Fervo Energy Company (FRVO) Earnings Call Transcript & Summary
November 9, 2026
Earnings Call Speaker Segments
Paxton Detwiler
executiveThank you, and good morning to all of you. It's a pleasure to have you with us for Fervo Energy's third-quarter 2026 earnings call. With us on the line today are Tim Latimer, our Co-founder and Chief Executive Officer, and David O'Very, our Chief Financial Officer. Ahead of getting started, I want to remind each of you that this discussion today is going to include forward-looking statements as defined under applicable securities laws. Such statements represent management's present expectations and assumptions, and they carry known and unknown risks along with uncertainties that might lead actual results to differ materially. I'd ask you to please refer to the forward-looking statements and risk factors that are disclosed in today's earnings release and in our filings with the SEC. On top of that, certain non-GAAP financial measures may be part of today's discussion. Where applicable, reconciliation tables appear in the appendix of the earnings release. With that, I'll hand things over to Tim to get us started.
Tim Latimer
executiveThanks, Paxton, and good morning, everyone. I want to begin with the quarter's biggest milestone: our first GeoBlock at Cape Station has entered commercial operation, sending power to the grid and earning revenue under our power purchase agreement. Not long ago, enhanced geothermal was just a concept, recently demonstrated through a pilot that had only just started running. As of today, it's a 33 megawatt power plant consistently supplying clean, firm electricity. Back in August, I laid out four yardsticks for our progress: the strength of the pipeline; how well and how fast our modular strategy delivers for customers; our social license in the communities where we build; and field execution. We improved on each of the four this quarter, and Cape Station demonstrates it most plainly. The first GeoBlock at Cape Station is the first greenfield enhanced geothermal development anywhere to reach commercial operation, and construction took just 23 months. It proves enhanced geothermal can provide dependable, carbon-free electricity at utility scale. We’re convinced that applying modular methods and top-tier ongoing improvement to infrastructure building will lead to faster completion schedules. And we’re pleased that our first GeoBlock was finished ahead of plan—an initial move toward making good on that commitment. On today’s call, I’ll first cover the beginning of operations in detail, then discuss our recent power purchase agreement with Google, which we think is the biggest enhanced geothermal PPA executed so far. I’ll also talk about ongoing operational achievements at Cape Station, favorable policy conditions, and advances throughout our project pipeline. But first, I want to start with safety. Whatever we construct means nothing unless we construct it properly. Our total recordable incident rate for the trailing 12 months is 0.10 at present, and that's happening while we ramp up both construction and operations at Cape Station. Also this quarter, the crew building our facilities hit a significant milestone: 1 million hours worked with no recordable incident. The people constructing our GeoBlocks take on complicated, physically demanding tasks — work at heights, hot work, and being out in the weather — so that reliable clean energy gets built here in America, and we're extremely thankful for what they do. A million hours with zero recordable incidents shows how seriously we treat this work, along with the tools and processes that make it possible to do it safely. At Fervo, we've stated our goal is to demonstrate that a company can drive innovation at the leading edge while also excelling in health, safety, and environmental performance. This achievement offers compelling proof that safety and innovation are compatible; returning now to Cape Station. We announced commercial operation at our inaugural GeoBlock on September 30th, which came in ahead of the deadline set by contract. Grid synchronization occurred on September 24th, and as of today GeoBlock 1 is producing revenue under its PPA. Within a mere 23 months, we converted a bare parcel of land into a completely functioning power unit. For customers, utilities, regulators, and fellow developers, this milestone sends an unmistakable message: enhanced geothermal is now being supplied at utility scale. We leveraged the science and intellectual property that had been validated at Project Red to construct a full-scale GeoBlock of 33 megawatts—one that is now fulfilling our PPA, supported by project finance, and which we completed on schedule. Cape Phase 1 remains at an early point in its overall operational life cycle, yet although our pilot demonstrated the building blocks of EGS, information coming from Cape Phase 1 is beginning to verify the advantages of operating EGS at scale. GeoBlock 1 is meeting our operational expectations, covering both production performance and the power supplied under our PPA. To put it plainly, the brine is arriving at the power plant at the volume and temperature it was designed for, and we're selling electricity according to plan. GeoBlock 1 has given us the blueprint—it taught us about the commissioning sequence, equipment and controls, contractor coordination, and regulatory approvals. We've executed that blueprint once, and now we'll execute it repeatedly, improving every time. GeoBlocks 2 and 3 remain on the schedule we outlined at our IPO. Mechanical completion has been reached at both. Grid sync has been achieved at GeoBlock 2—a significant milestone marking the conclusion of hot commissioning. The plant is now in tuning and early operations, exporting test energy to the grid. GeoBlock 3 is right behind it, now in cold commissioning — that's the phase where the mechanical and electrical systems get tested prior to brine being brought in. Commercial operation for these GeoBlocks is still anticipated by January 1st, 2027, and that maintains our trajectory toward roughly 100 megawatts of firm, clean power delivered from Fervo's first three GeoBlocks by 2027. As we roll out our repeatable GeoBlock delivery model to additional geoclusters, in Utah as well as other states, we anticipate efficiencies compounding on both speed and cost. We are confident that, over time, GeoBlocks can be built and commissioned in under 18 months. That leads me to something we now refer to as Cape Google 400: GeoBlocks 4 through 11, the following eight units from our factory model slated to reach Google in 2028 under the PPA we recently signed; delivery of these GeoBlocks remains on schedule for the middle of 2028. Now let me walk through the specifics of that deal; back in September, we announced an agreement we consider the biggest enhanced geothermal power purchase contract executed to date. It runs 15 years on a take-or-pay basis, which means Google must pay for this power no matter what happens with their data center plans in Beaver County, and the terms stay fixed for the entire contract term. This deal is for about 396 megawatts, and it comes in four tranches of 99 megawatts apiece. Commercial operation is targeted to start in mid-2028, and all of the GeoBlocks are targeted to be online before 2028 ends. Building is already underway, and I'll share that progress shortly. Beyond the 396 megawatts already contracted, we also agreed to give Google an option to expand by roughly 600 megawatts, which takes the whole thing to 1 gigawatt. Let me walk through how delivery works under this deal, since the structure matters just as much as the size. That signed 396 megawatts is the first layer, and at the outset it's connected to the grid. From Fervo's side, it's a firm, binding, financeable contract we can build against starting now, backed by parent guarantees from both Fervo and Alphabet. From Google's side, we think grid connectivity means the electricity they're purchasing holds value no matter how much of it they actually consume, since Google can monetize that power in the wider market. That's the whole purpose of this structure: it brings down project-on-project risk. We construct Cape Station on our timeline, Google can build their prospective data center on theirs, and neither side is waiting around for the other. The second layer — the 600 megawatt expansion option — sits behind-the-meter. Whereas the 396 megawatts are grid-connected, for this expansion Fervo and Google are going after direct-to-load delivery to the prospective regional data center. That would fall under Utah's SB 132, a framework allowing large-load customers to hook up directly to new generation, with safeguards in place for existing ratepayers. Our joint effort to obtain regulatory approval is already in motion, and we'll provide updates as things move forward.
Tim Latimer
executiveAll of this work gets our full dedication to openness and meaningful involvement of stakeholders, just as we apply throughout the remainder of the company. Our collaboration with Google follows the Geothermal Sustainable Development Pact — those voluntary standards I mentioned during the prior quarter. Back in October, we attended Google's community gathering at Milford High School, where 250 neighbors showed up to find out about the possible data center and pose questions; we feel good about where we stand so far, take pride in working alongside Google, and consider it an honor to operate within a community of citizens who are engaged and invested. Naturally, every bit of what we do ultimately comes down to execution in the field. I'll now move to construction. Cape Google 400 is proceeding on schedule across all eight of the 50 megawatt GeoBlocks, which represent our standard design from here onward. As I noted, we anticipate the first power out of those GeoBlocks in mid-2028, climbing to roughly 400 megawatts before that year is over. Since the prior quarter's call, the initial batch of 50 megawatt turbines has cleared factory acceptance testing, and we've taken delivery of key equipment consistent with our development plan, among it recuperators and more than 60% of all air-cooled condensers. Turning to the subsurface, four H&P Flex3 rigs are now operating at Cape Station. Drilling on GeoBlocks 4 through 11 stands at about 18% complete. Results from drilling keep getting better as we put more wells down using our 3.0 design. Keep in mind that the 3.0 design involves stretching laterals out to 7,500 feet, increasing the lateral diameter to 8 5/8-inch casing, and aiming for an average reservoir temperature of 430 degrees Fahrenheit. Every one of those adjustments yields greater power capacity by way of higher flow rates and higher temperatures. Lower costs and greater production don't come from some single breakthrough; they come from deliberate, repeated refinement, in which modest changes build on each other into substantial gains in productivity. Dissolvable plugs together with a redesigned toe prep cut down completion time and complexity. Rotary steerable systems plus insulated drill pipe let us get to deeper, hotter rock without any slowdown. Buying at scale is generating cost efficiencies on our surface equipment, where our ORC framework with Mitsubishi Heavy Industries, via its Turboden subsidiary, delivers improved pricing and dependable delivery schedules for the equipment at the core of every GeoBlock. No one action alone will carry the day on bringing costs down. What Fervo is showing is that, thanks to our disciplined approach to development and our commitment to getting better continuously, we keep taking costs out of the system. Consequently, we are positioned to hit $5,500 per kilowatt of installed capex for GeoBlocks 4 through 11. Our longer-term goal stays at $3,000 per kilowatt; we remain sharply focused on returns-oriented deployment of capital, in which every dollar spent has to justify its economic value. During the prior quarter, we discussed directing modest amounts of capital toward this effort. One thing we've pinpointed is that if we pair fairly modest volumes of solar with our GeoBlocks to serve our station auxiliary load, we boost the quantity of high-value geothermal power we can sell under our PPAs. We anticipate finding more opportunities of this kind, where our repeatable playbook lowers costs and lifts returns. Now I'd like to discuss policy developments. At the federal level, geothermal keeps drawing bipartisan backing—support that has been remarkably wide and lasting from one administration to the next. The Department of the Interior recently instructed the Bureau of Land Management to permit specified early exploration work through expedited approval. When we announced our 396 megawatt power purchase agreement with Google, Interior Secretary Burgum congratulated Google and Fervo, describing it, quote, "a powerful example of how geothermal can deliver more reliable, affordable, secure, around-the-clock American energy," end quote. The Department of Energy reinforced that backing by choosing Fervo for two potential grants worth roughly $20 million combined, to fund exploration drilling work. Pending execution of definitive funding agreements, these awards would speed capital toward assessing prospects in Idaho and Nevada for full-scale enhanced geothermal development. The Idaho award stands out because it would finance our first appraisal wells in that state, marking Fervo's entry into a new geography and giving us a chance to assess fresh geothermal resources there with government backing. Recognizing geothermal's remarkable potential, Congress has moved forward with meaningful bills covering permitting, commercial deployment, and R&D, each enjoying wide bipartisan support. Now let me zoom out and talk about our commercial pipeline; we currently hold 1,054 megawatts of binding power purchase agreements, equal to roughly $11.9 billion in contracted revenue. Including the Google PPA, that's a rise of 396 megawatts, or about 60%, versus last quarter. That binding backlog tells only part of the story. Past those executed agreements, we have an active pipeline of conversations spanning utilities, industrial customers, and hyperscalers. Such broad demand underscores how pressing the need is right now for firm power that can be brought online fast. Roughly 35% of those ongoing discussions involve utilities and load-serving entities, 15% involve large-load industrial buyers, and 50% involve data centers and hyperscalers. Our power delivery strategy will keep mixing front-of-the-meter and behind-the-meter development. Grid-connected assets stay the backbone, yet behind-the-meter offers customers a quicker route to power when transmission timelines slip behind their needs. Each of our geoclusters is designed for eventual grid interconnection—this isn't an either/or decision; it's about bringing customers power as fast as we can. Before I pass it to David, I want to mention that it's been roughly six months since our IPO, so it seems like a good moment to compare where we began with where we are now. We began with a 3 megawatt commercial pilot. As of today, with our first GeoBlock running at Cape Station, we've got 36 megawatts in place altogether; we held 658 megawatts of contracted power purchase agreements, and now that figure stands at 1,054 megawatts. Revenue backlog has climbed from $7.2 billion to approximately $11.9 billion; we lifted our 2030 capacity goal from 1 gigawatt up to 1.1 gigawatts. Our estimated resource potential has increased from around 40 gigawatts to more than 58 gigawatts. Net geothermal leasehold portfolio has been expanded from roughly 610,000 acres to 670,000 acres. And lastly, we moved from two drilling rigs up to four. What remains unchanged is our conviction. Six months ago, when we rang the Nasdaq bell, we held the belief that the subsurface technology driving the shale revolution could unlock geothermal on an enormous scale. That belief still holds today. The difference now is that we possess a fully operational commercial asset, along with more than a gigawatt of binding contracts supporting it. With that said, I'll turn things over to David.
David O'Very
executiveThanks, Tim. I'll start by going over what we saw in the third quarter, then move on to capital spending and liquidity, and finish with some near-term expectations before we get into the pipeline. Because GeoBlock 1 only began operating on the last day of the quarter, Q3 was largely a reflection of the construction and development activity currently in progress. G&A expense totaled $39.4 million, compared with $27.4 million during the second quarter. Non-cash stock-based compensation accounted for approximately $14 million of Q3 G&A, an increase from roughly $8 million in Q2. Leaving out stock comp, G&A rose roughly $6 million to about $25 million, due to public company costs and continued hiring. We ended the quarter with 306 employees versus 261 at the end of June, and the bulk of that growth was in operations and construction as Cape Station comes online. The operating loss came to $43.7 million. Net income was $11.7 million, including $15.4 million of interest income plus two non-recurring items: an $11.8 million non-cash gain on interest rate swaps and a $29.9 million tax benefit from tax credits earned when Phase 1 assets were placed in service. I’m calling these non-recurring since they make quarter-to-quarter comparisons harder, yet I’d also like to point out that the economic value of our tax credits is significant, and we hold a binding agreement to monetize them for GeoBlocks 1 through 3, with the proceeds going toward repaying our tax credit bridge loan. For the quarter, net cash used in operating activities came to roughly $12 million. The difference from our operating loss is largely due to non-cash expenses, interest income, and working capital changes. Capital expenditures were $256.7 million, compared with $226.5 million in the second quarter, mostly for drilling, completions, and surface facilities at Cape Station. Looking at Q4, our capex guidance is roughly $450 million to $500 million. That puts second-half 2026 capital spending at $700 million to $750 million, versus the $850 million to $900 million we had previously expected. The change comes from tighter capital execution on Cape Google 400 — mainly since some of that spending should now land later, with the project still on schedule. Our engineering and construction folks have identified ways to trim the build timeline, so we can put that capital to work nearer to the anticipated 2028 commercial operation dates. Those commercial operation dates haven't moved, and neither has the roughly $2.2 billion we plan to invest in the Cape Google 400 GeoBlocks through 2028. Our updated capex budget shows how we keep tightening construction schedules, and that lifts returns because money starts earning revenue sooner. One balance-sheet line worth flagging: we still expect the total cost of GeoBlocks 1, 2, and 3 to come in at about $7,000 per kilowatt. When GeoBlock 1 entered service on September 30th, approximately $514 million was reclassified from construction in process to property, plant, and equipment. That amount is not what GeoBlock 1 cost on its own — it also includes a larger share of Phase 1 wellfield costs and the shared infrastructure that serves all three GeoBlocks, such as our owned substation, gen-tie, and administrative facilities, along with capitalized interest and financing costs. After GeoBlocks 2 and 3 come online, that cost base will be spread across additional capacity. At quarter-end we held $1.9 billion of unrestricted cash and cash equivalents, alongside current and long-term debt totaling $301.6 million. A few near-term expectations to cover now. Q4 will be the first full quarter in which we recognize revenue from Cape Station under our PPA. GeoBlock 1, as Tim mentioned, is delivering in line with expectations. For fourth quarter 2026 revenue, we expect results consistent with what we laid out on the Q2 call. GeoBlocks 2 and 3 remain on schedule to progress through commissioning, grid sync, and into operations, mirroring the same sequence GeoBlock 1 followed. We still anticipate that GeoBlocks 2 and 3 will reach commercial operation by January 1st, 2027. As for 2027, our revenue outlook remains the same as what we shared during our Q2 call, and additional guidance will come when we report full-year 2026 results. In closing, I'd like to take you through our development pipeline, because each milestone discussed today started out years ago as acreage and early-stage resource. That pipeline is what drives our growth. I'll move from the most mature development to the earliest. At present, 36 megawatts are operating at Cape Station and Project Red. A further 66 megawatts — GeoBlocks 2 and 3 — are in commissioning, while an additional 400 megawatts — GeoBlocks 4 through 11 — are under construction. Our ready-to-build capacity stands at 550 megawatts, backed by our continued expansion at Cape Station beyond what's currently under construction, along with our Corsac geocluster, where we hold contracted PPAs with Google and Ava Community Energy. Fervo's advanced development pipeline remains at 3 gigawatts, while early development rose to 54.7 gigawatts from 48.6 gigawatts. Let me pause here. Much of that increase reflects our drilling advances at Cape Station. Our 3.0 well design reaches deeper and hotter than the Phase 1 wells behind the initial DeGolyer and MacNaughton heat-in-place report at Cape. Those drilling results are now included in added lease purchases, and a revised DeGolyer and MacNaughton report backs 8.4 gigawatts of potential capacity at Cape Station — almost twice the earlier 4.3 gigawatts and about 18 times the megawatts currently being built. This is the same pattern we saw in shale. Better well designs enlarge the resource base and widen the inventory of development locations. At Cape, every successive well design reaches greater depth and higher temperature. With 8.4 gigawatts of potential and a clear regulatory path for behind-the-meter development, we have a long runway to continue drilling, building, and driving costs down across that same footprint. Turning to a different topic, an update on the appraisal campaign: during our Q2 call we described how we've begun drilling appraisal wells throughout several of our geoclusters. The purpose of these wells is to help us identify and rank specific locations for future development. That effort is currently in progress, and we'll share additional details in upcoming periods. Beneath all of this, our landholdings continue to expand, now totaling 670,000 acres, compared with 650,000 acres in the prior quarter. Every phase of this pipeline is moving forward as we continue building option value across our portfolio. Right now, 36 megawatts are up and running. Another 466 megawatts sit in commissioning or are being built, with 550 megawatts shovel-ready. We've got 3 gigawatts in advanced development and over 54 gigawatts in early development — all of it across 670,000 acres. That's the pipeline that converts resources into megawatts, and our expectation is that it keeps moving forward. Before we take questions, I'd like to invite everyone to an investor open house at Cape Station on Thursday, November 19th. You'll be able to tour the site, check out the drill rig and the power plant, and meet our team. Capacity is limited, so please use the link in our October 16th press release to request a spot. For anyone unable to attend, we anticipate holding additional visits in 2027. With that said, operator, you can now begin the Q&A session.
Derek Podhaizer
analystHey there, good morning, everybody. Thanks for all the updates here. I guess I'd just like to begin by having you go a bit deeper on how Cape Station has been performing — in particular GeoBlock 1, that initial 33 megawatts you've now brought online. You said it's running the way it should, but could you highlight specific results and perhaps some of the early data that gives you confidence about the performance you're seeing so far?
Tim Latimer
executiveAbsolutely, Derek. Thanks for asking. On a personal level, for somebody who has now spent more than a decade working on utility-scale enhanced geothermal systems, it's simply thrilling to watch the flow results from Cape Phase 1 and GeoBlock 1 arrive right in line — very, very much where we expected them. As we said on the call, brine is reaching the power plant, and we are hitting both of our flow rate targets and our temperature targets, very much in line with what we modeled. And that is why we're so excited to hit that 33 megawatt net figure right out of the gate, in terms of the September 30th COD we disclosed in that press release. And as for other performance metrics, I think what matters most right now is how many megawatt hours we are producing and what that means for revenue. I'll simply repeat what David said there, which is that we are very much in line with our earlier disclosures on the Q2 call, cough, regarding our Q4 2026 revenue target — meaning things are tracking exactly as we expected there.
Derek Podhaizer
analystGreat. No, that helps; so next I'd like to ask about that heat-in-place study at Cape Station. You've essentially doubled your potential capacity to 8.4 gigs from 4.3. What does that mean for Fervo over the longer term, given Cape Station is a bigger asset than you first expected? As you mentioned with shale, you're tapping more resources than you had planned. I'd have to imagine this maybe adds additional GeoBlocks, or at least some extra color on the added capacity would be useful.
Tim Latimer
executiveAbsolutely. As you pointed out, Derek, and as we noted in the script, this isn't a unique feature of resource plays. Frequently, early estimates of heat-in-place or whatever resource you're examining tend to be quite conservative, since it's an unknown technology and data is scarce. Then what we observed in shale is that as additional wells got drilled and efficiency gains were realized and a better grasp of the original resource in place emerged, and spacing and assumptions were updated, shale developers found there were more and more hydrocarbons in each play. We're watching this unfold precisely the same way in geothermal. This independent report roughly doubled the capacity we anticipate on a technical basis in terms of heat-in-place at Project Cape. Largely, that's because we've managed to prove out deeper drilling and more efficient operations. The more data we obtain, the more comfortable third-party assessors become with giving us credit for these advanced designs and these greater drilling depths and greater drilling temperatures, and this reflects that. And I think a couple things: one, we don't believe this will be unique to Cape. We think we'll be able to repeat this playbook potentially across other prospects. The more we drill, the more we learn, the more efficient we become, the more resource we believe could be available. We're excited about what this means across the whole portfolio, with really just Cape being further along in terms of data collection as the first example of that. Then regarding Cape as well, we are seeing no shortage of customer demand, both through traditional front-of-the-meter customers or behind-the-meter customers. Knowing that we have confidence in more resource being available, as well as third-party verification of that, will give us more confidence to market additional expansion at Cape beyond what we've already disclosed. Those efforts are ongoing, even as we look at the rest of our portfolio and get excited about what these new efficiency and spacing and depth and temperature numbers mean for growing the total size of the prize across our acreage position as well.
Derek Podhaizer
analystExcellent. Thanks, Tim. Congratulations on everything that's been updated. I'll hand it back over.
Tim Latimer
executiveThanks.
Chris Dendrinos
analystAppreciate you taking my questions, and congrats on the impressive headway made here. To kick things off, I'd like to dig into a few of the main points of debate we've been hearing about out there, and in particular perhaps the longer-range assumptions regarding water loss and thermal declines. Could you take a few minutes to walk us through how we ought to—or ought not to—extrapolate some of the results at Project Red across to Cape Station, and then simply what underpins your confidence in those long-term performance expectations? Thanks.
Tim Latimer
executiveAbsolutely. Perhaps I'll begin by addressing water loss and roughly how we approach this. We've put out a tremendous volume of material on the subject. There are several blog posts on our website that explain water and why water stewardship matters in how we operate. Wanting to be strong stewards of water resources drove us to make very deliberate design choices—for instance, committing to dry cooling exclusively, with no evaporative cooling, at the power plant, and aiming to drill deeper wells that tap deeper, brackish layers rather than freshwater for our operations. In thinking about water and what we've learned, the questions are whether we're stewarding water well, whether it affects our cost structure, and whether we hold the proper permitted and allocated volumes to keep growing. Fresh information from Project Cape has validated every aspect of our approach there; this remains a case where our operations and construction involve almost no freshwater consumption, if any at all. What we're finding matches what we anticipated: it isn't a significant factor when it comes to opex or cost. We're also finding that the amounts we're observing at Project Cape fall within what we're permitted, and those levels can sustain many years of expansion and growth there, based on the early results gathered thus far and where we stand regarding water rights and allocations. What we've observed so far with water output at the early Cape operations matches precisely what we disclosed previously, and we continue to be confident that this issue can be managed by applying sound water stewardship. Moving on to thermal decline, it's worth keeping in mind just how valuable Project Red is as an asset. It was a first-of-a-kind test — a horizontal EGS system the likes of which had never been attempted — and from the very beginning, and still today, it has been built to maximize what we learn. Consequently, after a stretch of stable temperature, we have seen the production temperature decline. That was anticipated. We've mentioned this repeatedly on calls and elsewhere: after operating a geothermal asset for some time, a drop in reservoir temperature is exactly what you should expect. The real issue is how that affects a project's viability and its economics. I should add that this specific data—how thermal decline appears and what causes it—is now held solely by Fervo. A few competitors are beginning to design and permit their initial horizontal EGS projects, and they're several years behind us. No facility worldwide today offers three years of operating data, which would let us understand what drives heat output to fall off and let us try out ways to slow that decline and boost how well the site runs. Our position is unchanged: this will prove a highly useful resource for Fervo, and already we are conducting logging tests plus other intervention activities at Project Red so we can gather the maximum amount of lessons to later deploy at Project Cape. As we shift to those results at Project Cape, like any solid resource play, the real-world modeling results we observe at Project Red directly shape the reservoir forecasting and expectations we have for Project Cape; that information is, naturally, also shared with our underwriters and through the debt process—how those history-matched models at Red inform Cape. Once again, we're seeing plenty of encouraging signs from the system there. It's worth remembering that Cape is a very, very different resource from Red. Red was an isolated doublet system built to prove out the concept and maximize learnings. Cape is an operational asset built for economic returns. We've discussed the Gen 1.0, 2.0, and 3.0 well system. Things such as significantly greater lateral lengths, better spacing between wells, more efficient completion methods, larger casing diameter, and elevated temperatures all indicate that Project Cape's outcomes will be categorically superior to those of Project Red. The early data has us very enthusiastic, and as I noted when answering the earlier question, all aspects of Project Cape regarding temperature and flow rate are matching our expectations. We continue to recognize tremendous value in Project Red for maximizing what we learn and the data we gather, yet we are also extraordinarily excited about the operational and engineering enhancements already put in place at Project Cape. That’s still working out very well, and the evidence is clear that the results from our pilot have made a very substantial difference to how we run and execute things at Project Cape.
Chris Dendrinos
analystUnderstood. So perhaps to follow up on that—I believe you brought up scaling up in size, extending duration, and going deeper, then adjusting the frac design. What I'd want to ask is whether you have methods for measuring downhole after the fracs are in place, so that you're steering clear of channeling, and are there ways to monitor, say, even at GeoBlock 1 right now, whether the water is moving somewhat evenly through the network? And then, how much time does it take before you get some degree of performance data that lets you return later and say, "Look, this initial batch of wells is delivering as we anticipated, and it essentially validates the thermal decline assumptions we set out, say, around the IPO"? Thank you.
Tim Latimer
executiveAbsolutely. The brief response is that we already are. That data is being gathered and has been gathered; it's among the things that make Project Red so excellent and why we regard it as such a distinctive asset in this space, one that will generate a meaningful competitive edge. We possess original flow test results from Project Red dating back 3.5 years, and we've kept up substantial logging and characterization efforts to assess items such as flow conformance and thermal decline. What's intriguing today is that we can revisit and chart what we measured in those early flow test results and observe how it shows up two or three years afterward as shifts in flow distribution or temperature; that's a genuinely distinctive data set in our hands. Naturally, as we've noted in earlier cases, we've now devoted tens of millions of dollars specifically toward unique data acquisition at Project Cape through some of this downhole logging, measuring production flow, flow conformance, temperature profile. Having several wells online now, with dozens soon to be online, being able to gather and chart data across every one of them, and then revisit and history match it against Project Red, is extremely powerful, since it lets us pinpoint the key design attributes—not only in items such as well spacing, but in completions design—that genuinely produce best-in-class performance regarding flow rates and thermal decline. Yes, the response is that we have already gathered that data, and we will keep gathering it. As noted, although we currently have only a few weeks of flow data at Project Cape, all of it falls within our modeled expectations. I believe we can verify that many of the assumptions we've set out over the last year are proving true in practice. I think that as time passes, we'll simply gather even more data to support that case, but on really every dimension of the technical roadmap, it all strongly confirms what we had expected.
Chris Dendrinos
analystWell, thank you so much.
David Anderson
analystGreat, thanks. Tim, I'd like to hear a bit about how you're doing at cutting the capex costs at Cape Google. As we've seen with shale, things tend to get better over time, and my assumption is that most of the drop from $7,000 to $5,500 comes from the subsurface. I was hoping you could address both sides of that, starting with drilling. Where do you stand on drilling right now? Where do you need to get to — I'm curious how that's going along the way? And then second, I'm curious about the DeGolyer and MacNaughton study that raised heat-in-place. Does that alter the math on Cape 2? Put differently, is the megawatts produced per well now higher in your expectations? How should we think about that with respect to the nearer-term development? Thanks.
Tim Latimer
executiveThanks for those questions. To begin with capex, you're correct regarding drilling and production results. We're definitely seeing strong efficiency gains. In the earnings presentation, I believe we provided some excellent concrete examples of gains we're seeing in both drilling days and things such as deployment of dissolvable plugs. Perhaps before diving into that, I'll note that on the question of subsurface versus surface, in geothermal it's genuinely difficult to separate the two. It's a complicated system-wide optimization. First and foremost, I want to restate what higher temperatures do throughout the entire capex cycle. Higher production — as we've said, we've raised our target temperature by roughly 30 degrees Fahrenheit between Cape Phase 1 and the Cape Google 400 project — is a sort of overarching lever that lowers capex across the board. That means, since you produce more energy per flow of brine, you need fewer wells, and the power plant is also more efficient; that's part of the reason we've been able to go from 33 net megawatts to 50 net megawatts from the GeoBlock first-generation design to what we're doing today; we're actually seeing capex reductions on both the surface and subsurface, partly because of things like supply chain efficiency and construction optimizations like David mentioned, but partly because you simply get more bang for your buck as you raise the temperature, and we continue to see great results there. As for where we are on drilling costs, we do expect that, as we learn these longer laterals and different hole designs, we'll keep improving, as you said, just like shale. With each iteration of that well, as we drill dozens of these wells, we're going to become more efficient. We're already seeing the cost structure—drilling days relative to depth, completions figures—largely matching what we expected and driving results, which is why we were glad to reaffirm that $5,500 per dollar per kilowatt target; that's already very much aligned with what we need to see there. Regarding the D&M heat-in-place report, I'd say much of it simply boils down to gathering additional data. As I said earlier, it's also about receiving credit for greater depths. Usually when these studies are done, as I mentioned, you conduct them conservatively at the outset. You really only receive credit for what you've shown to be possible up to now. As we've drilled deeper wells, this is kind of the third dimension. You can drill longer laterals, you can drill those laterals across a larger dimension, and you can also drill deeper, giving you more benches of production. Now that our Cape Phase 2 wells are far deeper than the Cape Phase 1 wells, that's letting us receive credit for considerably more geology that we always knew existed but often wasn't included in the initial heat-in-place studies, because we needed to demonstrate the viability of drilling those wells. That's a large part of it. I'd say the heat-in-place study itself won't drive a design change in the Cape Google 400, where many of those wells were already planned; it just means that, as we've stated for a long time, as technology gets better, there's simply more geology we can reach and reach it more efficiently; that's really what this study reflects, and it isn't a major driver of changes to the planned Cape Google 400 wells at this point in time.
David Anderson
analystThat makes sense. And then, just to look at this from another angle — clearly, data centers turned into quite a heated subject politically over the course of this election season. I'm a bit curious, and you did mention this in your remarks, but where does geothermal now stand within that debate? When it comes to conversations with offtake companies and communities, is that shifting? Or perhaps, how would you say that's shifting, and what effect does it have on appetite for further developments as you look ahead?
Tim Latimer
executiveGreat question, and to be honest, public awareness of how important it is to develop data center or any other industrial infrastructure properly — with the right sustainability standards and the right community benefits standards — and the intense scrutiny on that today has only been a benefit to Fervo and to our talks with offtakers. I think certain things that were done fast and loose in the early boom days of this data center revolution, when communities weren't engaged properly and projects failed to meet the right emissions standards and so forth, are now well-known, hard lessons learned for data center developers about how important it is to do things properly. Because of that, a resource that is 24/7 carbon-free electricity, one with great attributes such as enhanced geothermal systems, together with a developer that has a track record of being in the community early, discussing community benefits, and being a good steward of the local environment, is really compelling. I can tell you that a project like the one we're doing with Google in Utah wouldn't have come about if we were a dirtier energy resource, or if we hadn't done the right community engagement work. What I'd say is that this scrutiny on making sure that, if you're going to pursue data center development, it gets done properly is something that has sped up our conversations with offtakers, because, frankly, clean and sustainable is back in the conversation in a way that it hadn't been. I believe that will be a lasting shift. We have the right sustainability metrics to be a fantastic community and environmental partner, and we're seeing ourselves as relative winners in this discussion, and a speeding up of our offtake discussions as a result.
David Anderson
analystAll right. Thanks.
Dylan Nassano
analystHi, everybody. Thanks. I wanted to ask about those PPAs of roughly 400 megawatts that I believe were somewhat rearranged at the time you signed the Google PPAs. Is there any news on when those customers expect or would like to take that power, and how do you intend to deliver it given interconnection?
David O'Very
analystHi, Dylan. Thanks for asking. Put simply, we are currently working through the amendments, and the conversations with those offtakers have been quite constructive. As you can imagine, dealing with load-serving entities of that kind involves a fairly drawn-out process; we keep pushing forward on it. The key takeaway, I'd say, is that we still see those PPAs landing around 2032. Some transmission options are coming online, particularly routes for sending power back to California, and I'd expect those PPAs to be strong contenders for using some of that capacity.
Dylan Nassano
analystUnderstood, thank you. A quick follow-up on the capex efficiencies — the ones you're describing as letting you push out your capex spending profile. On timing, I'm curious whether those efficiencies could be used to pull forward capex upside, or generate capex savings upside, compared with the plan as it stands.
David O'Very
analystThat's precisely the right question to ask. Our teams are always concentrating on how we assemble these schedules to handle construction along with the capital spending involved. I would describe this as a central element of what we task our teams with, namely to question every assumption. As they do so, they seek ways to bring lessons over to modular GeoBlocks, and that is definitely emerging right now. To offer a single concrete data point we are already observing, for commissioning from GeoBlock 1 at Phase 1 to GeoBlock 3 at Phase 1, we already anticipate roughly a 50% improvement in that commissioning timeline. As we carry that through our wider construction schedules, it will genuinely assist us in hitting the growth targets we're after while also, in a sense, boosting returns. If you consider what we're up to — we hinted at this — the total construction budget isn't changing. What's changing is the timeframe in which we deliver that identical amount of capex. By shifting dollars later, nearer to the point when we bring in revenue, simply by capitalizing on the time value of money, we're already enhancing returns. We're finding chances of that sort pretty much everywhere.
Dylan Nassano
analystGreat. Thank you so much.
Joseph Osha
analystGood morning. Thank you for taking my question. I've got two. To start, on page 11 there’s quite a bit that’s new — dissolvable plugs, rotary steering systems, insulated drill pipe. Has all of that already been introduced? Is every one of those needed in order to get to 5,500? Thanks. And I have one additional question as well.
Tim Latimer
executiveYeah, everything's been fully deployed at this point. We opted to highlight just a fraction of the enhancements and the effort our team's been putting in. For this one, we went with changes that were already in place and working well — things we've observed over the past two years at Cape. These items help keep us on course toward that 5,500 figure, though they're far from a complete rundown of the enhancements we've already put in place and those still in progress. As I mentioned before, we're feeling quite positive about the path to 5,500 given these and other improvements.
Joseph Osha
analystThanks. Now for my follow-up: you're getting really impressive results with that 8 5/8 casing. When does it become worthwhile to switch to the 9 5/8 you've mentioned, rather than simply drilling deeper, longer, and hotter with the casing you're using now? Because your larger bores clearly bring a different set of challenges. Looking at this 3.0 design on page 10, I'm just curious how much additional room there is to improve it before you have to move up to the bigger casing. Thank you.
Tim Latimer
executiveThat's an excellent question, Joe, and it's something our engineering teams grapple with daily. What I'd say is that on gains in drilling, completions, and production efficiency at the 8 5/8 level, we remain quite optimistic about driving substantial improvements there, and right now, every one of the Cape Google 400 wells is slated for the 3.0 design using 8 5/8-inch casing, so we believe we can meet these cost targets within the generation 3.0 well design, and down the road we'll assess, based on the data we observe, whether and when we might shift to that larger casing design; we don't think it's required to reach our cost targets. The only question is whether we believe it will serve as an even bigger lever for efficiency gains going forward.
Joseph Osha
analystGreat, thank you.
Julien Dumoulin-Smith
analystHello, everyone. This is Carter, covering for Julien. Thanks for taking our questions. I have just one brief follow-up about Google. We appreciate all the specifics on the PPA there. Regarding that 600-megawatt option in particular, at what point do they have to decide? I'm simply trying to reason through it, because you now have 550 megawatts ready for construction and the Cape asset sitting at more than 8 gigawatts — about when might that option be exercised if they decided to take that path?
David O'Very
analystHey, Carter. Appreciate the question — we're obviously thrilled about how things are going in the community with Google. We've partnered with them for a number of years now, and they continue to be an exceptional, world-class partner. What we're seeing there has us genuinely excited. On the 600-megawatt option you raised, regarding the extra capacity we have at Cape: there are clearly multiple times that amount of capacity available to host 600 megawatts. Capacity is definitely not the problem. What it really comes down to is sorting through the various requirements involved in constructing a data center, and our expectation is that Google will continue making headway on that through 2027.
Julien Dumoulin-Smith
analystGreat. Thank you. I think when Tim responded to a few of those questions about thermal decline, you pointed to data the lenders are able to view regarding Cape performance that we don't have access to. I'm just wondering if you could give us some color on the latest project financing discussions broadly, as we think about capex for the Google Cape 400 ramping into next year. Just some color on how those discussions are going and when we might see an update on project financing would be helpful.
David O'Very
analystGlad to share a bit of color. Our first project financing was for Cape Phase 1 — the facility we call Granden — and it was a $421 million loan that closed in March of 2026, earlier this year. That loan was very deliberate: it involved a wide group of lenders, and we now have a whole set of banks that are used to thinking about enhanced geothermal systems — what that means for production forecasting, what it means for permitting, and all the various requirements. We did all of that so we could begin these conversations sooner when it came to the 400 megawatt project, which we now refer to as Cape Google 400. We anticipate that Cape Google 400 will likely be set for project finance debt around mid-2027. Regarding the appropriate kind of debt, we're really converging on that 70% loan-to-value figure we've stayed fairly consistent about, so when we consider the right moment to place it, that's probably going to be mid-2027.
Julien Dumoulin-Smith
analystThank you.
Justin Clare
analystHey, good morning. Thanks for taking the question here. I'd like to kick things off with the 2027 outlook. You kept the revenue guidance at $60 to $80 million. I'm curious whether you've gotten any more visibility into the possible transmission-related curtailments you mentioned last quarter? With Cape Station Phase 1 progressing as planned, does transmission availability really stand as the primary factor determining where revenue is recognized, or ought we to consider additional important factors, such as the schedule for ramping up GeoBlocks 2 and 3?
David O'Very
analystThanks for that question, Justin. As a reminder for everyone, the situation we're talking about involves a genuinely unique, one-time outage at the substation where we interconnect, because a third-party solar project must physically tie into that very substation. While that work takes place, we clearly cannot move energy through that physical asset; we're continuing to collaborate with the counterparty and beginning to establish what we believe will serve as solid bookends on the outcomes there. That's everything for now. We'll be able to share more specifics once 2027 gets here, but we are in the process of locating a counterparty that is truly prepared to collaborate with us. Both sides' interests line up well. That very same counterparty holds additional wind and solar assets tied to the same substation, so with regard to curtailing that downtime, everyone involved has an incentive to get it done as quickly as possible. Turning to your second question, which concerns revenue from GeoBlocks 2 and 3 and the timeline we're seeing, I believe our expectation remains that GeoBlocks 2 and 3 will be ready when they need to be on January 1st. The early-2027 substation outage will definitely play a role in that, but assuming GeoBlock 1 performs as planned and GeoBlocks 2 and 3 presumably progress along a comparable path, we anticipate Cape Phase 1 reaching its full 100 megawatts in 2027.
Justin Clare
analystUnderstood. Thanks for that. Just one more item. You booked close to $30 million of tax benefit in Q3 as you put Cape Phase 1 assets on the surface into service. Could you clarify which tax credit election you're applying here? Does that refer to the ITC, or might you end up using the PTC instead — and could you also outline the tax strategy you anticipate for upcoming assets here?
David O'Very
analystThis case is somewhat unusual, and it's the sole instance that will function this way; with Cape Phase 1, the subsurface assets will qualify for an ITC while the surface assets get a PTC. That's because they come under earlier definitions of those respective tax credits. The $30 million figure you're currently seeing reflects an investment tax credit tied to certain wellfield assets. Looking forward, for a high-capacity-factor resource like EGS, our base case would be to monetize production tax credits for the GeoBlocks coming up.
Justin Clare
analystGot it. Thank you.
Jeff Grampp
analystGood morning. I'd like to go back to those solar installations you brought up. Can you help us get a handle on how big that is? I'm not certain solar per GeoBlock is the right KPI, but how scalable are they, and what kind of impact might they have on cost savings versus the longer-term capital targets you've laid out?
David O'Very
analystAppreciate the question, Jeff. When it comes to solar, what we're talking about is relatively small, and other geothermal developers have deployed this at other assets, and it seems to have worked for them as well. The real chance we have is in supplying power to pumps and the different kinds of station load. Solar works especially well during the summer months. We expect to get some advantage out of that. Every asset is going to be a bit different depending on where it's located, but figure this is 20% to 25% of the EGS system's nameplate capacity, so the dollars involved aren't big, though we do like the returns we expect from them. To us this is a very complementary thing to add to the asset.
Jeff Grampp
analystGreat, that's very helpful; as my follow-up, there's clearly a lot of attention on Cape for obvious reasons, but apart from Cape, I think you brought up some other exploration targets connected to DOE funding and things like that. Any important catalysts or exploration work that investors should keep an eye on for newsflow as you head into and through next year?
Tim Latimer
executiveFor sure. Like we've mentioned previously, an appraisal campaign will be underway at Corsac, which is among our next assets in Nevada; we anticipate providing updates likely next year on a few of those initial results. We're also pretty enthusiastic that in the last quarter we received two separate Department of Energy enhanced geothermal system demonstration project grants—one covering a project site in Idaho and the other for an additional project site in Nevada. We would probably anticipate incremental updates regarding our appraisal work at those sites at some point in 2027 as well.
Jeff Grampp
analystGreat. Looking forward to that. Thanks.
Sean Milligan
analystHi there, good morning. I appreciate all the detail on the operations front. I just have a question regarding corporate costs as we head into 4Q and the coming year. A few quarters out now, G&A expenses are running somewhat above what we had anticipated, but is there a run rate we ought to consider, or did this quarter include any one-time items that should be backed out going forward?
David O'Very
analystThanks for asking, Sean; obviously we'll return with greater detail in 2027 when we offer somewhat improved guidance on that. Thinking about what we're seeing at present, public company costs run high, and that's perhaps the key takeaway; we've brought on more employees, and quite a few of those hires are really centered on construction, on the GeoBlock factory side, though certainly we're also adding people in the back office and administrative areas. Beyond that, we've been engaging various service providers to help bridge the gap while new hires get up to speed on the administrative side. As we move into 2027, we expect that some of the employees we've hired are now carrying more of the load, so hopefully a portion of that service work will decline going forward.
Jed Dorsheimer
analystHi, guys. Thanks for taking my question. I came into the Q&A somewhat late, so I apologize in advance if this has already been covered. I wanted to explore the Google option a bit further, and I suppose if I took a cynical view of the PPA they signed, their ability to resell it could be seen as more of a protective—a put, if you will—but building that data center or filing for a permit seems like it would send a clear signal, triggering the option for the additional 600 megawatts. I guess I just wanted to say that out loud and see whether you'd view it differently or would agree with that?
David O'Very
analystThanks for the question, Jed, and you're correct. Regarding the 400 megawatt portion of this, as Tim mentioned, that's a firm contract. Our aim when we drafted that PPA was to have a 400 megawatt PPA that looks and feels like most PPAs and is financeable with counterparties and lenders in the sort, and that's what we ended up with there. As for the 600 megawatts, yes, that's more tied to the outcome on a data center. The thing that sets off the option isn't really tied to some particular permit or anything along those lines, though our feelings about the headway being made there are positive, and we've definitely spent plenty of time alongside Google and believe they're doing a genuinely strong job of moving things forward, and standing with them is exciting for us.
Jed Dorsheimer
analystAll right. Moving to my follow-up, there's the BAHA — the Bipartisan American Affordable Jobs Act — which is sort of working its way through the legislative process at the moment. There's a great deal of language, and Senator Mike Lee of Utah is one of the co-authors. A lot of that language deals specifically with geothermal, and I'm just wondering what you think — if it were to pass, how could that shift some of the regulatory framework surrounding geothermal for your company?
Tim Latimer
executiveThanks for asking; what BAHA could accomplish for the energy system of this country when it comes to reliability, affordability, and sustainability has us tremendously enthusiastic, and Fervo has been glad to put its support behind that legislation in several different forums; we value the leadership of Utah's Senator Lee along with his Democratic counterparts, and I believe they've produced a truly excellent bill that will matter a great deal to the future of the American energy system. As you noted, fixes to geothermal may be among the biggest and most additive sections, and that has us excited. Part of it grants parity in federal permitting for items that oil and gas has benefited from for decades while geothermal was excluded. Other parts supply additional financial resources and better-staffed offices, which we think will produce improved permit timelines. The context here is that administrative gains in geothermal permitting have already been substantial over the last several years, since it has grown into a bigger priority for this country. None of our go-forward expectations depends on the BAHA. The guidance we've provided before rested on our assumptions about federal permitting timelines. Should the BAHA pass, the transmission provisions along with the geothermal ones would be highly additive to our business, simply by establishing a better regulatory backdrop and quicker permit timelines for our project; because of that, we remain keenly focused on it, even though our growth plans don't depend on it. We're enthusiastic about it serving as a possible catalyst for still faster development going forward.
Jed Dorsheimer
analystThat's helpful. Thanks, guys.
Tim Latimer
executiveThank you.
Operator
operatorThanks. Ladies and gentlemen, the queue is showing no more questions at this point. That brings today's conference call to a close. We appreciate everyone taking part. You're welcome to disconnect now.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Fervo Energy Company transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Fervo Energy Company earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Fervo Energy Company or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.