Evolution Mining Limited (EVN) Earnings Call Transcript & Summary

October 14, 2025

Australian Securities Exchange AU Materials Metals and Mining earnings 39 min

Earnings Call Speaker Segments

Operator

operator
#1

We appreciate everyone being on the line, and we’re glad to have you join the Evolution Mining call covering results for the September 2025 quarter. <<operator_script>> At this point I’ll turn the conference over to Mr. Lawrie Conway, our Managing Director and Chief Executive Officer. Please proceed.

Lawrie Conway

executive
#2

Thanks, Darcy, and good morning, everyone. On the call with me today are Matt O'Neill, our Chief Operating Officer; Peter Rocky O'Connor, our General Manager, Investor Relations; and Fran Summerhayes, who came on board a month ago as our CFO. We're delighted to have Fran with us, and her first month has been an impressive start. Fran will say a few words introducing herself shortly. Earlier today we published the September quarterly report, and that's what this call will reference. There are 3 key takeaways from today's call. First, we remain on track to deliver against our FY '26 commitments — across group guidance, production, costs and capital. Our projects are running on schedule and on budget, and our 5-year capital outlook is unchanged. Second, the sector has seen a structural shift, in both gold and copper. Gold's role as a financial reserve has accelerated, with central banks as net buyers of gold in 27 of the last 28 months. For the first time since 1996, central banks now hold more gold in reserves than U.S. Treasuries. On copper, short-term supply issues combined with a rising long-term demand forecast, yet no clear pathway to increased supply, are driving both near-term and long-term copper prices higher.

Lawrie Conway

executive
#3

Finally, Evolution, with its long-life, low-margin portfolio that includes 2 high-quality copper assets and minimal hedging, can capitalize on the present metal price conditions, put money into future growth, and produce high-margin returns for shareholders over the long term, not merely the coming few years. The September quarter was yet another period in which we delivered safely according to plan, and FY '26 is off to a very good start for Evolution. Regarding safety, we kept up the improving trend, with our TRIF staying under 5. Quarterly production came in at 174,000 gold ounces and 18,000 copper tonnes at a very low all-in sustaining cost of $1,724 per ounce for continuing operations. That result produced record net mine cash flow of $366 million along with our second highest operating mine cash flow of $676 million. Net mine cash flow for the quarter rose 23% against an increase of only 4% in the achieved goal. The advantage of copper within the portfolio is shown further by the price rising 15% during the quarter. A couple of record net mine cash flows worth highlighting are $55 million at Northparkes and $39 million at Red Lake, where the operation keeps delivering positive cash safely and reliably.

Lawrie Conway

executive
#4

What matters here is that the cash we produced during the September quarter came in at prices that sit well under where spot stands today. Compared with what we realized in the September quarter, spot is higher by $1,200 per ounce and by $1,300 per tonne. The 2 cash flow charts on the first page make the upside plain to see for the year, provided these elevated prices hold. On that basis, operating mine cash flow would exceed $3.3 billion, and mine cash flow before major capital would come in at roughly $3.1 billion — an improvement of approximately $570 million relative to the spot prices in place when we issued our FY '26 guidance in August. It would also represent $1 billion more cash flow than we delivered in FY '25. Group cash flow for the quarter came to $196 million. As we laid out on the June call, a working capital unwind was anticipated for the September quarter. During the June quarter, capital ran higher, largely tied to completing the plant expansion at Mungari, starting the OPC project at Cowal, and ventilation and truck work at Ernest Henry. That left us with a high liabilities balance of $35 million at the end of June, which was settled in the September quarter. We also carried $26 million more in receivables at the end of September, driven by larger volumes of concentrate sales still outstanding, compounded by copper prices rising during the quarter.

Lawrie Conway

executive
#5

That's actually a good thing, though, since we get those proceeds in the December quarter. We now anticipate that working capital movements will go back to a normal rhythm in which, on a full year basis, the movement <<inaudible>> each either as an inflow or an outflow. Our balance sheet flexibility got even better, with gearing now sitting at 11% and a cash balance of $780 million. Our disciplined capital management carried on through the quarter, with $170 million of our term loans repaid. After the quarter end, we paid the remaining $110 million. Those loans are now fully repaid, and we have no debt repayment commitments until FY '29. Turning to the projects front, Mungari has successfully finished commissioning the expanded plant and will be in commercial production this month. The final project cost is now forecast at $212 million, which is 15% below the original budget. With $43 million of net mine cash flow for the quarter, Mungari is well on its way back to being a material cash contributor for Evolution and quickly paying back the project investment. At Cowal, the OPC made solid progress during the quarter, with commissioning of the open pit trucks and completion of the Northern Lake Protection Bund.

Lawrie Conway

executive
#6

Things are still progressing on time and within the budget for this project. So with that said, I'll pass things over to Fran so she can introduce herself, and then Matt will walk us through how operations performed.

Frances Summerhayes

executive
#7

Thanks, Lawrie. It's a real pleasure to have come on board at Evolution Mining at what is a pivotal moment for the company and for the wider sector, particularly given the structural shift we're seeing in gold and the supply disruptions affecting copper. With metal prices on the rise and a clear strategic focus in place, Evolution is well positioned as one of the lowest cost gold producers, consistently and safely delivering robust margins and cash flows. During my first month, I've had the chance to visit 3 of the operations and to take part in Board meetings. What stood out for me is the depth of the safety culture and the openness and enthusiasm people across the business have for being part of Evolution. As the CFO, my initial focus is on listening, learning and building relationships, including with our current and future investors and the analysts who cover us. I bring a disciplined, value-driven approach to capital allocation and operational efficiency. It's an exciting time to be part of the Evolution team, and I am committed, along with the management team, in elevating the business and making a meaningful contribution to Evolution. Thank you. Over to you now, Matt.

Matt O'Neill

executive
#8

Thanks, Fran. As Lawrie mentioned, the September quarter came in according to our full year plan, and we're still on track to hit full year guidance, which lets us keep benefiting from the rising metal price environment. Over the quarter we produced 174,000 ounces of gold along with 18,000 tonnes of copper. And pleasingly, we achieved this at an AISC below what we had planned, which helped us generate a second consecutive record net mine cash flow. Despite these positive metrics, the area I remain most proud of is our safety performance. Happily, I can repeat a message I've given a number of times in these updates, which is to report that our performance in this area continues to be strong as evidenced by our total recordable injury frequency rate for the group dropping below 5. The consistency and predictability we are seeing in the operation continues to be built on the back of teamwork and collaboration across the entire Evolution team, and it's a credit to everyone involved. Our goal remains the same. We say, we do, we deliver, and I'm very pleased to say that I think we've done that this quarter. As I noted earlier, our operations have started the year in line with plan and remain on track to meet full year guidance.

Matt O'Neill

executive
#9

A few things worth noting for the quarter were that Cowal and Ernest Henry carried out their usual twice-yearly shutdown work. Wet weather also caused some small disruptions to open pit operations, or mining activities, at Cowal. Still, it was good to see the team's efforts on building resilience paying off, since we could keep the processing plant supplied from surface stockpiles at the mine, which meant no mill downtime and no feeding of subgrade material. Work on the OPC project is moving along nicely. And as Lawrie mentioned, the Lake Protection Bund was finished ahead of schedule, inside the September quarter. Red Lake, Northparkes and Mt Rawdon kept delivering in line with their plans. Mill ramp-up at Mungari carried on through final commissioning, which remains on track for completion this month. And I'm glad to say that, through <<inaudible>>, we exceeded our expectations, and the site team is really excited about what they can achieve with the new plant. That concludes the formal portion of our update. I'll now pass things back to Darcy for questions.

Operator

operator
#10

<<operator_script>> Our first question is from Kate McCutcheon at Citi.

Kate McCutcheon

analyst
#11

To begin with Ernest Henry, you provided the update. The shaft is now filled through 2040 and beyond, and you deferred that $200 million of CapEx beyond the upcoming 5-year profile. That is a strong result. How should I think about the added expense for the AOF material that will be hauled by truck, since I would expect that to cost more? If we considered the mining cost per tonne at Ernest Henry as it stands today, roughly the mid-30s in real terms, what would that be under the revised plan? Or is there anything you can share on that?

Lawrie Conway

executive
#12

Sure, I'll let Matt take that question.

Frances Summerhayes

executive
#13

Yes. Thanks, Lawrie. As for the alternate ore sources, Kate, they come from a range of different locations. Many of them will actually be handled through the existing materials handling setup. That means they'll go via the passes back to the crusher, just as we did when those levels were first mined. A few of them we'll truck, moving them a bit farther into those passes. So there isn't much of a material shift. We're not hauling the material out of the pit. When that operation first began, we were trucking everything all the way up to the surface, which clearly nearly doubles the unit cost. That isn't what we're doing with the alternate ore sources. We'll do some rehabilitation, and then we'll return to the old approach of using the passes. Sorry, the last — below — below the — sorry — once we get beneath the crushing horizon, which is the area we're in now, we will be trucking back up to the crushing horizon, and that has a dedicated truck loop. Again, it's only a fairly short level, about 25 meters between levels. So clearly, as we go deeper, we'll add more trucks and ventilation, which we've more or less documented quite well over time.

Frances Summerhayes

executive
#14

Even so, that still doesn't take them outside the pit, which means there's no significant shift in unit cost.

Kate McCutcheon

analyst
#15

All right, understood, and that's useful. So at Cowal, now that the northern lake protection bund is complete, could you bring the southern bund forward and combine the two? I don't want to get ahead of ourselves, but do you see room to narrow that open cut feed gap later this year, or is there a risk it goes the other way?

Lawrie Conway

executive
#16

Kate, that was well put—just like a solid engineer would say it. Yes, the work has been completed. The site team is now evaluating whether we proceed with the southern lake bund as well. But yes, it isn't required. Still, considering the works and how far we've come on the northern side, they'll take a look at it. We're aware of this, and we've mentioned it before. Should we actually need to carry it out as a wet move on the southern bund—the project was designed for dry—you're looking at $40 million to $60 million in additional capital beyond the project budget, though it would give us access to the southern area. So that's something we'll be assessing over the next 3 to 6 months.

Operator

operator
#17

Daniel Morgan with Barrenjoey has the next question.

Dan Morgan

analyst
#18

My attention is sort of on the bund and the OPC as well. What advantages would there be in moving up the southern access, getting into those open pits? Could you help us frame the timing and rough scale? I realize you just described an extra expense if the move is wet. Still, with gold prices at current levels, accelerating that possible output looks fairly advantageous, doesn't it?

Lawrie Conway

executive
#19

Yeah. Look, I’ll pass that over to Matt, Dan. I’d say on that one — from an overall operational standpoint there are 2 things: when the time comes for us to do that in a few years, if you get a couple of wet seasons, then what effect does that have on how long it takes and what it costs to actually carry out that Bund versus doing it now while we’ve got the access. It does give us more flexibility on the site. But Matt, do you want to cover what it means operationally with the pits?

Matt O'Neill

executive
#20

Yes. It really comes down to flexibility, Dan. But nothing would show a material rise over the coming 12 to 18 months. Naturally, we are aiming to bring the northern area forward. And the work they finished in the first quarter has let us get somewhat further ahead than before. The southern one will unlock some additional, different material as well — it opens up some oxides, which we do enjoy treating. It does support our throughput. So it's an option we intend to pursue. But once more, it carries that price tag. So the question is when those extra ounces arrive to offset the stockpiles we plan to treat now. And right now, it doesn't fall inside the next 12 or 18 months, simply given where you'd place it.

Lawrie Conway

executive
#21

To put it briefly for your models, Dan, as Matt mentioned, there's nothing across the coming 2 years. If we were to reach that decision and inform the market, we would essentially lay out what it means for years 3 through 5.

Dan Morgan

analyst
#22

Yes, that's quite clear at this point. On — just remaining with Cowal and the nearer-term picture. Obviously, with the wet weather, it appears you saw some effect from the pit floor, simply having access to it on a temporary basis. Where does access stand right now? And should we be looking for that high-grade ore to arrive during this quarter, or maybe in the second half of the fiscal year?

Matt O'Neill

executive
#23

Yes. So access has been restored. We had somewhere between 1.5 and 2 weeks of impact in the pit during the quarter, mostly in September. We've gotten ourselves back to a pretty tight spot. As most people are probably aware, things get quite tight when we reach the bottom of that pit. Normal operations have resumed. We expect to see a pickup in the next quarter, and then we'll carry that through until that pit is done. Nothing has changed regarding the fact that this financial year is when that pit will be finished, and after that we'll move on to the stockpiles.

Dan Morgan

analyst
#24

And then just one last thing on Mungari — just the most recent live update on the ore sources ramping up in step with the mill expansion.

Matt O'Neill

executive
#25

Yes. So we're ahead on the ore sources. Castle Hill has performed really well. The team there working with NRW has done a fantastic job. So we're very pleased with where that stands, and we now have sufficient stocks ahead of the mill. We're putting it through its final stages of commissioning, almost as we speak, with varying types of material, hardness, and locations. So everything is doing quite well. And that's -- I'm fairly confident that by the end of October, we'll be in a good spot with that mill commissioned, and we'll be off and running, and we'll have enough feed to achieve what we need to achieve.

Operator

operator
#26

Andrew Bowler with Macquarie has the next question.

Andrew Bowler

analyst
#27

Let me ask about capital returns. You laid it out on the front page, and I believe it's fairly evident to everyone that should gold prices hold, you'll have net cash by the close of the financial year. Once you're back in that net cash position, is a review of the capital returns policy something you'd consider? Or is this very much a story of reinvesting in some other projects potentially — for instance, bringing a block cave forward a little sooner than anticipated at Northparkes, and so on? Or would you direct that surplus cash toward the capital returns line item?

Lawrie Conway

executive
#28

Yes. Andrew, honestly, having the gold price climb this quickly is a nice dilemma to face. At the August call, we noted that with gearing having reached 15%, we are now coming down toward 10%. That means we need to consider how we handle capital returns for shareholders. We will address that at the half year, when we review the interim, and again as we move into the second half of the year. Our approach of distributing roughly 50% of cash flows, I believe, continues to serve us well, and that leaves us with some options to examine. When you mention capital, our 5-year capital outlook includes a block cave at E22 that we are bringing forward. It had been scheduled for a decision in FY '27, so it would not actually alter our capital spend across the next 5 years in any case. But as I mentioned, once we reach the half year, we will talk with the Board about what we do regarding those returns.

Andrew Bowler

analyst
#29

Got it. One more question from my side. Of course, the media covered it during the quarter — there were ongoing problems with electricity supply around Kalgoorlie. If I recall correctly, Mungari draws its power from the local grid near Kalgoorlie. Could you walk us through whether that had any effect and what kinds of mitigation measures exist? Are you considering a backup plant, or possibly raising renewable penetration there to help smooth out those reliability problems Kalgoorlie is currently experiencing?

Matt O'Neill

executive
#30

Yes, this is Matt. We certainly experienced disruptions at Mungari because of the power problems that have been happening there. So we had several shutdowns — some planned, though with fairly short notice, and others being load shedding events that forced us to take the plant down. We do have a partial backup supply in place. We've got some generators thanks to the new investment. So we use those to keep the plant alive, but it doesn't run the mill, to put it that way. It prevents the sanding and the operational problems from arising. So yes, it did have an effect. We lost quite a few days — close to a week, if you will — due to the interruptions on the power side there as well. As for options going forward, we're like everybody else in that region. We'd like the government to take action on it. But also we would — we're examining what options are available to us. I know other companies have done things themselves. So we're looking at all our options, because those interruptions, we don't see them changing in the short term.

Operator

operator
#31

Hugo Nicolaci from Goldman Sachs has the next question.

Hugo Nicolaci

analyst
#32

Starting with Mungari for me, if that's alright. It seems processing costs there are still mostly being capitalized. Given that your processing rates have ramped up, should we expect that to normalize starting from this quarter onward? And on a per tonne basis, where do you see those processing costs normalizing to?

Lawrie Conway

executive
#33

Yes. Would you like to take that one?

Matt O'Neill

executive
#34

Yes, you're going to see it ramp up — sorry, ramp up. You're going to see it capitalizing, and you're going to see it come up. We had a forecast of reducing AISC by about 16%, I think that was a number, which at the moment, we see it in line with when we're looking at what we're looking at. So we'll keep running it in full mode for the next probably 2 quarters before we can give you a really good steer on where it is. But yes, it's in line with what the project expected. And at this stage, we haven't come up with any material variances in what we thought it would cost.

Hugo Nicolaci

analyst
#35

Understood. And then just one more about cash generation. I suppose I’m trying to understand where costs might normalize going forward. You noted at the outset, of course, the strength in commodity prices for both gold and copper. But when I look at major cash generation before major capital, it is clearly lower quarter-on-quarter. Could you provide additional detail on the timing of those copper payments you mentioned, and then on where costs might normalize from here?

Lawrie Conway

executive
#36

Yes. So, a few points on that, Hugo. I mean, regarding costs — the sole meaningful shift you'll observe in operating costs going forward is what Matt mentioned about ramping up production at Mungari. And so those processing costs will be roughly $16 to $18 a tonne in the second half of the year, and the all-in sustaining cost comes down the actual operating costs as we go forward. The other main driver will be obviously royalties on the gold and copper revenue. So we don't anticipate much change through the balance of the year. The guidance, as we've said, $1,720 to $1,880 remains in place. In terms of the concentrate, so it's different at each of the operations. So Ernest Henry has now reverted back to a 1-month quotational pricing period. It was — at the end of June, it was on a 4-month. So the shipments, therefore, will be settled within basically 60 days rather than 120. So that is why that receivable balance will come down through the December quarter. Northparkes is on a 3-month pricing period. So that's not going to change too much in terms of the 10% final payments that we receive, and it is then going to be driven on shipments.

Lawrie Conway

executive
#37

We had a strong quarter for shipments. This quarter at Northparkes we made 4 shipments, whereas in the prior quarter there were only — I believe it was 2. So as I mentioned, that should begin to settle down around our working capital.

Hugo Nicolaci

analyst
#38

And then finally, regarding Cowal and the throughput at that operation. Given the somewhat reduced throughput in this quarter, could you give us some indication of how tonnes and grade are likely to shape up for the remainder of the year? And in relation to that guidance, should we anticipate that you will keep processing the higher-grade material from the stockpile so as to maintain that throughput grade of 1.3 to 1.4?

Matt O'Neill

executive
#39

Yes. In short, yes. We'll see it return to that range at a somewhat higher level. And given where we are in the pit and the access back in the — it will go back to the normal operating range until probably quarter 4, when we see the pit finishing, but we also see that offset by the underground ore ramping up through there, and that is proceeding according to plan as well. So yes, it will rise from first quarter, but it will remain within the normal ranges you would expect for the guidance.

Operator

operator
#40

Baden Moore of CLSA has the next question.

Baden Moore

analyst
#41

On the CapEx guidance, it sounded as though you're considering pulling some production forward, or at least evaluating your growth options. With the 5-year guide at $750 million to $950 million, do you believe that figure still makes sense today, given where your cash flow is running and the fact that the market seems to be signaling it's time to produce more? And perhaps just a second question: I was wondering whether there's any shift in how you're thinking about raising utilization at your Ernest Henry mill, now that you have some certainty about what's happening in Mt Isa.

Lawrie Conway

executive
#42

Yes. So Baden, on the CapEx profile — that $750 million to $950 million across the next 5 years, as we've laid out before — and of course, the deck we released at Denver sets out every one of the projects. I mean, we have E22 at Northparkes, the OPC at Cowal, the Bert ore body at Ernest Henry; all of those projects appear in it. So any pulling forward of capital purely because of metal pricing would, at this stage, be incremental. And then, regarding utilization at Ernest Henry, that's the study underway at Bert, which lets us enter from the open pit and exit through there instead of relying on the materials handling system, so that we can achieve greater utilization of the capacity installed there.

Baden Moore

analyst
#43

So I just want to make sure I've got this right — there isn't any read-through here that you'd be reviewing as it relates to that $750 million to $950 million across the next 12 months?

Lawrie Conway

executive
#44

Only if other projects come into play. And, as I said a moment ago, moving that southern lake bund work at Cowal ahead of schedule would mean extra capital that isn't included in the 5-year outlook. Then, should we make any further decisions at each of the assets, we'd update you if that capital changes. Still, the capital we've laid out for the next 5 years is enough for us to deliver those growth projects at each of the assets.

Operator

operator
#45

Matthew Frydman of MST Financial has the next question.

Matthew Frydman

analyst
#46

Perhaps I could start with a two-part question about costs at Cowal. Obviously, there's been a fairly significant quarter-on-quarter jump in AISC, which is running somewhat above your guidance range. Could you walk us through what's driving that? I mean, is it purely the shutdown activity and the rain you mentioned? Or is there something else that really needs to normalize over the coming quarters to get unit costs back within the guidance range? And I suppose the second part is perhaps taking a slightly longer-term view. How should we think about mining cost and AISC as we approach the end of the year, when the open pit wraps up and obviously, you move to more stockpiles? Clearly, there are quite a few moving parts there with the stockpile drawdown, the OPC being capitalized, et cetera. So what does all of that mean for how we should think about unit costs relative to, I guess, the actual cash expenses coming out of the business into the back end of the year?

Lawrie Conway

executive
#47

Matt, that covered a great deal of ground in a single question. Let me do my best to work through it for you. After that, if Matt wishes to add something — Matt on our team, I mean, not you — then we'll bring that in. The first point I'd make is that you have to consider Cowal: across the years, it has hit its numbers. It remains on track to meet guidance. The first quarter was always going to include the maintenance shutdown and therefore weaker production, but you also have the maintenance costs. That has pushed the all-in sustaining cost higher. As Matt said, we lost 1.5 weeks, 2 weeks because wet weather forced us to draw on stockpiles. For this quarter's cost, that's a noncash draw of lower grade material, though costs will decline as we continue mining the pit out over the remainder of this year and replace that stockpile material. So if you step back, we will land within the guidance range. We're on track for that. Higher costs in the first quarter were anticipated. Moving into the following year, we will be processing stockpiles as we wrap up mining at E42.

Lawrie Conway

executive
#48

This should run roughly 18 months to 2 years. As a result, your costs measured on an AISC basis will be pretty comparable, maybe even somewhat higher, since the grade of that stockpile material declines as you work through it. But let me pull you back to the larger picture. I understand you <<inaudible>> are looking at Cowal, where operating cash flow for this quarter came in at $215 million. Annualized, that works out to $860 million, which exceeds what we produced last year. And if you take that and layer on the gold prices, for the remainder of the year you're likely looking at somewhere around $250 million to $270 million in additional cash flow. So it's almost as though at Cowal you purchase 4 quarters and receive a fifth one at no cost, since it would throw off over $1 billion in operating cash flow, in exchange for the $100 to $200 an ounce hit to AISC from the noncash inventory — I'll take that operating cash flow every day.

Matthew Frydman

analyst
#49

Right. Understood. You hinted earlier that as we head into next year with the lower-grade stockpile, AISC will be roughly flat or perhaps even somewhat higher. Still, when it comes to the business's actual cash generation, as you're suggesting, that ought to improve substantially, since on an expensed basis those stockpiles have already been paid for.

Lawrie Conway

executive
#50

Absolutely. And to be clear, next year we’ll spend a full year processing lower-grade stockpiles, so production is going to come down. As a result, AISC is going to be somewhat higher on a noncash basis, but I’d expect cash flows before the investment in the OPC to be fairly similar—obviously, operating cash flows will be very solid.

Matthew Frydman

analyst
#51

Right, right, absolutely. Okay, that's completely clear. And then perhaps just briefly — you mentioned in the text that the underground operation at Cowal is increasing toward 30% of mill feed. As I recall, you previously stated the goal was 2.4 million tonnes per annum. Does that figure still hold? It seems as though, if you're feeding — based on whatever your throughput rate is, if 30% of mill feed is coming from there, perhaps there's actually a bit of upside risk on the underground side. How should we, I suppose, think about your aspirations in that regard?

Lawrie Conway

executive
#52

I’ll pass it over to Matt so he can explain where the underground fits in. We aren’t really upgrading that. That happened this quarter. So then, clearly, since we — we had the mill outage for maintenance during the quarter. So as we brought it back online, the underground received priority feed ahead of the open pit. And definitely, while we were out for the wet weather, the underground received priority feed. But Matt, would you like to discuss the broader picture of the underground feed?

Matt O'Neill

executive
#53

Yes. So it was a pretty solid quarter at the underground, with total material moved rising to a level we're fairly comfortable with. We're going to be running at 2.3, 2.4, and we've seen the team on site able to deliver that. So at this stage there are no plans to go beyond that. Obviously, we're looking into what can be done with where everything sits, but that's where it still stands, and we're comfortable that it's achieved or achievable with the team we've got.

Operator

operator
#54

<<operator_script>> Our following question is from Alex Barkley of RBC.

Alex Barkley

analyst
#55

One question regarding the Ernest Henry feasibility study. First, I just want to confirm whether it has been completed and whether it might be released at some point. And then, could you discuss some of the updates relative to the PFS, perhaps regarding extensions to the mine life or changes in grade? Any details would be helpful.

Lawrie Conway

executive
#56

Yes. Thanks, Alex. I’ll have Matt add some detail here. The feasibility study has been completed. And as we’ve indicated, basically, given how much ore we’ve identified beneath the existing 1,175 level and the location where we intend to place the materials handling infrastructure, that area is now full of ore. So that means the infrastructure needs to be positioned deeper within the cave, and that work is going to happen over roughly the next 12 to 18 months. But basically, the result is that we keep on mining. We mine beneath the 1,175 level and we haul it back up to the materials handling system. And as Matt mentioned earlier, we will also be mining additional ore sources that have been identified and that we can use the existing materials handling system for. So there isn’t really a specific outcome from the study as such, because basically what we’re doing is expanding ventilation and refrigeration, bringing in trucking, and carrying out development. So it’s really just a continuation of mining, since we aren’t adding any of that infrastructure, and that takes the $200 million out of the next 5-year capital profile. And that’s essentially what the study’s outcome will be. Do you want to discuss the mining? And one of the key things that emerged from the study is that we actually keep the plant full through to 2038, whereas the PFS had it declining from around 2033 through to 2038.

Lawrie Conway

executive
#57

So at this point it keeps that filled at 6.8 through 2038. Do you want to focus just on, say, the mining side?

Matt O'Neill

executive
#58

Yes. At this point, the mining method is unchanged. Material beneath the crusher horizon is extracted by sublevel caving and trucked back up to the crushing level. There’s no meaningful shift in grade. Honestly, a few spots have shown somewhat more gold, though you wouldn’t regard that as a material difference from what we’ve mined to date. So overall, the drilling carried out for that study indicated, in a positive sense, that considerably more is present. The task now is figuring out where the infrastructure should go. That effort continues, and it won’t disrupt the current operations for a good number of years still.

Alex Barkley

analyst
#59

Alright, that's really useful. Just one more thing about the Mt Rawdon hydro project. Last quarter you made some remark regarding the Queensland investment, but there wasn't one this quarter. What's the reason for that? Could you give us a brief update on where the project stands and its timing?

Lawrie Conway

executive
#60

Right, Alex, so things are still progressing as expected. If you’ve seen what’s come out of Queensland over roughly the last 4 to 6 weeks, they’re taking a fresh full look at some older other renewable energy projects and putting their attention there. Our own project remains on track with respect to the commitment. Government-funded work is underway on site, and the expectation is that during the March quarter of next year we’d receive something like a final outcome regarding the government exercising that option on the project.

Operator

operator
#61

<<operator_script>> Our following question is from Ben Wood with UBS.

Ben Wood

analyst
#62

Several of the questions have already come up. But I suppose mine concerns the gross debt from this point, given that there are no obligations until FY '29, as kind of laid out in the release, yet the 100% pay down continues this quarter. How are you kind of thinking, I guess, about paying down gross debt from here with respect to the capital allocation piece that Dan sort of asked about earlier, and just kind of noting that the gearing situation has improved a great deal compared with even 12 months ago. So how are you thinking about that?

Lawrie Conway

executive
#63

Yeah, Ben — like I mentioned before, it's a nice issue to be dealing with. On gross debt, the upcoming repayment doesn't come until FY '29. Since those are U.S. private placement notes, prepayment isn't possible. So no further gross debt will be retired between now and FY '29. That repayment is $273 million, falling in the first half of FY '29 — that's essentially the next one on the schedule. As for what we do with the cash we're generating today, that's something we'll bring to the Board for discussion at the half year and then again at the full year. As you'd have noticed over the last 2 years, with gearing declining, dividends have risen. And because cash flow has grown on the back of pricing, we've kept lifting the dividend too. We expect that to keep going. How we deploy the surplus cash will be discussed over the next 6 to 9 months.

Ben Wood

analyst
#64

It's useful to know that early prepayment isn't an option until 2029.

Operator

operator
#65

That brings us to the end of the question-and-answer session. At this point, I'll return the call to Mr. Conway, who will offer some closing comments.

Lawrie Conway

executive
#66

Thanks, Darcy, and I appreciate all of you taking the time to join us on the call today. We've completed another quarter that was both safe and steady, establishing the groundwork for FY '26 and remaining on track to meet guidance, and we're certainly making sure to capitalize on today's elevated metal prices, whether that's gold, copper, or silver. Thanks for being with us today.

Operator

operator
#67

Thanks. That brings today’s conference to a close. We appreciate your participation. You’re welcome to disconnect at this time.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Evolution Mining Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Evolution Mining Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Evolution Mining Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.