BCI Minerals Limited (BCI) Earnings Call Transcript & Summary

July 29, 2025

Australian Securities Exchange AU Materials Metals and Mining earnings 29 min

Earnings Call Speaker Segments

Operator

operator
#1

Thank you for being with us, and welcome to the BCI Minerals Quarterly Update. At this point I'll pass the conference to David Boshoff, Managing Director. Over to you.

David Boshoff

executive
#2

Good morning, everyone, and thanks for joining. My name is David Boshoff, and our CFO, Steve Fewster, is here with me. We're glad to be with you today for this June quarterly update. Before we begin, I want to point out that today's presentation should be read alongside our June quarterly report, which can be found on BCI's website. As we go through today's session, please feel free to post questions in the chat function, and we'll address them at the end. It's been a strong quarter for BCI. We've made progress with filling the ponds, commissioned the first crystallizers, and achieved solid progress across construction. Importantly, safety and our community stay at the forefront of everything we do. We're excited about the milestones that show the momentum we're carrying as we move towards first revenue. This success comes from our people and our contract partners, who bring our values to life every day. The team has truly exemplified our value of winning as one team, delivering together. We are laser-focused on delivering salt production by 2026 and proving up SOP. We're committed to do what we say. Salt is now in full operations and set to deliver $286 million in EBITDA every year.

David Boshoff

executive
#3

Work at the SOP pilot plant is coming along nicely as well, with the goal of reaching $99 million in EBITDA once it's fully running. There's further upside at Cape Preston West Port too, since spare capacity could bring in revenue from third parties. Mardie already ranks as Australia's biggest salt operation and third largest worldwide. It's also the most significant salt and SOP development this country has seen in 30 years. Sitting strategically in an established solar salt region, Mardie provides a hard-to-copy asset base, with port advantages, access and approvals, plus land tenure. Our production target is 5.3 million tonnes per annum of high-quality industrial salt. Given its scale, coastal position and integrated port, Mardie is exceptionally well placed to serve growing demand across Asia. Now I'll walk you through a quick update on our progress this quarter. On safety, we've kept strengthening key fatality prevention controls, verified through more than 250 critical control verifications. We also logged over 500 field leadership interactions this quarter, and our total recordable injury frequency rate reflects our ongoing safe operations as well, with a 12-month rolling average now at 2.3. Construction remains on schedule and within budget, with overall completion now at 70%. I'll share more details on that later.

David Boshoff

executive
#4

This quarter we successfully completed the shift to running at full scale and measuring performance against plan. Seawater is now being pumped from both the primary and the secondary intake stations, and we've reached 77% service inundation, moving more than 146 gigaliters of seawater through the end of June. Importantly, we're still firmly on schedule for first salt on ship in the December quarter of 2026. On the corporate side, we keep building out our leadership team. Mhairi Cameron joined as General Manager for Operations, based in Karratha, and Elizabeth Shaw has come on board as Joint Company Secretary as well. During the quarter, an implementation committee meeting was held with the Wirrawandi Aboriginal Corporation. We expanded our university scholarships with the Pilbara Kimberley University Centre and carried on our partnerships with Karratha Senior High School through the Positive Behavior Support program. I'll now pass things to Steve, who will give an update on our financials.

Steve Fewster

executive
#5

Yes. Thanks, David. From a financial standpoint, BCI is still in a solid position. During the quarter we drew $115.4 million from our syndicated debt facility, which brings the total cash drawn under that facility to $236.1 million. All members of the syndicate will be involved in the next drawdown. And now that full-scale operations have begun, giving us a clear pathway to revenue, we've put our treasury management strategy in place. We have now hedged roughly about half of the U.S. dollars we'll receive from the sale of Salt in 2027 and 2028, at rates ranging from $0.642 to $0.657, which sits well below our target rate of $0.69. I'd also like to share a little about our drawdown process. Our funding covers a 45-day period. And before each drawdown, we're required to carry out a project cost reconciliation and provide it along with an opinion from our lenders' independent technical expert. That opinion confirms to lenders that BCI is fully funded to complete construction of the project and also has sufficient working capital requirements to operate beyond that. Today, we've received approvals under this process to issue 5 drawdown notices. This test gives us confidence, as we keep delivering on our project, that BCI remains fully funded.

Steve Fewster

executive
#6

It's also good to see our share price close the quarter at $0.34. That's a 39% increase from the $0.245 we closed at in March. The main driver behind this rerating was largely the approval to move into full operations. We've since watched our market capitalization reach $1 billion, though that remains under the $1.1 billion we've invested so far. Also, on the 1st of July, we received $34.1 million from Polaris Minerals, a subsidiary of Mineral Resources, after the Iron Valley sale was completed, as announced in June last year. David will now provide more detail on operations and construction progress at Mardie.

David Boshoff

executive
#7

Thanks, Steve. As noted previously, this quarter we moved into full-scale operations, and we wrapped up that process with 77% of the surface ponds inundated. By the end of June, water extended through Pond 1 right through to Pond 6, plus Pond 8. And shortly after the quarter closed, we began pumping water into Pond 7, once Transfer Station 6/7 was commissioned. On top of that, this past weekend we opened the weir gates leading from Pond 8 into Pond 9. As a result, water now runs from Pond 0 all the way through to Pond 9. We also brought several other key infrastructure items online. These took in the secondary seawater intake. They took in the first crystallizer, which is about to begin filling with water, along with Transfer Stations 2/3, 3/4 and 5/6. We commissioned the site-wide SCADA system, now fully installed, enabling remote operations from the control center at our village. We've additionally awarded fabrication of our salt harvester to Camco Engineering in Perth, and manufacturing of that capital infrastructure is moving along really well. I'm happy with the way construction is tracking. We're still on schedule and within budget. When the quarter ended, crystallizer construction was well advanced, with 76% already done.

David Boshoff

executive
#8

At Cape Preston West Port, the marine package likewise got to 91% complete. And with the Pilbara Ports Access Road, progress there has reached 82% complete. As things stand, just 2 major contracts remain to be awarded. Of those, the first covers construction of the salt wash plant, and the second is for the dredging. Each of these contracts is either in design or close to being awarded. Steve will now walk us through the all-important financials.

Steve Fewster

executive
#9

Yes. Thanks, David. And look, I'm genuinely enthusiastic about the market's developments. Having just been to Indonesia and Singapore recently, what we observe regarding the medium-term prospects for high-grade industrial salt is that robust demand will be coming from across the Asian region. This is mostly driven by the impact of elevated energy and labor costs in Europe. As a result, the Europeans are being compelled to shut down several of their chlor-alkali plants. At the same time, demand keeps rising in line with global GDP for the chemicals those plants produce. So because of that, we keep seeing new plants commissioned across Asia, and that is replacing the capacity shut down in Europe. In fact, in June, I went to one such plant built in Indonesia. Pricing data for the June quarter was still being turned in when we were putting this report together. So we had an incomplete data set in the databases we rely on for tracking. Still, the early indication is that salt prices have firmed somewhat since the March quarter. Now I should note that, anecdotally, some salt buyers we speak with are staying fairly cautious in the near term, and that is really a result of the current geopolitical landscape.

Steve Fewster

executive
#10

During our prior quarterly update, we mentioned that Cape Preston West Port infrastructure is entirely owned by BCI. This facility serves multiple users and was engineered to provide roughly 20 million tonnes of bulk commodity capacity, achievable through handling salt, SOP, and additional products like iron ore. When operating at nameplate capacity, the requirements for Mardie salt and SOP come to only about 5.5 million tonnes. That therefore leaves us with roughly 14.5 million tonnes per annum of spare capacity that we could be utilizing throughout this infrastructure. This may prove an important answer for certain mine developers in the West Pilbara region who presently lack port access. By the end of June, a substantial share of that marine infrastructure had been finished, and it now stands at 91% complete. Recent accomplishments include the jetty piling along with installation of the ship loader tower and the boom over the quarter. In fact, the most recent visit was to the top of that salt wash, at the top of the salt stacker. Efforts are ongoing on the small boat landing module, and what remains is a fairly brief dredging program lasting about 2 months, which is set to begin around April next year.

Steve Fewster

executive
#11

This is a crucial prerequisite before transshipping operations can begin. David will now walk you through an update on the SOP pilot plant.

David Boshoff

executive
#12

SOP is still a key piece of what lies ahead for us. It comes out of our salt operations as a byproduct, and it's a sustainable, high-value fertilizer ingredient that matters a great deal for food security in this country. Once our SOP output is at full scale, we expect it to bring in roughly $99 million of EBITDA each year. The KTMS trial crystallizers are close to finished, and we're nearly at the point of taking the first KTMS brines into the SOP pilot plant. The design of that SOP pilot plant is coming together as well, with a construction plan timed to match KTMS' self-production. Steve will take us through the cash flows now.

Steve Fewster

executive
#13

Thanks to its limitless resource and modest sustaining CapEx needs, Mardie could produce returns resembling a long-term annuity. And now that Salt is fully ramped up at 5.3 million tonnes per annum, we expect it to generate free cash flow equal to roughly $0.068 per share. Once we're producing 140,000 tonnes of SOP, that figure rises to approximately $0.088 per share. This also leaves out any possible contribution from the Cape Preston West Port. At present, our target for first dividends is around 2029, and we'll likely be able to fully repay the debt facilities for the salt operations in around 2035. I'll now pass things to David for the conclusion.

David Boshoff

executive
#14

Thank you, Steve. We're wrapping up both this quarter and the financial year from a strong position, succeeding together as one team. Mardie is a premium, large-scale operation ready to meet an anticipated supply gap while demand climbs worldwide. Since 62% of the salt we produce is already committed under offtake agreements covering the first 3 years, we expect robust annuity-style returns across a 60-year life. Add the possible upside from Cape Preston West Port and SOP, and BCI sits in a good place for a short runway to profitability along with sustainable growth over the long term. That concludes our presentation. We'll now take questions. If you haven't done so yet, please send them through the chat box.

Operator

operator
#15

Thanks, David and Steve. Our first question here is this: in your presentation, we heard that pumping to Pond 9 began over the weekend. Could you tell us how long filling it up will take?

David Boshoff

executive
#16

Yes, absolutely. Over the weekend, we opened up the weir gates. Those are the gates through which water flows via the culverts into Pond 9. Pond 9, of course, is the final pond in the circuit of ponds that runs right from Pond 1 all the way down to Pond 9. And with this pond, our expectation is that by the end of August it will have reached capacity. What that means is that, at that point, every one of our pond plants will be at capacity and set for the evaporation process to get underway in the summer season.

Operator

operator
#17

Great. You also brought up that 2 construction packages remain outstanding. Could you give us a little more information about those?

David Boshoff

executive
#18

Right, that's accurate. So neither the salt wash plant construction package nor the dredging package has been awarded as of yet. The salt wash plant sits at 30% design through one of our contracted partners, Sedgman. Sedgman is progressing really well. All the long-lead items have already been procured by us, and construction of that facility still has to be awarded. My expectation is that the physical -- the SMP construction will take place early in the new year. Civil construction will get underway this year already. On the dredging side, we're still working through a final component of our approval. As you may be aware, we've had full approvals in place for onshore dumping. However, doing sea dumping close to our location is more cost effective and environmentally friendly. We expect those approvals to come through later this year, ready for dredging to commence in April next year. Now, as Steve mentioned, the dredging program is a short one. That's because we've managed to optimize the volume. So I don't see any risk when it comes to the dredging being able to commence and be completed on time.

Operator

operator
#19

Steve, could you give us an update on where things stand with your transhipper?

Steve Fewster

executive
#20

Yes, thank you. Our approach to transshipping involves two separate transshippers. For roughly the first 12 months, we'll be relying on one named the Osprey. That vessel has already been constructed and is currently in China, where modifications are being made so it fits the Mardie application. Those modifications should wrap up early next year. After that, it will move to Mardie around July next year. A commissioning period will follow. The pilots will receive training — we hold a pilot exemption from the PPA — apologies, the skippers will receive training. That transfer operation will last approximately the first 12 months. This transhipper's annual capacity comes to about 3 million tonnes per annum. Around July 27, our replacement transhipper will show up, and that vessel will provide service throughout the 21-year term of the agreement, carrying capacity of roughly 6 million tonnes per annum. Final designs for the new transhipper are being progressed right now, and I'd anticipate that within roughly the next 3 to 4 months, the first deal will be cut and construction will begin to gather real momentum.

Operator

operator
#21

<<operator_script>> At this point we have a question regarding spending. How confident are you about keeping your capital budget on track? And are you taking any shortcuts in order to achieve that?

David Boshoff

executive
#22

We've made quite a bit of headway on the construction side. As everyone listening knows, we're close to 70% complete in terms of — a big share of the money we've actually outlaid or — so the residual capital risk comes down to 2 contracts: the dredging and the salt wash plant construction. On the salt wash build, once again, cost performance has been really strong. So my expectation is that it lands well under. The efficiency that lets us capture savings comes largely from productivity gains on earthworks. As you'd imagine, earthworks make up a very big piece of what we spend on construction. And the bulk of the cost reduction has come from measures that don't alter any outcome as far as the physical construction goes, yet lower the cost. A simple illustration: if you use a scraper, your haul circuits get shorter, and locating good material near your construction zones cuts cost without changing anything when it comes to quality and the construction finish. So everything we've built has either met or in fact beaten certain specifications. And a portion of those savings has gone toward pulling forward some of the capital construction that we had actually planned for later years.

Steve Fewster

executive
#23

If I may, I’ll add a point on that too. Under our debt facilities, the banks also bring in an independent technical expert. That expert visits the site every quarter and sends a formal report to the lenders, assuring them that construction matches the scope behind the debt financing. Should we ever wish to change that scope for any reason, we must follow a fairly rigorous process so the independent technical expert can sign off that any modifications still preserve our capacity. So first, we are managing the project extremely well. Second, everything we state is also being audited by the independent technical expert.

Operator

operator
#24

Great. We have a few questions now regarding the Cape Preston West Port. One concerns Agrimin, which intends to construct an extremely lengthy road leading to a distant port. Given that the Cape Preston West Port has 14.5 million tonnes per annum of surplus capacity, will that capacity be made available in order to improve Agrimin's viability as a proposition?

Steve Fewster

executive
#25

Of course — if Agrimin can make their project’s economics work by using our port facilities, then we would definitely welcome them as a possible partner.

Operator

operator
#26

You also brought up some additional interest in the Cape Preston West Port. Could you share anything further on that?

Steve Fewster

executive
#27

Right now, it's premature for us to say anything. It's enough to note that anyone familiar with or who grasps the West Pilbara region knows there is definitely a lack of capacity — of capacity that already exists — and of the ability to secure approvals. And building another port in that area carries a very difficult cost. So my expectation is that as more people come to understand what our capacity is, and as we get nearer to finishing the project, we'll see far more inbound inquiries regarding access.

Operator

operator
#28

So regarding those inquiries, for anyone who has interest in that area, what does the process look like for securing that capacity?

Steve Fewster

executive
#29

Absolutely. If you reach out to me directly — I think my contact info appears in several of our LinkedIn posts — but in any case, I'll serve as your initial point of contact.

Operator

operator
#30

Great. Now I have a question about what keeps management up at night. What are you focused on right now? And is anything running behind schedule?

David Boshoff

executive
#31

Well, I think there's definitely much less that keeps you up at night today compared with 2, 3 years back. It feels as though we've reduced the number of outstanding risks. The most recent one, and I'm pretty pleased with how we wrapped it up, was the jetty construction. As you'd have seen in the slides, progress has been really strong, ship loaders are on, and the final SMP work is well along. The 2 items still outstanding are the salt wash plant and the dredging. Those are the 2 things I'm concentrating on. On the salt wash plant, like I said, we're actually handling those costs very well. The construction team has done a great job making sure we build a fit-for-purpose facility. On the dredging side, we do have full approvals for onshore dumping. And even if onshore dumping were required, that sits within our current budget. The chance to cut that down and make it more efficient matters to me. So we're very focused on securing that sea dumping permit, which is one of the subsets of that approval. So those are the 2 items I'm focused on. Then third is, of course, the ramp-up to first salt on ship, which takes us to first revenue.

David Boshoff

executive
#32

Things are moving along quite nicely with the ponds. Our next priority for the coming quarter is to make considerably more headway on the crystallizer filling strategy, and I will of course keep shareholders updated as we make progress on that.

Operator

operator
#33

Moving on now to marketing and offtake: we’ve had a number of agreements sitting in place for some time. So for the remaining sales, what’s your plan?

Steve Fewster

executive
#34

Right. So the goal we have is to reach at least 70% of the output in any given year being sold through an offtake agreement. There are two reasons behind that: the main one is that our debt facilities demand 70% be sold; the second is that we're still fairly bullish on where salt prices could go, so we want to keep some product available for the spot market, since we see a chance to benefit from those prices as they rise over time and to use the spot market to capture that.

Operator

operator
#35

You mentioned that BCI is still on schedule and within budget. Could you tell us more about SOP and what comes next in that area?

David Boshoff

executive
#36

Yes, absolutely. Right now, the KTMS pilot crystallizer at the site is nearly finished. These are smaller-scale crystallizers that have actually been constructed on location, directly beside where the SOP plant will ultimately sit. So that work is moving along very nicely. We're expecting to introduce our first KTMS brine into it starting next month. It should then be set for the summer season, when it will begin producing KTMS salts. As you may remember from earlier updates, we've already made KTMS salts on site, though at a far smaller, more or less lab-style scale. So this marks an important next step in showing the market that we're able to produce high-quality KTMS salts on site at the Mardie location. The following step is to carry on with the design of our salt pilot plant -- sorry, SOP pilot plant. In the next couple of weeks, I'm actually traveling to China to look at some pilot plants that are already in operation. Construction of that pilot plant, I expect, will get underway early next year. After that, we intend to operate that pilot plant for a minimum of 12 months, so we can capture a complete weather cycle out at Mardie and show that we can produce SOP from it.

David Boshoff

executive
#37

Once we begin building the SOP pilot plant, we'll definitely ensure the market is kept informed about it. After that, we'll keep validating those test results and make sure we can reach a solid outcome. I think the key thing I want to emphasize here is that our SOP pilot timeline is driven by outcomes, not by time. That distinction matters, because I want to be certain we've verified all those various chemical outcomes and testing outcomes that we need to confirm, so we can have confidence that when we put money into a full-scale SOP plant, it will be efficient, it will be productive, and it will deliver what it's meant to.

Operator

operator
#38

On the engineering and design side, could you update us on how things are going with the salt wash plant?

David Boshoff

executive
#39

Yes, absolutely. So as I said in response to one of the earlier questions, we are 30% complete. We have already placed orders for the 4 key long-lead items for this pilot plant — sorry, for the salt wash plant. Design work is moving along very well. We are currently in the final stages of the SMP and electrical design. After that is finished, we will then begin by awarding the earthworks package first. My expectation is that this happens before the end of this calendar year, before Christmas, so that we can complete the earthworks. Then, soon afterward, comes the footings and after that the actual physical construction. This plant is in fact quite small relative to other plants I have been involved in building previously. And so our focus is very much on production efficiency. That means construction efficiency, which will involve modularization of some of the components, but also making sure we have an efficient supply system bringing those plant components to the site.

Steve Fewster

executive
#40

And David, regarding how the salt wash plant is designed — from what I understand, when the approvals were first secured, we were set to build a fairly large, complex structure. So what does the final design look like at this point? And how much has that design work helped us in managing the budget and maybe in achieving a better cost outcome?

David Boshoff

executive
#41

Right, so the initial design featured a really big elutriator — roughly 30 meters tall — and it was situated at the jetty. The issue there, naturally, is that you end up with just one production stream. That leaves you with a single point of failure within the production system, making it pretty vulnerable. On top of that, its placement near the jetty meant that in our region — given cyclone prime — you'd need substantial footings and construction design work, which again drives up cost. So about 2 to 2.5 years ago, we relocated it to the crystallizer. We also reduced the plant's height and divided the production system into 2 streams. The upshot is that when maintenance is needed on one stream, the other can keep running, so only 50% of your plant is down — or, if a breakdown occurs, as happens with all plants, you can operate one stream while repairs are underway. That boosts reliability and brings cost down.

Operator

operator
#42

Great. Thanks, David and Steve. That takes us to the conclusion of the presentation. Should you have any additional questions, we're happy to take them whenever. Feel free to contact us directly, and we'll see you next time.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete BCI Minerals Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to BCI Minerals Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in BCI Minerals Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.