Eos Energy Enterprises, Inc. (EOSE) Earnings Call Transcript & Summary
November 5, 2026
Earnings Call Speaker Segments
Liz Higley
executiveGood morning, everyone, and thank you for joining Eos's conference call for the third quarter of 2026. With me today are Joe Mastrangelo, Eos's CEO; John Mayhew, our COO; and Alessandro Lagi, our CFO. During this call, we may make forward-looking statements, which include expectations about future results and the outlook for our company. Such statements rest on our present expectations and assumptions and carry risks and uncertainties that might make actual results differ materially; for further detail on those risks and uncertainties, please see our SEC filings. Forward-looking statements reflect only today's view, and we assume no duty to update them unless the law requires it. Remarks today will also reference non-GAAP financial measures. You can find a reconciliation of those measures to the most directly comparable US GAAP measures in our earnings release. Non-GAAP measures are supplemental to, and not a replacement for, financial information prepared under GAAP. In addition, these measures might not be comparable to similarly titled measures that other companies use; a replay of this conference call will be available by webcast through Eos's Investor Relations website at investors.eose.com. Joe, John, and Alessandro will take you through our business outlook and financial results before we move to Q&A; with that, I'll hand the call over to Eos CEO, Joe Mastrangelo.
Joe Mastrangelo
executiveThanks, Liz. Morning, everyone, and I appreciate you joining us. The team delivered a solid operating quarter; we shipped a record number of Cubes while continuing to reduce product cost. Backlog, meanwhile, came down compared with last quarter, and I'll come back to that on a later slide. Three major industry shifts are influencing how we're performing. First, the power business has shifted away from managing retirements toward adding capacity as quickly as possible; for 15 years, US electricity demand hardly grew. Now, grid planners anticipate 166 gigawatts of new demand by 2030. More than half of that total comes from data centers, yet manufacturers and commercial customers confront an identical problem: they require power sooner than the grid is able to supply it. Storage assists in bridging that gap. At any gas plant, solar farm, substation, steel mill, or factory, each grid connection experiences hours when it operates under its capacity. Storage deploys that power more quickly than waiting on new generation or transmission. Second, the location where a battery is manufactured has become part of the project financing model. With the foreign entity regulations now in force since January, the size of a project's tax credit hinges on the share of its costs attributable to banned overseas suppliers, and the cell accounts for roughly half of that threshold. All systems delivered during this quarter contained batteries and cells manufactured by Eos using over 90% domestic content. That is precisely what we mean by America's battery. Third, dependable performance determines the winner, and it consists of two essential elements. The first is delivery. A late system can cause a project to miss its tax credit cutoff or postpone revenue from the system. So we are bringing operations together at Thorn Hill: a single plant, operating at scale, at reduced cost. You can see the results already. We lowered cost per Cube once again, and margins improved for an eighth consecutive quarter. Second is performance in the field. Our product is an asset lasting more than 20 years, and owners are using its flexibility to get more done and meet new demand needs. One system might run a short cycle in the morning and then a long discharge at night. Competing systems today are built for 2 to 4 hours. Duty cycles that are longer and more flexible call for a different design, and that is where Eos competes. Our installed fleet spans 2 hours to 14. We now have 12 sites either operating or in commissioning, versus 7 a year ago. More than half of what we have in the pipeline is at 8 hours or longer, and one of the recent deals is a new 10-hour project for Google in West Virginia. I've lived through quite a few booms and busts in this business. The companies that won were never the ones with the strongest technology on paper. They were the ones whose equipment arrived when promised, fixed problems, and then kept running year after year, day after day. Customers and shareholders want the same thing from us: be reliable. Now let's turn to the next page and look at fleet performance. Looking at the fleet we have deployed, Eos systems have delivered 6.9 gigawatt-hours across more than 4 million cycles, and close to a gigawatt-hour of that came from the Z3 fleet. On a full cycle, Z3 round-trip efficiency came in at 79% on average, which is up from 78% in the prior quarter, and those figures include systems that aren't yet running Dawn OS. Getting to this point wasn't a straight path, and the most important takeaway sits at the bottom of this page: in our earliest systems, we treated each Cube as a single unit, so one weak module determined how the entire Cube performed. We altered our approach to controlling the system, moving from a single control point per Cube to 3, then 6, then 168. Dawn OS oversees all 672 modules individually, monitoring each one's state of charge and state of health continuously. No single module is pulling the whole system's performance down, and because of the operational upgrades John will cover, the modules we currently ship exhibit a much narrower spread — a tighter distribution — in how they perform. Industry practice typically involves expecting capacity losses and continually adding batteries to compensate; since we have control over every module, the system holds its performance, and we can identify a module needing service before a system's output is affected. Because we know exactly what is installed at every site — right down to the module, the software version, and the firmware — an improvement made at one site can be rolled out to every other place where it applies. The hardest learning curve for this company was not the battery; it was the system as a whole: the battery together with power electronics, the controls, and the grid functioning as one. Our initial Z3 projects took more time to commission than we had planned, and we took lessons from every project and improved how our fleet performs; now let's examine a particular customer use case. On slide 6 here, we show what the Dawn OS architecture enables. The new loads arriving on the grid are not merely large; they are dynamic. An AI training cluster is capable of swinging tens of megawatts in less than a second, repeatedly, again and again, and arc furnaces and big industrial processes behave the same way. I have spent a large part of my career working around turbines, so I understand the risk involved. Swings of that kind wear on turbine generator shafts as time passes. Regulators are noticing this as well. FERC has instructed NERC to draft mandatory standards covering these loads by year-end, and grid operators are putting forward ramp rate limits. Here's what you're seeing: an Indensity core soaking up the swing within milliseconds, so the grid only picks up a small portion of those swings, and from the utility's side you look like a steady customer instead of a volatile one. A question we often get from customers is what this means for the battery itself. Rapid swings produce heat, and heat is precisely what degrades conventional batteries; we took two Indensity cores, which are available to customers now, and had them charge and discharge into each other under a fast fluctuation profile across 147 consecutive cycles spanning more than 735 hours; we saw no extra temperature rise, and round-trip efficiency held at 81%. Indensity relies on the same module-level controls covered on the previous slide. Testing continues, and we're leveraging that data to demonstrate our operating flexibility to customers. A single asset can perform two roles: smoothing load within milliseconds and shifting energy across hours. From the customer's perspective, that means a quicker route to power; for the utility, it translates into system reliability. For the community, it delivers growth without raising electricity bills. That's our definition of assets built for today's grid requirements. Moving to slide 7, let's examine the backlog in more detail. We finished the quarter at $765 million, roughly 3.2 gigawatt-hours. That represents a 19% increase versus a year ago and a decline from $807 million in Q2. Last quarter, shipments exceeded bookings. This is a matter of project scheduling, not any underlying change in demand. Right now we're handling 3.5 gigawatt-hours of late-stage opportunity, and that's larger than our entire backlog today. More than half of it is waiting on financing, while the rest sits in contract talks. Our pipeline shows where the market is going: storage with longer durations, expansion across several end markets, and standalone projects that will help existing energy infrastructure run more efficiently. Frontier Power USA currently makes up roughly 43% of the backlog, but we're widening the customer base as well. In the last quarter we booked orders with 6 customers, and 4 of those were new. Not all of those late-stage opportunities will necessarily close—the NYSERDA bulk storage program illustrates that well, and it's among several state programs we're pursuing. Eos had no projects selected in round one, and that round allocated less than one-third of the program's 3-gigawatt target. Applicants get another shot in the next round, which is expected to take place before the end of this year. Moving to the middle of this slide, you can see clearly why the capabilities we showed on the previous page matter so much. Round-trip efficiency isn't the primary driver of storage economics; the biggest factor is how many cycles you can run per day to generate revenue. A gain of merely half a cycle daily cuts lifetime storage costs by roughly 10 times more than boosting round-trip efficiency by 5 points. Beyond that, an Eos Indensity system's inherently lower operating costs push project returns up even further. State and federal policy is turning long duration into an essential requirement, and a rising number of states are establishing procurement goals that come with mandated durations. California is seeking bids for as much as 2 gigawatts of 12-hour and multi-day storage, and Massachusetts has started a 5,000-megawatt energy storage initiative aimed at projects lasting 4 hours or longer, which includes separate tranches dedicated to longer-duration storage. This spring, Virginia enacted one of the biggest storage mandates nationwide in PJM, targeting roughly 21 gigawatts by 2045. The market demands American-made, long-duration energy storage. We have to convert more of our pipeline into backlog, and that is exactly where Michelle and the team are concentrating their efforts. Having said that, I'll now hand things to John, who will cover operations and how we're progressing with the consolidation into Thorn Hill.
John Mayhew
executiveThanks, Joe. The team put up a strong quarter, and all of our operational work in Q3 brought us nearer to profitability. We raised output, cut unit costs, and lifted productivity at both Turtle Creek and Thorn Hill. That execution keeps making our manufacturing platform stronger and sets us up well to add capacity down the road. A few key highlights: shipments rose 23% versus the second quarter, battery production climbed 25%, and subassembly gained 26%. Line 2 plays a major role in that. Q3 marked our first quarter with both lines running commercially. Line 2 grew from roughly 1% of battery output in Q2 to 17% in Q3, and it did so on a partial-shift schedule. Line 1 also rose 6%. That's productivity from the same asset base. Here's a number I really like: on average, Thorn Hill turns out about 20% more batteries per shift than Turtle Creek. Faster cycle times and less equipment downtime explain it, and it's structural. It comes from the facility layout and the equipment enhancements built into Line 2. Same shift, more batteries, more efficiency. Yield follows a similar pattern. Line 2 hit the same first-pass yield as Line 1 in only 3 months. At Turtle Creek, the bipolar line needed 13 months and the battery line needed 26 months to get there. More opportunities to improve remain, and the faster ramp to those levels underscores the gains from our improvements and gives us a blueprint for scaling future lines more efficiently. This is where the economics appear. Greater output and better yields push costs down, and we improved on every major cost line this quarter; on materials, cost per Cube fell 9% from Q2; that reflects several supply chain initiatives gaining traction, and those savings are structural, not one-time. On labor, direct labor cost per Cube dropped 17%. That's our teams becoming more productive at both sites with added volume; on overhead, we cut manufacturing overhead per Cube by 8% via higher facility utilization and better fixed-cost absorption. That's the operating leverage designed into our manufacturing model. The more we build, the less each Cube costs. Now, consolidation is the next big lever. That move is already in progress, and on an accelerated timeline. We started disassembly early in the quarter, and equipment is moving now. Operating one site rather than two brings lower overhead, lower conversion costs, and simpler operations. Our manufacturing process is simple, but precision matters. We don't need cleanrooms, yet Thorn Hill's infrastructure gives much tighter control over air pressure, humidity, and temperature, all critical to process control; that means more consistent output, better yields, and all of it feeds our profitability roadmap. We're using the relocation to fold Line 2 enhancements into Line 1. On timing, the first bipolar lines at Turtle Creek are aimed at starting production in Q4; for the battery line, we're finishing the improvements we're seeing in Line 2's performance, and we're targeting the full line coming back into production around the end of the first quarter. Until that point, Line 2 will keep production going. In mid-October, we moved 4 shifts of Turtle Creek personnel over to Thorn Hill and started 24-hour operations. We feel really good about the progress made. We expect another step-up in shipments in Q4, we remain on track to deliver the revenue outlook, and we remain focused on delivering profitable growth. With that, I'll hand it over to Alessandro.
Alessandro Lagi
executiveThanks, John, and it's good to be back with everyone this morning. Three highlights from Q3: we set a revenue record, margins saw their largest gain of the year, and we handled the sequential growth while using less operating cash. Revenue came in at $82.7 million, which is 171% higher year-over-year and up 20% quarter-over-quarter. Volume was the driver: Cube shipments increased 23% sequentially. Pricing came down this quarter, but that reflected project mix rather than any market trend. As mix returns to normal, we anticipate average selling prices coming back to the first half 2026 level during Q4. All told, we delivered to 10 projects spanning a range of end markets and use cases. Related-party revenue accounted for 83% of quarterly volume, including two projects that independent third-party developers originated and FPUSA later acquired; this figure shifts with delivery schedule and project size, and we anticipate the percentage will move closer to our backlog mix in time, already declining in Q4. Importantly, we're starting to see revenue growth convert into stronger operating performance. Gross loss came to $44.2 million, with margin up 58 points year-over-year and 18 points sequentially. Adjusted gross loss was $36.8 million, with an 18-point gain in margin percentage. That makes eight consecutive quarters of gross margin improvement, and we anticipate the trend continuing. Beneath the gross profit line, we keep showing discipline on cost management. Our sequential operating expenses stayed level. SG&A plus R&D came to $34.7 million combined, and about 20% of that figure is non-cash. To sum up: 20% revenue growth, an 18-point improvement in adjusted gross margin, and OpEx holding steady. That shows the Eos operating model in action. Now on to the bottom line: net income reached $125 million, powered by non-cash fair value adjustments related to our capital structure. Those mark-to-market revaluations of warrants and debt mirror stock price movements, not operating results. The measure we track here is adjusted EBITDA, which came in at negative $63.8 million, with margin improving to negative 77%. Sequentially that's 27 points better, and year-over-year it's a 96-point gain. Two factors drove that. First, volume growth added roughly 16 points, or 12 net of price. This demonstrates how quickly our business model can generate strong operating leverage as volume scales through the plant. Across the past several quarters, we invested ahead of anticipated growth by building out the team and capabilities needed to support a much larger revenue base. As revenue keeps growing, we anticipate a larger share of every incremental dollar of gross profit flowing through to adjusted EBITDA and cash flow. We also anticipate SG&A becoming a smaller share of revenue over time, generating meaningful operating leverage across the organization. Next, better operations contributed an additional 15 percentage points — 12 of those from lowering product costs and 3 related to how projects were executed. As John noted before, Cube costs got better again this quarter, and we expect that trend to keep going in the coming quarters. The project execution gain resulted from the timing and mix of work during the quarter, including the continuing push to migrate installed systems to Dawn OS and simplify things for our customer, which Joe discussed earlier; we expect those benefits to appear in profitability as well as in cash flow and liquidity. Now, on liquidity, we finished the quarter with $344 million in total cash, which includes $271 million of unrestricted cash. Sequentially, that's a decline of $20 million. Net cash used came to $106 million, partly offset by $87 million of DOE reimbursement that came in during the quarter. Two key points stand out here. First, we handled a significant step-up in production and shipping without any rise in quarterly operating cash consumption. Once again this quarter, operating cash flow moved in close step with our adjusted EBITDA loss. Working capital stayed essentially flat, helped along by customer deposits and project milestone payments. We brought in an additional $11 million by monetizing the production tax credits we had left from 2025. Given how quickly revenue is increasing, keeping working capital flat reflects disciplined execution and solid cash management across the company. Second, we're nearly finished with the significant investment related to Line 2 and the Thorn Hill facility. After those projects wrap up, we expect CapEx to begin declining. On cash, the way to think about it is that a large share of the heavy work on building out Line 2 and the Thorn Hill facility is already done, and we still have substantial liquidity sources available: $20 million under DOE tranche 2, about $24 million in Pennsylvania grant reimbursement, and roughly $39 million of net production tax credits. That funding provides extra liquidity for us while we complete Line 2. Cash flow on a quarterly basis will continue to be influenced by how much we produce, our working capital needs, and when customers pay us. As Line 2 ramps up, margins get better, and capital expenditures ease, we expect our cash flow profile to strengthen over time. Now, moving to the gains we've made on margins. We have progressed consistently since Q1. Adjusted gross margin rose 25 points, and adjusted EBITDA went up by 42 points; we anticipate that momentum will speed up in the fourth quarter, with adjusted gross margin rising by an additional 19 to 24 points, landing between negative 25% and negative 20%. The way we're executing on this improvement is what we've already covered. A few main drivers underpin that forecast. To start, average selling prices are trending back toward where they stood in the first half of 2026 — that reflects what's currently sitting in backlog. Next, we're getting savings from buying materials in bundles as volume keeps climbing. Third, automation on Line 2 keeps bringing down labor cost per Cube. Fourth, the optimized Thorn Hill layout is lifting throughput and improving material flow. And last, moving Line 1 removes overhead cost tied to Turtle Creek. All of that lands product margin between negative 15% and negative 10% for Q4. Our profitability roadmap doesn't wrap up when the year ends. There are additional initiatives still to execute during the early portion of 2027, on top of the volume leverage and the two lines now operating at Thorn Hill. Turning to the full-year outlook, we're reaffirming 2026 revenue of $300 million to $325 million. As John mentioned, speeding up the Line 1 transition cost us some revenue near term, yet it also leaves us with a leaner footprint at full productivity for 2027. Right now, how Line 2 is performing gives us confidence in that guidance. The progress we're seeing encourages us. Margins are trending better, operating leverage is coming through, and a good deal of the heavy lifting on Line 2 and Thorn is now behind us. With that, thank you all for joining us, and I'll hand the call back to the operator for questions.
Chris Souther
analystHi folks, I appreciate you fielding my question, and nice work on the improvement, particularly where margins are concerned. Looking at the sequential gains we saw continue in 4Q on margins and OpEx, and the implied EBITDA — a loss of $50 to $60 million in 4Q — I figure we can work that out ourselves. Could you walk us through any cash variance from those figures we ought to factor in for 4Q and 1Q, as we keep ramping and move production across to Thorn Hill and begin bringing that facility up? Anything on the CapEx side or the working capital side we should keep an eye on during the coming two quarters? Thanks.
Alessandro Lagi
executiveHi Chris, Alessandro here. Good morning to you, and I appreciate the question. There are a few things to cover. As you mentioned, I'm quite happy with how far we've come on margin. We had a strong third quarter, and in the fourth quarter we're seeing margin expansion carry on. On the cash side, the picture is much the same, isn't it? We're glad that on the operating front our cash performance has been keeping pace with EBITDA, so essentially there's been no working capital absorption. Looking ahead, we expect this pattern to persist, correct? Looking at our cash situation, it should track alongside the EBITDA gains and strengthen as EBITDA grows until we reach profitability. We're fairly at ease with the cash position held on our balance sheet, and as you heard, we have some additional cash sources including grants and the DOE reimbursement, so we feel good about things until we become profitable.
Joe Mastrangelo
executiveHey Chris, one quick addition on the CapEx front. My view is that John and the team are executing against a plan that was set in advance for how we get there. The sole factor that could alter the CapEx profile in the near term would be the timing of those near-term projects as they come in, along with the way that ties into how we set out volume for 2027 while we work through things here across the next 5 or 6 weeks.
Chris Souther
analystUnderstood. That's really useful. So perhaps regarding the Frontier Power USA team that's now being put together, could you walk us through — we're beginning to see some of the backlog items move through there, clearly — but where are they in terms of beginning to establish their development process, whether that runs alongside your pipeline or inside it? Could you just describe how they're proceeding as they start reaching out into the market and seeking opportunities that might be incremental, or closing within the pipeline, that would be great.
Joe Mastrangelo
executiveChris, as you've noticed, Jay Bellows was announced as CEO of Frontier Power USA, and I consider that a terrific addition to the team — not just because he brings his own customer contact list that he can take out and has begun building pipeline and opportunities we're working to close, but also because he has decades of experience operating systems. The things we discuss around software and Dawn OS, and having someone who has actually run real-time assets, helps us improve ourselves. On the pipeline side, we have projects placed into it from our opportunity set that they are reviewing. They have their own pipeline too; it's a solid list of opportunities. And at the same time, they're working on securing the debt financing, which has been going quite well in terms of packaging up the area of ring insurance and going out to look at both specific project financing and broader portfolio financing so we can pursue projects. We'll keep everyone updated as it moves forward, but I genuinely like the team Jay is assembling beneath him. I believe it will make us stronger in the market and stronger as Eos.
Stephen Gengaro
analystThank you. Good morning, everyone. I've got a couple of questions, and maybe we can return to the cash burn and balance sheet topic. Regarding the guidance you've given for, I believe, 10% cash gross margins in Q2 of next year — if you reach that point, could you describe what quarterly cash burn would look like? I realize that's not the simplest question to answer, but it's plainly weighing on investors' minds. I'm just somewhat curious about your perspective on that, plus your thoughts on present liquidity and the sort of runway you have right now before additional capital may be required.
Joe Mastrangelo
executiveStephen, I'll begin, and then Alessandro can address the second half of your question. First, what I'd note is that with Alessandro having joined us a couple of months ago, you've now witnessed two consecutive quarters in which operating cash is tracking the operating results we have at the company. In fact, the growth rate we saw last quarter, combined with cash burns running slower than that growth, reflects his impact as our CFO and the experience he brings to the role, and I'd expect that pattern to persist. Then, as we move into laying out 2027, John has his CapEx plan, and we've assembled all of those pieces together to provide the runway to get there. Alessandro can share further details, but on operating cash, you've observed the effect of having an operating CFO, and I expect that to carry on.
Alessandro Lagi
executiveThanks, Joe. Steve, just to add to that — when you look at how we're using cash right now, there's an operating piece that follows EBITDA, like Joe mentioned, and we expect that piece to actually get better each quarter over the next few quarters until we reach profitability. On the CapEx side, in the fourth quarter we're starting to see spending on CapEx come down compared with earlier in the year, and then over the coming quarters we'll have an even lower run rate from the plant. All in all, we're comfortable with the cash sitting on our balance sheet, and again, with the other sources of cash we can draw on, until we get to profitability. As for guidance for next year, obviously we'll use the next quarter's call to give more clarity on those numbers.
Stephen Gengaro
analystAlright. Could you help us understand how a quarterly CapEx figure might shape up for next year?
Joe Mastrangelo
executiveStephen, let's hold off and revisit that when we get to 4Q, and we'll lay it out then. Again, as I mentioned in response to Chris's question, with some of that quarterly stuff, I don't want us getting ahead of ourselves on a number while we're working through it. We have near-term deals in front of us, and we'll know far more in the next 4 to 5 weeks — those will shape what it looks like — but I'd rather not state something and then have to return and revise it, and end up backing away from a figure based on what we see today.
Stephen Gengaro
analystThank you. And I have just a single follow-up. Thinking about the assets currently deployed, and considering your gross margin profitability, is there any spending you're taking on tied to assets out in the field that require warranty-related work, or anything along those lines, that has been dragging down gross margin?
Joe Mastrangelo
executiveNo, not warranties, Stephen, and I think it's like the page when I went through the Dawn OS upgrades — there are costs tied to performing those upgrades, and those will arrive over time, as we discussed. When you look at it — and Alessandro brought this up in his remarks — there's product margin, which is nearing breakeven, and there is spending taking place, namely the Dawn OS upgrade, that is going to take place across the next two to three quarters as we roll those systems out in the field.
Joe Mastrangelo
executiveWe aren't in a position yet to get into particular projects with NYSERDA; we're still sorting things out alongside the customers who filed earlier, as well as additional opportunities. You know, when it comes to the selection, the customer is the one in charge — they picked the starting point they preferred. That represents less than one-third of the announced amounts. Our view is that what we submitted last time were strong projects that aligned with the program's broader objectives. Our understanding is that round two is expected to happen by the end of the year, though naturally that depends on scheduling, given how things unfolded with round one. NYSERDA invested substantial effort in reaching the projects they chose, and we'll just continue collaborating with them going forward. ): All right. Then regarding what you raised about state-level mandates — one more point I'd make: we bring up NYSERDA since our submission there became publicly available, yet several other states run programs larger than NYSERDA's, and those are moving forward with a number of customers included in the late-stage opportunities figure we talked about. We're quite optimistic about the way numerous states are looking at long-duration storage and what it contributes amid the energy demand we're witnessing. ): All right. That was going to be my follow-up question on the state-level front. I understand you've been doing work on long-duration mandates in that area. You brought up Virginia by name. That appears to be a reasonably large opportunity. Do you have any specific call-outs on the technology side, or on duration periods — what makes that appealing, and where are you seeing momentum in other states? When you examine each of them, they're all building out a duration mix — they want the 12-hour, the 24-hour, and then multi-day and beyond, which wouldn't apply to our technology but would apply to others. Everyone is watching this and recognizing that shifting the market requires incentives, and not merely price-based incentives, but incentives that let you generate revenue from the assets. A lot of these programs are built around the idea that the owner gets a return on the investment. We're feeling very positive about collaborating with the states as they begin to shape policy, and about explaining to them that a battery exists — and a system exists — capable of performing those duties, and that it's manufactured in America, with more than 90 percent of raw materials sourced from the US. We believe we satisfy those requirements. Nothing in there names Eos specifically or zinc-bromide specifically, but when a program targets a discharge time and the way they want the system to operate, we believe our technology lines up with that. We simply need to let each state and each customer go through their own steps before reaching a purchase decision.
Julien Dumoulin-Smith
analystHi everyone, this is Carter covering for Julien. Appreciate you fielding our questions. There's plenty of detail in what you shared, though I'd like to explore the margin trajectory a bit further. Third quarter brought some solid gains, and you're anticipating further gains in the fourth quarter. My mind is drifting toward '27 somewhat. From what I hear, you'll need more certainty about how certain pipeline deals resolve before pinning down the precise cadence. If I look back at those 72 points you presented during the previous call, I'd like to know whether anything has shifted in a meaningful way across the four main categories among that 72, or whether the margin improvement really depends on where a few of those big deals close during the first half of next year.
Alessandro Lagi
executiveCarter, I appreciate the question. What we've achieved so far is quite encouraging. The third quarter was strong once again. When you combine the fourth quarter with the third, we're comfortably past 50% of the path toward reaching those 72 points, and we feel very good about that. If you look more closely at the margin expansion—John mentioned this earlier—it comes down to the progress we've made on Cube's cost, correct? Material costs declined during the third quarter, and we anticipate that same trend continuing into the fourth quarter. Then, of course, there's the conversion cost, and with the higher volume we'll be running at Thorn Hill, we expect that conversion cost to drop considerably, thanks to the improved plant layout, greater efficiency, and better automation we have compared with Turtle Creek. Those are the main buckets. As Joe mentioned earlier, once we complete the control upgrades in the field, field costs will also decline. The categories are largely the ones we discussed on the previous call, and we expect the same pattern to hold in Q3, carry into Q4, and continue through 2027.
Joe Mastrangelo
executiveCarter, the sole point I'd tack onto what Alessandro said, simply to clear up your question: it isn't that we require volume in order to take the cost out. There is structural cost removal happening that we're capturing, and I think John's remarks — and I want to be sure we zoom in on one piece of this — is that the building infrastructure we have at Thorn Hill lets the equipment operate better, and we're seeing a 10% improvement on cycle time of producing a battery module, and much of that comes down to the stability of the operating environment that we have. That removes cost in and of itself, plus downtime and a bunch of other things, right? I think, beyond that, volume is a big lever for us, and we are going to work through where that lands and how it structurally changes the cost profile of the project. What I would say again is that what Alessandro and John have built is a good, old-fashioned cost-out pipeline that they're executing on with Francis on engineering to just simplify the product, remove parts from the system, make the system more robust, and take cost out. The one other thing kind of echoing Stephen's question earlier and what Alessandro talked about — I know Stephen asked about warranty costs — I think the one clarifying thing I would give here is our warranty reserve goes up with volume; that doesn't mean there's warranty costs underneath it. Just as volume goes up, you reserve for the event of the warranty, but if you look at the usage of that reserve, it hasn't changed over time.
Julien Dumoulin-Smith
analystRight, thanks for that detail — it's genuinely useful. One final question from me: could you give a bit more detail on the Google M&A announcement in West Virginia? It looks like an exciting deal for you folks. I'm curious how you'd describe the broader interest coming from Google or other hyperscalers. Might we see more transactions of this kind down the road?
Joe Mastrangelo
executiveCarter, on the Google M&A — we spent a while on that one, working through the technical validations with several parties, both the M&A side and Google. Our view is that a long duration will benefit the project and improve the return for Google. As we speak with more and more people — and this ties to the remark I made about how these dynamic loads behave — we enjoy talking about AI, but if I take an AI load and stack it against the load from a steel mill, or the load from any industrial factory, with all the spikes and peaks and valleys that come with it, they basically all look alike. You need something capable of buffering those loads against conventional power generation equipment, and I believe that's the role we fill. What matters, and this is the part that gets the pipeline energized — and I know we've discussed it, and orders closing will be the proof — is that within that 3.5 gigawatt of near-term opportunities, we will see orders closing that fit this use case; we approach people and explain that we can absorb those short-term spikes while delivering long-duration discharge from the same asset and the same technology, and people respond well to that. What we still have to do is bring reliability in the field up to where it needs to be, operating day by day by day, and reach five nines capability on product reliability — and that's another major element of what John and Francis and Alessandro are working on, which drives not only performance for the customer but also cost reduction and profitability for Eos.
Joe Mastrangelo
executiveThanks, and thanks to everyone for tuning in. Once again, I feel a great deal of pride in what John, his team, and Francis have accomplished in truly driving throughput and getting Thorn Hill operational. Relocating the lines from Thorn Hill was a rather emotional experience for me — I visited Turtle Creek roughly a week ago, the place where Z3 production began on a semi-automated line, and now nothing remains there, since that equipment has been moved up to Thorn Hill, installed, and is being commissioned to begin running here. The pace at which they are progressing, and how efficiently they are carrying this out, is genuinely impressive, and I very much look forward to having everything under a single roof in a state-of-the-art facility once production starts, because what we are seeing from the Thorn Hill line isn't that the line itself is superior — it's simply that this line runs in an environment that fosters better performance. With Alessandro serving as operating CFO, you can see the results and how our cash is tracking toward profitability, and I believe that will carry on and strengthen as time goes by. With Michelle having been in her role here for the last couple of months and contributing a great deal of what you're seeing on those state mandates, connected to the work she did previously, I feel really good about what she and the team are doing to put us in position to win deals, and we simply need to put our noses to the grindstone, close, and grow that backlog to demonstrate, and keep demonstrating, that the technology is what the market requires going forward. We'll keep everyone posted on that, and I look forward to the 4Q call, where we will also set out guidance for 2027 and whatever the outcome turns out to be as we work through year-end.
Operator
operatorThanks, Joe. We’re glad you could join us on today’s Eos conference call. That brings our presentation to a close. You can disconnect at this point. Thanks.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Eos Energy Enterprises, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Eos Energy Enterprises, Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Eos Energy Enterprises, Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.