. And when we looked into it, the lowest capital and most efficient way to do that, and also very fit for purpose, was relocating the Dargues ball mill to Peak and installing that in a kind of a tertiary grinding capacity after the existing ball mill that we have at Peak.

Andrew Graham

executive
#17

So that gives us a genuinely capital-efficient way to boost throughput, since we'd be drawing on latent capacity that's already sitting there in the plant. And at roughly $20 million, that's approximately the same amount of capital you'd need to restart and reconfigure Hera, complete the tailings dam lift, and handle all of those related items. As I said, it generates considerable value — we're putting the figure at $40 million to $60 million in additional value. From that you can see this is a highly capital-efficient project, and that really stems from tapping the latent capacity that's already in place. The value comes from a few sources: first, higher net revenue from producing a lead product and a separate zinc product from the Federation ores at the Peak processing plant, instead of the bulk con we would have produced out of Hera. Just as importantly, we'd also be paid for gold and silver, which wouldn't happen with a bulk con out of Hera. And as you'll remember, the Peak plant is fairly unique in having a full CIL plant at the back end. So we achieve excellent recoveries on precious metals. Another point is that at Peak we'd be paid for copper, especially the copper from the Federation ores that we'd report to the lead concentrate.

Andrew Graham

executive
#18

That copper wouldn't generate any payment for us in a bulk concentrate coming out of Hera. Our operating costs are much lower. Put simply, we're operating one plant rather than two, which means we eliminate all the fixed costs tied to running Hera. Peak is connected to the grid as well, so power costs are considerably lower than they are off-grid at Hera. Let's not forget about Hera. Expanding Peak gives us something very useful: a highly valuable option within the Hera processing infrastructure. And the challenge for me and the team is this — how do we restart Hera, and what ores do we feed that plant with? There's a range of alternatives here. One option involves backhauling ore from Peak, and that depends on our ability to bring on things such as Great Cobar and grow that output. And Nymagee — I brought that up earlier in exploration. It sits very close to the Hera processing plant, and having that infrastructure in place certainly gives us a much better chance, as we're able to prove up resource at Nymagee, to bring it through a processing plant. We have a very prospective region of package, which we've discussed a lot previously. And certainly, any discovery becomes much more valuable when processing infrastructure exists.

Andrew Graham

executive
#19

We would also look at feeds from third parties. One item in the release is that the study found a compelling chance to boost slope performance by changing how process water is managed, and we intend to move on that very fast. So our next steps are, of course, to make sure that work is underway. We did not wait for this release to push those things forward. A tender process is close to wrapping up for engineering support that will carry us into the next stage of study. And the critical path for expanding throughput at Peak concerns permitting, and the study work needed to back any permit changes is certainly very active right now. We will keep you updated as things move along over the coming quarters. On the whole, the study is a real credit to the technical team, which has thought about the business differently, challenged the status quo and truly delivered a path to enhancing shareholder value. So we are certainly pleased with where we have landed. Passing now to Martin with the other strength, I suppose, our balance sheet. Over to you, Martin.

Martin Cummings

executive
#20

Thanks, Andrew. Moving on to Slide 10 now. As we mentioned earlier, it's genuinely gratifying that our operations have once again kept our balance sheet in a strong position. Total cash on hand is still above 100%, as you can see — $103.2 million. Peak and Dargues combined brought in $24 million, which more than covered what we invested in Federation and exploration. Peak remains a dependable source of cash, delivering $16.7 million this quarter. Our attention is still firmly on bringing unit costs down. That said, fewer ore tonnes mined during the quarter pushed the unit rate higher. I should note, however, that actual dollar spend came in roughly $2.6 million lower this quarter. Part of how we get those costs down is by lifting productivity at the mine. If you follow our LinkedIn page, you may have seen earlier this month that we're putting money into 2 new trucks, which will retire 2 old haul trucks at Peak and help deliver better availability and reduced operating costs. The first of those trucks is already working at Peak and the second is en route. That represents an investment of approximately $4 million, which we've included in our FY '25 sustaining capital guidance, and our equipment leases will fund them.

Martin Cummings

executive
#21

Dargues generated $7.3 million in cash flow despite having operated for just 2 months. And as was noted, every bit of concentrate is now going out, and we'll aim to wrap up all those shipments during the December quarter. It was a really satisfying way to finish up at Dargues, with the site team moving from operations into closure activities in a highly disciplined fashion. Within this cash figure sits roughly $3 million of payments tied to redundancies and the retention programs we put in place earlier in the year. We're now nicely positioned, with a compact team, to oversee the work at Dargues. And we guided $3 million to $5 million for this year, with about $300,000 spent during this quarter. And just as a reminder, closure activities at Dargues will carry on into FY '26. As Bryan noted, it was an extremely busy quarter at Federation — development restarted following the water delays, the official opening took place, we fired our first stope, and we finalized the contract with Redpath. And our total spend of $17.9 million is on track and consistent with our guidance of $70 million to $80 million for the year. As Andrew noted, exploration saw a somewhat quieter quarter in spending terms, as the team wrapped up the new drilling contracts and their plans for the rest of the year.

Martin Cummings

executive
#22

On the corporate tax side and other items, we got a tax refund of $3.8 million tied to our amended FY '23 tax return, so that was a welcome bit of news. The other thing I'll mention falls under financing cash flows. We've now drawn down in full on our performance bond facility with Trafigura — that facility was AUD 65 million. During the quarter, we had to put up an additional $10.4 million in performance bonding connected to Peak. That bond has been lodged, and it's fully cash-backed. The cash sits in a term deposit and is earning interest. Right now I'm working through options involving a bigger performance bond facility so we can get that cash back. Adjusting just for that item, we'd have ended the quarter with roughly $114 million in cash prior to lodging that restricted cash. Last thing — you'll have noticed we added some hedging to the book, and that was for FY '26; the prices we've locked in cover a modest share of our revenue but give the balance sheet added strength as we move Federation toward commercial production and progress organic growth options through the Peak expansion and Great Cobar.

Martin Cummings

executive
#23

For a more detailed breakdown by year, the accompanying release covers volumes and pricing for each year. So I appreciate everyone's time today, and I'll turn the call back over to Bryan.

Bryan Quinn

executive
#24

Thanks, Martin. To close out on where Aurelia's attention will be directed from here: clearly, we're highly focused on delivering our operating performance and our projects and operations safely, with the real aim of filling our mills with quality ore. That remains very much on track and is a priority for the team. With the existing operations and the ramp at Peak, at both South and North mine, the emphasis is squarely on figuring out how we maximize volume while bringing unit costs down. And with Federation's ramp-up to commercial production, that's very much a key priority across these 12 months — we're still on budget and on schedule for the end of this financial year to deliver that ramp-up to commercial production. So it's really about executing that well, and I'm fully confident the team has the right people and processes in place to make it happen. When it comes to maximizing cash generation over the remainder of this financial year and beyond, really it's about delivering our volumes consistently and reliably in line with our guidance, and our costs as well. There's a lot of work under way on the cost base, as Martin mentioned, around new equipment coming in to replace some higher cost equipment.

Bryan Quinn

executive
#25

We're also concentrating on deploying certain Dargues equipment largely to support other equipment that requires maintenance. And we remain very much on track toward a target of $100 a tonne for mining and under $50 a tonne for processing, given all the initiatives and improvements we're pursuing. We currently have a BOA process running at the Peak mine and at the Federation project mine. And in effect, that will produce substantial cash to genuinely assist us in meeting our cost targets across both processing and mine operations. As Andrew pointed out, considerable work is underway when it comes to advancing our studies. As you've heard today, regarding the Peak expansion, there's a strong emphasis on how we get it established, get the project completed and bring it to FID within this financial year, and likewise how we finalize the Great Cobar study to FID within this financial year. Both of those projects and studies will truly constitute the next chapter for Aurelia, focused on filling our mills with quality ore at low cost and delivering solid cash flow benefits to shareholders and stakeholders. Underpinning the growth is clearly essential.

Bryan Quinn

executive
#26

We know the infrastructure is there. We know we can grow it. And we know the geology exists, and we know that with the right amount of drilling we can find it. Obviously, what supports that is having the right talent in the Cobar region behind us. And that's clearly something we're working on very actively at the moment, revising our people strategies, examining how we can bring in and draw these genuinely capable and talented industry people to come work with us. So far, I have to say, over the last 12 months, we've had some really good success bringing in the right people, and I can only see upside from here with people joining us as we keep succeeding in growing. And last, but not least, our exploration is super important, as Andrew mentioned, it's kind of the feed for us when we look at our organic growth options. And really, if you think about it now that we have -- if this study moves in the right direction and the expansion happens with Peak, we've basically created an opportunity for over 1.5 million tonnes of capacity in the Cobar region for Aurelia, and that's going to be fundamental to us to then look at how we make sure we fill that capacity with our geology or with other third-party options or operational improvements.

Bryan Quinn

executive
#27

So honestly, our priority areas are arranged in the proper sequence, and we're confident that this will create substantial value for shareholders down the road. And so I suppose our view is that the plan we have now is functioning and heading the right way. So perhaps I'll turn things back to the adjudicator so we can take a few questions, and then I'll wrap up afterward. Many thanks.

Operator

operator
#28

<<operator_script>> The initial question is from Daniel Roden of Jefferies.

Daniel Roden

analyst
#29

I wanted to begin by getting some clarity on the Cobar optimization study. Regarding the timing of the plant upgrade within that NPV, is that upgrade expected around FY '26/'27?

Bryan Quinn

executive
#30

Andrew, do you want to take that question?

Andrew Graham

executive
#31

Yes. The plan is for us to work on that during the latter part of FY '25 and put it in place across all our schedules in FY '26. As Federation ramps up, obviously, we have some spare capacity at Peak right now, and we'll use that for Federation ore. But as it ramps up, we will be able to keep pace with the ramp-up of Federation. We obviously have the ability to restart Hera as an option if we really needed to, so for example, if there was an unexpected delay in permitting or some issue in permitting, for example. But at this stage, the plan is to achieve that in parallel and be able to move to the expansion to fit with the ramp-up of Federation.

Daniel Roden

analyst
#32

Yes. Perfect. So those permits are capped at 200,000 tonnes per annum right now, and I believe your discussions last quarter and earlier were about raising that to 600,000 tonnes per annum. Is there any room to go above that? And do those discussions form part of the application already in place to amend that permitting?

Andrew Graham

executive
#33

Yes. So there are a couple of components we need to work through to allow that. The first one, which you were quite right to bring up, is getting that 200,000 tonnes per year of trucking up to 600,000, or whatever Federation can handle. That's quite far along and is with the government at this point. We expect to receive it early next calendar year. Right now, we've capped our request at that 600,000. There's always room to revise that later if we found we had the ability to do so. But at a certain point, you have to ask, "Well, what am I trying to permit," and simply get it permitted. The other item we discussed regarding permitting is throughput at Peak. So at present we're constrained in what we can put through there. And we would then look to extend that to roughly 1.1 million tonnes, 1.2 million tonnes per annum. We don't view that as a problem. We're not causing any environmental impact. Obviously, a somewhat higher intensity since we'd be putting more through, but it fits within the permitted tailings dam use of the water we're already permitted to use. So we don't see any real problem on that front.

Daniel Roden

analyst
#34

All right, and perhaps just one final question regarding the study. That study does, though in a somewhat loose way, address Nymagee and Great Cobar as part of it. I just wanted to get clarification: if mill throughput rose, that would clearly accelerate the need for Great Cobar and possibly for Nymagee to form part of that blended feed profile. In its present form, does this study cover Nymagee and Great Cobar? Or would those be, I suppose, extra upside to the NPV and the valuation of that project?

Andrew Graham

executive
#35

Yes. So a study on Great Cobar has already been done before. Right now we're quite busy working through the process of updating that study, so that we can then move to a proper final investment decision early next calendar year and after that begin development toward Great Cobar. As things stand, that schedule lines up nicely with our capacity to feed extra Peak material first and afterward switch over to Great Cobar material, which would then run through that expanded Peak processing plant. Nymagee is a different story. So we haven't built that into our plans, and we've discussed before the need to prove up an additional resource at Nymagee, which is the reason we're drilling so actively at the moment. And the thinking, or the hope, would be that it sits only a couple of Ks from the Hera plant. If that Hera plant were available, it would make infinite sense to be able to put that through the Hera processing plant. But that's upside to the kind of numbers we talked about today.

Operator

operator
#36

<<operator_script>> Our following question is from Adam Baker of Macquarie.

Adam Baker

analyst
#37

Appreciate the Cobar Basin update. I'm curious how you're viewing Hera at this point, since restarting it ranks as the least favored choice. In terms of extracting value from that asset — whether through a sale, or as you noted, turning it back on should the need arise — how are you approaching that? Just interested in your thinking on it.

Bryan Quinn

executive
#38

Yes. Thanks, Adam, for that question. Right now, we'll keep it on care and maintenance, obviously, at a minimal cost. It's basically been down since April last year. So it hasn't been down for too long and in care and maintenance. And as I said, we'll get more results in FY '25 from our drilling campaigns to understand what that option looks like. But at the moment, we'll retain that part of our portfolio and look at how we can utilize that capacity going forward, whether it's with our ore that we establish and find and can make viable from our portfolio of growth options or we'll talk to third-parties about some sort of tolling option in the future as well if it makes sense. So definitely, we'll retain that option for ourselves. It gives us growth beyond Peak, obviously, beyond Peak processing facility, and it gives us an opportunity to really go after the next phase of growth beyond what's on the table now.

Adam Baker

analyst
#39

If a suitable offer were to come along for it, is that the kind of thing you would think about?

Bryan Quinn

executive
#40

That would probably come down to a commercial choice made at the time. I’m not in a position to answer that right now. But as I mentioned, right now we’re taking into account how we fill our mills and grow past the existing Peak expansion, and consider 1.5 million tonnes of capacity. And as you know, we’re devoting considerable time and considerable money to drilling in that region, particularly down in the Federation, Nymagee area. And the results — we’ve seen some growth in our resource base, and we’re actively pursuing that resource this year through our aggressive drilling program. So I think we’d always want to see what we have first before arriving at any commercial outcome. But as I mentioned, I’ll wait to see what that commercial option was first before making that decision.

Adam Baker

analyst
#41

Alright, great. And regarding Peak and the capacity that keeps rising — from 800,000 to 1.1 million, then 1.2 million tonnes per annum — could you remind me what the water license you hold at present can support, up to what level?

Andrew Graham

executive
#42

I'll take that one, Adam. Right now, Peak has 2 water sources in particular. The first is water supplied via the pipeline running from Nyngan over to Cobar. We hold an allocation of roughly 1.2 gigaliters from that pipeline, and once losses and everything else that happens are accounted for, we actually see about half of it. That supply, combined with around 200 megaliters from underground dewatering, is enough for what the plant currently handles and would support something in the order of 800,000. We hold a water access license for groundwater of up to 800 megaliters per annum. We also intend to dewater Great Cobar in particular, both as part of getting across the mine and because it's a genuinely good water source on the lease. So when it comes to water, we have more than sufficient for the expansion under the water access licenses we already hold.

Adam Baker

analyst
#43

All right, then. So the capacity arriving through the pipe wouldn't be raised — instead, you'd simply be pulling more from the underground water sources you already have in place. Is that correct?

Andrew Graham

executive
#44

Absolutely, that is definitely what we plan to do. And in addition to Great Cobar, there is also a lot of water underground at New Occidental, along with the old workings in that area. So there is considerable water in-ground inside the mine workings, rather than in bores and aqua and similar sources. What I mean is, we intend to draw on those, which is the reason I say there is essentially no environmental impact outside the footprint that already exists there from our operations.

Adam Baker

analyst
#45

Understood. And a final quick question from me: what's the timing for the Great Cobar study?

Bryan Quinn

executive
#46

As for those plans, we've brought them before the Board during this financial year. With any luck, in the final quarter of this year, we'll be able to share some FID outcomes with the market.

Operator

operator
#47

<<operator_script>> Our following question is from Ashley Chan, a private investor.

Shareholder

unknown
#48

Everyone, is my voice coming through?

Bryan Quinn

executive
#49

Absolutely, that’s something we’re able to do.

Ashley Chan

executive
#50

I'm only a small retail investor holding roughly 400,000 shares. I really appreciate your presentation covering the operational, geological, and optimization study. That was genuinely helpful, and I have no issues with it. I just have a question about hedging gold sales. First, why do it? And second, what has hedging cost, comparing the hedge price with the spot price, for full year '24 and first quarter '25?

Martin Cummings

executive
#51

Ashley, it's Martin. The reason behind this really comes down to running our business well. Sure, we're benefiting from the elevated prices at the moment, but we don't want our future to depend on this price level persisting. So I look at hedging as purchasing a measure of revenue insurance, and I'm keeping modest amounts of that insurance in place to safeguard the balance sheet and to secure some of that gain today. As you can see, our all-in sustaining cost sits well under the current gold price, so I'm locking in that margin on those ounces. That's the rationale, because honestly, there's a bigger prize here when it comes to the organic options we can unlock with a robust balance sheet. On cost, you can see, I suppose, the cost of -- I don't have that specific figure with me, but the realized prices we report in our quarterly reports are net of those hedge settlements that, as you noted, are negative at present. But as I said, they're prudent hedging and part of our overall capital management plan.

Shareholder

unknown
#52

Now, taking the first quarter — the September quarter's hedging, according to what's in the March quarterly report — you had a hedge price of, let's say, $3,080, and the average gold price for that quarter is $3,730, which gives a differential of $650. So on roughly 7,000 ounces hedged, just under that, the amount would be about $4.5 million. Then looking ahead, you've got hedging on 14,000 ounces with a differential of $550, so that's roughly $7.5 million, which brings us to about $12 million per year. So the revenue foregone, or the cost of hedging, comes to $12 million a year. Over 10 years, that's $120 million, or 1/3 of market cap. Would out-of-the-money put options be cheaper? What is the Board policy? And does that kind of hedging cost align with Board policy?

Martin Cummings

executive
#53

I'd prefer not to call that the cost of hedging, because at the time we put those hedges on, we didn't have the advantage of hindsight that we have today. And of course, you've cited a period of 10 years. Our hedge book initially covered more than 12 months, and we've since pushed it out to 21 months. So when we entered those hedges, the prices were very attractive and they locked in our margins. That's why we only do it on a modest share of our production. Under our policy, we wouldn't go above 50% within a 12-month window. So I do want to keep exposure to those gold prices over the longer term. But clearly, we have capital intensity in the near term, and we want protection from that. So I won't make the extrapolations that you've made. Yes, those adjustments you mentioned regarding hedge realizations of $7 million and $4 million are roughly right for those periods. But I'd also like to factor in the benefit we received on the unhedged ounces during that period as well, which is well above those amounts.

Ashley Chan

executive
#54

All right, turning to the latter portion of your question: does this fall under management policy or Board policy? And if it is indeed a Board policy, what precisely does the Board policy on hedging say? Also, would out-of-the-money put options have been looked at, or were they turned down?

Martin Cummings

executive
#55

When we use collars, the structure involves out-of-the-money put options. I imagine the zero cost collar idea is something you already know. At certain times, yes, those have been attractive when you weigh the upside potential against the downside protection. However, given how the forward price currently sits in contango, my preference is to lock in that certainty through forwards on a smaller share of production rather than turning to other derivative-style products. On policy, we do have a policy that permits hedging. Every hedge we put on is a separate, specific Board decision. So there's no mandate requiring us to hedge at all times. As management, we decide what level of protection we want for the balance sheet. We then bring a recommendation to the Board. The Board reviews it and either approves or rejects it. That's the process we follow right now. So it isn't a mandated program that obliges us to do it.

Ashley Chan

executive
#56

Alright, one final question on this—apologies for belaboring the matter. So is it your intention to tell the market, then, that you are hedging part of your gold output, and that your strategy does not give you full exposure to a rising gold price? Or is this merely a temporary step meant to cover the ramp-up at Federation?

Martin Cummings

executive
#57

It's definitely the second one. So right now we can secure an excellent price to carry out our growth projects and capture the upside you're seeing. The Peak throughput expansion, Great Cobar, and getting Federation online all add substantial value there. We don't want the balance sheet to be the thing steering that strategy during that window. Our balance sheet is strong. We intend to keep it that way. In our view it's as strong as, or stronger than, most of our peers, and we want to safeguard that. In that setting, purchasing a modest amount of revenue insurance is a sensible move.

Operator

operator
#58

That brings us to the end of the Q&A. I'll turn things over to Mr. Quinn now for some closing remarks.

Bryan Quinn

executive
#59

Thanks, Darcy, and I appreciate the questions coming in online today. To wrap things up, though, as I've said previously, what we're really focused on this year is making sure we can safely operate in line with our strategy — and that strategy is essentially about filling our mills with ore of the right quality. To achieve that, clearly, the Federation ramp-up is essential, and it remains well and truly on track for commercial production by the end of this year. We'll keep maximizing cash flow. You've watched us accomplish that through Dargues, through the quality at Dargues, and clearly right now our attention is very much on doing the same through volumes at the right lower cost, with Angus and the regional team helping us. You've heard today about our emphasis on project and study progress, which Andrew discussed. And there's a lot of work ahead this year to reach that FID stage both for the Peak expansion and for the Great Cobar FID later this year. You've also heard that people, obviously, are a pillar of success for us here, and we're putting a lot of effort into attracting and retaining people for our growing business, and that work continues.

Bryan Quinn

executive
#60

There's a great deal of effort already in motion on the planning side, aimed at restoring our exploration to where it basically was — running 4 to 5 rigs — so we can truly unlock our growth options. As I mentioned before, this marks roughly the fifth or sixth quarterly update in which we've managed to deliver consistent results. Obviously, there will be ups and downs along the way, but the team we've got in place genuinely believes we're headed in the right direction to position ourselves for success. So all the different activities we discussed today really do set us on the proper course to reach the point where we can grow the business organically with what we already have, before we start looking over the fence. I'd like to thank everybody for dialing in today, and thank you for the questions — we look forward to presenting next quarter. Thanks, Darcy.

Operator

operator
#61

Thanks. That brings today's conference to a close. We appreciate everyone taking part. You can go ahead and disconnect now.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Aurelia Metals Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to Aurelia Metals Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Aurelia Metals Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.