Coronado Global Resources Inc. (CRN) Earnings Call Transcript & Summary
April 30, 2024
Earnings Call Speaker Segments
Operator
operatorWe appreciate everyone being on the line, and thanks for joining Coronado Global Resources' Q1 investor call. Everyone is currently in listen-only mode. A presentation will come first, and after that we'll hold a question-and-answer session. Should you want to pose a question, press the star key and then the number one on your telephone keypad. At this point I'll turn the conference over to Mr. Andrew Mooney, VP, Investor Relations and Communications. Please go ahead.
Andrew Mooney
executiveThanks to all of you for being on Coronado's investor call for the first quarter of 2024. Earlier today we published our quarterly report to the ASX and SEC, which lays out our production and sales statistics along with other details concerning safety, coal markets, and financials. A fuller outline of our financial position and results will go to the market on 7 May, together with our Form 10-Q earnings release. Joining me today are our Managing Director and CEO, Douglas Thompson, and our Group CFO, Gerhard Ziems. In our report you will find our notice about forward-looking statements and reconciliations of non-US GAAP financial measures. We urge every listener to review those statements alongside our other filings with the ASX and SEC. We also remind everyone that Coronado quotes all numbers in US dollars and metric tons unless otherwise stated. With that, I'll hand over to you, Douglas.
Douglas Thompson
executiveThank you so much, Andrew, and thanks to all of you for being here. It's a pleasure to share that the team at Coronado keeps executing in line with what we set out to do. Safety performance during the first quarter came in better than we had targeted. The money we're putting into productivity gains at Buchanan and Curragh remains on schedule and is producing results as planned. Every cost-cutting step we laid out for the first quarter has now been carried out, our sustainability program is progressing as intended, and our growth projects are tracking to both plan and budget. Early in the quarter, we successfully shifted our mine plans at Curragh South and Curragh North in order to soften the impact across the full year from the heavy rain that hit in late December, which was then followed by two cyclones during the quarter. We accomplished this by bringing forward scheduled maintenance at our two processing plants at Curragh. Having two processing plants let us run one while we serviced the other during February and March. As a result, the effect on the full year is smaller, since we've now finished maintenance that had been slated for later quarters, and the benefits are beginning to show in April. We'll recover time and productivity over the coming quarters. Alongside that, we've been advancing our strategic plans, and during the first quarter we reached a number of strategic milestones.
Douglas Thompson
executiveAs a few examples, we said earlier that during this quarter we began mining at the southern section we recently developed at Buchanan. In the northern district, our development sections are running ahead of schedule, and when finished, that will give us added flexibility in mining and better productivity during H2 of this year, as we spread operations across the north and south. When the second set of skips comes online in H1 2025, we'll capture the full productivity benefit, along with the increased, increased volumes we're able to hoist to surface. During the quarter, we also started highwall mining at Logan, which will deliver incremental tons, and we successfully demobilized four contractor fleets from the Curragh complex in late March, again in line with our plans. Dragline productivities at Curragh are getting better, consistent with our plans, after the 2023 investment in strike length improvements and pit geometries. In the quarter, we also kept investing at the same time in organic growth and emission reduction projects without any need to raise additional capital. The organic growth investments we're making are unlocking substantial value within the 838 million ton reserve base we own 100%, a substantial reserve base that we're tapping into. The investments in our newly named Mammoth Underground and in our Buchanan expansion projects are at multiples substantially lower than the recent market opportunities and show the cheapest and best use of our capital, which we expect will create significant value for our shareholders over time.
Douglas Thompson
executiveBefore I go into the details of how we performed operationally, let me focus first on safety and walk you through the picture. I'm happy to report that our reportable rates in Australia and the U.S. are still far beneath the comparable industry figures. In Australia, the 12-month rolling average for the total recordable incident frequency rate stood at 1.63 as at the 30th of March, against 3.18 at the same point a year earlier — a year-on-year improvement of 49%, and in fact the lowest safety rate in Australia since May 2018. For the U.S., the 12-month rolling average of the total recordable incident rate was 2.12 as at the 30th of March, versus 2.8 across the prior year. That represents a 25% improvement year on year. At the group level, then, the reportable total recordable incident rate came in at 1.01, compared with 1.36 at this time last year. That is a 26% improvement year on year. Beyond these strong results, I'd like to take a moment to congratulate our Logan Complex on earning several safety awards for its performance in 2023. Every one of Logan's surface and underground operations received the West Virginia Joseph A. Holmes Safety Association Award, and three of those operations were also given the Mountaineer Guardian Award.
Douglas Thompson
executiveNow moving to how things ran. Coronado closed out the March quarter with group ROM coal output at 6 million tons, saleable output at 3.4 million tons, and sales volumes of 3.6. Over in Australia, raw coal output at the Curragh Complex came to 2.7 million tons, with saleable output of 2.2 million tons. Production rates dipped during the quarter, largely because of heavy rain late in December, which the two cyclones then followed, as we reported for the quarter. To soften the effect of that significant late-December weather, which cut into the mine's planned raw coal inventories at the start of the year, we pulled maintenance on our processing plants forward. Because of that, both CHPPs at Curragh have finished their annual shutdowns, and no further maintenance is scheduled for the remainder of the year. Curragh is also running ahead of plan on total waste movements and drill meters for the quarter. That positions the pits for better coal availability in the quarters ahead. By the end of March, the mine had successfully finished historic pre-strip — something that had been a deficit previously — and as a result, we were able to demobilize four contractor fleets from site. Removing those fleets, together with the pit rectifications under the One Curragh Plan, marks a significant milestone for the mine.
Douglas Thompson
executiveWe've also consolidated contractors, cutting resources in proportion to the reduced fleets and, as a consequence, the maintenance those fleets require. Thanks to these steps, starting in April, Curragh Complex anticipates a substantial drop in cost per ton. Beyond that, as a return on investment, Curragh's dragline fleets have delivered the productivity gains we planned, with the ratio of waste moved by draglines compared with truck and excavator rising to 44%, up from 37%. That matches our plan and shows the investment in the plan is paying off. Also, in late March we brought in a new PC7000 excavator, which will lift productivity rates further across our excavator fleets. Every one of these steps aligns with our plan to drive productivities and improve margins on a sustained basis. Curragh wrapped up the quarter strongly, with solid performance, elevated stockpiles and strong momentum that has carried into April. The mine remains on track to deliver 1 million tons of saleable production this month. Moving to our U.S. operations, raw production for the March quarter month came to 3.3 million tons, and saleable production was 1.2 million tons. A strong quarter for raw production, which was 20% above the December quarter.
Douglas Thompson
executiveThat came about because mining started up in the freshly developed southern district at Buchanan Mine. The hoist and the underground bunker sit quite close to that southern district, and that helped push raw delivery higher during the quarter — and we should see the same effect in upcoming reporting periods as we work those new panels. In the quarter, we performed maintenance on the hoist that had originally been scheduled for later in the year. That work will benefit us for the rest of the year. Skip counts are moving toward their strongest rates in 2 years, and downtime on our conveyor system is at record lows. Saleable production matched the December quarter while yields from the southern district were temporarily lower. That follows our plan, and yields should rise to more normalized levels in the June quarter. Output at Logan Complex was in line with plan. During the quarter, as I noted earlier, highwall mining got underway in late March, and we also went back into the Pelton Underground Mine in April. Turning to the June quarter, April performance across Coronado's operations has been strong, with better coal mining and a lower cost per ton at Curragh, improving yields at Buchanan in April, and solid incremental tons delivered at Logan.
Douglas Thompson
executiveAccordingly, we are restating the 2024 market guidance we gave earlier. At this point I’ll pass things to Gerhard, who will cover our financial and market outlook.
Gerhard Ziems
executiveThanks, Douglas, and greetings today from Beckley, West Virginia. Group revenue for the March quarter came in at $668 million, a 2% decline versus the December quarter, largely driven by lower sales volumes on a quarter-over-quarter basis. Metallurgical coal sales accounted for 95.1% of all coal sales revenues in Q1. The group's realized net coal price for the quarter stood at $204 per ton — a blend of FOB, FOR, and U.S. domestic pricing contracts — representing a 3% rise over the prior December quarter. Cash flows for the group in the March quarter took a negative hit from the extra payment made in March to the Queensland Revenue Office totaling $52 million, equivalent to AUD 79 million, tied to Coronado's acquisition of the Curragh Mine back in March 2018. That payment, which we had flagged in our full year results release, was made before the company formally lodged its appeal with the Supreme Court of Queensland on 11 March this year, challenging the QRO's stamp duty assessment. The remainder of the cash outflows is down to working capital, since we missed a handful of customer payments worth more than $46 million that were officially due right on Good Friday — the last day, almost, of March — and that money arrived in the first week of April.
Gerhard Ziems
executiveWorking capital clearly had a big effect here. When you combine the two items — the stamp duty and the late customer payments — that comes to roughly $100 million in cash. Consequently, at 31 March 2024, our net debt stood at $18 million. Add back that $46 million I referred to a moment ago, and you get $28 million of net cash. That figure is made up of a closing cash balance of $225 million alongside $242 million of senior secured notes outstanding. We also keep $375 million of available liquidity, which comprises available cash plus short-term deposits and the borrowings we continue to draw under the ABL. Turning to costs: for the group, the Q1 average mining cost per ton sold came in at $125.6 per ton. That higher cost per ton resulted from the production effects of the wet weather events early in the quarter and from the temporarily lower yields being realized at Buchanan, as Douglas highlighted. But, as Douglas said earlier, we anticipate a meaningful reduction in cost per ton during the second quarter, once four contractor fleets are demobbed at Curragh, the pre-strip deficit works are finished, yields at Buchanan are higher, and improved productivities are being realized across Coronado.
Gerhard Ziems
executiveTurning to coal markets, met coal index prices for both Australia and the U.S. fell during the first quarter. For the Aussie Premium Low Vol Coking Coal FOB, the benchmark average index price came in at $308 per ton, an 8% decline from the December quarter's $333 per ton. The benchmark average index price stood at $256 per ton, 3% lower than the prior December quarter's average of $264 per ton. That benchmark dropped from roughly $307 per ton in early March to $245 by month's end, as supply rose out of Queensland and combined at the same time with softer spot demand from China and India. Naturally, that is putting pressure on prices. Seaborne supply of Australian met coal climbed during March thanks to drier conditions, after the heavy rainfall that hit across the Bowen Basin earlier in the quarter. Queensland industry shipments in March were up 20% against the average weekly shipments of January and February. This stronger supply-side position, together with persistently reduced global steel demand, has ultimately produced additional spot market availability and the price fall seen in March and also in April. The global economic environment and a weak short-term outlook for steel demand keep weighing on steel margins, and steel makers continue to manage lower demand through lower hot metal production and by cutting demand for raw materials.
Gerhard Ziems
executiveBut my expectation is that pricing in the June quarter will hold steady around where we are now, since Indian imports should rise thanks to robust demand tied to pre-monsoon restocking. That pattern typically plays out during May and June, and the most recent read on the SGX forward curve — data as of today — points to the benchmark index sitting at $277 per ton across this calendar year. What these price forecasts keep telling us is that we truly are in a higher-for-longer pricing regime, one that should stay comfortably above the long-term average of $198 per ton. Before I turn things over to Douglas to talk through how our growth projects are progressing, I want to note that we recently hosted representatives from JFE Steel Corporation, one of our biggest customers, to mark 40 years of uninterrupted supply of high-quality, reliable met coal from our Curragh complex to the Japanese steel industry. In marking this milestone, we restate our dedication to providing excellent products to every one of our customers across five continents, and we keep looking ahead to building a good future together. I'll pass it to Douglas now. Douglas?
Douglas Thompson
executiveThanks, Gerhard — and yes, it’s a really strong, long-running relationship with a solid future ahead. Now I’ll shift my focus beyond the near term to a few of the strategic growth projects I referenced earlier. During the first quarter, the business kept investing at the same time in organic growth initiatives and projects aimed at cutting emissions, and we made meaningful headway on both fronts without having to issue extra debt or equity. As I noted earlier, the capital put into Mammoth Underground and our Buchanan expansion projects sits at multiples that are considerably below recent market opportunities, and we believe that will generate substantial value for shareholders going forward. On the underground project — now formally called Mammoth Underground — it is still within budget and on schedule, subject to environmental approvals, as we’ve said before. Power readiness remains on track to be finished and handed over to the underground teams in the June quarter. Through the March quarter, work carried on toward the critical-path requirements for the environmental approvals. The Mammoth Underground Mine gives the Curragh Complex a number of strategic improvement opportunities, chiefly: it provides diversified coal production. The underground mine won’t face production disruptions from wet weather, so we will reduce risk to production continuity.
Douglas Thompson
executiveLower cost per ton. For Mammoth Underground, our cost projections are forecasted in the second quarter, and that will bring down the complex's overall cost per ton. Then there are quality products that are in demand. Mammoth Mine holds substantial high quality met coal, a resource base of 41 million tons, with coal quality expected to mirror the existing Curragh North open cut, and it gives us increased production capacity. Once fully operational, the project is expected to produce 1.5 million-2 million tons of saleable production in the first phase. This is subject to the environmental approvals, and our forecast is to have first coal produced from Mammoth Mine in the month of December 2024. Organic growth plans in the U.S. also remain on budget and on target. Good progress has been made in the construction of our second set of skips in this quarter. As at the 31st of March, 95% of the shaft excavation works and concrete lining works are complete, with a balance expected to be completed by mid-June. The construction of the new surface raw coal storage areas to increase the mine storage capacity is progressing to plan, with excavation works to be complete in the June quarter, and the surface infrastructure and production hoists are also progressing to plan.
Douglas Thompson
executiveBoth projects remain scheduled for full completion in early 2025. In the end, the hoisting capacity along with the storage area will lower the chance of bottlenecks, which lets the longwalls at the Northern District and the Southern District operate at a greater capacity and boosts productivities. Moving on to our emission reduction projects, we're still advancing the gas pilot project at Curragh. The aim of this project is to capture and put to beneficial use the open cut waste mine coal gas from our operations, with the main downstream cases being power generation and use as a diesel substitute in our fleets. I'm able to report that production from the Europa 1 and 2 wells began in March, and dewatering has led to gas flows from both wells. As dewatering of the wells continues, gas flow is rising steadily and matching our modeling for this reserve. We intend to monitor gas flows in the near term and expand on our reservoir monitoring, grasp how each well is performing and, as a result, the optimal use of this waste gas going forward. During the June quarter, we'll also run a new trial on an updated conversion of a gas truck to test the feasibility of converting additional trucks to this dual fuel solution.
Douglas Thompson
executiveNow moving to the U.S.: because the ventilation air methane unit at Buchanan Vent Shaft 16 has proven successful at cutting our emissions, the business began installing a second VAM unit at Vent Shaft 18. Coronado sees itself as an industry leader when it comes to implementing VAM emissions reduction technology, and we keep sharing what we learn with the industry. Construction works advanced substantially over the quarter, and construction on the second VAM unit is now finished. That VAM unit is currently going through testing procedures and is set to be online and operational in May, which is actually a little ahead of our schedule. Establishing the second VAM unit should further reduce emissions across our business and is a key building block toward our aspirations of a 30% emissions reduction by 2030. I'll now hand over to the operator to take your questions.
Operator
operatorThank you. Should you want to pose a question, kindly press star one on your phone and hold until your name is called. To withdraw your request, please press star two. In case you are using a speakerphone, please lift the handset before asking your question. Our first question is from Paul Young at Goldman Sachs.
Paul Young
analystMorning, Doug and Gerhard — trust you’re both doing well. I’ll start with a question about the realized pricing that Curragh achieved during the quarter. My understanding is that it came in at roughly 73% of the high coking coal price — that is, the FOB price during the period. That was better than what we saw in the prior quarter, though I had expected it to land somewhat higher still. Was the reason a mix that didn’t improve, or some mix-related issue between semi-soft PCI and high coking — or is it simply a matter of shipment timing? And do you anticipate that some kind of benefit will be realized, or will carry through, in the June quarter?
Gerhard Ziems
executiveMorning, Paul — Gerhard here. So, first, I'd say it's substantially stronger than the December quarter, partly just because pricing came down, and in the December quarter we had the benefit of those higher prices. That's the reason it comes out higher. To be honest, it's consistent with what we've seen historically, 73%. The reason it may be below your expectation is that our relativities of PCI — PCI in particular — to the benchmark were very low. So that sat at just over 50%, you know. Now it's back above 60%, so it has improved, and as a result we expect some favorable effects from that to carry into the next quarter.
Paul Young
analystAll right, thank you, Gerhard. So nothing seems to be indicated regarding timing and shipments where high coking coal is concerned?
Gerhard Ziems
executiveNo — really, what mainly happened is that PCI relativity fell to a low of 50% during that quarter.
Paul Young
analystAlright, thank you. Then perhaps regarding Curragh — and this is a question for Doug — it's encouraging to see the complete fleets being removed from Curragh. Doug, I believe that's four of the 16 fleets, meaning truck and shovel fleets. Just a question about contractor consolidation: could you elaborate a little more on that? And what benefits arise from consolidating the contractors in terms of, you know, how the contracts are structured, or how should we consider the cost benefit there?
Douglas Thompson
executiveGood day, Paul. There are several things to cover. First, we're working to fold all of the support into a plan, so we have a systematic approach for addressing some of the past, and I'm glad to report that the current plan has done what it was meant to do. It's now wrapping up with a deficit catch-up, where we bring in extra fleets to close the gaps. But during that same stretch, with added maintenance, I think we've discussed some of the work done at the prep plants and the overland conveyor to lift their performance, and the same goes for running those additional fleets. As we phase that out, we examine our entire other contracting and support base and cut costs in proportion. Reducing headcount is among the best ways to take cost out of the business, since it also brings second-order costs with it. So we have a plan we've been carrying out toward that, and we keep measuring the reductions that come from it.
Paul Young
analystAll right, thanks, Doug. Then perhaps just looking at the U.S. and Buchanan — you've now started mining in the southern district, finished that up, and pulled forward the planned maintenance on the hoists. What kind of benefit do you anticipate for production at Buchanan in the June quarter? Or, I guess, what run rate should we be looking for from Buchanan between now and year-end, ahead of the new skips being commissioned?
Douglas Thompson
executivePaul, I’d rather not provide guidance until the timing is right. We’ll discuss June once June is over, but April has shown better results. Over the past two years, we’re beginning to see improvement, with skipping and our conveyor belts now running ahead of where they performed during that period. In the same way, at Buchanan, we had modeled and understood that yield would decline in this timeframe, so although ROM flows have been good, yield came in lower. That yield has improved as April progressed. We expect further gains for the remainder of the June quarter. The shaft work we carried out was mainly because a set of ropes required replacement. It came from the routine inspection we perform. When we found a change-out was needed, it came sooner than expected. So we used the chance to handle other maintenance too, and that is paying off now. What we want to highlight is that, since that maintenance has been completed, we will recover the time in future quarters, when the shaft will not be taken down according to our original plan, and we will get that time back.
Douglas Thompson
executiveIn the same way, at Curragh, since coal flows were low at the beginning of the year—owing to the extreme wet weather in December during that final week and a half—we simply lacked the ROM stock we had expected, along with the face positions, and then came the two cyclones. We were able to pivot quite quickly and perform the maintenance during those low coal flows, which means that in the second quarter, the June quarter and afterward, we won't need to carry out the prep life maintenance. And again, you get that time back, but we also gain the productivity improvements for the remainder of the year that we would only have begun to enjoy later in the year, and we could have seen that in April too. So that's how pulling preventative maintenance forward will benefit us for the rest of the year.
Paul Young
analystThanks, Doug. And regarding those — specifically the wash plant, the maintenance work at Curragh on the wash plant — how long did that scheduled upkeep on the wash plant take?
Douglas Thompson
executiveI would want to return with precise figures for you, but it's likely around 2 weeks—roughly 10 days for the first one and a little more than 2 weeks for the second. Both of them were big annual shutdowns.
Paul Young
analystAll right, that's useful. I'm finished with my questions. Appreciate it, everyone.
Operator
operatorWe'll take our next question from Chen Jiang at Bank of America.
Chen Jiang
analystMorning, Doug and Gerhard. Appreciate you taking my questions. I have two, please. First, a quick follow-up on your price realization. The PCI discount to premium hard coking coal has narrowed over, I'd say, the recent weeks. I'm wondering whether you could give some color on that narrowing discount. Is it mainly because premium hard coking coal prices have been declining, or has anything shifted in the seaborne PCI market, like decreasing supply of seaborne PCI coal, or stronger PCI demand — any color on the seaborne market? Appreciate it. Thank you. I have another one after this.
Douglas Thompson
executiveAlright.
Gerhard Ziems
executiveRight, so let me take that one first. Basically, the reason comes down to the fact that the benchmark — that premium global Australian FOB benchmark — fell from the $300s, above $300s, all the way down to $245. As I believe I mentioned in earlier quarterly updates, my concern now is that these indices have sort of decoupled. What really drove the premium global benchmark was low supply in the Premium Mid Vol segment combined with strong demand coming out of India for that Premium Mid Vol segment. That's what pushed this index up so high, while the PCI product saw none of those dynamics at all. So PCI, at those elevated prices, was sitting at 50% as the benchmark, as the premium global Aussie index dropped to $245 — almost $100 below the prior month or prior quarter. Today the relativity has climbed to 64%. So basically, these relativities have decoupled, as I'd put it, at this point, and that could well continue.
Chen Jiang
analystThanks, Gerhard. So your view is that PCI and premium hard coking coal will keep decoupling? In other words, are you saying the discount is going to remain where it is right now?
Gerhard Ziems
executiveWell, I mean, no — it's just that it isn't as dynamic anymore. The PCI price is likely steadier than the premium global benchmark. Since the premium global benchmark will probably rise as India restocks ahead of the monsoon, I think that relativity could fall again, you know, to under 60%.
Chen Jiang
analystOf course, of course, I get it. So I suppose, any—
Gerhard Ziems
executiveRegarding PCI, that market doesn’t move with quite the same dynamism as the benchmark does for the premium global.
Chen Jiang
analystYeah, absolutely. So looking at it through the lens of price realization, is there any product mix shift you could pull off that would bring a better price from this point through the remainder of the year?
Gerhard Ziems
executiveRight. So, we've accomplished some solid work there. I don't want to get into specifics, Curragh, but both in the U.S. and at Curragh, efforts have been made on our side to soften these effects of reduced relativities. Still, essentially, what March has shown us serves as a decent signal. A 73% realization on the met coal price is likely quite solid. That said, falling prices during that quarter also play a part. There's some of that baked in. Even so, we feel fairly confident about sustaining the long-term average for met coal price realization.
Chen Jiang
analystOkay, okay, thank you for that, Gerhard. I’ve got another question regarding the OPEX you reported this quarter. Comparing your first-quarter OPEX, it comes in 27% higher than the top end of your FY 2024 OPEX guidance. Then, if I look at your first-quarter OPEX against BHP’s FY 2024 guidance for BMA, it appears to be at the upper limit of BHP’s BMA met coal guidance. Do you believe your FY 2024 guidance is too low or overly conservative? I understand you mentioned several factors driving productivity and so on, but do you think your cost guidance is appropriate, and what essentially gives you confidence that you can meet the cost guidance? Thank you.
Gerhard Ziems
executiveYeah. No, that's a fair question. So, look, I mean, basically to unpack that, what it comes down to is that across the coming three quarters, we've got to see a cost of roughly $90 per ton, right? That's the point you're making. So whereas right now it's around, what was it? $125 or thereabouts, you know. So, yeah, you've got to go back to volume, you know. So when we look at the first quarter, we lost a lot of volume because of the wash plant maintenance that we pulled forward, and then the wet weather problems. So, since we've now absorbed, in particular, the wash plant issues, we are within guidance in our own forecast. So we don't see any problems there at this point. Now, if there's a major rain event, and we have budgeted and forecasted for rain events, but if anything extraordinary, outstanding happens in the fourth quarter, you know, that might impact cost as well as it impacts volume. But at the same time, you know, we are doing a lot of good things that Doug has already highlighted, you know, pulling out the four fleets out of Curragh will yield cost savings that will ensure that we are within guidance.
Gerhard Ziems
executiveHonestly speaking, we're examining additional gains in productivity — and these are truly significant, significant productivity enhancement initiatives. Taking fleets out of an operation such as Curragh is enormous — 3 or 4 fleets. That represents a substantial endeavor, and we keep reviewing further productivity gains. So this will guarantee we stay inside guidance for the remainder of the year, and that's what our internal projections indicate right now.
Douglas Thompson
executiveYeah, and to add to that point—you've got it exactly right. There's a plan in place. Everything we do follows that plan, and we're executing on it with real discipline. During the first quarter, the team delivered everything we anticipated under our plan. Some elements actually came in slightly ahead of schedule when it comes to lowering costs and boosting productivity—and boosting productivity is a genuine lever for us here. We have to eliminate wasteful costs. That difficult work is behind us. We'll keep our focus there, such as the contractor rationalization effort, but also the productivity gains. With the four fleets, the math is there for you to run, and it's substantial. A dragline productivity improvement where you're moving 44% of the waste instead of 37% under the historic approach, with the draglines, is in line with our plan, and that likewise translates into meaningful cost reductions. As Gerhard puts it, should those work out the way we intend, additional opportunities exist for us to rationalize installed capacity at site, which would lower costs once more. And then in the U.S., it's been a volume game that hurt the quarter from a cost standpoint.
Chen Jiang
analystOkay. Doug, Gerhard, thank you both. Appreciate it, and I'll relay your thanks. Thanks.
Operator
operatorGlyn Lawcock from Barrenjoey has the next question for you.
Glyn Lawcock
analystMorning, Doug and Gerhard. Perhaps to push that a bit further — obviously we're now fully past April at this point. So are we in fact running free cash flow positive as of now, and operating inside that new guidance you laid out, whatever the figure was — 90 to 95 to 99 — as things stand today?
Gerhard Ziems
executiveYou’re clearly pointing to April there, and we typically don’t provide an outlook for April performance. That said, when I review our internal reports and forecasts—and there’s nothing more candid than that—we are operating within guidance.
Glyn Lawcock
analystAll right. So every one of those benefits is coming through — and, as you mentioned, if you're able to deliver the next—
Gerhard Ziems
executiveSure.
Glyn Lawcock
analystWe’ve completed nine months, which comes to three quarters.
Gerhard Ziems
executiveSure.
Glyn Lawcock
analystWhen it comes to guidance, you will pull that first-quarter cost lower, and nothing you have observed in April points to you failing to hit that, and you are now generating positive free cash flow too.
Gerhard Ziems
executiveYeah. Yeah.
Glyn Lawcock
analystLet me ask one more thing, if I may. About that Queensland stamp duty — is there any way to recover it? Can you take that up with the government, or has the money gone for good and we won't get it back?
Gerhard Ziems
executiveAbsolutely. No, no, I'll pass things to Douglas at this point, but, as I mentioned, you know, we filed a claim against the Queensland Revenue Office, and lodged an appeal with the Supreme Court of Queensland on 11th March. So when you look at the stamp duty we paid here, on top of what we paid last year, we're disputing a large chunk of this, you know? So essentially, we just expected — as we had in our balance sheet, provided for — expected about AUD 43 million, Australian dollars, to pay for the stamp duty. In total, we've now paid about AUD 103 million.
Glyn Lawcock
analystWas it 103 million Australian dollars?
Gerhard Ziems
executiveRight, Aussie, that's correct.
Glyn Lawcock
analystAlright.
Gerhard Ziems
executiveOur expectation was to pay AUD 43 million, yet the total we ended up paying was AUD 103 million. That is precisely why we took the matter to appeal, you know, at the Supreme Court of Queensland on 11 March.
Douglas Thompson
executiveThe way this operates is that everything has to be paid upfront, interest included, and after that your only option is to appeal. So we've looked at it carefully, and we've concluded that, from a shareholder's standpoint, this is the prudent path to take.
Glyn Lawcock
analystMm-hmm. Yeah, no, that's logical. I mean, that's even worse than having to pay 50% of your tax in advance and then trying to argue about it. But Doug, is there any timeline at all for resolving this? Or is it just kind of like asking how long a piece of string is?
Douglas Thompson
executiveSadly, scheduling at the Supreme Court isn’t something we decide. We’ve received indicative dates suggesting it could still happen this year, and after that it depends on how swiftly the process moves through the system. That part, unfortunately, isn’t fully within our control.
Glyn Lawcock
analystYes, I’ve got it. Thank you so much.
Operator
operatorThe next question we have comes from George Eadie at UBS.
George Eadie
analystHello Douglas and Gerhard. My first question concerns Curragh. Would you be able to put a number on those higher stockpiles you referred to? What volume are we discussing, and what location are they in? Are they in the pit, uncovered and accessible coal? Do they sit at the ROM, at the TLO, or in some combination of the two?
Douglas Thompson
executiveGeorge, we don't provide that information, because the trouble is that if we begin, then we begin reporting, you know, right down to the minutiae, and that isn't helpful for you or for us. But what I will say is that we have good coal inventories exposed, thanks to the elevated and on-plan waste movements in drill and blast during the quarter. So it's input at hand. We also have decent ROM stockpiles, and we have decent product stockpiles, partly because there was a railage outage during the month of April, when the rail line did some maintenance. So there's a decent combination of product across all three areas.
George Eadie
analystAll right, no, that helps quite a bit. And perhaps one more quick follow-up. You said the dragline fleet is now handling 44% of waste, which is up from 37%. Maybe you could also touch on what rehandle assumptions you're using for the dragline system from here on. What I'm really asking is this: if additional dirt has been assigned to the draglines out of pre-strip, that could bring unit costs down, but does it create a risk around coal uncovery and put pressure on the plan, or turn the dragline into the bottleneck down the road?
Douglas Thompson
executiveNo, and those figures are at prime. So part of what made it difficult was pit orientation and strike length. We were using a good chunk of time relocating our draglines or primary dig and moving back onto blocks, since strike length hadn't been invested in previously. So in late 2022 and during 2023, we completed all the box cuts and then configured the pre-strip so it would be in balance, meaning the pit geometry was arranged for optimal dragline performance. And we began seeing that in the final quarter of last year, and then again this quarter, that the return on the four draglines shows they're performing at that optimal configuration. We'll keep pushing, wherever we have geological advantage, to raise the prime percentage with draglines, because that's our primary fleet. We engineer everything around that, and then back from that, and clearly then do a business case rebalance on the productivities. Just to stay on that point, since you've raised it, the PC7000 we introduced is replacing some of the less productive contractor fleet. It's a larger piece of equipment than what was deployed. So we've now got an hour shovel, a PC7000, and a 800-ton digger handling the upper alluvial material, so we can sprint ahead of dragline production in the most productive way and lower the cost per BCM, obviously, in the process, in the balance.
George Eadie
analystAlright, that's quite useful. So a greater share is heading to draglines. That's logical. Just to follow up on that point, how is rehandle shaping up across the coming two to three years compared with the past couple, perhaps?
Douglas Thompson
executiveAt this point in our plan, rehandle is unchanged, though we do see chances to make it better. At this stage in the model, it's unchanged, and that's likely the best spot to remain before the two of us begin engineering work on the call. Hello?
Operator
operatorWe still have Mr. Eadie on the line.
George Eadie
analystThat covers everything from my side. Appreciate it, everyone. And thank you, Douglas.
Douglas Thompson
executiveThanks.
Operator
operatorThat brings us to the end of the question-and-answer session. I'll now return the call to Mr. Thompson, who will offer some closing comments.
Douglas Thompson
executiveAll right, everyone, I really appreciate you making the time. We're well aware things are extremely hectic in the market right now. I want to note that we've been in communication on this for some time. There is a plan in place. In the near term, our U.S. and Australia operations are being run in line with that plan, and returns are beginning to show on earlier investments in productivity and performance, along with handling certain legacy items and getting them behind us. We're also putting money into a genuinely attractive future built from our core operations in the U.S. and Australia, and that will generate value for every shareholder going forward. We'll keep reporting to you against our plans for the year—on the improvements happening now and those still to come. Should you have any follow-up questions, feel free to reach out to our investor relations team, and Andrew Mooney in particular. Thank you.
Operator
operatorThat brings today's conference to a close. We appreciate everyone joining us. You're welcome to disconnect at this time.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Coronado Global Resources Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Coronado Global Resources Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Coronado Global Resources Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.