Core Lithium Ltd (CXO) Earnings Call Transcript & Summary

October 27, 2023

Australian Securities Exchange AU Materials Metals and Mining earnings 56 min

Earnings Call Speaker Segments

Operator

operator
#1

Good day, everyone, and thanks for joining the conference call on Core Lithium's September Quarterly Report. <<operator_script>> At this point, it's my pleasure to hand things over to the CEO, Gareth Manderson.

Gareth Manderson

executive
#2

Thanks so much for making time this morning for Core's quarterly — the first one reported against guidance, and, I'd argue, the first quarter of operations, or ramp-up of operations, at the Finniss site, Grants, and the concentrator. Here with me is Doug Warden, our CFO, who'll also be around to field questions at the end. I'll walk through the slide deck we put out earlier this morning, then we'll open it up for questions. So this is the first portal where we've managed integrated operations, thanks to commissioning the concentrator and establishing mining operations — essentially pit through to port. And it's the first period in which ore has flowed steadily to the plant — sorry, steady ore delivery into the plant following last year's wet season. We're focused on 3 things in building the business around Finniss operations: the Grants mine, developing the BP33 project, and exploration and growth. Highlights for the quarter include an 8% rise in total material moved, spodumene concentrate output of a little over 20,000 — 20,692 tons — and recoveries that improved to 50% as the quarter's average.

Gareth Manderson

executive
#3

I'll walk through some of the specifics on recoveries, since I know a few questions will come up there. The prepayment tons have also been finished. As you may remember, we undertook some prepayments so we could manage cash flow and secure or manage risk while our operations were starting up. Those are now complete and fulfilled. We've in fact begun fulfilling volume into our offtake — our long-term offtake agreements with Ganfeng — and a solid average realized price at delivered grades, so not referenced back to SC6, but at delivered grades of $2,550 per ton. As I mentioned, BP33 is coming along well. The feasibility study is underway and early works are in flight, and we have some photos and a bit more information toward the back end of this morning's presentation. And most pleasingly, after the quarter, we received the BP33 measured and indicated resource upgrade of 89%. That lifts confidence and in fact supports the mine plan and feasibility study work currently going into BP33. The cash balance at quarter end stood at $202 million, which includes the placement and SPP raise from earlier this year, and that was aimed at giving balance sheet flexibility and preserving our options, preserving our strategy to keep developing the BP33 project and the exploration program while the Grants mining operations are starting up.

Gareth Manderson

executive
#4

During the quarter, we recorded 1 reportable injury — a hand injury that needed some medical treatment, not lost time — and we've started critical risk management. That involves understanding the risks around fatality and making sure those controls are in place, and engaging people in identifying and applying those controls while they're doing work at the site. In the quarter, we placed a strong emphasis on bettering our mining and processing operations. So at the mine, you can see an 8% increase in TMM, and also, very pleasingly, through blasting improvement and dig unit availability improvement, we've been able to achieve record ore extraction at the end of September. This meant that during the quarter we saw consistent ore feed, which has let us be a little more strategic in how we present ore to the concentrator. We've also installed a second radar to improve monitoring of pit wall stability at Grants, and a significant amount of work has been done on wet season preparation — haul road upgrades, water storage facility, and new water storage facilities and improvements, and new dewatering equipment. At the end of the quarter, we had 165,000 tons of ore on the ROM pad, and that's rising to well over 170,000 — actually closer to 180,000 as we speak in the current month.

Gareth Manderson

executive
#5

This is something we're focused on as we head into the wet season in the Northern Territory late in this calendar year. To make possible some of the gains we've been pursuing at the concentrator, we've held some very productive talks with our offtake partners. One of them — we have in fact locked in and settled an arrangement to go to a 4.5% grade, and the other is nearly done being finalized. Later in the presentation, I'll walk through a bit more detail on plant recoveries and how that ties into this program. With that, I'll hand things over to Doug to take us through the financials.

Douglas Warden

executive
#6

Thanks, Gareth, and good morning, everyone. I'd like to spend just a few minutes giving you some additional detail on how costs and cash flow came in for the quarter. C1 unit costs for the September quarter came to $904 a ton, which was broadly in line with the prior quarter. One thing worth highlighting is that this C1 cost is net of $985 a ton in mining costs that were deferred to inventory during the quarter. Essentially, this reflects a build of all stocks on the ROM pad as we get ready for the wet season, and we expect that build to continue over the coming couple of months as we head toward the end of the calendar year. So cash costs prior to this inventory adjustment came in at $1,889 a ton, as the table shows. As you'll see from the quarter's unit costs, they were broadly in line with the previous quarter even though production was 40% higher. That isn't due to our cash costs being significantly higher — it's because the strip ratio for the September quarter was broadly in line with the life of mine average. As a result, most of those waste costs went through the P&L and therefore through unit costs.

Douglas Warden

executive
#7

In the June quarter, by contrast, the strip ratio stood well above the life-of-mine average, since we were carrying out more of a cutback, and as a result a far larger share of the waste costs was deferred onto the balance sheet, to be amortized afterward across the life of Grants. Operating cash flow — or rather, cash outflow — of $26 million was affected by shipment timing, with roughly 8,500 tons of concentrate sitting at port as of 30 September, which formed part of the early October shipment. Along with that came a repayment of almost $28 million to Yahua tied to a QP adjustment. That stemmed from the prepaid arrangement and arose because the spodumene price dropped significantly between the prepayment date and the close of the QP. Also left out of the cash flows connected to this prepayment was the 13,000 ton shipment made in early July. Those funds were received in quarter 4 of FY '23. Lastly, CapEx for the quarter came in at slightly under $20 million, including $8.5 million for the BP33 box cut, while the rest was tied to our Finniss operations, which comprised $3.3 million for water storage facilities, $2.4 million for site establishment costs, and $2.5 million in deferred stripping.

Douglas Warden

executive
#8

That covers everything I had. I'll turn it over to Gareth for the closing.

Gareth Manderson

executive
#9

Thanks a lot, Doug. I'd like to direct everyone listening on the call to Slide 8 in our materials, where you'll notice the trend line concerning both production and recoveries. I wanted to highlight that there are two areas of focus related to that. The first involves reviewing our commercial agreements, and that's likely the smaller of the two. The bigger one is really examining the operations and beginning to fine-tune and enhance them. A number of items have emerged through these trials, and I'd simply note that two factors are driving the variability you observe in the quarter and the recovery at 50%. First, a set of trials has been conducted. Second, we've ensured that all of our shipments have satisfied our customer specifications. We've since managed to agree on an approach with our customers whereby we could lower grade and raise lithia units, so the customer benefit is more lithia units overall, and the reduced grade allows some of the improvement work we're currently driving in the concentrator. So from a recovery standpoint at the facility, we've accumulated the ROM and are now reviewing feed blending and management options.

Gareth Manderson

executive
#10

We've started a set of crushing trials, and we've shifted the plant's feed size from 6 mill to 10 mill in order to cut down on fines. We've also examined the set points for how the plant is run, and in fact we've kicked off a few debottlenecking-type projects aimed at raising throughput. So you can see where our attention is: preparing and managing feed, optimizing the plant, and debottlenecking to lift the rate. Basically, what that has meant is that on an average basis, quarter to quarter, we've seen a mild uplift in recoveries. But what I'd say is that toward the end of the quarter and then into October, we've seen a pretty nice improvement as we begin to settle on what our operating parameters may be going forward to match the commercial agreements and the plant improvement. And in the first couple of weeks of October, we're averaging around 55%, and rest assured, our improvement program will carry on into the months ahead. So if I have to sum all of that up, we're saying that for the full year, our guidance is unchanged. We expect to be on track to hit production unit costs and CapEx guidance for the financial year.

Gareth Manderson

executive
#11

We are going to keep applying that model of integrated operations all the way from the pit to the port. And a great deal of effort is going into preparations for the wet season too. So ROM stocks have been building, and they will keep growing through to December. Then, once the wet season begins to arrive, we will alter the mining sequence and move toward more development work in the upper benches, which we expect to be affected less by the wet weather. And work on BP33 is carrying on, along with the exploration program. So let me walk through the slides. If you look at Slides 10 and 11, you can see how BP33 is progressing. The box cut currently excavated stands at 340,000 -- 354,000 tons out of a total of 393,000 tons. So excellent progress on cutting the box cut. And you can see the wider end, or the lower end, of the box cut there. So there is roughly another bench to go. On the slides on -- sorry, on the photos on Slide 11, you can see the first footing pores for the tunnel liners in the upper section of the decline.

Gareth Manderson

executive
#12

So that's the drop that carries us through to the portal. Then, on Slide 12, the slides or photos there show you pictures of the tunnel liners delivered to site and ready for assembly. And the photo on the right shows the steelwork reinforcement that goes into the tunnel liner footings. On Slide 13, very pleasingly, after the quarter in October, we could announce that the measured and indicated portion of the resource for BP33 has risen to 89%. Since then we've also seen grade go up and a slight rise in volume. But it's really more about the grade and the confidence. That's the substance of that announcement, which I think gives a great runway for the mine plan and the feasibility study due for presentation and contemplation by the Board to FID in quarter 1 calendar year next year. So in summary, our focus is on safe operations, particularly with establishing critical risk management — so what are the fatality risks associated with the work we do, how do we make sure the right controls are in place and in people's minds as they perform each and every task.

Gareth Manderson

executive
#13

We're putting a lot of effort into hitting the spodumene production guidance, and I'm genuinely pleased and very impressed by what the mine team and the concentrator team have managed to accomplish in boosting productivity. By doing that, we'll fulfil our offtake contracts — meaning our agreements with Yahua and Ganfeng. The exploration plan keeps moving forward. We remain on schedule to finish it. As you'll remember, the main emphasis of exploration is locating and enhancing our mines, especially early in the planned period — BP33 and Carlton above all — and you've seen some announcements on that front. The underground feasibility study at BP33 is ongoing. We'll be looking at fine-tuning. So, drawing on what the exploration program gives us, we'll keep fine-tuning and figuring out the strategy for the tenement packages we hold across the territory and how we might sequence options going forward. On the Community Grants Program, we're now in round two, and I'm really pleased that over a dozen community groups have gained from that very modest ask. It's a wonderful sort of win-win for Core to be involved in the community and to back some of those local community groups.

Gareth Manderson

executive
#14

And we're taking lessons from this initial stretch of operations. So be it the mine, be it the concentrator, be it BP33 early works, what are we learning this month, and how do we do better next month, especially when it comes to safety. And naturally, the DNA of the business. That means a modern approach to managing the workforce so we get safe, sustainable and cost-effective production outcomes, and we'll keep building an experienced, capable team to deliver for our shareholders. So with that, I'll stop there and open things up for questions, please.

Operator

operator
#15

<<operator_script>> Our initial question is from Jonathan Mannes at Bank of America.

Jonathan Mannes

analyst
#16

I just wanted to ask about lowering your grade from roughly 5.5% to 5%, but there aren't any cuts on the operating cost side. Does that kind of suggest that going forward, we're sort of looking at operating margins staying a bit under pressure while we work through our recovery improvements? And any color you could give on when operating costs might begin to move in step with the grade reduction.

Douglas Warden

executive
#17

Yes. Thank you for that question. Yes, so the point you're raising concerns the $902 C1 cost compared with $904. Right. What it comes down to is the stripping matter I mentioned earlier when I gave my opening remarks. Basically, during the June quarter, the strip ratio for that period ran well above the life of mine average. It was essentially twice — in fact more than twice — the life of mine average. As a result, the costs tied to that stripping were, for the most part, deferred onto the balance sheet. So here's how to think about it: the June quarter gained from this, since our policy is that when the strip ratio sits above the life of mine average, we push cost onto the balance sheet. And when it is below, or right at, the life of mine average, those stripping costs go through the P&L. That means the June quarter gained because stripping costs were deferred, while the September quarter came in roughly consistent with the life of mine average strip ratio. And so those stripping costs went through the P&L. That is the primary explanation for why you did not observe a decrease in the unit cost even though production came in 40% higher.

Douglas Warden

executive
#18

Is that what you were asking about?

Jonathan Mannes

analyst
#19

Yes. No. Understood well. My other question concerned your capacity to keep putting high-quality goods onto the market. From several of your peers, along with industry contacts, I've been hearing that DSO and the lower-grade items are beginning, you know, to turn unfavourable, because of the conditions we're observing in lithium ore and in conversion markets. I'm simply wondering whether you can offer any colour regarding your willingness to keep accepting that product.

Gareth Manderson

executive
#20

Yeah, look, I think that's a reasonable question. There are several value levers for Core in that area. One is that it clearly gives us extra capacity in our tailings facilities. Extracting that material lowers the requirement for raising dam walls and for capital expenditure there. And then, probably more significantly, and getting to your point, it's a product that carries some value in the market. It has up to now, and we continue to see interest in that product, but we're conscious that as spodumene concentrate prices decline, it could come under pressure. So we're monitoring that and we're — you know, responding to demand and pricing. So if we can't obtain the right kind of pricing for it and it doesn't make business sense, we won't sell that product into the market.

Jonathan Mannes

analyst
#21

Got it — let me squeeze in one more question if that's alright. So since you've reworked a few of your offtake agreements so they can accept the 4.5% product, should we be expecting you to stay near 5% for the remainder of this year and on into next year? Or do you believe you'll keep lowering that product quality further, with an eye toward trying to improve recovery rates?

Gareth Manderson

executive
#22

Yeah. Look, the flexibility built into those contracts—I'd say we're looking at a minimum of 4.5%. So that likely lands somewhat below the 5% figure we announced this quarter. And depending on production runs and our customers, you should expect it to come in nearer to 4.5%.

Operator

operator
#23

Hugo Nicolaci from Goldman Sachs has the next question.

Hugo Nicolaci

analyst
#24

Gareth and Doug, thanks for this morning’s update — plenty for us to dig into. I’ve got a couple of questions, please, and maybe just a quick clarification to start: on unit cost, you say that’s reported using an actual grade sales volume basis — is that right?

Douglas Warden

executive
#25

The figure is tied to production — specifically, concentrates output. Unless you're asking whether it's an equivalent measure, in which case, no.

Hugo Nicolaci

analyst
#26

Right, so that relates to output at actual grade. And indeed, that applies across the board, royalties included?

Douglas Warden

executive
#27

Absolutely.

Hugo Nicolaci

analyst
#28

Yes. Great. And then, I suppose, moving over to the mining side, you know, pointing out the higher material movements during the quarter, I was hoping maybe you could give us a bit more detail specifically about how much ore and what grade is currently coming out of the mine. And then how you see that developing across the remainder of FY '24. Just since you have, from memory, guided to $45 million to $50 million in deferred stripping costs this year, yet spent just $2.5 million on deferred stripping in the quarter.

Douglas Warden

executive
#29

Yes. No, the way we’ve stripped that out is creating some confusion, and I get why. The $2 million we mention in the capital part of the report is the amount that got deferred onto the balance sheet. So the actual cost was much larger, and it was absorbed into the P&L and therefore into unit costs. To give you a sense of it, total waste cost for the quarter was net $27 million. But only 2 of that was referenced in the CapEx that went to the balance sheet, and the remainder hit the P&L. That’s the point I was making earlier. Just to put you in the picture, we moved almost 2 million BCM of waste — 1.94 million to be precise — in the quarter. So yes, does that answer your question? Happy to take it offline — go ahead.

Hugo Nicolaci

analyst
#30

Okay, no — I may have a follow-up on that point, though that gives me a useful starting point. And then, I suppose, just building on the earlier question about the lower grade your customers are content with at that 4.5%: first of all, does that 4.5% apply across the life of your offtake agreements, or perhaps only for the coming 9 to 12 months? And, in terms of pricing for that lower-grade product, do you still anticipate a linear grade adjustment to a 6% price, or are you beginning to see a discount appear there as lithium prices decline?

Gareth Manderson

executive
#31

We do have a few small discounts, though they aren't especially significant relative to the realized price. One of the contracts is already secured. We're in fact working through the final steps right now, but the second one is quite near to accepting those terms. And what the customer gains is greater lithia content, so essentially they receive more volume. On our side, it genuinely gives us some operational flexibility at the plant, which lets us boost recoveries and supply those larger lithia units.

Hugo Nicolaci

analyst
#32

Great. Thank you for that, Gareth. And then, perhaps we can fit just one more question in. You mentioned the debottlenecking efforts that you intend to carry out. I was just curious whether you might say a little more about them. And I believe concentrator feed rate in the past was roughly 1 million to 1.1 million tons per year. What kind of uplift do you think those debottlenecking efforts could deliver?

Gareth Manderson

executive
#33

Yes. So there are a few different ways you can boost performance at a processing facility. It comes down to throughput rate, availability, and recovery. And we're putting focus on every one of those. On the recovery side, you'd describe it as tuning the plant — the reagent, the dosing, and so on. Some work has been carried out examining feed size going into the plant, cutting down the share of fines, that kind of thing. On plant availability, meaning uptime, honestly it's actually quite pleasing that this has turned into something the team needs to tackle, and they are tackling it. So things like excessive wear in certain spots, pipes getting blocked, that sort of thing. You know, understanding them and resolving them as fast as we can, but also getting down to the root cause and seeing how we might improve. And from a rate standpoint, it's really just about looking at product moving through the plant and identifying what's holding us up. So some modifications have been made to certain screens, for instance. Beyond that, what I'd say is the kinds of things I've witnessed at other facilities would be pipes, pumps, control loops, that sort of thing, just making sure we're maximizing throughput through a bottleneck.

Gareth Manderson

executive
#34

You operate the plant, you determine what the constraint is, and after that you implement an engineering fix to make that better, and then you move on to the following constraint.

Operator

operator
#35

And the next question is from Adam Baker at Macquarie.

Adam Baker

analyst
#36

Gareth and team, maybe just a quick question on recoveries, if I could. With the DMS circuit going forward, what do you think is achievable on recoveries? And thanks for putting that chart in the slide pack, which gives the monthly breakdown on recoveries. I see you reached 53% there in August. Do you think that level could be sustainable going forward?

Gareth Manderson

executive
#37

During the opening portion of October, we recorded 55%. We have a good understanding of what competitors have achieved, or at minimum what they have made public. As a result, there are certain goals we are assigning to the team in that area. What I would say is that the previous quarter involved a sequence of trials, with a range of options moved forward. We are now converging on an operating set of parameters—an operating recipe, so to speak—in order to bring stability at the level you're currently observing. So what is our target grade? What are the set points within the plant? And from that point, Adam, we will begin to step things up. At this stage, I am comfortable stating that we can deliver above 50%, and I would like to land at something comparable to what we saw during the first couple of weeks of October. And beyond that, the team—I don't need to drive them especially hard. They hold aspirations to go higher than that.

Adam Baker

analyst
#38

Great, and maybe just one more on inventory — it's encouraging to see such a substantial build there. I suppose there are some key lessons from last year's wet season. It looks like you've got nearly a quarter's worth of production mill feed on hand. So I'm just wondering, in the worst case, if it turns out to be a pretty wet season and water becomes a problem with the pit and so on, how do you fare with road access and linking your mill to port? Does that become an issue in the thick of the wet season?

Gareth Manderson

executive
#39

Yes. Those are some good questions. So, look, it's really pleasing to watch the ROM levels climb. I believe that comes from the productivity gains we've made at the mine — in particular, you know, bench turnover down at the pit floor where the ore sits. So getting that ready is a priority for us. So it's a — there's a piece here involving this integrated pit-to-port approach, sort of, that's in play. There's also a piece involving mine sequencing and getting set for the wet season so we build those volumes, which will be a major focus heading into the wet and into December. Look, everyone asks how big the wet is going to be. I think we simply have to be ready for it. The wet itself isn't really the problem. It's the rain pattern and those heavy falls that come, as you're beginning to suggest, Adam. So what we want to do over the — I guess, over the months ahead is put ourselves in a strong position to decouple the mine from the concentrator. So the concentrator has the ROM available to it. And so you see that ROM build, and it's built — but still building quite nicely across the last few weeks, after the quarter.

Gareth Manderson

executive
#40

On your question about the mine itself and moving concentrate through to Darwin Port: that route is an all-weather access road. As with most roads in the territory, in the wet season they can get covered in water. I don’t expect any significant outcomes, provided we don’t get anything worse than what we’ve had before — you know, a few days with water over the road, for instance. Even so, up to now we’ve managed to get people in and out fairly regularly. That said, to your point, if there’s a really excessive rainfall event — you know, we see plenty of impacts across the territory on the news — Core won’t be immune to that either. Our approach really centers on making sure we control what we can. So let’s get ROM up, let’s run the concentrator well, build our concentrate stocks between the port and the plant during that period, and then we’ll watch the weather and respond as needed.

Operator

operator
#41

We'll take our next question from Tim Hoff at Canaccord Genuity.

Tim Hoff

analyst
#42

Appreciate the quarterly update. Looking purely at your cash operating costs alongside your tonnages, it suggests roughly $40 million was spent on costs during the quarter just ended. Should we anticipate much fluctuation in that across the year? Clearly, in the wet season you move less material and you'll be drawing material from the stockpile. And how should we think about that $1 million figure across the year?

Douglas Warden

executive
#43

Yes, Tim, I'd say that's a fair estimate. As we've already addressed in a few of the earlier questions, there's this whole matter of how much ends up on the balance sheet versus how much lands in P&L. But as I've stressed, during the quarter that just ended, nearly all of the stripping costs hit the P&L, with the exception of $2.5 million. So if you extrapolate those figures and arrive at $40 million, that's a pretty solid number. I'd point out as well that it's net of roughly $4.8 million in margin tied to the fines — that's in the fine print too, as you can see in the report. So yes, though I'd say processing and crushing should stay fairly consistent. As we mine, it simply comes down to what goes to the P&L and what goes to the balance sheet, and we'll do our best to make that clearer going forward.

Operator

operator
#44

We'll take our next question from Al Harvey at JPMorgan.

Al Harvey

analyst
#45

Gareth, one more thing on recoveries. I appreciate what you said about there being a lot of trial work during the quarter. I was just wondering whether you could give us a little more of an update on those improvement projects you laid out — I believe on Slide 7. I'm particularly interested in the Met work you've been doing. I guess I'm just trying to get a sense of whether the fines issue is mainly geological or whether it's tied to comminution. And then, by extension, I suppose, how that affects your efforts looking into adding a float circuit?

Gareth Manderson

executive
#46

Okay, so fines production, as everyone knows, will come either from the plant itself in the crushing circuit, or at the drill and blast stage, or as a function of the ore body. What we are observing is that the ore body probably contains more fines than we had expected. At this point, at least, we don't think it is the blasting area—which hasn't received a great deal of attention in terms of creating fines. We have, though, and I've mentioned some blasting improvements—so we've examined the blast design and the equipment being used for blasting in order to improve that. That is actually meant to kind of cut down on oversize and make sure we don't generate extra fines as a result, you know, better load and haul, those kinds of things, and bench turnover at the bottom of the pit. So that has been fairly positive. But that is not—and has not had, to date at least, any metallurgical impact. We've conducted a series of trials around feed size, and for a period of time there we were actually blending—or sorry, running on a campaign basis at 6 mil and a 10 mil size. We're now able to move to a straight 10 mil size.

Gareth Manderson

executive
#47

We do believe that most of the fines we generate — not the ore-related portion, but the generation-related portion — was actually in crushing, so we're optimizing there. We'll keep working in that area. From a metallurgical standpoint, we've discussed the microclassifier, and we've touched a bit on ferrosilica dosing, for instance, and right now we're doing considerable work on presentation across screens and screen management, which is a mix, I suppose, of metallurgy but probably also a rate improvement step. So what fraction and grade is passing over the screen, and are we achieving the correct throughput across it?

Al Harvey

analyst
#48

And yeah, I suppose — yeah, how does that shape your thinking regarding the float study?

Gareth Manderson

executive
#49

Right, sorry — yes, the float study. At present, that float study is ongoing. We’ve collected some metal — actually, we’ve collected some metal bulk samples, which I believe I referenced earlier. Bench-scale testing is moving ahead quickly, and that study is being carried out alongside the BP33 study. So right now we see plenty of opportunities to improve the existing facility without a fines treatment circuit, and we know that others have managed to get, you know, fairly high recoveries, so we’re heading down that path. So we don’t believe there’s an urgent need today to go the route of a fines treatment plant, but what we do see is a realistic future option; because of the capital and complexity tied to that plant, it makes more sense to attach it to a project such as BP33 rather than Grants.

Al Harvey

analyst
#50

Thanks. And I suppose I can see that the feasibility work with the filter or belt press is still underway. I was sort of under the impression that this relates to float circuit recoveries, though maybe I'm mistaken. I'm just trying to get a handle on how that fits in with regard to the potential float circuit, and whether it's also part of the BP33 work.

Gareth Manderson

executive
#51

Yes, so that piece of equipment could potentially end up as part of our float circuit, if you will, and it — it was identified early on as an initial, quicker, lower-capital answer for dealing with fines at the close of last quarter. Where things stand right now is that, if you consider our float circuit, we would tie it to BP33, and the filter-type operation is, you know, given the capital and the commitment tied to that, and then also given what we can see as the pathway at present in the existing plant along with the improvement options and additional work that can be done there, we're really putting our focus there first, because those are essentially no-capital or very minor, you know, cash outlay kinds of options, and right now it involves very little spending. It's really more a matter of tuning and optimization.

Al Harvey

analyst
#52

Thanks, Gareth. One quick question, and sorry if this was covered in your opening remarks, but I just wanted to check whether there's been any news on the Tesla correspondence that was flagged back in August.

Gareth Manderson

executive
#53

No, look, we're still working with Tesla, as we've said before, to see if we can come to some resolution without litigation.

Operator

operator
#54

Jon Bishop from Jarden Group has our next question.

Jon Bishop

analyst
#55

Nice work on a solid quarter. It seems the team has gotten through a great deal of work at site, so congratulations to them. To build slightly on the flotation question Al raised earlier — clearly it's too soon for full specifics, but I'd imagine that, economically, you're using a rough ballpark for a chunk of capital tied to the plant, just to stress-test tolerances. Could you give us a sense of the sort of number range you'd be considering if you were to pursue flotation for BP33?

Gareth Manderson

executive
#56

Jon, thank you for raising that. We appreciate the feedback for the team, and we will certainly make sure it gets passed along. But look, I fully understand the desire to get a handle on the capital cost and what the range could be for the flotation plant. That is a question I would like to answer too. Unfortunately, the study is still being finalised, so I think I just need to let the team get some additional work done on it. Quite genuinely, in the latest update, they are still working to understand what the flow sheet and the design might look like, so obviously that has to be settled first before we can understand precisely what the capital costs might be. And then the second thing to consider there is that it is really more tied to BP33. It probably does not make sense with the mine life at Grants, at least not at this stage. So we will look at it as part of that BP33 work.

Jon Bishop

analyst
#57

Yes. Okay. So would it be reasonable to think that once you've made the final investment decision on BP33 and done the feasibility estimate, flotation will be part of that work, or is it — I know it's being run jointly, but will that come in later?

Gareth Manderson

executive
#58

When it comes to the concentrator, I'd say there are two factors to consider. The first is how much gain we can get from the concentrator in its current state through the improvement program we've discussed, which needs minimal or low capital. The second is what additional benefit a solution requiring more CapEx, such as a fines treatment plant, might bring to it. Based on the test work completed so far and the progress made to date, the two ore bodies still appear to process in a very similar manner — Grants and BP33. That would suggest whatever processing solution we settle on for Grants at the concentrator would very likely carry over naturally to BP33. So for BP33, my view is that we should treat it as an underground mining project, and then consider the float plant in terms of what processing solution the Finniss operations require.

Jon Bishop

analyst
#59

Yes, that's quite clear and completely reasonable. Regarding BP33 — I know this may be jumping ahead a bit — but what's the right way to think about how development of the mine could shape up? Obviously, you've made some solid gains when it comes to drilling confidence and resource confidence. And clearly, the depth extension has, as a result, stretched the ore body considerably at depth. Could you offer some sense of how you're thinking about mining that ore body, and, in turn, what the upfront development capital might look like? I'm not after a number, but, you know, what might it look like — do you have to drive a decline quite a long way down to the ore body, that kind of thing?

Gareth Manderson

executive
#60

Yeah, look, it's still probably a bit more about the mine plan, so let's just bear in mind, you know, we only announced that boost in confidence around BP33 a few weeks ago. So that's going to feed into the mine plan. That's part of the study work. You know, we'll probably — we're working to optimize, to your point, the mine's productivity with the access to ore and the timing to ore. So we'll probably — I think it's probably best, Jon, to wait until we've done a little more work and then come back with a bit more of a picture around what the BP33 mining sequence might look like.

Jon Bishop

analyst
#61

Yeah, that's fair. I know I'm kind of putting you on the spot here. So one last question, then: you mentioned that you're monitoring pit wall stability at Grants. Could you give us some sense of how that's actually shaping up? Are geotechnical problems still showing up? With the monitoring in place, you'd think it lets you get ahead of those problems and deal with them before they turn into something obvious. But can you speak to how the geotech is looking for Grants specifically, and maybe BP33 as well?

Gareth Manderson

executive
#62

Yeah, I think it's reasonable to say every mine has some geotechnical element. Each one needs monitoring, a rigorous set of controls, and then trigger action response plans tied to that. We're no exception. As we've begun that work in the Grants pit, we're likely seeing — we've got what you'd call the east and western walls, probably the 2 spots where we felt radar monitoring equipment would be a good fit. So instead of having 1, which we installed a while back, we now have 2, which lets us get a better view of both walls. And people likely understand that if you're directly across and that scanner is scanning from the opposite side of the pit, so to speak, you get a clearer picture of what's going on there. So that's really the reason we did that — simply to get better data and information. In the photos you can see the pit looks great right now. One thing we need to keep in mind is that with water, rainfall, and the wet season approaching, that's typically the area that begins to test some of the stability in those walls.

Gareth Manderson

executive
#63

So we're definitely going to keep a very close eye on it. We wanted to be sure the right equipment was in place so the teams could do that, which is why we made that change.

Operator

operator
#64

We’ll take our next question from Kate McCutcheon at Citi.

Kate McCutcheon

analyst
#65

Could you offer a few remarks on the physicals for this quarter? Hugo raised the mining side, so if I may turn to processing, could you comment on milled tons and grade for the quarter, and explain how those figures square with reserves or expectations?

Gareth Manderson

executive
#66

Sure, please proceed.

Douglas Warden

executive
#67

Yeah, so milled tons processed during the quarter came in at slightly below 150,000 tons. Crushing ran somewhat higher than that figure. And as I mentioned earlier, the waste mine was a touch under 2 million BCM. Ore tons mined in the quarter totaled a little below 320 kilotons. So hopefully that's helpful. Does that address everything you asked about, Kate?

Kate McCutcheon

analyst
#68

Yes. And then perhaps a few remarks about head grade and how it has done relative to reserves?

Gareth Manderson

executive
#69

Yeah. So on reconciliation, what we're seeing is roughly in line with, or perhaps slightly ahead of, expectations when it comes to volume and grade. So I wouldn't read too much into it. It isn't a massive percentage, but it's enough for me to say I'm genuinely pleased with the effort that went into defining the ore body at Grants. So basically, reconciliation is looking good.

Kate McCutcheon

analyst
#70

All right, then — I think we ought to treat grade as being at reserve, or something close to reserve.

Gareth Manderson

executive
#71

Yeah. Yeah, I believe that would...

Kate McCutcheon

analyst
#72

Thanks, that’s helpful. And on the prior quarter’s call, we touched briefly on the royalty talks with the government. Could you share any update on how those are being viewed—whether in terms of a DSO price or a spot con price?

Gareth Manderson

executive
#73

Yes. So the royalties being used right now are those under the existing NT Royalty scheme. And our dealings with the government have been positive. We've lodged our submission, and we're waiting on a response from them. We anticipate hearing back from the NT government early next year — so very early next year. But at the moment things are fairly quiet, since we've made our submissions, as others have, and we're simply waiting for an answer. What we've recommended and suggested to the NT government is that they examine the WA regime. It's straightforward. It's widely understood. And it would, you know, mean the NT sits on a comparable footing with WA, so from a competitiveness standpoint, it kind of takes that problem away.

Operator

operator
#74

Andrew Harrington of Petra Capital has the next question.

Andrew Harrington

analyst
#75

To kind of build on the float — not the float question itself, but fines and recoveries — what becomes of the fines in the event they aren't sold? Will you stockpile them, or will they simply go into tailings?

Douglas Warden

executive
#76

Yeah. So the fines we’ve managed to pull out of the tailings facility and send to sales come in at a grade of about 1.3%, so that’s actually a reasonably good grade. If we can’t sell it — sorry, if we can’t move it at a sensible price in a sensible market, then I think it makes sense to stockpile it, and that’s what we’ll do. So there are a few benefits there. One, I think, is that it becomes — you know, you might look at it as a lower-grade stockpile that can be handled later, or it’s ore slash, and it cuts down the volume that’s held in the tailings facility, so it lessens how often we need to raise the dam walls.

Andrew Harrington

analyst
#77

Right, so I just want to make sure — you mentioned 3%, and what's coming out as fine is 3%, correct?

Gareth Manderson

executive
#78

1.3%.

Andrew Harrington

analyst
#79

One point three percent.

Gareth Manderson

executive
#80

Yes. Just one thing — yeah, yeah. I wish that were mine, Andrew.

Andrew Harrington

analyst
#81

And could you remind us again what mine-life strip ratio you're expecting at Grants?

Douglas Warden

executive
#82

The ratio is roughly fifteen to one.

Andrew Harrington

analyst
#83

Fifteen to one, all right. And finally, it looks like many of my questions have already gotten answers. Regarding the $27.7 million repayment to Yahua, where would that appear on the cash flow statement? Was it deducted from the revenue line, or not?

Gareth Manderson

executive
#84

Yes, that’s correct.

Andrew Harrington

analyst
#85

Pardon me, yes. My connection may be giving me problems. Was that a yes?

Gareth Manderson

executive
#86

Absolutely.

Operator

operator
#87

Richard Knights from Barrenjoey has our next question.

Richard Knights

analyst
#88

Gareth, Doug, a quick follow-up if I may on the royalty payment. What I mean is, we seem to be getting a fair amount of quarter-on-quarter volatility in that royalty figure. It appears to have been roughly $500 a ton in Q4 of last year, then dropped to around $150 a ton in the quarter just gone. How should we be thinking about that going forward? Is there a simple way to frame it? Obviously, the Northern Territory regime is fairly confusing. But what would be the best way to think about that?

Douglas Warden

executive
#89

Yes, well, the reason it fluctuates is that it’s tied to profit. So it’s 20% of — the term I believe they use is net value. You can visit the website to see what that means, but the trouble is that the figure to which that 20% applies isn’t linked to any accounting number people generally recognize. They do, however, describe in broad outline, at a high level, which deductions are allowed. So clearly, when the price falls, profit — or that net value — falls too, and as a result the royalties are smaller, which is exactly what you’re observing from one quarter to the next. So, as Gareth mentioned, we’re pushing for the ad valorem approach used in WA, 5%. Will they move to that? Hard to say, though they’ve certainly signaled that switching to a simpler ad valorem-based method appeals to them. We’ll see how it plays out.

Operator

operator
#90

The next question is from Brett Hucker at Canaccord Genuity.

Brett Hucker

analyst
#91

Thanks for the context you've shared on the call up to this point. I'm just wondering about that shipment at the end of the quarter, the 10.2 — and maybe I missed this — but how should we think about it regarding the specs and the realizations you achieved? I'm not certain whether you're able to speak to that. As far as grade and prices go...

Douglas Warden

executive
#92

That September shipment—is that the one you mean?

Gareth Manderson

executive
#93

October.

Brett Hucker

analyst
#94

Absolutely.

Douglas Warden

executive
#95

Is October the month you're referring to?

Brett Hucker

analyst
#96

The tenth month — right, October.

Gareth Manderson

executive
#97

Allow me to respond to that, though I doubt it truly addresses what you asked. It's on spec. Regarding Gan — as it heads to Ganfeng, it will draw the same terms as any shipment under the offtake agreement. That — what is the — that likely doesn't get at your question, in my view.

Brett Hucker

analyst
#98

Honestly, I'd have liked a bigger figure, though it's okay if you're not in a position to say anything. I get that you might not be able to.

Douglas Warden

executive
#99

So, Brett, what you're really getting at is more about what that grade turned out to be, and because of that...

Brett Hucker

analyst
#100

Yeah, what I'm curious about is the grade—really the grade and the price you got. Can you—if you're able to comment, maybe you can't.

Douglas Warden

executive
#101

Yeah, look, we'd likely prefer not to say anything about the grade. I suppose it's probably enough to note that, consistent with what we've said in the quarterly commentary, we're approaching it — how we handle production and, as a result, the sales contracts is more tons at a lower grade. So I guess that's probably the best way to explain it...

Operator

operator
#102

Thanks. At this point, I'd like to return the call to our CEO, Gareth Manderson, who may have some closing comments.

Gareth Manderson

executive
#103

Great. So again, many thanks to everyone who took the time to join the call. We appreciate the questions and the interest in Core. Looking ahead, we have 3 areas of focus. First, growing the business in and around Grants. As you can see, we've got 4 concentrate shipments now, better recoveries, better mining operations, and plenty of effort going into getting ready for the wet season. On BP33, the early works are moving along nicely and quickly, and the team is trying to complete as much as possible ahead of the wet season, and they're doing a fantastic job. We're also working on putting together that feasibility study so it can be presented to and considered by the Board for investment in quarter 1 of the next calendar year. Then there's the exploration program, which is likely about halfway through at this point, given that we deal with a wet season and dry season effect. Early on, we aimed our efforts at proving up mining options and supporting studies, and now we're beginning to test some of the options we see, mainly around North Finniss, while also testing Central Finniss, and we'll have a look at Shoobridge and Anningie-Barrow Creek with some preliminary work too, if everything goes according to plan.

Gareth Manderson

executive
#104

We appreciate everyone joining us today, and thanks for making time for this call.

Operator

operator
#105

Thank you, everyone, for joining in. That brings today’s program to a close. You’re welcome to disconnect at this time.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Core Lithium Ltd transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to Core Lithium Ltd earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Core Lithium Ltd or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.