We appreciate everyone holding on, and we’re glad to have you join the Evolution Mining conference call on the March 2021 quarter results. Everyone attending is currently muted and can only listen. After a presentation, we’ll hold a question and answer session. Should you want to pose a question, press the star key and then the number one on your phone’s keypad. At this point I’d like to pass the call to Mr. Brian O’Hara, General Manager, Investor Relations. Please proceed.

Brian O'Hara

executive
#2

Thanks, Kelly. Good morning, everyone, and welcome to the March 2021 quarterly conference call for Evolution Mining. Joining us this morning are Jake Klein, our Executive Chairman, Lawrie Conway, CFO and Finance Director, Bob Fulker, COO, and Glen Masterman, VP Discovery and Business Development. The year has gotten off to an amazing start, with central banks pulling out all the stops to boost growth after the damage done to their economies in 2020. Rates are sitting at or close to zero, and we've seen unprecedented levels of both monetary and fiscal stimulus. Inflation is still low, and plenty of economies worldwide are now roaring, with prices across many asset classes—crypto, tech stocks, commodities, and real estate among them—skyrocketing. Given all that excitement, it's no surprise that gold has fallen to the background as real yields have climbed and demand for safe haven assets has faded. Still, at today's spot price above AUD 2,300 an ounce, producers continue to benefit from remarkably strong gold prices. With inflation expectations climbing and global currencies continuing to be devalued, gold will keep serving a key role as an asset class, just as it has for thousands of years. Thank you—over to you, Jake.

Jake Klein

executive
#3

Thanks, Brian. Good morning, everyone, and I appreciate you making time to be with us on today's call. We're grateful for that. I'll begin with what is perhaps the most significant item in today's quarterly release. Although I suspected this moment would come, Brian has chosen to move into a career in funds management after 8 years heading up investor relations at Evolution. Sadly, I've exhausted every way of persuading him to remain. Throughout his tenure at Evolution, Brian has clearly played a key part in strengthening the market's view of us as a provider of transparent, high-quality information to all stakeholders. On a personal note, I want to thank him for his work, his commitment, and what he has contributed, and to wish him the very best in his future endeavors. All of us at Evolution will certainly miss him. I'm happy to report that Martin Cummings will step into Brian's position as General Manager, Investor Relations, effective 1 July 2021. Martin brings substantial experience, among it the past 7 years at Evolution across several senior roles, such as General Manager, Commercial, where he was involved in leading all banking, procurement, and insurance relationships. To help with this transition, Brian will stay with Evolution through the end of September and make sure the handover to Martin goes smoothly.

Jake Klein

executive
#4

Now looking at the quarter — on the safety side, March closed with a TRIF of 8.6. The bulk of our recordable injuries are happening at Red Lake and Mungari, and those are the sites receiving the greatest focus. Company-wide, our attention is on critical risks and making sure corrective actions get closed out promptly. On the production side, the March quarter had been planned and budgeted as a lighter one. Heavy rains at Mount Rawdon limited access to ore at the base of the pit, which made the quarter softer than planned. Even so, every one of our other operations largely delivered to plan, and we're pleased that today we can lower FY 2021 all-in sustaining cost guidance from the original AUD 1,240-AUD 1,300 an ounce to a significantly improved AUD 1,190-AUD 1,220 an ounce. With investors rightly growing more worried about cost inflation as the Australian resources industry heats up, this is a very pleasing outcome. Underpinning it — and something I'm very proud of — are our very strong employee retention rates, which sit close to 90%. The June quarter ahead will be our strongest of the year, as Mount Rawdon recovers and Red Lake keeps ramping up its production.

Jake Klein

executive
#5

We've also used this chance to tighten the production guidance range to 695,000 to 710,000 ounces, and that sits comfortably inside the original guidance of 670,000 to 730,000 ounces. All in all, FY 2021 is shaping up as a really strong year for Evolution. Net mine cash flow so far this year is AUD 459 million. The Cowal underground feasibility study — the one that will let Cowal expand its production base to 350,000 ounces of low-cost gold annually — has moved forward nicely, and our engagement with the New South Wales government on the approvals has been constructive and positive. Red Lake produced ahead of plan and turned in a record quarter under Evolution's ownership. With the Red Lake mill back up and running, we expect the June quarter to be materially better. On the 15th of March, we announced an agreement to acquire Battle North for cash consideration of roughly CAD 343 million. The transaction has the full backing of the Battle North board and has been well received by shareholders of both Battle North and Evolution. Both groups see the compelling synergies that exist. The Battle North tenements are almost the same size as our Red Lake ground position and are contiguous with ours. They are highly prospective, with an existing reserve and resource base that would have underpinned a smaller standalone operation, producing around 74,000 ounces a year at an all-in sustaining cost of less than AUD 900 per ounce.

Jake Klein

executive
#6

The distance from our mining operations to their plant is roughly 12 kilometers by road. Our due diligence backed what Battle North believed: that capacity could be increased from the current 650,000 tonnes per annum up to 900,000 tonnes per annum, and at a low capital cost. They also hold material tax losses, and a merged operation would be able to use a large portion of them. The timing worked well. Battle North had obtained bank funding to start its standalone development, and a window existed in which an offer could be made. I want to commend and thank their CEO, George Ogilvie, along with his team and the Battle North board of directors, for their openness to engagement and for acting commercially at all times and in the best interest of their shareholders. The Battle North shareholder meeting is set for the 11th of May. With that, I'll turn things over to Bob, who will give some further detail on the operations.

Bob Fulker

executive
#7

Thanks, Jake. Good morning, everyone. Safety is where I want to begin. As Jake noted, our TRIF rose slightly, by 2%, in the last quarter. Mount Rawdon is still running an outstanding stretch without injuries, sitting at 453 days injury-free as of today. March output came to 161,000 ounces. The reason was a lower planned mill feed grade across the group plus Mount Rawdon's unplanned processing of stockpiles, which brought a net quarter-on-quarter decline of 8% in mill feed grade. All-in sustaining cost came in at AUD 1,263, generating AUD 101 million in net mine cash flow. Mount Rawdon's output fell because heavy rain required wall remediation. That impacted planned mill feed, since we replaced high-grade pit feed with low-grade stockpiles. The remediation work is finished now. As we said before, the fourth quarter was slated for higher ounce production thanks to a full quarter from both Red Lake mills. That now pairs with a better Mount Rawdon quarter from the delayed high-grade feed. Cowal produced 52,000 ounces at an all-in sustaining cost of AUD 1,078 per ounce, with operating mine cash flow of AUD 56.9 million. Happily, their spending on major growth projects carried on, with AUD 36 million of completed works during the quarter.

Bob Fulker

executive
#8

In February, the Cowal underground hit another major milestone as the Galway decline got underway. That decline is going to give us additional drilling platforms underground, and drilling from those is set to begin in the June quarter. Also in the June quarter, a feasibility study will be finished, and the regulatory approval process is moving forward as we anticipated. During that quarter, the Cowal operation was hit by a rain event of the kind you'd expect once in 100 years. It caused more weather-related delays than we had planned for, along with some geotechnical problems, but John and the team at site handled it very well, and as a result the mine is still on track to deliver its full-year numbers. Ernest Henry contributed significantly to the group financially once again, turning out 224,000 ounces at an all-in sustaining cost of -AUD 1,027 per ounce, and it generated net mine cash flow of AUD 74.8 million for Evolution. At Red Lake, output was 36,000 ounces with an all-in sustaining cost of AUD 1,966 per ounce, and net mine cash flow there came to AUD 1.3 million. It's worth noting that the operation sold 3,000 ounces fewer than it produced. Our transformation work at Red Lake is proceeding according to plan, and we achieved a number of highlights in the quarter. Mine development is beginning to show consistency, we successfully restarted the Red Lake mill, and the milling team posted a second straight record throughput month at Red Lake, putting 56,200 tonnes through in March.

Bob Fulker

executive
#9

The board gave the green light for the CYD decline spending, so work got underway on the box cut, and the next major milestone is mobilizing the underground development contractor. The decline project is still on schedule to produce ore in 12 months. Regarding the potential Battle North acquisition, the Red Lake technical team has been working on folding this exciting opportunity into the Red Lake planning cycle. Integration is progressing well, and within the next couple of months the team is eager for the chance to unite the whole field under a single leadership group. Mungari produced 27,000 ounces this quarter, with an all-in sustaining cost of AUD 1,561 per ounce and net mine cash flow of AUD 10.9 million. On the production side, seismicity affected the underground mining sequence and high grade delivery during the quarter. Underground production from other sources, though, held steady. Open pit mining rates rose 20% quarter-on-quarter as the Cutters Ridge infrastructure setup wrapped up. As noted, rain and the resulting geotechnical problems on the east wall seriously impacted Mount Rawdon's production. The team has fixed the pit wall and restored access to the pit bottom. They've also finished the work and raised the stability factors that had been a worry during the late wet season.

Bob Fulker

executive
#10

We’ve reforecast the mining schedule, factoring in the remediation timing as well as bench positioning, so that ore output rises considerably in Q4 from the pit’s northern end. To lessen the impact of additional rain events, depressurization holes are now in place on both the east and west walls. De-stacking of the eastern ramp is going to be pushed back until we’ve built up surface high-grade stocks. This quarter has been difficult for the team, yet their safety focus and resolve to work through the problems have brought them back into the high-grade zones at the pit face. Access to fresh ore at the negative 30 RL has been re-established, and it is grading 0.9 grams per tonne, versus the 0.5 stockpile material that was processed in the March quarter. Mount Rawdon performed as planned, though quarter cash flow was impacted by concentrate shipment timing, and that should reverse in the next quarter. During the June quarter, Mount Rawdon underground will focus on the western zone and the A39 decline. To sum up, our operations are well placed to produce a strong June quarter and to meet our yearly guidance for ounces, along with our welcome reduction in cost guidance.

Bob Fulker

executive
#11

Appreciate everyone joining, and now I'll pass things along to Glen.

Glen Masterman

executive
#12

Thanks, Bob, and good morning to all of you. During the quarter, drilling continued at Red Lake, Cowal, Mungari, and Cue, where we finished more than 14,000 meters of resource definition drilling along with 22,000 meters of discovery drilling. At Red Lake, as many as nine rigs were operating — six underground and three on surface. Several high-grade results from infill holes confirm that higher grades continue within the deep sulfide ore body at Lower Red Lake, and those results are expected to be converted from resources into reserves. Encouraging step-outs at Cochenour, which are outlined on page 11, will get follow-up in the June quarter. Those holes are planned beneath the upper main zone, with aggressive step-outs aimed at exploring the full extent of mineralization past the deepest levels of planned development. Discovery drilling carried on underground, targeting structural and stratigraphic targets in the hanging wall of the Kogarah Fault. That fault strongly influenced the geometry of the historically mined high-grade zone and may potentially connect to new mineralization in adjacent domains. Right now we are following up the promising results highlighted on page 12 to establish the potential scale and grade of mineralization intersected in this hole. The three surface rigs were placed on targets beyond the mining infrastructure footprint.

Glen Masterman

executive
#13

We had one rig positioned on the ice, and that gave us our first taste of drilling on a lake, Canadian style — which, as you can imagine, differs somewhat from the conditions we're used to when drilling salt lakes in Western Australia. We expect to have results from the East Bay trend program, from the western stratigraphy, and from the SR zone during the June quarter. Figure two on page 13 shows where the three prospects are located. Over at Cowal, one surface rig put in eight holes into GRE46 underground. The strong results we're seeing keep sharpening ore body definition at Dalmeny and push the resource further down plunge. Late in the quarter, that rig relocated into the pit at E42, where it finished geotechnical drilling before moving to the southwest crest to drill four deep step-out holes. This drilling targets high-grade extensions of mineralization below the ultimate pit design, an area where historic high-grade intercepts tie in with the central fault. At Mungari, underground drilling at Frogleg was meant to extend mineralization incrementally at the Rocket ore body, beneath the deepest development in the mine. The purpose of this drilling is to establish how far the mineralized vein structure can reach into an untested space that a panel of deeper drilling ultimately seals off.

Glen Masterman

executive
#14

The visual outcomes have been promising, though the structure seems to be narrowing at depth. Those results, which we anticipate will come out later in the June quarter, are going to inform additional drill planning that could potentially extend the mine life underground. Over at Cue, in Western Australia, Musgrave Minerals — our joint venture partner — has kicked off a seven-hole diamond drilling program. What that drilling is aiming to do is pin down the high-grade bedrock sources of the 5-kilometer-long gold in-ore anomaly at Lake Austin. We expect those results to be available in the June quarter. And finally, at Crush Creek, we're planning to start drilling early this quarter, continuing to build on the 126,000-ounce made mineral resource that was released back in February. The drilling will focus on expanding the resource base and following up on the positive results reported last quarter from Gamma and Delta. A number of new targets were developed over the summer wet season, and those will be added to the work program in this quarter. With that, I'll pass things over to Lawrie.

Lawrie Conway

executive
#15

Thanks, Glen, and good morning, all. Pages 10 and 11 of the report summarise how we performed financially in the March quarter. There are a few main things I'd like to point out today. Even with gold prices lower, our margins and cash generation are solid. The June quarter looks healthy, so we can raise our cost guidance, and the strength of our balance sheet shows we can do well right through the cycle. In the quarter we brought in AUD 100 million of net mine cash flow along with AUD 40 million of group cash flow. On operations, as Bob described, the principal factors behind production and unit costs were largely planned grade reductions — these fell 8% quarter-on-quarter — plus the knock-on effect on recoveries, which declined 2%. Metal prices, though, were what hit our cash flow hardest. The gold price we realised came in 8%, or AUD 200 per ounce, lower. Higher copper prices of 20% helped us, so the net price effect overall was roughly 5% lower. Even so, despite that weaker price, we achieved an all-in cost margin of AUD 467 per ounce, equal to 21% of revenue.

Lawrie Conway

executive
#16

So far this year, our all-in cost margin sits at AUD 731 per ounce, which is a touch above 30%. We expect better performance in the June quarter, and that margin should rise. Turning to the June quarter, we're on track there for increased output and reduced costs. Running the Red Lake mill for the entire quarter and reaching better grades in the pit at Mount Rawdon will be the key things driving the June quarter. The remaining operations will be broadly the same, with small rises or falls. As a result, the group's average grade and recovery should climb back toward the levels we saw in the December quarter. That has let us narrow our guidance range to 695,000 to 710,000 ounces. Given this June quarter plan, the steady cost profile throughout the business, and a better realized copper price, we've brought our all-in sustaining cost guidance down to AUD 1,190-AUD 1,220 per ounce. The genuine bright spot, however, is that the area we can influence most is under very good control. That area is costs. Our operating expenditure has stayed at the AUD 225 million level in each of the first three quarters of this year.

Lawrie Conway

executive
#17

There's going to be a modest uptick in the June quarter, though the main driver behind it is the Red Lake and Mount Rawdon work we talked about earlier. Sustaining capital has likewise held steady, running between AUD 23 million and AUD 25 million every quarter. Taking the June quarter forecast into account, we'll close out the year somewhere in the AUD 100 million to AUD 110 million range, a reduction from the AUD 113 million to AUD 138 million we originally guided to. Looking at all-in costs, our major projects are progressing as planned, and their spending profile rises as those projects move forward. We remain on track to end the year inside the original guidance band of AUD 260 million to AUD 290 million. Year-to-date net mine cash flow came in at AUD 455 million and group cash flow at AUD 258 million, so the balance sheet is in very good shape. Net bank stands at AUD 167 million, following the record interim dividend of AUD 120 million that we paid out during the quarter. Unaudited gearing sits at 6%, and we expect to reach a net cash position by year-end, ahead of completing the Battle North transaction. We intend to fund the Battle North transaction using existing cash along with our credit facility.

Lawrie Conway

executive
#18

We still have our AUD 360 million revolver facility completely undrawn, and that gives us sufficient liquidity as we move ahead. Thanks for joining us this morning, and Kaylee, would you please open up the lines for questions.

Operator

operator
#19

Thank you. Should you want to pose a question, kindly press star one on your phone and hold until your name is called. To withdraw that request, simply press star two. In case you're using a speakerphone, please lift the handset before asking. Our first question is from Nick Herbert at Credit Suisse. You may proceed.

Nick Herbert

analyst
#20

Hello there, everyone.

Jake Klein

executive
#21

Nick, that's you.

Nick Herbert

analyst
#22

Yes, that was me speaking. There was a slight delay there. I want to begin with Red Lake, if I could, simply to clear up a few points regarding that Upper Campbell. I'm curious about the ramp-up schedule after the first ore in 12 months, and what level of sustainable extraction that ultimately reaches. I'd also like to know about grade continuity at that site — should we simply assume the reserve grade of 7.4, or is there some variability once you begin from the top down? Thank you. I have a couple more questions after this.

Jake Klein

executive
#23

Thanks, Nick. Bob, over to you.

Bob Fulker

executive
#24

Thanks, Nick. On the grade — your assumption is correct. As for the ramp-up, we expect it to happen over an extended period — or maybe not extended, but it definitely won't be instantaneous. Reaching a full production tonnage regime is going to take a bit of time. It will come after the 12-month timeframe. We might get some development ore within that first 12 months, but nothing major beyond that. After that point — we're using pretty broad numbers at the moment — most underground decline mines would see that second year at some sort of half rate, then move into full rate for the third year and subsequent years. We are planning for the area to have a couple of mining fronts. As we said last time, full production is around about — I don't know. Is that a good scope?

Jake Klein

executive
#25

I'd say we're putting substantial strategic work into figuring out how the Bateman facilities and projects get integrated as well. Once the shareholder vote over there has happened, we'll bring the market up to date. Had we only the Campbell and Red Lake mill, we would have faced mill constraints. At this point the Bateman mill may become available to us, along with the Bateman deposit. As soon as the Bateman shareholder vote wraps up, we'll update the market.

Nick Herbert

analyst
#26

That’s excellent.

Jake Klein

executive
#27

On the subject of providing additional specifics regarding ramp-ups, where the ore comes from, and grades.

Nick Herbert

analyst
#28

All right, thanks a lot. That’s a good segue into what I wanted to ask next. I’m just curious about how you’re viewing the Bateman acquisition and whether it alters your longer-term thinking on the 300,000 to 500,000 ounces you’ve set out as a target, or whether it’s really more about the flexibility it provides. Specifically regarding that available mill capacity. And related to that, where it fits into your thinking, since it’s a new mill and potentially lower cost. If you could offer any comment on that, thanks.

Jake Klein

executive
#29

Right. That doesn't alter our 300,000 to 500,000 ounce profile at all. The reason is that one constraint we faced was this: with just the Campbell and Red Lake mills available, we would have been limited by milling capacity once the upper Campbell area ramped up and the lower areas hit full production. As things stand now, the bottleneck has moved back to the mining area. So what does that mean for how we're thinking? It's not going to exceed 300,000 to 500,000 ounces, but it does give us a chance to potentially get there sooner. The tricky part will be deciding which mill to fill. How do we deliver the highest grade to the mills at the earliest point? That work is continuing, and I think we should hold off until we've been through the shareholder votes with Battle North before really giving you a detailed sense of our thinking on that. Putting the highest grade through the lowest cost mills will be the strategy.

Nick Herbert

analyst
#30

Alright, thanks.

Jake Klein

executive
#31

I should clarify that the Bateman mill carries lower costs compared with our remaining mills.

Nick Herbert

analyst
#32

Yeah, got it. Thanks. Regarding Ernest Henry, could you provide some update on the progress of the deep drilling beneath that 1,200 meters? And just a reminder, please, of when a resource update is expected there.

Lawrie Conway

executive
#33

Yeah. Morning, Nick. The program is proceeding according to plan. We have doubled the budget for this year — this calendar year — together with Glencore and Ernest Henry, so that we can complete an update during the first quarter of calendar year 2022. They anticipate progressing to a concept study around the middle of this calendar year, which will guide decisions about what happens beneath the 1,200. All drilling and the programs are on track.

Nick Herbert

analyst
#34

Alright, thank you, Lawrie. And last, Brian — I appreciate everything you've done to help me throughout the years. Working with you has been a pleasure, and I wish you the very best in whatever you take on next. Cheers.

Brian O'Hara

executive
#35

Thanks, Nick. I wasn’t aware you were on my team, but that’s a kind remark. I’ve truly appreciated all the interaction with the wider market throughout the years, and I’ll miss it. Thank you.

Jake Klein

executive
#36

What worries me is that once Brian transitions into fund management, he could end up on calls like this one, posing the tough questions. Thanks, Nick.

Operator

operator
#37

Hayden Bairstow of Macquarie is up next with a question. Go right ahead.

Hayden Bairstow

analyst
#38

Morning, everyone. Brian, nice work, mate — and it's good to see you getting one last jab at the gold bugs' crypto argument on your way out. Well done on that. Jake, just a couple of items. I'm not quite following, because obviously a big gold transaction has just closed, and you touched on things alongside Brian's remarks regarding the outlook for gold — so how are you viewing the portfolio's structure and a few of the smaller assets? Clearly capital will be stepped up in Canada, and where are your thoughts heading there? And a bit on managing the hedge book — is this a chance to shut down a larger portion of those money hedges while pricing is somewhat softer? Just how you're looking at that, please. Thanks.

Jake Klein

executive
#39

Lawrie, would you like to start by saying something about the hedge book?

Lawrie Conway

executive
#40

Okay, Hayden — absolutely. Our stance has been that the hedging was put in place for particular reasons, whether that's the cutbacks that were developed or Red Lake, for instance, and it was simply to guarantee that during this initial two years of transforming the asset, they'd be able to fund their own capital. Our position hasn't changed: we will deliver the hedge books as they come due. We're not about to speculate on where the gold price is headed. What we want is for the assets to produce at the lowest cost they possibly can. We still come out with 85%-90% of our production and sales benefiting by going into the spot market. We're comfortable with where it stands right now.

Jake Klein

executive
#41

Regarding the portfolio, Hayden, the strategy stays the same. We'll keep evaluating everything by asking whether it raises the quality of our portfolio and whether it's accretive to our shareholders. That applies to both investments and divestments.

Hayden Bairstow

analyst
#42

All right, thanks. Turning to that Canadian acquisition — is the conversation really just going to center on how fast you're able to ramp up mine development, now that the surface capacities are already in place?

Jake Klein

executive
#43

Yeah, that's right. What I mean is, all eyes are squarely on Bob at this point to lift mining productivity and make sure those mills are filled.

Hayden Bairstow

analyst
#44

All right, that's great — thank you, everyone.

Jake Klein

executive
#45

Appreciate it.

Operator

operator
#46

Sophie Spartalis from Bank of America has the next question. The line is yours.

Sophie Spartalis

analyst
#47

Morning, everyone. I’d like to ask a couple of questions if that’s all right. On the better cost guidance, Lawrie, could you split out for us what portion came from copper versus other factors—specifically tied to the copper price?

Lawrie Conway

executive
#48

Yeah, Sophie, so I think what we're likely looking at is that in the second half of the year we average AUD 11,500 a ton versus AUD 8,400. We'd expect that to come to roughly AUD 50 an ounce as the full-year impact. There's going to be an effect of, I'd say, probably AUD 5 an ounce from sustaining capital, and the rest will fall across a combination of OpEx and production mix for the portfolio.

Sophie Spartalis

analyst
#49

All right, that's great. A quick second question, and this is probably better directed to either Bob or Jake. Regarding Cowal, could you walk us through how sustainable that plan of reaching 350,000 ounces really is? What more do you need to firm up in order to see those rates held for the life of mine?

Bob Fulker

executive
#50

Yeah. Sophie, that's a good question. In my view, sustainability ties to the underground development and to getting ore of higher grade through the mill. It's that mix of stock feed from the open pit plus the underground, which gives us the grade needed to lift production. As we've said, the feasibility on the underground has reached its conclusion, and it will be done late this quarter — well, the fourth quarter. We'll come back once that's wrapped up too. That's the way I see the stability there. The grade boost we need will come from that underground.

Jake Klein

executive
#51

What comes next as a genuine catalyst in that area is approvals from the government, and engagement on that front has been both positive and constructive. Every question that has been raised, we have responded to. Support from the public has been solid, and it is moving through the standard process.

Sophie Spartalis

analyst
#52

All right, regarding the underground development, Bob — that jump in grade: are you confident it’s actually there? Or would you need to do more exploration to find higher-grade material so it can be sustained? Given what you’ve found so far, are you fairly comfortable?

Bob Fulker

executive
#53

Yeah. We have a good deal of confidence. Yes, confidence is high on our side. Definition drilling — what has been completed to this point, and what Glen and his geological team have carried out — has in fact demonstrated that when those holes are placed nearer together, we achieve improved definition as we move down toward the stope size rather than relying on the regional block model. As time goes on, we anticipate that this will keep holding true.

Glen Masterman

executive
#54

Yes. Sophie, I would simply add that the underground resource — every reserve founded on an indicated classification — we feel confident represents a solid worldwide estimate of tons and grade within the model. What comes next for us is, as that development reaches positions where we can begin shifting from indicated into measured classification through additional infill drilling to enhance or boost filling density, and afterward ultimately into grade control. That will provide us a stronger grasp, for stope design, of grade and through the sectional locally.

Sophie Spartalis

analyst
#55

All right, that's excellent. Appreciate it, everyone. I'll stop at that point.

Jake Klein

executive
#56

Appreciate it, Sophie.

Operator

operator
#57

Kate McCutcheon from Citi has the next question. Go right ahead.

Kate McCutcheon

analyst
#58

Hey Jake and Bob. I've got a couple of questions about Red Lake, if that's alright. Since you took over that asset, the unit processing costs have come down quite a bit. Can we count on that continuing going forward? And second, those seismic issues you mentioned at Red Lake — are they temporary, or do they tie to that particular mining area? Any thoughts on that?

Bob Fulker

executive
#59

Kate, what we intend to do is keep bringing down costs at Red Lake across every area — mining, processing, and G&A alike. When we made the original acquisition, we described it as a 3-year process, and we're halfway through it now. At Red Lake, the seismicity itself is mostly in the lower Red Lake zones. It appears we don't have that issue, or we don't have it, in Cochenour or in some of the upper levels at Red Lake. That's a matter we work on, and it's a matter they have a solid management plan in place for. The remark was really about seismicity at Mungari from a production standpoint for last quarter. That's a matter we're addressing, and the team actually is aware of it, and they have plans along with geotechnical sequences that they follow so that it can indeed be continued.

Jake Klein

executive
#60

Kate, I’d just like to add that at Red Lake we’re achieving both improvements and cost reductions, which is excellent. The Bateman Mill runs at a materially lower cost than the Red Lake and Campbell Mills do. That gives us an opportunity, as we begin feeding material into that mill, to bring costs down even further beyond the gains in productivity and efficiency we’re already delivering at Red Lake.

Kate McCutcheon

analyst
#61

Yes. All right. If Battle North does go through, could you walk me through the permitting process once more—both for trucking ore from Upper Campbell and for raising the permitted capacity at the Bateman Mill?

Jake Klein

executive
#62

Right. A permit is required. To haul that material, you need a provincial permit. Some testing of the material is needed to make sure there aren't any problems tied to putting that material into the tailings dam. We don't expect that permit to be hard to get. It's really about timing. It's a comparable process to increasing development or raising the capacity limit from 450,000 tons to 900,000 tons per annum. We don't view those as obstacles when it comes to ramping up to more than 2 million tons of throughput at Red Lake.

Kate McCutcheon

analyst
#63

Yeah, okay — those two are both provincial permits.

Jake Klein

executive
#64

Absolutely.

Kate McCutcheon

analyst
#65

Great. Last thing on Cowal: does any part of the feasibility study hinge on how the permitting decisions come out, or could that work proceed entirely as its own separate stream?

Jake Klein

executive
#66

How soon development can begin hinges largely on securing the permits. After that, the client base and the accommodation are the major cost items we have to put in place. Yeah, when it comes to actually getting development underway, the practical reality is that those permits have to come through.

Kate McCutcheon

analyst
#67

Yeah. Alright, got it. Thanks, and best of luck to you, Brian.

Brian O'Hara

executive
#68

Thanks, Kate. I appreciate that.

Operator

operator
#69

Mitch Ryan from Jefferies has the next question. Go ahead, please.

Mitch Ryan

analyst
#70

Morning, everyone. This is a bit of a broader one — not among the main questions that have come up — but following the shareholder meeting on 11 May, could you remind us once more about the settlement timeline? If the vote goes your way, when do you get the keys to that asset?

Lawrie Conway

executive
#71

Voting takes place on the 11th, and approvals are anticipated by May 17; soon after that, the whole thing will be finalized and the keys will be in our hands.

Jake Klein

executive
#72

I think it's comparable to a scheme of arrangement year, where the matter goes before the courts for confirmation or affirmation of the shareholder vote, though it's really a procedural matter.

Mitch Ryan

analyst
#73

All right, that makes two.

Jake Klein

executive
#74

Sure.

Mitch Ryan

analyst
#75

Moving to the second question, which is separate, but from what I gather from peers who hold assets in Western Australia, labor availability has been a major concern on the cost side. Your costs are coming down, and clearly part of that is due to copper, but could you offer any insight into how labor availability looks on the East Coast and what cost pressures that is or isn't creating for your cost base?

Jake Klein

executive
#76

Thanks, Mitch. I want to go back to what I said earlier about our retention rates being high—they're near 90%. Making sure we keep our people has genuinely been a priority for us. Retention is stronger on the East Coast than on the West Coast, where turnover has risen and pressure has grown. On the East Coast in particular, our retention rates are really high. Taken as a whole, as a group, we're very happy with a retention rate near 90%.

Mitch Ryan

analyst
#77

Alright, yeah, thanks. This is my third and final question. I suppose your company’s stance on operating a portfolio of assets has been communicated fairly well, but since a lot of the soft quarterly production comes from Mount Rawdon and its contribution to NPV is negligible, are you considering a strategic review of that asset?

Jake Klein

executive
#78

My view is that Mount Rawdon had a weak quarter, and the rain was the reason. Honestly, it will recover. The only additional point to make is that every one of our assets is constantly being reviewed. I don't believe we ought to treat that single quarter at Mount Rawdon as showing where it stands within the portfolio.

Mitch Ryan

analyst
#79

Sure, that's fair. No problem at all. Thanks, everyone, for spending some time with us — and good luck to you, Brian.

Jake Klein

executive
#80

Appreciate it, Mitch.

Lawrie Conway

executive
#81

Appreciate it, Mitch.

Operator

operator
#82

As before, should you want to pose a question, press star one on your phone and hold until your name is called. Andrew Barack of S&P Global Market Intelligence has our next question. You may proceed.

Andrew Barack

analyst
#83

Hi there. A quick question, if I may, about the United Nations Global Compact you announced a few weeks ago. I'm just curious, because companies often publicize these things when they sign on to such initiatives, yet not much was mentioned here. I know you laid it out in your sustainability report. I believe your letter applying for it also referred to this. So what does it really mean? Could you say anything about what committing to it means for you in a tangible sense — for example, does it oblige you to do something where you might currently see yourself as somewhat inefficient, or to seek out new initiatives, or to improve a particular thing that you're clearly already working on for the most part? I was hoping for something more concrete regarding what it means for your company.

Jake Klein

executive
#84

Yeah. I think what we'd say is that even before signing up, we were already compliant and aligned with the 10 Principles. We viewed it as a meaningful signal of our dedication to continuing with those principles, and ideally something the entire industry will embrace. It's more of an initiative than work that has to be done to make sure we're compliant, since we were compliant ahead of this.

Andrew Barack

analyst
#85

Taking a wider view, do you think there's anything particular to the gold sector when it comes to advancing those objectives that the Global Compact is generally pursuing, compared with other commodities — perhaps in the field of gold bar tracing, or anything else that's fairly distinctive to gold mining that genuinely has to be addressed?

Jake Klein

executive
#86

No, I’d say it centers more on the ten principles — environmental matters, human rights matters, labor matters, anti-corruption. All of those are connected. I don’t believe there’s anything that is necessarily specific to gold. On the issue you raise about tracking a gold bar, we will listen to shareholder and stakeholder feedback on whether that is something they want to see in the future. A few people have pitched us that blockchain is the answer to that, but I’m still learning about blockchain and that technology.

Andrew Barack

analyst
#87

Alright, thanks.

Jake Klein

executive
#88

Much appreciated.

Operator

operator
#89

The following question is from Alex Barkley at Morgan Stanley, Australia. You have the floor.

Alex Barkley

analyst
#90

Thanks. Morning, everyone. I’ve just got one question about the improvement in sustaining capital guidance. What drove most of that, and was it largely good work bringing costs down, or is some of it likely to be deferred into FY 2022 and affect the AUD 110 million–AUD 135 million guidance for that year? Thanks.

Lawrie Conway

executive
#91

Alex, it came from a mix of things. At Red Lake in particular, given some of the gains they've managed to make, they don't expect to spend that entire amount of capital during this year. Some of it could carry over into next year. Across the remaining sites, it was simply an overall decrease in what they're projecting for sustaining capital needs this year. We're roughly five weeks out from completing every life of mine plan and the final budgets for next year, but we don't anticipate sustaining capital next year shifting materially from our three-year outlook.

Alex Barkley

analyst
#92

All right, that’s very useful. Appreciate it. Best of luck, Brian.

Brian O'Hara

executive
#93

Much appreciated, Alex. Thanks.

Operator

operator
#94

Paul Kaner from RBC has the next question in the queue. Go right ahead.

Paul Kaner

analyst
#95

Hey, guys. Appreciate you taking my question. I just want to dig a little deeper into those Red Lake costs — I understand that Bateman is able to lower the fixed portion of your milling cost. So does that mean we should probably expect a revision to your long-term cost assumptions for Red Lake across the wider region?

Jake Klein

executive
#96

Our stated three-year outlook, absent Bateman, involved reaching AUD 1,000 per ounce at 200,000 ounces annually. We aren't prepared at this point to define how 300,000 to 500,000 ounces would take shape. My view is it's preferable to hold off until the Bateman project is in hand, at which point we can lay out the strategy for how those mills will be filled.

Paul Kaner

analyst
#97

Sure, I hear you.

Jake Klein

executive
#98

At those three processing mills, we'll have capacity exceeding 2 million tons. As I mentioned before, the priority is going to be getting the highest grade into them as quickly as we can.

Paul Kaner

analyst
#99

Yeah, no problem. Got it. Appreciate it. I’m finished on my end. Brian, thank you for all the support you’ve given me over these past few years.

Jake Klein

executive
#100

Thanks, Paul. Cheers.

Operator

operator
#101

Stuart McKinnon from The West Australian has the next question. Go right ahead.

Stuart McKinnon

analyst
#102

Hello, everyone. This question is likely directed at you, Jake. I believe during the previous quarter—or maybe the one before that—you mentioned that a softening gold price might reduce asset valuations, making M&A more realistic and achievable. We have just witnessed a notable asset sale at Tropicana, at what some regard as a fairly high price. So I am curious whether you are observing that lower gold price feeding through into decreased asset valuations, or whether conditions remain quite heated in the M&A market.

Jake Klein

executive
#103

That is a fair question, Stuart. We have completed a single M&A transaction, the Battle North project, since we identified an opportunity there. Regarding the Tropicana sale, we were not the acquirer. You are free to form your own views about that. My expectation is that we will remain committed to the approach of pursuing transactions that add value for our shareholders, and we will keep searching for opportunities where either a geological opportunity exists that Glen and his team are able to identify, or the seller faces some stress or has motivation. Finding motivated sellers is harder when the gold price is rising. It now falls to Glen and his team to locate geological upside.

Stuart McKinnon

analyst
#104

Thanks, Jake — that's great.

Jake Klein

executive
#105

Appreciate it.

Operator

operator
#106

Peter O'Connor from Shaw and Partners has the next question. Go right ahead.

Peter O'Connor

analyst
#107

Morning, Jake. This one's for Bob. What's the outlook for Red Lake? As the mine develops and output begins to grow underground, and that constraint goes away. I'm just thinking through how costs trend. In the current operations you have some older, more complex stoping areas at depth. You have new areas at Bateman, and with the decline at Red Lake, obviously you're sort of free of the legacy mining areas. On stoping cost, does it make a difference whether it's fresh virgin ground in the decline, at Bateman, or at depth at Red Lake — if stoping costs are equal, or is there a meaningful advantage from being able to open a new area at surface from the decline?

Bob Fulker

executive
#108

Thanks, Peter. Doing the decline is easier, and that will open up access and productivity gains since the shaft no longer limits us. That said, the shafts have room for more than 1.1 million tons out of underground. Much of the Red Lake area, as I mentioned earlier, has some seismic problems, but plenty of zones there have none of that, and there's lots of virgin ground where it's fairly simple to block in good, easy-sizing stopes and mine them productively. Whenever there's clear open space between the historic openings and the new ones, we can mine at lower cost and with less complexity. To answer your question, it's somewhat a mix of all those things. I do expect underground stoping costs at Red Lake on the deeper levels to get better as we achieve improved cycles and better solid stopes. I also expect upper Campbell to come into its own thanks to the decline and the cost reductions available from trucking rather than hoisting.

Peter O'Connor

analyst
#109

That's not a meaningful difference in dollars per ton, is it?

Bob Fulker

executive
#110

Honestly, that's just something we can't determine.

Peter O'Connor

analyst
#111

Brian, I have to say I'm envious — hashtag jealous. Nicely done.

Brian O'Hara

executive
#112

Appreciate it, Rocky. Thanks.

Jake Klein

executive
#113

Thanks, Peter.

Operator

operator
#114

That brings us to the end of the Q&A. Mr Klein, I'll return the floor to you for any closing comments.

Jake Klein

executive
#115

Yes, thanks to all of you, and I appreciate you tuning in. I'm looking forward to bringing you an update after the Battle North shareholder meeting takes place, with announcements and more detail regarding what we have planned at Red Lake. Many thanks.

Operator

operator
#116

That brings today's conference to a close. We appreciate your participation. You're welcome to disconnect at this time.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Evolution Mining Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to Evolution Mining Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Evolution Mining Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.