operatorLadies and gentlemen, good day, and welcome to Q3 FY '26 Cemindia Projects Limited Earnings Conference Call Hosted by ICICI Securities Limited. [Operator Instructions] Please note that this conference is being recorded. I now hand the conference over to Ms. Nidhi from ICICI Securities Limited. Thank you, and over to you, ma'am.
Nidhi Shah
analystThank you, Muskaan. Good evening to all. On the behalf of ICICI Securities, I welcome you all to the Q3 FY '26 Earnings Call of Cemindia Projects Limited. Today, we have with us from the management, Mr. Jayanta Basu, Managing Director; Mr. Nitesh Sharma, the CFO; Mr. Ritesh (sic) [ Rahul ] Agarwal, Head of Investor Relations. We'll begin with the opening remarks from the management, followed by a quick Q&A. Thank you, and over to you, sir.
Nitesh Sharma
executiveYes. Good evening, everyone, and thank you for joining us on the Q3 FY '26 results con call. This is Nitesh Sharma. So before we begin, I would like to mention that our discussion today may include certain forward-looking statements relating to Cemindia Projects Limited. These statements are based on management's current expectations and assumptions and are subject to various risks and uncertainties. Actual results may differ materially from those expressed or implied in such statements. So let me first start with the financial performance for the quarter and subsequently, our MD, Mr. Jayanta Basu, will be taking you through the operational performance of the company. So we are pleased to share that Q3 FY '25-'26 marked another quarter of good performance for the company. The key highlights for Q3 FY '26 are that the total operating income stood at INR 2,315 crores in Q3 FY '26 against INR 2,270 crores of the previous corresponding year quarter. EBITDA stood at INR 245 crores in Q3 against INR 217 crores of previous year, which recorded a growth of 13% on a year-on-year basis. The EBITDA margin was at 10.6%. We recorded a PAT of INR 111 crores in Q3 FY '26 against INR 87 crores of the corresponding quarter of the previous year, again, 27% growth on a year-on-year basis. Now the financial performance for 9 months stood at ending 31st December was operating income at INR 7,087 crores in 9 months against INR 6,714 crores in the previous year, a growth of 6% year-on-year. EBITDA for 9 months stood at INR 749 crores against INR 668 crores in the previous year 9 months period, a growth of 12%. EBITDA margin at 10.6%. PAT of INR 356 crores in 9 months against INR 259 crores of the previous year, a growth of 37% year-on-year basis. The company stood at a very conservatively financed with a net debt to equity of 0.26x [indiscernible]. Now during this 9 months period ending 31st December, the company has secured order worth INR 9,725 crores. Post December '25 till date, we have also secured orders worth INR 2,000-odd crores, so that makes the total order book in the current year at INR 11,700 crores. The overall pending order book in hand today stands at INR 21,800-odd crores. So this was from my side. Now I would request our MD, Mr. Jayanta Basu, to take the word on the operational performance. Thank you.
Jayanta Basu
executiveHi, good evening. Welcome to this con call Q3 '25-'26 of Cemindia Projects Limited. I think Nitesh has covered all the parameters related to the last quarter results. As you can see that revenue has increased moderately, around [ 5.6% ] compared to last 9-month quarter 2024. There is a reason behind that, which I'll explain. But I'm very happy to share that our profitability has increased a lot. Our PAT is now around 5%, which was 3.9% last year in the same period. INR 259 crores becomes INR 356 crores. EBITDA is close to 11%. And you might have seen that for several years, our EBITDA used to be around 9% to 9.5%. But last few quarters, we have been able to maintain more than 10%. So these are the good signs. Regarding revenue, I think 2 factors have impacted. Otherwise, it would have been a little more. We secured a job at Project Vadhvan, the port job. That was secured a year back. Not a year back, say, beginning of this year -- last year. And we would have expected some revenue from this project. But because of some issues related to local problem and all, you must be knowing that through reading newspapers. We were able to make any -- hardly any progress. So that has really impacted our revenue. Similarly, the order flows, orders we have secured around INR 9,000 crores orders by this time. But this order flow will impact coming quarters. In the last year, if you see, our order up to Q2 was only INR 2,000 crores and [ quarter 4, INR 834 crores ]. So whatever order we have secured last year, that is being matured now for revenue, which is comparatively less, as it should be. So this issue, there's some deferred revenue because of delayed order, and Vadhvan Port not getting, I mean, initiated has really impacted our revenue. Otherwise, we would have been very happy to report around 18% to 20% revenue more than last quarter -- last year. So having said that, profitability is better. And I have to share there are some significant or good things which have happened last year. We have completed the Mumbai Metro tunnel. We have handed over a beautiful building to Government of West Bengal. That is the new High Court building at West Bengal. We have completed Vizhinjam Port. We have completed Udangudi Port. We have completed Kolkata Metro. You know how difficult it was a few years back. So some big challenging jobs we have completed last year, which is a good achievement. All are very challenging jobs. And now our main focus is to handle a few challenging jobs -- a few more challenging jobs like Project Varsha, like Pune Metro, we have received an order a few months back, at Dahej, Petronet, and Ruwais in Abu Dhabi. We [indiscernible] (7:16) jobs are all going well. And I think that quarter 4 results will be better than quarter 3. And there are opportunity-wise, it is something like that you may get one order which may impact you a lot because the big-ticket jobs are waiting. And each job will be INR 5,000 crores to INR 10,000 crores. There are a few jobs in that range. If we are lucky, if we get 1 or 2 jobs in that big-ticket jobs, the whole scenario will change. And we hope that -- we are working very hard, and we hope that some of them will be secured by us. So good orders secured so far, opportunities are ahead to secure some more order, big-ticket jobs, profitability is better, finance is good. So that is what, from my side. If you have any questions going forward, please ask. I think that's all from my side.
Operator
operatorSo we can open the floor for the question and answer?
Jayanta Basu
executiveYes, yes.
Operator
operatorThe first question is from the line of Dhananjay Mishra from Sunidhi Securities.
Dhananjay Mishra
analystAm I audible?
Jayanta Basu
executiveYes, yes.
Dhananjay Mishra
analystSo just wanted to know, as you said that a lot of projects got completed in this current quarter, and we have seen very strong margin expansion. So I guess this is kind of one-off because we got a lot of orders completed. Or is it going to be kind of double-digit margin sustainable for the upcoming quarter as well?
Jayanta Basu
executiveYes. I think that is the [ endeavor ]. We definitely have double-digit margin, which is expected next quarter or going forward, yes. And that is consistent we are doing. If you see last quarter also, it was double-digit margin. I'm talking about EBITDA. This quarter also a little bit more than last quarter. So [indiscernible].
Dhananjay Mishra
analystOne quarter improvement is one thing and -- on higher side. And despite [indiscernible] all these new Labor Codes provision of INR 16 crores, and so that is the one. And can you give some road map about order inflows pipeline for next 3 to 6 months, whether these orders will come from group or outside private and government and which sectors we are expecting order for 6 to 9 basis at least.
Jayanta Basu
executiveOkay. So far, we have INR 9,000-odd crores jobs till now. And there are jobs which are -- we have submitted our bid, and we are waiting for the results like Vadhvan Port [indiscernible], the Metro jobs at Delhi, and one port job in Odisha. So there are plenty of jobs in the group, including data center. So I think tenders [ submitted ] but yet to open there are [ INR 500 crores ] and another further INR 30,000 crores to INR 40,000 crores [Indecipherable]. So that is the kind of future job [indiscernible]. For coming quarter, this quarter [indiscernible] secure a few jobs for the group, which are all under discussion. So road map-wise, if you see that, we still maintain that another INR 2,000 crores, INR 3,000 crores jobs [ can be secured ] this year, which is February and March. And Q4 or Q1, Q2 next year, there are some big-ticket jobs. It depends upon when government opens the tender or what is the timing. So if it happens, then there are very -- quite big-ticket jobs, which will change the whole scenario.
Dhananjay Mishra
analystLastly, on guidance front, because of this Q3 soft revenue, as you said, the deferment happened in Vadhvan Port order. So what is the status over there? And are we still maintaining INR 11,000 crores mark or maybe INR 10,000 crores, INR 11,000 crores mark? For that, we have to achieve INR 4,600 crores kind of turnover in Q4. So what is your view?
Jayanta Basu
executiveSee, it is not very sure how Vadhvan will take place, because it's totally not in our control. And -- but at the same time, the Pune Metro should start producing something and that project [indiscernible] start producing something. So I think that it will be at least 15% to 20% more than this quarter, roughly.
Dhananjay Mishra
analystThe current quarter?
Jayanta Basu
executiveThe current quarter, yes.
Dhananjay Mishra
analyst20% more.
Jayanta Basu
executiveYes, yes. Estimate, yes.
Operator
operatorThe next question is from the line of Niraj Mansingka from White Pine Investment Management.
Niraj Mansingka
analystI just wanted to understand about the data center. Adani has a plan of data center on its own, as well as a joint venture with global scaler -- hyperscalers. One, I want to understand how much are you ready to -- in capability to take those orders? And number two, what is your visibility on the orders of those coming in and the execution of those?
Jayanta Basu
executiveYes. This data center is under discussion for the last at least 7, 8 months since Adani has started, I mean, taking over this company. And we have ramped up our capabilities during the last few months. We have recruited several engineers, those who are experienced in data centers. We have visited a lot of sites all over the world to see how this happens, what is the method, what is the [ dos and don'ts ] in this business. And we have already started 2 data center building in Mumbai and foundation work is already completed. Precasting work also are done. So we are in readiness to take up this activity. Visibility that Adani has got a big plan. And even if we do half of that, that will be quite big for our company.
Niraj Mansingka
analystAnd any potential -- if any thought process on how much is your -- opportunity size for you on the data maybe on a per megawatt basis? It will help me understand how much you are present in the data center.
Jayanta Basu
executivePer megawatt, you're asking about the cost?
Niraj Mansingka
analystNo. I'm asking how much you would be capable of doing the projects, like...
Jayanta Basu
executiveSee, a data center of 120 megawatts, 130 megawatts, typically, it's a 2-year cycle from beginning to the commissioning, 2 years to 27 months. So we have already secured 3 data centers of similar capacity. We may have another 2 or 3. Each year, we can do around 500 megawatts roughly with the present capacity.
Niraj Mansingka
analystThis year means FY March ending '26?
Jayanta Basu
executiveYes. It depends upon the secured -- if you secure the job. Now what happens when you secure the job, there are 2 parts. First part is the civil, second part is the balance. So civil part is hardly 20%. So you may not see that ramp-up in revenue in the first year. But second year, definitely with the electromechanical part, balance 70% or 80% revenue will come. So you have to factor all these numbers when you calculate the revenue from data centers.
Niraj Mansingka
analystAnd, sir, how much -- if you take example of, say, 120 megawatt, how much would that -- if you get an order of 120 megawatt, how much revenue could you book -- order can you book on that side, as a potential range?
Jayanta Basu
executiveSee, you are asking a direct question, what will be the price of 120 megawatts. It's very difficult to answer because it depends upon the conditions, depending upon where is bidding, what are the terms and conditions of the project, [ something like sublet fee ]. But what I can say is that 120-megawatt time line may take 2 to 27 months' time, and first year, 20% revenue, next year, 80% revenue. These are the guidelines we can give.
Operator
operatorThe next question is from the line of Vaibhav Shah from JM Financial.
Vaibhav Shah
analystCan you provide some clarity on the Bangladesh order status right now?
Jayanta Basu
executiveBangladesh work is going on absolutely okay. I mean, there are natural reasons why everybody should get scared. I know that. But local government is really supportive to us. Not only us, to any foreign companies those who are working there. And our people are quite okay. We are delivering the job as per our schedule. We're getting paid on time. And we are almost completing the piling job by end of May. So then our majority of the work will be completed.
Vaibhav Shah
analystWhat is the outstanding book as of December in the Bangladesh order?
Jayanta Basu
executiveOutstanding, I have to check up. Give us some time.
Vaibhav Shah
analystSir, secondly, when do we target to complete the Bangladesh order? In FY '27?
Jayanta Basu
executiveBangladesh order will be completed -- see, physical work will be completed by -- before next monsoon, that is May or June next year.
Vaibhav Shah
analystSir, if I got the number correctly, so our year-to-date order inflows, including the INR 2,000 crores, which we won in January, it should be around INR 11,700 crores?
Jayanta Basu
executiveYes, you are absolutely right.
Vaibhav Shah
analystSir, how do you see the margins going ahead? So it should be double digit, right, between 10% to 11%?
Jayanta Basu
executiveI think you don't expect too much of a hike, but the same margin pattern will be there, 10% to 11%.
Vaibhav Shah
analystSir, lastly, one bookkeeping question. What would be our gross debt as of December?
Jayanta Basu
executiveIt's close to INR 920 crores. Gross debt.
Operator
operatorThe next question is from the line of Vinay Chaudhary from Invexa Capital.
Unknown Analyst
analystSo...
Operator
operatorI am sorry to interrupt, sir. Your voice is not audible.
Unknown Analyst
analystAm I audible?
Operator
operatorYes, sir.
Unknown Analyst
analystYes. So in the last quarter, we had basically the inflow of about INR 7,100 crores. And we had a couple of L1s, like Pune Metro and sewage plant of about INR 3,000-odd crores. So what is the status of those L1s? Because that also totaled up to about INR 11,000 crores plus. And currently also we are about INR 11,000 crores, including the 2 projects what you mentioned. So just wanted to have some clarity and fill the gaps in that.
Jayanta Basu
executiveI will not be able to [ connect ] last year -- last quarter, but I can tell you the present status. So far, I think we have got around total INR 11,700 crores. And that includes Pune Metro of INR 1,500 crores as well. And there are no such job where we are L1, except a small job in Seabird, [ INR 600 crores ]. But there are plenty of jobs we have submitted our bids. So it depends upon how it comes out. I think we have submitted a bid of around INR 25,000 crores total. Out of that, one job we have already secured or L1, that is that group company called Adani Mor Sagar project at Rajasthan, which is around [ INR 6,700 crores ] job. So that will be added to the [ CT ] very soon.
Unknown Analyst
analystSo about INR 15,000-odd crores what we were expecting. So is there any upward revision what we are expecting in this year?
Jayanta Basu
executiveSo I still maintain around INR 14,000 crores, INR 15,000 crores, because what has happened, a few of the government tenders, which we were expecting to have already completed, is still getting delayed. And as well, some group jobs are also getting a little delayed. It's a matter of time. Otherwise, we would have achieved INR 15,000 crores this year.
Unknown Analyst
analystSir, will this -- the delay, will that come up in the next year? Or it's kind of a lost bid for us?
Jayanta Basu
executiveNo, it is not lost. It will come next year. It's a matter of time lag. That's all. I mean, if you get, you'll get now, you can get later on also. So that is the issue whichever you get or do not get. But if you get now, if you get later on, that is not going to affect much in our progress -- financial progress.
Operator
operatorThe next question is from the line of Aditya Sahu from HDFC Securities.
Aditya Sahu
analystI hope I am audible.
Operator
operatorYes, sir.
Aditya Sahu
analystI do have a few questions. I think this may be a bit repetitive. I got disconnect in between. So what would be the revenue guidance for FY '26, the revenue, EBITDA margin, and the order inflow guidance?
Jayanta Basu
executiveWell, I think for -- to answer your question, this is a big issue because we spend month after month to evaluate how much is the revenue and all. So it is not appropriate for me to give you a correct number. But as I have maintained, it will be around 15% to 20% rise in the revenue and EBITDA...
Aditya Sahu
analystAnd on the EBITDA margin, 10%, 11% is what I could gather.
Jayanta Basu
executiveYes, yes.
Aditya Sahu
analystOn the order inflow front, you have mentioned INR 15,000 crores. I hope that would be the correct number.
Jayanta Basu
executiveYes. I think -- see, there are a few jobs which are quite big. And if we are lucky to close one of them, the number can be anything. I mean, it can be INR 10,000 crores-INR 12,000 crores to INR 20,000 crores-INR 25,000 crores as well.
Aditya Sahu
analystOf this, how much are we expecting from group entities and what percentage are you expecting from group entities?
Jayanta Basu
executiveYes, I think we'll maintain a number of 20% to 25% from group in that range.
Aditya Sahu
analystOkay. 20%, 25% from group entities. And what would be the current bid pipeline that we have? And how much of that is also from the group entities, if you can throw some light on that?
Jayanta Basu
executiveCurrent work pipeline, a few data center jobs from the group, which they are developing in many places. And some job, as I mentioned just now, Mor Sagar one irrigation job in Rajasthan and maybe some road jobs if they got -- if they get.
Aditya Sahu
analystOn the value terms, if you can provide the bid pipeline.
Jayanta Basu
executiveValue terms, whatever I have said. Going forward, I don't know. But immediately, maybe around INR 10,000 crores to INR 12,000 crores job may come to us.
Aditya Sahu
analystIn terms of the CapEx, so I understand that we did a CapEx of about -- I think last time the guidance was INR 300 crores for FY '26. Is that the same CapEx guidance that we have right now? And how much have we deployed till now?
Jayanta Basu
executiveSee, it depends upon, again, how -- which job we go on. Because last year, we have secured many building jobs, and we have to invest a lot for more material. Though it is not as costly as plant and tooling equipment, but still it is costly because nowadays, everybody go for [ system forward ]. So there's a lot. And a few general plants we have procured. So this year also will be around what we spent last year, INR 300 crores, this will be 10%, 15% more than last year.
Aditya Sahu
analyst10% to 15% more.
Jayanta Basu
executiveIn 9 months, we have spent around INR 200-odd crores towards the CapEx.
Aditya Sahu
analystAnd in the current order book that we have of INR 21,000 crores, how much of that is from the group entities [ at this time ]?
Jayanta Basu
executive27%.
Aditya Sahu
analyst27%. On the Vadhvan Port that you had mentioned, that 30 days [indiscernible]. Any visibility as to when do you see that happening? And also, how much -- what would be the contribution of that particular order in the overall order book?
Jayanta Basu
executiveIt is INR 1,600 crores, out of INR 21,000 crores work in hand.
Nitesh Sharma
executiveLess than 10%.
Jayanta Basu
executiveAnd we have got visibility. We cannot speculate what may happen. This is not in our control.
Operator
operatorThe next question is from the line of Jayesh Shah from OHM Portfolio.
Jayesh Shah
analystMy question again relates to the Vadhvan Port delays that you talked about in this quarter where apparently we have seen a revenue loss, but your margins are actually better. So how should we think about it? Because if your revenue loss is due to work not being done, then that means that you have not been able to deploy your people or equipment and you have -- resulted back into revenue loss. Then is there also corresponding expenses that should have come in? Or does it mean that the rest of the business was at much higher margins? That's my first question.
Jayanta Basu
executiveWell, revenue loss, because work hasn't happened, so there is a direct -- you can see that. I think I'm sure another INR 200 crores, INR 300 crores revenue would have been more had this Vadhvan Port been in operation. Regarding margins betterment, we have done good. We have efficiently handled the project. Yes, sir. That is how this margin is better.
Jayesh Shah
analystNo, so do we understand that INR 200 crores to INR 300 crores revenue loss is the unbilled item, in which case the expenses are also booked. So perhaps your margins are better than what you have reported?
Jayanta Basu
executiveWell, actually, definitely, we have not spent INR 200 crores of expenses in Vadhvan Port. We are very cautious. We have very small and scanty set up at site because expenses are mostly due to the material what we've sourced and what we've done, and which converts to revenue.
Jayesh Shah
analystBut you were able to redeploy your people to other projects?
Jayanta Basu
executiveSo in Vadhvan Port, hardly 2 or 3 engineers are there. That's all.
Jayesh Shah
analystI see. But even the redeployment of people did not yield to higher revenue from -- on an overall basis, is it?
Jayanta Basu
executiveI couldn't get you, sir. What is your point?
Jayesh Shah
analystI said that if you could not proceed with the Vadhvan Port order and there was some loss of materials and whatever, but you were able to redeploy your team, that team should have helped you to recover that revenue from other projects. Or were they idle for the quarter?
Jayanta Basu
executiveYes. I mean, you see, in a large company like ours, 5, 6 engineers here and there doesn't make much difference. So even if we have a team Vadhvan working somewhere else, doesn't mean that they are generating extra revenue because the project is [ fixed ].
Jayesh Shah
analystAnd next quarter, you are able to figure out as to where to redeploy and recover the turnover lost, is it? In this quarter, basically.
Jayanta Basu
executiveWe want to redeploy tomorrow, provided the situation simmers down.
Jayesh Shah
analystNo, no. I'm saying that your Vadhvan is delayed, but you are able to redeploy your team elsewhere, and that is where you are expecting your revenue to be 15% higher over the quarter.
Jayanta Basu
executiveNot because of Vadhvan resources deployed somewhere will give us better. It is because of time cycle. When a project starts, the initial 5, 6 months, you do at less progress and then the progress increases, per month turnover is more. So all these factors, if you put together, then you'll find that the revenue is a little bit more than this quarter.
Jayesh Shah
analystAnd my last question is, when do we see a meaningful scale up in your quarterly revenue run rate? I'm not asking for specific guidance, but given that your order book is very large, perhaps you are capable of growing at least, say, 20%, 30% from your current base now. Of course, this is dependent on how your projects scale up and the milestone. Is that something that is going to happen in the next few quarters? Or will it still take time?
Jayanta Basu
executiveWell, it depends upon the orders, the nature of order, how fast they are converted to revenue. But if you ask me, as a company, we have got the capacity to ramp up the progress by 30% with our existing resources.
Jayesh Shah
analystRight. But based on your current orders and the milestone and the promise for execution, do you see a significant ramp up in the coming quarters?
Jayanta Basu
executiveI mean, quarter 4 -- sorry, quarter 4 is okay. Quarter 1, quarter 2, yes, that will be better than quarter 3, quarter 4, definitely better. Because few jobs like Pune Metro will be in full swing, like Abu Dhabi Port will be in full swing, like some more jobs which we have secured recently, data centers will give more revenue. So this INR 11,000 crores order what we have secured, they are now in threshold stage, initial stage. So they will be giving the revenue from next year, quarter 1, quarter 2.
Operator
operatorThe next question is from the line of Vaibhav Shah from JM Financial.
Vaibhav Shah
analystSir, what would be our revenue growth guidance for FY '26 given the weaker Q3?
Jayanta Basu
executive18%.
Vaibhav Shah
analystSir, but to achieve that 18%, the asking rate would be much higher in the fourth quarter. So we are confident of around INR 3,700 crores, INR 3,800-odd crores revenue in Q4?
Jayanta Basu
executiveNo, I'm not talking about Q4. I'm talking about next year.
Vaibhav Shah
analystOkay. For FY '27?.
Jayanta Basu
executiveEntire FY '27.
Vaibhav Shah
analystOkay. And for '26?
Jayanta Basu
executive[indiscernible] It is not correct. It will be around 16% to 20% growth in next year in terms of revenue. That's what I'll say.
Vaibhav Shah
analystAnd for FY '26?
Jayanta Basu
executiveFY '26, we are left with one quarter now. And maybe we have achieved INR 2,300 crores. Maybe another -- it will be another 15%, 20% more -- 15% more say per quarter.
Vaibhav Shah
analystCompared to Q3 and Q4.
Jayanta Basu
executiveCompared to Q3 for Q4, yes.
Vaibhav Shah
analystAnd sir, what would be our outstanding receivables from Bangladesh? It was around INR 120 crores last quarter.
Jayanta Basu
executiveYes. INR 170 crores in this quarter as on December.
Operator
operatorThe next question is from the line of Aditya Sahu from HDFC Securities.
Aditya Sahu
analystJust one bookkeeping question over here. I did notice that the numbers -- so for example, historical numbers for, say, Q2 of the FY '25, for that matter, were marginally different. If you can elaborate a little bit because I see that the numbers that are there for Q2 in the Q2 disclosures versus the numbers that are there for Q2 in the current disclosures of today, those are marginally different. Can you elaborate on that one?
Jayanta Basu
executiveI really couldn't pick up your question. If you can repeat once again.
Aditya Sahu
analystSir, I was mentioning that the historical numbers, say, for example, for Q2 is marginally different from the disclosure that we -- as compared to today's disclosure versus the Q2 disclosure that we had. Similarly, I saw this one for the FY '25 [ origin ] numbers. If you can throw some light on that.
Nitesh Sharma
executiveYes, yes. So there's an accounting representation change, which has -- like, the jointly controlled operations, which we were doing in various JVs. So the grossing up of net line items have been done. And accordingly, for this entire year, the numbers have been reinstated in the line item wise. However, the profit number and the P&L will not change. The profit and loss remains the same. And that's an accounting treatment which has happened, which has led to a change in numbers which were disclosed earlier.
Aditya Sahu
analystUnderstood, sir. The reason because I saw this on the audited numbers also. So that is the reason, yes.
Nitesh Sharma
executiveSo it's more of like we have benchmarked it with the best of the industry practices, and we took a view and then this is a judicial decision which was taken to...
Aditya Sahu
analystSo this was a onetime exercise, is what you're saying, in terms of the grossing of net line items, as you mentioned.
Nitesh Sharma
executiveRight, absolutely.
Operator
operatorAs that was the last question for the day, I would now hand the conference over to the management for closing comments. Over to you, sir.
Nitesh Sharma
executiveSo thank you so much. Thank you so much for joining and attending this call, and we wish you all a very happy and good day, and we wish that whatever we expect, the things go well and the next period performance would be in line with the expectations which we have told to the investors. Thank you so much. Thank you so much for joining us.
Operator
operatorThank you. On behalf of ICICI Securities Limited, that concludes this conference. Thank you for joining us, and you may now disconnect. Thank you.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Cemindia Projects Limited transcript — plus 251,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Cemindia Projects Limited earnings transcripts and 251,000+ others is available through the
EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.