Bathurst Resources Limited (BRL) Earnings Call Transcript & Summary

April 29, 2024

Australian Securities Exchange AU Materials Metals and Mining earnings 25 min

Earnings Call Speaker Segments

Richard Tacon

executive
#1

Hello, everyone. I'm Richard Tacon, CEO of Bathurst Resources. Thank you all for joining us and for walking through our Q3 results presentation. I hope and trust that everyone can see the presentation, and we'll get started. A few disclaimers. There hasn't been much movement in the corporate overview since we last gave a quarterly update — a bit more cash sitting in the bank. Roughly $13 million extra is in the bank. Out of that, approximately $13 million belongs to the Bathurst account. Honestly, there's not much of a shift in our market capitalization either, I'm afraid. Our overall shareholder base hasn't really changed. So for anyone who's new to Bathurst or wants a quick refresher, the company operates across 2 distinct regions. We have New Zealand, which is shown on the slide in front of you. We have 2 operations on the North Island, Maramarua and Rotowaro, which mostly supply New Zealand steel plus a couple of other large agri businesses, and that includes some domestic coals for heating purposes, but primarily it's New Zealand steel and the steelmaking process. The Stockton mine on the South Island and the West Coast is 100% export to Japan, Korea, India and China. And then we have Takitimu down south, which is a 100% owned operation, supplying mainly process heat coal to value-added New Zealand prim production.

Richard Tacon

executive
#2

Okay, so once more, this is a dairy advertise business, vegetable manufacturing, and it's primarily for export. Our head office sits in Wellington, and there's a regional office in Christchurch that handles the joint venture. The two North Island mines plus the South Island mine, Stockton, are held via a joint venture structure alongside a big New Zealand company that's privately owned, and our stake in those operations is 65%. Turning to Canada, there are two projects: the Crown Mountain project, which we've been part of since 2018, and the Tenas project, which we acquired recently and own 100%. Crown Mountain is held in a joint venture with an Australian listed company named Jameson. Right now we hold 22% of that project, with an option at FID to move up to 50%. One sits in the Elk Valley, a well-known hard coking coal district, while the other is a greenfields project north of Vancouver in the Telkwa area. Now, on our safety stats for the last quarter — well, this is year-to-date. Unfortunately we've had one lost time injury at the Rotowaro mine, a twisted ankle suffered by a worker getting out of the Canada fuel truck. We've had a number of injuries across the whole of the business.

Richard Tacon

executive
#3

We had quite a few fairly small injuries that needed treatment away from the site. As a result, both our rate of injuries requiring medical care and our total recoverable injury rate sit well above what we consider acceptable — they are very high. So we launched a program. Some of the signals we saw suggested our training setup was somewhat fragmented. So we're rolling out a learning management system company-wide. On top of that, we have a broad audit program and we're working with site management teams on how they use risk management tools, which we also identified as contributing factors. Turning to the quarterly result — let me go back to that slide — for the export side of the business. We're basically where we want to be for the year. Clearly, pricing came in somewhat above what we had originally assumed in the budget when we assembled it in June of last year. Our production tonnes took a substantial hit across the past two quarters because of rail outages, which meant we had to keep going with overburden removal — that has actually stayed on target — but we had to limit where we run production so we could still cover immediate shipment requirements, since we've been short on the tonnes we've had moving on rail.

Richard Tacon

executive
#4

And we expect that shortfall to continue into quarter 4, with roughly 50,000 tonnes potentially lost across the full year. It's not that those tonnes disappear — they'll move into the following year — but overall earnings will be offset by elevated prices that the benchmark price keeps supporting. Rotowaro sits well below. We've faced a good number of problems with output at the Waipuna West extension mine — part of the mine, equipment, weather. And also in terms of staffing up through this period, with a fairly substantial increase in overburden removal risk as we move into that new block. The older block, Waipuna West, is in fact doing very well. A lot of coal now sits under cover there. So that coal will be coming through over the next 2 quarters. But we do have a fairly high strip ratio. And I have another slide on that as we move further ahead — looking at some more forward-looking material. Maramarua has been doing very well. We've seen increased tonnage from the K1 pit.

Richard Tacon

executive
#5

A lot of that coal is headed to steelmaking and to a big dairy customer, and we're more or less on target for the year and slightly ahead for the quarter. Takitimu is doing really well. We've seen production rise on the back of higher sales. The average price is stronger, and our overall cost actually being lower means we're ahead on EBITDA, profit, and cash generation. So the mine is performing very well. And looking at our safety stats, Takitimu and Maramarua have recorded 0 lost time injuries over the last 12 months. In fact, Takitimu has gone 5 years without a lost time injury. So we've kind of got 2 quite different parts of our business with Stockton and Rotowaro, but both of them have a reasonable fourth quarter ahead of them. So overall, again, revenue is up, EBITDA is up, and profit is up for the quarter, and we're now pretty much matching where we said we'd be for the full year. So again, as we've kind of shown in some of these past presentations, we've got about $145 million in the bank today.

Richard Tacon

executive
#6

Outside of some modest yellow goods financing, we carry 0 debt. With strong earnings, we continue to expect to land in that range of $95 million to $105 million. And based on the half yearly result, our net asset backing sits at roughly $1.64. So we're in a good position. Regarding our guidance, we still anticipate being within that $95 million to $105 million range. There are some movements on the export side, obviously, with certain tonnage dropping out. But as I mentioned, we're enjoying higher benchmark pricing this quarter and expect that to carry through into the next quarter. We also have hedging that assists in holding up that position. Overall, we'll be slightly negative in the North Island, but we will be net positive in the South Island. So Telkwa — a small amount is going into that at the moment, mainly around the environmental assessment application process. And again, there'll be a bit more of an update once we get into the next phase. The forward curve, I mean, is relatively flat. We have seen it come off a little. But if you translate that another 12 months further out, we see it sort of rising, and it's really in contango going out to about $261, I believe, which was the pricing over the weekend at 12 months out.

Richard Tacon

executive
#7

Clearly, that is now becoming a component of how we build out our hedging strategy. In addition, we will look to draw direction from it when preparing for the coming fiscal year. What I mean is that additional supply is arriving from Australia, and that has genuinely been satisfying spot market needs, and a significant portion of the benchmark price is composed, clearly, of the spot average across the prior 3 months plus 1. Right now we are observing somewhat more of that spot coal being offered. The Indian and Chinese markets have remained rather flat, with domestic pricing having softened somewhat. Yet the signals suggest that early in the upcoming fiscal year, beyond June of 2024, we should begin to witness a pickup in steel output and in demand for coking coal specifically, and for iron ore as well. So I believe near that 250 level we have referenced as a longer-term price, we should be able to look at that on a sustainable basis for our pricing next year. Naturally, we will provide further guidance on this around the time we release our quarterly results for quarter 4 and the full-year result for next year -- for last year.

Richard Tacon

executive
#8

Looking forward, then — and for anyone who's just joined the company — we have 2 main areas. First, North Island, which supplies, again, mainly into steelmaking at a domestic steel plant; second, the export business out of Stockton, which sells into the international coking coal market. So we have several growth projects tied to both of those hubs. The reason we frame it that way is that fixed infrastructure already exists there, so we don't need to duplicate it in order to bring on additional coal reserves. In Stockton's case — that's the export hub — there's the wash plant, the aerial system that moves the coal to the rollout facility, and obviously the existing contracts and customer base let us bring on other projects that dovetail into existing production remaining within the Stockland holdings. That forms part of an overall plan aimed at trying to hold production at current rates of roughly 1.2 million tonnes for about another 20 years. So we're somewhere between feasibility and pre-feas, depending on which project we're in right now, and looking to pull that together, which, again, fits into the fast track process the government has announced.

Richard Tacon

executive
#9

We’ll cover that once more across a few additional slides. As for the North Island, everything revolves around the infrastructure already in place at Rotowaro. So once again, you’ve got a washery, a rail loader, a rail unloader, storage capacity, water control, and all the remaining infrastructure needed so that we can genuinely expand into other locations roughly 3 kilometers away from that hub infrastructure. Our current operations sit south of that infrastructure, and the places we’re discussing moving into lie to the north of it at approximately the same distance. And once more, coal will be transported there through a mix of private and public roads. That makes for fairly straightforward infrastructure and a fairly low cost to bring us into that production. Turning to Maramarua, again, it does not make use of stock and infrastructure, but it is a coal that does not need washing. It is a single seam of coal that has not been underground worked previously. So we are not affected by dilution. The mine gets -- the mine extracts the coal clean, and that goes directly to the customers. And we expect that an increasing share will be going into the Glenbrook steel plant. So just looking at Rotowaro, we have moved into the new area, which we call the Waipuna West extension.

Richard Tacon

executive
#10

We are 2 years into this, and we're roughly about a year through now of pretty extensive overburden removal. The strip ratio overall there is 20:1, so it's a high strip block. Obviously, the revenue we get for it compensates us for that. But we've got 2 years of fairly extensive removal, more than 10 million BCM per annum. And based on their forecast today, that's expected to begin scaling back in August '25. And then from that period on, we move into a future production phase where a lot of coal will be under light cover. We'll see a significant reduction in the overall cost, and we'll have around about 350,000 tonnes of coal coming out per annum out to 2028. So we've got a period now where we've got probably our highest production risk, the most amount of overburden removal. One of the issues we've had year-to-date is that we've been down in terms of the overall production on a month-by-month basis. And so we haven't been putting as much of the C1 cash cost onto the balance sheet, which has then affected the EBITDA that we've been reporting. But in terms of a cash basis, we're not moving the debt, but we're also not spending the cash.

Richard Tacon

executive
#11

So clearly, at some point we can't let ourselves keep sliding out. The reconciliation between anticipated coal and the coal mine has actually been good. And we're also a bit ahead of overburn removal at the Waipuna West pit — the one you see in the lower half of this picture with plenty of coal in the light color. We also have substantial coal stocks that we've had to draw down on so we can meet steady sales. So the big push right now — we're at the stage of forming this now — is to get into a position where we hit our targets month by month. We're moving toward that very quickly and expect that for the rest of the period through August '25, we'll be in that high-cost but also high-productivity region. So production in Canada — I touched on this briefly earlier — the 2 projects, 2 different districts and really 2 totally separate projects. As we said, obviously, the Crown Mountain project is owned through Jameson.

Richard Tacon

executive
#12

When it comes to Jameson, our stake stands at 22%, and there's a chance for us to raise it to 50% by paying CAD 106 million, essentially at the point when the final investment decision gets made. So that happens following permitting and once the rest of the project finance has already been put in place. As for the Tenas project, we finished that acquisition in late '23, in December '23. We'll be pressing ahead with it. Bathurst will own it 100%, and it's expected to produce roughly 1 million tonnes annually, while Crown Mountain comes in at about 2 million tonnes a year. That works out to roughly 1 million tonnes of equity tonnes for us. On the Tenas project, as I mentioned, we've now assumed full ownership. We've got a small team that came to us with that project, which makes us very happy — mostly mining engineers plus some people on the ground in the Smithers Telkwa area, where the mine sits. Our engagement with First Nations and the local community has been really positive. And I'd say one sign of that is the project assessment agreement should be signed off very soon. That's a fairly clear step which really lets us begin crossing off some of the information requests we've received from the regulator as we move toward the next, or final, stage of the permitting process.

Richard Tacon

executive
#13

When it comes to Crown Mountain, it's genuinely the sole steelmaking coal development project in Canada that has reached the joint federal and provincial review stage. So we've been working through the formal public and technical review processes, which really involved a lot of open houses. 6 open houses were planned and carried out during that effort earlier this year, and from there we moved into the more technical study components of the environmental assessment and the application phase. That's a solid step forward into the next phase. Clearly, as a result, it sits roughly one phase behind where Telkwa stands with the Tenas project. So yes, we expect it will likely be around 12 months behind the Tenas project in terms of development. So when it comes to cash spend and the intensity of activity, that's probably going to be a positive thing. Bringing it all together, once again, anyone who has followed the company for some time would recognize this graph. Our South Island business is expected to begin running out of customer in '28, '29. That aligns with the existing reserve at the current operation.

Richard Tacon

executive
#14

There are growth projects tied to that. But honestly, what our major customers in the region are telling us is that they intend to switch to alternative fuels and/or relocate production. So we expect that portion of the business to conclude around '28. Clearly, we're still making — we don't foresee any slowdown whatsoever, especially in the timeframe we're discussing, out to 2040. So the existing business at Stockton sustains us through to '34. And then there's the expansion project, as I mentioned earlier, which kicks in beginning in '28, which then lets us replace those extra tonnes and continue at roughly that 1 million to 1.2 million tonnes. The North Island business is the same, serving the same customers and running through to 2040. And again, really around the northern growth of the business, using the existing hub. Tenas arrives in the '26, '27 period and again, entering the coking coal market, and Crown Mountain arrives a year later, '27 to '28, at about 2 million tonnes a year into the hard coking coal market. So really what underpins, particularly the New Zealand developments, is that we had a change of government come in late last year, late '23.

Richard Tacon

executive
#15

That's a coalition between national ACT and New Zealand First—the first of its kind. As part of that coalition agreement, all 3 parties shared a general understanding that something had to be done about the resource management process, and also about the broader permitting and resource allocation process. New Zealand has seen some large projects that were planned over a long period and fully funded, yet they simply haven't happened. And that applies not only to the private sector but to the public sector too. So the answer that's been devised and that the national government is currently advancing is a Fast Track Approval Bill. Now, calling it Fast Track isn't really a misnomer. They're trying to get projects approved and out the door more quickly. But the key part here, really, is that a single application will then result in multiple permits, consents, approvals, and authorizations. So for any major project in New Zealand, especially a mining project, you've generally got district council consents or land use consents, and you've got regional council consents. If you're on public land, you've either got a lien sign-off or a Department of Conservation sign-off regarding access and/or you might hold concessions with Department of Conservation.

Richard Tacon

executive
#16

You also need wildlife permits and various other approvals before a project can actually get underway. What has typically occurred historically is that every one of those came with a somewhat distinct set of conditions or, even more significantly, a somewhat distinct test, which means the applications differ a bit and the time frames differ a bit. So it's quite possible you receive your resource consents from the District Council. Interested parties may appeal them, and that takes you through the court system. Then, running alongside or in sequence with that, you go through a range of other application and review processes that lead, hopefully, to a consent or an authorization at the finish. So what the bill is designed to do is bring all of that together into a single panel process, in which a panel then sets out a set of conditions built around an approval. And from that, you get the separate consents or authorizations you need in order to actually go and run the mine, the infrastructure project, the wind farm, the aquacultural project, whatever it may be. The other minor adjustment -- well, in fact, it isn't minor for coal miners, but the Resource Management Act got amended a couple of times over the final year of the last labor government.

Richard Tacon

executive
#17

Among the significant shifts was the introduction of a genuine sunset provision affecting the capacity of coal mines—and only coal mines—to seek fresh approvals under the freshwater environmental standards as well as the national policy statements concerning indigenous biodiversity. That applied solely to coal mining. Clearly, then, it was an effort aimed at reducing coal supply. Yet users continue to expect they will rely on coal considerably beyond 2030, be it for value-added prime production, steelmaking, cement making, or various other processes that contribute to economic development in New Zealand. Accordingly, this government intends to reverse those changes and create a level playing field. It will then make no difference whether you are mining gold, obtaining aggregates for cement or regional development, or coal—you will receive identical treatment. So this does not represent a lowering of environmental standards. It is essentially about leveling the playing field. What we have—returning to this graph—is that one question raised recently concerns the impact of having the extension projects. And what portion of that involves Bathurst 100% owned coal, and what portion of those, especially the New Zealand projects, is held via a joint venture structure.

Richard Tacon

executive
#18

Now, when we look at the export extension, roughly 50% of it will be coal that BRL owns 100%, and 50% of that portion will be BT coal. The NAS project, clearly, is wholly owned by Bathurst, and currently about 50% of Crown Mountain will be held by Bathurst, and that sits outside the joint venture that already exists in New Zealand. So when you think about how things shape up going out to, say, 2030, the outcome is that Bathurst-only coal, the coal that isn't locked inside a joint venture, will make up a considerably bigger share. In fact, that takes us to roughly 1.5 million tonnes of coal headed into steelmaking that sits outside any joint venture structure. There was another question that came up about the joint venture structure and where we stand on that. Well, the joint venture is working very well. Really, if you go through that presentation, essentially all of the cash-generating operations in the portfolio belong to the joint venture. And honestly, that structure hasn't really changed at all. Right now, the cash that is tied up there is held in deposits at the best rate available.

Richard Tacon

executive
#19

And I guess the JV's stance has been, and still is, that those funds can be put back to work in appropriate projects, and that could very well include the ones I've just described. So clearly, a number of the New Zealand assets we're expanding into will need capital to move them forward. We're looking at roughly $30 million to $40 million across the North Island and the South Island — probably somewhat below that. On the BRL side, though, we need something in the order of $40 million to $50 million. Then, with the Tenas project and Crown Mountain, Tenas will require about CAD 100 million, and Crown Mountain, as I mentioned, will require CAD 106 million to get us to the 50%. And beyond that, some additional project financing will be needed, whether that comes via debt or a cash injection from the joint venture partners, to bring that project on. That's roughly a CAD 300 million spend in total, with that initial CAD 106 million coming out of our cash in. So thanks very much. As we said earlier, we aren't running the sessions as a straightforward Q&A.

Richard Tacon

executive
#20

It’s somewhat unfair to those unable to join the call live. But if you record anything or submit questions, following the most recent quarterly, there were a few remarks that we — once more, we didn’t actually issue a Q&A. The reason is that no questions reached us. So you’re welcome to send questions, and I’ll gladly respond to them, and we’ll share those as a general announcement to the entire market. Once again, many thanks for being with us, and I hope to reconnect with you before long. Thank you very much.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Bathurst Resources Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Bathurst Resources Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Bathurst Resources Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.