executiveThanks for being with us today for this highly significant Evolution FY '20 results call and business update. Joining me this morning are Lawrie Conway, our Finance Director and CFO, along with Glen Masterman, VP of Discovery and Business Development. As you’ll have noticed in the ASX announcement we issued yesterday, forest fires have been burning in the area around the Red Lake community, and that area was evacuated on Tuesday evening. Our people’s safety comes first for us, and I’m pleased to report that every one of our employees and contractors is safe. Operations have been halted for the time being, though we don’t anticipate this situation will materially affect Red Lake’s September quarter production. At Evolution, we took a strategic decision to operate in the Tier 1, mining-friendly jurisdictions of Australia and Canada, and we’re fortunate that both of these countries are managing the COVID-19 pandemic well. So far, Evolution’s handling of the COVID-19 pandemic has also been very successful. To date, COVID 19 has not had any material impact on our production. Our safety performance keeps improving. Results in this area can never be good enough, yet the signs we’re seeing are encouraging.
Jacob Klein
executiveThe way we engage with, report on, and learn from each incident is likewise getting much better. It's a pleasure to note that in the latest MSCI ESG report, released 2 weeks ago, Evolution's rating was affirmed — and, a, raised from BBB during the last 12 months — and we ranked among the top 5 industry leaders for health and safety and business ethics. Community support and our social license to operate are among our most valuable assets. Beyond the numerous positive interactions and contributions our people make as Evolution employees and, in most cases, as members of communities close to our operations, we gauge our social license via a stakeholder perception survey that Deloitte completes every 2 years. I'm happy to say our most recent results showed our overall social license to operate score climbed from 4.06 out of 5 in 2018 to 4.21 in 2020, with every Evolution operation sitting in the high approval category. At Cowal, we remain on track to lodge the regulatory development application with the New South Wales government for the underground mine early in the December quarter. We anticipate as many as 300 jobs will be generated in the Central West of New South Wales near West Wyalong through the construction phase, and as many as 100 new long-term jobs will be generated over the life of the underground mine.
Jacob Klein
executiveMoving on to the FY '20 financial results. Reporting record statutory and underlying net profit after tax, along with record cash flow, is something we find very pleasing. Yes, a higher gold price has given us a tailwind, but as these results show, we have consistently delivered on our strategy of upgrading the quality of our asset portfolio and have built a sustainable, high-margin, long-term business. Group free cash flow over the last 12 months, after investing significant capital to enhance our future, came to $542 million. For comparison, 5 years ago, in FY '15, mine operating cash flow stood at $306 million versus $1.1 billion in the last 12 months. Net mine cash flow 5 years ago was $138 million. In FY '20, it reached $736 million. That is a fivefold increase, compared with the Australian dollar gold price rising 52% over the same period. We believe our shareholders should benefit directly from this journey. That is why I am particularly pleased that the Board has declared our 15th consecutive dividend of $0.09 per share, fully franked. This brings total dividends for the last 12 months to $0.16 per share, an increase of almost 70%. Cumulatively, once this final dividend is paid, we will have rewarded shareholders with $732 million in dividends.
Jacob Klein
executiveBut we recognize that markets look ahead. Those figures reflect the past, so I'd like to change direction now and discuss what lies ahead for us. To borrow the words and idea popularized by the famous investor Warren Buffett, "During these good times, we need to build out and widen our economic moat." At Evolution, our way of doing that is to keep sharpening the quality of our portfolio — lengthening mine life while holding margins intact. By concentrating our business on a limited set of high-quality assets, we've now expanded our mineral resource inventory to 30 million gold equivalent ounces. Across the next 3 years, the guidance we've issued today points to a rising production profile paired with declining costs. That cost guidance means we'll stay among the world's highest-margin, lowest-cost gold producers. All of the growth stems from near-term organic opportunities that already sit within our portfolio. Crucially, it's largely powered by our long-life assets at Cowal and Red Lake. And looking past that 3-year outlook window, we see still more upside and growth at these key cornerstone assets. This 3-year outlook takes in what I've called our initial investment case at Red Lake — a 3-year transformation plan aimed at delivering a sustainable 200,000 ounces per annum at an all-in sustaining cost below USD 1,000 an ounce.
Jacob Klein
executiveOur base case is going to produce suitable returns for shareholders, and that's what drove us to invest and buy the asset. In our June quarterly report, which we released 3 weeks ago, we said we're happy with how things are going, that we remain well on track, and that we're confident this initial investment case can be delivered. What the 3-year outlook doesn't capture, though, is what I consider the most transformative value-creating opportunity in Evolution's history. That's the 11 million ounce JORC-compliant resource we announced today at Red Lake. For reference, the last mineral resource made public for the operation put the resource inventory at 2.9 million ounces. This new resource estimate doesn't trigger any of the contingent payment consideration to new mines. Let me quickly add that those contingent payments are ones I'll be very happy to make, because it will mean we've been successful and found even more ounces at this exciting property. Red Lake is best described as looking at an opportunity through a different lens and coming out with completely different, and I'd add much better, results. Up to now, Red Lake's history has been seen and structured as a narrow vein, very high-grade underground mine, and the site geologists tell us that generally anything below 3 to 4 grams per tonne was treated as waste and often wasn't sampled in the drilling.
Jacob Klein
executiveUp until not long ago, the mine plan would only take into account material grading roughly 15 grams per tonne or better. For much of the mine's history, that approach served very well — especially between the early 2,000 and 2016, the years when the celebrated high-grade zone was being mined: an extraordinary 7 million ounce orebody with grades of 50 to 60 grams per tonne, a footprint measuring just 200 meters by 200 meters, and extending more than 1 kilometer down plunge. Throughout that period, there was little reason to reconsider the thinking, since this orebody drove Goldcorp to become one of the most highly valued gold companies anywhere in the world. Over the last 4 to 5 years, with the high-grade zone being depleted, operations at Red Lake have been difficult. The cost base was too high and was suited to the Bonanza-style grades. The mine consistently missed its forecasts, as its corporate strategy of trying to increase production, reduce costs and minimize investments collided with a site situation that required a reset of expectations, investment in underground development and exploration, and most importantly, a rethink of what the future could look like if the operating model was changed. Again, as a point of reference and a different perspective, it's worth noting that at a head grade of 7 to 8 grams per tonne, this mine, Red Lake, will be the highest-grade mine within Evolution's portfolio.
Jacob Klein
executiveAs the new owner, we've been able to carry out a significant reset. First off, we've addressed several matters that previously were seen as roadblocks. Our workforce has been cut by 20%. We're optimizing the plants, rationalizing the equipment, simplifying planning and the mining fronts, and most importantly, we now have a motivated workforce eager to take on the challenge of change. We're 5 months into what is a 3-year process, but we're making solid progress. With an 11 million ounce mineral resource and plenty of exploration upside still to be tested, we now have the chance — really the luxury — to fully rethink what this mine's future holds and to consider what is possible. That mineral inventory represents just the initial step in reimagining Red Lake's future. We anticipate a step-change in our reserve base, and work is already underway to optimize this into a new life-of-mine plan, with the intention that we will be positioned to declare a reserve update in our 2020 MROR statement. At our Investor Day on the 1st of September, we look forward to laying out some of the exciting upside opportunities we intend to investigate regarding how this materially larger resource base could deliver a completely different future for Red Lake.
Jacob Klein
executiveOur portfolio's resource base now stands at 30 million gold equivalent ounces. Every one of those resources is economically constrained at a gold price of AUD 2,000 per ounce. At the gold price we see today, that resource base equates to more than AUD 80 billion of in-ground revenue. What we need to do from here is keep growing our resources and bring the greatest possible share of this in-ground value to account, converting it safely, efficiently and responsibly into cash in our bank accounts, and then in the end, into yours as a shareholder of Evolution. With that, I'll pass things over to Lawrie.
Lawrie Conway
executiveThank you, Jake, and good morning to all of you. I'm glad to be here walking you through the FY '20 financial results, along with our FY '21 guidance and the 3-year outlook through FY '23. If you'll turn to Slide 7, that gives you the financial highlights for the year. What these results show is genuinely a very good year for the company — every metric came in better than the prior year, and several records were achieved. On the profit side, both our statutory and underlying figures set records, at $302 million and $405 million respectively. What separated the statutory number from the underlying number was an impairment on the Mt Carlton asset — a noncash write-down of $101 million, post tax. Even though it's noncash, that outcome is a disappointing one. The good news is that it's the only genuine blemish in the financials. I'll take you through what drove the improved profit performance on the following slide. Cash generation across the business still speaks to the quality of the portfolio we've built over the past few years. Operating cash profit and cash flow each rose roughly 40% to 45%, and group cash flow climbed 86% to $542 million.
Lawrie Conway
executiveIn line with the rise in underlying profit, our underlying earnings per share climbed 84% to approximately $0.24 per share. Given these outstanding financial results and the cash we generated, we have raised our final dividend by 50%, to $0.09 per share fully franked. Although our policy is grounded in cash flow, this dividend additionally equals 2/3 of our underlying profit. Turning to Slide 8 and what drove our profit. Underlying profit came in at $405 million, an 86% increase, powered by higher revenue, which rose 29% — matching the same increase in price as the gold price we achieved. Royalties rose 20%, reaching a total of $76 million. The standout element of the profit result was that we essentially held our operating costs flat, with an increase of just over 1%. Given that labor makes up roughly 45% of our cost base, and it grew 4% over the year, we incurred additional costs, including the full year of Total's leach at Cowal and the start of the Mt Carlton underground, yet savings elsewhere let us keep a low cost position. Red Lake contributed more than $15 million in the first quarter, while at Cowal and Mt Rawdon, planned drawdowns of stockpiles added a noncash charge of $49 million to costs.
Lawrie Conway
executiveMoving to Slide 9, you can really see how our low-cost position is converting into genuine cash generation. For the group, the cash operating margin — that's the EBITDA margin — rose 10% to 53%. As the charts on the right show, each of our assets is contributing individually to that result. Red Lake performed well in its first quarter, posting a 37% EBITDA margin. And in time, we expect it to reach the levels of our high-margin, long-life assets, Cowal and Ernest Henry. Those two delivered margins of 60% and 69%, respectively. Happily, Mungari and Mt Rawdon also turned in improved results. A crucial part of managing our capital allocation is that assets must fund their own investment needs. Apart from Mt Carlton, every asset generated positive and record cash flows during the year. It's also worth acknowledging the reliability the Mungari team is achieving, since the payoff for that effort came to more than $113 million in net cash flow for the year. On Slide 10, we show our group cash flow. This is essentially the net cash we generate to fund acquisitions, service debt and pay dividends. We generated over $542 million, which continues our sustained high cash generation. It means we are putting cash in the bank.
Lawrie Conway
executiveAnd the key point is that this is happening with a very strong margin. The chart in the upper right shows our cash flow calculated for each ounce produced. For every ounce we produced, $726 came through to the bank. That works out to a net margin of 32%, an 88% improvement on last year — a meaningful result given that our achieved gold price rose only 29%. Discipline on debt has been maintained, and the balance sheet remains solid. When the Red Lake acquisition closed, our gearing stood at 14%, and we have since cut that in half, to a very manageable 7%. What is encouraging for both the business and shareholders is that all of this was achieved at a gold price AUD 400 under the current spot price. Turning to Slide 11. With the balance sheet strength and record cash generation, we have declared a final dividend of $0.09 per share. That dividend is fully franked and will be paid on the 25th of September. It reflects our policy of targeting a payout ratio of 50% of group cash flow. That takes the full year dividend to $0.16 per share fully franked, an increase of 68% on last year.
Lawrie Conway
executiveThat works out to $365 for each ounce we produce, and that's a really strong return for shareholders, as is the yield at slightly below 3%. I'll turn now to guidance for FY '21 along with the outlook covering the next 3 years. Slide 12 shows our production and cost guidance for FY '21. Our guidance is for output of 670,000 to 730,000 ounces, with an all-in sustaining cost between $1,240 and $1,300 per ounce. Among the main drivers on production is Cowal, which will come in lower because we'll be processing low-grade stockpiles until the end of the year, when Stage H ore becomes available. Red Lake, we'll see, rises on an annualized basis from the June '20 quarter to 125,000 to 135,000 ounces. At the remaining sites, there'll be a mix of declines and increases, but taken together, no material net change is expected. Turning to costs, Red Lake will at first add $200 to $215 an per ounce to our AISC, then trend downward as the cost benefits and higher production from the transformation program are realized. We don't anticipate any material rise in operating costs through the year. That's because we see recently negotiated savings on input costs, which negate any increase in labor or other costs.
Lawrie Conway
executiveWeaker copper output is going to push our AISC up by $30 to $35 for each ounce. One thing worth pointing out is that both our guidance and our outlook assume a gold price of AUD 2,200 per ounce along with AUD 8,400 per tonne for copper. That flows into our AISC via royalties and byproduct credits. If you go to Slide 13, on capital guidance: we're guiding sustaining capital at roughly $113 million to $138 million, while major capital comes in at $260 million to $290 million. The sole item worth flagging within sustaining capital sits at Red Lake, where the ramp-up stems from the transformation program, under which we'll put $55 million to $60 million in this year. The slide lays out the key components of that investment. As for major capital, spending lands mainly at Cowal, Red Lake and Mungari. Those investments cover either continuing projects already approved, like Stage H and the IWL at Cowal, or pushing growth projects forward, like the underground feasibility study at Cowal, mine development at Red Lake to rebuild ore stocks for higher output, and mine development of satellite pits at Mungari. Now let's turn to our FY '23 outlook on Slide 14.
Lawrie Conway
executiveWe expect output to rise above 800,000 ounces by FY '23, and over that stretch the AISC will fall to a range of $1,125 to $1,185 (sic) $1,122 to $1,185 per ounce. The increase in production will come from starting the Cowal underground, which is planned for the end of FY '22, and from finishing the transformation plan at Red Lake successfully. In addition, we now believe Mungari can deliver 110,000 to 120,000 ounces across a prolonged period by using satellite pits, regional resources and better plant throughput rates. As I said earlier, the key reason the AISC will be higher in the coming couple of years is the processing of lower-grade material at Cowal until Stage H or higher-grade underground ore is available, along with the delivery of lower-cost and higher-cost -- higher production at Red Lake in FY '23. Once more, we don't anticipate meaningful cost inflation anywhere in the portfolio over the next few years. Finally, the capital outlook, which is on Slide 15. Sustaining capital should land between $95 million and $138 million, and outside of those mentioned for Red Lake in FY '21 there are no significant projects. Major capital spending centers on our substantial growth projects at Cowal and Red Lake, which will meaningfully lift production over the long term and further enhance the portfolio's quality.
Lawrie Conway
executiveAt Cowal, our investment is aimed at pushing output past 300,000 ounces yearly by building a new underground mine, with $100 million to $130 million going in each year across FY '22 and FY '23. Over at Red Lake, we keep putting money into mine development — $70 million to $85 million is slated for the coming 3 years — so that production can rise beyond 200,000 ounces. Before I pass things to Glen, I want to say thanks to the entire Evolution team, who spent a great deal of time and effort over roughly the past month compiling the full year financial results, the FY '21 guidance and the 3-year outlook. Their substantial contribution is truly appreciated. So, thanks for your time, and I'll now hand over to Glen.
Glenton Masterman
executiveThanks, Lawrie, and good morning everyone. I'm really pleased to walk you through the results of the mineral resource update at Red Lake, and those results have come in at 11 million ounces of gold at a grade of 7.1 grams per tonne, with the details laid out on Slide 16. With this modernization of the resource, Evolution has a tremendous opportunity to take a step back and optimize a life of mine plan that fully unlocks the potential of this world-class geological address. The hard work and long hours put in by the team on-site, together with our expert consultants, have produced a result consistent with what we believed was possible over time. But this outcome has come in well ahead of any schedule we'd imagined. Moving to Slide 17, which breaks down the individual numbers across the various orebody groupings at Red Lake. The most significant result comes from the upper Campbell area of the operation, where we are reporting a new resource of 4.3 million ounces, grading 10.5 grams per tonne gold. This resource begins at surface and extends to a depth of 1,200 meters below. I'll come back to upper Campbell later in the presentation. Our revision of the mineral resources began back in February, when we decided we would completely modernize the resource model.
Glenton Masterman
executiveSo we returned to first principles, constructing geological models right from the beginning. That involved reworking the framing of mineralized domains, estimating grades into the block model, and carrying out thorough validation of the model, after which came resource classification. Data from 47,000 drill holes was used, amounting to more than 7 million meters of drilling, and 85% of that has been drilled within the last 20 years. The drilling database ranks among the largest we have ever handled and contains slightly under 6 million samples. In light of how big the project we are undertaking is, we brought in Roscoe Postle Associates, a mining consulting firm based in Toronto, to start a complete rebuild of the mineral resource. More than 10,000 hours have gone into this project across a 5-month span starting in February. This modernization work led to the consolidation of 142 individual block models that previous owners had developed down to a more manageable 19 models. Evolution geologists, working together with RPA, completed classification of each model. The resources reported this morning were constrained by an underground mining shape optimizer that assumed a gold price of AUD 2,000. It used a conventional mechanized mining technique along with parameters typical of current underground mining operations, which aligns with Evolution's approach across all its assets of constraining resources at $2,000 an ounce and estimating reserves at AUD 1,450 per ounce.
Glenton Masterman
executiveFor grade estimation, we’ve taken a cautious stance by factoring in dilution from geological contacts between our wireframe and block model volumes. Our approach to classification has likewise been conservative, especially in the Upper Campbell and Red Lake portions of the mine. Around every old opening in those areas, we established a buffer 2 meters wide, and we’ve left that material out of the models; it is reflected in the figures reported this morning. That 2-meter buffer was not used in the mine’s lower sections, where modern survey control exists. In the mine’s upper Campbell area, indicated resource accounts for more than 61% of total volume, with average drill spacing there at 6 meters. Inferred resource makes up 30%, supported by an average drill spacing of 17 meters. That leaves 9% of the resource still unclassified because drilling is insufficient to meet our minimum standards for geologic confidence. So how and why have we managed to spot this opportunity at a mine with a 7-year history? To grasp that, I think you need to look back at the past, which appears on the time line in Slide 18. The history of the Red Lake camp strikes us as incredibly fascinating.
Glenton Masterman
executiveFor us, the two most significant lessons were these: two mines run by different owners were extracting from the same set of orebodies. The Campbell operation—which in the 1980s would come to be owned and operated by Placer Dome—had historically produced more than the Red Lake mine sitting right next to it. By adjacent, I mean it's one mineral system, with the same orebodies running continuously from one mine to the other, though a tenement boundary separates them—one we fondly call the party wall. That party wall initially created a boundary line for the Campbell operators and later, under Goldcorp's consolidated ownership, carried on dividing those same orebodies. We've managed to broaden our field of view and pinpoint a substantial high-grade resource that reaches the surface and goes down to 1,200 meters in depth. The benefit of a lengthy record of high-grade output from Campbell and afterward the high-grade zone has been both a blessing and a curse for the Red Lake operation. Mining extremely high-grade mineralization locked in a cost profile that could only be sustained by mining those very high grades. On top of that, any drilling that found mineralization below double-digit grades got classified as subeconomic.
Glenton Masterman
executiveWhat we've come across here is an unforeseen chance that comes with updating the resource base. And it's worth acknowledging, too, that the gold price we're using today sits above what the models assumed back in the early 2000s. On the upcoming slides, you'll see what we've found in the upper Campbell area of the mine. Slide 19 presents the Red Lake operation, with the mineralization beneath it and the mine workings projected up to surface. Cochina lies to the west, on the left by the airport. Campbell and Red Lake sit on the right, and the old party wall that divided the historic ownership of the mines is marked as well. Moving to Slide 20, we'll examine a window into the upper Campbell side of that party wall, sliced at the 9,510 level — that's 150 meters below surface. This view is taken from a 100-meter vertical section through the upper Campbell mine and shows how grade control was carried out previously, with every colored point standing for an individual underground face sample. The stopes and development drives appear as the blue-gray S-build shapes. Looking at the legend in the top left, you can clearly see that extremely high grades were mined from narrow structures that are now shown as mining voids in the gray panel shapes.
Glenton Masterman
executiveHistorically, this kind of ore control sampling stood in for costlier grade control drilling. Eventually, drilling caught up with mining, and you can see that by going to Slide 21. There, the results have clearly outlined new mineralized areas situated outside and beyond the mined-out high-grade shared zones. What's interesting is that the mineralized volume in the center — so, to the left of the party wall on the old Placer side — has been outlined through very tightly spaced drilling, which gives us strong confidence in the geological continuity of the mineralization. That said, the grades in the drilling results come in lower than what was historically mined. Based on our on-site inquiry, this looks like an area that was largely overlooked owing to the luxury of the high grades being produced from the high-grade zone. Slide 22 presents a slice of our new block model, with estimated block grades filtered above 3 grams per tonne gold. The block model grades are informed by historic drilling outside of and excluding previous production. Slide 23 displays outlines generated by the mining shape optimizer, from which we can strand and report resources for inferred or better grade blocks sitting above a cutoff grade of 3.4 grams per tonne.
Glenton Masterman
executiveThe same methodology has been applied to the lower Campbell, upper and lower Red Lake, and Cochenour bodies, and it produced resource uplifts similar to those we saw at upper Campbell. In my view, the opportunity we have at Red Lake is a strong illustration of the whole being greater than the sum of the parts. We were able to apply a different lens and approach to the mineral resource solution. For the first time, the mineral resources have been evaluated within a rationalized geological framework and by using a wider range of cut-off grades than previous owners had considered. With that, operator, I will open the line for questions.
Operator
operator<<operator_script>> The initial question comes from Mr. Matthew Frydman of Golman Sachs.
Matthew Frydman
analystAppreciate the update and the outlook you shared today. If I may, I’ll begin with a couple of questions about Red Lake, given how enthusiastically Glen was discussing it. It’s great to see the resource base grow. As you pointed out, that growth has clearly come from rethinking the economic cut-off grade. First, could you give us some indication of how we should think about this converting into a reserve grade? Should we still expect a reserve grade that, after accounting for mining widths and dilution, sits a couple of grams per tonne below the current resource grade?
Glenton Masterman
executiveYes, Matthew. Look, I think it's reasonable to say that for the reserve, the optimization program is at an early stage. But look, I think some conservatism around the dilution has already been built into the resource model. So, as I mentioned earlier, we have included the dilution that exists between the wire framing and the block model. And we've also included dilution around the historic workings, especially in the upper areas of the mine. And so this — just as an example, the dilution between wire frames and the block model volumes really accounts for 5 million additional tonnes into the model that have been sort of accounted for at 0 grade. So we feel that the grades being reported by the resource model are already fairly conservative. The reserve grade is obviously going to be estimated at a higher cutoff grade, which will drive the average grade of the reserves higher. And by the time we bake in the mining dilution and recoveries, we would hope to be able to deliver a reserve at around about the same average grade as the resource reported this morning.
Matthew Frydman
analystThanks — that’s a really useful level of detail. So, building on that point, as you laid out, you have some quite favorable resource grades up in upper Campbell. I’m therefore wondering whether, conceptually, there’s a chance for mine sequencing to hold things nearer to, I suppose, the current head grade. You mention that upper Campbell begins at surface. Does that create open optionality? And could that assist you in balancing the requirement for multiple working faces in the mine so the operation stays productive, while still keeping head grades at some elevated or higher level?
Glenton Masterman
executiveMatthew, once more, I believe you've got it right. What I think this update accomplishes is providing us with several levers to examine and activate down the road. The spectrum of possibilities is quite broad, I mean. Clearly, with a deposit situated fairly near to surface, and the window shown in this morning's slide pack extending just 150 meters in depth, we'd consider things like a surface portal paired with a decline developed to reach that shallow mineralization. And I suppose too, since it starts at surface, open pits enter the picture as we look ahead.
Jacob Klein
executiveMatthew, let me just build on Glen's remarks: Bob Fulker, our COO, was grinning from ear to ear when he saw that diagram. And that near-surface Plus 10 grams has him considering a broad set of possibilities, which he'll lay out at the Investor Day.
Matthew Frydman
analystAbsolutely, Jake, and thank you. Perhaps I could get ahead of a few of those questions once more and simply pick up where we left off at Red Lake. With the operation rethought around a lower-grade operating model, how are you fellows viewing mill capacity? Which alternatives are you weighing in the revised mine plan, I suppose, in order to fully hit that target of more than 200,000 per annum? And past that, what about the possibilities you have outlined within this resource?
Jacob Klein
executiveYou're kind of getting ahead of Investor Day there, since those are among the things we're considering. I mean, the size of this resource and the opportunity really astonished us. When we put the investments into Red Lake, our expectation — the investment case we had in mind — was 200,000 ounces at under USD 1,000 an ounce. What's now in front of us has the potential to be entirely different. So we've only received this resource estimate within the past few weeks, really. We're working through the options. But yes, the range of options is broad.
Matthew Frydman
analystYes, absolutely. All right. Perhaps to wrap up with something broader, and this may be directed at Lawrie. I was wondering whether you might give us somewhat more granularity regarding the growth CapEx within the outlook, especially for FY '22 and '23. You gave a pretty helpful breakdown covering most of the projects. Still, based on my rough calculations scribbled on the back of an envelope, roughly $100 million of CapEx in that breakdown appears to remain unaccounted for. So I am curious whether anything specific stands out across those later years.
Lawrie Conway
executiveYes. Thanks. Thanks, Matt. Look, I think there's — from what we remember in FY '22, the bulk of that capital will go toward completing the integrated waste landform underground at Cowal, and those 2 projects combined at the upper end will account for roughly $210 million of that major capital, which runs $250 million to $280 million. Then you've got $35 million of mine development at Red Lake, plus some satellite pits at Mungari. So if you take the midpoint of those, it nearly covers the whole major capital figure for FY '22, since not much else is happening, certainly at Ernest Henry, Mt Rawdon and Mt Carlton. So we don't expect much more that year. In year 3, we certainly will see — in FY '23, we've got the satellite pit at Mungari of 10 to 15. We've also got some capital earmarked, probably around $30 million or $40 million, for regional resources at Mungari, but nothing — no specific projects locked in on those. It's work that we'll be — we'll be doing studies through '21 and '22. So that will be one of your gap closes in FY '23. But when you look at the balance of the 10 to 15 at the satellite pits at Mungari, up to $20 million at Red Lake continued mine development, and then finishing the underground at Cowal at $100 million to $125 million.
Lawrie Conway
executiveSo really, the sole difference on the major capital side would be a bit of work at Mungari. Again, since Ernest Henry, Mt Carlton, and Mt Rawdon don't have much in the way of major capital underway, as we see it.
Matthew Frydman
analystThanks, Lawrie, that's useful. My assumption is that this $30 million to $40 million is set aside for possible additional work at Boomer, should Glen's team do well there?
Lawrie Conway
executiveGlen, that's a good question, and one you get asked a lot.
Glenton Masterman
executiveThere are some results we need to share with you at the close of this quarter so you stay updated on how that work is coming along.
Operator
operatorNick Herbert of Crédit Suisse has our next question over the phone.
Nick Herbert
analystAlso, regarding Red Lake for me, if I could just build on what Matt said. With respect to that upper Campbell zone, can you clarify or give some indication of the timing for when you think you might get into that area? And what a potential sustainable mining rate would be?
Jacob Klein
executiveNick, I believe it's premature to address that. It hinges on the particular weekday when you happen to talk with Bob. He brought up recently that a permanent zone exists where a decline could be driven downward. Still, we're in the early stages. We truly are only beginning to put the plan together. In this context, I think we have 2 areas — or 2 avenues — that must be delivered on. First, we absolutely have to deliver the base investment case. That requires pushing operational efficiencies and improvements forward, and that work is well underway. This new effort — envisioning what Red Lake's future could be, how large and how different it can and should become — is something that we believe will make the operation sustainable at a far different economic outcome across multiple years. We're discussing 11 million ounces, plus exploration upside, and this ought to be a multi-decade opportunity.
Nick Herbert
analystSure, that's reasonable. I realize it's still early, Jake, and we can revisit this at the Investor Day. But regarding that resource upgrade, and I suppose the considerable upside you've mentioned compared with what your investment case was, you haven't actually revised any of those targets yet — could you perhaps share, I guess, or give us your current thinking on what a realistic target might be beyond that 200,000 ounce figure you've held to?
Jacob Klein
executiveAt this point, I think that assumption has to be made, since we don't yet have clarity. It really hinges on which options you choose, but that 4.3 million ounces at plus 10 grams at upper Campbell is clearly a near-term target. Bob told you yesterday about the drilling at the aviation zone, which is a new and clear zone that we could be mining into and could be productive. I think the scale of opportunity and the opportunities available to us require us to really think carefully about the long-term future of this. I will say, it will be much bigger than 200,000 ounces per annum. I'm not prepared to say how much bigger.
Nick Herbert
analystAll right, and then just one more regarding the CapEx program next door — sorry, this year at Red Lake, where does that leave you on all the above-ground works? Is that more or less finished there when it comes to the mill upgrade, equipment — new equipment — and the staff programs, so to speak?
Jacob Klein
executiveYes. Nick, a decent chunk of it will be completed during this year. Some work, though, carries over into FY '22. What I mean is that sustaining capital is going to decrease. When we ultimately reach the 200,000 ounce rate in FY '23, what you'd likely see is a level back around $30 million to $35 million. But after that, as Glen's presentation has shown, hopefully there are additional items we'll need to put money into in order to exceed 200,000. Still, a good share gets done this year, somewhat less the following year, and then it likely settles at a sustainable level of $30 million to $35 million.
Nick Herbert
analystOkay. Great. And finally, Jake, I know you've talked about this somewhat before, specifically regarding reserve gold pricing, and you brought it up again today—extending mine life without hurting margins. I'm just wondering: within the portfolio, are there particular assets that might produce a stronger economic result or NPV if you raised the reserve gold price assumption?
Jacob Klein
executiveYes. Our approach is to consider a long-term assumption for the gold price. Acquisitions therefore get a conservative look, since we're allocating shareholders' money and acting as its custodians, and appropriate returns are required. So there's no plan on our part to alter the reserve price assumption. That assumption is conservative. It ranks among the lowest across the industry, yet we believe it is correct, given that the emphasis falls on margin rather than volume.
Operator
operatorThe next question we'll take over the phone comes from Daniel Morgan at UBS.
Dan Morgan
analystBack to Red Lake, clearly a major topic today. At the time of the initial acquisition, you stated the ore reserve you anticipated declaring would be 30% to 40% below what the previous owners had declared under JORC methodology. What you seem to be indicating today regarding the resource side looks considerably larger than what you envisioned when you first bought the asset. So does that mean those earlier remarks about the reserve are no longer valid?
Jacob Klein
executiveDan, when we put out that announcement, the most recent reserve figure that had been published was Goldcorp's from June 2018 — 2.1 million ounces — and that's the depletion figure we're talking about. We did mention a range of 30% to 40%. So our guidance pointed to 1.3 million to 1.4 million ounces of reserves as of the takeover date. With this new resource, we think the reserve estimate will come in at multiples of that.
Dan Morgan
analystYes, I can hear you perfectly. And could you go over it once more for us — you took care to note that the work carried out under that arrangement has not set off the contingent payments. Would you remind us what would need to happen, what work still has to be completed, for those payments to be triggered?
Jacob Klein
executiveRight, so those contingent payments were structured around finding ounces beyond the resource envelopes that already exist. Glen and his team are collaborating closely with Newmont to establish those boundaries. So in effect, it ties back to the ounces we're adding.
Dan Morgan
analystOkay, and finally, a question about Mungari. Part of the capital that was laid out includes some work on tails expansion. I'm just wondering whether that signals renewed life expectancy at the asset, and if you could comment broadly on what you're seeing at Mungari.
Jacob Klein
executiveYes, Daniel. This concerns cells 3 and 4. It's the next stage of tailings capacity that the site needs, and the rationale is that mine life has been extended and throughput is now holding at 2 million rather than 1.6 million or 1.7 million. So within this financial year we're building 3 and 4 so that capacity is in place for the longer life.
Operator
operatorLevi Spry of JPMorgan is on the line with our next question.
Levi Spry
analystLet's stay on Red Lake. And actually, Slide 17 might be useful for me here. Could you walk me through what the investment case looked like? So that 200,000 ounces plus at $1,000 an ounce — where did that come from? What were the tonnes and grade, so we can do our own work on the optionality going forward?
Glenton Masterman
executiveGlen here, Levi. The investment thesis was essentially constructed on top of the earlier models. What you see on Slide 17 is our updated version of that model. Each of the colors shown represents one of the 19 separate models, which came out of the 142 we acquired at the point we assumed control. And really, the guidance — what we guided toward when we made the acquisition, as Jake said a moment ago — rested on the 2.1 million ounces of reserve, with a 30% to 40% reduction for depletion and the other modifying factors we'd apply. On top of that, there were 5 million ounces of future resource. Our acquisition case, I suppose, was constructed around converting portions of those 5 million ounces. As Jake noted too, that covers in particular the deeper sections of the mine — lower Red Lake especially. Jake brought up Aviation. That's one of the areas we concentrated on quite heavily in the early days, since it handed us what was effectively a big resource and reserve, and then let us produce over extended periods.
Glenton Masterman
executiveThat was the picture we had before, based on that resource. However, under the contingent value rate, this resource update became necessary. And once we truly, I suppose, opened things up — or removed the constraints across the whole camp — we quickly began to see that the opportunity in front of us looked quite different.
Jacob Klein
executiveYes. So, to build on that point: the base case really centers on 1.3 million ounces, with a portion of resources converted into reserves. But we're certainly not viewing it as an 11 million-ounce orebody, and there's further upside beyond that. And as I mentioned before, I would be more than glad to write that check in $20 million increments to Newmont as we find additional ounces.
Levi Spry
analystYes. Absolutely. But let me probe a bit further on that. So at present, which source is supplying the ore? And back in '23, when you were running at, say, 900,000 tonnes at whatever grade, where was that volume slated to originate from?
Glenton Masterman
executiveRight now, Levi, we’re producing in the Cochenour zone of the mine and also down in lower Red Lake.
Jacob Klein
executiveThe bulk of that comes from the deeper sections of the mine rather than the upper Campbell area.
Levi Spry
analystRight, that's helpful. Yeah — good. On Cowal specifically, could you run through the feasibility study schedule again for me, and also how that lines up with the capital guidance you've given for the underground portion?
Jacob Klein
executiveYes, of course. The filing seeking regulatory approval is set to be submitted at the start of the December quarter. And within the assumptions behind our outlook, we have factored in approval in June for the underground development — June 2021.
Operator
operatorThe next question we have over the phone comes from Ranjeetha Pakiam of Bloomberg News.
Ranjeetha Pakiam
unknownJake, I just wanted to ask something fairly broad about gold prices worldwide, since they've reached an all-time high. With all that cyclical movement, do you figure there's a higher floor for gold now?
Jacob Klein
executiveYes, I do. There are, I believe, plenty of grounds for seeing positive elements that support the view that the gold price has established, or is going to establish, a fresh floor and will climb further from this point. You have geopolitical tensions, plus the fiscal programs that governments are rolling out. And naturally, gold is that one currency which cannot be printed. Having said that, I trust we've made clear the strong impression that here at Evolution we remain focused on making sure we build a business possessing a robust economic moat, one capable of weathering any cyclicality in the gold price. Still, we currently sit in a very favorable section of the gold price curve. Lawrie mentioned earlier that the gold price right now stands $400 above what we realized over the last 12 months.
Operator
operatorReg Spencer of Canaccord has our next question by phone.
Reg Spencer
analystMy question is about CapEx at Cowal. I was hoping you could give more detail on the underground establishment CapEx and how that ties to what you expect the scale of the underground mine to be. I know on the quarterly call you gave a range of somewhere between 1.5 million and 2 million tonnes. With that CapEx figure, can we assume the scale of that underground will be toward the upper end of that range?
Glenton Masterman
executiveYes, Reg. What I mean is that the capital we've deployed remains within that range, and it's more likely to land toward the middle to upper part of it.
Reg Spencer
analystAll right, thanks. And on that upfront capital figure once more — my assumption is that a decent share of it would cover upfront development, not merely the initial establishment capital, correct?
Glenton Masterman
executiveYeah, it does. The capital there is really about sequencing. So this year, we have the feasibility study — the Board approved it this week — at $25 million to $30 million. We also have a second exploration decline included in the guidance figures, with roughly $25 million for Glen's discovery spend. Then moving into FY '22, which you can see in the outlook, the capital spending across '22 and '23 forms part of that development — nonprocessing infrastructure and all the rest that we need in order to bring production on stream during '22 and '23, plus some capital in '24.
Operator
operator<<operator_script>> The following phone question comes from Kate McCutcheon at Citi.
Kate McCutcheon
analystRegarding that 3-year outlook — for FY '23, you're anticipating a significant increase in production. Should I take that to mean you'll be hitting that 200,000 ounce per annum level at Red Lake during FY '23? I know in the past you've sort of mentioned that 3 years would be needed to turn things around there. But is that the way you see it now?
Jacob Klein
executiveYes, Kate. So the way we see it in this outlook covering 3 years, the premise is Red Lake getting to 200,000 ounces through FY '23. Essentially, by FY '23, once we've finished a great deal of that transformation and we're at that process — our production rate.
Kate McCutcheon
analystAll right, understood. Turning to Mt Carlton, what's your current view of that asset within the portfolio? And could you remind me where you now see the mine life there, and how that shapes up across FY '22 and FY '23?
Jacob Klein
executiveYes. So the mine life has been cut back — cut back substantially. During the quarterly call, we mentioned our plan to drill at Crush Creek, and that's a pretty interesting and exciting opportunity for us. After that, we'll evaluate Mt Carlton, though production there will be lower next year. And if Glen doesn't achieve success at Crush Creek and with other opportunities in that area, then it falls further in year 2 and year 3. There are certain opportunities we keep examining. But as things stand, this really is a case that requires some exploration success, and we are drilling at Crush Creek quite aggressively.
Kate McCutcheon
analystAll right, thanks. Now, regarding Mungari in the year ahead, could you explain what's pushing those costs up somewhat there, please?
Glenton Masterman
executiveAt Mungari, the biggest shift is that operations are heading toward satellite pits, where grades run lower. To compensate, you're pushing throughput higher, and we aim to hold that at 2 million tonnes per annum. Yet when you compare FY '20 with '21, roughly half of that year was spent at 1.2 million, so the full benefit of 2 million tonnes per annum really only applies for about six months. That is precisely what will shape our AISC. Beyond that, our hope is that by the close of FY '21 we can return to Burma — development and work are underway during this year — which should then help counter a portion of that lower-grade material from the satellite pits.
Operator
operatorThe next caller on the line is Ben Crowley with Macquarie.
Ben Crowley
analystI'm just curious, circling back to the idea of a possible open pit at Red Lake. Let's assume that really centers on the upper Campbell zone and the party wall, but as far as I can tell, quite a lot of surface infrastructure sits there. So I suppose my question is: do you believe that potential open-pit opportunity might be large enough to warrant essentially a full recut of the operation?
Glenton Masterman
executiveBen, Glen here — I’ll take that one. So, look, I think — as I said earlier, there are several levers we’ve only just begun looking into at this point, and the pit concept is merely one of those. I think, as you noted, infrastructure exists near that upper Campbell mineralization and on the other side over in Red Lake. We’d like to believe at this stage that there’s no party wall — it’s simply a single orebody. And that is really what’s beginning to provide the uplift in resource. But I think, as I mentioned, we’re at a very early stage in terms of how we approach optimizing this resource and what the optimal solution will be when it comes to creating value and what will serve the business best.
Jacob Klein
executiveI'll just add this: when you refer to an open pit, right now we have roughly 1.1 million tonnes of milling capacity across the Campbell mill and the Red Lake mill. If an open pit is what you mean, then you'd be looking at a new mill with throughput rates that differ considerably. So again, everything remains conceptual at this point in time, though it does give you a sense of some of the opportunities we're considering.
Operator
operator<<operator_script>> We've now exhausted all remaining inquiries from the queue. At this point I'd like to return the call to the speakers so they can offer their closing remarks. Please go ahead.
Jacob Klein
executiveThanks, operator. And thank you, everyone, for being on the call. I genuinely think that when we look back, today's announcement about the Red Lake resource will prove to have been a turning point for our future. We're looking forward to Investor Day next month, when we'll be able to lay out some of these highly exciting opportunities that lie ahead of us. I also want to echo what Lawrie said — these results and outcomes really hinge on, and stem from, some of the remarkable people we have within this organization. My thanks go out to them for the effort and hard work that has gone into delivering the financial results, the resource updates and the financial accounts across the whole business. Please stay safe and well. Operator, would you please end the call.
Operator
operatorThanks so much, everyone. That brings today's call to a close. We appreciate each of you for joining in. You're all free to disconnect now. Take care.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Evolution Mining Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Evolution Mining Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Evolution Mining Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.