Century Aluminum Company (CENX) Earnings Call Transcript & Summary

August 6, 2026

NASDAQ US Materials Metals and Mining earnings 39 min

Earnings Call Speaker Segments

Chad Rigg

executive
#1

Thanks, operator. Hello everybody, and good afternoon — glad you could join us for the second quarter conference call. With me on the line are Century's President and Chief Executive Officer, Jesse Gary, along with Executive Vice President and Chief Financial Officer Peter Trpkovski. Once we've finished our prepared remarks, we'll open things up for your questions. Just a reminder that you can find today's presentation on our website, www.centuryaluminum.com. Our website serves as one channel we use to disclose material information about the company and to satisfy Regulation FD. Now let's move to Slide 2. I'd ask you to spend a moment reviewing the cautionary statements regarding forward-looking statements and non-GAAP financial measures that apply to what we discuss today. With that, I'll turn the call over to Jesse.

Jesse Gary

executive
#2

Thank you, Chad, and I appreciate all of you taking the time to be here. To kick things off today, I'll go over how our operations performed in the second quarter, which includes finishing up the Mt. Holly expansion as well as bringing Potline 2 back online at Grundartangi, and after that I'll discuss the robust market backdrop we continue to see right now. Following that, Pete will take you through the numbers for Q2 and what we expect for Q3, and then I'll wrap up the call by sharing the newest updates on the Oklahoma smelter we're building and on the significant new executive order from President Trump that gives an incentive to businesses such as Century that are adding new aluminum capacity here in America. But before diving into the quarter, I want to express my gratitude to the Century team at every one of our locations for delivering yet another quarter of excellent safety results. Across the past six months, our people have carried out two significant capital projects spanning two continents, and at the same time they've brought hundreds of new hires into our facilities, and all of it was done safely; that doesn't happen by chance. It comes from careful planning, strong discipline and a workforce whose members watch out for each other. My thanks go out to every one of you. Let's move to Page 4. During our May conversation, I said that by the time July ended, every Century asset ought to be running at full capacity for the first time in more than 10 years. I'm extremely proud to announce today that our team came through on that promise. At Mt. Holly, we finished bringing the last 90 pots back online in late June, hitting both our schedule and our budget, which restored the plant to its full capacity. This undertaking lifts total U.S. primary aluminum output by almost 10% and has brought more than 150 full-time American manufacturing positions to the facility. Last week we were honored to welcome U.S. Commerce Secretary Howard Lutnick along with South Carolina Attorney General Alan Wilson to the plant to mark this significant milestone. At Grundartangi, we wrapped up the restart of Line 2 at the close of July, which is about six months earlier than the schedule we initially provided to you back in October. It's worth pausing to reflect on this for a moment. Ten months ago, we had just suffered the loss of a potline in Iceland after an unprecedented transformer failure, and Mt. Holly was operating at just 75% of its capacity. Now, both facilities are running at full capacity in a market that requires every single unit we're able to make. Achieving that turnaround came from our operations and technical personnel collaborating across different time zones simultaneously on two of the most complicated projects this company has ever taken on. Congratulations to each of you. This is a truly remarkable accomplishment, and you have every reason to feel proud. Still on Page 4 regarding operations; we delivered solid results throughout the portfolio during the second quarter even as we were carrying out this much major project work. At Mt. Holly, the ramp-up stayed on track all through the quarter, and the plant hit full production as June came to an end. Just to remind everyone, since the restart happened in stages, Q2 only captures a partial quarter of the higher run rate. The complete advantage from these additional tonnes is going to show up for the first time during Q3. Keep in mind, we have experienced a bit of plant instability after bringing it back up. That kind of thing is pretty typical when you restart something of this scale. Our team is actively addressing it, and that effect has been factored into the outlook. Also note, we don't anticipate anything carrying past Q3, and the project is still completely on schedule to return its capital cost by the close of 2026. Over at Grundartangi, Line 2 came back up without issues, and that facility is now operating near its full capacity. As we mentioned during the previous quarter, Line 2 is being run at a somewhat lower amperage while we wait for the new replacement transformers to show up and get installed during the fourth quarter; we're intentionally taking a cautious approach so we don't place excessive strain on the repaired units, and the team has handled that trade-off nicely. Turning to Jamalco, we started up our new power generation turbine, referred to as TG4, at the start of August; that's a meaningful achievement. TG4 lets us operate Jamalco entirely on power we generate ourselves, which removes the costly and — as we found out last winter — occasionally unreliable purchases from the Jamaican grid. The complete advantage will come in gradually across the rest of the year and represents a major shift in the Jamalco cost structure. Excellent job by the Jamalco team for getting that done. As we mentioned during the previous quarter, the refinery is still encountering lower quality bauxite from some of its mining areas. The team now has a revised mining plan and is executing against it, but we figure it will take an additional 2 quarters before it's fully in place; for now, it stays a modest headwind affecting Jamalco's cost and volumes, and Pete has accounted for that in our outlook. Last but not least, Sebree turned in yet another outstanding quarter; that plant has now delivered quarter after quarter of top-tier operating and financial results, and it keeps raising the bar for the rest of the portfolio. Fantastic work once more from everyone at Sebree. Before passing it over to Pete, let's take a few minutes to talk about the market, beginning on Page 5. The brief summary is that we're delivering these extra tonnes from Mt. Holly and Grundartangi into as robust a market as this industry has experienced in a very long time. After the partial reopening of the Strait of Hormuz, prices have come back to where they were before the conflict. LME is roughly $3,250 per tonne as of today. The U.S. Midwest premium stands at roughly $1.11 per pound, while the European duty paid premium is around $500 per tonne. The market is still assessing the situation in the Gulf. Restarts have only been announced at EGA, which is a positive development for our friends over there. However, we haven't yet seen any restart announcements in Bahrain or Qatar, and I'd be cautious about presuming that production levels across the Gulf will recover quickly. Bringing idled potlines back online is a gradual, challenging process. Few companies understand that as well as we do, since we have just completed the task on two occasions. On top of that, these facilities are managing it while their supply chains for raw materials remain only partially normalized. How long this will take is something we lack clear insight into, and none of us can confidently state what additional interruptions to shipping through the Strait would mean for those schedules. Turning to demand, conditions in the U.S. are the most robust they have been in years. The ISM manufacturing report released Monday for July significantly exceeded forecasts — marking a seventh straight month of growth and the highest figure since May 2022. Our customers are working within a powerful environment, and we observe that firsthand in our conversations with them. Demand for aluminum is powered by the build-out of power and data infrastructure, by commercial aerospace, and by defense and rearmament efforts, along with ongoing reshoring of extrusion and downstream fabrication that followed President Trump's April move to close valuation loopholes within the Section 232 program. Putting supply and demand together, our expectation remains a worldwide shortfall of roughly 1 million tonnes for this year, and we anticipate that deficit conditions will persist into 2027. Since smelters in the Middle East will produce less metal during 2026 than they would have otherwise, a substantial share of that gap is already unavoidable regardless of how the restarts proceed from this point. Lost tons cannot be recovered in a market that was already tight. Inventories make this clear. The number of days of consumption stored worldwide has now dropped beneath the post-financial crisis troughs we have mentioned on earlier calls and is nearing record lows; as deficits endure for the remainder of this year and into the next, we anticipate that reduction will keep going. Almost no buffer remains anywhere across the system; when a market has zero slack, secure domestic units become more valuable. With both restarts finished, Century now holds a greater number of such units to offer in the U.S. and EU markets alike. Pete will now walk you through our second quarter financial results and Q3 guidance.

Pete Trpkovski

executive
#3

Thanks, Jesse. I'll start by walking through how we did financially in Q2, then give you an update on Mt. Holly's expansion and the restart of Grundartangi 1 and 2, plus a look at cash flow for the business. Finally, I'll go over what we expect for Q3. If you'll turn to Slide 8. Looking at things on a consolidated basis, shipments in the second quarter came to roughly 131,000 tonnes, which is 6% higher than the previous quarter, driven by extra production from the restart of Line 2 in Iceland and the Mt. Holly expansion. Net sales came in at $752 million for the quarter, up $103 million quarter over quarter, largely because of better realized LME and regional premiums, along with greater shipments. Net income reported for the quarter was $249 million, or $2.39 per share. Adjusted net income came to $257 million, or $2.46 per share, once exceptional items are excluded. Those exceptional items consisted of unrealized gains on our derivative contracts, business interruption losses in Iceland, and restart expenses at Mt. Holly. Adjusted EBITDA for the quarter reached $327 million, mostly thanks to higher LME and regional premiums and more volume from expanded output at Mt. Holly. Throughout the quarter, we kept working on strengthening the balance sheet. Our cash balance was $388 million as of the end of June; we remain focused on paying down debt, with $66 million repaid during the quarter, leaving no outstanding borrowings on our credit facilities when the quarter closed. Net debt came down to $98 million. And by the end of July, our cash position was larger than our total debt. I'll say more about that in a couple of minutes. Now to Page 9. Adjusted EBITDA rose $96 million in the second quarter, reaching $327 million. Realized LME was $3,250 per tonne, which is $350 more than the prior quarter. Our realized U.S. Midwest premium came to $2,480 per tonne, an increase of $280, while the higher European premium of $450 per tonne was up $140. Combined, LME and regional premiums pricing added an incremental $95 million relative to the prior quarter. Energy costs went back to normalized levels once winter ended, and raw material costs rose as we had expected. Volume and sales mix improved by $8 million versus the prior quarter; this higher production volume was anticipated from our Mt. Holly expansion. That said, shipments at the end of the quarter were impacted by cutoff timing, which led to a sequential rise in finished goods inventory tied to the Mt. Holly expansion. We expect that inventory to ship in Q3, and I'll get into that in more detail shortly. As we anticipated on our last call, operating expenses were higher than the prior quarter, driven by the Mt. Holly expansion and reflecting the 100% capacity run rate. Let's now go to Slide 10 for a look at cash flow. We started the quarter with $332 million in cash. We produced strong cash from operations during the quarter. We keep accruing 45X tax credits quarterly, with cash receipts coming after we file our annual tax return. In Iceland, insurance recoveries tied to Line 2 lost profits keep arriving behind schedule each quarter, so we still see a cash impact there. During the quarter, $46 million came in for lost profit margin from earlier periods. CapEx for the quarter came to $59 million, and $37 million of that went toward the Mt. Holly expansion investment along with our new power generation unit, TG4 at Jamalco. Hedge settlements totaled $30 million in the quarter. Cash interest came to about $5 million for the quarter. Working capital grew this quarter, since the Mt. Holly expansion pushed our working capital back up to 100% capacity, and finished good inventory also rose — something I mentioned earlier — because of shipment timing. We anticipate recovering cash from a portion of that finished goods inventory in Q3. We reduced our Icelandic revolver by $66 million in Q2, and the quarter closed with zero borrowings on our revolving credit facilities; Q2 ended with $388 million in cash and solid liquidity in place. As we discussed, a lot of these items will turn into cash in later quarters. For instance, at the close of July, we collected $94 million in cash for 45X tax credits outstanding tied to fiscal year '25. We also brought in another $19 million during July for the Grundartangi insurance recoveries. On top of that, Century's balance sheet has never been stronger, with every short-term debt repaid. And as of today, the cash Century holds on hand is greater than its total debt. Looking ahead, we anticipate even better cash flow conversion, since investment CapEx for the Mt. Holly and Grundartangi restarts is now finished, leaving mainly sustaining CapEx across the second half of the year. Now let's move to Slide 11, and I'll look ahead to the coming 90 days; for Q3, lagged LME is expected to be $3,325 per tonne, up about $75 compared with Q2 realized prices. The Q3 lagged U.S. Midwest premium is expected to reach $1.09 per pound, which is down $0.03 from Q2 realized prices. The European duty paid premium should come in at approximately $520 per ton in Q3, or up about $70 per ton. Combined, the lagged LME and delivery premium changes should add $5 million to $10 million to Q3 adjusted EBITDA relative to Q2 levels. We expect energy headwinds of $10 million to $15 million, which is typical given warmer summer weather. Turning to our other raw materials, input costs keep rising at a moderate pace. We see a small $5 million sequential headwind. OpEx should be flat in the third quarter. Volume and sales mix should improve by $15 million to $25 million, helped by higher production and shipments at Mt. Holly. And at expected realized prices, we anticipate Q3 adjusted EBITDA in the range of $325 million to $345 million. As we've done before, we've put the projected hedge and tax effects at the bottom of the page to assist with modeling the business; we anticipate a headwind of $20 million to $25 million stemming from realized hedge settlements, plus $10 million to $15 million in tax expense, with both running through our Q3 P&L and affecting adjusted net income and adjusted earnings per share. So with that, I'll turn the call back over to Jesse.

Jesse Gary

executive
#4

Thanks, Pete. Before we head to Oklahoma to wrap up the call, let me say a few words about Hawesville, which is shown on Page 21. Back in February, when we divested that site, we got $200 million in cash and kept a 6.8% nondilutive stake in the finished data center. Since that time, the project has moved ahead considerably. TeraWulf, our partner, has brought Anthropic on board as a data center tenant under a 20-year lease, which is anticipated to produce roughly $19 billion in lease revenue across its initial term. The expectation remains that energization will happen in the latter portion of 2027, and one year after that, we hold the option to sell our portion of the data center back to TeraWulf; as we shared in February, our belief is that this stake would be valued at substantially more than the cash we originally got. That perspective gains strong support from a signed 20-year lease with a top-tier tenant that includes two 5-year extensions, and Century bears no responsibility to contribute toward any part of the development cost. The expected monetization schedule for our 6.8% stake lines up fairly well with the construction in Oklahoma, which makes it another possible source of capital to help fund Century's portion of that project should the need arise. Let me turn finally to our new Oklahoma smelter project alongside our joint venture partner, Emirates Global Aluminum. During the second quarter, we made additional progress. Bechtel is carrying on with its detailed engineering work. We moved negotiations forward on a final energy contract, and we achieved meaningful progress on the financing for the smelter. Three things remain our immediate focus: securing the last power agreement, completing detailed engineering, and locking in financing. We continue to anticipate a final investment decision and start of construction before this year wraps up, and we still project the first hot metal coming off the line by the close of 2029. Moving to Page 12, I want to highlight what I view as the most significant policy news of the quarter. A new executive order from President Trump, issued on July 20, establishes an incentive aimed at encouraging businesses to construct or grow primary aluminum capacity within the U.S. Through this initiative, qualifying businesses get the ability to bring in primary aluminum each year, with that allowance matching the volume of fresh output they're currently constructing, and they'll pay a lower tariff of 25% instead of the 50% that would normally be charged on such imports. I want to stress the significance here. Initially, the Section 232 program created fairness for workers and producers in America. This past April, the Trump administration shut down the valuation gaps that those importing goods had exploited to sidestep the program. With this order now, the program moves even further, giving real incentives to companies that are investing money into building additional capacity within the United States. Every stage depends on the prior one, and we've applied all of them strictly—no carve-outs, no exceptions granted. That hits Century in a very immediate way. Our expectation is that the Oklahoma project gets the green light under the program that permits up to 750,000 metric tons to come in at the lower 25% rate, beginning in 2027. EGA takes 60% of that split while Century gets 40%, so from 2027 on, Century could begin importing up to 300,000 metric tons each year at the discounted rate, and we intend to steer those savings toward funding Century's share of the Oklahoma project. This represents yet another thoughtfully crafted policy measure, and our thanks go to President Trump and his team for backing us and for their dedication to bringing American aluminum production back. When you put it all together — a balance sheet on which our cash now stands above our total debt, the tariff advantage from the new executive order, and the value generated at Hawesville — Century possesses genuine and expanding balance sheet capacity to finance its portion of the Oklahoma project and also to chase additional opportunities and priorities aimed at delivering best-in-class value for our shareholders. In closing, we stated earlier this year that by the end of July every asset would be running at full capacity, and that is exactly what we achieved. Looking ahead, our plan is to break ground on the first new American smelter in close to 50 years. When it comes to restoring American primary aluminum production, no company is putting more money in than Century; we are already the biggest aluminum producer in the United States; we have more American primary aluminum workers on our payroll than any other company. And because of President Trump's leadership along with the Section 232 program, we are putting billions more into new and expanded production at Mt. Holly and in Oklahoma. Execution is our sole focus; we appreciate your time, and we are ready to take your questions today.

Nick Giles

analyst
#5

First off, I just wanted to ask about that executive order — where will the metal ultimately come from, and how do you quantify this advantage when it comes to EBITDA and cash flow?

Jesse Gary

executive
#6

Yeah. Like I said, that executive order matters a great deal and it opens up a solid opportunity for Century, and naturally for anybody else putting money into new aluminum production here in the U.S. On our end, we think there are several different places we'll be able to source the metal from. Clearly our own resources in Iceland, but we expect additional sources as well. Here's how that part of the call is likely to go: Commerce is going to put out some rules at some point, and until that happens we're going to sit tight, and once they're out we'll come back to you with the final analysis. I want to give you a sense of how big this opportunity is for us. As I said, we'll hold off on firm figures until we see the final version. But you can take that lower tariff rate — say we're looking at 25% instead of 50%, just as a rough guide — and plug in whatever LME price you like. Right now it's $32.50, so run that through and you'll get an idea of what the per-ton benefit looks like. After that, Century ought to be in a position to bring in the portion of the fresh output belonging to us—that's 300,000 tons—and simply take those two figures and multiply them. What you'll find is that the upside would be pretty substantial, and it ought to land identically whether you're looking at EBITDA or cash flow.

Nick Giles

analyst
#7

Nick, thanks, glad that was useful. Now, regarding the project — an update on the DOE grant would be nice. When do you think we'll have additional details on that? And then, more broadly, on where the money's coming from. What financing work for the project is happening right now? You also brought up the stake at Hawesville. I'd like to hear what you think about that.

Jesse Gary

executive
#8

Sure. A quick note on the DOE grant: it's locked in. Naturally, plenty of milestones have to be cleared for the project, and for DOE, before that grant gets released. But the grant essentially disburses matching funds, dollar for dollar, against what we invest in the project, to unlock that $500 million. So nothing has really shifted versus our earlier statements. It all stays as is, and things look fine. Turning to financing more generally, we're pursuing several possible sources. As soon as they're locked down, we'll of course bring you the specifics. That said, we're in discussions with multiple parties, among them some possible government financing sources.

Katja Jancic

analyst
#9

K (Katja Jancic): Jesse, you brought up multiple — potential cash sources exist in more than one place for financing that smelter. And going forward, your free cash flow conversion should get better. Could you speak — say a little about what your thinking is right now regarding returns to shareholders, particularly given that your balance sheet sits in a really strong spot.

Jesse Gary

executive
#10

For sure. If you turn to Slide 22, like you said, we've already generated some quite robust cash flow. As Pete noted, following the quarter, we received our $94 million 45X refund, plus roughly another $20 million from insurance recoveries, and that leaves us where our cash is above our total outstanding debt as of the end of July. You can also see our liquidity at $785 million, which is well above our target. So the balance sheet is well positioned, and we expect to keep it well positioned, and there's a great deal of opportunity with a great deal of cash flow coming in for us to do that. We did say we'd return to you about capital returns once we get past these targets, and we will. But we've also stated that we had a clear priority when it comes to capital allocation. Naturally, that means maintaining liquidity through the cycle, then making sure we have sufficient sustaining capital; and after that we'd seek organic growth opportunities. Clearly, the new smelter in Oklahoma belongs in that category; and all we ask is that while we're proving out the last details there, while we're working through the final engineering numbers and CapEx numbers and moving toward FID, people stay patient with us; but we absolutely expect that we'll be in a position where we have ample cash to finance the smelter, including our equity piece, and also to chase other priorities, whatever they turn out to be, and naturally, that includes capital returns.

Katja Jancic

analyst
#11

Perhaps we could pivot slightly to Iceland. During 4Q, you plan to put in the new transformers. Is there going to be an effect on production volumes? Or what's the right way for us to think about it?

Jesse Gary

executive
#12

Yeah. As I mentioned during the call, at this point we've returned to nearly full production, though we're keeping somewhat cautious regarding how much amperage we push through the transformers that were repaired. This isn't — the amounts we're discussing aren't large. We're quite near full production. However, after those new transformers are actually installed in Q4, you ought to see us raise the amperage, and that will push the volume coming out of Grundartangi even higher, and you'll observe it going back to that normalized run rate that existed prior to the interruption, that complete normalized run rate.

Pete Trpkovski

executive
#13

Also, Katja, let me jump in — I believe what you were asking is whether there will be any disruption to production once we begin installing these and putting them into operation. Given the redundancy the repaired transformers will provide, we'll return in 3 months with our Q4 outlook, though as I sit here today, I wouldn't anticipate any production interruption.

Jesse Gary

executive
#14

No, no, there shouldn't be any interruption to production.

Timna Tanners

analyst
#15

I'd like to ask about Mt. Holly. To start, when you talked about who might benefit from the new executive order and that 50,000 ton restart, you left them out — so is it possible they don't qualify? Or do they? And separately on Mt. Holly, could you put numbers on the instability and what it means for Q3?

Jesse Gary

executive
#16

Thanks, Timna. No. Since Mt. Holly is now finished and that new output is flowing, our expectation is that it won't qualify. As we understand the program — at least as of today — the way it's built is to permit imports while an investment is pending and new output is still ramping. Once that output is up, though, you can't keep bringing in more imports. So with Mt. Holly complete, we don't expect it to qualify as of today. On the instability, like I said, that's the kind of thing that can crop up during restarts. Naturally, a facility is accustomed to running at a lower output level, along with certain supporting sections of the plant, so when they have to run at a higher output level, you've got more metal moving through the tank house. More anodes are getting made in the carbon area; and occasionally you see a bit of instability there. This isn't material. It's reflected in our Q2 guide. It does carry some effect into Q3, Timna. Still, we believe we'll have it completely sorted out in Q3; so you ought to see somewhat more volume returning in Q4 compared with what's already showing up in Q3.

Timna Tanners

analyst
#17

All right, that's useful. For my follow-up, could you give us some insight into what's going on with the new Oklahoma smelter, since we're quite removed from it — all we get are the news stories, plus a bit of resistance and arguing coming from people in that area. Could you walk us through what's taking place and share your level of confidence? It sounds like, for you, the path ahead is quite certain, but I'd appreciate hearing your side of it in more detail, if you don't mind.

Jesse Gary

executive
#18

Of course. Naturally, whenever a big project is unveiled near where people live, they're going to want to know what it involves. I believe we're engaging quite closely with residents in Inola and other parts of Oklahoma, both to gain a clearer picture of what worries them and to ensure they possess the full set of facts regarding our technology and our process. Beyond that, we have a great deal of confidence that this smelter won't cause harm to anybody, that everyone will feel at ease with what's taking place, and that they'll come to recognize what the state and the surrounding area gain from all the money put in and the positions that get created. What we're discussing here is an enormous set of gains for all involved. Still, we're putting in the effort to grasp their worries and to help them reach a point of comfort.

Matthew Key

analyst
#19

You brought up that some power capacity at Jamalco would be finished in August. Could you perhaps assist in putting a number on what financial upside that represents? Is it that you'd only see cost advantages when there's something like an energy outage? Or is this something more durable over the long term?

Jesse Gary

executive
#20

There are genuinely two parts to it, Matt. First, as I said, we'll be capable of meeting all our own energy generation needs inside our four walls. Put differently, we'll be able to run like an island inside the island, so to speak. Naturally, though, in ordinary conditions, we'll stay tied to the grid because of stability. Yet should the grid run into trouble, we can then run like an island. The second piece is the savings on cost. Energy, naturally, is pricey in the Caribbean, and through TG4 we'll be capable of producing energy on our own that completely satisfies what we need. So starting at the beginning of August, we can halt those grid purchases moving forward. And savings will show up. Naturally, it hinges on where market prices sit in Jamalco, what those savings come to. But roughly a $20 per ton benefit there is what you'd think about, and that would bring you close.

Pete Trpkovski

executive
#21

Also, Matt, let me mention that I've already factored that into what I gave you for Q3.

Nick Giles

analyst
#22

I was just wondering — and apologies if this was already covered — could you walk us through part of the working capital release, along with what's happening with cash flow in the back half, on the insurance side or elsewhere?

Pete Trpkovski

executive
#23

Absolutely, Nick. I'll kick things off on that. I mentioned briefly the working capital increase during this quarter, the second quarter. I didn't give specific figures on how it broke down, but picture it as 2 components. First, we restored Mt. Holly and scaled the expansion up to full capacity. That means you saw growth in supplies and inventory, plus receivables to match. And second — since output rose, we had shipments converting, and the close of a quarter is just one moment in time. So there was some cutoff timing affecting those shipments. That's what drove the working capital increase in Q2. Looking ahead, clearly you won't recover all the working capital required to run Mt. Holly at 100%. Still, you'll definitely recover a solid share of that finished goods inventory that's on the balance sheet as of the close of Q2, during Q3; that ought to provide a nice cash tailwind. Then, moving forward on cash flow conversion, as I noted in my remarks, we expect it to come in even stronger than what we've seen so far as we keep going. As I mentioned, there's the $94 million from the 45X credit. We received another $20 million related to the insurance recovery, and we keep pushing on that. Meanwhile, growth CapEx drops off significantly. The Mt. Holly expansion is done. Bringing Line 2 back online in Iceland is done, and from here we should really only have sustaining CapEx. So considering our balance sheet position, I believe you'll see that robust cash flow conversion ahead.

Nick Giles

analyst
#24

Understood, that's very useful, Pete. Perhaps we could return to Oklahoma for a moment. I'm wondering if you have any news regarding the discussions around the power agreement. Is there anything blocking progress that you'd be able to identify? And at what point ought we to anticipate it being completed prior to the final investment decision and the groundbreaking that's coming later in the year?

Jesse Gary

executive
#25

Absolutely, Nick, our collaboration with the other side there remains very productive, alongside our partners, EGA, and also with the utility on the other side of the table as we push this effort ahead; progress is being made; these agreements are complicated. Finalizing them through the lawyers and everything else genuinely requires time. Still, I'd simply say the situation keeps advancing nicely and we're achieving solid momentum. Naturally, it will be finished before we reach FID, though at this point I'd rather not estimate any further. Just understand that we're putting in the effort and momentum keeps building.

Jesse Gary

executive
#26

Thanks to all of you for being here on today's call; this quarter is one we feel great about. We're eager for Q3 and for whatever lies ahead for Century. Many thanks.

Operator

operator
#27

This concludes today's call. Thank you for attending. You may now disconnect.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Century Aluminum Company transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Century Aluminum Company earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Century Aluminum Company or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.