Ero Copper Corp. (ERO) Earnings Call Transcript & Summary

November 11, 2021

Toronto Stock Exchange CA Materials Metals and Mining earnings 30 min

Earnings Call Speaker Segments

Operator

operator
#1

We appreciate everyone being on the line. I'm the conference operator speaking. Welcome to the Ero Copper call covering financial and operating results for the third quarter. Just a reminder that everyone joined today is in listen-only mode, and this conference is being recorded. Following the presentation, attendees will have a chance to ask questions. <<operator_script>>. At this point I'd like to hand the conference over to Noel Dunn, Executive Chairman of Ero Copper, to give opening remarks. Please go ahead.

Noel Dunn

executive
#2

Thanks, operator, and good morning, everyone. The news release that announces Ero's financial results for the third quarter of 2021 is up on our website, along with our financial statements and MD&A covering the three months and nine months that ended September 30, 2021. On this call we'll be making forward-looking statements, and those involve risks and uncertainties about the Company's businesses, operations, and financial performance. For a discussion of the Risk Factors in our business and how they could affect our future performance, we'd point you to our most recent AIF, which is available on our website, SEDAR, and EDGAR. Unless we say otherwise, all amounts we discuss on this call are in U.S. dollars. With me today are David Strang, Co-Founder and Chief Executive Officer; Makko DeFilippo, President; Wayne Drier, Chief Financial Officer; and Courtney Lynn, Vice President, Corporate Development and Investor Relations. Our third quarter centered on executing the milestones and objectives that are key to our growth strategy. Following the results of our updated Boa Esperança project, which we highlighted this past quarter, we stay focused on creating long-term shareholder value by maintaining quality margins and by continuing to execute on high return, low capital intensity projects. That formula has underpinned the industry-leading returns on invested capital that we have generated, and it also underpins how we approach future growth.

Noel Dunn

executive
#3

Like we said, Boa Esperança stands out as a strong illustration of that approach. Beyond extending copper output over the mine's life by a factor of two relative to the 2017 study, we lifted yearly output levels, stretched out the mine's lifespan, and have spotted further upside chances inside the existing design that we're quite far along in chasing. Equally important, this ranks among the copper development projects with the lowest carbon intensity anywhere in the world. Over the quarter, we hit three more milestones that are central to our strategy. Those are: first, wrapping up safely the replacement of two mill shells at our MCSA Mining Complex as we get ready for expanded operations; second, bringing the Phase One cooling plant into service successfully — a first for the Pilar mine; and third, completing the Goal Stream with Royal Gold that we had announced earlier. Altogether, our team achieved meaningful strides this quarter in getting both the company and the balance sheet ready for a successful stretch of investment in substantial growth that we expect to unfold across the coming years. If you look back to the time we bought our asset portfolio, the aim was to place the MCSA Mining Complex and the NX Gold mine on firm ground. We'd say we met that aim across the past four years — including the roughly two-year shadow of COVID — having more than doubled output volumes and reserve life at MCSA.

Noel Dunn

executive
#4

At NX Gold, we've built an operation that's both sturdy and inexpensive to run. Unit operating costs have come down considerably throughout our portfolio; we've established one of the biggest exploration programs anywhere in the world; we've put meaningful money into modernizing and optimizing our processing operations; we've deepened and broadened our dedication to backing the communities where we work, and set multiple records across the history of our assets when it comes to safety performance, while cutting lost time incident rates sharply over the years. With our focus now shifting to carrying out our two key projects in the years ahead — the new external shaft at the Pilar mine and construction of the Boa Esperança project — our balance sheet has never been in better shape. Beyond the solid operating cash flows our mines produce, the balance sheet got a boost this quarter from the $100 million in upfront proceeds tied to the NX Gold Stream. Advances on the COVID-19 front in Brazil during the quarter also did a great deal to strengthen our operational resilience. Case numbers have gotten better across the country as vaccination campaigns roll out at the federal, state, and municipal levels. Our colleagues in Brazil have made major strides in protecting themselves, their families, and the communities where we operate, with more than 95% of our mine site employees having received at least one dose, and over 50% of our workforce now fully vaccinated.

Noel Dunn

executive
#5

At this point I'll hand things to David, who'll walk us through how operations performed. Wayne will then take over to discuss Ero's financial results for the third quarter. As usual, our team will be on hand to take questions right after this call wraps up.

David Strang

executive
#6

Thank you, Noel. I want to second what Noel said regarding the distance this organization has traveled, and I also want to discuss the distance we intend to cover in the years ahead. We have established a culture centered on innovation and optimization, along with a robust team, and that combination will keep letting us turn our strategy into reality and deliver returns to shareholders. Over at the MCSC mining complex, our strong and stable foundation acts as a cornerstone for our vision of an expanded Hub-and-spoke operating model. As Surubim open pit operations ramp up, the count of ore sources feeding the mill rises from two to three. We likewise kept up a meaningful exploration investment throughout the Curaçá Valley, expecting that what the drill has delivered will eventually become further sources of mill feed. At the Pilar mine, our review of the 2020 shelf design for the deepening extension project is nearing completion. Although the improved shelf design with a larger diameter calls for greater upfront capital, we consider that decision well justified by the operating efficiency gains we expect, plus the inherent potential to raise production volumes from Pilar substantially over the medium to long-term.

David Strang

executive
#7

As we mentioned earlier, we finished both phases—the second and final ones—of mill maintenance at the MCSA mining complex in the quarter, getting ready for continued growth of our operation. Our third quarter results reflect the planned downtime tied to this work. All told, mill throughput came to roughly 570,000 tonnes at a grade of 1.9% copper. The steadiness of our improved metallurgical recovery rates across grade profiles was clear once more this quarter, thanks to the recent HIG mill installation, which keeps benefiting our operations. Copper production was strong at just over 10,000 tonnes, achieved through a mix of favorable grade reconciliations in active areas within the Pilar mine and ongoing planning efforts aimed at producing supplementary high-grade tonnes from the upper levels of the mine. With mill maintenance complete, during the third quarter, we expect higher mill throughput volumes to drive higher copper production in the fourth quarter, despite lower expected process grades tied to the ramp-up of processing ore from the Surubim open pit. Consequently, we continue to guide toward the high-end of our full-year production guidance of 42,000 to 45,000 tonnes of copper. Our operating costs and KPIs during the third quarter reflected lower copper production stemming from reduced mill throughput and inflationary pressures affecting many other key input consumables.

David Strang

executive
#8

Even though those inflationary pressures have carried over into the fourth quarter, we anticipate that our unit costs at MCSA this quarter will likewise gain from greater mill throughput and higher copper production rates. In light of year-to-date C1 cash costs at MCSA that are still under the bottom of our guidance range, along with the expectation that we will turn in a solid cost performance during the fourth quarter, we are continuing to hold our guidance at the lower end of our full-year C1 cash cost guidance range of $0.75 to $0.85 per pound of copper produced. Our capital expenditure guidance for the full year has been revised to reflect acceleration of Phase 2 of the cooling project at the Pilar mine. That covers the placing of long lead order items for our new external shaft, which we now expect to incur in the fourth quarter, and the effect of inflation and specifically higher consumable pricing on our capitalized development. The forecast increases in capital expenditures for the full year at the Pilar mine and the deepening extension project have been partly offset by CapEx reductions in the fourth quarter at MCSA and Surubim, since we have given priority to projects with higher returns. At our NX Gold operations, we produced just over 9,400 ounces of gold during the quarter, and we are tracking towards the high end of our full-year production guidance for that mine.

David Strang

executive
#9

At NX Gold, our cash costs, all-in sustaining costs, and operating cost KPIs were likewise hit by inflationary pressure. That said, we reordered certain CapEx activities over the course of the year and moved a portion of sustaining capital into 2022. Consequently, we are bringing down our full-year all-in sustaining cost guidance range to $650 to $725 per ounce of gold produced. Over at Boa Esperança, we have raised our capital guidance for the full year as we push forward on road construction, detailed engineering, and exploration work ahead of a construction decision in the first half of 2022. Complete details on our reaffirmed production guidance, cash cost guidance, and updated capital guidance appear in our news release and MD&A. Before handing the call to Wayne, I would like to acknowledge the tremendous work our organization is doing to support our communities, which continue to recover from the financial toll of the pandemic. Thus far this year, we have donated roughly 10,000 food baskets to families in need in the area of influence of our operations. And we anticipate carrying this program on through the end of the year. In the third quarter, we also broke ground on a multi-year $4 million hospital clinic renovation, which we expect will substantially enhance access to and quality of medical care for all stakeholders in the Curaçá Valley.

David Strang

executive
#10

Just as a quick aside—since today is Remembrance Day, I’d like to take a moment to honor and keep in mind all those who gave everything. Wayne, the floor is yours.

Wayne Drier

executive
#11

Thanks, Dave, and good morning, everyone. Strong operational results in the third quarter, together with ongoing strength in metal prices and increased quarter-over-quarter copper sales volumes stemming from a decrease in finished goods inventory, pushed adjusted EBITDA to $72.9 million, taking year-to-date adjusted EBITDA to roughly $245 million. We also posted record quarterly cash flows from operations of $150.7 million, mainly because of the $100 million in upfront cash we received when the NX Gold Stream with Royal Gold closed. Consequently, we have produced close to $300 million in cash flows from operations so far this year. I believe the accounting treatment for the Stream agreement deserves a mention. The $100 million upfront cash consideration was recorded on our balance sheet alongside offsetting current and non-current deferred revenue liabilities. As we deliver the ounces under the Stream, just as we did in the third quarter on a prorated basis to reflect the May 1 effective date, our revenues from these stream sales will consist of two components. The cash revenues, based on a percentage of spot call prices, and non-cash revenues, meaning the amortization of deferred revenue liabilities tied to the $100 million of upfront Stream proceeds. Further detail on how our realized pricing for the NX Gold Stream sale builds up can be found in our MD&A.

Wayne Drier

executive
#12

On the topic of our foreign exchange derivative contracts, realized settlements for the quarter came in at $4.4 million, which is a decrease of roughly $1.5 million from the second quarter, when we took the opportunistic step of accelerating settlement on a portion of those contracts to capitalize on temporary strength in the Brazilian Real. As I've noted on earlier earnings calls, we still anticipate FX settlements landing somewhere in the range of $4 million to $6 million each quarter, assuming the Brazilian Real remains relatively range bound around these levels. I'd also note that these foreign exchange derivative settlements show up in our adjusted EPS figures but are not included in adjusted EBITDA, since we treat FX hedging as an ongoing corporate-level activity rather than part of our underlying operating business. Headline net income for the third quarter was $26.4 million, with $26.1 million, or $0.28 per fully diluted share, attributable to Ero Copper shareholders. Once we adjust for non-cash items, including unrealized foreign exchange gains, adjusted net income came to $45.7 million, or $0.49 per fully diluted share. As mentioned earlier, our balance sheet strengthened substantially in the third quarter, thanks to receipt of $100 million upon closing of the NX Gold Stream.

Wayne Drier

executive
#13

Using that money, we paid down $100 million of principal against our $150 million revolving credit facility. That left us with available liquidity of close to $220 million at quarter-end: roughly $120 million in cash and short-term investments, plus $100 million of revolver availability. I'm glad to share as well that, for the first time since our IPO, the balance sheet now sits in a net cash position of about $64 million. With that, I'll turn the call back over to Noel, who has some closing remarks.

Noel Dunn

executive
#14

Thank you, Wayne, and to everyone who joined today's call. Before we begin the Q&A session, I want to acknowledge and express appreciation to the Ero team—particularly our colleagues in Brazil—for their daily hard work in delivering strong operating performance while also reaching the milestones that are critical to advancing our growth strategy. As we begin a multi-year phase of growth investment, our company and our team have never been stronger. I'm excited to see that reflected in how we execute our strategy and in the value we're creating for shareholders. I'll now hand the call back to the operator so the lines can be opened for questions.

Operator

operator
#15

Thank you. At this point we'll move into the question-and-answer portion. <<operator_script>>. Orest Wowkodaw with Scotiabank has the first question. Go right ahead.

Orest Wowkodaw

analyst
#16

Hello, everyone, and good day. We were hoping you might give us some additional detail on your present view regarding the new Pilar shaft. I understand it seems you'd like to increase its size, and clearly that will cost more, since it is larger. It also sounds as though you encountered some inflation. Even so, you obviously still gain the benefit of a larger shaft for the production profile. Could you offer any insight into roughly how you expect all of this to fit together, and then when the market might gain some visibility into what some of those details could look like?

David Strang

executive
#17

Sure, Orest. Given how well exploration has kept going — reaching further down into the mine, with resources still open at depth — we saw a chance to make the shaft deeper. Doing that let us then examine which other efficiency gains were available. As I understand it, the present shaft plan calls for an additional 200 to 300 meters of depth. By widening the shaft as well, we expect efficiencies in three key areas. First, we'll cut back on, and potentially nearly eliminate, hauling waste out of the deeper section via the ramp with trucks, since we can now use the shaft for that job, which boosts efficiency and brings costs down. Second, shift changes will turn around faster and more efficiently when it comes to moving men up and down that shaft. And third — though it's the smaller one, we consider it fairly important — we free up the ramp by also using the shaft to move consumables up and down from those deeper levels.

David Strang

executive
#18

So ultimately, what this lets us do and assess is that by giving us more chances to use the ramp—especially in the shallower sections of the mine—there’s potential over the longer term to pursue bigger efficiencies and opportunities to boost output in the upper portions of the mine as well. As for how that unfolds, clearly, we—the technical report we currently have out, as of last year, isn’t being updated. We don’t see any material change to the business that would justify altering the 43 to 101 report. And we’re now shifting to a five-year guidance methodology. So although the shaft will be built during that timeframe, unfortunately, within it you won’t see the full upside potential reflected once that shaft is finished. But as we progress on a year-on-year basis, you’ll see that show up through greater production coming from the depths—the deeps, which is the other area I forgot to mention. We think we’ll be able to mine more material from the deeps, and you’ll see greater efficiencies in operations when it comes to reducing costs as well.

David Strang

executive
#19

So for that reason, we believe right now is an excellent moment to move forward with that and carry out a solid build of the shaft.

Orest Wowkodaw

analyst
#20

Following up on that, what's your expected schedule for finishing the shaft and getting it into operation?

David Strang

executive
#21

Our expectation is that this will occur at some point toward the end of 2024.

Orest Wowkodaw

analyst
#22

Alright, alright. Then you brought up that you're shifting to guidance covering 5 years. My assumption is that happens in January, though I might be mistaken about that.

David Strang

executive
#23

That is accurate.

Orest Wowkodaw

analyst
#24

Does that cover a production profile, costs, and CapEx, or is it strictly all three together? All right, great. All right, thanks so much. I'll let another person take a turn in the queue.

David Strang

executive
#25

Much appreciated, Orest.

Operator

operator
#26

Jackie Przybylowski from BMO Capital Markets has our next question. The line is yours.

Jackie Przybylowski

analyst
#27

Thank you so much. I suppose my question is about Boa. The report mentions that Boa is still awaiting approval—from your Board, I take it. So I was wondering, what's the timeline for that? What does the Board need to see before it can make that call, and what would that shift when it comes to how you proceed with spending or plans?

David Strang

executive
#28

Thanks for those questions, Jackie. On that point, the Board has gone through the feasibility study, and we discussed what our aim was — and although the Board feels it could reach a decision on that study, from where we sit it seemed wiser to fold in a portion of the more granular engineering work, together with certain drilling work that will come from the gap zone, so that the Board can review that material and the project as a whole. So it isn't — neither the Board nor management identifies any fatal flaws in the project; it's simply that we'd rather the Board reach its final call on the project armed with the strongest information before construction begins. So that's what we've done — a management decision made together with the Board. That said, as you'll notice, we are — we have already spent some money, and we'll spend more during this year's fourth quarter on certain development at the project, especially some civil works involving roads, and further capital will go out before formal Board approval, toward the back half of the first quarter, for some additional work that has to get done.

David Strang

executive
#29

This isn't about major spending on cost—it's about the work that has to get done to keep the approved project advancing on the schedule we want to maintain. And that comes down to a construction decision. I mean, starting the civil construction work somewhere around the April, May timeframe.

Jackie Przybylowski

analyst
#30

That’s precisely the reason I raised the question. You’re absolutely right. And I suppose, to return to what you said—or regarding the guidance—I’m assuming that for 2022 and for the five-year guidance, you’d be operating on the assumption that Boa will be approved and therefore will be included in that, and then I guess, in a situation where it wasn’t for some reason, you’d likely revise guidance at that point. Is that the correct way to think about it?

David Strang

executive
#31

So what we'll do on that front is have a budget that gets approved by the Board, and that obviously feeds into guidance for 2022 and beyond. What we — and so there'll be some capital tied to that, which goes into the general capital budget, our sort of number. And after that, we'll put a line item beneath it that highlights the Boa costs in each subsequent year. That way we'll make it simple for you folks to tell the two apart and to see when the numbers get triggered.

Jackie Przybylowski

analyst
#32

Thanks a lot — that’s great.

David Strang

executive
#33

Is that clear?

Jackie Przybylowski

analyst
#34

Yeah, Noel, that works great. Appreciate it.

Operator

operator
#35

We'll take our next question from Stefan Ioannou at Cormark Securities. Go right ahead.

Stefan Ioannou

analyst
#36

Yeah, thanks a lot, guys. I'm just wondering whether there's anything more recent to share, or perhaps not only regarding how the ore sorting is coming along and what your thinking is on that, when it comes to putting it into practice?

David Strang

executive
#37

On ore sorting, as with everything else we do in the district, we keep evaluating — that's the great thing about this company. It's our capacity to assess opportunity sets and determine when and what delivers the highest return for our shareholders. On that point, as you know, N8/N9, the deposits close to Vermelhos and the open pits there, their construction depends on us implementing ore sorting. At present we see other near-term opportunities from other ore sources that give us a higher return than those projects. So ore sorting is very much linked to our implementation of it with respect to N8/N9. And we see other opportunities in the portfolio right now through which we can achieve higher returns while maintaining our copper production over the next few years, which suggests we can perhaps defer some of that construction and implementation.

Stefan Ioannou

analyst
#38

Understood. As we discussed previously, some other deposits—Surubim being one example—aren't really as well suited to ore sorting, are they?

David Strang

executive
#39

Yeah, well, it isn't necessarily the case that — when you've got a portfolio like ours, and the flexibility we have to adjust — we have this optimization project that we're doing within the Pilar mine. Specifically, the areas that we've seen — and you'll see there's a significant difference between the reserves and resources highlighted for Pilar. We see opportunity there, and we're starting to see opportunities within that mine that allow us to mine higher grade material and evaluate higher grade material that gives mined at a lower cost and obviously less capital requirements versus these projects, and give us the same amount of copper production. So naturally, what you would do is you would do that before you build those.

Operator

operator
#40

We move to a follow-up from Orest Wowkodaw at Scotiabank. Go ahead, Orest — your line is open.

Orest Wowkodaw

analyst
#41

Apologies for that—just flagging that the queue is short today. Thanks for letting me ask a follow-up. You’ve mentioned inflation a few times in the release and in today’s update. I’m curious specifically about Boa: I mean, you recently revised the capital figure there, I believe it’s $294 million. Is that number still pretty much valid, or can you give us some color on it?

David Strang

executive
#42

Sure thing.

Orest Wowkodaw

analyst
#43

So that's reflecting what input costs are right now?

David Strang

executive
#44

That really mirrors what input costs looked like around the middle of the year. And as everyone is aware, steel and cement expenses make up two major pieces of that sort of capital figure. What we've observed after the capital estimate was issued is that, clearly, steel prices eased during the third quarter. And we've also seen that show up in certain costs we've been running into at other mines, where steel pricing has declined. So at this point I'd say our capital costs for Boa have been fully loaded for the costs that were estimated at mid-year this year.

Orest Wowkodaw

analyst
#45

All right, that's great. And could you remind me what percentage for contingency is included in that figure?

David Strang

executive
#46

Orest, that figure sits at roughly 5% — don't pin me down to a range of 5% to 8%, and that range itself mirrors 7%, which mirrors how much detailed engineering has been finished as of today.

Orest Wowkodaw

analyst
#47

So regarding the development plan for Boa, is there a plan for them to build it on their own, or will that be outsourced to an EPCM? I'm just curious about what the approach would be.

David Strang

executive
#48

Correct — we'll be handling an EPCM or EPC contract when it comes to building it.

Operator

operator
#49

That brings the Q&A portion to an end. I'll now hand the conference back to management in case they have any closing comments.

David Strang

executive
#50

Thanks, Operator. And thanks once more to everyone for joining us today on Remembrance Day and taking part in this call. Also, to repeat what Noel said, a big thank-you to our team, who keep working hard to make our company successful. And thank you to all of you for your efforts in following us, and to our shareholders for their support. With that, Operator, we'll bring the call to a close. Thank you.

Operator

operator
#51

Appreciate it. That brings us to the end of today's conference call. You can go ahead and disconnect your lines now. Thanks for joining us, and enjoy the rest of your day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Ero Copper Corp. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to Ero Copper Corp. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ero Copper Corp. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.