operatorWe appreciate everyone being on the line, and we're glad to have you join us for the Evolution Mining call covering results for the December 2024 quarter. <<operator_script>> At this point I'll pass the conference to Mr. Lawrie Conway, our Managing Director and Chief Executive Officer. Go right ahead.
Lawrie Conway
executiveThanks, Harmony, and good morning, everyone. I hope you managed to get some downtime over the holidays and wish you all the best for a safe, healthy, and successful 2025. Joining me on today's call are Barend Van Der Merwe, our Chief Financial Officer; Matt O'Neill, our Chief Operating Officer; Glen Masterman, our VP Discovery; and Peter O'Connor, our GM, Investor Relations. The December quarter results were excellent in that we delivered safely to plan, which materially lifted our cash flow by 54% to $165 million. At the halfway point of FY '25, we're ideally placed to deliver a significant step-up in cash flow versus last year. Safety performance during the quarter was a real highlight, with our TRIF reduced time to 5.44, and every one of our operations now has single-digit TRIFs. We remain on track to meet production guidance of 710,000 to 780,000 ounces of gold and 70,000 to 80,000 tonnes of copper at a very low all-in sustaining cost of $14.75 to $15.75 per ounce. Group production came in line with plan at just under 195,000 ounces of gold and 19,000 tonnes of copper.
Lawrie Conway
executiveFor continuing operations, our all-in sustaining cost came in at $1,543 per ounce, a bit above what we had planned, though the reasons are the timing of sales and a lower realized copper price. During the quarter, Cowal sales trailed production by 8,000 tonnes, and that will show up in the March quarter. The copper price we achieved was marginally under the assumption in our guidance, but spot is now trading above that assumed level. The charts on Page 1 of our report make it very clear how we are tracking on the key <<inaudible>> and on cash flow. We sit at 52% of the midpoint of group production gold guidance, while cash flows are running around 55% to 56%. At today's spot prices, operating mine cash flow for the year could potentially exceed $2 billion. Two key takeaways: this would deliver a mine operating cash flow margin of almost $2,700 per ounce. And the $200 million benefit shown on that chart covers only a 6-month period. Annualized, that means as much as $400 million more than where metal prices stood when we released guidance in August. Group cash flow rose materially to $165 million, which brought gearing down further to 22.6%, and our balance sheet keeps getting stronger.
Lawrie Conway
executiveOur projects also delivered outstanding results. The 4.2 processing plant expansion at Mungari is now set to be commissioned in the June quarter, roughly 9 months earlier than planned. The total project cost is expected to come in at approximately $235 million, 6% under the original budget of $250 million. With this project, everything that needed to go right has gone right. The mill's arrival at the HV substation in early December, the contractor's continued strong progress, and the mobilization of the open pit mining and all haulage contractors have come together to let the project move forward far better than originally planned. Delivering a project of this size and cost in Western Australia ahead of time and under budget is a genuine credit to everyone involved. With the plant commissioned in the June quarter, we expect Mungari to return to being a significant cash generator for the group. At Cowal in December, we obtained New South Wales regulatory approval to extend open pit mining by 10 years and the overall operation to 2042. We are grateful for the strong support we received from the local community and all the relevant regulatory bodies.
Lawrie Conway
executiveWe anticipate asking the Board to approve this project during the June quarter. The $366 million Cowal has generated in cash so far this year, along with $268 million in operating cash flow and net mine cash flow respectively, demonstrates the genuine worth of this asset, today and into the future. Yes, so let me restate what I mentioned last quarter. This asset remains a cash cow. Finally, we put out our exploration update today as well, with outstanding results. At Ernest Henry, following the recent drilling successes at the Bert orebody, we have now started a pre-feasibility study examining it as an additional ore source there. At Northparkes, further encouraging results have come in at Major Tom, and we have pinpointed a possible new ore source at the Cowal underground. We keep achieving success across our operations to feed the growth pipeline, and Glen will cover these in greater detail shortly. I will now pass things to Matt for an operations update.
Matt O'Neill
executiveThanks, Lawrie, and good morning everyone. Lawrie already mentioned it, but the second quarter was a solid one for us on production and cash flow, and I'm genuinely happy with where we stand. To me, the biggest highlight of our current position is probably how much safety has improved. Across the past 6 months, our recordable injury frequency rate has come down by 24%, from 7.1% to 5.4%, and I want to give a special shout-out to the teams at Red Lake, Ernest Henry and Mungari, who've driven meaningful gains here. As I said on the previous quarterly call, while I'm delighted with how our safety indicators have moved, we're still concentrating on leading indicators — things like critical control verifications and material risk actions — consistent with our continuing commitment to <<inaudible>>. In the December quarter we turned out a touch under 195,000 ounces of gold along with roughly 18,500 tonnes of copper, again tracking to plan. Cowal and Northparkes beat their plans for the quarter, while Red Lake, Mungari, Ernest Henry and Mt Rawdon were all broadly in line with plan. As I mentioned earlier, Cowal put in a strong production performance, and that operation is well placed going into the scheduled major shutdown in March.
Matt O'Neill
executiveThis shutdown is going to cost Cowal roughly 25,000 ounces in the March quarter. At Ernest Henry, output matched what we had planned. And the drilling results have stood out for a second quarter running, and Glen will speak to those later. Mungari, pleasingly, is back where it needs to be for the year, with the Rayjax pit producing at full capacity and early works now under way at our new Castle Hill pit. As I mentioned earlier, the expansion project is tracking very well — it's running ahead of schedule and under budget, with commissioning targeted for the June quarter. Northparkes delivered a strong quarter, with the highlights being the start of commissioning of loader automation in the block cave and the completion of improvement works in the crushing area. Red Lake, really pleasingly, matched plan and generated positive cash flow for a second consecutive quarter. During this quarter, we carried out our usual scheduled shutdown works at the processing plants and rebuilt surface stocks as planned. Mt Rawdon keeps processing stockpiles, and the team on site is working through that process well. I'm pleased to report once again that the outlook for the operations for the rest of the year is positive, and we remain on target to hit full year guidance.
Matt O'Neill
executiveAt this point I'll pass things over to Glen, who will walk us through the exploration results from the quarter.
Glenton Masterman
executiveThank you, Matt, and good morning to everybody. I want to direct everyone's focus to the exploration news we put out this morning together with the December quarterly report. As Lawrie mentioned before, we've gotten additional encouraging drill results from Ernest Henry, Northparkes and Cowal, and each of them points to the chance for incremental production growth in the future from a range of alternative ore sources. Over at Ernest Henry, the latest step-out drilling results at Bert, which are shown in Figure 1 on Page 2 of this morning's announcement, have pushed mineralization out to a minimum of 160 meters beneath the footprint outlined previously. We're now beginning to see how the Bert orebody could potentially align with other isolated copper farther down plunge, which opens up the possibility of adding future production and mine life. Infill drilling results from Bert are shown in Figure 1 as well. We've encountered robust gold and related copper grades, located high up within the Bert orebody and next to possible access points from the pit wall. The metal grades verify continuity of the higher-grade gold domain, and that's an encouraging result for Bert. A PFS is now underway to assess options for developing the Bert orebody separately from the underground materials handling system. Moving on to Pages 3 and 4 of the announcement.
Glenton Masterman
executiveWe're pointing to fresh drilling results from Northparkes, where the work centered on defining how the near-surface copper mineralization at the Major Tom and E51 prospects extends both sideways and at depth. At Major Tom, those results have enlarged the mineralized footprint and, in my view, have cemented the prospect as a future open pit opportunity. Mineralization begins within 40 to 50 meters of surface, and its lateral extent has grown to a scale comparable to the E31 open pits, with the mineralization still open. As it happens, Major Tom is copper dominant, sits in an ideal location on the mining lease, and lies within 3 kilometers of the processing plant. Drilling has also delivered additional results at E51, located 500 meters southeast of Major Tom. Our exploration team has done an excellent job disentangling the complex geology to sharpen our understanding of where mineralization occurs and why it occurs there. What we've learned has opened up an entire search space along the edge of the monzonite stock, which appears in pink in Figure 2. That geological relationship also comes through very clearly in Figure 3. Mineralization follows this prospective contact and has yet to be effectively tested over its full length. Our exploration team will keep pursuing this concept over the short to medium term, aiming to identify further near-surface open pit opportunities that can be brought in and along.
Glenton Masterman
executiveModeling of the geology and assay results is presently in progress to establish whether open pits at Major Tom and E51 can be optimized. That effort is anticipated to wrap up during the June 2025 quarter. When we provided our most recent exploration update at the close of the September quarter, we discussed a significant new exploration target identified at Cowal. As a quick recap, we drilled a hole in an area between the E42 open pit and the Cowal underground, where we think we were testing a separate repetition of the geological architecture that hosts mineralization in the adjacent underground mine. Figure 4 on Page 5 includes a small inset showing where the target sits. The key geological relationships that control mineralization are illustrated in the cross section. The contact between the pink-colored diorite unit and the sedimentary rocks around it closely resembles the geologic setting hosting gold mineralization in the underground mine. From the underground, a new hole was completed in the December quarter, and it confirmed this geological concept, hitting 2 significant gold intercepts, each of which is described on Page 5. This target excites me given its large-scale implications. It lies in an area where no exploration had been done before.
Glenton Masterman
executiveAnd if we draw a comparison to the nearby underground operation, there’s a strong geological rationale for the gold’s presence, and we believe that favorable architecture will continue both along strike and at depth. Separately, we have just finalized an arrangement with Rio Tinto Exploration to secure a 1,200 square kilometer land package plus exploration tenements around our Ernest Henry mine. That follows the Cloncurry North earn-in JV, and it now solidifies a substantial exploration portfolio with promise for future copper gold discoveries near Ernest Henry. I’m eager to be able to update you next quarter on the drilling progress currently underway at Ernest Henry, Northparkes and Cowal. I have confidence that we will keep growing and unlocking resource potential across these richly mineralized geological terrains around our operations. With that, I’ll pass things to Barrie.
Barrie van der Merwe
executiveThank you, Glen, and good morning to all of you. In the December quarter, the company produced substantial cash flow and set multiple new financial records. We're making strong progress on our deleveraging plan while also putting money into the business and boosting returns to shareholders, which you can see from the final FY '24 dividend of $0.05 per share that was paid out in this quarter; we achieved all-time record operating and net mine cash flow of $561 million and $263 million, respectively. As Lawrie and Matt described, this came from our production continuing to perform according to plan along with us capturing the advantage of elevated metal prices. Group cash flow of $165 million came in 54% above the September quarter. That cash flow contained a $27 million tax payment tied to the FY '24 return, which falls due every December. Tax payments during the second half will go back to $25 million to $30 million <<inaudible>>. Our cash balance rose by $36 million to $520 million after we paid $99 million in dividends and made a $15 million scheduled debt repayment. Gearing fell by another 1.3% to 22.6%. This marks the fifth quarter in a row that we have brought down our net debt, and at the same time we are lowering gross debt as scheduled debt repayments begin.
Barrie van der Merwe
executiveCost performance in the quarter carried on tracking nicely, with an AIC per ounce of $1,503, a modest improvement on the September quarter. That figure covers continuing operations, since Mt Rawdon is now processing stockpiles. We're in a solid position to hit full year cost guidance for AISC of $1,475 to $1,575 per ounce. Our disciplined stance on capital expenditure remains — we only deploy capital on projects at the point it's needed. The earlier commissioning of the Mungari 4.2 project will pull forward roughly $80 million of major project capital from FY '26, and the overall project is expected to land under budget. To support the accelerated mill ramp-up, about $25 million of major mine development capital will likewise be brought forward. So for FY '25, Mungari's major project capital will sit between $190 million and $210 million, while major mine development capital will be between $55 million and $70 million. Guidance for the rest of our capital expenditure is unchanged. Only $60 million of scheduled debt repayments remain in the rest of FY '25, with $28 million of that due in the March quarter. Given the very good first half to the financial year and ongoing cash generation momentum — including potential upside from the current gold spot price, which is roughly $400 per ounce above what we've achieved year-to-date — we are tracking very well to cut gearing to 20% or less by the close of FY '25, while simultaneously investing in the business and continuing to grow shareholder returns.
Barrie van der Merwe
executiveAt this point I'll pass things back to Harmony so we can begin the Q&A. Thanks. <<operator_script>> Our first question is from Kate McCutcheon at Citi.
Kate McCutcheon
analystGreat job on Mungari running ahead — maybe it’s a good market in which to sell a gold mine. I notice there’s CapEx for the mill and mine that has been pulled forward, and Barrie provided those updated figures earlier. Group guidance remains unchanged, I suppose. Are there any assets worth flagging that might be somewhat light on their spending this year?
Lawrie Conway
executiveKate, some of the sites will, yes—but as Barrie explained, every one of the remaining assets stays in line with the guidance we originally gave. And at Mungari, we're pulling that $80 million of additional project spend in '25 forward into mine development. When you consider where each of those projects stands, I don't think you'd assume the other projects offset that. All of them remain on track.
Kate McCutcheon
analystAlright, understood. So perhaps a question for Barrie regarding the financials coming up. Is there anything one-off or exceptional worth flagging? And on that net debt figure you gave, I just want to confirm it relies on the year-end FX rate for your U.S.-denominated debt?
Barrie van der Merwe
executiveLike we mentioned in the quarterly, the only adjustment is for the Edna May royalty, roughly $17 million. That amount gets written off, since the project has moved to care and maintenance and receiving that royalty is uncertain. Then on the debt side, the USPP debt is fully hedged. The debt figures we show in the quarterly are at the hedged rate of $0.715, so no debt revaluations will flow through the financial results beyond what's already in the quarterly number we reported. As a result, the debt figure will remain the same, and gearing will remain the same when we report the half year results.
Operator
operatorThe following question is from Levi Spry at UBS.
Levi Spry
analystTo pick up where Kate left off, on cash going forward: is there anything more you can flag for the coming 12 months? I'm thinking in particular about stamp duty, which we keep bringing up, and also the contingent payments tied to Northparkes. Beyond the $60 million debt repayment, is there anything else?
Lawrie Conway
executiveYeah, so on the stamp duty — there's still nothing on the one for Ernest Henry. So we'll hold off as long as we can on that. And as for the contingent, that gets assessed at the end of the financial year, with payment coming in the first quarter of next year. At the halfway mark, we're probably sitting somewhere between about USD 1.2 million and USD 1.5 million in contingent payment that would have been earned in the first half.
Levi Spry
analystRight, okay, yes — those are small figures. And on Mungari specifically, Matt, could you go into a little more depth for us? For instance, what does it actually look like at the site? What takes place during FY '26, given that commissioning lands in the June quarter? Clearly, we're likely pulling some output forward from other mines as it is. How fast are you able to feed the plant? And how would you describe the expected ramp-up?
Lawrie Conway
executiveI’ll take one part first, Levi, and then pass things to Matt, since those are really good questions. They’re the same ones I’ve recently put to Matt as the projects <<inaudible>>. As we see it, we’ll work through commissioning and ramp-up, and so, given that we are 9 months early, you should expect output to climb toward 200,000 ounces for next <<inaudible>> the period required for us to commission and bring things fully up to a 100% production rate. Matt, would you explain what we’re seeing at site?
Matt O'Neill
executiveYeah. No, I believe Lawrie addressed the commissioning window during the quarter. Regarding on-site, the main item we're working through is probably ensuring we have sufficient material to feed the mill. So with the pits progressing quite nicely, Rayjax performing well, Paradigm doing fine, and then Castle Hill — I visited there last week. Honestly, Castle Hill is beginning to resemble what it ought to as a long-term pit from which we'll keep producing. So when we go through all the various figures across operations, we have more than enough material for the early start-up. And during that stretch, across the first 2 years, we were building stockpiles, so there isn't much risk of running ourselves out of feed for that mill right now. Yes, as I mentioned, we'll determine, once the commissioning process is complete, how next year shapes up, but it's clearly fairly good news, and we'll see some uplift from it.
Levi Spry
analystYes, and let me add a little more detail on that point. I’m assuming that as the underground operation ramps up, it acts somewhat as a grade driver — how does that fit into the overall picture?
Matt O'Neill
executiveYou've got it exactly right. From an improvement standpoint, that's likely the main area we're focused on. We're where we need to be on that front and tracking as planned, though I do think there are opportunities, and Scott and the Mungari team are pursuing them — the underground is what lifts the grade, and that's where we're really concentrating our push. Arguably the most important thing we tackled during the last quarter was development and getting ourselves ahead of the game, and the team has performed really well. Development delivered a fantastic result last month, and that's what we need to keep moving so we stay in front there. So yes, you're right. Right now it's in line, but I'd like us to be a bit further ahead.
Operator
operatorHugo Nicolaci of Goldman Sachs has the next question.
Hugo Nicolaci
analystLet me ask a few quick questions, if I may. First, regarding Northparkes, I was just looking at the reduced underground volumes during the quarter. You mentioned that haulage was halted for 8 days. The effect on production appears larger than that single disruption would explain. Could you clarify whether this reflects a deliberate choice to prioritize high-grade open pit material, or whether any other problems arose during the quarter?
Matt O'Neill
executiveRight. The big disruption was the winder and the transformers at Northparkes. We took considerably more from the open pit, and that's clearly where the gold grade came from, so nothing else material there. The one small impact — and it wouldn't show up in the figures — I'd describe as tied to bringing the autonomous fleet online. During the first few weeks we ran into a couple of teething problems. Beyond that, nothing material affected that number for the quarter.
Hugo Nicolaci
analystGreat. Then just one more on Mungari. So, Matt, obviously congratulations to the team for coming in ahead of both the schedule and the budget there. In the past, you've spoken about the possibility of divesting that asset. With the improvement in performance there, are you more inclined to keep it in the portfolio? Or could it mean you're able to look at starting a process on that sooner?
Lawrie Conway
executiveI’ll respond for Matt here. My sense is that Matt has no desire to sell an asset. He has just completed construction of a new plant ahead of schedule and under budget. I think he’d like to run it for a while. From where we sit, though, this is something we’ve discussed over the last 6 months. If you sell an asset while a project is only partly finished, you wouldn’t receive value for it. Another point we’ve made as well: once we commission this plant — a brand-new plan at 4.2 million tonnes right in the half of the Eastern Goldfields — it’s a great asset to own. It goes to 200,000 ounces, generating a lot of cash for us. I think there’s a lot more opportunity there. The only thing you’d add is that if someone wants to walk in and give us a large check that gives us something we can’t resist, we’ll always look at that, but we’re not actively looking to sell the asset.
Hugo Nicolaci
analystThanks, that's helpful. Clearly the present gold price backdrop is providing support there. Then just one last quick item: with the project summary table added to the release, I noticed Mt Rawdon pumped hydro isn't included. Could you update us on where that pumped hydro prospect stands after the change of government there, and what options you have for continuing to process there and for deferring the start of rehab work until a decision is made on the pumped hydro piece?
Lawrie Conway
executiveYes. Thanks, Hugo. Jake will be happy that you raised it. There's a small item within the Mt Rawdon section itself. We haven't exactly classified it as a project. That said, the shift in government has benefited us. Jake and the team have been talking with the new government, and it keeps moving forward. With mining now finished there, that has made it possible to carry out some work on site, including drilling and all the other things needed to complete the technical study. On top of that, the continuing negotiation with the government agent appointed to hold renewable projects is making headway, and we would like to see a result at some point during this year, though it remains very positive there. As for the closure and rehab, that stays the same in terms of how the project would be structured — we <<inaudible>> closure and rehabilitation costs as the first part of divesting the project, and we continue to manage and maintain those actual closure and rehabilitation obligations.
Operator
operatorDaniel Morgan at Barrenjoey has the next question.
Dan Morgan
analystStarting with Northparkes, Major Tom, and E51 — could you clarify whether you plan to declare a resource in June '25? And if those open pits prove viable together, when might they potentially enter the mine plan? Also, a quick comment on whether that, ideally, defers the decision on the E22 block cave, which I understood you might need to make around 2027?
Lawrie Conway
executiveThanks, Dan. I'll pass it over to Glen to discuss Major Tom and where it all fits in. I think what — the second part of your question, you wouldn't see that Major Tom pushes E22 out because you need — we need that bulk tonnage. Ultimately, at some point, Major Tom doesn't fill that void. It obviously would supplement like we've got with E31 now. So maybe you want to...
Glenton Masterman
executiveCorrect, that's how we're viewing both Major Tom and E51, Dan. Going back to the start of your question about whether we're running resource models and so forth — well, look, I'll make the site quite nervous by answering this. They rightly tell me we need to see — we need to carry out the modeling work to determine whether the open pits were optimized. That's really where we stand right now. We have enough drilling <<inaudible>> to begin connecting the dots between drill holes and placing shapes around the mineralization footprint. We'll build resource models. And then, naturally, we need to optimize them and check whether they will pull-pit and so on. What I like is the scale we're seeing. They aren't super large, but we're talking in the range of millions of tonnes, yet the grades are pretty healthy, and we're looking at, in some areas, particularly at Major Tom, 1% copper grades quite low on the gold side. And pleasingly, these — both Major Tom and E51 are pretty close to the processing plant. So that's the work taking place over the next 6 months, and we'll have a better understanding of where these things are landing in terms of resources toward the end of the June quarter.
Dan Morgan
analystAll right, turning to Cowal. It's encouraging to see the OPC approval come through. Could you give us an update on whether the approval timing has caused any disruption whatsoever to open pit operations carrying on — is there any chance of a pause at all? What do you need — or does it transition without interruption from Stage H? And with trucks and personnel continuing to work, is there anything still pending that you require from the Board before FID can be made?
Lawrie Conway
executiveYes, Dan, regarding that item, there isn’t anything really left hanging that we’d need to bring to the Board. We expect to receive the final federal consent conditions in February, and after that we’ll present it to the Board. Looking at it from the perspective of the actual open pit at E42, we’ve been lucky that the weather conditions we’ve experienced over the last 18 months have meant we’ve had to process stockpiles for probably longer stretches than originally planned. So as a result, we would anticipate that once Stage H wraps up through FY ’26, we move directly into Stage I with no interruption to mining at E42.
Dan Morgan
analystAll right, that's encouraging. One final question, likely directed at Matt. At Red Lake, it's nice to see positive free cash flow across 2 quarters, though my bigger focus is simply on the operations, which appear to have reached a degree of stability. Could you walk us through what's functioning well there, and perhaps give an update on what's anticipated for the remainder of what you're able to see ahead?
Matt O'Neill
executiveYes. What's really driving that stability is adherence to a plan and pushing slightly ahead on certain development work. The team has faced pace-related difficulties and has gotten past them. As a result, the coming 2 quarters appear largely unchanged as we move forward. Nothing materially different is on the horizon. The key focus has probably been operational discipline — holding to the plan and avoiding self-inflicted surprises along the way — and that's likely what John and the team have concentrated on most. Even so, there are certain areas where contingency exists, so that if a problem arises, we can access it, and I think that was probably one of the main gaps we had before. That isn't to claim we hold 100% contingency. Still, as things stand right now, I'm at ease with where it stands. So yes, what we expect is more of the same across the next couple of quarters. Beyond that, we're doing some work to genuinely grasp how this looks over the longer term, and our primary driver is going to be cash — ensuring we earn a solid margin and produce healthy cash from that business.
Matt O'Neill
executiveThat is likely the central element we focus on when it comes to our long-term plans.
Operator
operatorMatthew Frydman of MST Financial has the next question.
Matthew Frydman
analystAnd Matt, perhaps picking up where we left off on that topic and the question that came up — clearly, mining and cash results at Red Lake have been solid, but grades do seem to remain somewhat inconsistent. Some of that, of course, is simply quarter-to-quarter variability. Still, is there anything specific you can share regarding how grades will look over coming quarters? I assume you're probably adding more Upper Campbell material into the blend. Then, on the broader question, are grades coming in as you anticipated relative to the reserve and relative to the grade control drilling you're conducting? Or does further reassessment need to happen regarding what actual mined grades look like under the more productive mining methods you're currently putting in place?
Matt O'Neill
executiveYes. I'll likely address a few of those in a single response. At the moment, grade is what matters most to us. And from my perspective, that comes down to how predictable our operating conditions are. So we aren't experiencing significant deviations between what we expected to be present and what actually is. Often in the past, where we were mining drove the variance in grade. So it wasn't really a question about the model. It was more an operational matter. Looking ahead, grade will probably be the central issue for us, along with certain related elements that everyone knows about—dilution and mining practices—but also making sure we're aiming at the higher-grade zones. Naturally, that is what will produce the most cash for us. So many of those conversations about cutoff grades, about where we stand, and about discipline are taking place right now within our life of mine process. So what I expect is that I would like to see grades begin to rise, and that is what we're striving for. Clearly, we are producing cash at this point with these prices. But I would like to see us make our way through that, and for it to climb somewhat from where it stands today.
Matt O'Neill
executiveStill, we’ll see how things go as the planning process moves along.
Lawrie Conway
executiveYeah, one more point to add there, Matt. When we consider it as one combined operation, and once we start receiving material from Cochenour — which is lower grade and serves as a base feed — that pulls the overall grade down. So you do see stretches where grades sit between 5.5 and 7 grams. But once you also have that base feed from Cochenour, which is bringing <<inaudible>> — maybe that's the right way to put it — we want to source more material from the higher grades and then lessen our dependence on Cochenour to keep the plants filled.
Matthew Frydman
analystNo, that's clear. And perhaps one more quick question for Matt. It may be a little nitpicky, but I did feel Ernest Henry could have done somewhat better in the December quarter, since throughput and production were essentially flat versus the prior quarter. But recalling the September quarter, it did include some scheduled maintenance that was flagged. So is there anything specific to point to at Ernest Henry for that quarter? Or is it simply business as usual? And clearly, you have another round of scheduled shutdowns coming in the March quarter.
Matt O'Neill
executiveYeah, there are likely some small issues in there. I think the main thing for us is that I'm expecting somewhat of an improvement at Ernest Henry during the next half. And a major factor behind that is going to be the ventilation work that's currently underway. It has slipped a bit relative to where we wanted it to be, but we're aiming to finish in the quarter -- in the following quarter, and that ought to unlock a couple of other areas. Of course, it's a rather hot region of the country. And during the summer months, there are certain areas where we -- I mean areas where work couldn't carry on. So we're anticipating a step up in the second half, and that ventilation work is likely the key to it.
Matthew Frydman
analystOkay, so from a mining standpoint, would it be fair to say the December quarter may have been somewhat limited because that kind of pressure just wasn't there?
Matt O'Neill
executiveYes, more — yes, up to a point. We managed to carry out work in other regions, though certain regions were in pullback. We weren’t able to work in those. That’s the place where I’m watching for the step up. So yes, every region will be open to us once that network is up and running.
Operator
operatorPaul Kaner with Ord Minnett has our next question.
Paul Kaner
analystStarting with Cowal, and building on what Dan was asking about: how should we think about that grade profile as you move from Stage H into Stage I and draw on those lower-grade stockpiles? Given that there's no production hiatus, should we simply assume it looks like earlier stage transitions?
Lawrie Conway
executivePaul, yeah, so it's much the same story, really. As Stage G wrapped up, we hit the good grade, and after that we moved back into the stockpiles. We'd anticipate the same pattern as we work through Stage H and then on into Stage I, processing those stockpiles. The one thing that's different for Cowal this time around, compared with that last cutback, is that the underground is now in place. We go up to 2.4 million tonnes in FY '26 at roughly 2 to 2.5 times the grade we'll be mining from Stage H. That's how we see it shaping up as we head into next year. The key thing, as we finalize the FY '26 plans and get sign off on OPC, is looking at that sequence in FY '26. When do we complete that, when does the underground ramp up to that 2.4 million tonnes that drives the production. But what you'll still see is output in similar ranges this year versus next year, likely a bit lower, since some lower grade stockpile material comes through in the second half of FY '26 that the underground can't fully offset.
Lawrie Conway
executiveAnd once we’ve brought the OPC to the Board and secured the approvals, that’s the point at which we can lay out precisely what you should expect moving forward.
Paul Kaner
analystYes, perfect. And then, I suppose, one more item. Now that Mungari is being moved up, when should we anticipate commercial production from that asset, purely for capitalization and accounting purposes?
Lawrie Conway
executiveYes, I’ll pass it over to Barrie. But basically, what we need to observe is that we’ll be working through lower-grade material during that <<inaudible>> phase. So we simply have to watch it in order to reach a production — processing rate, and see those recoveries arrive. And during that stretch, there will be certain costs we need to examine with respect to commissioning. Barrie?
Barrie van der Merwe
executiveYes, just to confirm that — we'll stick with how we normally handle ramping up any mining asset. So we'd likely be looking at throughput at 80% and reaching a fairly high level of recoveries, where they ought to be. Then, depending on when the ramp-up actually begins during the quarter, we'll see where things stand at that point and consider capitalizing some of those processing costs on the balance sheet, and also look at the ounces that go into the AIC calculation. So I don't have those details yet, since it hasn't happened. But the usual principles will apply, Paul.
Lawrie Conway
executiveTo put it briefly, Paul, we are building in a commissioning period of 3 to 4 months, and that represents roughly the base load, after which we will simply observe how it ramps up.
Operator
operatorAndrew Bowler of Macquarie has the next question for you.
Andrew Bowler
analystApologies for returning to Mungari once more, but I saw that the AE capital expenditure has been shifted from next year into the current one — is any CapEx going to be pulled ahead from ’27 into ’26, for instance an open pit that you would need to accelerate in order to supply the larger mill which begins operating nine months earlier than originally planned.
Lawrie Conway
executiveNo, look, Andrew, as Barrie explained, we need to speed up that development of the mine. And luckily, with the contract being awarded and the mobilization happening, that lets us align it with the plant. So what you'd see is that next year, we'd have been ramping up mining in any case and getting set for the plant visit. So '27 versus '26 doesn't look much different. We have to be mining at a 4.2 million tonne rate in '26 just as we would have had to in '27. So we don't expect anything extra to come into '26 out of '27, because the project capital for construction will be done.
Andrew Bowler
analystYeah, understood. What I was getting at was more the new pits that have to be moved up. If I remember right, it was around 8 pits over the mine plan. I figured some might shift from '27 into '26, but it sounds like that's just how it works, so no problem.
Lawrie Conway
executiveOkay, so Andrew, Castle Hill is the foundation for us in that region, exactly as Matt described. We're building up the remaining ones across the other mining centers. So out of the 3 mining centers, that additional one supplies extra material, and then there's the underground as well.
Operator
operator<<operator_script>> Our following question is from Al Harvey of JPMorgan.
Al Harvey
analystSorry to ask something that isn't about the quarter, but I was hoping to understand better the announcement you issued in mid-December regarding the class action that Echo Law filed. Is there any additional detail you can share on the timing and on the impact you might be watching for?
Lawrie Conway
executiveYeah, look, what we released on December 12 sets out the situation. We think our continuous disclosure duties have been satisfied, and we intend to defend that case. It’ll go through the courts over the next few months, and beyond saying that we believe we’ve fulfilled our obligations and that we’ll defend it, it wouldn’t be right to comment further.
Operator
operatorThat brings us to the end of the question-and-answer session. At this point, I'll return the call to Mr. Conway, who will offer some closing comments.
Lawrie Conway
executiveThank you, Harmony. So, the numbers we posted for the December quarter were genuinely the product of the effort we've put in over the past 6 to 9 months to become a more dependable operation. That has delivered 4 strong quarters in a row now, and keeping that going is a real priority for us as we move forward <<inaudible>>. A handful of points to take away: we are delivering safely against our plan. Cash generation keeps building, with $273 million <<inaudible>>, and there's more upside in the second half, since spot price sits roughly $400 above what we've realized year-to-date — and keep in mind our hedging obligations for the second half are quite limited, at about 25,000 ounces. As a result, the price we actually achieve should land fairly near spot. We're staying disciplined on operating costs and capital investments, so we truly bank and capture the benefit of metal prices. The projects are performing ahead of what we'd planned, and the drill results we're seeing are excellent — they genuinely support sustainable incremental growth and bring upside to the portfolio. Thanks for your time today, and I look forward to updating you in a few weeks with our half year results.
Operator
operatorThanks. That brings today’s conference to a close. We appreciate your participation. You’re welcome to disconnect now.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Evolution Mining Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Evolution Mining Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Evolution Mining Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.