Dominion Energy, Inc. (D) Earnings Call Transcript & Summary

August 1, 2024

New York Stock Exchange US Utilities Multi-Utilities earnings 38 min

Earnings Call Speaker Segments

David McFarland

executive
#1

Hello, everyone, and thanks for being on the call today. The earnings materials, which include the prepared remarks for today, have forward-looking statements and estimates that carry various risks and uncertainties. For a discussion of factors that could cause results to differ from management's estimates and expectations, please see our SEC filings, including our latest annual reports on Form 10-K and our quarterly reports on Form 10-Q. Some measures of our company's performance that we'll talk about this morning differ from those recognized by GAAP. Reconciliation of our non-GAAP measures to the most directly comparable GAAP financial measures, which we can calculate, appears in the earnings release kit. I encourage you to go to our Investor Relations website to review the webcast slides and the earnings release kit. On today's call with us are Bob Blue, Chair, President and Chief Executive Officer; Steven Ridge, Executive Vice President and Chief Financial Officer; and Diane Leopold, Executive Vice President and Chief Operating Officer. I'll now hand the call over to Steven.

Steve Ridge

executive
#2

Thanks, David, and good morning to all of you. I'll begin with the quarterly results, which you can find on Slide 3. For the second quarter, operating earnings came in at $0.65 per share. That figure included $0.03 of benefit from weather that was better than usual in the areas where our utility operates, so normalizing for that, operating EPS would have been $0.62. When we compare to Q2 of the prior year, the favorable items this quarter were $0.11 from improved weather, $0.10 from growth in regulated investments, and $0.17 tied to Millstone — made up of $0.13 from not having extended duration outages and $0.04 from realized power prices being higher. If you recall, during Q2 of the previous year, Millstone experienced outages, some scheduled and some not. Another notable factor this quarter was an $0.08 drag compared with a year earlier, caused by lower revenue at DEV tied to specific riders shifting into base rates under legislation that became effective last July. A complete breakdown of what drove earnings relative to the same period a year ago appears in Schedule 4 of the Earnings Release Kit. GAAP results for the second quarter likewise totaled $0.65 per share. When you look at the difference between our operating results and what we reported, it comes down to a few items: the net gain from businesses we've exited, which was mostly from divesting the gas distribution operations, plus mark-to-market swings — both unrealized and noncash — in nuclear decommissioning trust funds and economic hedging derivatives. You can find every one of those adjustments summarized in Schedule 2 of the Earnings Release Kit. Turning now to Slide 4 and our guidance: everything we laid out financially at the March 1 Investor Meeting still stands. Let's begin with 2024. Our expectation remains that operating earnings per share for 2024 will come in somewhere between $2.62 and $2.87, which puts the midpoint at $2.75. So far this year, our operating earnings are tracking right in line with the illustrative quarterly ranges for earnings cadence that we laid out back on March 1. Looking ahead, we think stronger-than-usual weather during the first part of July, plus the $0.03 benefit from weather in the second quarter, will come close to canceling out the $0.06 hit that weather cost us in the first quarter. For the back half of the year, we're expecting certain headwinds tied to short-term interest rates running above what we budgeted, along with O&M expense that's weighted toward the back end — and that combination keeps us positioned for the midpoint of our guidance range. You'll find the year-over-year drivers and the illustrative EPS cadence for Q3 and Q4 summarized in today's appendix, carried over from our March 1st meeting. Moving on to the period from 2025 to 2029: our guidance for 2025 operating earnings per share stands reaffirmed at $3.25 to $3.54, which includes roughly $0.10 in RNG 45Z credit income, putting the midpoint at $3.40. Beyond that, we still project operating earnings to grow annually at a rate between 5% and 7% all the way through 2029, measured from a $3.30 midpoint that leaves out any RNG 45Z credit effects. Keep in mind that year-to-year results will likely vary inside that 5% to 7% band because of the Millstone refueling schedule, which calls for an additional planned outage in one out of every three years. When we look at 2025 in particular, PJM came out earlier this week with the clearing prices from the base residual auction for the 2025, 2026 planning year. The higher capacity prices in the RTO and DOM zone confirm the message we've been delivering for several years now. Making strong investments in an all of the above mix of generation resources plus new transmission infrastructure is essential if we're going to reliably meet our Virginia customers' growing needs. Because we're a vertically integrated utility, we enjoy a natural hedge: the capacity we buy to serve our load is largely offset by capacity revenue that our own generation brings in. Consequently, the way the capacity market resolves doesn't really put customers at meaningful risk, so it isn't automatic that rising prices translate into bigger bills for them. During our latest semiannual rate case, net capacity expense made up roughly 1% of what customers pay. From then until now, we've identified various actual and possible build drivers—including doing away with the Reggie rider—that might substantially offset whatever net impact increased capacity expense has on customer bills; and remember, DEV's current rates are about 22% under the national average. When we submit our upcoming biennial filing next March, we'll examine how bills for customers are affected from a complete perspective, and those new rates should be in place before the year is over. While we wait for the new rates to kick in, and given that we hold a modest short generation position, we anticipate that increased capacity costs during the latter half of 2025, compared with what we had previously assumed, will create approximately a $0.04 headwind for 2025 — something we absolutely expect to beat. Although that effect is short-lived, from a broader standpoint it sends an unmistakable and strong message that strong price levels and continued spending on our infrastructure will remain necessary for many years ahead. Finally, just to be perfectly clear, every piece of financial guidance we provided on March 1 remains exactly as it was, and that covers earnings, credit, and dividend guidance alike. Now I'll give you an update on where things stand with our business review debt reduction efforts, which you can see laid out on Slide 5. Over the course of that review, we've announced deals amounting to roughly $21 billion in debt reduction. We've wrapped up the transactions involving Cove Point, East Ohio Gas, Questar Gas, and Wexpro, and we've also finished the DEV fuel securitization. That puts us at 72% of the target from our business review. Things are moving along well as we work to close out the two remaining debt reduction efforts on schedule: handing over public service company in North Carolina to Enbridge, and bringing in Stonepeak for noncontrolling equity financing on the Coastal Virginia offshore wind project. Let me give you a bit more detail on what to expect. Regarding PSNC, every party involved came to a comprehensive settlement toward the end of May, and an evidentiary hearing took place on June 11. A joint proposed order got filed with the commission on July 24, and that represents the last procedural move. Sometime during Q3, we expect the commission's final order to come through, with the closing taking place shortly afterward. Turning to CVOW, we secured Affiliates Act approval on June 26 — that's the first of 2 Virginia approvals we require from the State Corporation Commission. Over the past week, SEC staff filed their comments on the Transfer's Act and financing partner petition, which counts as the second of 2 Virginia approvals needed. Nobody else filed comments, and we see the staff's comments as constructive. A hearing is scheduled for August 27, and we expect the final order to arrive before this year is over. Regarding North Carolina, approval of the affiliate agreement is required for the financing. This week, comments came in from just one party — the NCUC public staff — and we consider their input helpful. From here, the process moves to commissioned hearings if any are requested, followed by a commission order. We still expect the CVOW financing partnership to close before the year ends, and we look forward to continued collaboration with everyone involved. Turning to financing on Slide 6: since our last call, we completed an issuance of $2 billion in enhanced junior subordinated notes. The credit rating agencies assigned a 50% equity credit to those tax deductible securities. In addition, we've put out about $400 million in equity via our ATM program — that's 80% of the midpoint of our annual guidance — along with approximately $100 million from our DRIP programs. As we told you before regarding the remainder of the year, we will wrap up ATM and DRIP issuance, finish one last long-term debt issuance at DEV, and apply the money from the PSNC sale and the CVOW partnership financing closings toward paying down debt even more and lowering interest expense. In closing, let me repeat that my confidence is strong when it comes to our ability to hit our financial plan. The post-review guidance was designed to be suitably conservative without being excessively so, so we can handle unexpected challenges that might arise. With that, I'll hand the call over to Bob.

Bob Blue

executive
#3

Thank you, Steven, and good morning. I want to kick off my comments by focusing on how we're doing when it comes to safety. Slide 7 shows that during the first 6 months of this year, our OSHA recordable injury rate for employees came in at 0.38%, which continues the favorable direction we've seen over the past 2 years. That's an encouraging beginning, yet safety means far more than a figure printed on a slide; it stands as our number one core value and reflects the welfare of our workforce. Driving workplace injuries down to 0 remains where we keep our attention. Now let's discuss CVOW. We're delivering this project within the planned schedule and budget, in line with the time lines and estimates we shared earlier. First, I'd like to point out the thrilling strides we've achieved with monopile installation. To date, 72 monopiles have arrived at the Portsmouth Marine terminal, which works out to 40% of the project's total. EEW, our partner, keeps delivering outstanding results, and we anticipate that deliveries will keep arriving at a steady pace over the upcoming weeks. Slide 8 illustrates how, on May 22, we kicked off monopile installation with the Orion, a heavy crane vessel from DEME. As of yesterday, 42 monopiles have been successfully put in place. Following an initial phase in which we properly calibrated our sound verification process to comply with our permits, we've managed to increase the pace of installation significantly, even completing 2 monopile installations within one day on July 21, and doing so again on July 28. The project brought in a second bubble curtain vessel last week — a key ancillary installation vessel. Each monopile installation involves deploying a bubble curtain around the pile driving location, as Slide 9 depicts. That second vessel will meaningfully cut down the time needed between installations; in short, we're on a confident path toward our target of 70 to 100 monopiles installed across the first of 2 planned installation seasons. Another significant milestone: scour protection installation for the monopiles got underway in June. Work has begun on 23 monopiles so far, which aligns with the final project schedule. Now let's move to Slide 10 for several additional permitting updates; every federal permit has now been received. That remains the same; regarding materials and equipment, we're on schedule and progressing very well. 2 of 3 offshore substation topside structures are finished and have been sent to SEMco and Denmark for outfitting, 33 transition pieces are fully fabricated, and 15 of those have reached the Portsmouth Marine terminal. All 161 miles of onshore underground cable is manufactured, and roughly half of the 600 miles of offshore cable has been produced. In fact, we anticipate starting export cable installation later this quarter. Our turbine manufacturing schedule is still on track. Tower fabrication for our turbines got started in June; worth pointing out is that turbine installation won't begin until 2025 according to our schedule. DEME recently wrapped up its support of a monopile installation campaign for Moray West, a project situated off Scotland's coast that has now successfully installed the identical Siemens Gamesa wind turbine model that CVOW will rely on. About 50% of the turbines are now in place, and power is already being generated by the earliest units. What we take away from that effort is going to help us when we install turbines on this project going forward. Shifting to onshore work. Our construction timeline hasn't slipped, and that covers civil work supporting overhead lines, horizontal directional drills, plus duct bank for the underground portion and the bores at the point where export cables reach land. On the regulatory side, back in November we submitted our 2023 rider filing, which covers $486 million in annual revenue, and on July 25 the final order came through, granting the revenue we asked for. Now to Slide 11. For this project, expected LCOE remains at $73 per megawatt hour with no change. Invested so far on the project comes to roughly $4.5 billion, and we're still aiming to reach about $6 billion in spending by the close of 2024. According to the quarterly update filing made today, unused contingency right now stands at $143 million, versus $284 million in the prior quarter. This drawdown on contingency is happening as we anticipated. Worth pointing out that unused contingency at present, measured as a share of remaining project costs, sits at 3%, which matches the same percentage recorded when we originally filed in November 2021, even though we are now about 33 months deeper into the project. Measured against total budgeted costs, the present contingency level still compares favorably to other major infrastructure projects we have examined, including ones finished in earlier years. Our team, our suppliers, and our partners have all heard us say it plainly: delivering this project within budget is what we expect. Finally, the project stands at 33% complete today, and Slide 12 lays out the major milestones still ahead. Now a few updates regarding Charybdis. The main crane structures and the Helideck structure have been installed since May, as you can see on Slide 13. Work on the upper leg is proceeding as planned. Main engine load testing has begun and is progressing on schedule. Main crane load testing will take place over the next few weeks. Please turn to Slide 14. The vessel now stands at 89% complete, which is up from 85% at the time of our previous update. Expected delivery remains late 2024 or early 2025, unchanged, and sea trials finishing successfully will signal that point, after which the vessel comes back to port for further work so it can hold turbine towers, blades, and the cells. The vessel's expected availability for supporting the present CVOW construction schedule is also unchanged, and we expect that work to begin in the third quarter of next year. As today's materials show, we have revised the project's current estimated costs, financing costs included, to $715 million, up from $625 million in the last quarter. Modifications needed to accommodate project-specific turbine loads, based on the final certified weights and dimensions of the equipment, along with additional financing costs, are what drove the increase. Thanks to these modifications, Charybdis will be able to handle the newest turbine technology design. Charybdis matters greatly not just for CVOW but for expanding the offshore wind sector throughout the U.S. The East Coast, and it's essential for growing a domestic supply chain further, since it offers a made-in-America answer for putting offshore wind turbines in place; we keep witnessing robust demand for using this ship once the CVOW commercial project wraps up. Now let's move to South Carolina, Slide 15; on July 12, we, together with the office of regulatory staff and additional interveners, filed a comprehensive settlement agreement in our electric rate case that's still pending, for the Public Service Commission of South Carolina to approve. All parties either signed on or didn't oppose, which is part of the settlement, and it shows how well everyone worked together during this process. A 9.94% allowed ROE and a 52.51% equity capital structure form the basis of the settlement, versus rates when we made our initial request in March, and once the fuel reduction and other elements are factored in, the rate request in the settlement would amount to a net 1% increase for residential customers' electric rate. Should it be approved, new rates take effect September 1; we're eager to keep collaborating with stakeholders in South Carolina. Shifting to data centers now, Slide 16.

Bob Blue

executive
#4

Like I mentioned earlier, we are stepping up to meet a massive, expanding, decades-long utility investment cycle. That spending is needed to serve resiliency and decarbonization public policy objectives, along with the extremely strong demand growth we are seeing right now throughout our service territory. Outside parties have taken note of this expansion. To give just one illustration, in 2024 Virginia earned the title of America's top state for business. That marked Virginia's sixth occasion at number one in CNBC's rankings — a record — and its third victory within 5 years. No other state has matched that record since the study started in 2007. Looking at full year 2024, our expectation is DEV sales growth in the 4.5% to 5.5% range, propelled by economic expansion, electrification and faster data center buildout. Notably, during July we set 6 new all-time peak demand records, and exactly as we anticipated, our customers probably never noticed these demanding load conditions, thanks to the high-quality operational performance our colleagues delivered. In Virginia, the data center sector keeps expanding; through July of this year we have connected 9 new data centers, which aligns with our forecast of 15 data center connections for 2024. On average since 2013, we have connected roughly 15 data centers annually. Even so, growth is speeding up by orders of magnitude, fueled by how many requests come in, how large each facility is and how quickly each facility's ramp schedule moves toward full capacity. We are doing what is required to keep our system resilient and reliable. Our accelerated plans for new 500 kv transmission lines and other infrastructure in Northern Virginia remain on schedule. During the PJM open window last December, we were awarded more than 150 electric transmission projects worth $2.5 billion in total. PJM's most recent open window opened on July 15, and investment needs are expected to be equal to or larger than before, as the RTO works to accommodate data center growth in Northern Virginia and elsewhere through additional transmission upgrades; we are moving swiftly alongside PJM, the SCC, local officials and other stakeholders to fast track critical projects. Our commitment is to pursue solutions that benefit our customers and the region's continued growth. That involves evaluating dispatchable generation needs, particularly in winter and on-site backup fuel storage. Along those lines, in June we submitted a petition to the SEC to build and run a backup fuel source for the Brunswick and Greensville power stations, in order to support operations and boost system reliability. Also, in July we revealed the acquisition of another offshore wind leasehold in North Carolina from Avangrid, which we see as an appealing option for future regulated offshore wind development, plus a request for proposals to assess the feasibility of developing small modular reactors at our North Anna site; taken together, these projects represent an all-of-the-above strategy for meeting rising demand. When we look at this demand growth, we consider the entire value chain — transmission, distribution and generation infrastructure investment — which has driven and will keep driving utility rate base growth. With those factors in mind, our view remains that additional regulated capital projects could arise later in our planning horizon and past it. As I've noted previously, whenever we evaluate extra capital, we apply four tests: whether customers can afford it, how it affects reliability, how conservative it keeps our balance sheet, and how well it fits our low-risk profile. Turning ahead, an updated IRP will be submitted in October. In last year's IRP, we incorporated substantial load growth plus spending on generation and transmission across the coming 15 years so that growth could be served, all while holding the cumulative average yearly increase in the customer bill under 3%. The newest PJM DOM zone load forecasts, presented on Slide 17, differed only slightly from the prior year's figures, and together with our efforts to find the optimal approach to serving this load, they will shape the planning behind this year's IRP. Before wrapping up my remarks, I want to address data center cost allocation, shown on Slide 18, an issue investors have frequently raised. Our practice is to regularly review cost allocations and the associated rate designs to confirm they are equitable and sensible. Every 2 years, the SEC examines distribution and generation rates, and our next biennial review falls in 2025. Transmission rates, by contrast, come under SEC review annually through our rider T1 proceeding. Under either proceeding, should the expense of serving one or more customer classes shift over time, costs get reallocated so that every class pays its fair share. Suppose the expense of serving a particular class rises; that class's allocation then goes up, while every other customer's allocation goes down. The clearest illustration in recent years has been the sizable shift of transmission costs away from residential customers and onto bigger energy users like data centers. Residential customers' share of transmission cost has fallen 10% since 2020. Meanwhile GS4, the class using the most energy, has seen a 9% increase. This mirrors both a larger portion of our system being composed of data centers and a change in the way transmission costs are divided among the classes. In recent years we've also put other rate mechanisms in place that, alongside our regular and routine evaluation of cost allocation and rate design, guarantee costs are shared fairly across rate classes. Our history of partnering with data center customers is long and thrilling, and we're eager to keep serving every one of our customers going forward. That brings me to a summary of our remarks on Slide 19. Safety results this quarter were excellent, yet additional effort is needed to bring injuries down to 0; we restated our financial guidance. Our offshore wind project remains on time and on budget. We keep making the investments required to deliver the reliable, affordable and progressively cleaner energy that fuels our customers daily. And execution is our sole focus, 100%. We recognize we have to deliver, and we will. With that, we're ready for your questions.

Constantine Lednev

analyst
#5

Let's begin with how things are going offshore. You've clearly made a lot of headway during pile driving season; it appears you've managed to reach that goal of 2 monopiles each day. Might we see you go beyond the upper bound of the 70 to 100 range planned for this year, and are there any obstacles left that we ought to consider?

Diane Leopold

executive
#6

Diane Leopold here. Yes, we're pleased that we've reached the two, and the second vessel we have will allow us to remain in production mode for a greater portion of this season. At the moment we're basically at the peak of the season as the weather begins shifting slightly. It's possible we won't be able to keep achieving that as frequently. So our confidence in the 70 to 100 is quite high, and remember as well that over this season, we need to install at least sufficient pin piles to set one of the offshore substations. That's something we must factor in. So on the whole, I'd say the team—both our own internal group and the DEME team—is performing wonderfully, and 70 to 100 is an excellent range. We have a lot of confidence in it.

Constantine Lednev

analyst
#7

All right. You brought this up regarding resource adequacy. Clearly, the Dominion zone breakout came out much earlier this week, and it was significant. Could you discuss how capacity plans are changing with respect to the upcoming IRP? Also, is it possible that right now you're seeking additional Chesterfield style gas projects?

Bob Blue

executive
#8

That's right, Constantine. As we consider where we're headed, at the Investor Day in March we provided our 5-year capital plan, and every year we'll refresh it. That's what we expect to do. After that, in the fall, our IRP gets filed. That also gets refreshed each year. And a longer-term perspective is what it takes. However, regarding demand growth, as the slide shows, we observed a large increase with PJM from their '22 to '23 forecast, while from '23 to '24 the rise was a little more modest — actually much more modest. Therefore, as we said during the prepared remarks, certainly, later in the plan there could be some chances to raise CapEx, and plenty of data points show generation is needed, which for a while now we've been stating, both renewable and dispatchable, here in our Virginia service territory. So next year the capital plan gets refreshed. An updated IRP will be ready, based on the PJM forecast, which compared with last year's was not hugely different, and on ensuring we can satisfy our customers' demand, we'll stay very focused. In Virginia, this is a really exciting time. Helping the state remain #1 for business going forward is something we're very excited about, and as outlined in the plans we've put forward, that will call for investment in distribution, transmission and generation.

Nick Campanella

analyst
#9

I’d like to ask a bit more about what you said regarding the auction, since I realize you covered that fairly fast. For next year, your short generation creates a $0.04 impact. How will that appear once we reach '26? You’ll have more generation entering service, correct? I’m basically attempting to work out whether, if conditions remain quite tight in '26 and '27, that $0.04 persists. Could you also elaborate on the mechanism, explain how the vertically integrated VIU model differs from the T&Ds, and clarify why this dynamic exists?

Steve Ridge

executive
#10

Sure. Nick, I’ll handle that; as I said, we have a natural hedge, meaning the generation we own bids into the capacity market and gets the elevated price, or will get the elevated price you observed clearing; therefore, that revenue is credited to customers. At the same time, as a load-serving entity, we must also procure sufficient capacity to meet our load, and we will pay that high price too. So by nature, we hold this hedge of essentially collecting revenue while incurring expense. The cause of a modest hurt in the latter half of '25 tied to this is that we hold a short position between the organic generation we own and bid into the market and the load, and usually we meet that through imports from PJM, which isn’t new. That short position falls somewhere from 2,000 to 3,000 megawatts. Looking ahead, the reason it is leakage, if you will, is that we are between rate cases. And we could not — owing to when this auction occurred, specifically, we could not put the expected cost into the cost of service we submitted during the last biennial, and we cannot adjust rates before the end of 2025. So for 6 months, or I suppose 7 months, beginning in June. For 7 months, we will effectively absorb the cost of that leakage; after that, it will enter rates and those rates will take effect. Capacity sits within base rates. It is a prudently incurred cost; customers can be charged for it, which is why we offered some remarks about the possible effect on customers. So this is extremely, extremely temporary. It stems in part from our inability to raise rates under the most recent biennial settlement. It relates to the timing of this specific auction; and moving forward, we fully anticipate recovering 100% of this leakage through our rates from customers. That is why it is temporary. And that is why we more or less said we wanted to be transparent with people by saying, "Hey, here’s the math, here’s how it works. This is the situation, and beyond that, it points to something that is only short-term when you look at the larger picture, which was mentioned in the previous question. This is a steady indication of what we have kept stating: the requirement for step-by-step regulated spending will stretch out our growth rate across a longer stretch of time as we deploy increasingly more capital into our system. That is the reason we have this built-in offset. That is the distinction between the vertically integrated model and, if the short position continues, which it will, for a certain stretch, we will bring in offshore wind, we will bring in the Chesterfield CTs; so — yet demand keeps rising. So while that continues, we will consider methods to become essentially self-sufficient, just as we were previously, as we close the gap on demand. But when it comes to financial effect, it really is only a short-lived matter.

Nick Campanella

analyst
#11

All right, that's extremely useful, and I'm grateful for it. Regarding the Charybdis shift, you're at 90% or 89% done, and the costs have risen by $90 million. Could you briefly explain what's causing that, and why this ought to genuinely be the final revision?

Diane Leopold

executive
#12

Certainly. This is Diane once more. As Bob mentioned, with these modifications, there really was no alteration to the base ship, so those costs stayed flat; however, modifications of this kind simply aren't out of the ordinary. The ship had to be ordered well before the final turbine design for our project was finished. Consequently, given the final loadings, extra <<inaudible>> reinforcement is needed for the towers and to support the cantilever blade rocks. That's essentially the cause. There's no scope change of any sort in the ship; it's merely a few of these routine modifications; we're therefore handling quite a lot of them. That work has already begun — and much of it will take place as we're completing the internals of the ship, so to speak, finishing the piping, the electrical work, the crane loading. We'll head out for sea trials, after which we'll bring it back and complete the remaining portion of that work, ensuring we can get the sea fasteners on to support our particular towers, blades and the cells.

Steve Ridge

executive
#13

Also, Nick, I want to mention that roughly $55 million of that higher amount is strictly CapEx, while the remaining portion relates to financing expenses. Our method for funding this vessel involved a lease agreement with a banking consortium. We've been collaborating with them, and they've proven to be excellent partners throughout this process. We do not anticipate any further increases. That's what I'll say. Our confidence in this is strong. By cooperating with this consortium, we've managed to mitigate the possible cost escalation from a financing cost standpoint. Consequently, we see this as under $0.01 in terms — I believe it comes to roughly $0.05 regarding 2025 costs because of this rise; so financially it isn't significant, but once more, I wanted to be open about it.

Jeremy Tonet

analyst
#14

I'd like to shift the discussion, if that's alright, over to Millstone and the potential for data center colocation at that site? Could you share any additional perspective on how that looks going forward? And perhaps also, how do you handle the various stakeholder concerns?

Bob Blue

executive
#15

Absolutely. Jeremy, as we've talked about previously, Millstone is a tremendous resource for us in New England. It supplies more than 90% of Connecticut's carbon-free power. And as you're aware, 55% of what it produces is locked in at a set rate until late 2029, with the rest of the generation substantially hedged through our program; so we're working hard with several counterparties to secure the greatest value for Millstone after the existing PPA expires. We've definitely shown interest in longer-term PPA arrangements. Over the past year, there's been legislative movement in New England focused on enabling additional future procurement. We'll need to wait and see how that plays out. We're definitely receptive to the concept of a data center located on-site. We keep examining that possibility; we fully recognize that any colocation arrangement must be sensible for us, for a prospective partner, and for Connecticut stakeholders. So there's nothing new to report on that front. We're still searching for ways to maximize Millstone, and it continues to be an outstanding asset for our company.

Jeremy Tonet

analyst
#16

Understood. That's clear; and I was hoping to dig a bit deeper, if you could maybe speak to some other aspects here; but regarding that ISA protest before FERC, where we could potentially get some news tomorrow. I'm just curious whether you have any views on this matter that you'd be open to sharing?

Bob Blue

executive
#17

Jeremy, we aren't involved in that case. So anything I'd say wouldn't be properly informed. So that decision is up to FERC and the other parties.

Jeremy Tonet

analyst
#18

Understood. You said, I believe, that expenses tied to net capacity used to represent just 1% of what customers pay. Any sense of how that might change following the auction we just had?

Steve Ridge

executive
#19

The figure will remain quite modest, Jeremy. We avoid viewing bill impacts as coming from single, separate causes. Instead, our approach is to consider every element and component involved. As I noted earlier in my prepared remarks, the Reggie rider has been removed. That amounted to $3 or $4 each month. So when we return to the commission in March with a holistic approach, we're very, very focused on making sure customer bills are a high priority for us and making the best possible offer to our customers; so I can't give you any specific information about this, but it's not going to be a big number.

Operator

operator
#20

That brings us to the end of the portion set aside for questions and answers, and with that, this morning's conference call is officially finished. Feel free to leave the lines now, and have a good rest of your day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Dominion Energy, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Dominion Energy, Inc. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Dominion Energy, Inc. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.