David McFarland
executiveGood morning, and thank you for being with us on Dominion Energy's Q4 2024 earnings call. The earnings materials, which include today's prepared remarks, contain forward-looking statements and estimates that carry various risks and uncertainties. For a discussion of factors that could cause results to differ from management's estimates and expectations, please refer to our SEC filings, including our most recent annual report on Form 10-K and our quarterly reports on Form 10-Q. This morning, we'll discuss certain measures of our company's performance that differ from those recognized by GAAP. Reconciliations of our non-GAAP measures to the most directly comparable GAAP financial measures, which we can calculate, are contained in the earnings release kit. I encourage you to visit our Investor Relations website to review the webcast slides as well as the earnings release kit. With us on today's call are Bob Blue, Chair, President and Chief Executive Officer, Steven Ridge, Executive Vice President and Chief Financial Officer, and Diane Leopold, Executive Vice President and Chief Operating Officer. I'll now hand the call over to Bob.
Bob Blue
executiveThanks, David, and good morning. About a year ago, we completed our thorough business review and set out five core principles for a repositioned Dominion Energy: strategic simplicity, steady long-term financial performance, a conservative balance sheet, a secure dividend, and delivering an outstanding customer experience that would position us to champion and achieve balanced policy frameworks and sensible regulatory results. You heard from me and directly from board members that we would all be held jointly accountable for the company's performance going forward. Finally, we committed to devoting 100% of our focus to executing our updated plan successfully. A year later, none of that has changed. These commitments are just as essential to who we are today as they were a year ago. We recognize that earning back your confidence calls for steady performance over time. While this new chapter for our company is still fairly young, the beginning has been encouraging. Looking back at 2024, our operating earnings per share landed in the upper half of the guidance range we provided, even with weather-related challenges and an extraordinary storm restoration push in South Carolina after Hurricane Helene, one of the most devastating storms the region has ever experienced. The results we've seen from regulators in the base rate proceedings in South Carolina and North Carolina, along with several rider cases in Virginia, demonstrate that we can collaborate with regulators and stakeholders to reach outcomes that benefit customers and shareholders alike. They also reflect substantial de-risking of the Coastal Virginia Offshore Wind Project, achieved both by continuing to hit major milestones on schedule and by completing a 50% non-controlling equity financing, which has meaningfully lowered project risk for our shareholders. I'll share additional thoughts on CVOW shortly in our prepared remarks. We accomplished all that even as our safety results for employees came close to the best ever recorded, and while moving forward with a strategy that draws on every available source to satisfy our customers' swiftly growing energy needs dependably and at reasonable cost — needs that encompass the biggest grouping of data centers anywhere on earth. At this point I'll hand things to Steven for the financial portion, after which I'll cover further progress on carrying out our plan.
David McFarland
executiveThank you, Bob, and I appreciate all of you being on the call today. On slide five you can see that 2024 full-year operating earnings came in at $2.77 per share, landing in the upper half of our guidance range, even though weather ran $0.03 worse than typical. For the full year 2024, GAAP earnings stood at $2.44 per share. Our fourth-quarter operating earnings were $0.58 per share, and weather across our utility service territories was normal for that quarter. Q4 GAAP earnings came to $0.15 per share. As we always do, Schedule 4 of the earnings release kit summarizes every driver behind earnings versus the prior period, while Schedule 2 summarizes all adjustments made between operating and GAAP results. Moving to earnings guidance: we have tightened our 2025 operating earnings per share outlook to a range of $3.28 to $3.52, which includes RNG 45Z credit income, while keeping the midpoint at $3.40 as before. The reason we give a range is mainly to account for swings in weather from normal. We are reaffirming guidance for annual operating earnings growth of 5% to 7% through 2029, measured off the 2025 midpoint of $3.30, and that figure leaves out RNG 45Z credit income because that credit sunsets legislatively at the close of 2027. Keep in mind that we still expect variation inside that range stemming from the Millstone refueling cadence, under which a second planned outage is needed once every third year; we are also reaffirming the dividend guidance we gave previously; our expectation is to hold the dividend at its current level of $2.67 per share on an annual basis until we reach a payout ratio aligned with the utility industry. Now to capital investment: we have raised our five-year capital forecast covering 2025 through 2029 to $50 billion, which is a 16% increase over our earlier guidance. Across distribution, transmission, and generation we see a need for added investment to keep reliability intact as demand keeps growing in our service areas. In line with our heightened emphasis on transparency, the appendix of today's materials contains comprehensive, detailed disclosure, so I will simply highlight two takeaways. First, roughly 80% of the capital increase sits at Dominion Energy Virginia, pushed by greater transmission, distribution, and nuclear subsequent license renewal spending, and second, 60% of the updated capital spend will qualify for recovery through rider mechanisms, subject to regulatory approval; this is an exciting update, and we have confidence in our ability to execute for our customers' benefit. Beyond today's forecast, we still see chances for further investment throughout the value chain, weighted toward the latter part of the decade and after. We will fold those opportunities into future updates when their development status justifies it. Before I turn to the financing plan update, let me affirm our dedication to balance sheet conservatism, which slide seven illustrates. Across the five-year plan, we expect parent leverage to stay consistently under 30% and FFO to debt to come in around 15%. Last, our targets are mid-BBB range credit ratings for the parent company and single-A range ratings for our regulated operating companies. Nothing has changed on that front. Our ability to keep securing inexpensive capital for our customers depends heavily on the long-standing commitment we have shown to earning and preserving these ratings. Now, if you look at slide eight and the financing plan, we are giving you a five-year view of sources and uses. Strong cash flows from operations, paired with a balanced combination of outside financings, meet our forecasts for capital investment and dividends. Since our previous update, we have raised external financing somewhat across debt, hybrid, and equity issuance. On equity specifically, slide nine shows an increase for 2025. As of today, we have already sold $600 million via forward-settled sales through our current ATM program, we expect to issue $200 million over the course of the year via DRIP programs, and we expect the remaining portion of the roughly $300 million requirement to be met through the ATM. Past 2025, our guidance for common equity issuance is unchanged. Given our substantial growth capital spending program, we consider this pace of steady equity issuance through existing programs to be suitable for keeping our consolidated credit metrics inside the guidelines for our strong credit ratings category. Before handing things back to Bob, I want to say that we are happy with how we performed financially in 2024, though what really matters is how we execute from here. Since the March 1st meeting, tailwinds have appeared, such as more regulated capital investment opportunities, and headwinds have appeared too, such as higher interest rates. What has stayed the same, however, is our confidence in the plan, which was built to be appropriately conservative while not being unreasonably so. With that, I will hand it back to Bob.
Bob Blue
executiveMoving to slide 10 and the topics of safety and affordability: in 2024 we posted safety results close to a record, as tracked through our employee OSHA injury recordable rate. As for affordability, our prices remain below both national and regional averages, and we are sharply focused on making sure our service is not only reliable but also stays appropriately affordable. Now, on the Coastal Virginia Offshore Wind Project, we gave a number of updates last week, but I want to open with a few highlights on slide 11. To begin, the project stands at 50% complete and remains on schedule to finish in 2026. Second, CVAL enjoys backing under Virginia law and has secured approval from the State Corporation Commission along with federal agencies. Third, CVAL will add badly needed new generation to sustain America's AI and cyber preeminence in the world's largest data center market. On top of that, the project offers the quickest and most cost-effective route to bringing 2.6 gigawatts of supply onto Virginia's grid. And last, CVAL has generated roughly 2,000 direct and indirect American jobs and produced $2 billion in American economic activity, while also holding strong bipartisan support from Virginia's state and federal elected leaders. To sum up, this project aligns with the objective of securing American energy dominance and forms part of a comprehensive all-of-the-above energy strategy aimed at meeting growing energy needs affordably. Turning next to recent construction progress and milestones: during 2024 we wrapped up a highly successful first season of monopile installation, and through this winter work has carried on with the export cableway, transition pieces, and, within the coming days, offshore substation installation. As slide 12 shows, we started installing transition pieces on December 31st and have since finished 20 in total. The first offshore substation jacket and topside arrived in Portsmouth at the end of January and will start installation later this month. The other two offshore substations remain on track for delivery this summer and installation in the fall, following completion of monopile season in October. On materials and equipment, 130 monopiles have been loaded out so far, with 116 successfully delivered and 14 more currently in transit to Virginia. Roughly 75% of the project's monopiles are either installed or awaiting installation. Our partner EEW keeps making strong progress, and we expect deliveries to continue steadily over the coming weeks. Of the project's 176 transition pieces, all have been rolled. Among them, 152 have been successfully steel welded, and of those, 91 are complete, which is over 50% of the total. We expect the final transition piece to be finished in October. In addition, the manufacturing schedule for our turbines remains on track. As a reminder, Siemens Gamesa, the project's wind turbine supplier, is building the same turbine model for CVAL that has already been successfully fabricated, installed, and is now operating at the Moray West Offshore Wind Project. Eight towers are done, with another 31 in progress. Blade manufacturing has started, and cell production should get going next month. On the regulatory side, we filed our quarterly offshore wind construction update on February 3rd, and with it came a detailed explanation of why project costs moved from $9.8 billion to $10.7 billion. Let me offer a few thoughts. First, as you'd imagine, this increase is disappointing. Our organization takes real pride in finishing on schedule and within budget. In the 40 months since we submitted the original cost figure, we've worked tirelessly as an institution to stay true to that initial estimate. In the end, even though roughly $300 million was budgeted for network upgrades—more than enough under PJM's initial estimates—those estimates turned out to be too low. Any new electric generation resource built in PJM, whatever its type, gets assigned costs by PJM that are considered necessary to integrate it effectively and to keep the grid reliable and stable. PJM's higher network upgrade estimates mirror the substantial growth in demand, which calls for additional generation and transmission resources system-wide. It's worth pointing out, I think, that total costs for other project inputs, offshore scope included, have stayed consistent with the original budget. Second, network upgrades have no effect on project construction or timeline, and they were by far the largest unfixed project cost. We now see those costs much more clearly, though the picture isn't final. In addition, we've reset contingency to 5% of remaining project costs. Third, cost sharing and risk sharing are functioning as designed to protect customers and shareholders. Under the cost sharing settlement Virginia regulators approved, this cost update is expected to raise residential customer bills by an average of $0.43 per month across the life of the project. And the updated LCOE still compares very favorably against new generation alternatives, including solar, battery, and gas fired generation. For our customers, CVAL remains among the most affordable energy sources. Of the $900 million increase, 80%, or $700 million, is expected to be recovered through the rider and added to rate base, subject to regulatory approval. Stonepeak, not Dominion Energy shareholders, will bear 50% of the non-recoverable portion of the increase. Finally, I know investors are watching closely for the likelihood of further cost increases. I understand how critical it is to deliver on any guidance we give. The project remains on time, and we're committed to delivering it consistent with the now updated cost estimate. We don't have perfect visibility into what information PJM will use to finalize costs by mid-year, but we've done substantial analysis around the latest estimate, and that analysis informs our updated cost estimate. I have confidence in our updated estimate, and I believe that if a revision up or down on PJM network upgrades arrives in July, it would not be of a similar magnitude. To wrap up, a few updates on Charybdis, which you can see on slide 16. That vessel now stands at 96% complete—up from 93% when we last held an earnings call—and sea trials are currently in progress. What you see there is an image of the 30,000-ton vessel, fully jacked up to its maximum height of nearly 400 feet. Our expectation remains that Charybdis will finish sea trials in early 2025, in line with the schedule we previously gave, and that it will be handed over to CVAL during Q3. The vessel's cost likewise remains unchanged at $715 million. Now moving to data centers, where we keep seeing encouraging developments, so allow me to provide a few updates. First, the current situation. By a wide margin, Virginia is home to the biggest concentration of data centers anywhere in the world. Since we began tracking, roughly 450 data centers have been connected by us, accounting for close to nine gigawatts of capacity. As of today, data center sales make up around 26% of DEV's total sales. What draws data centers to Virginia is connections to world-class fiber networks, the state's appealing business climate, a trained workforce that is available, and access to energy from us that is affordable, reliable, and increasingly clean. In recent years, to meet this demand, we have pushed forward electric transmission projects that bring both new and upgraded infrastructure, enabling continued connection and expansion of data center customers in Eastern Loudoun County, Virginia.
Bob Blue
executiveThe work so far has involved reconductoring lines, growing our substation infrastructure, and constructing a 500 kV transmission line, which is on track to wrap up by the end of 2025 as planned. Also, only last week, the SEC gave the green light to an additional 500 kV line serving Eastern Loudoun County; we anticipate that line will be serving customers by the end of 2027, and it will keep us ahead of the fast-rising power demand in the region. Second, what comes next? Load growth in the PJM DOM zone is unlike anything we've seen. That growth keeps accelerating by orders of magnitude, fueled by: one, how many data centers are asking to connect to our system; two, how large each facility is; and three, how quickly each facility's ramp schedule moves toward full capacity. For some context, as slide 17 shows, PJM has just refreshed its forecast for the DOM zone, and it now projects peak summer load growth of roughly 6.3% annually over the coming 10 years. To put that into perspective, the resulting peak load projected for 2034 has risen from 26.1 gigawatts in the 2022 PJM estimate to 41.5 gigawatts in this year's estimate — a jump of nearly 60%. Earlier in the year, we modified the way our system processes requests for new delivery points; with this update, load requests can be grouped into batches and handled according to when they arrive. Since we began sharing information about these adjustments, customer demand has grown. Slide 18 reflects our revised contracted capacity for data centers. As of December 2024, we have roughly 40 gigawatts at different points in the contracting process, compared with about 21 gigawatts as of July 2024 — a gain of 19 gigawatts, or 88%. Just to restate, these contracts belong to one of three groups: first, substation engineering letters of authorization; second, construction letters of authorization; and third, electrical service agreements. When customers move from one to three, the financial commitment and obligation on their side increases. Right now we are examining more than 26 gigawatts of data center demand at the substation engineering letters of authorization stage — meaning a customer has requested that the company start the engineering work needed for new infrastructure to serve them. That compares with roughly 8 gigawatts in July 2024, a remarkable 245% increase. We've looked at the data from several angles, and we certainly believe part of this growth comes from the new batch system, which naturally gives customers an incentive to enter the process early; but what can't be denied is that data center growth in Virginia is not slowing down. Actually, that growth is speeding up, and we are doing everything possible to seize this opportunity. In addition, roughly 5 gigawatts of data center demand now have executed construction letters of authorization—agreements that let work start on the distribution and substation electric infrastructure those projects require. Should a customer decide to walk away at this point, the company must be reimbursed for costs incurred through that stage. Meanwhile, the approximately nine gigawatts under electrical service agreements, or ESA, represent contracts for electric service between Dominion Energy and a customer. Since July of 2024, that number has risen by nearly a gigawatt. Each contract is structured as its own separate account. Once a customer enters into an ESA, they're committing to a fixed annual electricity volume, often structured under ramp schedules where the contracted usage increases over time. As Steven mentioned, this all points to opportunities for additional investment across the value chain stretching out over many years. Turning to slide 19, I want to highlight a few additional business updates. To start, here's an update on the transmission business and the joint planning agreement involving AEP and FirstEnergy. In its open window process, which remains ongoing, PJM has shortlisted a set of projects — some ours and some jointly proposed — with final approvals expected this month. Dominion's portion of the joint planning agreement will produce roughly $1 billion in incremental capital spend within the five-year plan. Combined with our other DEV transmission projects, that brings annual transmission capital spend to more than $2.8 billion starting in 2027, up from the $2.5 billion we had forecast previously. Next, in South Carolina, lawmakers are in session and are still assessing possible energy legislation. We appreciate the considerable time the legislature has devoted to this important topic so far. We've stated previously that our commitment is to support South Carolina's growing economy. That said, as our testimony has made clear, DESC's regulatory structure creates regulatory lag, which makes it virtually impossible to earn the return we're allowed—especially when measured against regulated jurisdictions elsewhere in the Southeast, including Virginia. Turning finally to Millstone: the plant provides more than 90% of Connecticut's carbon-free electricity, and 55% of its output is secured by a fixed-price contract that extends through late 2029. Our hedging program keeps substantially reducing risk on the remaining output, and we've refreshed that program in the appendix to today's materials. In 2024, Millstone delivered strong results with a 92% capacity factor, consistent with what we expect from exemplary performance and a reflection of our unwavering commitment to safety and best-in-class operations. You're probably aware that New England—and Massachusetts in particular—has seen legislative efforts lately intended to allow for further nuclear power purchases down the road, and we've continued working with several parties in that region so Millstone gets the greatest possible value. In addition to procurements backed by the state, we're still looking into whether we can back incremental data center activity. Our strong view is that any data center path has to be developed jointly with Connecticut stakeholders. At present, we have no timeline for any potential announcements. We're staying focused and will continue to share updates as things move forward; with that, let me recap what we've said here on slide 20. Our safety results this year came extremely close to a record. On March 1, we reaffirmed our guidance for the long-term growth rate of operating earnings per share, along with our credit and dividend guidance, and we tightened the range for our 2025 operating earnings guidance. CVAL is still on track, with strong cost sharing that shields both customers and shareholders. Working alongside policymakers, regulators, and stakeholders, we keep making the investments required to supply energy that is reliable, affordable, and increasingly clean — the energy that powers our customers each day. And our attention is entirely on execution, at 100%. We understand we have to keep delivering, and we will. With that said, we're ready for your questions.
Shar Pourreza
analystHey, guys. Good morning.
Bob Blue
executiveMorning, Shar.
Shar Pourreza
analystGood morning, Bob. So, regarding CVAL, given the news we got earlier this month, could you expand a bit on what variability is left across the projects? If supplier component deliveries slip, how much room does the schedule have, how would standby costs be recouped, would the suppliers bear them, and is there anything new on how you view additional wind projects given what you've learned from CVAL one so far, plus the outlook for policy and tariff headwinds coming out of DC? Thank you.
Bob Blue
executiveOkay, Shar, you packed quite a bit into a single question, so let me try to address the different parts one by one, and I’ll have Diane speak a bit about where things stand on the project and on de-risking. We’re in a strong position on this project, and we feel quite confident in the estimates we just provided, while recognizing that more data is still coming from PJM regarding network upgrades. Still, we’ve done substantial work using the best information available to us. The data we’ve relied on so far appears consistent with what PJM is reviewing, and we believe that leaves us in a fairly good position. Let me say a little about tariffs, since you raised that, and then I’ll hand it to Diane to discuss the overall de-risking effort on the project. It’s really too soon to determine how possible tariffs could impact this project. What I can say is that remaining spend outside the United States is approximately $2.5 billion, with most of that coming from Europe, and only part of it involving components that would contain steel or aluminum. As for possible steel and aluminum tariffs specifically, generally, tariffs of this kind are not meant to cover most finished products. We would view the CVOW components as finished products. That said, we don’t have the annexes that go with the executive order. We can’t know which, if any, portion of our remaining spend might be subject to tariffs. These are finished products that contain some steel and some other materials, so it isn’t as straightforward as taking a contract value and applying a percentage. For instance, the cells contain thousands of components. Blades, as most people know, do not contain steel or aluminum. If the steel and aluminum tariffs do take effect, that won’t happen before March 12, so we ought to have better insight before that date. The past may not predict the future, but if these tariffs take a form similar to those imposed in 2018, they largely would not apply to CVAL at all. Then finally—and Diane will discuss how we’re progressing on de-risking the project—it’s worth keeping in mind that we have $200 million of contingency within the current project budget of $10.7 billion-$11.3 billion. 50% of costs are recoverable from customers, and costs are shared 50/50 with Stonepeak. Diane, would you like to say a little about where we are in development?
Diane Leopold
executiveAbsolutely. Good morning, Shar. When I consider the risk, the first thing I do is look at our current position. Every permit we need is already secured. We've purchased all of the materials. Fixed-price contracts are in place for all the major equipment. Fabrication is progressing very well. Deliveries of that fabricated equipment are arriving right on schedule, and installation work has been advancing on track. So as I assess how the suppliers are performing while we move forward, with us now at 50% complete, risk is naturally continuing to come down. Take DEME as an example, with the vessel and installation logistics. During the first piling season, we kept improving and reached a run rate of 25 monopiles a month. This winter, as we've observed, transition piece installation and cable installation are proceeding exactly on track. Looking at which costs remain unfixed, we've discussed the final estimate on PJM that we feel good about. There's fuel for all the vessels, and there's project management; we need to finish fabrication, which is going very well; and we need normal weather. So we feel really comfortable about where we stand and how the suppliers have been performing.
Bob Blue
executiveShar, let me come back in on that. You brought up projects down the road as well. It probably won't shock you that our attention is squarely on this project and on delivering it in line with the schedule and the budget we've discussed. There are a couple of additional leases we hold. The plan carries no capital tied to those leases, and we'll simply watch how things develop going forward; the priority, though, is this project. Shar, did we cover all the pieces and parts you raised, or is there anything we left out?
Shar Pourreza
analystDavid, I'll just add < > Back on Slide 17, where you see that PGM forecast 2034, summer peak of 41.5%. We we would suggest that the increase we've seen in our Q is not fully reflected in that PJM update, it's a little bit backward looking. And to Bob's point, and to your question, will all of the amount that we're seeing in that first phase, ultimately convert. We don't know for sure. Many of them do in the past. And as we've moved further from down the column, we've seen increasing conversion rates up to 100% from the second to the third bucket. So again, I think it's a sign, a bullish sign. Will all of it ultimately convert. We don't know. We think a lot of it will, and that to us is a bullish sign of the ability to continue to invest across the value chain, in support of those customers in a low-risk regulated environment.
Nick Campanella
analystHey, appreciate you taking my questions. Good morning. Hi, Lauren. So that revised gigawatt figure on the data center side is a really big number, and I'm just kind of curious. First I'd like to confirm that this comes on top of what PJM has sort of released here at the start of the year. And then second, how do you sort of view the timeline for folding some of that into the plan within the current decade? And should we be thinking about some sensitivity for each gigawatt of new data center hookup? Is there a CapEx amount, whether for transmission or generation, that would be needed for that? Thanks.
Bob Blue
executiveYeah, Nick, is that within PJM? No — the gigawatts sitting in the substation engineering phase aren't part of the PJM forecast. There's no real rule of thumb tying any given number of gigawatts to the capital plan and so on. What matters is that everyone grasps that data center demand across Virginia, northern Virginia, and Loudoun County remains very substantial. The figures bear that out. To give you a sense — I know some folks may misunderstand Loudoun specifically, regarding how much additional capacity is available there. When you look at the transmission work we have underway, including those two 500 kV lines from our prepared remarks, that adds 6 gigawatts of capacity in Eastern Loudoun by itself. So the system in Eastern Loudoun has room, and data centers keep growing outward from Loudoun County, especially into neighboring counties along Interstate 95. Data center growth is also happening quite substantially in the Richmond metro area. That demand keeps coming, and we're very focused on being able to serve it in a way consistent with our mission of reliable, affordable, increasingly clean energy.
Nick Campanella
analystHey, thanks for that. So, following up a bit on what you said about Millstone and the chances of landing some kind of incremental large customer for the portion that isn't fixed yet — there seems to be a lot of emphasis on additionality whenever colocation is involved in any form. Could you maybe weigh in on whether you'd view that as necessary before pursuing a contract opportunity there, or what catalyst we ought to be watching next to gauge whether this is potentially heading in the right direction? Thanks.
Bob Blue
executiveI can't hand you a catalyst to watch for. As we've said, this has no timeline. Among the potential large user customers we've spoken with, additionality isn't essential; sure, they bring it up, but it doesn't act as a gating item. So we'll keep talking with potential data center colocator customers, with the states of Massachusetts and Connecticut, and with others in New England. And we'll continue to stick with what we've stated quite clearly: we need to make sure the interests of stakeholders in Connecticut are taken into account as we think about this very valuable asset.
Nick Campanella
analystAll right, thank you very much.
Jeremy Tonet
analystGood morning. Hi there, Jeremy. Hey. Hey. I'd like to dig a little deeper into that Virginia data center opportunity—that's quite a big jump, as you described. I'm curious whether you could say more about how stakeholders have reacted, and really, just thinking about this load creating extra build pressure, plus your thinking on build headroom broadly speaking.
Bob Blue
executiveSure, Jeremy, excellent question. Virginia policymakers are paying close attention to data center expansion since they recognize the economic gains it brings. That's evident in communities that already host a significant volume of data center load. Property tax bills—take Loudoun County—are much lower than they otherwise would need to be absent the tax revenue flowing in from data centers; that segment of the economy, and making Virginia a tech hub, matters a great deal to Virginia stakeholders, especially Governor Youngkin. He brings it up often. There's real interest in seeing data center growth continue. When more megawatt-hours get sold to data centers, the total costs get spread across a bigger pool of customers, which can actually assist with customer bill headroom. I realize there's frequent debate over whether our data centers are paying their fair share, or whether other customer classes are subsidizing data centers. Arguments of that kind—about one customer class subsidizing another—have existed since utility regulation first began. In Virginia there are always mechanisms to handle that, especially through biennial reviews, so my expectation is that in the biennial we file in March, the commission will take up this matter, and I'm confident their decision will ensure data center growth can continue in Virginia in a manner that works for all Virginia customers. This simply benefits Virginia's economy, and it's vital to keep it going.
Jeremy Tonet
analystUnderstood. That's useful, and could we pick up with the biennial? I'm just curious about how things stand overall with stakeholder engagement? And apart from affordability, which you described, are there any other major matters to work through? I'm simply trying to figure out what lens we should use for Virginia's regulatory process at this stage.
Bob Blue
executiveOur plan is to file a fairly uncomplicated rate case in Virginia. As I believe a lot of people are aware, a prescribed ROE existed during the last biennial. That isn't the situation this time around. There are a couple of relatively new judges sitting on the SCC — they've been on the bench for a little less than a year. When we consider how we're positioned in a rate case, reliability and affordability come first for us. Both are extremely strong in Virginia. Among stakeholders, we're widely viewed as a highly dependable supplier of electricity. As we noted in our prepared remarks, our rates remain under regional and national averages. We're positioned well. The broader climate heading into the case, in my view, is quite favorable, and a result will come by the end of November, though nothing especially unusual is involved in this upcoming biennial.
Jeremy Tonet
analystUnderstood. That's clear. Thanks for explaining.
David Arcaro
analystHi there, thanks. Good morning.
Bob Blue
executiveGood morning, David.
David Arcaro
analystLet me check something here. I had a question regarding the offshore wind part. An executive order came out earlier this year about offshore wind, and the interior secretary is reviewing projects that are already up and running. I'm just wondering how you read that situation and what you think it could mean for leases that already exist, like CVOW.
Bob Blue
executiveYeah, we believe the executive order won't have any impact on CVOW. Consider it this way: it already has all the permits it needs, including every federal permit. This fits with several key energy objectives the administration has set forth. It's a central piece of an all-of-the-above strategy for supplying additional power to Virginia's expanding economy, and it is unquestionably the fastest and most cost-effective way to get 2.6 gigawatts onto the grid. Stopping it would represent the most inflationary action possible when it comes to energy in Virginia; the project is homegrown. It supports American energy dominance. We need it to serve that growing data center market we've discussed. It's essential for maintaining U.S. leadership in AI and technology. It's generating American jobs — 2,000 as of the latest count. Virginia law expressly authorizes it. It enjoys strong bipartisan backing from Virginia's leaders. One thing worth pointing out: during his confirmation hearing, Secretary Burgum stated that projects which are sensible and already enshrined in law would move forward — and CVOW clearly falls into that category.
David Arcaro
analystAll right, that's great. Thanks for those remarks. I also wanted to ask about the data center angle and dig a bit deeper there. Clearly, your pipeline has expanded enormously across the past six months. Yet when we look at the PJM forecasts for the 2034 forecast, those have risen only slightly. Do those figures need to climb from here, or are there bottlenecks when it comes to actually hooking up all these data centers, or something else that leads you to believe not all of them will actually materialize and connect to your system?
Bob Blue
executiveWell, I think when you consider what we are planning for and what we have capital for, we have high confidence that those data centers will appear on our system. I mean, if you think about it, we have served data center customers longer than anyone else. In my view, we grasp better than other companies how they construct, how they ramp up, and we have an extremely good understanding of a confidence level regarding their arrival, so the new batch system may have had some impact on how many customers have sort of jumped into that substation engineering letters of authorization group; but the bottom line is a great deal of growth is coming in data centers in Virginia, and we are building the infrastructure in order to serve them.
David McFarland
executiveDavid, let me just return to slide 17, where the PJM projection for summer peak in 2034 shows 41.5. Our view is that the growth we have recorded in our queue isn't completely captured in that PJM revision — it looks somewhat backward-looking. And picking up on Bob's comment and on your question: will every bit of the volume we're seeing in that first phase eventually convert? We can't say with certainty. Historically, many of them have. And as we've progressed further down the column, conversion rates have risen, reaching 100% between the second and third buckets. So once again, I view that as a signal — a bullish one. Will all of it convert in the end? We don't know. We believe a substantial share will. And for us, that's a bullish indicator of our capacity to keep investing along the value chain to support those customers within a low-risk regulated framework.
David Arcaro
analystUnderstood. All right, that's great. Yes, many thanks. I appreciate that.
Anthony Crowdell
analystMorning to you. Very quickly, just one thing that builds on what David asked. Looking at that column on page 18, is there a simple rule of thumb for how long a project typically takes to move from one category to the next as it makes its way down the chain?
Bob Blue
executiveOkay, so we provided customers with some revised guidance—as you remember, we’ve discussed this—shifting away from a serial model toward something more like a cluster or batch approach. And once we made that change, we signaled that the stretch from roughly when you begin the process to the point where you might sign the ESA and receive power would grow by about 12 to 36 months, which lands us at a speed to market of 4 to 7 years. 26 gigawatts—those are all at quite different stages and likely different timelines. I don’t have specific guidance on how to map the 26 into the CLOA category or the ESA category; but again, from approximately the very start of the process to the very end, think 4 to 7 years. Given this level of demand, could that perhaps create pressure on that? It really depends on where a given project wants to be located and where we already have delivery points. So I don’t have very specific guidance for you or anything—I apologize. But it’s quite tailored depending on where the need is.
Anthony Crowdell
analystNo, that's exactly right—and I really appreciate the update. Thanks a lot. Thank you.
Bob Blue
executiveAbsolutely. Thank you.
David Paz
analystHello, good morning.
Bob Blue
executiveHi there, good morning.
David McFarland
executiveGood morning, David.
David Paz
analystYeah, thanks for making time. Just a quick question on the earned return assumption in your outlook. Are you expecting any lag over that period? And maybe how much lag? If you could also break that out between Virginia and South Carolina, that would be great.
Bob Blue
executiveYeah, David, we haven't provided that kind of specific guidance as we head into periodic rate cases and engage with stakeholders. But I think what we've noted previously is that at DEV in particular, where a fairly significant share of the investment sits in riders, which generally earn at their allowed level, we see pretty solid ability to hit allowed returns. In 2023, in our annual information filing, if you adjust for a handful of items — weather, some amortization of fossil retirements that we needed to take — we were landing on the base side of the business at pretty close to our allowed, and we expect that to more or less continue; and then in South Carolina, I think what we've indicated in testimony is that under the existing rate case process, by the time new rates take effect, given how backward-looking it is, we could be somewhere between 80 and 90 basis points under-earning right when rates go into effect.
David McFarland
executiveWe've also put a number on it, I believe: on average, 100 to 200 basis points of under-earning across a rate case cycle. As Bob said in his prepared remarks, we've made that a key focus in our talks with stakeholders in South Carolina, and we're excited about supporting the growth needs in the state, but it's also a conversation about our ability to earn a return closer to what's allowed; so obviously, work is underway on that right now. We've tried to stay appropriately conservative in the plan's assumptions regarding both where the allows are set and where the earned are set. We certainly have assumed we can do somewhat better than we have in the past through some mechanism, whether that's legislation or the possibility of more frequent rate cases in South Carolina. But I'd rather not get into a specific assumption we've made. I think we've tried to be reasonably conservative, but appropriately so.
David Paz
analystOkay. No, that makes sense. And just maybe quickly, the $4-plus billion of new CapEx, does any of that include any incremental spend on your interest in V.C. Summer two or three?
David McFarland
executiveNo. No, it doesn't. We've indicated that we're not participating or interested in that project. And I think you meant. I think you referred to $7 billion total capital increase, but yeah, none of that's related to V.C. Summer.
David Paz
analystAll right. Appreciate it.
Bob Blue
executiveThank you all for making time to be on today's call. Have a good remainder of your day.
Operator
operatorThat wraps up our conference. We appreciate your joining today's presentation. You're free to disconnect at this time.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Dominion Energy, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Dominion Energy, Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Dominion Energy, Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.