We appreciate everyone holding on, and we’re glad to have you join the Evolution Mining conference call on the March 2020 quarter results. <<operator_script>> At this point I’ll turn the conference over to Mr. Bryan O’Hara, GM, Investor Relations. Please proceed.

Bryan O'Hara

executive
#2

Thanks, Izzy. Good morning, everyone, and welcome to the Evolution Mining conference call covering the March 2020 quarter. Joining us this morning are Jake Klein, our Executive Chairman; Lawrie Conway, CFO and Finance Director; and me — and we're all keeping a proper social distance here at Evolution's group office in Sydney. We're also joined by Bob Fulker, COO, and Glen Masterman, VP, Discovery & Business Development, both of whom are on the line remotely. The quarter ended March 2020 will go down in history, as the COVID-19 pandemic set off some of the biggest and swiftest drops ever seen in financial markets. Governments and central banks worldwide have answered this crisis by pledging extraordinary monetary and fiscal stimulus, and it has been heartening to watch gold play its part as a relative store of value, with the Australian dollar gold price climbing more than 25% so far this year to a record above $2,700 per ounce. Although gold equities were swept up in the broader market's extreme swings in early March, they have rebounded firmly, and a number of Australian and global gold producers are now trading at or close to record highs. Evolution stands out among them, with sector-leading cash generation per ounce, a commitment to rewarding shareholders via rising dividends, solid balance sheet liquidity, a track record of dependable operational delivery across our diversified portfolio, and an appealing growth profile powered by Cowal and, now, Red Lake.

Bryan O'Hara

executive
#3

Much appreciated. Now I'll pass things along to Jake.

Jacob Klein

executive
#4

Morning, everyone. Thank you, Bryan, and thanks to all of you for making time to be with us on today's call. We genuinely appreciate it. I also want to say that I hope you, your families and your colleagues are all healthy and well and finding your way through these unprecedented times that all of us are facing. Here at Evolution, we do recognize that we belong to a very small minority of businesses operating in an environment where, if we can get our colleagues to sites and keep them healthy and safe — which we have managed to do so far — we are in a very fortunate position where we can sell everything we produce at the current record-high gold prices. We are doing our best to remain grounded, to engage openly and transparently with our communities and to respect the very tough times so many people are going through. To date, our management of the COVID-19 pandemic has been very good. We are navigating through this with authenticity and staying true to our health and safety values whilst continuing to keep our business strong. To date, there have been no reported cases for our employees or our contractors and no impact on our production related to COVID-19.

Jacob Klein

executive
#5

There are numerous striking instances of how dedicated our workforce is, and we feel thankful toward them. To keep disruptions to a minimum, staff have demonstrated a readiness to step up beyond normal expectations and adapt by working extended shift rotations or, for certain critical positions, moving closer to the operations so that travel between states is avoided. On safety, we are making gains. We have not reached the standard we aim for yet, but what bolsters my confidence most is that Fiona Murfitt, our General Manager of Sustainability, remarks that following 3 months inside the business — and what a 3 months it has been — she perceives a real depth of care existing throughout the organization, which underpins any strong safety culture and, for that matter, any strong corporate culture. Our ongoing efforts and attention in sustainability were recognized with an upgrade of our MSCI sustainability rating from BBB to A. As you have grown to expect from Evolution, we stay focused on margin and cash flow. We firmly believe this ought to serve as a distinguishing metric for shareholders examining this sector. Net mine cash flow rose 11% quarter-on-quarter to nearly AUD 160 million, while group free cash flow climbed 33% quarter-on-quarter to nearly AUD 112 million, and both represent highly pleasing outcomes.

Jacob Klein

executive
#6

Cash flow remains robust. As of today, our cash balance has grown to roughly $240 million, and when you factor in our undrawn revolver facility, liquidity stands at about $600 million. Having financial strength and robustness matters in times like these that are uncertain. This quarter, our results also illustrate the benefits of holding a portfolio of assets where some assets are delivering material contributions — assets that at times in the past have been overshadowed by our larger ones. Both Mungari and Cracow delivered record net mine cash flows this quarter. Mungari has produced a very impressive $73 million in net mine cash flow year-to-date and is also enjoying very encouraging exploration success. The June quarter will be a big one for us, and we expect it will bring us in at our guidance of around 725,000 ounces at an all-in sustaining cost at the top end of our guidance range of AUD 990 an ounce. These figures exclude any contribution from Red Lake. The rise in production will mainly come from Mt Carlton as it accesses higher-grade material for the first time from the underground mine that it has developed, and also from Mt Rawdon, which is expected to be back mining the higher-grade area of the pit after recovering from the rockfall it had in the September quarter.

Jacob Klein

executive
#7

We had the good fortune of being able to access the Red Lake site for more than 3 months, from when we signed the deal in late November until the lockdown began. Acquiring an operation that you cannot physically be at when the keys are handed over is something none of us had experienced before, but I believe the teamwork, the preparation, our use of technology and the level of engagement really show what is special about Evolution. If our first 3 weeks of ownership offer any indication of what lies ahead, Red Lake will surpass even our most optimistic expectations. We were happy that, under the locked box mechanism in place since 1 January, we will get AUD 18.8 million in April. We are also using this opportunity to build up our team and place the right people in the right roles. At Red Lake, change is already underway, beginning with the appointment of Amber Adams as Interim General Manager and a 40% cut in site leadership team roles. I have felt hugely encouraged and impressed by how Amber and her new team have taken on the challenge ahead of us to turn the operation around. In a group role of real importance, I am delighted to announce that Amanda Weir has been appointed General Manager, Transformation and Effectiveness, a position that reports directly to our COO, Bob Fulker.

Jacob Klein

executive
#8

Amanda brings a truly strong record, having most recently served as Head of Geoscience and Resource Engineering at Olympic Dam for BHP. What matters greatly is that the drill rigs have not stopped turning, and we remain encouraged by the success we are achieving at Cowal, Mungari and now at Red Lake as well, which Glen will tell you more about shortly. With that said, I will pass things over to Bob.

Robert Fulker

executive
#9

Thanks, Jake, and good morning to all of you. It's a pleasure to begin my quarterly remarks with a few positive items on the safety front. Our site behavior safety programs keep delivering solid results, with TRIF falling 15%, from 8.4 down to 7.2, during the quarter. So far, COVID-19 has not had a material impact on us. Regarding COVID-19, we have put in place and are running under rigorous protocols aimed at minimizing risk to our people and communities while making sure we can keep producing gold safely through these times. We have halted international travel, limited domestic travel, implemented stringent social distancing measures, cut back face-to-face interaction, expanded flexible working arrangements and stepped up communications with our entire workforce or, at the very least, we are in line with government protocols. At the site level, we are also holding on-site management meetings tied to our Evolution crisis management daily meetings, conducting shift screening that includes temperature checks, bringing in extra vehicles and chartered flights, applying floor markings in pre-shift meeting areas to support the 1.5 meter distancing, lowering contractor numbers for nonessential mill shutdown work and making changes to rostering as required, all while collaborating closely with the communities where we operate. 5 of our 6 operating sites have workforces that are essentially residential rather than FIFO.

Robert Fulker

executive
#10

That provides a degree of shielding against the effects of travel bans. We also took a lot of encouragement from the fact that infection rates are slowing throughout Australia. As is widely understood, the situation keeps shifting and developing, and daily meetings of the crisis management team are being held to support every operation and office location. During the March quarter, we produced 165,500 ounces at an all-in sustaining cost of $991, which generated net mine cash flow of $160 million. Looking back, this year has brought us some genuine difficulties — wall instability at Mt Rawdon, variability in the ore body at Mt Carlton, and now COVID-19. Even so, taking everything into account, we remain on track to meet guidance in spite of all of these challenges. The outlook across all of our operations excites me. From an innovation, optimization and data standpoint, we are accomplishing some excellent things, and I genuinely believe these will enable our business to strengthen its reliability, repeatability and resilience. We are right now operating in a period of considerable uncertainty, and despite this constantly changing environment, I believe all of our people are performing exceptionally well at managing the risks and making sure everyone stays informed and safe. Turning to Page 6, Cowal produced 60,500 ounces at an all-in sustaining cost of $1,031 per ounce, with net mine cash flow of $34.5 million, even while investing $54 million in total capital projects that build for the future.

Robert Fulker

executive
#11

Our emphasis on leading safety indicators and on building awareness around hand injuries has driven a continued, sustained decrease in TRIF, with Cowal now sitting at 2.5, which is a record for the site. We've also taken a proactive approach to long-term water security, and I'm pleased to confirm that this, together with completion of the pipeline twinning and recent rain, has eased the immediate threat for Cowal from a water availability perspective. Work is continuing on additional saline bores to further cut our reliance on freshwater sources, and we're confident there is sufficient water supply to meet Cowal's ongoing water requirements, with no material impact on operating costs or recoveries. Mungari delivered 33,000 ounces, with an 18% reduction in its all-in sustaining cost of $1,099 an ounce. As Jake said, this came with record net mine cash flow of $31.9 million. Frog's Leg Underground continues to deliver its scheduled tonnes and ounces, and the Boomer development now sits only 90 meters from mineralization. That will be an exciting day for the team at Mungari. The open pit fleet has started the new Cutters Ridge pit, another major milestone for Mungari.

Robert Fulker

executive
#12

The plant is still operating nicely at those higher rates—just about 2 million tonnes per year—and the project team is making progress on figuring out the maximum capacity of the plant. Please turn to Page 7. Mt Carlton produced 13,000 ounces, with an all-in sustaining cost of $1,417 per ounce and mine operating cash flow of $20.1 million. We've sped up underground development and capital spending so that the high-grade underground ore can start producing in the June quarter, and we expect that to drive a substantial increase in output and a decrease in costs. The first underground gold bar came from development ore in March. Grade control drilling is ongoing at both the Mt Carlton open pit and underground, and exploration drilling has begun at Crush Creek. Mt Rawdon turned out 16,400 ounces at an all-in sustaining cost of $1,357 per ounce. While that figure remains high, Mt Rawdon's all-in sustaining costs have come down in line with forecast as I work through the western wall cutback. Net mine cash flow is steady at $9.1 million. Once again, we anticipate improvement as the capital burden from stripping the western wall wraps up. We expect Mt Rawdon's production to rise as access to higher-grade ore in the pit floor is opened up during the June quarter.

Robert Fulker

executive
#13

If you turn to Page 8. Cracow keeps delivering steadily, with output of slightly more than 22,000 ounces, an all-in sustaining cost of $1,150 per ounce, and mine operating cash flow of $31.7 million. And it's good to see that Cracow's net mine cash flow came in at $27.6 million, which was the best ever recorded. Ernest Henry once more contributed substantially to group production, with 20,000 ounces at a negative all-in sustaining cost of $188 an ounce, while producing net mine cash flow of $61.3 million. Page 9 covers Red Lake. At the Red Lake operation, real progress is being made in these -- in critical areas. I'll leave the financial implications at closure to Lawrie. From an operational standpoint, though, the site leadership team has been restructured, a reduction of 40%. We've begun resource definition drilling in the production -- future production zones; raised underground development rates, with a plan to surpass the 1,000 meters per month rate by July; started the underground equipment procurement process; started #1 on Campbell shaft decommissioning; and we've started refurbishing the Campbell mill. It's an exciting period at Red Lake, and the new SLT is energized and motivated to carry on the improvement journey. To sum up, we remain focused on bettering our safety performance and safeguarding the health and well-being of our people while delivering to guidance on both ounces and cost.

Robert Fulker

executive
#14

Amid all the uncertainty and change we're seeing globally right now, I believe we have to stay locked on our objectives, keep our people and our operations linked together, and go on seizing every chance that comes our way. So with that said, I'll now pass things over to Glen. Thank you.

Glenton Masterman

executive
#15

Thanks, Bob, and morning to you all. Before I get into the drilling highlights for the March quarter, I'd like to give a quick rundown of what our discovery group has done to handle the COVID-19 situation. At Red Lake, Cowal, Mungari, Mt Carlton and Cracow, drilling programs are still going, and there we've put in place the strict measures Bob mentioned earlier. Exploration work has been halted at 3 of the 4 greenfields projects we manage and operate in Western Australia and Queensland, so as to avoid any risk of spreading the virus through contact with indigenous communities. At the Crush Creek project, situated 30 kilometers south of Mt Carlton, the exploration program is carrying on. The first diamond holes are now finished, after the first diamond rig turned up 2 weeks ago. Another rig should get here in May, and that will help us speed up confirmatory and extensional drilling of vein targets, which we're hoping will turn into a significant ore source for extending mine life at Mt Carlton. We were delighted to take the keys at Red Lake earlier this month, and by now we've put in a full quarter of drilling under Evolution's stewardship. Throughout the quarter, 4 rigs have been running continuously underground.

Glenton Masterman

executive
#16

At Cochenour and Lower Red Lake, our drilling efforts are aimed at turning resources into reserves and growing the ore bodies in those sections of the mine. To date, recent drill results have us quite encouraged — especially those from Cochenour, which have delivered high grades across solid mining thicknesses. You can see examples on Page 13 of this morning's report. In early April, we kicked off the yearly review of exploration programs and targets throughout all our operations and greenfields projects. That process involves developing, ranking and prioritizing new and existing targets, for which we will propose budgets in FY '21. Targets with the potential to discover new high-grade resources at Red Lake are ranking very highly and will be moved into the FY '21 drilling schedule. At Cowal, underground drilling with 3 rigs keeps building mineral inventory for the maiden reserve, which remains on target for release in the December 2020 half year. Infill result highlights appear on Page 15 of this morning's report. Surface drilling continues with 2 surface rigs and is outlining mineralized extensions at the lava zone, as highlighted by the results received in holes 544C and 453G on Page 15 of this morning's report.

Glenton Masterman

executive
#17

Also, a new zone called Galway South is taking shape on the left-hand portion of the Figure 5 long section on Page 15. That mineralized zone is still open down plunge, and future drilling is planned to push mineralization past the cluster of holes illustrated on the long section, which terminate at hole IDs 545, 466A and 466EXT. Mineralized intercept examples at Galway South include 7.2 meters at 12.1 grams per tonne in hole 545, drilled next to a previously reported intercept of 30.4 meters at 6.6 grams per tonne in hole 545A. At Mungari, drilling at Boomer delivered better results, with a new folded vein position found beneath the original drilling area. Drilling highlights are summarized on Pages 16 and 17 of this morning's report. Access development sits 90 meters from the design breakthrough position, and we expect to reach ore positions later in the 2020 quarter -- the June 2020 quarter. The Boomer structure has not yet been tested for climate north of the main mineralized area. Work along strike has been deferred because cultural heritage clearance is required, and the company has suspended that clearance owing to the COVID crisis.

Glenton Masterman

executive
#18

Having said that, I’ll now pass things over to Lawrie.

Lawrie Conway

executive
#19

Thanks, Glen, and good morning, all. Before we walk through the financial results for the March quarter and the outlook for the year, I'd like to lay out how we're handling the balance sheet amid the COVID-19 situation. For roughly the last month, alongside the steps we've taken throughout the business to protect the health and well-being of our people, we've been making sure the balance sheet stays strong. We have no material production impacts and no liquidity problems, but doing this work is certainly prudent. That meant running multiple scenarios covering different kinds of impacts on our business. When we ran those scenarios, we were getting ready to pay our FY '20 interim dividend of $120 million and to draw down $570 million of debt to close the Red Lake transaction. Both of those items were factored in as well. The scenarios we ran examined the possibility of a prolonged impact on our business, including reduced production across all operations through to the end of FY '21 and a complete suspension of all our operations for a period of up to 6 months, with effects at Ernest Henry also incorporated into every one of our scenarios.

Lawrie Conway

executive
#20

The scenarios made allowance for extra costs stemming from inefficiencies of running the business this way, for any redundancy and restructuring expenses, and for metal prices as much as 25% beneath current spot levels right through to the close of FY '21. What pleased us most about this exercise is that it confirmed we hold a quality suite of assets that generate strong cash and are able to ride out the disruption event over a prolonged stretch. Under the scenarios we ran, every one of our operations would be cash flow positive across the FY '21 year. We may not have captured every element in these scenarios, but we feel comfortable about how robust they are. From a group standpoint, the outcome of the reviews is that we would not anticipate drawing down on our 3-year revolver facility, our debt facility and hedge commitments are all satisfied, and our liquidity would keep growing over this period. It reinforced our confidence to go ahead with the interim dividend payment. Our cash balance in April has risen to approximately $240 million. And together with the undrawn $360 million revolver, we now hold more than $600 million of liquidity. Moving to the financials for the March quarter, which appear on Pages 10 and 11 of the report.

Lawrie Conway

executive
#21

We turned out more than 165,000 ounces, and our all-in sustaining cost came to $991 per ounce. Production ran a bit below plan, yet the better AISC matched plan. Operating costs held steady quarter-on-quarter at comparable activity levels, and sustaining capital fell as we laid out in our December quarterly results. Higher metal prices pushed the AISC up, but net cash generation more than offset that. Had we realized the metal prices our current guidance assumes, all-in sustaining costs for the quarter would have come in at roughly $970 per ounce, and our year-to-date all-in sustaining cost would have been near the $1,000 mark. Net mine cash flow reached $160 million, with records at Mungari and Cracow of $32 million and $28 million, respectively. Group cash flow before dividends, debt and M&A costs came to $111.5 million. Year-to-date group cash flow exceeded $350 million, or $640 per ounce sold. Margins year-to-date are very healthy: an EBITDA margin of 51%, an all-in cost margin of $695 per ounce and a free cash flow margin of about 30%. With the Red Lake transaction closed, drawing down the $570 million term loan moved us back into a net debt position.

Lawrie Conway

executive
#22

Our gearing sits at a very conservative 14%, and by the end of June we intend to bring it under 10%. Repayment amortization on this loan has been matched to group cash flows and to how we expect cash generation at Red Lake to build up over the coming few years. A first repayment of $20 million comes due in July, with $95 million payable through FY '21. Turning to the June quarter and wrapping up FY '20, we anticipate output of roughly 195,000 ounces, and, as Jake mentioned, most of that added production should come from Mt Rawdon, where we'll be accessing higher-grade ore in the open pit, and from Mt Carlton, which is reaching first production at the higher-grade underground mine. That takes the full year to approximately 725,000 ounces, at the top end of AISC guidance of $990 per ounce. Red Lake is excluded from this. If spot metal prices hold at current levels through the June quarter, higher royalties and lower byproduct credits would hit our AISC by $20 to $25 per ounce. Even so, our cash flow would be $90 million to $95 million greater than at the metal prices our guidance assumes.

Lawrie Conway

executive
#23

And finally, at Red Lake, we expect roughly 25,000 ounces at an all-in sustaining cost between AUD 2,100 and AUD 2,300 per ounce, as that operation concentrates on putting the interim and transformation plans into practice. Sustaining capital should come in at about $5 million to $7 million, and major capital at about $15 million to $17 million, while exploration investment is anticipated to be $3 million to $4 million. Thanks for spending time with us this morning. I'll now hand things to Izzy to open the line for questions.

Operator

operator
#24

<<operator_script>> Today's initial question will be taken from Nick Herbert at Crédit Suisse.

Nick Herbert

analyst
#25

Let me begin with Red Lake. Jake, you brought that up during your remarks. What I’m curious about is how significantly the COVID travel restrictions are affecting your capacity to carry out the initial plans for that site, since you’re unable to get key personnel or equipment there.

Bryan O'Hara

executive
#26

Appreciate that, Nick. Jake’s going to take that question.

Jacob Klein

executive
#27

Thanks, Nick. It's great to see you're carrying on your predecessor's tradition with the first half report.

Nick Herbert

analyst
#28

A handful of tricks came my way from him.

Jacob Klein

executive
#29

We’re eager to keep moving forward. Obviously, COVID-19’s effects kept us from physically being at the site when we acquired the asset. Even so, we’ve had the chance to spend a number of months there in person. The entire leadership group, along with quite a few members of our technical and commercial teams, have been present on the ground. We put substantial planning into it, and some of our colleagues remain on-site right now. But just as we do across every one of our locations, we are supporting the leadership group—the new leadership group—at that site. Amber Adams, as I mentioned, has taken on greater responsibility. We have reshaped the leadership structure. We’ve cut the number of positions by 40%. That site was prepared for change, and the people there are genuinely getting behind it. And although we know difficulties lie in front of us, technology has let us run 5 virtual town hall meetings, meaning we’ve reached most of the employees there in a highly interactive format. Responses from those meetings were favorable. I don’t see it as limiting the changes we intend to carry out, and I’m quite encouraged by these first few weeks.

Nick Herbert

analyst
#30

All right, that's good to hear. And then, I suppose, you've been fairly clear about that 3-year turnaround schedule of yours. But I'm just wondering whether you could point to some milestones closer in, so we might get a sense of things by looking at that performance and thinking about when we could perhaps see a notable step up in productivity mine rates, or a significant staff cost reduction coming through — really, anything that represents major progress ahead of that full 3-year implementation period.

Bryan O'Hara

executive
#31

Thank you, Nick. Jake is going to address that question too.

Jacob Klein

executive
#32

Nick, we also picked up some lessons from the person who held your role before, and one of them is to avoid the trap of revising the promise too fast. So that 3-year time line stays as it is. There are encouraging signs, and I'll have Bob walk through a few of them and flag some of the things we view as opportunities there.

Robert Fulker

executive
#33

Thanks, Jake. I suppose I'll begin with a few of the simpler items. On development, we've already begun reaching some of our targets quite pleasingly, and we're seeing growth month over month. We do anticipate that around the July-August window we will in fact be surpassing that rate of 1,000 meters per month, and we're currently on track to achieve it. So that's a good one to kick off with. The second item involves some of the infrastructure work we have underway, such as the Campbell shaft shutting, which, although it's a minor one, matters a great deal in terms of fixed cost and everything else. And that will take place probably in the -- not probably, it is scheduled to take place in the March quarter of '21. So that's a good one to mention too. The other one is something we're currently working through with the leadership team. We worked on the leadership team. We spoke with them first and, as both Jake and I have said, restructured it and a 40% reduction of people in that team. Now they're in fact working with the site teams and with the people on the ground to actually examine the entire workforce.

Robert Fulker

executive
#34

We anticipate that taking place in the current quarter, toward its latter portion. So our workforce will be the first group we speak with. Still, within this quarter, we expect the bulk of those enhancements to be firmly in place.

Nick Herbert

analyst
#35

Great. Bob, that was really useful. Perhaps just a couple more questions. One relates to the gold price, Jake. Your reserve price now sits at AUD 1,450, which remains well underneath the spot price. I’m curious what prompted the shift in your thinking there. Or maybe, what period of time would gold need to hold around where it is today before you’d reconsider that reserve price once more, and could that have any effect on how you plan the mine?

Jacob Klein

executive
#36

Yes, Nick, that's a solid question. What we really want to determine is whether these $2,700 levels hold up — are they lasting, are they here for the long term. When we put together our budgets and did our planning for this year, the gold price assumption we used was AUD 1,800. That means the gold price now sits $900 above it. As you've gotten to know us by now, margin is where our focus lies. This is a cyclical business. We're currently in a very favorable portion of the cycle. We hope it improves further. But looking at it from a business standpoint, as Lawrie mentioned, the way we stress test the balance sheets for events of the kind we can't anticipate, like COVID-19, we want to be a business capable of prospering right through the cycle. So it will be a conservative reserve price. We'll reassess it at the end of this year when we do our MROR once again, just as we always do, but it will stay conservative, because we want to be a margin-focused business.

Nick Herbert

analyst
#37

Right, that tracks. Last thing, along similar lines, I suppose: how are you thinking about hedging any appetite past what you've already locked in for Red Lake? And then on the Stage H cutback at Cowal, that's a big material movement. So I'm just wondering, how much of a swing factor is the oil price when it comes to the economics of that cutback? And are you considering locking in some oil price hedging at all?

Jacob Klein

executive
#38

Thanks, Nick. First off, on the hedging question — yes, look, with Red Lake, when we consider that 3-year turnaround plan, we wanted to be sure that the asset can fund its own capital programs and essentially not create an impact on the rest of the business. So we did place 120,000 ounces in at an average of a spot average $2,300 an ounce across the 3 years. That works out to roughly 10,000 ounces there per period. But past that, we don't see a need to put more in place at Red Lake. We don't want to go — at a group level, we're probably, when you take that plus existing hedges, around 15% of our annual production is hedged, and the benefit we see is that 85% to 90% of our production is exposed to the spot price. So we're comfortable — we're continuing to use hedging more as a tool for balance sheet and capital management rather than trying to claim that we know what the gold price is going to be. On the diesel side, the thing I'd say there, yes, Stage H is certainly our biggest user. Diesel is 5% of our cost base, and we are looking at, as we do our FY '21 LOMs and budgets, whether there's any benefit there for us.

Jacob Klein

executive
#39

If we look at where diesel spot prices sit right now, accounting for the weakening Aussie dollar, that translates into an all-in cost improvement of roughly $20 per ounce over a full year — obviously leaving Red Lake out of that. What we're observing, though, is that oil's forward curve still doesn't mirror today's spot levels. Essentially, somewhere in the 18-to-24-month window, prices climb back above the levels assumed in our current plans. So over the coming few weeks, as we wrap up our life of mine plans, we'll factor that in for Stage H.

Operator

operator
#40

Daniel Morgan from UBS has the next question for you.

Dan Morgan

analyst
#41

We have a few questions. Regarding the Stage H reduction at Cowal, I'm just curious what your current view is on the timing for finishing that.

Bryan O'Hara

executive
#42

Thanks, Dan. Lawrie is going to handle that one.

Lawrie Conway

executive
#43

Yes, Dan, thank you. Our expectation is that we will be completely in ore by the close of FY '21, which means the Stage H cutback will be finished at that point as far as its capital waste position is concerned.

Dan Morgan

analyst
#44

All right, that's very clear. Turning to Red Lake, you mentioned some early wins or milestones, and one of them is the higher development rates. I'm just wondering how you're managing that when it's so early—you've only just got the keys, and you haven't brought in new equipment or put new protocols in place. I'm curious how you're achieving those higher development rates this early. What's behind the improved productivity?

Bryan O'Hara

executive
#45

Thanks, Dan. I'll pass things to Bob, and he can build on the answer he gave a moment ago. Thanks, Bob.

Robert Fulker

executive
#46

Okay, thank you, Bryan. Dan, I appreciate the question. There's nothing magical about it. Our development efforts have been concentrated in the zones where we intend to generate output. So we've taken workers out of the less productive regions and moved them into the higher-tonnage areas and the open stopes that will be coming online down the road. We've also added more development headings. So instead of limiting the development write-down to merely 1 or 2 per cycle, that figure now stands at 6 to 8. And we're aiming to push it beyond that, so they can achieve greater effectiveness within their cycle. So essentially it comes down to removing constraints on the crews, directing their focus, and getting everyone to truly zero in on achieving that turnover of headings each and every shift.

Jacob Klein

executive
#47

And, Daniel, I’d like to build on what Bob said. What has encouraged us the most is that the people at Red Lake appear to be welcoming change on-site, and that change is really cultural. The geological potential exists. The infrastructure exists — probably more infrastructure than needed. There is too much equipment, and not all of it may be the right equipment. But at the core, the people are there. They want to feel proud of that operation again, and in my view that is what will drive the biggest shift in how things get done. And that is already being embraced. It will take time. Mistakes will happen. But what we’re describing is somewhat similar to when we took over Cowal in 2016. Everyone on-site understood what had to change. What was missing was the framework and the capacity to carry out those changes. And I think that is largely what we are providing. So I don’t view it as very different from other assets we’ve acquired.

Dan Morgan

analyst
#48

On the guidance side — I realize you didn't use the quarterly update as a chance to cut the FY '20 guidance to below 725,000. If the year were to land at exactly 725,000, that does suggest a sizable jump in the last quarter. I'm just wondering whether you could say more about your confidence there and restate the main drivers behind it.

Jacob Klein

executive
#49

Yes, Daniel. It does depend on it, and we're confident that higher-grade material will be delivered from the underground mine that has been built at Mt Carlton. The first stopes will be the ones that deliver ore to the mill. And we're confident that we're ahead of schedule there. And as Bob said, the first gold bar has been produced from development ore there. And then Rawdon has basically been treating stockpiles predominantly since the wall failure in the September quarter, and it will be back in the higher-grade part of the pit and will deliver a quarter which is much higher than this quarter. So really, it's been the things which have impacted our production to date that we expect to now have addressed, and that's from the Mt Carlton underground and Rawdon getting back into higher-grade ore.

Dan Morgan

analyst
#50

And then my final question is just about the Cowal underground studies. Obviously, with these mobility restrictions, working from home and remotely, everyone's jobs are harder. I'm just wondering whether the timing of that might slip a little bit. Or, given these mobility restrictions, what can you say about that study?

Bryan O'Hara

executive
#51

Appreciate it, Dan. Lawrie is going to take that one.

Lawrie Conway

executive
#52

Yes, Dan. I mean, I think where we stand right now — with the exploration work that's underway and the decline, the underground — the team and the crews can get to site, they're performing that work, and they're getting the meters we need. So no issues are coming up there. And as for the remaining studies, the teams are either working out of Cowal or working remotely. So we're seeing all of that move forward according to plan. I think what we're watching is the question of when we file the submission with the regulator so that they're in a position to be ready to operate and to receive such a submission, and that's the sole item that might affect our timing. But everything remains on track for, as Glen said, our maiden reserve before the end of December, and that would mean a submission to the regulator by the end of the December quarter as well.

Operator

operator
#53

The following question is from Sophie Spartalis at Bank of America.

Sophie Spartalis

analyst
#54

To pick up on what Dan asked about production guidance: it looks like for the full year you're targeting the middle-to-upper portion of the production range, yet at the same time you're pointing toward the top end of the cost guidance. Could you perhaps walk us through the cost pressures that are showing up, please?

Bryan O'Hara

executive
#55

Thank you, Sophie. Here's another one directed at Lawrie.

Lawrie Conway

executive
#56

Yes. Thanks, Sophie. So where cost pressures are concerned, honestly nothing much has shifted for us over the course of the year. Labor has been the main driver, and we saw those changes during the first half. That came in at 3% to 3.5%, in line with the guidance we put out in August. What we're observing is that it's the production mix across each of the assets this year — as Jake and Bob both mentioned, Mt Carlton and Mt Rawdon came in below target but are definitely going to return to the revised figure that takes us to the low end of guidance. And clearly, on a per-ounce basis, that's really the reason our AISC has risen. And the second item, which goes back to October when we updated guidance, is that the higher gold price and lower copper price contributes roughly — that, together with the Mt Rawdon effect, has put $50 an ounce onto our guidance. Based on where we're trending this last quarter, we see Mt Carlton and Mt Rawdon getting back to the higher grade, so we pick up the ounces, which will pull our AISC down in Q4 and move us back toward $990 an ounce.

Sophie Spartalis

analyst
#57

All right, great. And perhaps a question for Jake. Regarding COVID-19, clearly all of us now understand the strains involved and how we have needed to adapt to them. Could you perhaps walk us through the positives emerging from this in terms of how your team is approaching things, and whether we should anticipate continued change in the cost base given new methods of operating, reduced travel, and so forth?

Jacob Klein

executive
#58

Okay, Sophie, maybe I'll kick things off with a somewhat cheeky remark — it's possible a few of our locations are actually doing better precisely because they're getting fewer visits from the group office. They just haven't found the nerve to say so to our faces yet. That said, I believe the response from the team has been outstanding. We truly are adjusting and taking things on board, and staff have exceeded what we'd ordinarily ask of them. The dedication to the protocols that our CMT group established has genuinely been remarkable. The CMT team gathers daily and discusses what's changing, how we might approach things, and how to get protocols in place. On communication, I'd say it has likely increased, in that we run a daily briefing on COVID-19 covering the entire organization. We're highly mindful of communication. Naturally, the — technology has enabled us to run these virtual town hall meetings. We're in constant contact with our sites. During our quarterly general manager leadership team catch-up, which ran over a couple of days last week, one of our site general managers told us he felt communication had in fact improved, and that we were more linked to one another and to our people.

Jacob Klein

executive
#59

So will that alter how we conduct business going forward? Well, right now I’m not purchasing airline shares, but -- and I’d rather hold gold shares. Still, I’m not certain about that. But it definitely, I believe, will get us reflecting on and kind of considering how much traveling we do, and whether technology exists that could assist us in doing so more efficiently.

Sophie Spartalis

analyst
#60

All right, that's great. Then one last question from my side. Regarding exploration at Ernest Henry, could you perhaps give us an update on that, please?

Bryan O'Hara

executive
#61

Appreciate that. That one’s probably best directed to Lawrie.

Lawrie Conway

executive
#62

Thanks, Sophie. Yes, the program is on track with the plan, and what we saw from the December and March program gave the JV parties enough confidence to approve putting the third platform in place. And really, what we want is to get that third platform in and see the drilling down there. We do have a fourth platform planned for later in the year, which will bring us to a total of 18,000 meters. But essentially, we just want to see the full results from that to determine what the impact would be on infrastructure and logistics underground and everything before making anything public around that work yet. But I think it's fair to say that, as you know, our joint venture partner, Glencore, spends nothing on exploration and development unless they absolutely have to or see value in it. And the pleasing thing is we got approval to go to the third platform.

Operator

operator
#63

The following question is from Levi Spry at JPMorgan.

Levi Spry

analyst
#64

I’ve got a couple of questions. The first is about Red Lake, which looked like a pretty solid quarter. So when you forecast lower production this quarter, is that really just about focusing on development and setting it up for the future? And can you remind me when the reserves and resource statement for Red Lake will come out?

Jacob Klein

executive
#65

Yes, Levi. Thank you. Look, I think you could reasonably say the asset is genuinely operating in harvest mode. My sense is that very little development was planned or carried out during the first quarter. And in truth, cash was harvested in that first quarter, and now we're changing course entirely to concentrate on exploration and development. So that's what comes through in the numbers, and that's the reason we generated — or rather the mine generated — that $18.8 million, which honestly came as a pleasant surprise to us, since we hadn't expected it to be that cash generative in the first quarter. But it also gives us some confidence that once we get this asset right, it will be a very cash-generative asset. As you can see from the exploration results Glen laid out this morning, and that's in our quarterly, the prospectivity there is great. It simply requires a shift in cost structure along with efficiency, productivity and culture to really generate those — to make it a great mine again. And that's the path we're on. And sorry, yes, the MROR. So as you know, we have a commitment with Newmont to essentially establish a base for the resource numbers. That's being worked through, and we expect it to be done sometime in the September quarter.

Jacob Klein

executive
#66

To build on that point, at Red Lake I believe we have 160 wireframe models, which gives you a sense of the complexity that mine has gotten itself into. Glen's interest and wish is certainly to consolidate those and simplify them, and that work is underway. So it's a substantial piece of work taking place right now.

Levi Spry

analyst
#67

Yeah, but that's tied to the market reserve for the September quarter — is that how I should read it?

Jacob Klein

executive
#68

Yeah, roughly around then.

Levi Spry

analyst
#69

Yeah, yeah, all right. And regarding Cowal specifically — the underground reserve in the December half, so that's going to — that'll incorporate a PFS so we can model it more accurately?

Jacob Klein

executive
#70

Correct, that's accurate. Indeed.

Levi Spry

analyst
#71

Yes. Could you remind me how the recovery work there is ramping up — what that looks like over the next little while?

Bryan O'Hara

executive
#72

Thanks, Levi. Bob is going to handle that question.

Robert Fulker

executive
#73

Thanks, Levi. Is this about the overall recovery? Because right now, what Cowal is dealing with is that they are processing low-grade stockpiles. And as you process progressively lower grades while the stockpiles are being drawn down — as Lawrie mentioned, we will be processing those for the next 12 months until we are back into ore and Stage H — you will see a net impact on overall recovery. The float tails leach is performing well. We are getting a good uplift from ore sorting. So all of those things are doing what they are meant to do. But the overall figures are being influenced by the lower grade going into the processing plant. Does that kind of answer the question?

Levi Spry

analyst
#74

Right. So they won't have that significant increase until we achieve improved grades in FY '22. So what kind of recoveries are we discussing over the longer term at this point, including the float tail leach?

Jacob Klein

executive
#75

Levi, we put that figure at roughly the mid-80s.

Operator

operator
#76

The operator has finished giving instructions, and the following question is from Ben Crowley of Macquarie.

Ben Crowley

analyst
#77

Could you give us a bit more detail on sustaining CapEx? I understand that at December you were heading toward the low end of the range, and now you've reduced it again slightly beneath the original range. Still, on a per-ounce basis it's a fairly big step down across the board, with the exception of Cowal, I believe. So if you could give me some sense of what has driven that, whether anything is being deferred, and really whether these are the kinds of numbers we should have in mind going forward.

Lawrie Conway

executive
#78

Yes. Thanks, Ben. So, in the December quarterly results, we stated that the second half would come in over $10 million lower. And really, it came down to the timing of the programs, because looking at the first quarter, we spent more than $27 million. So annualized, that puts you close to $120 million, and that wasn't the level we expected to spend. So therefore — and in the second quarter, we did $20 million. In the third, we've done $12.5 million. We would expect the last quarter to be $15 million, $20 million. And it really just comes down to when these programs are completing. We have seen that in the fourth quarter, and while we've lowered it again now, it's simply because some programs at some of the sites had planned to be doing really can't be done because of the restrictions, really only getting essential things on site. And some things have just been purely pushed out. What we'd see, and it's no different to what we said at the start of the year around the guidance, is that, effectively, for all of our sites, we would see that $90 million to $110 million is the run rate that the sites would be operating under.

Lawrie Conway

executive
#79

By the close of this year, we'll likely land somewhere in the range of $80 million plus up to $85 million. That said, that's roughly how we see things shaping up from here on.

Ben Crowley

analyst
#80

Yes. Fine. That’s not a problem.

Jacob Klein

executive
#81

Appreciate that, Ben. If you'd like, feel free to pose a second question.

Ben Crowley

analyst
#82

Okay, so in that case, maybe just a quick question for Glen. I was just wondering about Crush Creek. Obviously, you're beginning the drilling down there. But yes, perhaps if you could just give us a slightly better sense of what sort of target it is and what you're looking at regarding the potential target size. Maybe just a little more detail on the geology there.

Glenton Masterman

executive
#83

Yes, absolutely, Ben. Crush Creek is an epithermal-style geological target, and it differs somewhat from Mt Carlton — Mt Carlton being a high-sulfidation, high-sulfide type of ore body where we float a concentrate and also run a gravity circuit. Crush Creek, though, is closer to the mineralization style found at Cracow. So it's a low-sulfidation epithermal system. There's a drilled mineral inventory at Crush Creek, sitting somewhere between 100,000 and 200,000 ounces. It remains unclassified, which means it doesn't enter our resource classifications. The drilling program there, however, is aimed at some of the higher-grade shoots within these vein targets, essentially to confirm the grade continuity that has emerged from some earlier open-hole RC drilling — that's part of why we won't call it a resource. We're not fond of that drilling type. So we have the 2 — well, we have 1 core rig, with a second 1 on the way. And really, the plan, as I mentioned, is to confirm some of these higher-grade shoots, extend them wherever possible, and then grow the mineralized resource footprint so we can build additional mine life that lets us augment production at Mt Carlton.

Operator

operator
#84

Matthew Frydman from Goldman Sachs has the next question.

Matthew Frydman

analyst
#85

My questions concern Red Lake, and the mills in particular. I'm wondering how you're thinking about the milling infrastructure now that the acquisition has closed. And in the quarterly you touched on the plans, currently underway, to refurbish the Campbell mill. I'm wondering what the work program looks like there. Is the plan still to take that mill to 1 million tonnes per annum, or there or thereabouts? And I'm also wondering whether the Red Lake mill is on care and maintenance at present and whether the plan remains to keep it that way.

Bryan O'Hara

executive
#86

Appreciate that, Matt. Bob should take that one.

Robert Fulker

executive
#87

Thanks, Bryan. So just quickly, right now — as of today, the Red Lake mill is in fact running and turning out gold, since we've just started — we're in the middle of a 5-week shutdown at Campbell aimed at boosting reliability and swapping out certain parts that need replacing. At Campbell we're covering the full range of work, the autoclave included, the crusher circuit included, and the wet end too, meaning the tanks and the steel replacements. On top of that, we're addressing some spots that can enhance or debottleneck things around certain of the shoots and a few of the conveyors. So it's a broad slate of work we've got underway at Campbell. Our long-term approach is to put our focus on Campbell and try to bring it to maximum throughput, while Red Lake sits either under care and maintenance or mothballed. In the near term, though, we have to keep the Red Lake mill running so we can generate that additional gold until Campbell's mills reach where we need them. We're targeting getting Campbell's availability back to comfortably above the 90% mark, and we're aiming to really zero in on debottlenecking and shrinking those bottlenecked areas of the Campbell mill so throughput improves.

Robert Fulker

executive
#88

This is going to take quite a while. We've said consistently that it's a process spanning 3 years, yet our overall philosophy remains the same.

Matthew Frydman

analyst
#89

Absolutely. I wonder whether it’s still too soon to provide any specifics about the potential fixed-cost savings if you were to mothball that Red Lake mill or put it on care and maintenance — in terms of millions of dollars each quarter or each year, what you could save by taking that step.

Jacob Klein

executive
#90

Matt, I’ll handle that question. And I believe it’s too soon for us to offer you any guidance on it. At Red Lake, the difficulty is that there is no shortage of opportunity, and what is really difficult for us is narrowing our focus to those that will deliver the greatest improvement in productivity and efficiency at that site.

Matthew Frydman

analyst
#91

Sure. Perhaps another way to look at it: is your aim still to reach those processing costs at that asset? I think it was — you're targeting well below AUD 100 per tonne. My assumption is that some kind of change to how you run the Red Lake mill is essential to hitting that figure.

Jacob Klein

executive
#92

Yes. Definitely. And like Bob mentioned, we are examining every one of those adjustments. Even so, our approach remains the same. We are convinced that Red Lake is capable of generating more than 200,000 ounces of gold while keeping all-in sustaining costs below USD 1,000 per ounce.

Operator

operator
#93

The following question is from Reg Spencer at Canaccord Genuity.

Reg Spencer

analyst
#94

To pick up where some earlier questions about Red Lake left off: since you were already beginning to observe those gains in your development rates, should we anticipate a meaningful further improvement over what you guided to for the June quarter as we progress through FY '21? And, as part of that same question, when would we expect to begin seeing some of those cost benefits — or at least some of them — from the on-site improvements you're making show up in the all-in sustaining cost figures?

Jacob Klein

executive
#95

Yes. Thanks, Reg. As I think you've come to expect from us, we're going to be cautious when it comes to giving longer-term guidance. We've only just taken ownership of the asset. It's going to be baby steps. We have plans and a real transformation plan in place. But as for starting to articulate exactly when we believe those are going to be captured, baby steps, though they're all in the right direction.

Operator

operator
#96

Ian Warden from Global Mining Research has the next question.

Ian Warden

analyst
#97

Appreciate the Red Lake update, especially the COVID detail. I was just wondering, on the subject of bringing Red Lake into Evolution's wider culture and team, roughly what share — what percentage — of the existing Evolution team is now integrated at site? And did COVID alter that at all versus your original plan?

Jacob Klein

executive
#98

Right now, 3 individuals are either already on-site or making plans to be there, and we're running orientation sessions as we speak. So the question of what Evolution represents and what the Evolution culture is — all of the Red Lake employees are participating in that. It's happening virtually, and it's going really, really well. We've had the Red Lake team join the virtual town hall meetings. I believe they're getting — they're developing a very clear picture of what we expect from them and what they can expect from us, and it definitely is different. And they're embracing it. So it's been interesting, the way we've navigated around this lack of access, and it has meant far more virtual meetings and the like. But up to now, it's going really well.

Operator

operator
#99

Our following question is from Paul Kaner at RBC.

Paul Kaner

analyst
#100

One quick question from my side. Over the last 2 quarters, recoveries at Mt Carlton have run somewhat low. Could you perhaps comment on how you expect that to shift going forward, particularly once the underground material is incorporated?

Bryan O'Hara

executive
#101

Thanks, Paul. Bob is going to take that question.

Robert Fulker

executive
#102

Thanks, Paul. The recoveries have taken a hit solely due to the grade we've been feeding, and what we've been feeding has mostly been low-grade stocks. So once the underground starts up and the first stope is fired, we'll get some decent tonnages and the grade will rise, which means the recovery should climb along with it. We're also seeing some good gains from the capital works completed in the plant, so that ought to help it too.

Operator

operator
#103

There don't appear to be any more questions right now. At this point I'll return the call to Mr. Jake Klein for his closing remarks.

Jacob Klein

executive
#104

Thanks, Izzy, and I appreciate all of you taking the time to be on this call — we're genuinely grateful. As you're able to see, things at Evolution are looking very strong, and I want to emphasize that this stems not just from how good our asset portfolio is but, above all, from how good the people are whom we're extremely lucky to have within the business. At every level of the organization, they stay focused on values, put in hard work and, importantly, cooperate as an excellent team in order to produce these results. Please keep yourselves healthy and safe. Take care of yourselves, your families and your colleagues, and we can't wait to talk with you again soon. Thank you.

Operator

operator
#105

Appreciate everyone. That brings today’s conference to a close. Thanks for joining us. You’re welcome to disconnect your lines at this point.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Evolution Mining Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to Evolution Mining Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Evolution Mining Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.