operatorWe appreciate everyone being on the line, and we’re glad to have you join the Evolution Mining conference call on the results for the June 2022 quarter. <<operator_script>> At this point I’ll turn the call over to Executive Chairman Mr. Jake Klein. Please go ahead.
Jacob Klein
executiveThanks, Darcy. Good morning, everyone. Thanks. This morning, Lawrie Conway, our CFO and Finance Director, is with me; Bob Fulker, our Chief Operating Officer; Glen Masterman, our VP of Discovery is also here to answer any questions you may have on our exploration results. I'll make a few comments this morning before handing over to Bob, noting that our commentary will be shorter than usual given the comprehensive business update that we provided on the 27th of June. Strategically, in an inflationary higher cost environment, which is what we're in, it is more important than ever to have a portfolio of low-cost operations. Our all-in sustaining cost margin we achieved in the last 12 months is AUD 1,166 an ounce, and this is sector lead <<inaudible>> if we want to build a business that can prosper through the cycle, and I believe we are well placed to do this. We finished the year in line with our update. The June quarter was the strongest quarter of the year from a production perspective. I want to highlight just a few things I think are particularly noteworthy in the quarterly that we released today. Ernest Henry had a stellar year. It generated $435 million of net mine cash flow, and we only owned 100% of it for 6 months.
Jacob Klein
executiveThe potential of this ore body is just as thrilling. We're currently completing the last checks and reviews on the mineral resource, and I'm confident that once it's released on August 1, the opening day of the Diggers & Dealers Forum, you'll share our belief in the operation's extremely bright and long future. The cash flow coming from Ernest Henry is backing our significant investment in accretive growth at both Cowal and Red Lake, and those drive the 25% increase in production over the next 2 years. At Red Lake, progress is coming along well. Our ore reserve models are reconciling as expected, development rates are holding steady, and mining rates and compliance to plan have gotten better. That let us deliver 8% higher grade and process 8% more tonnes, for a 17% improvement on production to over 38,000 ounces this quarter. Those are the metrics needed to deliver our FY '23 guidance, and July has seen these improvements continue. Because Red Lake carries a relatively high fixed cost component, as production grows we do expect cost per ounce to keep improving. We're confident about Red Lake's future.
Jacob Klein
executiveWe're going through a transformation, but this is one that will deliver meaningful value to our shareholders. Cowal keeps demonstrating that it's a terrific asset. I'm glad that, even with the inflationary cost pressures, the $380 million Cowal underground mine is still on its original schedule and budget, and all major contracts are now in place. Despite tough operating conditions, Mungari finished the year very strongly, and the pumped hydro opportunity at Mt Rawdon is moving forward. Lastly, we do acknowledge and recognize how important operational delivery is in FY '23, and we're motivated and well positioned to deliver it. With that, I'll pass things over to Bob.
Robert Fulker
executiveThanks, Jake, and good morning, everyone. During the June quarter, group production rose 16% to 173,000 ounces, with an all-in sustaining cost of $1,290 per ounce. Going straight to the operations: following a weaker start to the quarter because of weather, Cowal had a strong finish and lifted overall material movement 6% versus the March quarter. Ore mines also rose by 42%, and Stage H is set to move into significant ore movement over the quarters ahead. In addition, underground development ore climbed from 2,000 tonnes in Q3 to 62,000 tonnes in Q4. We apply a marginal costing approach to the development cutoff grade, and that explains the 1.17 grams per tonne from the underground. Under the open fleet replacement strategy, the new 400-tonne primary excavator was delivered. Through better availability, this will boost total material movement over the coming quarters. The $380 million investment in the underground remains on cost and schedule. Spend to date totals $112 million, and practical completion is due this financial year. We have seen a nice lift in development meters with the additional jumbo, with the June month drilling -- sorry, delivering 743 meters with 2 rigs.
Robert Fulker
executiveErnest Henry turned in another robust quarter, lifting output to 21,000 ounces of gold along with 15,300 of copper. Revenue took a hit from concentrate revaluations brought on by a 23% drop in the copper price, yet we still generated $117 million in operating mine cash flow. Last quarter we spoke about the development focus aimed at boosting sublevel access so cave production could rise. In this quarter, Ernest Henry raised lateral development by 39%, reaching an average of 770 meters per month. The site team has plans ready to push this higher in the months ahead, all directed at enhancing the cave's operational draw and at getting ready to deliver the feasibility study outcomes for the mine extension beneath the 1125 RL. The pre-feasibility study remains on track to be finished by the end of calendar year '22, and the updated mineral resource is set for release on August 1. Red Lake's transformation keeps producing gains, with output up 17% to 39,000 ounces, positioning the mine to deliver FY '23. Red Lake is now running at the rates needed to hit FY '23 guidance. Development rates have stayed above 1,200 meters per month for 9 months now. And the advance rate at the CYD of 727 meters in the June quarter will let us extract the first stope in Upper Campbell during the September quarter.
Robert Fulker
executiveWe're on the verge of reaching the old 3-level Campbell. Even though regional flooding limited site access in May, the operation produced 235,000 tonnes at 5.16 grams per tonne — a mine grade 12% above the prior quarter — and processed a record 258,000 tonnes at 5.1 grams per tonne, which is an 8% gain over the March quarter. Processing in the June quarter is running at an annual rate beyond 1 million tonnes per annum and is consistent with FY '23 guidance. Both mills are exceeding our expectations, and we're identifying ways to push throughput even higher without hurting availability or recovery. The December 21 resource models keep reconciling nicely and are also performing within plus or minus 5%. The FY '23 budget leans toward delivery, and our focus is on grade and mining the right tonnes at the right time. The budget was constructed with a factored Upper Campbell grade so the new model and remnant mining variations could be accounted for. The Mungari integration is coming along well, and it has offset the broader impacts of COVID during the quarter. Mungari June production came in above plan thanks to Kundana and Frog's grade and the limited East Kundana ore processed.
Robert Fulker
executiveWe keep finding cost savings via synergies across sites and by consolidating contracts, and that effort will carry on throughout FY '23. At Mt Rawdon, the water and North wall geotech challenges continue to be handled well, and output came in as anticipated given those constraints. To sum up, Red Lake turned in a stronger quarter and is now running at the rates required to meet our FY '23 guidance. First stope ore at the Cowal Underground project is now under 12 months away, and both the schedule and costs for that project stay on track. Ernest Henry keeps producing substantial cash, and I'm excited about the resource update coming up and the positive effect it will have on the extension study. Thanks for your time. I'll now pass it to Lawrie.
Lawrie Conway
executiveThanks, Bob, and good morning to everyone. I'm glad to give you an update this morning on how we performed financially in the June quarter, which is laid out on Pages 8 and 9 of the report. Our financial metrics came in consistent with the business update we released on 27 June, with group all-in sustaining costs for the year at $1,259 per ounce, while sustaining capital came in under the low end of guidance at $146 million and major capital sat comfortably within guidance at $459 million. Operating cash flow for the quarter was $228 million. For the full year, that figure was $893 million, equivalent to roughly $1,400 per ounce. Having invested $146 million in sustaining capital, we had a little under $750 million left for investment in growth and other uses. Net mine cash flow for the year came to $284 million, or $445 per ounce, equivalent to a 20% margin. Group cash flow was $66 million and $110 million for the quarter and the full year, respectively. Our balance sheet is in very strong shape, with $300 million of debt repayments made during the year, and our cash balance finished ahead of plan at $572 million, giving us liquidity of more than $930 million.
Lawrie Conway
executiveWith that kind of balance sheet strength, we took a proactive approach to managing where our revenue and costs stood as conditions shifted both inside and outside the company, so that our margins and our balance sheet stay protected. Our cost guidance for FY '23 came out in our update on 27 June, with group all-in sustaining costs guided at roughly $1,240 per ounce. Sustaining capital is guided between $190 million and $240 million, and major capital is guided at $530 million to $600 million, with Cowal making up most of that at $325 million to $360 million. I'm looking forward to bringing you an update next month on the full year financial results. Thanks for spending time with us this morning. And I'll now hand it to Darcy to open the line for questions. Thank you.
Operator
operator<<operator_script>> David Radclyffe of Global Mining Research has the first question.
David Radclyffe
analystI have a couple of questions, and maybe we can start with Cowal. Throughput at that plant last quarter was the strongest it has been in quite a while, coming in near roughly that 9 million tonne annualized rate. So I'm just wondering if you could give a little more detail on that. Was it simply a good run? Or do you think this is something that could be more sustainable as we go forward? It appears you've clearly mined considerably more ore over the last 6 months than you've been able to process, so I'm trying to think about what the potential upside there might be.
Jacob Klein
executiveRob, that one's probably yours to take. Appreciate it, David.
Robert Fulker
executiveThanks, David. David, the ore percentage is elevated. It's going to stay elevated, since within the pit we're now in a higher ore ratio than in earlier quarters. Obviously — perhaps not obviously, but our approach is to process the higher grade coming from the pit together with the underground dirt. And we're once again building stockpiles, as happens during this phase of the pit. Planned throughput is really based on the blend of ores, the oxide percentages, the underground percentages, and simply what we're able to push through. Last month did go well, however — at Cowal, throughput made it a solid quarter.
David Radclyffe
analystAll right, I suppose the budget for the upcoming 12 months is somewhat nearer than what we've seen over the past couple of years, as opposed to this quarter.
Robert Fulker
executiveAbsolutely.
David Radclyffe
analystAlright, and perhaps just a few brief follow-ups for Lawrie. To start with, could you perhaps address how QP or PP at Ernest Henry affects copper sales? And where would we see that reflected — is it within the received price? Then, a slightly accounting-related question as well. Looking at the quite significant swings in depreciation rates at Ernest Henry and Mungari, I'm just trying to grasp why they are shifting so considerably. And should those rates be the ones we apply going forward?
Lawrie Conway
executiveYes. Thanks, David. On the first point, the QP adjustments for copper at Ernest Henry do flow through into their revenue. So as each shipment gets finalized, the final price is what shows up as revenue for the copper at Ernest Henry. And that's kind of why, for the quarter, you'll see we averaged roughly $10,500 a tonne in the quarter versus about $14,000 in the March quarter. So that's where we see it. Then on D&A, what happens in the June quarter is that when we update our MROR in February, we then run the changes from that MROR through the latest life of mine plan. So you actually end up with a number of true-ups in the quarter, and that's what occurred at those 2 sites. Now the only other thing is, with Ernest Henry, you're dealing with the transition from an economic interest joint venture to the new asset, 100% ownership, but there's very little in the June quarter for that item. And we have to finalize the valuation of this acquisition in the coming months. When we get to the August full year results is when we'll break out the D&A by site for this year.
Lawrie Conway
executiveWhat I believe you'll notice is that the majority of those assets will essentially align with the full-year figures for FY '22, as opposed to only the June quarter.
Operator
operatorOur following question is from Matt Greene at Credit Suisse.
Matt Greene
analystLet me just ask one more thing about QP pricing, if that's okay. Broadly speaking, how long is the settlement lag? For your copper sales, is it 3 to 4 months?
Lawrie Conway
executiveYes, Matt. So it depends on the shipments and on where we sit in the contract year — Glencore has the right to nominate the QP. Right now, they’re using a 4-month moving average. So as things stand, each shipment stays open for 4 months.
Matt Greene
analystUnderstood, that helps. Now, regarding FX—we've obviously watched it shift considerably. I assume these are priced in U.S. dollars. As for the Aussie dollar, though: on settlement—does that get settled at the settlement date? Or do you hedge the FX exposure out at the settle date?
Lawrie Conway
executiveNo, we don’t hedge it out. The copper gets sold on U.S. terms once the 4-month period is over and we reach the final copper price. That price is set in U.S. dollars. Then, when settlement comes through, any FX variance goes into the FX account in the P&L. And that applies only to the stretch from setting the price at the end of those 4 months through settlement. So that stub period doesn’t affect copper revenue as such.
Matt Greene
analystUnderstood. Alright, that's useful. Then regarding Red Lake, the reconciliation upgrade of 5% to 6% that you're seeing in the grade control model — in recent months, has that tended to skew more positive or more negative?
Jacob Klein
executiveMy view is that it moves around somewhat. What I mean is, we have a lot of confidence that the models are functioning. It goes up and down. And we feel quite good that the models are right. I believe that is a really key point — the takeaway for those on this call is that questions have come up regarding how the models have performed. And at this point we understand where the dilution came from and where the impact came from during the first half of the year. We have fixed that. And the models are doing well, and we are confident that in the areas where we are mining, the models are accurate and reliable.
Matt Greene
analystAll right, that's wonderful to hear. And then just one final item regarding Cowal — the CapEx figure of $380 million you have there: how much contingency is baked into it? And I suppose, now that all your contracts are in place, do you remain at ease with that contingency level?
Jacob Klein
executiveYes, that's right. I'd say the team deserves credit for the investment decision they brought to the Board. We built in a sizable contingency. It has turned out to be suitable and solid, and we expect to come in within the $380 million.
Matt Greene
analystPerfect, that covers everything I had.
Operator
operatorDaniel Morgan of Barrenjoey has the next question.
Dan Morgan
analystI'll start with Ernest Henry. From what I see in your latest update, copper output is set to fall to 55,000 tonnes and then to 50,000 tonnes across the coming 2 years, if I'm reading that correctly. I'm curious about the cause — is it a matter of tonnes or of grade? And does it tie in at all to the cave reorientation you're carrying out? It might also be helpful to restate just what that cave work involves.
Robert Fulker
executiveDan, this is Bob. A couple of points. First, the cave’s shape is in fact changing as time passes. As a result, the count of draw points available and active phases available is going down as time passes. That is also partly why reorienting the cave, or changing its orientation, is beneficial for productivity, because we move from — and these figures aren’t exact, so treat them as indicative only — we move from roughly 14 to 18 draw points per level back up to the 25 to 30 draw points per level the cave had 3 or 4 years ago. So once you genuinely raise the number of active headings available, you can genuinely bring tonnes per draw point back up again, since draw point turnover rises. So over the next year or so, the tonnage regime depends somewhat on that. The other thing from where I sit is simply the grade and the hardness as we pass through the various zones in the cave. Grade shifts a little, not much, but this is simply a direct result of that.
Robert Fulker
executiveAgain, the model itself isn’t the problem. The models are going to be solid, and I’m quite eager about what we’ll be discussing in August.
Dan Morgan
analystAnd finally, Jake, valuations in gold mining have really been compressed lately. Given that this company has historically had better access to capital than a lot of others, does that create a chance to strengthen the portfolio? Or will the coming 12 months be far more concentrated on the various asset turnarounds now underway?
Jacob Klein
executiveDan, that's a fair question. Look, I'd say asset prices have taken a real hit. When we issued that release, I personally bought shares in Evolution — that shows how much faith I have in this company and in what's ahead. The fact is, we've got to accomplish both things. We committed ourselves to operational delivery last year. We understand that's the key to opportunities. But certainly, in a stressed market such as the one we're in, where capital is hard to come by, we are seeing opportunities arise and we'd like to be positioned to seize them, while keeping in mind that we must make sure investors feel confident that our operational predictability and delivery remain on track.
Operator
operatorThe following question is from Mitch Ryan with Jefferies.
Mitch Ryan
analystTo pick up on what Dan asked about Ernest Henry and that reduced copper portion — I was wondering whether that also stems from you placing more emphasis on the mine's wider economics rather than, say, under Glencore's management, where the main focus was on the copper. Or is that something that could unfold over a longer time frame and simply wasn't part of the '23 guidance?
Robert Fulker
executiveMitch, I’ll do my best to respond, and then I’ll pass it over to Glen too. What we’re seeing is gold recovery that’s stronger and better than what Ernest Henry has delivered in the past. Copper recovery isn’t being impacted in any way by that. So in effect, we’ve been able to raise gold recovery while leaving copper recovery unaffected. That therefore isn’t something that plays into that calculation. Glen?
Glenton Masterman
executiveAnd I think too, Mitch, what we're observing in these kinds of mineral systems—copper, gold—is that grade tends to be fairly uniform across the ore body. But with our infill drilling, we are seeing a bit of heterogeneity among different domains that carry different grades. So that will be reflected in the mineral resource model we have scheduled to release on August 1. We'll then be in a position to speak to some of these insights, I suppose, that we're developing as a result of this work.
Jacob Klein
executiveTo wrap things up, I'd add one point: during due diligence, the data room showed 60,000 tonnes per annum for the coming couple of years. Based on what we saw at the site, we brought that down to 55,000 and 50,000 tonnes. If you went back to Glencore and asked whether those 60,000 tonnes were deliverable, they'd tell you their expectation was that the site would push and could hit that figure. We've taken a conservative approach. As Bob puts it, it's a budget and a forecast that's biased toward delivery.
Mitch Ryan
analystMy second question is mainly for Glen, and it concerns the revised MROR at Ernest Henry. Looking at Figure 3 among those planned drill results, I take it that figure won't be telling us that. When are we going to — when should we expect those kinds of numbers to come out to the market, or any assays from them?
Glenton Masterman
executiveRight, Mitch — those will begin showing up during September, then largely finish in the December quarters. So the underground drilling results we’ve finished since the cutoff date for the MR update — at this stage it’s purely a mineral resource update that we’re preparing. The OR gets refreshed at year end, in our annual year-end statement. In addition, we’re drilling from service right now. Two rigs came back in April. The aim is to achieve a better angle of attack on the ore body. What we’re observing in the mineralized footprint is that it’s actually somewhat bigger than what we’ve modeled so far. That’s a positive result from the surface drilling. And that’s roughly grounded in visual estimates we’re able to make, given the copper distribution visible in the call. But look, we want to hold for those results. As I mentioned, we’ll be in a position to release them across the coming couple of quarters. The mineral resource update we’re finalizing will include approximately 35,000 meters of new drilling.
Glenton Masterman
executiveSo it doesn't really reflect the surface work, or, as I mentioned, the underground work from June or May onward. Still, a good amount of fresh data feeds into that model update, and it will shape the result we put out to the market on August 1.
Operator
operatorThe question after that is from Peter O'Connor of Shaw and Partners.
Peter O'Connor
analyst<<inaudible>> getting pumped for August 1st — Jake, I'm really pumped, since I know Rob, and I want to pivot back to what Dan said regarding valuation. Let me just ask: could you work into that some thoughts on purchasing your own equity? So buy versus build versus buying Evolution's, as you've laid out what you're doing. And just a buyback, broadly speaking, for Evolution.
Jacob Klein
executiveRocky, I think — I mean, our capital commitments are set up so that we're putting money into growth through those opportunities at Red Lake and Cowal. So a buyback, I don't think, is something that's on the horizon for us. I mean, we have to get through this phase of growth and capital, and then we'll see what happens. But over the next couple of years, a buyback from us isn't something you'll see. We're leaving that to other investors. I mean, just to flag — I mean, there's one question I was hoping to get, and maybe it'll come out in the next couple of questions, but on Page 6 of our full year report, just to flag the improvements being made at Red Lake. You can see the tonnage coming up. This is a mine where we produced 43,000 ounces in the first half of this last financial year. And then we've done 33,000 ounces and 38,000 ounces. And you can see the tonnage, the grade and everything going up. So the transformation is really happening at Red Lake. And I think it's worth just emphasizing that and getting people — we're looking forward to taking investors there in September, and that will allow us to showcase the real changes that are happening at Red Lake.
Jacob Klein
executiveWith any luck, that journey is one you'll get to take.
Operator
operatorThe following question is from Troy Wilkinson with <<inaudible>>.
Troy Wilkinson
analystI'm not certain which of you is in the best position to take this — perhaps Bob, or perhaps Lawrie. Broadly speaking, on exposure to U.S. dollar costs, if there is any, and on supply chain matters, especially perhaps where chemicals are concerned for the mining process: are you observing any problems there? Or, if you are, is the situation getting better? Just some sense of the outlook regarding the supply chain.
Lawrie Conway
executiveYes. Thanks, Troy. On that first question, I mean, as we see it, looking at FX exposure right now, on the Australian assets we're still observing that our direct exposure is 15% of costs tied to the U.S. dollar. So yes, that comes to a few million dollars annually. It isn't material in the bigger picture when 50-plus percent of our cost is labor. And then looking at the Red Lake operations, we're kind of seeing that they cost more, with around the 90% mark tied to Canadian. So again, not much exposure there relative to the Aussie dollar. On supply chain, luckily, right now we haven't had any major problems at any of our operations when it comes to supply and delivery of chemicals, reagents, consumables. That's something the site teams and the group supply team have really been working on for the last couple of years, since the pandemic began and now with the inflationary market we're facing, making sure we have adequate levels on site and alternatives in place. So luckily, at present, we aren't seeing any issues with the supply chain.
Operator
operator<<operator_script>> Our following question is from Jim Pollock of Surbiton Associates.
Jim Pollock
analystMorning, everyone. I’ve got one or two questions about Mungari. Regarding the numbers you provided for Mungari, you stated the recovery rate was — let me see, my handwriting is hard to read — 72.5%. But when I worked it out, I got much nearer to 80%, 8-0 percent. What explains that gap? And would it be because of a Rand Tribune effect?
Jacob Klein
executiveJim, could you show us where that figure is coming from?
Jim Pollock
analystSo, if we take a look...
Jacob Klein
executiveThe recovery rate stands at 92.5%.
Jim Pollock
analystRight. But when you calculate it using the tonnage of ore mined, the grade, and the gold that came out of it, I get a recovery figure nearer to 80%.
Jacob Klein
executiveCorrect, that reflects the EKJV effect. So while all of the material is being processed, what we book is the gold production attributable to us, along with the applicable recoveries on that gold — on the entire gold amount.
Jim Pollock
analystRight, okay. So we're talking about total tonnage, and the grade is stated — but that roughly 35,000 ounces of production, that's just your portion, correct?
Jacob Klein
executiveYou've got that right.
Jim Pollock
analystRight, okay. Sounds good. Great. We'll see everyone at Diggers.
Operator
operatorThat brings us to the end of the question-and-answer portion. I'll turn things back over to Mr. Klein now for some closing comments.
Jacob Klein
executiveThanks, everyone. As I mentioned, this is a quick commentary and call to bring you up to speed as of the 27th of June. We've got a very busy stretch of months coming up. The Ernest Henry mineral resource update is scheduled for the 1st of August. A site visit at Mungari takes place on the 2nd of August. On the 18th of August, our full year results come out. Then in September there's a fantastic chance for anyone who wants to see what's going on at Red Lake, since it truly is a seeing-is-believing story — a September site visit, the first chance we'll have to bring Australian and North American investors along and show off the changes made at site. Thanks very much. We hope to see you at Diggers.
Operator
operatorThat brings today's conference to a close. We appreciate everyone joining us. You're free to disconnect at this time.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Evolution Mining Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Evolution Mining Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Evolution Mining Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.