Chad Rigg
executiveThanks, operator. Good afternoon, everyone, and welcome to the third quarter conference call. Joining me today are Jesse Gary, Century's President and Chief Executive Officer, and Peter Trpkovski, Executive Vice President and Chief Financial Officer. Once we've finished our prepared remarks, we'll take your questions. As a reminder, today's presentation can be found on our website at www.centuryaluminum.com. Our website serves as a channel for disclosing material information about the company and for complying with Regulation FD. If you'll turn to slide two, please take a moment to review the cautionary statements regarding forward-looking statements and non-GAAP financial measures in today's discussions. With that, I'll hand the call over to Jesse.
Jesse Gary
executiveThanks, Chad, and thanks to all of you for joining us. I'll begin today with the results for our third quarter, then take you through operations and update you on the Oklahoma smelter project, before moving to the great market conditions we're still operating in today. After that, Pete will walk you through the quarter in detail along with our fourth quarter outlook. First, I want to thank our teams at all our locations for another strong quarter on safety; we faced hot summer temperatures and many new employees across the assets because of restarts, and our team stayed dedicated and focused. On page four, you'll see that our strong third-quarter results came about because our assets ran at full capacity for the first time in over ten years. Combined with solid demand and pricing in our U.S. and European markets, those assets generated net sales of almost $1 billion for the quarter, along with adjusted EBITDA of $332 million. Also on page four, under operations: at Mt. Holly, the production instability we mentioned back in August is now fixed. That kind of instability wasn't surprising following a restart of that magnitude, and the team acted well to address it, even with record-high summer heat in South Carolina. With the instability now resolved, we expect the plant to operate at full volume and a normal production mix throughout Q4. At Grundartangi, the smelter delivered a strong production quarter after restoring its full pot complement in July. Three of the four replacement transformers have arrived in Iceland; the first has been installed, a second is going into service this month, and the other two should be installed over the coming months. As those additional transformers come online, we will be able to raise Potline Two amperage from the reduced levels in place since the restart and bring the plant back to full nameplate production. We expect the line to be back at full amperage sometime during the first quarter, and we'll share more on that during the Q4 call in February. Getting the line back into production six months ahead of our original expectation is a real credit to the team. Over at Jamalco, the team is still dealing with the bauxite quality problem we flagged back in May. The updated mine plan is now being put into place, and we're moving forward, though as I mentioned, it will take a few quarters to fully carry out. Also, our TG4 power generation turbine came online in August and is performing well, which lets us sidestep purchases of costly energy from the Jamaican grid. Sebree also delivered another outstanding quarter on both operational and financial fronts. That site is setting the benchmark for the remaining Century portfolio and keeps getting better. Once more, great work from that team. Before we move on to market conditions, here’s a brief Oklahoma update. Alongside our EGA partners, we made solid headway on the new smelter project during the third quarter. Financing discussions have advanced, with the main commercial terms largely agreed and anticipated to be wrapped up in time for FID. Our power contract also advanced this quarter, as we move toward completing final documentation with the supplier. Meanwhile, we keep collaborating with Bechtel and the EGA team on the detailed engineering plan, and that work will carry on in full force during the fourth quarter. We are engaging state regulators and the community to move the project ahead and respond to concerns that have come up; this September we filed a revised environmental plan with the Oklahoma Department of Environmental Quality, committing the project to cut permitted fluoride emissions by 37%, which would rank the new smelter among the finest anywhere in the world. We also released a new economic impact study showing the new smelter should raise Oklahoma's GDP by close to $1.5 billion annually, equal to nearly 1% of the state's total GDP. Along the same lines, we have started partnering with Tulsa Innovation Labs on workforce development, since the smelter is ultimately expected to generate more than 1,000 permanent direct jobs plus 5,000 indirect and induced jobs. Although our dialogue with regulators and the community continues, we feel we have made headway in resolving the concerns that remain. Last, we were delighted that Mike Mazzei won election this past Tuesday as Oklahoma's next Governor. Mike and the sitting Governor, Kevin Stitt, have both backed the project strongly, and we look forward to cooperating with them in the months ahead as we work toward FID. Once constructed, the Oklahoma smelter will about double total U.S. primary aluminum production and bring back domestic output of military-grade high-purity aluminum. Upon completion, it will rank among the most efficient and advanced smelters globally and stand as a crown jewel of the U.S. industrial base. Okay, let's take a few minutes on the market, beginning on page five. Market conditions stay robust, with supply still tight owing to Middle East disruptions and a sluggish restart of curtailed production in that region. Demand across our U.S. Demand across European markets is still solid, driven by construction of data centers and power systems plus healthy automotive demand. Other bright spots are commercial aerospace, defense, and rearmament, together with recovering U.S. domestic manufacturing demand. Recent production disruptions elsewhere in the world have only reinforced our standing as a dependable supplier with short, flexible supply lines serving both the U.S. and European markets. All of this shows up in the historically low global inventories on page six, leaving a very favorable pricing backdrop with spot LME at roughly $3,175 per ton, a Midwest premium of roughly $1.12 per pound, and the European duty-paid premium at roughly $575 per ton. In addition, we expect robust demand for value-added products in 2027. At present, we are right in the midst of contracting season, and we'll give you guidance regarding 2027 value-added premiums during our Q4 call. Turning to costs, as page seven illustrates, you can observe how high summer temperatures affected Indy Hub power prices in Sebree, though those prices have moderated quite nicely as temperatures returned to normal over the last couple of weeks. Given persistently high oil prices stemming from the Middle East conflict, coke and heavy fuel oil prices are still elevated. Pete will now walk you through our third quarter results and our fourth quarter outlook.
Peter Trpkovski
executiveThank you, Jesse. I'll go over our results for the third quarter, our cash flow, and our financial position, and then I'll discuss the outlook for the fourth quarter. Shipments in the third quarter came to roughly 173,500 tons, a sequential rise of 33%, which reflects Mt. Holly getting back to full capacity along with the restart of Potline Two at Grundartangi. Net sales rose $209 million quarter over quarter to almost $1 billion, mainly on the strength of higher realized LME prices and shipments. Net income came in at $303 million, or $2.89 per share. Adjusted net income was $272 million, or $2.58 per share, leaving out exceptional items. Those exceptional items were mostly unrealized gains on derivative contracts plus business interruption losses in Iceland. Adjusted EBITDA reached $332 million, helped by higher LME prices, regional premiums, and volumes after the Mt. Holly expansion. In the quarter, we turned $332 million of adjusted EBITDA into $365 million of cash flow, and we finished the quarter with $755 million of cash on the balance sheet. Moving to slide nine, adjusted EBITDA was up $5 million sequentially at $332 million. Realized LME rose by about $150 to $3,400 per ton. The U.S. Midwest premium fell $30 to $2,450 per ton, or $1.11 per pound, whereas the European premium climbed roughly $70 to $520 per ton. All together, pricing added an incremental $9 million compared with the prior quarter. As we had expected, energy costs were a seasonal headwind, with MISO Indiana Hub prices for Sebree averaging about $60 per megawatt hour. Volume and sales mix added another $19 million sequentially, which reflects the Mt. Holly expansion and the timing of shipments. Operating expenses went up after some initial instability at Mt. Holly following the expansion. Moving to slide 10, we started the quarter with $390 million in cash and generated strong operating cash flow. First, we collected $94 million in cash for our fiscal 2025 Section 45X tax credit and continue to accrue credits each quarter. We also expect to receive the outstanding $80 million from our fiscal 2023 credit in 2027. Next, in Iceland, Potline Two came back to near full production. We received $19 million in insurance proceeds during the quarter and expect further recoveries to keep coming in on a lag basis in Q4 and into 2027. CapEx totaled $38 million. About $18 million of that was investment spend tied to the Iceland transformer replacements, but the vast majority of this investment spend on restarts and the new power turbine in Jamaica is now behind us. Cash, interest, and taxes came to approximately $16 million. This mainly reflects the semi-annual interest payment on our senior notes. Hedge settlements totaled $24 million. Working capital also released nearly $40 million in cash as inventory built after the Mt. Holly expansion shipped as expected. We ended the quarter with $755 million in cash, no revolving credit borrowings, more cash than total debt, and more than $1 billion in liquidity; we expect strong cash conversion to continue, supported by additional 45X tax credits and Grundartangi insurance recoveries. Moving on to slide 11, we’ll walk through the fourth-quarter outlook. For lagged LME, we’re anticipating $3,150 per ton, roughly $250 lower than the realized prices in Q3. The lagged U.S. Midwest premium should come in at $1.10 per pound, a decrease of $0.01. Meanwhile, the European duty-paid premium is projected to climb to $550 per ton. Taken together, those pricing shifts are anticipated to cut adjusted EBITDA by $35 million-$45 million on a sequential basis. On energy costs, we’re looking for a flat-to-$5 million sequential improvement, since MISO Indiana Hub prices are forecast to be about $10 per megawatt hour better than in the previous quarter. Raw materials running higher should generate a sequential headwind of $5 million-$10 million. Operating expenses are expected to rise by roughly $5 million quarter over quarter. Volume and sales mix should contribute a $5 million-$10 million improvement, helped by increased production and shipments at Mt. Holly. A portion of off-spec material stemming from the earlier instability will be a slight drag on the Q4 sales mix. All told, at expected realized prices, we anticipate Q4 adjusted EBITDA in the range of $275 million-$300 million. For modeling purposes, assume realized hedge settlements of $20 million-$25 million and tax expense of $10 million-$15 million. Each of those will impact Q4 adjusted net income and adjusted earnings per share; with that, I’ll turn the call back over to Jesse.
Jesse Gary
executiveBefore we open the line for questions, I want to spend a brief moment underscoring how well the business generated cash and how solid our balance sheet is. In the third quarter, as Pete mentioned, we turned $332 million of adjusted EBITDA into $365 million of cash flow for the quarter, and we closed September holding $755 million in cash while carrying just $486 million of debt. Century is presently converting earnings into cash at an exceptionally strong rate, and we anticipate that will persist. Our big investment CapEx initiatives — bringing production back at Mt. Holly and Grundartangi and putting TG4 in place at Jamalco — are all finished now. This year those projects accounted for roughly $125 million in investment capital spending, and that outlay is done and won't recur. Going forward, we look for CapEx to come back to more normal levels, which leaves room for cash flow conversion to rise considerably. Beyond that, we still expect certain additional cash payments tied to earlier quarters to come in during 2027 — specifically the Section 45X tax credits for the 2023 and 2026 tax years, plus what remains of our Grundartangi insurance recoveries. We also continue to hold our 6.8% interest in the TeraWulf data center under construction at Hawesville, along with the right to put that stake to TeraWulf for $300 million once the data center is operational, or to sell it to a third party should we be able to obtain a greater value. On that subject, TeraWulf has reported quite favorable progress on the project, engaging Fluor for the EPC build and obtaining investment-grade credit support from Google to stand behind the financing. Keep in mind that our 6.8% interest applies to the finished data center, and we carry no obligation to put in additional capital. Taking it all together, we anticipate that our cash position — already robust — will keep strengthening over the next several quarters as we harvest the rewards of the investments that bring Grundartangi and Mt. Holly back to full capacity, along with supportive market conditions. Our plan is to deploy that strong cash position first toward funding our share of the Oklahoma project once we reach FID. After that decision is made, we intend to give you further guidance regarding possible additional high-return investments and returns to shareholders. Bear in mind that the Oklahoma project will gain from the import incentive program we covered last quarter, which ought to let us import primary aluminum up to our share of annual production in Oklahoma at a discounted tariff rate of 25% rather than the 50% rate that would otherwise be charged. No other company is putting more into restoring American primary aluminum production than Century; we are the biggest aluminum producer in the United States; we have more American primary aluminum workers on payroll than any other company, and we intend to invest billions more in new production in Oklahoma. We stay sharply focused on execution and look forward to discussing our 2027 plans with you on our February call. We appreciate you joining us, and we’re eager to answer whatever questions you may have.
Nick Giles
analystYeah. Thanks, operator. Good evening, everyone. It's good to see the progress here. I suppose, just following up on your final point there, Jesse, you said you'd like to accumulate sufficient cash to cover the equity check for the Oklahoma project. I'd have to think that a lot of the CapEx spending might come more in 2028 than in 2027; so there could be something of a timing mismatch where you'd end up with extra cash sitting on the balance sheet. What are your plans for that cash, and would you be open to considering shareholder returns sooner than anticipated, given that the stock has been under pressure? Thank you.
Jesse Gary
executiveYeah. Thanks, Nick. We've had some minor technical issues on our side. Is everyone able to hear us clearly?
Jesse Gary
executiveThanks, Nick. That's a good question. We're quite pleased with how things performed and with the cash we accumulated during this quarter, and we anticipate the same in the quarters ahead. I mostly share your view that, at today's level, the stock clearly looks undervalued. When we consider how important and how large the Oklahoma project is for Century and, honestly, for the whole U.S. industry, we think it's sensible to hold off on returning capital to shareholders until we get to FID. That gives us time to complete the financing and structuring of the import incentive and to see not only the total size of our equity needs but also the shape and timing of those requirements — how that spending might unfold across the period — before we make further capital allocation decisions. In the meantime, as you noted, we'll stay responsible stewards of the cash and push toward FID as fast as we can. With the strong cash flow this business generates, we'll keep evaluating where things stand, and if we keep producing substantial cash the way we expect to, we'll simply monitor the timing of FID and monitor that cash accumulation, and should an opportunity emerge, we'll come back and share it with everyone.
Nick Giles
analystGot it, Jesse. That's really useful detail. I just wanted to ask about the broader power approach in Oklahoma. Would you expect that power to be hedged? And what are the main gating items when it comes to the power agreement specifically?
Jesse Gary
executiveYeah, good question. Obviously, at Century, we buy power in a lot of different ways across our assets. In Oklahoma, we'll be purchasing from the utility directly rather than from the market, like you see at Sebree or with an LME percentage type arrangement like you see in Iceland. It will look more like the structure you're used to seeing from us in South Carolina, although it will have its own structuring within that that we'll give to you once we reach that FID decision. Hopefully, that gives you a sense of the type of contract we're talking about at least. Then to your second part of your question.
Nick Giles
analystNo, that's great.
Jesse Gary
executiveNick, we've really made solid progress on that with our counterparty, and we keep making it. Like I mentioned, we're kind of entering the final documentation stage now, so things are advancing on that front.
Nick Giles
analystAll right. Well, that's good to hear. I appreciate the update, and yeah, once again, nice work.
Jesse Gary
executiveThanks.
Matthew Key
analystGood afternoon, and thank you for taking my questions. I wanted to discuss just the progress that's being made on the ground in Oklahoma. Was the community debate surrounding the project mainly tied to worries about fluoride emissions? Were there any other potential areas of concern regarding the project? I'm trying to get a sense of whether there's any risk, in your view, that some areas could be potentially dragged out from a permitting standpoint, or do you think you're essentially dealing with it effectively over the last couple of months?
Jesse Gary
executiveYeah, good question. Obviously, when you're working with regulators as well as people from the community, all sorts of issues and concerns come up, and we've tried to handle them as responsibly as we can. That covers everything from the voluntary reduction in our fluoride emissions — as I said in my prepared remarks — to running town halls and answering questions individually with community members who show up. What I can say is that support from the state and federal levels remains very, very strong, and our communication with regulators in Oklahoma is really good as we keep trying to move ahead and deal with the concerns that have arisen. I'd say progress has been solid—we’re working to tackle and respond to questions as they arise, while keeping the project on schedule and advancing it.
Matthew Key
analystUnderstood. That’s really useful. Thanks. I’d like to ask about the import ARB opportunity. After you reach a final investment decision—an FID—in Oklahoma, how quickly might you be able to use that program, and what does the application process look like there?
Jesse Gary
executiveYes; we are in contact—actively in contact—with the Department of Commerce regarding all those specifics, with quite constructive two-way exchanges while the precise mechanics of how it will operate get settled. I would say we are progressing quite well and are closely aligned with the Department of Commerce on this, and they have been extremely helpful in advancing it. I absolutely expect that we will be in a position to use that program very soon, possibly even at the same time as FID.
Matthew Key
analystUnderstood. That's great, and I appreciate your time, and best of luck moving forward.
Jesse Gary
executiveThank you, Matt.
Katja Jancic
analystHello, and thanks for taking my questions. I believe you mentioned before that you had or were considering a number of promising financing options for the Oklahoma smelter. Where does that stand now? And does the midterm election alter the opportunity set at all?
Jesse Gary
executiveRegarding the first part of your question, Katja, as I noted in my remarks, we're still pushing that financing forward, and our progress has been very good. I'd say essentially all of the material terms are now agreed, and we fully expect to be prepared to proceed as soon as we make and reach FID. I honestly don't anticipate any problems when it comes to the financing. It remains my belief that this will be a highly attractive financing package. We're genuinely enthusiastic about it. As for your second question about the midterms, well, we're only a couple of days in here, so we'll need to see precisely what the new Congress intends to advance from a legislative standpoint. What I'd say more broadly is that, generally speaking, re-industrialization of U.S. manufacturing is truly among the few bipartisan issues that exist. We've gotten a great deal of backing, whether through a Democratic Congress, a Republican Congress, and with the current administration on this project; we would expect, regardless of what happens, to keep enjoying that kind of broad-based support across the aisle.
Katja Jancic
analystAll right, thank you.
Richard Garchitorena
analystThank you, and good evening to everyone. My first question concerns the 4Q guidance, though specifically on the production side — I believe you said something about how it ought to improve relative to the third quarter. There was a bit of instability, I take it. Did that have an effect on 3Q volumes? And connected to that, with Grundartangi Potline Two operating close to full output, will it also be at 100% during the fourth quarter in your assumptions?
Peter Trpkovski
executiveYes. Hi, Richard, and thanks for asking. Regarding the instability at Mt. Holly, as we discussed, it got resolved during the third quarter, so that is reflected in the results. If you consider what we stated in our remarks — that the instability was resolved in the third quarter, and that we will devote the time in the fourth quarter to restoring volume to full production — you will see the effect of those units coming online across the fourth quarter. That estimate for those units is included in our Q4 outlook, so there are no further adjustments on that. And yes, I do remember Potline Two at Grundartangi. For Grundartangi, what we have done is adjust back the losses stemming from the business interruption in the prior quarter. So from an outlook standpoint, really, no further adjustments are needed for Iceland either.
Jesse Gary
executiveTo add to what Richard said, as I mentioned in my prepared comments, you'll see us begin raising that amperage again in Q1. More Grundartangi units are coming onstream beginning in Q1 as we bring that capacity back up, and Q1 will also give you the full benefit of the Mt. Holly tons being back in production, which we're ramping up during Q4.
Richard Garchitorena
analystAll right, excellent. Thanks. So perhaps I could ask a follow-up regarding Oklahoma. You've described the contract talks on both the power side and the financing side as nearing completion, I believe. Given the conditions there right now, is there anything that might hold things up or make the process slower, or are you able to just proceed with the financing and power contracts? Those conversations are distinct from what you're doing with the community and that sort of thing.
Jesse Gary
executiveYes, Richard, that's a good question. Clearly, what we'll aim to do is get all of those work streams lined up essentially simultaneously, so that every piece of information and every component of the project is ready to go at the moment we reach that final investment decision. To accomplish that, while we're busy addressing the community's concerns and collaborating with the regulators on permitting, we're likewise carrying on with the engineering work, and we are entirely permitted to undertake all those pre-construction activities that the site requires from us during this stretch. So we're truly advancing on every front, and the plan is that we'll manage to bring those all into alignment at the same time, so we hold all the information required for reaching that final investment decision.
Richard Garchitorena
analystGreat. Thank you.
John Tumazos
analystThanks for taking my question. I worked out a cost improvement of $0.33 a pound across the last two quarters, after costs had climbed $0.60 in the three quarters before March 31. Given that the improvements are continuing at three of the four locations — all except Sebree — should we expect those costs to fully come back in the December and March quarters?
Jesse Gary
executiveNo. Much of what you're seeing, John, comes from the benefit of bringing the smelters back to full production level. What you're seeing is fixed cost absorption, plus more efficient use of power and more efficient use of labor. The cost structure you're seeing now — and probably a bit more improvement still to come — ought to carry on into 2027 and beyond.
John Tumazos
analystIf I could ask one more.
Jesse Gary
executiveSure.
John Tumazos
analystThings are going well. It's possible cash rises nearly as much during the December quarter. It's possible you don't require the whole financing package—just half of it. Why should you pay the fees and take on the debt when business is performing so well and the money is already there?
Jesse Gary
executiveJohn, that's a fair question; our aim is always to maintain the most efficient capital structure possible. We believe the financing arrangements under consideration are extremely, extremely appealing, in terms of rates and structure. Naturally, though, once we get to FID, that decision will be made. Still, based on what we currently know about the financing—cost, rates, and structure alike—I would expect you'll see us aim to use it in full.
John Tumazos
analystThanks.
Jesse Gary
executiveI really appreciate all of you taking the time to be on this call. There might be a question that comes in late from Timna. If possible, I'd like to let her have the opportunity to ask it.
Timna Tanners
analystThanks a lot, folks. It's genuinely pretty striking, after all this time, to be sitting here looking at net cash — so let me come back with a follow-up tied to a few of the questions asked earlier. I believe I heard you mention that going forward, you'd keep us posted on potential additional shareholder returns as well as projects. Previously, my recollection is that you described projects of a fairly modest size, like the one at Jamalco — but is there any chance something could be bigger in scale? Turning to cash uses once more, at this rate, I mean, over the coming couple of quarters, wouldn't you potentially be pushed toward some alternative use, given how nicely it keeps building?
Jesse Gary
executiveYes. Timna, that's correct. That's a challenge we're glad to face, and we're enthusiastic about it. We feel good about how far the company has progressed and about everything the team has achieved. So, as I mentioned, we'll keep evaluating the most effective way to deploy that cash. You're correct that we've noted before that few opportunities resemble the Mt. Holly restart are out there for us. There are certain cost-related projects at Jamalco. Still, as you'd expect, we keep working to come up with fresh concepts, new projects, and better approaches to strengthening the business going forward. Basically, we're just leaving space for that to occur. Our teams keep pushing hard on it and won't stop. If that doesn't pan out, and things keep going the way they are, we believe we'll be sitting in a strong position — able to cover our portion of the Oklahoma project as well as either fund other solid projects or return capital to shareholders.
Timna Tanners
analystAll right, thanks for that. I wanted to dig a little deeper, because since we last had this chance to reconnect on a conference call, we've seen movement on possible trade deals with Canada and Mexico. On Canada specifically, there was some talk about a possible carve-out for aluminum and steel tariffs, and that seemed to run counter to what we'd been expecting might happen. Given your ties to the administration, I'm curious whether you can offer any additional insight into how they're approaching aluminum tariffs, especially with respect to Canada.
Jesse Gary
executiveThat's a good question. Naturally, I can't comment on the negotiations themselves, since I haven't been part of them. What I can tell you is that the government plainly recognizes the Section 232 program is functioning the way it was intended to. Since the program began and over the course of the President's term, Mt. Holly has restarted, lifting U.S. production by 10%. The New Madrid smelter in Missouri ought to come back online imminently, which should raise U.S. production by a further 10%. And then, of course, we keep moving closer to FID on our Oklahoma smelter project, which will double U.S. capacity. So I believe the administration is quite clear that the government is operating as it stands and as designed, and delivering the outcome that was wanted, namely re-industrialization and self-sufficiency when it comes to U.S. aluminum production. They've been extremely consistent. I mean, there's been plenty of chatter, as you put it, but in reality nothing has changed. The program remains in place, with no exemptions and no exceptions. So that's roughly how we see things going, Timna. Naturally, we listen and watch, but we're fairly confident the government understands and is pleased with the progress the industry is making.
Timna Tanners
analystAll right. Thanks a lot for that color. Wishing you the best of luck.
Jesse Gary
executiveThank you, Timna.
Jesse Gary
executiveAll right, thank you all for being here, and we look forward to speaking with you again in February.
Operator
operatorThis concludes today's call. Thank you for attending. You may now disconnect.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Century Aluminum Company transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Century Aluminum Company earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Century Aluminum Company or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.