Mark Learmonth

executive
#1

Thanks, Scott, and welcome to the results presentation for Caledonia's third quarter. May we open the presentation, please? Fine, let's proceed to the disclaimer, which I trust you'll consider and digest. Let's carry on. As I mentioned, I'm Mark Learmonth, chief executive of Caledonia. With me is Ross Jerrard, our CFO, and Victor Gapare, another executive director, who is chiefly responsible for the Bilboes project. Craig Harvey serves as our Vice President of Technical Services, and he'll speak to us about exploration. Maurice Mason is here as well. He handles corporate development and investor relations. Could we continue, please? Right, just highlighting a half dozen items coming out of the quarter. What isn't on this slide is that it was actually an excellent quarter for safety, which we'll discuss in a moment. The gold price was good; we realized more than $4,100 an ounce, up 20% on the comparable period. Production, as we previously indicated, was somewhat disappointing at just over 17,000 ounces for the quarter. We're going into more detail, but that stemmed from production problems arising from a lack of compressed air, compounded by some difficulties in the metallurgical plant. The operating financial performance was quite strong. EBITDA came to $28 million for the quarter, and for the nine months, that puts us at nearly $108 million. Ross will talk in a lot more detail about that, but it's fair to say that below EBITDA, there was an awful lot of very complex financial accounting, largely concerning the financial accounting for some derivatives, which went a long way toward unpicking the reasonably solid financial performance. At quarter end, we're delighted to announce that we've secured the third leg of our funding package for Bilboes, which is a $150 million interim funding facility. Again, Ross will discuss that in more detail. Craig will talk to us a bit more about this, but we were also very pleased to announce a significant increase in the measured and indicated resources at Blanket, up 22%. That includes quite an exciting short-term opportunity in respect of some oxides, which Craig will talk about. Then also a maiden resource at the Motapa property, just under 400,000 ounces there, and that sits immediately adjacent to Bilboes, and we believe will, in due course, give rise to some exciting potential there. And then finally, it's worth just noting that we've declared another quarterly dividend of $0.14 a share, which will be paid, I think, at the end of this month. Shall we move on? Okay, let's just talk a little bit more about production. I've already indicated that for the quarter, it was just over 17,000 ounces, just over 49,000 ounces for the nine months, and that was somewhat less than we'd expected. So building on that, we lowered the 2026 guidance to between 69,000 and 72,500 ounces for the year, and that points to a solid Q4, which I'll cover in a little more detail shortly. It's really worth asking what held us back during the third quarter. As I mentioned, two issues were at play. The first was on the mining side; a compressed air shortfall cut into our ability to mine effectively in the deeper, high-grade zones at Blanket. We had anticipated this and ordered four additional compressors to provide the extra compressed air capacity. Two of those arrived. Two, unfortunately, got stuck at the port in Beira, Mozambique, because of congestion there. We'll say a bit more later about what happened after the quarter ended; but the effect was that during the period, especially late in the third quarter, we simply could not extract the tonnage we had planned from the deeper, higher-grade areas. The other difficulty during the quarter really came down to two mutually reinforcing problems in the metallurgical plant. The first involved certain changes we had made to the gravity gold circuit, which caused more free gold to report into the CIL plant, and that was compounded by a longstanding lack of efficiency and capacity in the elution circuit, so we could not recover that higher loading in the CIL process. Those two mutually reinforcing factors meant that at quarter end roughly 11,000 ounces of gold sat trapped in the CIL plant. Our focus for 2026 and into 2027, then, is to raise compressor capacity to support mining in the high-grade areas on the 30 and 34 levels; to add elution capacity; first of all to stop the gravity circuit decanting into the CIL, which we have done; then to add elution capacity so we can recover the retained gold; and after that to move on to recovering the gold in the activated carbon sitting there. We are also focused on raising production at the Little Lima metallurgical plant, which we recommissioned during the third quarter. Its contribution in the third quarter was very modest, but we are ramping up output there, and that should deliver more ounces in the fourth quarter. In addition, we are now starting to see the benefit of the accelerated development we began earlier in the year, which gives us better access to higher-grade mining areas and also improves our operating flexibility so we are protected from unforeseen eventualities. That's the overview of production for the quarter. Shall we move on? Given the dynamic situation we are in, we thought it appropriate to provide an immediate update on what has happened since the quarter ended, which was in October. In October, Blanket turned out slightly less than 7,000 ounces of gold, which marks a meaningful step up from the pace we were running at during earlier months. What you're seeing there was mostly the result of better grade. The grade achieved in October came in at 3.07 grams per ton, versus roughly 2.7, I believe, in the third quarter. So performance at Blanket improved considerably; it's fair to say that we were awaiting the new compressors, and those replacement compressors went into commission right at the end of October. Before that, during October, we had redirected whatever compressed air capacity was available so we could be sure of delivering the planned tons out of the high-grade areas. That lowered how quickly we were filling the plant with low-grade material. We also brought the new elution vessel into commission on the 16th of October, and that has let us begin making a dent in the 11,000 ounces of gold that was tied up in inventory as of the end of September. Smelting happens roughly once a week, so the latest smelt with complete results available to me took place on the 7th of November.

Mark Learmonth

executive
#2

As of 7 November, roughly 750 of the 1,100 trapped ounces had been recovered, and we anticipate getting the rest back, perhaps during the next smelt. After those trapped ounces are recovered, we can use the added elution capacity to deal with the 1,300 ounces of gold held in, I believe, around 60 tons of stockpiled activated carbon. So that covers production at Blanket. Another item you'll see approaching late in the quarter and continuing into next year is our work on the K-Pits. That involves oxide mining and processing at Blanket. We have loaded, or are in the process of loading, roughly 10,000 tons of material onto the test heap leach pads. Completion should come by the end of this week, irrigation begins on Monday, and we anticipate gold production starting between late November and December. Then, based on the results — and let's be honest, this remains a test heap leach — depending on how that process turns out, we have secured EIA approval, meaning we ought to be able to shift almost straight away into full-scale oxide mining and processing, with a target throughput of approximately 40,000 tons per month. So that looks quite promising; that sums up what has taken place since the quarter ended. May we go on, please? A bit more detail now on the quarter's operations. Next slide. It was, as I mentioned, a really solid quarter for health and safety. We recorded no lost time injuries, and we now have a streak exceeding 500 days without an LTI; an outstanding result, and may it keep going. Next slide, please. This graph has appeared before, but it usefully highlights the key drivers of production. The upper graph displays grade and tons. The top line indicates tons held steady, yet the grade, even in Q3, recovered only to roughly 2.7. Yes, that was above what we saw in the first quarter, but below our expectations. During the first quarter and part of the second, our capacity to reach high-grade zones was limited simply by lack of physical access. In the third quarter, access was available, but we couldn't actually mine there as planned, because of, as I noted, the compressed air shortage. Looking at the second, lower graph, the bars represent ounces, while the line represents recovery. Recovery did take somewhat of a step back during the third quarter, which mirrors the grade coming in a little below what we'd hoped for, but more significantly it mirrors the gold getting tied up in the CIL circuit, so our recoveries suffered as a result. Gold production for the quarter ended up somewhat disappointing, driven by both grades that fell short of expectations and weaker recovery. Let's move on, shall we? That gives you a quick picture of the quarter and of what has taken place since the quarter closed. I'll now pass things to Ross, who will take us through the third quarter financial results in greater detail.

Ross Jerrard

executive
#3

Thanks, Mark, and good afternoon, everyone. I'm very pleased to walk you through the results. Let's move to the next page and go through the summary. My overall take on the financial results for the quarter: it was a tough quarter when it comes to top-line gold ounces produced and sold, plus some working capital tie-up as Mark described, and there's also the fair value adjustment that ran through the quarter. Even so, we see the results showing up in a solid Blanket performance, and we're excited about the reset and how we close out the year in Q4, and importantly as we head into 2027. The activities, the expenditures and all our initiatives are coming through and bearing fruit; but just briefly on the summary, you'll see on the slide that gold ounces produced fell by about 11%, and Mark has already covered the compressed air shortages and some of the gold retained in the plant. On-mine cost came in higher, and if you jump to on-mine cost it's up about 23%, driven by higher volume movement but also by those lower ounces produced and sold, which affect that metric. I think the key thing is really our on-mine cost per ton milled, which rose about 9%, but importantly for the year it's only up 4%; so it's very much in line with what we expected and with performance. On absolute costs, the teams have done well at controlling their activities and their costs and making sure those flow through; we did get the benefit of the gold price, up about 20% at $4,134 per ounce, which went some way toward offsetting the lower ounces, but it did increase our royalties. You will see in our all-in sustaining costs, which are up about 21% on the ounces sold metric, that the 20% increase in average realized gold price has affected that and flowed through to our AISC number. Overall, EBITDA is down for the quarter, down about 16%, driven by those activities. I'm going to dive into a bit more detail on our P&L, and we can talk through some of those specifics. Let's turn to the next slide, please. Just quickly walking through the profit and loss statement, you will see top line revenue was up about 10%, which was that combination of the higher gold price and somewhat lower sales volumes. The flow-on impact in terms of the royalty I discussed shows the royalty charge increasing about 15% on the comparative quarter. Production costs broadly in line with our expectations, albeit up about 6%, but well controlled and we're happy with those activities. Gross profit up 14%, driven by those improved margins and because of the gold price. We have benefited at the top line. Moving down from gross profit, the majority of those line items are consistent, and while there have been shifts and some decreases, the main item is the $12.9 million derivative loss, or the change in fair value of the derivative. I want to emphasize that this is a non-cash item, and it comes from the different valuation models. I should also note that we recorded gains during the first and second quarters. Across the nine-month period, on that accounting basis we are in fact still ahead by $2.5 million. That said, it is non-cash, it is all recorded at corporate, and it has had a significant effect on our performance during a difficult quarter. Dropping a bit further down to profit for the period, and importantly what that means for the NCI, while Blanket delivered a solid performance despite the challenges and generated cash, distributed funds and earned a profit, the deployment of funds both to Blanket and the corporate adjustments I mentioned did result in a lower NCI, or a higher NCI, relative to profit attributable to the company, which came in at just a shade under $3 million for the quarter. Let's go to the next slide, please. Spending a moment on cash flows, top line cash inflow from operations rose roughly 19% to $31 million for the quarter. Our first finance cost charge has come through, reflecting finance costs on the convertible bond of $4.3 million. In the end, net cash flow from operating activities of $13.6 million was mostly applied against our capital expenditure profile, though it remains consistent with our expectation for the year. I will say a bit more about CapEx spending shortly, but it is very much on track and consistent with prior guidance. Beyond that, there were few other movements in cash flows other than our dividend payment of $9.2 million. Essentially, the cash generated went to CapEx, and we also had our dividend distributions, which meant the cash balance declined by just a shade under $10 million during the quarter, and we closed the period with cash and cash equivalents of $158 million. Please move to the next slide. What that means for our liquidity position appears in this table, and you can see cash on hand now stands at $161 million; we had a larger build in bullion on hand and in our gold sales receivables. There were 3,700 gold ounces in bullion on hand at period end, along with 1,600 ounces of gold sales receivables. Combined with our normal facilities of around $20 million, with just under $4 million drawn, that gives total liquidity of $196 million across those categories; we were very pleased with our interim financing facilities. As we said back in November, that strategy has now been executed. After the period closed, we find ourselves with pro forma liquidity available to us of slightly less than $350 million. Next slide, please. A brief reminder regarding our revised cost guidance, all of which was announced earlier. Our guidance was updated to align with the Blanket gold production. Let me also touch on the CapEx profile. Although we revisited CapEx alongside the re-guidance, this was not a matter of pushing back expenditures or postponing any deployment of funds. It is entirely about execution, ensuring those projects can be delivered. Several sizable projects sit in the pipeline, and a substantial deployment of funds is scheduled. Although at present it appears we are behind on our CapEx spend, a significant amount is likely to drop, or we expect it to drop, before year-end. That, however, is at risk, and it comes down to execution, making certain all those projects come in and get delivered. Although our CapEx profiles have been maintained, I wanted to stress that this is very much about execution and delivery, not a deliberate effort to delay any expenditures on our CapEx. Let's go to the next slide, please. I will pass things to Victor, who will walk through our Bilboes project.

Victor Gapare

executive
#4

Thanks, Ross. Could you advance to the following slide? To recap, Bilboes is our flagship development project, holding 1.75 million ounces of proved and probable reserves. Once at peak, it will yield 200,000 ounces of gold annually. With gold priced at $4,156 per ounce, the project carries an NPV of $1.5 billion and a post-tax IRR of 58%. May we go to the next slide, please? Work has begun at Bilboes, so I will walk through what has been accomplished to date and what comes next. We awarded the EPCM contract to DRA, and in March 2026 they began the front-end engineering designs, also called the FEED phase. That FEED phase is well advanced, and designs for the long lead items are already finished. The housing strategy covering contractors and employees has been finalized and is now being rolled out. The earthworks contract has been signed, and that contractor began work in October. Clearing and grubbing of the plant site is finished. Excavation of the plant terraces has started. Later in my presentation I will show you some photographs. The quantity surveying and site surveying services contract has been signed, and that contractor has begun work now that the earthworks contract is underway. The BIOX license with Metso has been signed. Mine planning is well advanced, with mining block models and mine designs now complete. Mine scheduling is in progress and should finish by the end of this month. The process plant area configuration and layout are also complete. Long lead item orders have been placed, covering the mills and the cyclones, while the flotation cells contract is close to signing and order placement is imminent. Again, this demonstrates that the project truly is moving forward. Next slide, please. You have skipped one ahead. Please go back one slide. Apologies, I believe a slide has gone missing somewhere, or perhaps it is simply being skipped. In any case, what comes next? Which items are we currently working on? The BIOX equipment supply contract is being finalized and should be in place by the end of this month. The crushers, screens, feeders, and samplers packages are under evaluation, with contract signing targeted before the end of the year. The construction power contract is to be in place by the end of this month. As you know, power must be brought from Shangani, and we will need to build a 132 kV overhead line. The Environmental and Social Impact Assessment study is underway and should be completed by the end of this month. Shortly after that ESIA study is completed, we expect to award the contract for constructing the overhead line itself. The mining contract scope of work for tendering should be completed by the end of January. That work is already well along, and when it wraps up, we anticipate awarding the contract by May 27, in May of next year. The water supply study has been finished, and the site has sufficient water. Our current focus is the water storage and reticulation strategy, and we've made some headway on it. Completion of that is also expected early next year. For structural mechanical piping and plate work, the plan is to finish by the end of December, meaning next month. This is in fact a sizable contract, so it ought to be finished by the end of December and awarded at some point next year. Last, the tailing storage facility, also called the TSF. Design work on this TSF should wrap up by the end of this month, and tendering for construction is anticipated to be done in February next year. Could you go to the following slide? Here we're simply displaying a few photos of the work that has been done. Looking at the first picture, beginning on the right, there is an aerial view of the earthworks contractor accommodation and workshop. Next, in the middle, the contractor's workshops, and the final picture at the top right. Below, we're showing work already begun, the clearing and grubbing, bulk earthworks in progress, and in fact the contractor's equipment already operating on site. Those are at least the visuals we're able to share with you today regarding the work being carried out; that concludes my presentation. Perhaps you can go to the following slide, Ross. You can discuss the financing.

Ross Jerrard

executive
#5

Thank you, Victor. It's really exciting to see all those activities. And importantly, an update on the funding strategy. As we laid out to you before, we've set out a four-pillar approach for our funding strategy, covering gold price hedging, convertible notes, the interim facility, and wider project finance. As we've discussed and announced, the third pillar of the strategy is now finalized. We completed our $150 million interim facility, and that's across a syndicate of eight Zimbabwean banks. So we're delighted with the outcome; we'd like to thank our co-lead arrangers at Stanbic Standard and CBZ Capital, and also the syndicate banks for their participation. The facility is made up of two parts. There's a term facility of $100 million, and then also a revolving credit facility of $50 million. Importantly, the interim facility was very much interim in nature. It was designed to make sure we had enough liquidity and basically to allow us time while we navigated the wider project financing for Bilboes. Equally, on that work stream, it has been well progressed. We're at an advanced stage of negotiations, due diligence, and lender engagement on that wider project facility, and we're looking to close that out early in the new year. This interim facility really supports our strategy to allow us time to navigate that process, but equally make sure that we've got enough funding in place to make sure that we can deploy the funds against Bilboes. Overall, a fantastic result, and I think we've moved forward very nicely on the overall funding strategy to match the activities that Victor had articulated. So if we turn to the next slide, we just provide the update on the normal slide, on our use of funds and source of funds. Again, if you look at the right-hand slide, you will see the makeup of circa $600 million of funding requirement across both capital costs, working capital, and some capitalized interest. Then the makeup of those source of funds at both our hedge price of $3,500 per ounce and also the $4,000 ounce mark. It really points to that middle bar of senior debt and other facilities of being somewhere in the order of $317 million to a lower amount of $277 million; in our discussions and our work streams with that pillar four, we are certainly very confident that we can get that delivered and make sure that that can all get rolled out early next year. With that update, I will hand across to Craig Harvey to talk to us about exploration.

Craig Harvey

executive
#6

Thanks, Ross. If we could proceed to the following section there. Thank you; on the upcoming slides, if you could advance to the next one. Over the quarter at Blanket, we've received some positive news. We announced an update to our mineral resource estimate for Blanket, covering both underground, and as you've heard, we now have a small at-surface mineral resource. For underground, measured and indicated mineral resources rose by 22%. Reaching just under 2.2 million ounces of gold, contained within 17.7 million tons of ore, at an average grade of just about 3.8 grams per ton. The total mineral resource grew only 3%, from 2.85 to 2.92, and there are some reasons for that. What this mineral resource really reflects is an improvement in our resource categorization, our confidence levels, and it's largely driven by on-reef development; on-reef development, typically close-spaced samples, levels 15 meters apart, it drives the measured resource category; then of course, we have the normal run-of-mine drilling that we do, and then we have the deeper long-hole drilling whose results we publish every six months to every nine months. What follows this is that we are now refining our life-of-mine plan. A number of engineering-type things are taking place because we'd like to take advantage of it. A revised life-of-mine plan, which then offers a conversion into a mineral reserve, will follow shortly. As we said, in addition to the underground, we now have a small but quite valuable surface mineral resource at the moment. There is approximately 22,000 ounces of indicated oxide and transitional material, with a further 8,000 ounces in sulfide. Of note, everyone must bear in mind that the drilling we did was intentionally for oxide resources only, so the deepest level of drilling we did was only effectively 40 meters deep. On the back of what we've seen, we did indicate that we would be looking and drilling from underground. I can say that we've intersected the mineralized structure at depth on 18 level at Blanket Mine. It's about 500 meters below surface. Assays are still pending. It's all independent laboratories, and that will be made public in due course. What do we do with it? Looking ahead, as we've heard, we've constructed a trial leach pad. All of the approvals are in place so that if the trial is successful, we can move ahead and execute on this; on the next slide, we'll see what the activities are. If we could just move to the next one, please. This is the kind of activities that are taking place at what we call the K-Pits heap leach pad or heap leach surface operation. There's approximately 10,000 tons loaded, which is the intention for our trial. We need to verify what our column testing has been indicating regarding the real recovery from a properly constructed pad, and to check the metrics for the different reagents and concentrations we tried during column testing. As you can see, there is the heap leach; we have every necessary pregnant pond, barren pond, overflow pond and emergency pond you could imagine, more than we need. At the bottom, you can see the location of the open pit. The haul road distance is roughly, it is a bit more than 1 km from the heap leach. It is fairly close. On the surface exploration opportunity, you can see for yourself, we are looking north in that view, but all those structures extend farther north. Whether they contain gold in economic quantities is what we need to examine. If we move to the next slide, we can discuss Motapa a little. Again, in the quarter, we were able to publish a maiden mineral resource for Motapa: 379,000 ounces of measured and indicated, 7.8 million tons at a grade of 1.51, plus an inferred mineral resource of 131,000 ounces, 2.7 million tons at just under 1.5. What matters about this is that 500,000 ounces is not small. I mean, it is actually quite good. Most of this mineral resource is reported from Motapa North. Even within the Motapa North area, there remain mineralized shears on which we do not yet have enough intersections to carry out mineral resource evaluation and make a grade estimation. This represents exploration in 2024 and 2025. What the 2026 exploration program has been focused on is infill drilling at Motapa North, obtaining more intersections in order, first, to bring in more resources. Second, to raise confidence in what we currently see here now. In 2027, we will actively move into Motapa Central and Motapa South. If we go to the next slide, one of the core takeaways here, and it has been mentioned, for everyone's benefit, is that one of the key potential synergies is Motapa in that lovely purple color, which is the Motapa mining lease, and then what currently makes up the Bilboes project that is on the table and being executed. We have heard that it is adjacent. I mean, we can see there that it is adjacent, so in due course, discussions will all take place, but 500,000 ounces adjacent to Bilboes, I think that can only bode well; with that, I will hand over to Mark for any closing comments.

Mark Learmonth

executive
#7

Alright, thank you. Could we advance to the following slide, please? All right, so as we go forward there are four distinct priorities. First, getting Blanket back to a reasonable level of consistent output, and the main pieces for that are already in place — namely more compressed air capacity as well as greater elution capacity. Second, carrying on with the fundraising for Bilboes, aiming to produce first gold by the close of 2028, with 2029 as the first full year of output. We'll keep up exploration work at Motapa so as to build on that maiden resource, and at the right time assess how Motapa might potentially be folded into a larger project at Bilboes. The last item is to keep exploring and carry out further work at Blanket to extend that mine's life, potentially lift output above the current level, and unlock the oxides we have there. So, I'd say the outlook appears especially promising. That brings the presentation to a close. We can now take questions.

Executive

executive
#8

Hello everyone. I’d like to ask briefly about the CapEx at Bilboes, which has dropped — the estimate that went from $132 million, then to $43 million this year, and is now around $38 million, which is what remains; all of that will be spent during this quarter. Do you have any view on what the underlying escalation in CapEx might be? I see that you’re pointing to the earlier study, the feasibility study, but do you have a sense that certain costs could be increasing faster than expected, or roughly in line with your expectations?

Mark Learmonth

executive
#9

Which of them is going to handle that, Ross or Victor? I should note that right now we're midway through, nearing the finish of, the real procurement process, and that gives us visibility. Ross, Victor, would either of you like to address that?

Ross Jerrard

executive
#10

Glad to jump in on that, though Victor, my sense is you've taken that course too.

Victor Gapare

executive
#11

Yes, of course. As I mentioned during the presentation, we're currently in the process of procuring the various packages. What remains, really, are the packages that have gone out to tender, for which we don't yet have the final numbers. We should know the final figure toward the end of January next year. Once we get the figure for the TSF, mining will follow later. That's the point at which we'll be able to give you a clear indication.

Mark Learmonth

executive
#12

Are we seeing anything that is particularly alarming at this stage?

Victor Gapare

executive
#13

Nothing alarming at this stage.

Mark Learmonth

executive
#14

There you go; it is the best we can give you, Nick.

Executive

executive
#15

All right, thanks. There's a question about June of next year. Sorry, am I coming through? Okay. Regarding June next year, your expectation is that the metallurgical plant will be operating at full capacity, and the Lima plant will also be running at full capacity. As part of the strategy you initially put together for that, a sizable stockpile was to be built ahead of all those plant expansions. Does that plan still hold, and what do you figure the stockpiles will amount to by the end of June?

Mark Learmonth

executive
#16

Okay, so a stockpile is needed so we can carry out work on the central shaft. The winder at the central shaft is being switched from AC to DC operation, which will give us better controls for safety purposes and also bring down operating costs. About 15 days of suspended operation at the central shaft will be required for that, so the stockpile has to carry us through that period. Somewhere around 30,000 to 35,000 tons would be needed for that stockpile, since we will obviously keep hoisting some material at number four shaft. After that, the stockpile's only purpose is to serve as a buffer for future production. Really, the sole reason we need the stockpile is to give us that leeway while the AC/DC conversion takes place.

Executive

executive
#17

All right, thank you. My final question for you, Mark, is this: you've placed considerably more personnel underground, and I realize you haven't been able to realize the complete advantage from that, given the access constraints you mentioned and the equipment shortages you brought up. Have those people delivered any meaningful benefit so far, and if so, in what respect?

Mark Learmonth

executive
#18

Right, since we do have a stockpile. As you may recall, we had drawn that stockpile down to essentially zero midway through the year, before we started the new seven-day working week. Right now, our stockpile sits at roughly 18,000 tons. Yes, we are getting a benefit when it comes to run-of-mine production, and we are also seeing a benefit that will show up during the second half of the fourth quarter through more mining activity and, as a result, a higher overall grade, since we are carrying out more mining in the deeper, higher-grade areas. Yes, that benefit is coming through.

Executive

executive
#19

Okay, thank you.

Mark Learmonth

executive
#20

Oh, no, I'd like to express gratitude for your involvement. Challenging—depends on who it comes from. No, continue. No, we have room for one more question. This is— Oh. Okay, fine. The third quarter has been a difficult one, and we've positioned ourselves toward a rather ambitious target for the fourth quarter, which I'm confident we will achieve. As I mentioned, the outlook, at Blanket as well as in other parts of the group, for a robust 2028 looks very appealing. Apologies—a robust 2027 looks very appealing. Thank you for your involvement.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Caledonia Mining Corporation Plc transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to Caledonia Mining Corporation Plc earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Caledonia Mining Corporation Plc or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.