CleanSpark, Inc. (CLSK) Earnings Call Transcript & Summary
August 6, 2026
Earnings Call Speaker Segments
Harry Sudock
executiveAppreciate that, Lacey. We're glad you could be with us as we go through CleanSpark's Q3 2026 financial results. Please take a look at the earnings release we put out today, which you can find on our website. Our 10-Q is going to be filed before long. Once a replay and a transcript of this call are ready, they'll be posted on our site as well. Joining me today are Matt Schultz, who serves as our Chairman and Chief Executive Officer, and Gary Vecchiarelli, our President and Chief Financial Officer. A portion of what we say today is forward-looking, reflecting how we currently see the world and our business. Those statements and that information are still subject to the risk factors laid out in our 10-K; in addition, we'll touch on some non-GAAP financial measures related to how we performed on this call. A reconciliation of those non-GAAP financial measures appears in the press release, which you can access on our website. With all that said, over to you, Matt.
Matthew Schultz
executiveThank you, Harry. Hello, everyone, and I appreciate you being here this afternoon. First off, I want to talk about the way we are deploying our operations and our balance sheet as we keep advancing toward becoming a diversified digital infrastructure platform. Once this quarter ended, we finalized an arrangement that stands as the largest deal ever undertaken by CleanSpark. It's a triple net lease running 20 years at the Sandersville, Georgia campus, signed with a top-tier global technology firm carrying a high investment grade rating. That deal signals the beginning of our shift into a diversified digital infrastructure platform and kicks off monetization of our power portfolio on an institutional scale. Under this lease, the business has secured $6.6 billion in contracted revenue, and that figure can grow to $11.6 billion if two five-year extensions are exercised. Because the structure is genuinely triple net, we anticipate a net operating income margin close to 100%. We've additionally established a partnership with a vertically integrated manufacturer and design builder specializing in mechanical, electrical, and plumbing, which contributed 885 megawatts of commercial growth. When you put all of this together, our second-mover advantage is fully realized. A lot of you were with us for the investor update on July 14th. Today, I'd like to go back over three points. First, I want to take some time to explain why we see this lease as not merely a milestone, but one of the very finest commercial outcomes anywhere in the sector. Second, I'll bring you up to date on execution at Sandersville, throughout our Texas portfolio that's under exclusivity, and across the wider platform. Third, I want to speak briefly about our legacy Bitcoin mining operation and how the optionality it gives us amounts to a strategic advantage as we move into this next chapter of evolution and growth. Let me begin with the market. Demand for compute keeps exceeding what the industry is capable of supplying. The bottleneck isn't chips. It isn't capital either; it's energized, grid-connected power at scale, located on land able to support a complete AI campus build. That mix is in short supply today, and in our view it will stay in short supply for years ahead. This agreement is a triple net lease lasting 20 years that covers our entire Sandersville campus. Close to 250 megawatts of gross capacity, along with 175 megawatts of critical IT load. The initial term holds roughly $6.6 billion in contracted revenue, and with two five-year extension options the total reaches approximately $11.6 billion across 30 years; we expect average annual NOI of about $330 million. We estimate our cost per critical IT megawatt to fall in the $10 million-$12 million range, consistent with what the market commands for this generation of data center. There are two takeaways I want everyone to get from those figures. First, we believe that on a risk-adjusted basis, these economics rank among the strongest in the space. Headline comparisons between data center deals can deceive, since differing contract durations, differing lease structures, differing risk allocations, and differing financing packages can hide what the actual returns are. Second, this is a triple net lease. Property taxes, insurance, and—this matters—maintenance CapEx are the tenant's responsibility. So basically, every dollar of contracted revenue drops through to net operating income, roughly a 100% conversion. And there's more upside than just that. On the financing side, the triple net setup acts as a really strong risk mitigant. When lenders underwrite a project like this, what they see is 20-plus years of cash flows that are clean, predictable, and high-margin, all backed by a counterparty with a high investment-grade rating, and nothing in the way of operating cost swings coming between the rent check and the debt service. That's the reason we can put this deal together with no credit wrappers, and the reason we anticipate that the bulk of this build-out—sorry, let me start that again. Our expectation is to fund the majority of this build-out through project-based financing at attractive pricing. Gary will walk through what's happening in the capital markets. Here's the abbreviated version: this lease was structured deliberately so that financing would be simple and a high loan-to-cost would be achievable, which shields our equity. A longer duration lease was something we pursued on purpose; a triple net structure was something we targeted on purpose, and a high investment-grade counterparty was who we picked on purpose to be our tenant. Every one of those decisions was made with the strategic aim of safeguarding and growing shareholder value. As things stand right now, the equity piece of the Sandersville project has been fully funded by us. When it comes to execution, the project is moving forward as planned. Site prep has been going on for months now on that 122-acre Greenfield parcel we bought earlier this year, and that lets us build without disrupting our Bitcoin mining footprint just down the road. We're partnering with our tenant's preferred engineering procurement and construction management firm and general contractor. That partner brings a demonstrated track record in domestic manufacturing capability across key mechanical, electrical, plumbing, and cooling components. That level of familiarity takes meaningful risk out of both the supply chain and the long lead equipment timeline. It also represents one more move toward shifting construction out of the field and into the factory, which cuts on-site labor and delivers a build that's faster and more repeatable. The first data hall is still on schedule to be ready for service in Q4 of calendar 2027, and for RFS, we've already placed orders and prepaid for all data center long lead items. Now let's shift to Texas. Tied to the Sandersville lease, the whole Texas portfolio of ours—718 acres and as much as 885 mw of secured and planned capacity spanning our Sealy and Brazoria campuses—is under exclusivity with that very same counterparty. Like I mentioned on July 14th, what we're in is an exclusivity window, not the finish line. What we're discussing here lines up with the portfolio dynamic we laid out to you last quarter. Sophisticated compute buyers aren't in the market for one data hall. What they want is a growth path measured in gigawatts, plus a developer they can rely on over a multi-decade relationship. Sandersville is chapter one. Having exclusivity over 885 mw in Texas tells you how our counterparty sees the remainder of our portfolio. Beyond CleanSpark's Texas efforts, there's been a wider policy conversation this week. A lot of you have probably already heard that Governor Abbott instructed the Public Utility Commission of Texas along with ERCOT to examine and confirm every data center project that's looking for a grid connection prior to allowing it to proceed. Some might interpret this as ambiguity or a near-term hurdle, but that isn't our read on it; we appreciate the Governor's careful focus on what is among the country's most vital power markets, as well as the wider consequences of what ERCOT will do next. The operational strictness and financial obligations needed to advance through the subsequent stages of development and energization in Texas line up precisely with the way CleanSpark already plans and runs. Although a formal batch process is now anticipated to run past August 7th, our campus quality, discipline, site selection, and project readiness stay the same. ERCOT has told large load applicants that final Batch Zero determinations are being pushed back, with the following significant milestone being the August 20 PUCT open hearing. Meanwhile, state agencies are ramping up to respond to the Governor's directive, which highlights the essential part our sector contributes to the Texas economy. CleanSpark's past growth achieved via counter-cyclical acquisitions gives us a solid foundation to execute a comparable playbook within the ERCOT market.
Matthew Schultz
executiveTake, for instance, the original Sandersville campus — as you might remember, we bought it while the previous owner was facing tough political and economic conditions. We think comparable chances could emerge in Texas before long. Everyone should understand one thing clearly: the exclusivity agreement we talked about earlier is still in place. We keep putting money into our Sealy and Brazoria sites, and we don't expect any shift to our energization timelines. Looking at the wider portfolio, we currently hold 1.8 gigawatts of contracted capacity, and we're quite confident that will grow past 2.1 gigawatts soon via the ERCOT review process. We're looking at multiple gigawatts of potential projects in order to grow and broaden the reach of our digital infrastructure across America. Our land and power engine has not been slowed down one bit by this lease. In fact, our confidence has only been reinforced by the deal. Land with power available is the rare resource of this moment. Finding it, getting it under contract, and developing it — that is where our team outperforms everyone. Before I hand things over to Gary, I want to spend a moment discussing our legacy Bitcoin mining operation and the role it serves as we become something very different. When a utility cares about how quickly power can be delivered, we are able to get a paying load connected faster than a typical data center developer would. That skill set is what let us put this portfolio together, and it's what will let us grow it. Over at Sandersville, we'll keep mining going so the site stays productive right up to the moment we cut over. On the financial side, mining plus our Bitcoin treasury hand us a set of levers that almost nobody else in this sector has. The HODL balance isn't just sitting there doing nothing. It's capital we can move around freely and put to work wherever it creates the most value. Practically speaking, that means we're never in a spot where we have to sell anything — not our Bitcoin, and just as importantly, not our equity. Gary's going to get into the capital strategy in detail, but the idea behind it is straightforward. The platform is powered by our mining operations, while shareholder interests are safeguarded through the balance sheet. For many decades ahead, the portfolio will generate revenue via the AI business. As is my habit, I'll wrap up by discussing our team. The grit, discipline, and talent of the group I'm fortunate enough to work with is evident in that July lease agreement. A sincere thank you goes out to everyone—from the operators located in Sandersville and throughout Georgia, Texas, Mississippi, Tennessee, and Wyoming, as well as the deal team who got this transaction across the finish line. The future success we're building has been made possible by your relentless dedication to the mission that unites us. Having said that, I'll pass it to Gary so he can take us through the numbers. Gary?
Gary Vecchiarelli
executiveThanks, Matt, and good afternoon to all of you. I'll start by walking through the quarter's figures, and after that I'll cover the new Sandersville lease as well as our capital strategy moving forward. During the quarter, revenue came in at $138 million, which was a slight rise of one percent relative to the second quarter that came before it. Average revenue per Bitcoin mined during Q3 stood at roughly $72,000, which represents a five percent drop from the previous quarter, when that metric was $76,000. Even so, we were still able to record higher revenue, since both our uptime and our hash rate rose during Q3. Gross margin for Q3 landed at about 38%, versus 40% in Q2, because power prices went up slightly, by $0.001, compared with the earlier quarter. On a GAAP basis, our net loss for Q3 was $240 million, against a loss of $378 million during the second quarter before it. What mainly drove this quarter's net loss was roughly $133 million in unfavorable mark-to-market adjustments on Bitcoin balances. By comparison, in the prior quarter we booked a bigger unfavorable mark-to-market adjustment, at $263 million. Adjusted EBITDA for Q3 came in at negative $113 million. Worth noting: that adjusted EBITDA figure does not strip out the $133 million mark-to-market adjustment. Once you normalize for those kinds of non-cash items, we actually generated a positive $20 million during the quarter. In Q3, our digital asset management activities once again produced net positive cash returns. This quarter we brought in around $8.6 million in cash, lifting our total for the fiscal year to $25.8 million. On top of that, we sold most of the Bitcoin we produced during the quarter, and thanks to our digital asset management team's work, we realized sales on Bitcoin that came in seven percent above spot. Before we move to Q&A, I'd like to talk about our capital strategy. Now that the Sandersville lease is announced and we're making headway toward announcing additional leases in the future, we're getting close to a point where our cash flows will be far more consistent, predictable, and durable. Our task in the meantime is to unlock meaningful shareholder value by continuing to educate the market about how our business is evolving and about the progress we're making toward that objective. On last quarter's call, I brought up our second-mover advantage in the AI infrastructure space. As Matt mentioned, we've watched that advantage materialize through the commercialization of Sandersville. The 20-year duration of our lease, together with its triple net structure and the strong investment-grade credit quality of our counterparty, places us in rare company among our peers; we're positioned very well to deliver on time and on budget, generating strong returns for our shareholders. Regarding how we'll finance the Sandersville project, let me be completely explicit. Our intention is to pursue project-based debt financing that covers the large majority of the build-out. Given our projected project costs of $10 million-$12 million per megawatt, we anticipate total cash required for CapEx to fall in the range of $1.75 billion-$2.1 billion. Lately, the financings we've seen have gone past a 90% loan-to-cost level. That said, the equity piece for the Sandersville project is already covered, and for Sandersville we won't be bringing in capital through equity or instruments tied to equity; another key point is that as of June 30th our total liquidity stood at $917 million, which included roughly $200 million in cash plus nearly 14,000 Bitcoin. Picking up on what Matt said, our outlook on the recent ERCOT developments is quite favorable, since we anticipate more accretive chances will emerge. Before Governor Abbott issued that directive, quite a few opportunities reached us right as the SB6 attestation deadline requirement was approaching. That says a lot, because we think there are possible sites that are either in need of capital or lack any way to obtain it. Thanks to our Bitcoin balance, we hold considerable dry powder, and we'd be prepared to give that up whenever the proper opportunity shows up. Our approach will stay aggressive while remaining disciplined as we chase opportunities that build a pipeline capable of producing meaningful returns. On that note, I'll turn things back to Harry and move us into Q&A.
Harry Sudock
executiveAppreciate that, Gary. At this point we'd like to invite the analysts to ask their questions. Operator, if you could share the instructions and handle the line-up for the question-and-answer portion, that would be great. Thanks.
Paul Golding
analystThank you very much, and congratulations on getting all the long lead time items secured for Sandersville. My first question concerns that $10 million-$12 million per megawatt CapEx range — does the infrastructure already present at the site give you any advantage that's included in that figure? How should that cost per megawatt compare with somewhere like Texas, where perhaps there's somewhat more greenfield work required, or perhaps not? Any detail you can offer would help, and I have a follow-up. Thanks.
Harry Sudock
executiveGreat, thank you, Paul. This is Harry. A really important element of our Sandersville development strategy was acquiring that 122-acre parcel a short distance away, which allowed us to construct the data center as a genuine greenfield development. As we consider every data center cost tied to the build-out, in our view those are truly apples to apples against any greenfield project. There's a quite modest accretive benefit stemming from the current deployment, tied to the substation already being constructed and energized. That factor mattered greatly in the commercialization process, since having power delivered and energized turned it into a particularly appealing campus. If you look at the CapEx budget apart from the substation itself, this really is a genuine greenfield build.
Paul Golding
analystThanks a lot, Harry. Building on that point, it sounds like you're in a strong spot to take advantage of both your cash reserves and the chance that ERCOT currently offers. When it comes to behind-the-meter versus grid-connected projects, what's the right way for us to frame that? Based on what you said about timing and SB6 and the things brought to you, it sounds like grid-connected options are coming your way. I just wanted to understand the market better and how you view that value proposition. Are you looking into behind-the-meter at all, or is that unnecessary given the grid-connected prospects you're seeing? Thanks a lot.
Harry Sudock
executiveThanks, Paul. From a big-picture economic standpoint, what I'd say is this: the data center sector is expanding so quickly, and the appetite driving it is so persistent, that hitting even the lowest or middle-of-the-road growth projections out there—whether those come from you folks or from other firms trying to gauge what the next five, 10, and 15 years of buildout might actually look like—will mean relying on behind-the-meter installations. That's a topic we're examining quite closely on our end. Our approach mirrors how we handle all initiatives: we act with careful intent, ensuring genuine linkage across the power supply, CleanSpark's own strengths, and what customers actually require. That way, every project gains complete clarity from start to finish prior to any of these solutions reaching the market.
Paul Golding
analystThanks a lot, Harry.
Greg Lewis
analystYeah, thank you. Good afternoon, and I appreciate you taking my questions. You know, we recognize that the opportunity in Texas offers a lengthy favorable trend for you folks. You've got additional sites as well, correct? There's Wyoming, Georgia, and Tennessee in the mix. I'm just a bit curious—considering that Texas appears to be somewhat stalled at the moment, might we see a few of those other places shift into greater prominence? Have customers been displaying heightened interest in them, especially after what occurred recently? Tennessee looks like it's turning into a central hub. Clearly, you already have that extended agreement in Georgia. I'm just wondering how you're approaching that 340 mw sitting out there throughout those states.
Matthew Schultz
executiveGreg, I really appreciate that question; Matt here, and I'll handle it. Given how large our Texas assets are and how far along our talks have gotten — on substation permitting and the Batch Zero base load process we're in — I wouldn't say anything is going to jump the line, exactly. What I can tell you is that we've had a VDR open to a number of parties over time, and interest in assets such as Washington, Georgia, for instance, is an extremely compelling opportunity; today it's 86 megawatts of energized capacity. That said, at MEAG's request, along with a local utility, we've already submitted a line study to expand it by up to 500 mw. As those talks have moved forward, we've also locked in options on several hundred acres next to the existing substation to support that build. On top of that, you're right. We have 100 mw in Wyoming. In Jackson, Tennessee, we have 60 megawatts. We have additional capacity in Ripley, Tennessee, as an example. I'd say that for those looking for 2027, 2028 RFS, the value of the assets outside Texas rose considerably because of the uncertainty around the timing of this audit period that Governor Abbott pushed forward.
Greg Lewis
analystOkay, super helpful. Thank you for taking my question.
John Todaro
analystHello, everyone. I appreciate you taking the time for my question. Nice work on everything that’s been accomplished. You walked us through the slides. We’ve had quite a few questions from investors, or I believe there’s simply some slight confusion regarding Texas here. Could you please lay out very clearly the Texas capacity you haven’t signed yet? What still requires any approvals tied to ERCOT, and which capacity and sites require none of that, so you’re able to go ahead and sign them?
Harry Sudock
executiveYes, John, of course; this is Harry speaking. Our approach to buying the remaining two Texas locations was highly intentional. Risk management is what we prioritize above all else in this company. The method we used to obtain those projects aligned with that same approach. With the Sealy asset we purchased, crucially, that property already had ERCOT's approval secured back in 2025. That situation shifted in January of 2026, when Batch Zero was introduced, strictly regarding scheduling and what was required. Right away, what that location got was Batch Zero go status, meaning the base load designation. Although we still need ERCOT's final determination before we can interconnect that site, it has received every green light at each stage, even though the final check mark is required to move through that last energization gate. The other one is located in Brazoria. There, the 300 megawatts of extra phase I capacity function in practically the same manner as Sealy, except that they received go status during 2026 instead of a 2025 overview. The other 300 in Brazoria represents the portion of megawatts awaiting the final determination between base load status and studied load status, even though we still conducted a highly thorough transmission line assessment prior to deciding to buy that location. Given the transmission line capacity we examined, we recognize that site as having an enormous amount of capacity, both upstream and downstream, inside that portion of the utilities system. We remain very optimistic. That is the portion of the load for which we are still awaiting base load versus studied load status.
John Todaro
analystGot it, thanks — that's really useful. And just to build on that regarding what we're seeing on the demand side: Matt, you touched on this somewhat. I was just curious whether any hyperscalers or chipmakers have grown more aggressive when evaluating locations. Are there any that perhaps have eased off and turned less aggressive? Any detail you can offer there.
Matthew Schultz
executiveThere's absolutely no slowdown at all. Over the past 48 hours, the volume of incoming inquiries has really picked up, and a lot of them are asking about whether any exclusivity exists on the Washington project. I'd say that one has drawn the most attention recently, simply due to its ability to scale up quickly.
John Todaro
analystGot it. Very helpful. Thank you, everyone.
Harry Sudock
executiveThanks a lot.
Brian Dobson
analystHey, appreciate it. Nice work on the deal once more. So, when you look at that memorandum from Greg Abbott, would you say it signals what could happen in other big — let's say utility — regions? And do you figure that, in the end, it gives an edge to incumbents like you?
Harry Sudock
executiveSure. Let’s address the latter portion first. On the tenant side, demand keeps coming without letup, and the well-established firms with lengthy histories of sourcing and building energy and infrastructure assets will keep emerging as the best of the best moving forward. As for how many of these audits or assessments spread, I’d call it fluid. Governor Abbott, in my view, has before him the biggest interconnection request backlog anywhere in the country. What he does will be shaped by conditions unique to Texas and by the ERCOT-specific factors affecting that grid. In the end, I believe one point isn’t yet widely grasped by the general public: the economic upside that data center projects bring to municipalities, counties, and states nationwide, along with certain technical details of how data centers get deployed. The way these facilities run has improved technologically to a striking degree compared with 20 or 25 years back. Water consumption has been driven down to virtually nothing. From a land-use standpoint, the physical area on which these data centers sit keeps getting smaller. While members of the public are still moving along a learning curve, I think that 5 to 10 years from now, we’ll view this as a second industrial revolution here in America. If I can jump in, Brian, to build on what Harry said regarding the latter portion of your question about established players: I’ve had substantial dealings with senior site selection executives at several hyperscalers. The general agreement seems to be that much like Las Vegas residential real estate two decades ago, in Texas many developers—or many hyperscalers—are running into people who perhaps placed a deposit on land near transmission lines and sought status in ERCOT approvals. What we observe today is that with SB6 now in effect, you must back up your words with actual capital. Many of these projects that might have had genuine viability have largely fallen away, since the necessary financial backing isn’t there. Given what we’ve heard from communities and from ERCOT, possessing the balance sheet to firmly support the guarantees and the attestation process leaves us in a highly advantageous spot going forward.
Brian Dobson
analystYeah. In the end, that likely encourages more responsible development. When you look at your portfolio, are there any areas you'd want to move into over, say, the medium term, without getting too specific — I get it?
Harry Sudock
executiveYes, thank you, Brian. One thing we take a lot of pride in, I'd say, is how dynamic and flexible we are. The chance to pursue these power projects really exists at the project level, which is where the major opportunity evaluation work gets done. We've got the diligence team and the relationships needed to succeed in basically every American power market as it stands right now. Where our special sauce really lies, from where we sit, is the ability to absorb a huge amount of deal visibility and be the best selectors within that deal volume, so that we can be hyper surgical and specific about where we choose to make selections. Much of that isn't tied to region or jurisdiction; it's even more granular than that.
Brian Dobson
analystGreat. Thanks very much.
Harry Sudock
executiveThanks, Brian.
Mike Colonnese
analystHello, and good afternoon, everyone. Thanks for fielding my questions. To start, I'm wondering — given what you've heard from the tenant over at Sandersville — would you characterize securing a final approval for Batch Zero covering Sealy along with Brazoria phase I as a prerequisite before that counterparty would put pen to paper on a lease? Or would you count that among the prerequisites? Are there additional development milestones that the counterparty wants to see hit at either Texas location that CleanSpark would have to deliver before they'd proceed?
Matthew Schultz
executiveHey there, Mike. Appreciate you asking. Matt here. To offer a bit of context, we had opened a VDR that covered several of our sites, and we brought in a number of major players to that VDR so they could run an analysis. What caught us off guard wasn't hearing, "Hey, I'm interested in site A or site B or site D," or whatever it might be. The answer we got was, "I'll take it all." Our Sandersville tenant was part of that VDR too, and given how the negotiations went and their grasp of the tailwinds we delivered to the Sandersville project, they pushed hard to obtain that exclusivity and optionality going forward. Exclusivity with them remains in place. We engage with them constructively every single day. It's fair to say that if this were to slip past — should we receive bad news at the August 20 PUCT meeting — there is such a large amount of pent-up demand for energized megawatts that, in my view, if they were to walk away, another company would be racing to the gates before long, on account of the asset's quality, on account of where things stand in that Batch process, and also on account of how far along the work is that we've completed to get those sites pad ready.
Mike Colonnese
analystThat was really useful context, Matt. I was wondering if you two could share a bit more detail about the kinds of opportunities showing up in ERCOT right now. Perhaps a few of those projects that aren't fully funded or aren't quite legitimate. When it comes to the sites being brought to you, which traits would make you want to chase them most?
Matthew Schultz
executiveExcellent question, Mike. A number of the things we reviewed previously and decided against didn't meet the high standard that I believe CleanSpark holds itself to. Perhaps the power involved was tied to a subsequent batch process, so we declined — yet once that SB6 window drew nearer, quality assets began picking up speed, simply because people lacked either the time or the money to cover those first payments. As I see it, nothing shifts on our end given Governor Abbott's stance; our approach to choosing sites will stay just as strict. They have to satisfy our requirements. This came up during the Bitcoin era, Mike, if I recall — the point being that we'll seek out top-tier assets, and we turn things down far more often than we accept them.
Harry Sudock
executiveInstead of locating land that already has power and then attempting to force something into that space, our approach is to seek out the opportunities aligning best with the demand profile we observe.
Mike Colonnese
analystFantastic. Thanks, Matt. I appreciate your time on my questions.
Nathan Frankovitz
analystHello there, good afternoon, everyone; Nathan here, dialing in from Cantor Fitzgerald on Brett's behalf. Congratulations once more on the transaction. Matt, something caught my attention when you said Bitcoin mining's function goes beyond just building the portfolio — it could also act as a point of distinction as you continue growing it. Could you explain how mining could be integrated into future site acquisitions and development? Would it look like Sandersville, where there's a separate standalone data hall apart from the data center, or are there other setups you'd consider?
Matthew Schultz
executiveYeah, excellent question. Thanks for being here. Let Brett know he's not off the hook for skipping this. What I find most interesting is that whenever a utility has electricity to spare, or when additional generation gets brought online, those loads are often initially presented to the market as interruptible. You can volunteer and say you'll accept that power while allowing up to 90 hours of curtailment each year, with the understanding that after we prove the new generation is sustainable, it converts into a fixed or firm load. Bitcoin mining gives us the means to do that. On top of that, when there's dependable capacity sitting there that could be turned into revenue right now for the local utility and the surrounding community, the identity of whoever settles the electricity invoice isn't their concern — what matters is that the bill gets settled. We're able to install modular immersion-cooled Bitcoin mining equipment in under 90 days and begin earning off those megawatts that would otherwise sit unused. There's a playbook we've used in plenty of other markets: buy up enough land nearby, then take your time constructing a data center that matches the end-use tenant's basis of design, and flip the power across once that facility is finished, whenever that happens. Worth remembering that on a lot of these modular builds, the CapEx needed for that step has already been laid out. Once we exit Sandersville a few years down the road, the immersion-cooled pods and the ASICs get a second life — repurposed to clear the path, so to speak, for whatever comes next, should those chances for interruptible or early energized assets present themselves.
Nathan Frankovitz
analystThanks for taking my question.
Stephen Glagola
analystHello, and thanks for the questions. I've got one for Matt and another for Gary. Matt, could you perhaps give us additional detail regarding the anticipated schedule for getting clarity on the audit process? In your prepared remarks, you pointed to the August 20 PUC hearing as a critical date. What ought investors to expect to find out by that point, and what upcoming milestones should we be monitoring? Gary, you brought up aiming for high loan to cost on the project debt side. It would be helpful to dig into that further — what are you currently observing in the funding markets when it comes to lender appetite and the cost of debt, and possibly what has shifted across the last few months? Thank you, guys.
Matthew Schultz
executiveYeah, I appreciate you asking that. Regarding Texas, honestly, the right response is that we simply don't have the answer. There isn't much certainty about what happens after that PUCT meeting on August 20. What I can share is that from the outbound communications we've made, and from the dialogue we've had with both sets of CenterPoint, the governor along with the governor's representatives are pushing hard to send a message to the market that the data center portion of the loads matters to Texas. It's a priority. If we're being honest, the difficulty here — and this is purely my own speculation — is that many of the objections you're hearing about in Texas seem to stem from the 765 kV high tension lines that have to be forced across farmland or other areas. We're really lucky because the properties we own don't require that. To me, that looks like something of a differentiator. That might be accurate; it's just what we're hearing from the community relations people we have on the ground there.
Gary Vecchiarelli
executiveStephen, on the financing side, let me say this: if you look at a few of the deals done lately, you'll notice that covering more than 90% of cost through debt is quite typical, and that's what we're aiming for. Naturally, when debt covers a larger share of cost, your internal rate of return climbs, since you're putting in fewer equity dollars for the project; clearly, we're after the strongest returns we can get; our goal is above 90%; as far as demand goes, we've kept a very close watch on the market, and perhaps you caught it on the wire this morning, perhaps you saw Google, or Alphabet, attract interest of roughly $115 billion in demand for a transaction of only $25 billion, correct? That works out to something like four and a half times oversubscribed. For us, that signals plainly that demand is still robust. Although spreads have grown wider over recent months, we've watched those hyperscaler bonds tighten when bid, by as much as 25 bps, within just the past week. Markets can be somewhat fickle, we're monitoring things closely, and we feel fairly confident that our targets are within reach.
Stephen Glagola
analystGreat. Thank you.
Bill Papanastasiou
analystGood evening, gentlemen. Thanks for taking my questions. Congrats again on the deal; in the remarks, there was mention that the team is looking at new opportunities in the multiple of gigawatts across the country. Can we just double click there? Where do you see the most value today?
Matthew Schultz
executiveHey, Bill. Thanks for the question. I think what you've probably known about CleanSpark since the day we sat in the van when we had two sites way back in the day, kind of talking about the path forward. We've been very disciplined. One thing that sets us apart, I believe, is this: when we cite a 2.1 gigawatt pipeline, or the 1.8 gigawatt contracted pipeline, what we're actually disclosing is what has been contractually committed to the company, backed by some degree of certainty that lets us move ahead. Duncan and his team, as of the last time I checked, had somewhere between six and a half and seven gigawatts of projects undergoing active analysis and development. A lot of our competitors would count that within their pipeline. We take a very cautious approach on this point, since certainty matters to us. It's somewhat reminiscent of the guidance we used to give on hash rate in our earlier business. Our track record shows we met our targets, lifted them, and met the new ones too — we weren't a business that fell short and then offered justifications. When we discuss these matters, we take a cautious approach. As for regions, I can share that right now we're actively pursuing opportunities across each of the four time zones.
Bill Papanastasiou
analystThat's much appreciated. Matt, I recall the site tour quite clearly. I'm eager for us to spend additional time together once more. Next, thank you for the news regarding the exclusivity agreement. I'm just wondering — has any conversation taken place with the tenants about adjusting the deadline for that exclusivity, given this indefinite postponement of Batch Zero? Have they made their position known in light of these developments? Is there anything you can share on that front?
Matthew Schultz
executiveWhat I'd say is that the exclusivity still holds. Talks have genuinely carried on without interruption; these projects are what they want. Moving ahead is what interests them. On our end, there's no worry about somehow forfeiting that should it continue for an unspecified length of time, since, frankly, Bill, what we're witnessing is rates climbing. Terms keep getting better, as we see it. Were this to drop away, for some reason or any reason at all, we would again conduct a market-clearing exercise, and given the demand before us, chances are we'd generate still more value.
Bill Papanastasiou
analystThanks for that vote of trust. Appreciate it, Matt.
Henry Hearle
analystThanks to our operator, and hello everybody on this call; Henry Hearle here, sitting in for Nick. Once more, congratulations on the Sandersville lease and on securing those long lead items with payment up front. This really builds on something I asked earlier. Was there, for the Sandersville tenant, also a chance to secure exclusivity across Atlanta Metro, Washington, Georgia, Jackson, Tennessee, or Cheyenne, Wyoming — or did you only put Texas in front of them? Thanks.
Matthew Schultz
executiveHonestly, at the time we filled the VDR, what went in were the three sites they latched onto right away. Like I said when answering something earlier, every party who came into the VDR asked for D, all of the above. Clearly, since Sandersville is power that has been running Bitcoin mining at 11x a hash quite successfully, and since it is enormously popular locally, with fantastic community backing behind us, that was the site they wanted to lock down at this moment, because it delivers Q4 RFS on the first data hall. Texas, plainly, mattered greatly since it accounts for nearly 900 megawatts of power that we hold, and as Harry noted when he spoke, there is a strong level of certainty that it qualifies under that Batch Zero base load certification; those were the properties, or rather the projects, that we presented. Only afterward did we begin discussing Washington, Georgia, and the response there has been a flood of inbound interest. Given how we have described our portfolio and how openly we have shared which megawatts we control and in what locations, a lot of these developers came to us on their own and asked, "Hey, what about that?" All I can say is that as far as the Sandersville tenant goes, every opportunity we placed before them, they grabbed.
Henry Hearle
analystUnderstood. I appreciate the detail you provided, Matt — that helps a lot. Beyond Governor Abbott's pause, my understanding is that on July 27th Austin County passed a moratorium applying across the whole county to AI data centers. In theory, would the Sealy site be affected by that? Hearing anything about your engagement with the county would be quite useful. Thank you.
Harry Sudock
executiveYes. The key point is that it's temporary, and in our experience a huge share of these efforts by counties, cities, and local bodies to draft zoning rules have been struck down by courts. At the end of the day, we continue to be very constructive with the community. Our view is that reaching a positive resolution is always the preferable route, and that's how we've operated for a great many years. My sense is this will turn out to be a fantastic success story in which the community's leaders raised some further questions. Those questions will be answered for them with outstanding results, and we'll be in a position to move forward together constructively very soon.
Henry Hearle
analystHenry Hearle here — appreciate the added detail, Harry, and keep wishing you all the best going forward.
Harry Sudock
executiveThank you.
Matthew Galinko
analystHi there, good afternoon everyone. I appreciate you taking the time for my questions. Could you perhaps provide a bit more detail regarding where things stand with the digital asset management strategy? Does operating it remain a priority, or is your attention now fully pivoting toward the transition?
Gary Vecchiarelli
executiveHi Matthew, I appreciate you asking that. Our approach to the Bitcoin HODL balance and how we manage digital assets has stayed extremely steady, and I want to restate that point at this moment. On our balance sheet, there are just about 14,000 Bitcoin, and as we've repeated many times, we hold no ideological attachment to that Bitcoin balance. Our approach is highly strategic, and we view it as a capital asset, with every intention of deploying it that way. So what does that actually mean? While our belief is that Bitcoin's value currently offers more potential gain than potential loss, we'll keep putting the Bitcoin to work in a few ways. First, we generate cash by using covered call derivative strategies. In what I said earlier, I noted that fiscal year to date, this strategy alone has already brought in close to $26 million in premiums, and that even lets us remain above spot price, since at present we sell most or all of the Bitcoin we produce in order to cover operating expenses. Second, from two angles, it serves as an excellent source of capital that isn't dilutive. For one, we're able to borrow against it, because as of 6/30, we had $400 million that was undrawn on the Bitcoin-backed lines of credit. For another, as I mentioned in my comments as well, we're prepared to give up that Bitcoin balance when highly accretive opportunities appear in the market, particularly since management now believes our equity isn't receiving a respectable valuation. Recognizing that we want our cost of capital to remain low, we'll turn to the Bitcoin balance to help hold that cost of capital down while also driving shareholder value.
Matthew Galinko
analystOkay, thanks. So for my follow-up question, how would you view your mining equipment if the economics become worse, especially after the halving? From what I understand, you regard that as an asset for acquiring land and power. If conditions shift somewhat, do you still consider it a helpful lever? Is there any situation in which you would step back from that approach? Thank you.
Gary Vecchiarelli
executiveYeah. Appreciate you asking that. Honestly, if I possessed some fortune-telling device and could predict the direction of Bitcoin mining economics, chances are I wouldn't be here in this seat right now. Forecasting this industry is genuinely tough. What I can share is this: our fleet ranks among the most efficient anywhere in the world, and that let us run at a 38% gross margin during what was, in other respects, among the hardest stretches Bitcoin mining has ever seen. Where things stand 24 months down the road, I can't say. But I will say our attention is on putting capital to work so shareholders see meaningful returns. At this moment, the best possible use for that capital is AI data centers plus scouting out land and power, and that happens to be something we excel at. My view is Bitcoin mining becomes the route to that destination, helping us arrive there.
Logan Hennen
analystHey everyone, Logan speaking — I'm stepping in for Mike. Thanks for giving us the chance to ask a question. We just have one today. Right now, we're about 20 to 25 days into that exclusivity period. Would you be able to take us through what was learned from the Sandersville leasing push, and how those takeaways are being applied to the process now underway with the Texas sites? Also, how does the 6.5 or 7 gigawatts figure fit into that picture? Thanks so much.
Matthew Schultz
executiveYes, I appreciate that question. Thank you. What I'll do is share the feedback their team gave me once the lease was successfully executed and we moved into exclusivity. It largely reflected CleanSpark's DNA, our track record in energy markets, and a shared grasp of how those markets function. How we structured the project is something we haven't discussed much. We hold 40 acres with 250 megawatts mining Bitcoin, and before we signed an agreement, the community came forward and helped us secure an additional 122 acres. On top of that, the community stepped forward and said, "We'll help you handle the easements and the powered pathway so power can be moved from your current site over to the new one." Having that kind of cooperative, productive connection with the utility, the community, and the policy folks involved with and near the project gave us real momentum. What the tenant said to us was, "There's something different about your team — they genuinely get energy markets, they get how leasing works, and the whole thing felt collaborative." Of course, the headline lease figures are something everybody cares about. If you compare a full 100% NOI structure against a modified gross arrangement at 80% or 85%, the headline revenue figure matters far less; we made clear to them which elements were critical on our side. Give them credit — they bargained in good faith, working toward an agreement that carried real value for them while still meeting every objective we had. Then the Texas opportunity came into view, and that exclusivity agreement echoed a lot of what had already been set out in the Sandersville lease, since we had created a reference point — and I'll borrow their wording here — as they described moving ahead with CleanSpark serving as a development partner. Their intent is to treat this as something they can rinse and repeat. That deal's execution, and the trajectory we see from here, gave us a lot of faith in the group we have in place.
Logan Hennen
analystThank you. Appreciate the color there, guys.
Jon Hickman
analystHello there. Could you expand a bit on precisely what needs to be handed over to the other party under this triple net lease arrangement?
Matthew Schultz
executiveYeah, great question. The initial lease contemplates a powered data center.
Harry Sudock
executiveWe also came to an agreement to carry out some TFO work, which went beyond the initial lease. Since this is a genuine triple net arrangement, after we hand over the keys, we essentially step away. We don't have to mow the lawn or replace light bulbs. Every operational expense is passed on to our tenants.
Jon Hickman
analystYou're responsible for the maintenance of the power that's being delivered?
Harry Sudock
executiveNo, Jon. Our job is to provide certainty for the data center once construction wraps up. That covers getting power from the substations that already exist over to the data center, though it doesn't cover keeping that power infrastructure maintained on an ongoing basis, whether it's the part in between or at the substation itself. On the data center side, then, you can view this as covering everything from ground level up through the shell and into the MEP and gray space of the core — but from a leased asset standpoint, not anything within the white space. As for one final layer regarding risk mitigation, I believe we mentioned this in our prepared comments, but it deserves emphasis: the EPCM contractor we chose also manufactures a lot of the mechanical, electrical, plumbing, and cooling components; they've got a track record of successful execution with this end-use tenant. It came about as an introduction, and it provided us with a great deal of certainty around execution timelines and compatibility with the end-use tenant.
Jon Hickman
analystAll right. Regarding community assistance, historically the community enjoyed an advantage where electricity could be cut off when necessary for various reasons. Now that the data center is being established, that will no longer apply, and yet they continue to back the initiative?
Harry Sudock
executiveYes. Jon, grasping a few of the electricity market forces at work in that region matters a great deal. What a 20-year long duration arrangement like this actually provides is predictability, plus the chance for the utility to obtain power while knowing far better how it will be consumed daily and each quarter. They do give up a portion of the real-time demand response abilities that a Bitcoin mine would have offered, yet the tax base improves substantially. A data center brings higher employment density than a Bitcoin mine does. In the end, the people in Sandersville, and I believe plenty of other communities nationwide, strongly want those outcomes.
Jon Hickman
analystWill there ever come a moment when the identity of the counterparty gets revealed to us?
Harry Sudock
executiveAs with a lot of the transactions you've observed, Jon, they reference a tenant covered by an NDA; what we're describing is an AI data center built for high-performance compute, using proprietary technology, and our tenant preferred to stay relatively unidentified. That isn't unusual in this sector. What I believe matters here, and you're welcome to Google it, is that this is a global technology company with a high investment grade rating. That's the most they've permitted us to say. The high investment grade, in my view, is truly what sets it apart. No credit wrappers exist. No equity piece was surrendered as a backstop. Financing rates come in favorably since the tenant's credit rating ranks among the highest in the cohort. We're at ease with what we've disclosed, and they've requested that we leave it there.
Harry Sudock
executiveWe appreciate you being with us on this call once more. We’re eager to keep the lines of communication open and to bring you further updates over the quarters ahead. Keep watching, as additional advances and notable milestones lie in front of us at CleanSpark.
Operator
operatorLadies and gentlemen, this concludes today's call. You may disconnect.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete CleanSpark, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to CleanSpark, Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in CleanSpark, Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.