Ero Copper Corp. (ERO) Earnings Call Transcript & Summary
August 7, 2020
Earnings Call Speaker Segments
Operator
operatorWe appreciate everyone being on the line. I'm the conference operator, and I'd like to welcome you to Ero Copper's Second Quarter 2020 Financial and Operating Results Conference Call. <<operator_script>> Please note that this call is being recorded. <<operator_script>> At this point, I'll hand things over to Mr. Noel Dunn, Executive Chairman of Ero Copper. Sir, the floor is yours.
Christopher Dunn
executiveThank you, and good morning to all of you. Ero's second quarter results news release can be found on our website as well as on SEDAR, along with our financial statements and MD&A covering the 3 and 6 months that ended June 30, 2020. On today's call we'll be presenting forward-looking statements involving risks and uncertainties about the company's businesses, operations and financial performance. For a discussion of our business's risk factors and how they could affect future performance, we point you to our latest AIF, which is also posted on SEDAR. All amounts are in U.S. dollars unless stated otherwise. With me on the call today are David Strang, Ero's Co-Founder, Chief Executive and President; Wayne Drier, Ero's Chief Financial Officer; and Makko DeFilippo, Vice President, Corporate Development. Before turning to the second quarter's results, I want to note that although the recent rise in COVID-19 infection rates in Brazil has raised the danger of outbreaks in communities close to our operations, our in-country teams have kept up extraordinary precautions aimed at keeping our employees, contractors, their families and local communities safe. To date, the early and detailed litigation efforts carried out across our organization have achieved precisely that.
Christopher Dunn
executiveIn the second quarter by itself, community relief and on-site COVID-19 litigation efforts received roughly $1 million from our operations. Thanks to those continuing efforts, our dedication to in-country -- to our in country -- work and the dedication shown by intra-country colleagues, we still see no interruption to operations, supply chains or sales channels. Over the first 6 months of this year, our core assets in the Curaçá Valley turned in a strong performance. Production from our NX Gold Mine is also rising as planned, and Dave will go into more detail on that. Financially and from a liquidity standpoint, we remain in excellent shape and, frankly, as well prepared as we have ever been to keep navigating uncertain times. We closed the second quarter with about $52 million in cash. As a reminder, because we amended our credit facilities in the first quarter, no material principal debt payments were due until -- due until March of 2022. As our record quarterly cash cost shows -- $0.65 per pound of copper produced and $437 per ounce of gold produced at NX in the second quarter -- our operating business keeps benefiting significantly from the currency tailwind tied to the weakening of the Brazilian real against the U.S.
Christopher Dunn
executiveThat's on the dollar side. The currencies underneath kept moving around, and that affected our GAAP earnings and working capital in the period. The reason is the noncash accounting treatment for U.S. dollar-denominated debt and forward-dated FX option contracts — those are meant to shield the business if the Brazilian real strengthens quickly against the U.S. dollar. Worth pointing out: we generated the strongest quarterly cash flow from operations in the company's history, at $42.5 million, even with $4.4 million in cash settlements of derivative contracts in the second quarter. So as we look ahead, on one hand, if the Brazilian real stays persistently weak against the U.S. dollar, our underlying business benefits, and we'll keep making modest payments to settle existing contracts, just as we showed in the second quarter. On the other hand, since a global recovery from the COVID pandemic is inevitably going to come at some point, the export-driven Brazilian economy is likely to perform well on a relative basis. And we've shielded our business against the currency strengthening and its effect on our profitability. With that, I'll hand the call to David for a brief review and update on our operations, and Wayne will walk through the company's financial performance.
Christopher Dunn
executiveRight after this call wraps up, the team will be standing by to take your questions.
David Strang
executiveThank you, Noel. I'd like to add a few quick points to what Noel covered. Throughout every part of our organization and across all our operations, we keep managing this business prudently, so that we're positioned as strongly as we can be to weather any unexpected difficulties that COVID-19 might create. As an organization, our leadership team — in both Brazil and North America — still places the utmost importance on the health and well-being of our employees and the communities where we operate. Our colleagues in Brazil have kept proving, through their results, that they can run our operations safely while also managing and reducing the effects of COVID-19. And the recognition our company received recently for its ongoing ESG initiatives stands as evidence of their hard work and their dedication to those principles. Turning to production for the quarter, our figures continue to show solid operational performance at the underlying level. At MCSA we produced 11,178 tonnes of copper in concentrate, and at NX Gold we produced 8,739 ounces of gold during the period. Looking first at MCSA in the Curaçá Valley, we milled 627,071 tonnes of ore grading 1.98% copper and posted average metallurgical recoveries of 90% for the quarter. Overall, these gains came largely thanks to contributions from the Vermelhos Mine, where 253,349 tonnes grading 3.26% copper were mined during the period.
David Strang
executiveContained copper from Vermelhos rose by a substantial 56% versus the first quarter. During the period, 371,794 tonnes grading 1.4% copper were mined at the Pilar Mine, basically matching the first quarter, though with a slight gain in tonnes mined. As Noel noted, we set a new quarterly record for C1 cash costs, at $0.65 per pound of copper produced, which mirrors strong operational performance, ongoing currency tailwinds and better byproduct gold and silver prices in the second quarter. For the first half of 2020, C1 cash costs came in at an average of $0.68 per pound of copper produced. Our 2020 production guidance for the Curaçá Valley operations stays unchanged, as does the previously revised C1 cash costs guidance of $0.70 to $0.85 per pound of copper produced. In the same way, we are holding to our previously revised capital expenditure guidance range of $56 million to $68 million, along with $20 million to $25 million in exploration expenditures through September of this year. As we have done in prior years, when we release our third quarter results, we will aim to update full year exploration spend guidance to include planned drilling during the fourth quarter. Even though every one of our capital programs has run and continues to run normally through the first half of the year, our full year -- excuse me, our full year guidance is subject to an elevated degree of uncertainty as a result of the COVID pandemic.
David Strang
executiveWe keep moving forward on a number of important growth initiatives. Even with the major difficulties brought about by COVID 19, our project crew managed to deliver and completely install the new high-intensity grinding mill at the start of July, just a week or 2 later than planned. Integration of the instrumentation and control system remains on schedule to wrap up this week, and commissioning is progressing through an inventive approach that brings together on-site teams who went through rigorous quarantine protocols and a virtual multinational commissioning support team. We anticipate full commissioning and handover to operations before August ends. This marks a remarkable achievement, made possible by substantial efforts from our whole project team around the world. And I want to certainly -- I want to congratulate every one of them on this call. Turning to the second half of the year, with commissioning as the foundation, we anticipate a meaningful gain in overall stabilization of metallurgical recoveries at the mill. Our ore sorting testing campaign, running at a commercial scale since January, is essentially finished, and by now we have tested 8 separate discrete ore bodies across the Curaçá Valley spanning our range of grades. The results are very encouraging. We will keep running the test program through the third quarter on the final planned orebody, as data analysis, process integration and operational optimization efforts carry on to fully quantify the benefits of preconcentration.
David Strang
executiveFrom the work completed so far, we think ore sorting is going to be a key piece in taking things further — driving additional optimization of the production portfolio across the different Curaçá Valley operations, along with future new discoveries. We expect more detail on the work carried out and the results from the test campaign during the third quarter. Beyond ore sorting, I'm quite enthusiastic about finishing a laboratory upgrade project that will let us perform multielement analysis in-house, platinum group metals in particular. That project wrapped up at the end of the quarter, and we are ramping up daily sample volumes over the coming several weeks according to schedule. Once fully integrated, we anticipate this addition to other borrowers will cut costs significantly but, more importantly, shorten turnaround time for platinum group metal assay results, which will be a welcome addition to the ongoing work of our exploration department. On exploration in the Curaçá Valley, we currently have 28 drill rigs operating. Our in and near-mine exploration programs remain focused on the deepening extension of the Pilar Mine, where we have continued to intercept very high-grade Superpod mineralization at depth, including the recently announced intercept of 96.4 meters, grading approximately 3.97% copper, the best hole we have ever drilled in the Curaçá Valley.
David Strang
executiveAlso at Vermelhos, we're pushing ahead with drilling and borehole EM programs, seeking down-plunge extensions of the Siriema massive sulfide conduit, and we're continuing the fan drill program that's designed to test whether mineralization continues beneath the main Vermelhos ore bodies. With a substantial share of our in- and near-mine programs now finished, we've been moving aggressively on regional exploration across 4 recently interpreted mineral systems. Preliminary results from those systems keep looking encouraging, and more detail on these ongoing exploration programs is still planned for the second half of the year. As with our scheduled quarterly updates, results from our ongoing exploration programs will be detailed further in the upcoming exploration update, which we typically put out 4 to 6 weeks after our financial results. At the NX Gold Mine, production for the quarter came to 8,739 ounces of gold and 5,327 ounces of silver, from total mill feed of 39,108 tonnes grading 7.75 grams per tonne gold, with average metallurgical recoveries of 89.6%. Gold production, mill throughput and recoveries all improved quarter-on-quarter, reflecting the anticipated ramp-up of mining at the Santo Antonio Vein. Operational performance gains contributed to record C1 cash costs of $437 per ounce of gold produced during the second quarter, an improvement of $157 per ounce compared with the first quarter.
David Strang
executiveIn the first half of 2020, C1 cash costs came in at an average of $511 per ounce of gold produced. As we mentioned earlier, we still anticipate that full year production will be weighted toward the second half. For the NX Gold Mine, our annual production guidance is unchanged at 38,000 to 40,000 ounces of gold, along with the previously revised C1 cash costs of $425 to $525 per ounce of gold produced. Annual capital expenditure guidance for the NX Gold Mine is also unchanged from the previously revised guidance of $7 million to $9 million, plus an additional $2 million to $3 million to fund its ongoing exploration programs. Although it isn't part of our current operating portfolio, an initial review by our buyer team to evaluate the Boa Esperanca copper project has turned up some fairly compelling opportunities — recall that we effectively inherited the existing design of the project after our acquisition of MCSA. And for the first time, I've taken a very hard and close look at the project together with the engineering group. While we had initially planned a fairly routine desktop update, several aspects are pointing us toward a rework of the entirety of the project from the ground up, and we continue to make progress on that front.
David Strang
executiveHaving said that, I'll now hand things over to Wayne, who will give an overview of how we performed financially.
Wayne Drier
executiveThanks, David, and good morning to all of you. In the quarter, we sold 10,586 tonnes of copper contained in concentrate along with 8,739 ounces of gold, generating consolidated revenues of $70.8 million. Copper sales volumes matched the prior period, while gold sales volumes kept climbing, coming in 11% above the prior period thanks to ramping production at the Santo Antonio Vein. As David noted, we posted record C1 cash costs at both MCSA and NX Gold for the quarter, at $0.65 per pound and $437 per ounce, respectively. Across the first 6 months of 2020, C1 cash costs averaged an impressive $0.68 per pound of copper and $511 per ounce of gold produced. Strong operating performance at both of our operations, favorable exchange rates and, for MCSA, higher byproduct gold and silver prices underpin these results. Together, these factors drove $42.5 million in cash flow from operations, a record quarter for the company and a 13% improvement from the prior period. Adjusted EBITDA came to $42.4 million, a 27% increase over the prior quarter. Over the first 6 months of 2020, adjusted EBITDA totaled $75.9 million, in line with the first 6 months of 2019, even with a 17% decrease in the average prevailing copper price over that same time period, which frankly speaks to the strength in profitability of our operations.
Wayne Drier
executiveAlthough the Brazilian real’s decline versus the U.S. dollar has obviously helped both our operations and our headline financial results, we’re still seeing foreign exchange volatility affect what we report for the second quarter. Foreign exchange losses for the period included $4.4 million in cash settlements on out-of-the-money callers, $8.5 million in unrealized derivative losses on foreign exchange based on the fair market value of those contracts at June 30 compared with March 31, and another $3 million tied to translating our U.S. dollar-denominated debt in Brazil, which stems from the real being our functional currency. Our headline net income for the quarter came to $7.5 million, or $0.08 per share, after adjusting for the unrealized portions of those foreign exchange losses; adjusted net income was $20.3 million, or $0.22 per share fully diluted, a figure that much more accurately captures how the underlying operations performed. At quarter end, total cash, including restricted cash, stood at $52.3 million, up from $45.5 million at the close of the first quarter. That rise mainly reflects strong operational performance, which helped deliver record cash flow from operations for the period. Our working capital position at period end was hurt by the current portion of the fair market value assessment on our outstanding foreign exchange contracts, by the timing of certain payments tied to the HIG Mill, as David discussed, along with associated consumables and critical spares, and by the current liability from the short-term lines of credit drawn in the first quarter as a proactive step against COVID-19.
Wayne Drier
executiveGiven how solid our balance sheet is, we feel quite confident about our capacity to pay down or refinance those short-term facilities. As our results from the first 6 months of 2020 show, the business keeps performing very strongly and producing substantial free cash flow, especially with metal prices and foreign exchange rates where they are today. With that, I'll turn the call back to Noel.
Christopher Dunn
executiveThanks, Wayne. The way I’d sum up how we did in the second quarter is this: first, we kept taking proactive, ongoing steps to lessen COVID-19’s effects on our operations so they could continue running safely, and at the same time we gave extraordinary backing to local community response efforts; second, we kept moving key growth projects forward even though conditions were difficult; third, our core business delivered exceptional operating and financial results, helped by the currency tailwinds that are still with us. I really appreciate your being on the call. We’ll hand it back to the operator so the line can be opened for questions.
Operator
operator<<operator_script>> Our first question is from Orest Wowkodaw at Scotiabank.
Orest Wowkodaw
analystI'm curious—you kept your operating guidance as it was. During the first half of the year, though, throughput came in much stronger than anticipated, while the grade, I suppose, ran considerably below what your guidance implied. I'm just wondering how we should think about that for the second half: do you expect things to normalize, with throughput dropping meaningfully and grade rising, or should we simply concentrate on the copper production guidance rather than the details surrounding it?
David Strang
executiveYes. Orest, thank you for those excellent questions. Regarding the second half of the year, we're placing a lot of emphasis on copper output. As you can well imagine, with an ore operation such as ours, given the high-grade character of the different ore bodies and the heterogeneous nature of the mineralization, we do observe variation in grade when it comes to stope sequencing. So we're keeping guidance as we've emphasized with regard to copper production. And I think you'll want to adjust around that with respect to your grades and/or your output in terms of ore being mined. It simply has to do with sequencing off stopes. And so, as you can see, you would expect during the second half of the year, in order to sustain that kind of copper production level, that you'll see a reduction in ore throughput, a subsequent rise in grade, together with an anticipated improvement in recovery tied to the commissioning of the HIG Mill.
Orest Wowkodaw
analystAll right. Could you give us some detail on the reason you expect throughput to decline? Is it simply that mining is the constraint, or is something else causing that?
David Strang
executiveOur stope availability is tight. That is the limiting factor in how we plan what we are attempting to accomplish month by month. So, for example, at Vermelhos you would see some rockfill that we need to use for replacement. As we know, there is no peso plant up there. Therefore we rely on rockfill. And so the timing around being able to fill stopes with rockfill, et cetera, affects that throughput. Whenever possible, we will always aim to produce more with regard to our throughput through the mill, but on a month-by-month basis that is not a perfect science. So that is the reason we are keeping our guidance for copper production as it is.
Orest Wowkodaw
analystAlright. Great. And then one last thing from my side. Could you remind us what level of gain in copper recoveries you anticipate coming from the HIG Mill?
David Strang
executiveThe guidance we've given for the marketplace sits somewhere around 2% to 4%.
Orest Wowkodaw
analystAll right. And how much time would that need before it shows up — is that roughly as we leave the year?
David Strang
executiveMy expectation is that those gains would begin to appear, since the COVID situation and commissioning have put us a bit behind schedule. If you're thinking about updating your models, I would hold off on making any changes until October.
Operator
operatorOur next question is from Jackie Przybylowski at BMO Capital Markets.
Jackie Przybylowski
analystTo pick up on what ore was asking about — I know you’ve previously mentioned a second mill, and I realize it’s still quite early, since the first HIG Mill isn’t fully commissioned yet. Could you share a bit more detail or an update on where you stand now regarding installing a vertical mill or another HIG Mill? And perhaps what the timing for that would be — whether it’s still roughly consistent at a couple of years out, or whether that has shifted at all?
David Strang
executiveYes, Jackie. Thanks. On the going-forward question about continuing to raise the mill's capacity — what we want to do at this point is get the HIG Mill settled in. We want to run it in a way that lets us test what it can do beyond the metallurgical gain, namely its potential to help us lift capacity from roughly 3.2 million tonnes today, and we've guided that we believe that could reach $3.7 million. I'd like — and I believe all of us would like — to see that mill running. The wonderful thing about that mill is that it has variable gearing. So how we manage and operate it gives us enormous flexibility to test the upper reaches of its performance. Once we're comfortable with that, we can then look down the road at how we want to keep pursuing expansion. Any further expansion past that, though, depends on exploration success. Certainly, what we're beginning to see in our operations right now — with the HIG Mill now installed, with the work underway on ore sorting, and the opportunities we're seeing in ore sorting for our longer-term chances to bring on other projects in the district — will, in a sense, keep supporting our efforts toward running at $1 a tonne or better.
David Strang
executiveThat has us pretty energized. So we just want to get settled in, basically. As I mentioned, we have a couple of major projects — the HIG Mill, and then ore sorting. After that, we can look ahead and determine our next step where the plant is concerned. That's roughly where our thinking stands at the moment. We don't want to get ahead of ourselves when it comes to looking ahead. What I think we should do is embed the HIG Mill, see how our performance looks, and see whether we can exceed 3.7 million tonnes of capacity. Ore sorting gives us enormous flexibility to potentially upgrade ore and allows us to produce even more copper than anticipated with that mill capacity. So there are a lot of variables at present. We want to work through them over the course of the next couple of years before we get too far ahead. And we are at — doing the 5.5 million tonnes.
Jackie Przybylowski
analystUnderstood. On the ore sorting side, could you provide a little update? Again, I realize this may be an unfair question since the studies aren't complete, but you've already worked on quite a few different ore types. Are you finding consistent benefit from ore sorting, or do certain ore types perform better than others through the ore sorter? So, in terms of early impressions, how do you see being able to fold this into your plan going forward?
David Strang
executiveWell, I think we need to be cautious regarding selective disclosure — sharing things with certain individuals as opposed to the market as a whole. The best way for me to respond is to suggest that, as we bring all of this together, you watch for a news release that I believe we'll issue covering this first round of testing. As I mentioned in my notes, we're quite pleased with how it has gone. The consultants we've now engaged to help us figure out how we transition from a testing phase into full integration have been extremely impressed by the results we've achieved. But honestly, Jackie, I don't think it would be fair, and I don't want to get too far ahead of things. That goes well beyond where we are. We'll make certain that the market receives as complete an understanding of the results as we can provide, and we'll do it promptly.
Operator
operatorUp next, we have a question from Dalton Baretto of Canaccord Genuity.
Dalton Baretto
analystJackie got to the ore sorting questions ahead of me, so I'm switching direction now, though I still have a few more here. So, pulling all of this together, Dave, and with the tack report coming in November, could you give us a sense of what you're aiming to include there on the drilling side, and in terms of a mine plan, from the standpoint of mine life and capacity? And will some of this ore sorting material be captured in there?
David Strang
executiveThanks. Good to hear from you, Dalton. And yeah, that's a solid question on that front. Clearly, what we most want to have in the 43-101 is the deepening project. That project is really coming together nicely now. And we expect, of course, that it will serve as the centerpiece of whatever we put in the technical report. On ore sorting, we'd like to be able to fold that into our 43-101 wherever we see a chance to apply it. But it's too soon to say whether I can confirm that it will serve as the basis for the 43 — or be part of the 43-101. We're working with SENCO at the moment on how we integrate the projects, the different projects, into the mine plan using ore sorting. And if they clear our hurdle, and they get — and the return metrics are such that they satisfy our return metrics, then we'll include them. But I can't — I don't want to be pulled into saying that it's definitely going to be in there or not at this point.
David Strang
executiveStill, our outlook is positive. We genuinely feel a sense of encouragement.
Dalton Baretto
analystThat's fair, that's fair. And now you have the lab right there on-site at Keel Zone Siriema PGMs. Is the advantage simply quicker turnaround, or do you anticipate a shift in exploration strategy regarding Siriema?
David Strang
executiveLook, the main reason we installed a complete ICT suite analyzer in the lab was to give the exploration team the capability to examine every mineral. When it comes to magmatic sulfide exploration work, one point that all the consultants we've engaged and who've joined the project have stressed strongly is this: being able to examine your samples — and not just the mines you intend to mine, but other minerals too — can be hugely valuable for identifying targets and steering you toward particular kinds of ore bodies. As for the PGMs, and why we've singled PGMs out: as you've seen in earlier exploration updates from us, we have published PGM results. The difficulty we face, though, and have faced historically with PGMs, is that we can't do every hole and test every hole. So we've had to be selective about which samples we shipped to South Africa for testing and then got results back from. What we're observing with PGMs and the tests we've sent to South Africa indicates that this is a portion of our exploration program that has been — what's the term I'm after — underlooked, to put it as well as I can.
David Strang
executiveWhat we're after is the chance to devote far more time to being able to run full suite assaying — to examine every hole at PGMS and see how they're distributed across our ore bodies. Are the concentrations at levels that tell us we ought to be approaching this in a different way? All of that remains early stage. But for sure, what we'd like to have is the capability, rather than looking at 50 samples, we want — at this point we'll be able to — we'll have the capacity to examine each sample we run through the lab for PGMs. Does that answer it?
Dalton Baretto
analystYeah — that’s certainly making a difference.
David Strang
executiveI don't want to get too far ahead of ourselves yet. The PGM work that has happened to date is interesting. It's encouraging. It was unexpected, but a lot more work has to be done because we don't know enough with regards to the distribution of PGMs and how they how they exist in our -- in the Curaçá Valley.
Dalton Baretto
analystThen I was taken aback that Boa got mentioned at all today. What's driving this broader overhaul? What's the thinking on your end? And what's the general view of that project — setting strategy aside?
David Strang
executiveWe brought onto our team a man by the name of Ricardo Re. Ricardo is a king when it comes to resources — much like Mike and Pablo are with resource estimates — and he helps our team in Brazil upgrade and reach a more robust 43-101 level. Ricardo came aboard earlier this year. And as part of one of the projects he was reviewing, he wanted to take another look at Boa. You began taking another look at Boa. He had prior experience with Boa, and a few things he told us led us to go back to the upside engineering firm that had completed the feasibility study for Glencore. And during those conversations with them, combined with what Ricardo had done in terms of his grasp of the resource, we had a very significant pause and said we have to really examine this from the very, very beginning. It — these are early days, but there were significant things we had noticed that left us head-scratching about why Glencore had proceeded in a certain way when there are things within the deposit — the existing deposit that's known — that would point to a more optimal way of approaching the project.
David Strang
executiveOn top of that, Ricardo's efforts point to some meaningful chances to potentially grow the resource. It has now become clear that a great deal of the drilling — most of it — was aimed at hitting a meterage rather than drilling on a geological basis. And there are a substantial number of holes in areas that ended, in certain cases, in high-grade mineralization. So Noel and I have asked Mike to assemble a program for some geological and exploration work next year so we can start examining it from that angle. I mean, we have always known well in advance of a very good IRR and strong return potential. But now, as we look at it, we are approaching it from a front — or sort of first principles — footing. We are now seeing that there may potentially be more to Boa than we ever believed before, which is quite exciting for the team. But it is early days. A lot of work has to be done.
Dalton Baretto
analystUnderstood. All right. And perhaps just one final question from my side. Dave, during last year's Q2 call, you were generous enough to share the internal plan regarding an aggressive ramp-up. I'm curious whether you'd be willing to do the same again for this year.
David Strang
executiveThanks, Dalton. No, I think I'll hold off until we've got the 43-101 out to all of you later this year. <<inaudible>>
Operator
operatorOur next question is from Stefan Ioannou at Cormark Securities.
Stefan Ioannou
analystGood to see the quarter. Perhaps just to build on Jackie's question about ore sorting. And again, I don't want to split hairs. I know you've already given a lot of information. Just curious, you mentioned that there were 8 batches or big test runs through the ore sorting plants so far. Could you maybe, without saying too much, maybe just give us an idea, was it all lower-grade open-type ore? Or did you actually look at some moderate-grade stuff that may be coming from underground that could travel with ore sorting?
David Strang
executiveThanks, Stefan. That's a really good question. Yes. We examined 8 distinct ore types, covering both underground and open pit material. Those included high-grade as well as lower-grade material. So we attempted to — we've sought to cover as broad a range of ore bodies as possible across the Valley, plus particular locations such as Vermelhos, Pilar, and a few other ore bodies where we assessed large — the capacity to assess large tonnage at high grade and large tonnage at low grade. So we've examined — we've aimed to be as thorough as we possibly can regarding — I believe we've put slightly more than 100,000 tonnes through the plant so far. And so it's reasonably thorough. We're extremely pleased with how much work has been completed.
Stefan Ioannou
analystAll right, thanks. Changing topics to NX Gold now — I recall you previously said that alongside the drilling at the San Antonio Vein, there would also be some regional exploration of a complementary nature, the first such work in quite a while. Is that still going ahead? Or has attention shifted entirely back to the Vein itself?
David Strang
executiveOkay, so the Vein itself has been getting continuous attention from us, and we've been putting work into a few other areas as well. I believe it was roughly a couple of months back that we launched our regional program — that is, we began doing the work in that area. So yes, the program is beginning to grow. As I mentioned, 4 to 5 rigs are operating there at present. And going forward, I think we would want to see that program grow further, though that will come down to Mike and Pablo's efforts when it comes to rig availability, crews, et cetera. With COVID-19, no matter how much you'd like to move as fast as possible, you have to be extremely cautious about, number one, obviously bringing teams into your environment. You haven't run operations there before. So it's about locating rigs and locating available personnel, since that's exactly what Mike and Pablo are handling at the moment. But — that's a long answer to a short question — we are indeed stepping out into the region.
Operator
operator<<operator_script>> Our following question is from CIBC’s Raphael De Souza.
Raphael de Souza
analystI think most of what I wanted to ask has been covered already. Just one final thing, though. Given how elevated gold and silver prices are at the moment, has anything shifted in how you view NX Gold and a possible divestment?
David Strang
executiveNo. At this moment, I'd say we're extremely pleased with where NX stands. Obviously, there's considerably more work ahead of us, and the exploration program has us genuinely excited. And we certainly hope that when a new 43-101 comes out at the end of the year, we'll be in a position to demonstrate further extension of mine life. Like anything else, though, we're always assessing opportunities around how to derive the greatest value from our assets. And as for NX right now, I think, Raphael, I'd just leave it at this: we're evaluating a number of different opportunities regarding how to extract additional value from it. But there's nothing concrete that I'd say we're prepared to discuss at this stage. I think anyone who holds a gold asset ought to be doing what we're doing. And I think we're no different from any other company out there, assessing what's the best way to extract the most value for our shareholders from its operation.
Raphael de Souza
analystAnd just one more quick question about NX Gold. So to reach your guidance of — I believe it's 9 grams per ton — grades need to rise pretty substantially in the back half of the year. So what kind of grades should we be expecting over the coming quarters?
David Strang
executiveOn that point, Raphael, I’d rather not dig too deep into it. Still, I’ll hand it over — though not in a way that means I’m tossing the bucket to Makko. Makko devotes a great deal of his time to working with the NX Gold team, well beyond what I do. So, Makko, is there anything you’d like to add about that?
Makko DeFilippo
executiveYes, Raphael. Look, I'd say we have clearly kept our guidance in place for one additional full year. I think we have consistently signaled that output would lean toward the latter six months of the year. I think as we have progressed at Santo Antonio, we have clearly kept raising production volumes, and both — if you examine throughput, it has run considerably above the first half. So I think you can take our full-year guidance and calculate backwards regarding roughly where we will land. I mean, if you look at that range for production volumes at NX Gold, you can — as I mentioned, you could work backwards to figure out what the grade should be for the second half. And we are working the team, and everyone is working, to deliver that.
Operator
operatorJackie Przybylowski of BMO Capital Markets has the next question.
Jackie Przybylowski
analystI apologize in advance—I'll likely ask additional questions you'd rather not field. Still, I want to return to the regional drill program. You mentioned a moment ago that you hoped to bring in additional rigs there, subject to availability. So my first question: does that availability refer to rigs from your current near-mine programs, or would those be new rigs beyond the 28 you already have? And then, on top of that, could you perhaps provide some detail on whether you're using RC or diamond drills, or both? And then maybe you could say a bit about how the drilling is being carried out—is it concentrated on particular targets, or are you spread across the various core systems you've identified? Or any detail you can offer in that kind of context would be very helpful.
David Strang
executiveJackie, on the question of rig availability, that mostly comes from rigs we already own internally. We did bring in 1 rig — as you can see, at the start of the year we stood at 28. There's a chance we could bring in one more for a particular purpose we're considering. That said, at present we'll likely sit somewhere in the neighborhood of 27 to 29 rigs. Every one of them except a single unit is core. We have that one big <<inaudible>> that we operate. It serves as our scouting rig across Valley, traveling around to check out specific areas. As we've made the pivot toward the regional, I'd say some of the ongoing exploration success we've had — especially near the deepening project — is probably why we haven't placed as many rigs on the region as we'd expected by this point, though we will as we move into the back half of the year. At the moment we're zeroing in on particular areas. As for the program, mainly in and around the Sirabian district for our first pass and a few of the things we've observed there regarding the complete greenfields work. And we'll see how it goes.
Jackie Przybylowski
analystSo I suppose what I'm really asking is this — will the regional program give you enough data that you could begin putting some of it into inferred, or M&A, or some other kind of resource category?
David Strang
executiveRegarding this year — yes, this year. Jackie, that is a fair question, though giving a sensible answer is difficult. As for anything we undertake, obviously, once we have made a new discovery. And if you take Siriema from last year as an illustration, there is definitely a chance that this could happen. But in general, we want to — before we even put out word of a new discovery, as you know, we want to be sure that the resource in question can be brought into the 43-101. So typically, if you use Siriema as an illustration, that was 19 holes before we even made the announcement. And I believe by the time we completed the 43-101 last year, we were probably at 25 to 30 holes. So if you see us announce a new discovery, it will rest on the basis that there is a high probability that part of that discovery will be brought into the 43-101. If we are not announcing a new discovery, that does not mean we have not necessarily found anything. It is simply that we keep doing the work to assemble the resource so that we are able to announce it. So, as you know, as a company, we are not a company that releases single exploration drill results.
David Strang
executiveThat doesn’t strike us as fitting for the kind of company we are. So even though we might have drilled into mineralization, we won’t always put out those results until we feel confident a resource can be established around it. Could someone please ask Noel a question?
Operator
operatorThat brings us to the end of the question-and-answer session, sir. At this point I'd like to hand the conference back to management in case they have any closing remarks to offer.
David Strang
executiveNoel, would you like to offer a few final thoughts?
Christopher Dunn
executiveYes. Well, thanks to all of you. As David mentioned, there are numerous moving pieces in our operations, at both NX and MCSA. And at the same time, we're contending with the COVID crisis. In my view, the company is performing remarkably well. On the operational side, our management team and employees in Brazil continue to draw nothing but complete admiration from us — they are accomplishing incredible work under very challenging conditions. And a tremendous opportunity lies ahead of us. There is plenty for us to do. This is a difficult period. Still, I believe the team and the company are doing the very best they can, producing such tremendous returns and profitability. With our cash costs so low on a global basis, your company is in great shape, and we look forward to talking with you again down the road. Thank you.
Operator
operatorThanks. That brings us to the end of today's conference call. You can go ahead and disconnect your lines now. We appreciate your participation, and enjoy the rest of your day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Ero Copper Corp. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Ero Copper Corp. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research