Evolution Mining Limited (EVN) Earnings Call Transcript & Summary
October 17, 2023
Earnings Call Speaker Segments
Operator
operatorAppreciate everyone being on the line. Welcome to the September 2023 quarter results call for Evolution Mining Limited. <<operator_script>> At this point I'll pass things over to Mr. Peter O'Connor, who serves as General Manager, Investor Relations. Over to you.
Peter O'Connor
analystThanks, Rachel. Good morning, everyone, and welcome to today's conference call with Evolution Mining. As Rachel mentioned, I'm Peter O'Connor, General Manager of Investor Relations at Evolution Mining. We've lodged 4 announcements today on the ASX platform. First, the September quarter FY '23 quarterly production update, an exploration update covering Cowal, Mungari and Ernest Henry, and also our annual report for FY '23 and our sustainability report for FY '23. Four members of our leadership team from Evolution Mining are joining the call today to speak specifically to the first 2 of those announcements, the quarterly update and the exploration report. Joining us are our Chief Executive Officer and Managing Director, Lawrie Conway; our Chief Operating Officer, Bob Fulker; our Chief Financial Officer, Barrie van der Merwe; and our VP of Exploration Discovery, Glen Masterman. With that, Lawrie, over to you.
Lawrie Conway
executiveThank you, Peter, and good morning to all of you. We're grateful you could be with us today as we walk through the September quarter results, which were released on the ASX this morning. Before we get into how we performed during the quarter, I'd like to say something about where the gold price stands right now. There are, as we're aware, numerous factors that move the gold price, and geopolitical unrest is among them. Having said that, the continuing situation in Israel, which is helping push the gold price higher, is one of those drivers that leaves us feeling uncomfortable. The civil unrest and atrocities bringing such devastation to so many people, including the loss of life, is deeply saddening, and we sincerely hope this situation can be resolved promptly. Because of that, we feel somewhat more subdued about the benefits we're getting from today's higher spot gold price. During the June quarterly and our full year financial results, I set out that we are working to close out FY '23 in a way that positions us to deliver better results and improved financial performance in FY '24 and beyond. In the September quarter, we have been tracking to that plan. On the sustainability side, our recordable injury frequency fell further, to 8.3, which extends the trend seen across recent quarters.
Lawrie Conway
executiveDuring the quarter, we also verified that our emissions for FY '23 had been cut by 11.2% relative to the FY '20 baseline. That puts us firmly on the path toward our target of a 30% reduction by 2030. As the first quarter closes, we continue to expect to meet our guidance of 770,000 ounces at an All-in Sustaining Cost of $1,370 per ounce, plus or minus 5%. We anticipated that Q1 would be a period of lower output and elevated costs, given several factors: the ramp-up at Ernest Henry, scheduled shutdowns at multiple processing facilities, and the use of lower-grade material, including some stockpile material carrying higher noncash inventory values. In the quarter, output came to 158,000 ounces at an All-in Sustaining Cost of $1,612 per ounce. Through the remainder of the year, production will rise as we reach more higher-grade material at Cowal and Red Lake, and AISC will trend downward. Bob will walk through operational performance shortly. On the financial side, we delivered operating cash flow of $280 million, at a rate above $1,700 per ounce. That represents a 42% gain versus the June quarter. It does, however, capture the benefit of Ernest Henry once again being the dependable cash contributor it was prior to the effects of the March weather event.
Lawrie Conway
executiveEvery one of our operations was cash positive before major capital, and together they produced $245 million, which demonstrates that the business is getting back to a stronger position on cash generation. That figure will grow further as the year progresses and ought to take us comfortably past the $1 billion annual rate. Should the spot price hold, cash flows will be materially higher once more and add further to our deleveraging of the balance sheet. Turning to projects, we made solid progress at the Mungari 4.2 project, formerly called the Future Growth Project, with the main EPC contract awarded in the quarter. That contract locks in more than 60% of the total project cost. More importantly, though, we have confirmed construction will stay within the original project schedule and budget, and the required workforce has been secured along with the associated accommodation. The project team held a kickoff meeting with the contractor last week, and activities will ramp up over the coming months. When we approved the project, we spoke about the potential to grow the resource base, targeting underground opportunities to support the ability to sustain for longer the 200,000 ounces per annum post-expansion production rate. Today, we announced some excellent drilling results from 2 new structures within the Kundana Mining Center at Genesis and Solomon.
Lawrie Conway
executiveWhat these numbers show is that we can be confident about the prospect of feeding higher-grade material to the expanded plant over longer stretches. Equally encouraging are the results from the underground mine at Cowal, where meaningful intersections between Dalwhinnie and Regal point to upside beyond the resource we already have. Glen will walk you through those results shortly, but what it does establish is that the organic growth opportunities we set out at our Investor Day carry considerably more upside, and we will keep working on them to further enhance the financial returns from the projects and the assets. I will now pass things to Bob for an operations update.
Robert Fulker
executiveThanks, Lawrie, and good morning, everyone. As Lawrie mentioned, our safety is trending nicely. Right now, all operations are focused on making further improvements through their safety improvement plans and on implementing an online critical control verification system. Production in the September quarter of 158,000 ounces was consistent with the previous quarter, and we expect quarterly production to improve through FY '24. Notable highlights for the quarter were Ernest Henry back to normal operation, operating mine cash flow improved to $280 million for the quarter, and the Mungari 4.2 Growth Project commenced and remains on schedule and budget. Turning to Cowal. Their cash flow improved significantly during the quarter, and we expect this trend to continue through the remainder of the year. The high-grade underground mine project is now in ramp-up phase to circa 1 million tonnes this year and will underpin the 18% lift in production. Capital spend is also forecast to be significantly lower. The significant achievement for the quarter was on the scheduled completion of the planned processing plant maintenance, the accommodation village becoming fully operational, and paste to delivered underground has commenced. In summary, Cowal has returned to a substantial cash generator for the group, generating $112 million in operating mine cash flow in the September quarter, combined with a reducing capital expenditure profile.
Robert Fulker
executiveErnest Henry remains on schedule to meet both production and cost guidance. As planned, the team has brought production back to normal operating levels, with 20,000 ounces of gold and 13,500 tonnes of copper generated during the quarter. Operating mine cash flow rose substantially, reaching $110.6 million for the quarter. In addition, they achieved record underground development — across both Evolution and prior ownership — with an impressive 3,114 meters finished in the quarter. That speaks to the site team's ongoing commitment to improvement. Future growth plans keep moving forward, and the Life Extension Feasibility study is still on track for delivery in the March FY '25 quarter. Turning to Red Lake, they remain on course to hit our full year guidance. September quarter production came in within the previously guided range of 15% to 19% of FY '24 production, and quarterly output should strengthen as the year goes on. Workforce reductions were carried out during the quarter so that headcount matches the production fleet requirements. That delivers an annual saving of roughly $12 million. Remediation work has advanced well, safeguarding future continuity from the Cochenour mine. The work program shown in the figure on Page 5 of the September quarter sets out the immediate fix for the #3 PASS along with the near-term fix of the raisebore #4 PASS.
Robert Fulker
executiveCompletion of this PASS is planned for the December quarter. Down the road, the ramp breakthrough is going to offer another option for hauling ore as well as for mine access. Happily, All-in Sustaining Cost came down 16% versus the prior quarter, giving an AISC of $2,552 per ounce, and the underlying cost is trending toward improvement — sorry, the cost trend is continuing to improve. We're still on track to hit the FY '24 AISC guidance of AUD 2,000 per ounce. One big highlight this quarter was the substantial gain in operating mine cash flow, which reached AUD 27 million. That marked the strongest operating mine cash flow in nearly 3 years. To wrap up, Red Lake has rightsized its workforce, produced positive operating mine cash flow, tackled the near-term haulage constraints, and stays on track to achieve FY '24 guidance on both production and cost. Mungari's output is tracking toward this year's guidance. The September quarter came in as expected, reflecting lower ore availability while the Paradigm mining hub ramped up. Mill throughput was sustained by processing stockpiled ore. Over the coming quarters, we'll see better production and less stockpile ore processed, which reverses a noncash inventory charge recorded in the September quarter.
Robert Fulker
executiveWe anticipate that the new Paradigm mining hub will reach full ore production in the December quarter, and it will help drive the higher quarterly output at Mungari. Mt. Rawdon is tracking toward its FY '24 production guidance and turned in steady output during the September quarter. Those assets keep adding meaningful value to the group, producing $8.2 million in operating mine cash flow. To sum up, we are still tracking toward our FY '24 production guidance and our All-in Sustaining Cost guidance. The September quarter came in as we expected, reflecting the return to normal production at Ernest Henry and planned maintenance work across a number of the operations. On a positive note, every operation was cash flow positive at the operating mine level before major capital, with $245 million generated. Thanks for your time, and I'll hand things to Glen for an exploration update.
Glenton Masterman
executiveThanks, Bob, and good morning, everyone. I want to point you toward the exploration news we put out this morning, which lays out some exciting, high-grade drill results from Mungari and Cowal. Those results point to the possibility of added high-grade mineralization beyond the non-mineral resources close to the active mining fronts at both operations. At Mungari, the numbers back up how we go about finding and defining more high-grade underground ore to underpin planning for expansion from 2 million to 4.2 million tonnes per annum, which puts the site in a position to grow its mineral resources further. The Cowal results widen what the underground mine could deliver and show clearly that our priority is steady, dependable higher-grade underground output over the years ahead. Starting with Mungari, please look at Figure 1 in this morning's ASX announcement, which shows how the Genesis and Solomon veins sit in relation to the Christmas vein, where the bulk of our underground production at Kundana comes from today. Today's drilling results verify that Genesis is the next high-grade find at the Kundana Mining Center. It's encouraging that we have already reported output from along the Genesis structure, among it a stope that reconciled above 17 grams per tonne from the area we showed to those of you who could join our Mungari tour during Diggers and Dealers in August.
Glenton Masterman
executiveIf you remember that site visit, there was the ore drive we walked through and examined, with high-grade <<inaudible>> visible along the side walls and in the backs. Our geological understanding has moved forward, and it now backs up what we interpreted at the time — that we were positioned at the very top of the vein structure, roughly 500 to 600 meters beneath the surface. That helps explain why Genesis stayed hidden from us for so long, and so does the fact that the bulk of earlier drilling was done from the footwall side of the mine and stopped before reaching where Genesis sits. Our site geology team has moved away from the geopolitical dogma assuming that the centenary and stress laking main vein structures were the sole hosts of high-grade mineralization at Kundana. Our geological work shows there are additional mineralized structures, not known before, located in new geological positions with substantial strike and depth potential. We are excited about the growth and life-of-mine prospects at Kundana, with more drilling planned this year, aimed at expanding mineralization at Genesis and Solomon while continuing to extend the same drill holes to infill the Christmas resource for conversion to reserves.
Glenton Masterman
executiveAt Cowal, we’re genuinely glad to be able to share the new underground drilling results, and they line up very well with the drilling update I discussed during our Investor Day in June. Please see Figure 2 in this morning’s announcement, which shows where these new results are located; they have stretched the Dalwhinnie and Regal ore bodies across the Gap Zone toward one another. The Gap Zone—which, in line with the St. SingleMalt theme, we will rename shortly, as we have done with our other underground ore bodies—is among the underground areas that are still very under-drilled. As we extend drilling coverage into this space, there is strong potential to link Dalwhinnie and Regal across it. We are also getting some quite encouraging results from our close-based, or definition, drilling in the areas prioritized for early production in the underground mine schedule. Our best example is at Galway, where we are generally seeing higher grades from slightly smaller ore volumes, for overall higher metal reported entirely within the ore reserve. Finally, I would like to note that underground drilling restarted at Ernest Henry during the September quarter. 2 rigs are operating at present, with initial drilling aimed at the down-plunge extension of the Bert orebody, as well as possible extensions to the Ernie Junior orebody.
Glenton Masterman
executiveI’m eager to share fresh results with all of you once we’ve wrapped up the December quarter. With that said, I’ll now pass things over to Barrie.
Barrie van der Merwe
executiveThanks, Glen. <<inaudible>> delivered robust cash flow during the quarter, supported by Ernest Henry getting back to normal operations. Every operation added positively to operating cash flow of $280 million and mine cash flow before capital of $245 million, which rose 42% and 98%, respectively, versus the prior quarter. Net mine cash flow went back into positive territory, an improvement of $176 million from the last quarter of FY '23. Group cash flow got better by $69 million, or 72%, an outflow of $26 million for the quarter. As Lawrie laid out, our production is set to rise and our AISC per ounce will fall further as the year goes on. That will produce even stronger cash generation across the remaining quarters, keeping us on track to cut net debt in FY '24. We're very pleased that group AISC per ounce fell 16% to $1,612 per ounce quarter-on-quarter. The drivers were Ernest Henry being back at normal operations and Red Lake coming in lower, thanks to higher ounces sold, partly offset by the Canadian dollar being slightly stronger than Q4 of FY '23. Mungari rose quarter-on-quarter, driven by extra costs from noncash or stockpile drawdowns to mitigate the slower ramp-up at Paradigm.
Barrie van der Merwe
executiveThat isn't something we anticipate happening again, since Paradigm will be running at full mining rates during the December quarter. Keeping costs under control stays a major priority for us, and our cost guidance for the full year, at $1,370 per ounce, is unchanged. As Lawrie said earlier, capital intensity is coming down, and our capital expenditure guidance sits roughly $117 million below last year. Capital expenditure for the quarter came in $60 million under the prior quarter, reflecting lower capital intensity as well as the timing of spending at Cowal and Ernest Henry in FY '24. With the Mungari 4.2 project ramping up over the months ahead, capital expenditure will rise above current levels, and that lines up well with the stronger cash flow we expect later in the year. Our full year guidance of $450 million to $490 million for major capital and $190 million to $230 million for sustaining capital is unchanged. In August, we finished the debt restructuring that we announced at our Investor Day in June. We did this to match our debt maturity profile with lengthening mine lives and to give us financial flexibility for shareholder returns. In August, we brought in USD 200 million from our latest U.S. Private Placement, which is repayable in equal parts in FY '34 and FY '36, respectively.
Barrie van der Merwe
executiveThat restructuring left our gross debt position untouched, and no repayment obligations come due before the quarter ending December 2024. Following our USPP issuance, 10-year U.S. treasury yields rose roughly 100 basis points, reaching approximately 4.6%, not counting the margin spread. Our average cost of debt sits at 4.8%, with an average tenor of roughly 7 years, which is quite favorable. We hold $504 million in available liquidity, and the committed $525 million revolving credit facility remains accessible through October 2025. Having paid the $38 million interim dividend in October, and with production continuing to ramp up throughout the year alongside a robust gold price and lower capital intensity, our expectation and commitment to deleverage the balance sheet is still well on track. I'll now return the call to Rachel to open the lines for questions. Thank you.
Operator
operator<<operator_script>> The initial question will be from David Radclyffe of Global Mining.
David Radclyffe
analystStarting with the just-released reports about Glencore apparently planning to shut down production at Mount Isa — my first question is about that. From what I gather, the smelter isn't impacted, and perhaps you could confirm that, plus you already have a mine gate arrangement in place. This is all quite fresh news. Still, putting you on the spot, I'd like to hear whether you see any possible effects on Ernest Henry, or perhaps opportunities. For instance, could greater labor availability turn out to be a positive? Is there anything around tolling that might present an opportunity?
Lawrie Conway
executiveThanks, David. Yeah. So, on Glencore's plans at Isa — first of all, our offtake agreement covering Ernest Henry's life of mine already includes provisions that apply if the smelter does close, and those essentially still oblige them to take the concentrate and put it into smelters, with freight rates and all other terms already settled. On the second part, clearly there'll be a redeployment of people there that Glencore will consider, but it does mean people will be available, and if any of that matches what we need at Ernest Henry, we'll certainly take a look. And then the last piece: does it create opportunities for us around toll treating and similar arrangements — we know we have capacity at the plant. We do hold some contracts with Glencore under which we toll treat on campaign at present. But if that opportunity does arise, which would obviously help with processing costs, that's something we'd have a look at.
David Radclyffe
analystThen perhaps, to follow up, could you give us a bit more detail on how the capital spending shapes up for the year? I realize you're just one quarter in, so it's still early, but on an annualized basis it appears you're tracking below guidance on both growth and sustaining capital. Clearly, Mungari spending is still ahead, yet everything else seems to be somewhat under as well. So is this simply a matter of managing spending to align with anticipated stronger second half cash flows? Or might you in some cases actually be running below the anticipated run rates?
Lawrie Conway
executiveYes. So, David, if you look at it, sustaining capital over the course of the year doesn't move around too much, as you'd expect. So, it gets rushed through in Q4 to finish all of last year's, and because of that, there's a slower start-up in Q1. As we move through Q2, Q3 and Q4, it will be higher than what we saw in Q1, but still within the range, as Barrie said, of the $190 million to $230 million. Then when it comes to major capital, it really does come down to the expansion project at Mungari, where a lot of that activity comes into -- the back end of Q3 and into Q4. So, you'll see Q2 similar to Q1, Q3 increased a little bit, and then Q4 will be the biggest quarter as the Mungari plant expansion works expand, which then also lines up to the hedging that was put in place that are in the second half of this year, leading into next year to cover for that capital as it comes on.
Operator
operatorThe following question is from Andrew Bowler at Macquarie.
Andrew Bowler
analystThis first one’s likely for Barrie. I’m seeing the $47 million working capital movement, and some of that came from accounts receivable tied to Ernest Henry recon. Now that Ernest Henry is running at full capacity again, has that fully normalized? Or is there still some normalization left for next quarter? And could you also give us an update on the stamp-duty timing for Ernest Henry?
Barrie van der Merwe
executiveYes, absolutely, Andrew. Regarding what drove that working capital outflow, part of it involves the Ernest Henry debtor — and with that pipeline full once more, Ernest Henry is back to normal operations. So that working capital absorption has already occurred. Most of it, really, was creditor payments tied to CapEx we incurred in Q4 of last year. We had fairly heavy capital expenditure in <<inaudible>> quarter that got paid. That explains the $47 million outflow. If you look at it across the year, as we move into the Mungari project and, as Lawrie mentioned, as CapEx ramps up, you'd see the working capital position ease back somewhat again. So we'd expect that $47 million to improve modestly as the year progresses. And then, on stamp duties, we don't have any timing on that. It will come through when it comes through. But as things stand, we haven't been notified of any of it.
Lawrie Conway
executiveAndrew, let me add a bit more on Ernest Henry. The way to think about it is this: in the June quarter, there was basically no production at all. So receivables sat very low. Now as we move into this quarter, that's when it builds back up. Receivables rose by more than $25 million, because with Ernest Henry's cash flow, they don't carry working capital — they use a notional cash flow. So the net of that is what would have occurred in the quarter. But at this point, with full production restored, the receivable should more or less flatten out, depending on the copper price. I'd also note that the working capital outflow at the group level for the year — for the quarter, I should say, the September quarter of last year — came to roughly $30 million, $35 million of outflow, while the total working capital movement across the year was a positive $20 million. So you should expect working capital to move up and down each quarter depending on where we're at. Over the full year, though, working capital doesn't move a great deal in material terms.
Andrew Bowler
analystAnd the final one from me concerns the drilling results at Kundana. Clearly, there are some quite useful results at Solomon and the Genesis load. Lawrie, I believe you said earlier that this provides somewhat greater clarity on underground grades over a longer period. But is there any possibility of raising production level by level — or rather, increasing output quarter by quarter as time goes on and you begin moving into those areas? Or are the Kundana mines constrained when it comes to haulage capacity, meaning those additional loads would result in extensions to mine life rather than a production increase over the medium term?
Robert Fulker
executiveAndrew, let me try to respond to that. Output at Kundana will likely hold steady, which means we'll gain added mine life, since we factor in both the mining sequence and the orebody's actual profile—that is, its geometry. So my expectation is not that this raises the current instantaneous output or the annual output, but rather that it extends the duration.
Operator
operatorOur following question is from Levi Spry of UBS.
Levi Spry
analystThis one might be for Bob. Could you give us some sense of how matters are moving along at Red Lake now that roughly 6 weeks have passed? And perhaps remind us what the profile looks like for the rest of FY '24 — tonnes, grade, that sort of thing?
Robert Fulker
executiveYes, Levi, like we mentioned in the report, we've in fact brought the alternative parts in for Cochenour. That has raised the ore flow security at Cochenour. A second path is in progress right now, and it will improve the security of the Cochenour ore flow even further. Both of those will secure the remainder of the year and make sure we raise our production across the year. It's heavily weighted toward the back end of the year, as we've announced before. We also ran a trial in the Upper Campbell area of our <<inaudible>> area, as we noted in the announcement too. And it came through quite nicely. So that proves the theory of bulking at a somewhat lower grade mining block. So those 2 went well. Development is beginning to pick back up again. Broadly speaking, I think we're on track.
Levi Spry
analystAnd perhaps just one more thing to follow up on Dave's Glencore question. So from what we understand, those mines are shutting down — is that correct? Might there be a chance for you to acquire some assets there, or run some assets that still have useful life under a different operator, given that you seem to have a solid relationship based on how things have played out at Ernest Henry.
Lawrie Conway
executiveYeah, Levi, the way I see it, we hold the strongest mine in the area with Ernest Henry. And if it's shutting down owing to grades and costs, then I doubt there's much chance for us to shift our focus elsewhere from Ernest Henry.
Operator
operatorDaniel Morgan from Barrenjoey has the next question.
Dan Morgan
analystLet me start with the first question, team, on Cowal, because the commissioning of the paste plant looks a bit slower than I had expected. Could you outline any issues you may have encountered during the quarter? And have those now been resolved? And are you delivering paste reliably?
Lawrie Conway
executiveYes. Thank you, Dan. I’ll pass it over to Bob. We did commission it during the quarter, and with plants like these, you have to work through that commissioning and some teething issues, which we have had. But when we consider it for the year, it will still ramp up consistent with the production ramp up. But Bob, perhaps you could just discuss the plant?
Robert Fulker
executiveThanks, Lawrie. Dan, like Lawrie mentioned, we did place first paste underground during the quarter. We've been working through the commissioning. As happens with paste plants, we ran into some quality and throughput issues both ore, which are fixed now. We're getting good-quality paste underground, or the actual UCS sampling is coming back well. So, paste is continually based.
Lawrie Conway
executiveWe also anticipate reaching 1 million tonnes from the underground, as further planned, over the course of the year.
Dan Morgan
analystAnd regarding Red Lake — while we were on site, a seismic event occurred, which you did mention during the quarter. I just want to confirm that production isn't still being affected by that event. Is it fairly isolated?
Robert Fulker
executiveThat seismic event that took place while you were on site still has one part of the R Zone under an exclusion, and we anticipate having that lifted sometime this month, or if not, at the start of next month. It was a pretty sizable event. So getting back in there has taken us some time. In situations like this, our preference is to be cautious and ease back in gradually, and we're working around that. John and the team, in fact, have plans in place to work around it, and that's exactly what they're doing.
Dan Morgan
analystMungari, you're starting up the Paradigm open cut. Could you say a bit more about how the grade from there will look across the year?
Robert Fulker
executiveParadigm sits somewhat farther out from the processing hub. Because of that, the pit's average grade runs higher than we've seen previously. I'm trying to recall precisely what the — Glen, do you remember the resource grade? 1.5 — in my recollection it was 1.5 or 2 grams, roughly that, Dan, that was the actual resource growth we were mining. Right now we're getting some good grades out of it.
Dan Morgan
analystSo it's fair to say that at Mungari, we ought to expect better grades in the coming quarters, and that should raise the production profile as the year goes on?
Robert Fulker
executiveAbsolutely.
Lawrie Conway
executiveYeah, Dan — for the rest of this year's quarters, I'd figure the Paradigm grade lands around 1.8, give or take.
Robert Fulker
executiveAnd keep in mind, Dan, that low grade stockpiles were processed by us over the previous quarter.
Dan Morgan
analystAnd sorry, coming back to that Glencore topic, could you remind us again how the offtake arrangement works alongside your treatment charges? At present, is it the mechanics or the financial side of things such that a smelter shutdown would not create an impasse — or is it structured so that, I suppose, you are already sending it implicitly to Asia on the financial side? That's really what I'm trying to ask.
Lawrie Conway
executiveYes. That’s a good question, Dan, because the way the offtake works means you don’t receive the full advantage of avoiding shipments into Asia. So your treatment and refining rates are basically set on a hybrid basis between Australia and Asia. So there isn’t a material change there. And the other thing that would shift is that, through the government, you actually do get a benefit on royalty, since it’s treated and refined in Australia. So your royalty would go up. But those 2 items aren’t material. And as I understand the announcement, there’s a commitment for that smelter to remain open until 2030 — that’s our understanding.
Operator
operatorMatthew Frydman of MST Financial has the next question.
Matthew Frydman
analystLawrie and team, perhaps I can just pick up where the questions about MIM left off. I believe it was Levi who asked about, I suppose, the mines themselves and whether there’d be any interest there. But maybe, more broadly, are there any tenements or assets — infrastructure assets or otherwise — that could potentially be interesting to you in time? Maybe anything that might help to derisk Ernest Henry’s future or, I guess, give you further options at Ernest Henry specifically?
Lawrie Conway
executiveYeah, Matt, I'd say it's a little soon to go that deep into the specifics. Like I mentioned before, Ernest Henry is the one we view as the best fit for us. If anything of that kind comes up at the asset level, nothing there would appeal to us when it comes to other infrastructure and similar items. We'll simply watch how it develops, but nothing is top of mind right now.
Matthew Frydman
analystGoing back to Red Lake for a moment. You obviously mentioned the ore pass problems during the quarter, and as Bob walked everyone through, there's a fairly clear plan in place to fix them at Cochenour. Cochenour, of course, is perhaps a somewhat deeper and older part of the different production areas you have. Are there other places where you're aware these kinds of problems could crop up down the road — maybe the deeper sections of Red Lake — and how are you approaching that? Then, thinking about Upper Campbell, which clearly will contribute more to your output as the year progresses, that's plainly a shallower production phase. It involves a new mine design, new mine development, and obviously entirely new materials handling infrastructure. So should we expect that this part of the mine won't have — or won't be affected by — any of these kinds of problems, whether seismic or ore pass related? Is that a reasonable assumption?
Lawrie Conway
executiveI'll pass it over to Bob, Matt. Still, I think it's reasonable to say that regarding the ore pass at Cochenour, the genuine upside is how John and the team have handled it — building in the contingencies, but also the demonstration, as Bob mentioned, of the trial we ran with the low-grade stope to keep the plant supplied with ore that actually generates money, which kind of shows the change at the asset in terms of operating it better. And Bob will also speak to the Upper Campbell.
Robert Fulker
executiveThanks, Lawrie. Matt, I believe that single question actually contains three separate ones. I'll do my best to address them, but please don't simply repeat the same question. What separates the Cochenour ore pass from the Red Lake ore pass comes down to the geology and the rock types found in those distinct areas. In the Cochenour system, we incorporated future redundancy through the raisebore, and once a breakthrough happens, the decline will provide us with additional redundancy, and we'll keep taking that forward-looking approach to make sure it doesn't cause problems down the road. Turning to Red Lake, that one is actually deeper. We aren't experiencing the same problems with the ore passes there, even though we still have a number of raisebores to install. If you look back roughly 6 to 9 months, we discussed the ore pass problem we had at Bama, and we've designed the whole thing with a bypass to make that flow better and enhance the actual material handling. We also have a second ore pass, which will serve as the waste pass design and will improve the waste transfer too. So we have several improvements underway at the same time. Right now, the Cochenour one is the top priority, simply because we need redundancy in that system, and the Bama ones are in fact operating as we speak.
Robert Fulker
executiveWe simply want those to perform better. Regarding Campbell, it’s going to be a truck-based operation. So we have a 62 tonne truck there that can hoist a substantial quantity of dirt up through the decline. So it’s de-risked purely because it is — I’ll call it a conventional decline operation like we’d know in Australia, with the capability to move equipment around and to enhance production flow as we advance it.
Matthew Frydman
analystThanks, Bob — I believe you touched on all of it, so I appreciate that. Perhaps just one last thing, and this may be mainly for Glen, though it could be broader as well: regarding the drilling at Cowal underground in the Gap Zone, where you've already seen some early successes, how are you thinking about developing that underground area over time — specifically, would linking together all these various signals, and I suppose providing a fuller resource, change how you consider the mining methods you employ, and might you eventually look at shifting toward a more bulk underground mining approach? Obviously, there's a pit and a lake above, which does constrain things somewhat, but is that still a possibility as you keep exploring those underground areas? And could you also remind me when the open pit continuation study is expected, and what the current status is, please?
Glenton Masterman
executiveMatt, let me take the underground exploration part. Right now we're genuinely excited about the prospect of closing that gap and, with any luck, filling it with ore as we expand drilling coverage across that area. As for how we tackle it from a mining standpoint, I'd say everything you listed is on the table when it comes to folding this into the mine design we already have and figuring out what has to change to get the most out of the ore body. So the first step is grasping what the resource upside will be, nailing that down, and then building a design around it and working out how we optimize it into the plan. There's a good deal of work still ahead, I'd say. That said, I think as we drill there will also be chances to sequence things in a way that optimizes grade and production around those kinds of opportunities, and whether we approach it from the Regal side or the Dalwhinnie side, the work has to come first so we understand that part of the underground.
Glenton Masterman
executiveWhat we see, though, is significant potential for growth, and that will stretch the life of the mine beyond what our current plan assumes. I'll pass things over to Bob for the OPC.
Robert Fulker
executiveAlright, to wrap up on the Cowal underground. I share Glen's view on all of it. And from where we sit, what's genuinely exciting about the drill results we're seeing is the chance to lift the grade near term and extend how long the mine actually operates. So the underground itself is shaping up very well. On mining methods, as Glen mentioned, it's all of the above — we'll factor in the constraints coming from the open pits above, plus the lake protection bund itself and every environmental and social consideration that comes along with it. So all of those elements have to feed into the thinking. OPC is on track with the plan. Let me just recall — it was still 2 years, what, 20...
Lawrie Conway
executiveYeah. Matt, I'd say the project's main status right now is that every public display comment and piece of feedback has come in, and the team is working through those responses — we'll send our replies back out during this quarter, within the next couple of months. And after that, really, it'll be up to the regulator; we've budgeted at least 12 months to get through the regulatory process. But as Bob mentioned, it's at least 2 years before we reach that decision point on the project. There will, of course, be certain decisions on parts of the infrastructure and similar items over the next 12 months, but it all does <<inaudible>>, and the only other point is that, with what Glen is finding, it's going to need to be a high-quality single <<inaudible>>.
Glenton Masterman
executiveCould be a mix there, Lawrie.
Matthew Frydman
analystPerhaps there's a touch of <<inaudible>> in there, or something along those lines.
Operator
operatorAlex Barkley of RBC has the next question.
Alex Barkley
analystRegarding that $63 million in restructuring and nonoperating costs, largely capitalized at Cowal, I wanted to ask whether it falls outside the major CapEx guidance for FY '24. And what could that figure look like over the next few quarters?
Lawrie Conway
executiveYes. So Alex, essentially, at present you've got the underground mine in its ramp-up phase, and it isn't commercial production yet. Under the accounting standards, which have been revised over the past couple of years, you basically capitalize the costs. You no longer net them off against revenue. So, revenue from the underground will still flow through to the P&L, and you have to move the cost onto the balance sheet. So, as we guided at the start of the year, we expect commercial production to begin in the second half of the year. So, you should expect one more quarter in which the underground's costs go to the balance sheet and go to the P&L. And then from the -- and at December, Barrie and the team have to make an assessment of whether we have reached commercial production or not, and then we'll inform the market based on where we stand at December.
Alex Barkley
analystAnd just a quick question about Red Lake. I believe a whole-of-site study covering milling and mining was underway. Is there an expected date for it — perhaps something tentative?
Lawrie Conway
executiveMy apologies — let me restate that point.
Alex Barkley
analystRegarding Red Lake, I believe a study covering milling and mining across the entire site has been moving forward. Is there a date you expect for that?
Lawrie Conway
executiveYes. On that point, we had completed the work identifying what the alternatives would look like if we chose to exceed the 1.1 million tonne processing rate at the close of FY '23. However, since we've decided to hold Red Lake at 200,000 ounces and 1.1 million tonnes per annum for the foreseeable future, we're actually not pursuing that study at all, because it's probably at least 3 years before a decision on it becomes necessary, and we'll take another look at the study then. What it amounted to at the end was that it laid out several options for moving from the 1.1 million to 1.8 million, the capital that would be required, and how we would go about it. But right now, we aren't proceeding with it.
Operator
operator<<operator_script>> Our following question is from Al Harvey at JPMorgan.
Al Harvey
analystI just wanted to get some clarity on Red Lake — those ore pass problems are tied to the seismicity, so seismicity is what's causing them. I just want to confirm that. And if that's the case, what risk is there that PASS 3 and PASS 4 could run into difficulties as well?
Robert Fulker
executiveAl, several factors were in play there. First, the ground conditions the ore pass passed through. There was some activity in the wall of that ore pass, but it wasn't the same activity I mentioned at Bama — completely separate and isolated. The ore pass we're using now is #3, and the lower half has been ground supported. It's an old almanac rise, so it was ground supported at installation. We've put a small hole into the top of it — essentially a small raisebore-equivalent hole — to maintain that circular integrity. I don't expect the ore passes at Cochenour to last 10, 15 years; they'll last a shorter period than Bama, purely because of the rock type and geology. But if we can — or when we do get a raise, the intent is not to disturb the integrity of that circular opening, just to tip at the top and pull at the bottom, and not break into it anywhere in the middle of the ore pass, which is a different strategy from the past.
Al Harvey
analystAnd maybe just one quick thing, a very brief reference to drilling at Ernest Henry in the exploration release. You're drilling down depth at Ernie Junior and Bert and looking for results in the December quarter. Will we likely get those results separately, or will we probably see them with the December quarterly next year? And I guess I'm just wondering if you can remind us what's in scope for the Ernest Henry expansion feasibility study, and whether there's any potential for that to slip in there as an option?
Lawrie Conway
executiveThanks, Al. I'll handle that question. So, with the current drilling program, our plan is simply to provide a results update in January, which aligns with our usual December quarter reporting schedule. The reason I'd prefer to hold off on sharing those figures is to allow ourselves as much time as possible to get a clear picture of how the drilling program is progressing. That's the approach where the drilling program is concerned. As for the feasibility study, we're primarily examining the mine extension project we've discussed before, between 1,125 and 775. That's what the FS is centered on. Naturally, alongside that, we're beginning to develop <<inaudible>> the FS will mainly concentrate on that mine extension I just mentioned.
Operator
operatorThat brings us to the end of the question-and-answer portion. I'll now return the floor to Lawrie Conway, Managing Director and CEO, who will offer some closing comments.
Lawrie Conway
executiveThank you, Rachel, and thanks to all of you for spending part of your day with us. We genuinely appreciate the effort you made to be on this call. Before we wrap up, I want to restate what I said at the start regarding the present spot price and the effect of the situation in Israel — the genuinely hard period and the atrocities taking place there, which are touching many people, among them quite a few of our friends and colleagues in Australia. Our hope is that this can be settled sooner rather than later. We have had a good start to the year. We remain on track to deliver 770,000 ounces, and at $1,370 an ounce, our capital intensity is <<inaudible>>, as Barrie noted, $117 million below last year. Combining those factors with the higher gold price compared with what we actually achieved last year puts us in position, as we go through the remaining quarters, to generate stronger cash flow and to keep working on deleveraging the balance sheet this year. Thank you, <<inaudible>>.
Operator
operatorThat brings today's conference to a close. We appreciate everyone joining us. You're free to disconnect at this time.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Evolution Mining Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Evolution Mining Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Evolution Mining Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.