Evolution Mining Limited (EVN) Earnings Call Transcript & Summary
April 15, 2025
Earnings Call Speaker Segments
Operator
operatorWe appreciate everyone being on the line, and we're glad to have you with us for Evolution Mining's March 2025 quarter results. <<operator_script>> At this point I'll pass the call to Mr. Lawrie Conway, our Managing Director and Chief Executive Officer. Over to you.
Lawrie Conway
executiveThank you, Ashley, and good morning to all of you. With me on today's call are Jake Klein, our Executive Chair; Matt O'Neill, our Chief Operating Officer; Nancy Guay, our Chief Technical Officer; Glen Masterman, our VP, Discovery; and Peter Rocky O'Connor, our GM, Investor Relations. Today, along with releasing the results for our March quarter, we're excited to have announced that the Cowal Open Pit Continuation project has been approved — one that will keep this operation going as a world-class #1 asset for at least the coming 17 years. Glen Masterman, our VP Discovery, tells me that no discoveries are being made at Cowal, and I'm sure he's right about that. A presentation pack has been released today, and that is what <<inaudible>>. Moving to Slide 3. And I think it's fair to say that another successful quarter is behind us. Beyond our day-to-day operations, though, we've made enormous progress on multiple value-accretive organic growth projects. As I said in January, our commitment has been to keep building on the consistency of the past 4 quarters, and that is what we did in the March quarter. We are delivering to guidance. Our safety was stable with our TRIF at 5.4. We produced around 180,000 ounces of gold and just under 20,000 tonnes of copper.
Lawrie Conway
executiveOur all-in sustaining cost is still among the lowest anywhere in the sector — $1,616 per ounce for the quarter, and $1,575 per ounce year-to-date for continuing operations. We're also keeping up our discipline when it comes to costs and capital allocation. That consistency and delivery, combined with a rising gold price environment, means cash flow generation has carried on, with $207 million of group cash flow delivered during the quarter. Beyond that, we had an extremely productive and successful quarter across our projects. Construction at the Mungari plant expansion finished ahead of schedule and it's now in commissioning and ramping. That moves Mungari back to being a material cash contributor for the group. We've now received final regulatory approval for the continuation of open pit mining. With that in hand, the Board had the easiest of decisions on the project, given the quality of the asset and the high rate of return it will deliver. The project is now fully approved and Cowal has extended out to at least 2042. Finally, at Mt Rawdon, all of the work over the past few years on the Pumped Hydro Project is starting to come to fruition, with the Queensland government committing to funds for the next phase of the project.
Lawrie Conway
executiveI won't take the spotlight from Jake on this project. He'll get the enjoyment of addressing it in a moment. Turning to Slide 4, which genuinely illustrates what a successful quarter produced. Deleveraging has sped up even more, and that makes the balance sheet stronger. Group cash flow for the quarter came to $207 million, delivered at a rate equivalent to $1,115 per ounce. That's 30% above the December quarter, even though the average spot gold price rose only 11%. We anticipate additional cash flow gains in the June quarter as we hit our production guidance, paired with a spot gold price $550 to $600 per ounce above what we realized in the March quarter. There's been plenty of discussion about hedge books, and Evolution carries minimal hedging — 65,000 ounces to be delivered through to June 2026. In the grand scheme, it isn't material. And looking at it, this year we've realized 98.5% of the average spot price. In the quarter, we paid off all of the remaining FY '25 scheduled term loan repayment. With cash of more than $660 million, a near-term cash generation outlook that's strong, and gearing now under 20%, we'll keep speeding up repayments on these term loans.
Lawrie Conway
executiveOur long-dated debt by way of the USPP notes leads the sector, with a very low average cost of debt at 4.5% in Australian dollar terms. It makes up 75% of our total debt, with an average tenor of about 6 to 7 years. At the time we issued these notes, we fixed our currency exposure, and we are now seeing the real benefits of that. Our principal debt is currently $180 million lower, and our interest expense is $7 million to $8 million per annum lower than if we were exposed to currency movement. By delivering to our planned disciplined capital allocation and banking the benefits of high metal prices, this will enable us to continue to increase returns for our shareholders. Turning to Slide 5 and shifting gears to our projects. Cowal is truly a world-class Tier 1 asset. Since acquiring the operation 10 years ago, it has consistently delivered low-cost ounces, the resource base has grown. It has fully repaid all acquisition and investment capital. It still has at least a 17-year mine life. And as I said earlier, there is more upside to be extracted. Just this year alone, for the 9 months, Cowal has generated around $480 million of net cash at just under $1,900 per ounce.
Lawrie Conway
executiveIt's difficult to hold back, but this is a cash cow. Given the asset quality and the project's compelling economics, deciding to put money into the open pit continuation project was straightforward. Nancy will walk you through the details soon. In brief, though, the project will produce roughly 2 million incremental ounces from 3 satellite open pits plus the existing E42 pit. The plan and capital are largely consistent with what we laid out on-site in June last year. We're investing $430 million across the next 7 years to generate an incremental NPV of between $875 million and $2.3 billion at a 34% to 71% rate of return, with a very short payback period of 1.5 years to 4.5 years from first ore. Now is the right time and this is the right place to allocate the funds. It aligns fully with our capital allocation discipline. This financial year we'll invest $65 million to $70 million of project capital and around $5 million in mine development so the project is ready for full ramp-up from July. That capital wasn't part of our original FY '25 capital guidance, since the project was awaiting regulatory approval at that time.
Lawrie Conway
executiveThis capital for F '25 includes a timely acquisition of a low-hour used haul truck fleet, which saves roughly $35 million versus what new haul trucks would cost. Right now, conditions in the market for this kind of equipment are favorable. So we'll keep evaluating alternatives in order to get the best results from a capital and operating cost standpoint for the long-life open pit plant. At this point I'll pass things to Jake, who is eager to share the good news about the Mt Rawdon Pumped Hydro Project.
Jacob Klein
executiveThanks, Lawrie. Morning, everybody. I’m really pleased that you invited me, Lawrie, to make a guest cameo appearance on today’s call. I have to admit that when I requested 20 minutes from you, Lawrie, to give the complete story on Mt Rawdon, you nearly took the invitation back. So I’ll do my best to honor the commitment I made to you and to be as comprehensive as I can, given how exciting this project is. But as a lot of you on the call know, turning Mt Rawdon into a Pumped Hydro clean energy storage facility has been a pet project of mine for <<inaudible>>. It carries such — it carries such strong positive messages at so many levels for the mining industry and also for our country’s transition to renewable energy. What could be better than turning an old gold mine into renewable clean energy infrastructure assets? We have been working on this project for over 5 years, ever since our partners and joint venture owners in the project, ICA Partners, identified Mt Rawdon as a site suited to conversion to Pumped Hydro. That was centered on its steep topography, its proximity to the grid, and the fact that it is a disturbed mine site, so its environmental <<inaudible>> is so well known.
Jacob Klein
executiveEverything we've completed across the past 5 years has shown this to be accurate, and a portion of that is laid out for you on Slide 6. Mt Rawdon has shown itself to be the most -- among the most sophisticated pumped hydro developments in Australia with the least capital intensity. On every metric that matters, it stacks up competitively against other energy storage options. The project got a significant lift last week when <<inaudible>> made known Queensland government backing for moving the Mt Rawdon Pumped Hydro Project forward to a final investment decision. That backing comes via CleanCo, an entity owned by the government, which right now is putting $30 million into additional geotechnical study before it decides whether to take up its option by the end of September this year. Under the agreement we've established with CleanCo, ICA and Evolution's interests are tied to the project's success all the way through commissioning by way of various milestone payments, plus the right to process any gold extracted as the existing open pit is recontoured to act as the lower reservoir for an infrastructure asset that will be constructed and run across 100 years. Last, something probably not factored into the original analysis, yet it is genuinely showing itself to be invaluable, is the outstanding relationships with community and indigenous partners that Evolution has cultivated over the past decade.
Jacob Klein
executiveFollowing the Queensland government's announcement last week, feedback and responses from these key stakeholders have been extremely positive, with acknowledgment that constructing this project will create jobs and benefit the local community for decades ahead. Lawrie, thank you once more for the guest slides, and I will now pass things to Matt, who will give further detail on what has truly been an exceptional quarter for Evolution.
Matt O'Neill
executiveThank you, Jake — those are tough shoes to fill. The March quarter was yet another strong one, with safe delivery against plan. Over the past year, how consistent and predictable our operations are has gotten substantially better. That rests on solid teamwork and collaboration at every one of the sites, and also more widely throughout the broader Evolution organization, with the aim being that when we say something, we do it, and we deliver. If everyone could please turn to Slide 7, there's a bit of an operations update. First, what we achieved in the March quarter. Several significant milestones were reached in this quarter, as Lawrie mentioned earlier. At Mungari, we finished the 4.2 mill expansion successfully, ahead of schedule and under budget. And at Cowal, every approval needed to extend the mine's life to 2042 came through. As preparation for the coming 20 years of operation at Cowal, the mill went through a major refurbishment, which got underway in mid-March. These 2 assets form core pieces of the foundation for the group's continued success and demonstrate well our project execution capabilities, which position us for long-term growth opportunities. The operations performed consistently throughout the quarter, though Red Lake production was disrupted in February because of a blocked pace line.
Matt O'Neill
executiveI'm glad to report that the line has returned to full operation, with Red Lake getting back to planned production rates throughout March. As we look ahead, we're positioned to close out the year strongly and remain on track with group guidance. Mt Rawdon should keep generating meaningful cash flow over its last quarters of operation as it processes the stockpiles. At Ernest Henry, the ventilation upgrade is on schedule to be completed, enabling more productive operations in the June quarter. Meanwhile, at Mungari, commissioning of the new 4.2 mill is progressing well. Notably, at Cowal, the major mill refurbishment remains on track and is due to come online in mid-April. While that refurbishment was taking place, we also completed work to expand the capacity of the elution circuit. To finish this upgrade, we drew down on our working gold stocks, and those will be replenished over the first part of the June quarter. I'll now pass things to Nancy, who will walk through some of the exciting projects we have underway.
Nancy Guay
executiveThank you so much, Matt. Before we get into the 35 project discussion, I'd like to share something personal. Having been a member of the Evolution team for more than a year now has truly been a privilege. Our portfolio's strength excites me, and even more so, the substantial value we are positioned to generate in the coming years. What inspires me most, though, is the chance to work with such a capable, committed and enthusiastic group. I bring over 30 years of experience in mining, including the past 2 decades at Agnico Eagle, where I served as Vice President, Technical Services, Innovation and Optimization. This is my second professional stint in Australia — I previously worked here as a consultant for <<inaudible>>. Across the next 3 slides, I'll walk you through an overview of our project portfolio, with a focus on the strategic rationale for the Cowal Open Pit Continuation project — which I'll refer to as OPC — and the long-term potential of the Cowal underground. We oversee a strong, well-aligned set of projects built to deliver sustainable value for Evolution. Every asset has been strategically positioned to strengthen our portfolio, and we stay focused and disciplined on timely, capital-efficient <<inaudible>> delivery. A number of key projects have been given priority, and we're pleased to report strong momentum throughout the portfolio.
Nancy Guay
executiveOne standout case is the Mungari expansion project, where the timing lined up nicely with supportive market conditions and was made even stronger by outstanding cooperation between Evolution and our contracting partners. That project came in 9 months ahead of schedule and 9% under budget, with total capital of $220 million. Commissioning is moving along well and stays firmly on track. Cowal's long-term future is strongly supported by developing its underground potential, which I'll discuss in more detail on the final slide. We keep making solid progress on development activity while deepening our geological understanding of this high-quality ore body. Production stays on track, and we are moving toward achieving 2.4 million tonne per annum throughput by 2026. At Northparkes, the E48 project is advancing as planned. We are now integrating the outcome of a recent study with our life-of-mine plan to confirm the optimal production profile and development schedule. The next 6 to 9 months will be an active and pivotal period across the portfolio. Key milestones include completion of commissioning at Mungari, continued advancement at Northparkes, including the trade-off study for E22, block caving versus a sublevel block caving, finalization of the feasibility study for the Ernest Henry extension at depth and the Bert deposit.
Nancy Guay
executiveAnd as the slides that follow show, we're starting the Cowal Open Pit Continuation project. That OPC project substantially extends Cowal's mine life and backs Evolution's long-term production profile. Slide 9 sets out that the OPC project is fully ready for execution. Construction of a lake protection bund gets underway in July — essential infrastructure that lets us safely develop 3 new open pits. That takes in the E42 extension, with E46 GR due to enter production in <<inaudible>>. E41 is slated to become the third producing pit when it comes online in 2030. The main value drivers for this project are extending the open pit by more than 10 years, an extra 2 million ounces across the overall production profile, building the critical infrastructure needed for future underground expansion, and the sustainability gains from in-pit tailings storage at E46 and GR. This project is a cornerstone of Evolution's strategy, delivering scale, longevity and future optionality at one of our key assets. As I said earlier, Cowal's long-term future <<inaudible>> . The OPC project is central to delivering production and the critical infrastructure that will underpin future underground expansion. Slide 10 shows the deposits stay open at depth, and we keep delivering consistent low-cost resource replacement at an average of just $20 -- $23 per ounce.
Nancy Guay
executiveThat speaks to the organic quality and to how disciplined we are when it comes to exploration and development. Underground work done recently has sharpened our geological understanding and confirmed that the system has broader potential. Along with Cowal's location in a Tier 1 jurisdiction and Evolution's operational capability, this has reinforced how strategically valuable this asset is within our portfolio. The Cowal underground kept unlocking material upside, strengthening our production base and delivering long-term share. I'll now hand over to Lawrie for the conclusion.
Lawrie Conway
executiveThanks, Nancy. Here's the summary as laid out on Slide 11. We're poised for a strong finish in the final quarter. Thanks to the hard work across the first 3 quarters, we've put ourselves in a good position and remain on track to meet our guidance. That will mean a substantial lift in cash generation during the June quarter, and we're on course for $2.3 billion in operating cash flow this year. That stacks up well against what we planned back when we issued guidance in August — roughly $500 million more cash flow. We're advancing our organic growth projects so they deliver high returns. Mungari being delivered ahead of schedule and under the original budget, the compelling economics at Cowal, and the unique approach we've taken at Mt Rawdon are all perfect illustrations of how we're driving value out of the portfolio. We stay disciplined on capital allocation. The only revisions we've made to capital guidance stem from the early completion at Mungari and at Cowal, together with approval of the compelling investment and the opportune acquisition of a fleet. We keep timing our major projects appropriately. The cash flow we're generating is definitely making its way through to the bank, so shareholders realize the benefits of these high metal prices through higher returns.
Lawrie Conway
executiveAshley, if you would, go ahead and open the lines so we can take questions.
Operator
operator<<operator_script>> The first question is from Kate McCutcheon at Citi.
Kate McCutcheon
analystNice work on the record cash flow. Turning to when the projects land: the CapEx range you laid out — $750 million to $950 million across the coming 5 years — is an average. Could you shed some light on how that actually breaks down, which years run high and which run low? And are there any major unknowns when it comes to the scheduling of certain projects?
Lawrie Conway
executiveYes, Kate, thank you. So, looking at the portfolio overall, the timing will vary from project to project. And once we complete the FY '26 plans over the next couple of months, at the point when we provide guidance, we'll be in a position to lay that out more clearly. If you take Cowal as an example, though, since we're opening up pits and relocating the bund wall, CapEx will be higher during the first couple of years, and after that it declines across the remaining years 3 to 7. So we're still working through what that will look like. In a similar way, with the fleet we've bought to date, we reach a peak requirement of roughly another 7 to 8 trucks. So should Matt and the team be able to find suitable secondhand trucks that cost a lot less than the new ones, we might pull those forward. As for the other assets, they're all fairly well aligned over the next couple of years, with Ernest Henry building up in around year 3 to 5. But as I mentioned, once we get to our guidance, that's when we'll be able to lay it out. But that $750 million to $950 million average over the next 5 years.
Lawrie Conway
executiveTherefore, assuming those rates over a five-year span, that is the basis you ought to use for your planning.
Kate McCutcheon
analystAll right, that's useful, Lawrie. So then two questions rolled into one, on the CFO update. Where does that stand right now? And you're nearing that 15% gearing target. Would you plan to pay off the remaining term loans? Or, I suppose, what happens next with the balance sheet after that?
Lawrie Conway
executiveOn the CFO question, yes — we're quite far along there, and I wouldn't anticipate it taking very long before we name a successor. On gearing, right — our initial target was to drop under 20%, and we've reached that level now. So we've stepped up repayments on the term loans, which means nothing further is due from us during this financial year. Some payments will be made in the June quarter, and once June arrives, we'll assess how much more we can accelerate. Still, I think it's reasonable to say that by the point we hit 15%, we'd have been bringing gross debt down more quickly than net debt alone. We'll be able to give an update on that in June.
Operator
operatorThe following question is from Daniel Morgan at Barrenjoey.
Dan Morgan
analystStarting with the first question, which is likely fairly simple. The overhaul at the Cowal mill should be wrapping up around now. Could I just confirm where things stand on that? Has it been completed, or is it nearly there?
Lawrie Conway
executiveThanks, Dan. I'd describe it as imminent. It's scheduled to be back online this week, and we're tracking to that plan.
Dan Morgan
analystI realize it's quite soon, but on the subject of the Mungari mill — could you say a bit more about how the commissioning process is progressing? I understand it's only been, what, the second week?
Lawrie Conway
executiveYes. I can pass that over to Matt, but honestly, it's just going well. Everything is proceeding as planned. Scott Barber, the GM, was delighted to send me a screenshot of the remittance after it had produced its first gold bar and sold it at $5,150. So he's really pleased with it. Matt, anything to add regarding the commissioning?
Matt O'Neill
executiveNo, I believe you've already addressed that. Everything is proceeding as expected. The team is working through the usual commissioning issues, but nothing material has surfaced that I think would create a problem for us. So no, things are going quite well.
Dan Morgan
analystAnd assuming all goes according to plan, at what point would the mill be running at full throughput and expected recoveries?
Lawrie Conway
executiveThe real obstacles, then, are commissioning and reaching commercial production. We have to run for roughly 3 months at a 70% rate — that works out to something like $3 million per tonne per annum — with recoveries landing within a few percent of plan. Speaking for Matt, I can say we anticipate that being in place by the end of June, as stated in the release, but...
Matt O'Neill
executiveYeah. No, that's roughly correct. That's the goal we're aiming for.
Dan Morgan
analystAll right, and one final question — perhaps a chance for Jake to weigh in on his favorite subject, Pumped Hydro. As I recall, and I believe this figure is correct, Mt Rawdon carried $47 million in rehab liabilities at the close of FY '24. Does the Pumped Hydro project alter that in any way, if at all?
Jacob Klein
executiveThanks, Dan — that's a great question. In our release, I believe we laid out the main commercial terms: once FID is reached, there's the $90 million payment to Evolution, and Evolution holds 100% of that, on top of some — in addition to the $100 million payment upon FID that we share with ICA, but the $90 million, which will go toward that $47 million liability.
Operator
operatorRahul Anand from Morgan Stanley has the next question.
Rahul Anand
analystI have a couple of questions. Maybe I'll start with the all-in sustaining cost performance — I just wanted to dig into that a little. Clearly, on a year-to-date basis, you're tracking toward the top end of guidance, or perhaps even a touch above it. And looking at this quarter in particular, gold sales came in around 8% above consensus, while silver sales were 14% higher. Copper production also ran somewhat ahead of consensus. And when I look at copper pricing for the period, nearly AUD 15,000 a tonne against your guided copper price of AUD 13,750 per tonne — yet all-in sustaining costs came in at AUD 1,680 a tonne, which is still above guidance. Granted, Mt Rawdon was part of that, but even so, it's top end to slightly above. Would it be fair to say the underlying cost base is now running sustainably higher as we look toward next year? And how are you thinking about the final quarter as well? That's my first question. I'll come back with the second.
Lawrie Conway
executiveThanks, Rahul. So, I think that single question actually contains a few separate ones we should work through. On copper, the key point is that so far this year we're basically tracking the price assumption baked into our guidance. Sure, this quarter came in higher, but year-to-date we're more or less right on what we told you to expect. Turning to gold, we realized $4,500 versus $3,300, so royalties come in higher. That said, as I keep saying, we're happy to book the extra 95% on the revenue side as long as we also wear the extra on the cost side. So that's likely costing us somewhere around $50 to $60 an ounce relative to our guidance. And when you look at the March quarter, keep in mind that Cowal, our biggest and lowest-cost producer, has its shutdown. So half of those maintenance costs land in this quarter alongside weaker output. In the following quarter, production improves, though some of those shutdown costs will still be with you. Once those shutdown costs are spread across the entire year, though, the full-year all-in sustaining cost number comes out lower.
Lawrie Conway
executiveThen if you look at — you're moving toward sales consensus versus — my bigger concern is what our own plan says. We sold a little more during March since the timing of the December quarter end meant we couldn't sell then, so that material got sold in the March quarter. The March quarter ended on a week day. We were also capable of making sales right at the close. As a result, sales came in higher. But when you turn to Red Lake, Red Lake's sales were 3% — 10% lower, and the reason is a build-up of concentrate stocks until we reach the salable quality that will sell into June. So greater production at Red Lake plus the sale of that concentrate will bring their all-in sustaining costs down. So addressing the last part of your question, are we noticing a shift in the overall cost base? No. What we're seeing is pretty well in line. The one item I would mention that I hadn't covered was at Mungari, where we sold some very low-grade stockpile material through toll treating that would be above the average cost, but with the plant now being commissioned early, that material would otherwise not have been processed until the back end of the mine life.
Lawrie Conway
executiveSo we took the chance to get that toll handled. It's pushed the AISC up somewhat, but from where we sit that isn't material, seeing as we're collecting the revenue at this moment. There's no change to the guidance.
Rahul Anand
analystUnderstood. Understood. Well, that is quite thorough, and I suppose we will need to form our own views regarding next year and so on, but you appear to be in a strong position for the final quarter. And then I believe the second question is...
Lawrie Conway
executiveI’ll add one comment there. It’s nice that once we reach the end of the March quarter, everybody simply shifts attention to the following year. Sadly, in Matt’s case, I can’t allow that. He still has one quarter left to complete. That said, if you examine our cost base, labor accounts for 50% of it. What we anticipate seeing is a smaller percentage rise than we saw last year, considering the current level of inflation, but you should anticipate that across 50% of our cost base, labor expenses will climb by roughly 3% to 4%. So that’s half of it. The remaining costs are fairly stable, and after that it depends on whichever gold price assumption you apply for next year, since that represents roughly 5% to 6% of our cost base. If you keep it at $5,000 an ounce, while we are averaging $4,500 this year, then consequently your royalty cost will be higher next year. Those, however, are the major factors you would observe when comparing our costs for next year against this year.
Rahul Anand
analystNo, that’s excellent. That’s very clear and very detailed. Look, the second item I was going to move on to was just the variability in grade at Red Lake that we’ve been seeing from the mine. Obviously, you’re doing some work in there. But what I suppose I wanted to understand was whether the work you’re carrying out at the moment leaves you in a better and more predictable grade profile into perhaps next year, or whether we should continue to expect that grade variability to persist for the asset.
Matt O'Neill
executiveMatt speaking — I’ll take that question. On the grade variability for the quarter, past conversation drove it, and basically we were mining in locations different from where we had planned because of that. That is the main factor there. Yes, you should expect — and we do expect — greater predictability from the grade going forward. There are 2 aspects to that. One is everything operating according to plan, along with the pace and things turning over. But also the drilling and understanding precisely where we are and getting further ahead of ourselves. Those are the 2 drivers. That is exactly the direction we’re heading.
Operator
operatorThe following question is from Andrew Bowler at Macquarie.
Andrew Bowler
analystStaying on Red Lake for a moment, this one's for Matt. I'm just curious whether the trade situation between the U.S. and Canada right now is bringing any added costs. What share of your consumables originates south of the border, and the same question for plant and equipment, since that would obviously flow into the CapEx line at Red Lake.
Matt O'Neill
executiveYes. Andrew, that's likely about as solid a question as we could get. I mean, regarding what the outcome will be, we aren't sure, and I doubt we're the only ones. So we do anticipate some effect, and the team is working through it, mainly concerning budgets for next year in terms of the discussions. We have fairly decent stock levels for our key consumables in bits and pieces on site. But the truthful response is that we aren't certain, and we'll wait and see across the next quarter. But I'd like to say not much, though we'll see. I know that isn't the answer you're hoping for, but I genuinely don't know the answer.
Lawrie Conway
executiveYes, and to build on what was said, Andrew, operating costs would be roughly CAD 260 million to CAD 20 million annually, with labor making up a big share of that. Then there’s power and similar items, which are domestic. We’ve completed an initial analysis considering the tariff levels currently being signaled for Canada. We don’t view it as material or significant. A rough estimate would likely be about 5%, though that’s at the high end, depending on how far it escalates. As for capital at Red Lake, we aren’t purchasing much mobile equipment or infrastructure. It’s largely civils and works around — the largest component will be tailings, which will be in country. We’ll keep monitoring tariffs, just as everyone else is dealing with the daily updates.
Andrew Bowler
analystThat's true, of course, provided Canada doesn't turn into Eastern Alaska. On the operational side, perhaps another one for Matt. I was just reading the quarterly, which mentions an improvement in recovery during the June quarter at Ernest Henry thanks to the flash float circuit being commissioned. I was wondering whether you could put a number on that recovery improvement for us. And it also sounds like this is a piece of new equipment — will those recoveries keep going?
Lawrie Conway
executiveYes. So as far as it being up and operating and performing pretty nicely, there are 2 sides to the recovery. First, we'll get a modest lift in our grade from the ventilation circuit being up, and second, we'll get a bump from the additional plant. So what we're aiming at is roughly 1% in terms of where that gain comes from. Those are the 2 main sources we're drawing it from. So that's what we're after. If we can squeeze out a bit more, we will, and the team is doing a good job on it, but that's what we're pursuing.
Operator
operatorDavid Radclyffe from Global Mining Research has the following question.
David Radclyffe
analystLet me come back with a question on Cowal. Regarding the stage I cutback, I'm really just after some more detail. Could you perhaps give us a sense of when you'd expect the first year of ore from that cutback to begin generating that base case payback of 4.5 years, or better at spot? Maybe also some idea of which years are the key stripping ones, and what the material movement peaks at? And tied in with that, which are the key years when you'll be pulling on low-grade stocks, either supplemented or received from the underground?
Lawrie Conway
executiveThanks, Dave — there are a few pieces of that to unpack. I'm glancing at Matt and Nancy, and neither one is looking my way; they're getting set to leave. Still, if we view it the way Nancy described it — the order in which the pits come on, the reduction at Stage I at the close of this calendar year, and then a few years passing before we reach the ore, while at the same time we bring E46 online as the following pit, and after that Galway Regal — then, when you line them up, the general strip ratio range: E42 sits at roughly 3, E46 at 4. And the lowest among them all is E41, at approximately 2. So that gives you a sense of it. Rocky can bring you up to date on the tonnages and how each one fits in. But that's the order they come in. On the stockpile question, it means that by roughly the final quarter of this calendar year — so the second quarter of FY '26 — we begin drawing on stockpiles, and that will carry on essentially across the coming 3 to 4 years, though declining annually, with the largest being essentially a bit more than half a year of stockpile use, and you have 2.4 million tonnes arriving from the underground.
Lawrie Conway
executiveThat's roughly how it plays out, then. Matt?
Matt O'Neill
executiveNo, the profile has been addressed. Yes, we begin in Stage I essentially right away and then progress through it, but stockpiles account for a portion of what we'll be processing during that time, and our aim is to try to replace that with the underground as Glen and Nancy identify more that we can go and take from there.
Lawrie Conway
executiveAnd to give you a bit more clarity there, since I know you're getting somewhat more detail on this. Out of stockpiles, you're likely looking at 120,000 ounces next year, and from there it steps down to 100,000 for a few years, after which it falls off in year 4 and year 5.
Operator
operatorOur following question is from Meredith Schwarz at Bank of America.
Meredith Schwarz
analystTo build on what David asked regarding Cowal: given the expanding potential from underground, when do you anticipate an updated resource for that new area? My assumption is it won't be included in the upcoming resource statement. Then, considering stat mineralization growth and the rising potential for ounces — could you walk through how you're viewing that? Obviously it will displace some of the open pit ore coming through from the OPC. Do you have a rough sense of how the E41, the E46 and all of that will then come through following the underground?
Lawrie Conway
executiveAbsolutely, I’ll pass that question along to Glen.
Glenton Masterman
executiveThanks, Lawrie. Meredith, that's the kind of question I've been hoping for all morning, so I appreciate you raising it. Look, I think if we go back to the start, as a way of giving a resource update — look, our annual MR is coming out, but with the drilling we've been doing, especially at the underground extension, and if I point you to Slide 10 in this morning's pack, just to orient you on where our work is happening. On that slide, at E42, there's a shape shown there that indicates where we are drilling right now. That target sits between the E42 open pit and the existing underground. We've only got a handful of holes into it at this point, but what we've picked up again is a repeat of the architecture that controls the underground, in a new location, and that has opened up a brand-new search space. So that's the piece we're really excited about, because every hole we've put in there has hit grade where we expected it, over some pretty decent intervals. Right now we've only really got a half dozen holes in there.
Glenton Masterman
executiveWe're still a long way from putting out a resource update. That will take shape as drilling continues. But there are plenty of strike lengths for us to work with. And I think that's the genuinely exciting part, because it gives us some scale — so that if we do manage to grow a resource there, it represents a possible new mining front where we can raise production incrementally if everything comes together. And the aim there would definitely be to displace some of that low-grade stockpile currently sitting in the life-of-mine plan, pushing it further out into the future and growing our underground output at a much higher grade, and that's how we believe we'll achieve production growth going forward.
Meredith Schwarz
analystYes, that's great. And staying on the exploration topic, would you say that, looking across the whole portfolio, Cowal holds the biggest potential for more upside — exploration upside? Or is it roughly on par with Mungari and Ernest Henry? Would you say Cowal excites you the most? Is that basically how you see it from an exploration standpoint?
Glenton Masterman
executiveOnce more, that's a solid question. I'm enthusiastic about every part of it. Look, with Cowal, what we have — and Lawrie and Nancy brought this up before — is a world-class mineral system sitting at a fantastic geologic address. On the slide, we show a total endowment to date of just over 13 million ounces. Since it's a world-class system, I remain of the view that there's multimillion ounce potential still to unlock at Cowal. That's the exciting part. But looking across the portfolio, we're fortunate to have a full range of options when it comes to growth levers we can pull. We still have terrific targets that haven't been tested yet, not necessarily tied to extending the underground. So we have targets there that we plan to drill in FY '26. At Mungari, I'm really excited about some of the results coming out of the Genesis and Solana underground areas. And again, the approach mirrors Cowal, where we're looking to grow the underground resources and convert them into reserves. That's our higher grade. And if we can keep going not just at current underground production levels, but with incremental growth there at higher grades, that's clearly a key driver of Mungari's value, and it will also be a big focus for us in FY '26.
Glenton Masterman
executiveAnd finally, at Northparkes, I believe there's a chance we've discussed, especially when it comes to pinpointing fresh open pit mining zones that could either stand for or provide us flexibility within our life-of-mine plan, assuming we can keep that going. We've just restarted drilling at major time following a switch of the drilling contractor, and we're back drilling there to expand that resource or at least declare a maiden resource and keep studying it. So I'd say that's the number one target for a new open pit at Northparkes, and we sense we have plenty of runway for identifying additional ones.
Meredith Schwarz
analystThanks. Could I squeeze in one more question about Northparkes, regarding Major Tom and E51 — what's the soonest you think those could be incorporated into the mine plan? Since the open pits up there are obviously done. You've now got the open pit material, which will be processed over the next 12 months. So I'm just kind of looking at how you then bring those additional open pit sources into the mine plan to supplement the underground feed. Because my assumption is that E48 sublevel cave is scheduled to begin production in FY '27, '28 — is that right?
Lawrie Conway
executiveNo. So with E48, development is underway at this point. We'd anticipate that it builds up over the course of '26. Glen can speak to the status of those 2 deposits. But basically, moving forward, the combination of the current underground at E26, then E48 along with the stockpiles, is what's going to keep the plant full and buy us time on Major Tom, E51.
Glenton Masterman
executiveYes. Thanks, Lawrie. I believe we remain at the pre-resource stage at Major Tom and E51, Meredith. So the task is to finish the drilling phases we're currently working on. We'll model those. The aim is to determine whether we can actually optimize some open pits at both targets, and that will then guide what we need to do in the study. So I'd say you're really looking at a 3-year plan here in terms of what we can accomplish by bringing on some new open pits in that mining sequence.
Operator
operatorAl Harvey from JPMorgan has the next question for you.
Al Harvey
analystTurning to Cowal OPC — I remember being out there on one of the site visits at Cowal. There are several ways to go about developing the lake protection bund. I guess, given that Lake Cowal has some water in it, that raises the question of what a wet build would mean versus a dry one. So I just wanted to get a sense of where your thinking sits right now — how are you approaching planning for the bund at this point? And is there any sequencing risk in the planning if there's heavy rainfall during the build time frame?
Nancy Guay
executiveThanks for that — happy to take the question. So at this point, every bit of our planning has been carried out with construction in mind. However, for the North site and the South site, we have 2 construction stages. For the North site, the plan is for work to be completed in the wet area — that is, on the wet lake. So — and we've got solid codes from the contractor. We have experienced people. We've reviewed <<inaudible>> and are fairly comfortable. There are certain things — I should mention — risk mitigation, or mitigation plans, that are built into our schedule and our project time line. As for the South, this should be carried out during a dry period. It ought to be dry at that point when we're going to move into...
Al Harvey
analystThen perhaps over to Jake regarding Mt Rawdon Pumped Hydro — I was hoping to understand what those extra ounces within the pit might amount to, given the gentler pit wall angles, and how and when they'd actually enter production. My assumption is that it would arrive after CleanCo exercises that call option on FID, should it proceed.
Jacob Klein
executiveThanks, Al. Glen and I are both pretty keen to get more questions this morning, so there's stiff competition between us, and I appreciate yours. Look, I'd say it's early days. The reality is, as you may remember, we had originally contemplated a Stage 5 cutback at Mt. Rawdon's open pits, and we chose not to go ahead with it. So that's not because the mineralization ends there. It was really the cost — there is definitely gold at the bottom of the pit, but what really determines things is the shape of the low reservoir. Right now, wall angles at a mine — and Mt Rawdon is a clastic example — are obviously designed to almost fail on the final day of mining, whereas a lower reservoir really needs much flatter wall angles to last over the last 100 years. So quite a large earth movement and cutback to shape it is contemplated, but it's predicated on FID being achieved, the project going ahead, and then it will be extracted after construction of that low reservoir or during construction of it, because essentially we have the option of tagging trucks coming out of the pits during the cutback to send them to an ore stockpile or to a <<inaudible>> stockpile.
Operator
operatorDavid Coates from Bell Potter Securities has the next question.
David Coates
analystA lot of this has probably already been addressed. I’ll just cover the remaining part of FY — output for the remainder of this financial year. Our production was somewhat lower this quarter because of shutdowns, but — and you’re clearly on track for guidance. Still, you expect a modest increase with Cowal. It sounds like it’s nearly — the shutdown is nearly finished. So should we expect a slight increase in tractor for the last quarter?
Lawrie Conway
executiveYeah, you’ll see a little bit. As Matt mentioned, we had to draw the circuit down so the elution circuit upgrade could be completed during the shut period. That means we’ll build those stocks back up during the June quarter, as Matt said. So we wouldn’t say you get — we’re basically 15 days out in the March quarter, 15 days out in the April quarter thereabouts, in terms of that major shut in the elution circuit. So you’ve got roughly the same number of operating days, and you’ve got that circuit buildup. So you will see higher grades coming through from the open pit, which we’re building up through the March quarter, but we don’t expect it to be materially higher. From a group perspective, Matt said, Red Lake, you get that higher production; you’ll get less production at Mt Rawdon as we’re going through those stockpiles. You’ll see pretty consistent at Northparkes, Ernest Henry. And at Mungari, we’re going through that commissioning. Yes, we get the higher tonnage, but we’re processing very low-grade stock through the commissioning period. We’re tracking 1% above midpoint of guidance as at the 3-quarter mark; that’s a good indication of where we’re going by the full year.
David Coates
analystGreat, that's excellent. My second question—and this has been touched on somewhat—is whether you'd like to add a little extra, but on the use of cash. You sent a fairly clear signal with the interim dividend. You've sped up the debt repayments. Could you perhaps give us a bit of, I suppose, how you're thinking strategically about deploying cash and how those two options fit into that?
Lawrie Conway
executiveYes, Dave. Our dividend policy hasn’t changed since we did the interim dividend. We review that every 6 months. So what we aim to pay out is 50% of group cash flow. So because we’re seeing higher cash flows in the June quarter, that means dividends will be higher. The fact that we have $660 million in the bank and paid the dividend in April — that’s why we’ve begun accelerating the term loans, the higher cost debt. So we’ll keep paying those down while also maintaining flexibility on the balance sheet by sustaining a good cash level. I think if you then carry that through to our capital investment, where Kate mentioned that $750 million, $950 million, that’s roughly what we invest on average over the next 5 years. There’ll be years above it, years below it depending on where the projects are at. They’re multiyear projects. But that discipline of when we invest in those projects when we need it, not just because we’ve got the cash. And I think you might have picked up from Glen’s conversation, he’s putting his hand out for a bit more exploration money based on the drilling successes that we’re having.
Lawrie Conway
executiveThat is essentially how we approach it when it comes to capital allocation.
Operator
operatorHugo Nicolaci from Goldman Sachs has the next question.
Hugo Nicolaci
analystCongrats on the Pumped Hydro progress too. This is my first one, so just from observation, looking at that project summary table — a helpful addition to the report these last couple of quarters. It just looks like the Ernest Henry mine extension study is now this quarter, when it was June last quarter? Any sort of comments there on timing or what's caused that quarter slippage?
Lawrie Conway
executiveYes. Look, briefly on that, Hugo — as the teams near the end of the feasibility study phase and review the drill results we've received during the study, and making sure regarding the best approach to go below 1,200, we felt it was a good moment to give them time to complete all of that assessment. So, we're rolling that into the June quarter.
Hugo Nicolaci
analystYes, that's clear. Then, for my second question, I suppose, taking a somewhat longer view — I realize you already have quite a few projects on your plate, and with gold prices at current levels, there may be somewhat more upside when it comes to drilling and the timing of studies and so on. But I suppose, if I consider your total asset life based on the resource base as it stands, you likely still rank among those with the longest resource lives, both locally and globally, compared with some of your peers. How do you think strategically about what the appropriate mix of asset life should be, and where the constraints might sit relative to the mining rates you currently have?
Lawrie Conway
executiveYeah, that's a genuinely good question, Hugo. I mean, when we look at it, Ernest Henry and Northparkes have latent capacity in the plants. Those are high-returning assets. That's the first area we'll look at. We've obviously upgraded Mungari now, and the focus there will be on how we put more volume through from the underground. Similarly at Cowal, as Nancy mentioned, the potential of the underground and the role it plays — it's 30% of the feed. So the more we can get through the underground through that plant, that's where we get that potential. And then I think the other one is just when you look at the resource base, Northparkes has the largest. So therefore, are there opportunities for basically looking at expanding the processing rates without actually reducing the mine life materially. So those are the ways that we look at across the portfolio.
Operator
operatorMatthew Frydman from MST Financial has the next question.
Matthew Frydman
analystAnd Lawrie, you've already partly answered this in what you said to a few earlier questions, but let me try to pull it all together. There's the MROR update coming midway through the year. There are several material studies, as you were just describing, especially at Ernest Henry and Northparkes, plus some exploration work still underway, which Glen mentioned this morning. Sitting on top of all that, of course, is the gold price backdrop, the cash being generated and a balance sheet that keeps getting stronger. So there's potentially a lot of optionality when it comes to timing and payback on putting incremental growth capital to work and delivering those projects. So I suppose the question is, how are you thinking about bringing the results of all these different studies into one multiyear outlook for the business? Should we expect an update on that at some stage in FY '26? And really, is there anything beyond the studies you've laid out that you'd want to include in that kind of outlook before you present something to the market?
Lawrie Conway
executiveYes, Matt, thanks for assembling all of that. I mean, essentially, the dilemma we're working through as we put together our business plans and budgets is where all of this ultimately aggregates to. But I think the positive is that, viewed at a portfolio level, there's no pressure on us to speed up projects simply because of the current metal price or our cash position, since from an operational perspective they actually sequence very well. Mungari — that investment is now complete. It reverts to being a major cash generator as we move into the Cowal OPC, which can fund it and still produce cash for the group. We then look at going below the 1,200 at Ernest Henry over the coming few years and how that unfolds in terms of how we mine it and what it delivers below the 775 over the longer term. Northparkes, as I just said, how do we unlock the capacity we have there and then move beyond it. But with E48 and E26 running, and E22 fits in there, that's over the next few years, rolling through after those other projects, and Cowal is back into ore.
Lawrie Conway
executiveAnd so, when you consider all of those across the coming 5 years, they line up pretty nicely without introducing operational risk, and given where the balance sheet stands, we can therefore fund those projects. That average of $750 million to $950 million over the next 5 years remains valid. As I mentioned, some years we'll be above it. Some years we'll be below it. But provided those multiyear projects keep delivering to plan, we're very pleased with the direction we're heading on cash and the balance sheet.
Matthew Frydman
analystYes. So, is there any particular timeline we should look for on a refreshed multiyear outlook? Or are you content to simply let the results from the ongoing studies, as they come out, essentially speak for themselves regarding how they fit into the portfolio?
Lawrie Conway
executiveI think over the coming 6 to 9 months, as those studies wrap up and we work out what they mean for the portfolio — as we provide updates on them, we always layer in what that means for a group. So I don't think you're going to get a specific "here's everything" in a single update. You'll see them as studies or projects move forward. We show what benefit those projects bring and what that means for the portfolio. And Cowal today is a classic example. The economics are really compelling. It's the right time, it can fund it. It still delivers cash. But from a portfolio perspective, Mungari is now becoming a major cash contributor. So the capital we've been investing over the last few years at Mungari is being replaced by Cowal.
Operator
operatorThat brings us to the end of the question-and-answer session. I'll now return the floor to Mr. Conway for his closing remarks.
Lawrie Conway
executiveThanks, Ashley, and thanks to all of you for being with us today. It was genuinely pleasing to post another successful quarter, delivering to guidance and seeing that cash flow land in the bank account, which is helping us from a balance sheet perspective and allowing us to increase returns to shareholders, but also on the project side — the successful completion at Mungari, the approvals at Cowal and the progress at Mt Rawdon say that, from a company perspective, we're in good shape to finish the quarter, and we look forward to updating you in the coming months on each of these projects. Thank you.
Operator
operatorThat brings today's conference to a close. We appreciate everyone joining us. You're welcome to disconnect at this time.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Evolution Mining Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Evolution Mining Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Evolution Mining Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.