Fluence Energy, Inc. (FLNC) Earnings Call Transcript & Summary
August 6, 2026
Earnings Call Speaker Segments
Chris Shelton
executiveHello everyone, and thanks for joining Fluence Energy's call for the third quarter earnings. On the line with me today are Julian Nebreda, who serves as our President and Chief Executive Officer, and Ahmed Pasha, our Chief Financial Officer. Our earnings presentation, the press release, and the supplementary metric sheet that covers financial results, plus supporting statements and schedules — including reconciliations and disclosures about non-GAAP financial measures — can all be found in the Investor Relations section of our site, fluenceenergy.com. While this call is going on, management at Fluence might make forward-looking statements about a range of matters tied to our business. These include, though they aren't limited to, statements about our future financial and operational performance, future market growth and opportunities related to it, anticipated growth and business strategy, liquidity and access to capital, expectations about pipeline, order intake and contracted backlog, future results of operations and the impact of the One Big Beautiful Bill Act, projected costs, beliefs, assumptions, prospects, plans and objectives of management, and when any of the above might occur. Statements like these rest on current expectations and particular assumptions, so they carry certain risks, uncertainties and other important factors that could make actual results differ materially. For more detail on these risks, uncertainties and important factors, please look at our SEC filings. Be careful not to rely too heavily on these forward-looking statements, since they speak only as of today. Also, keep in mind that the company has no duty to update or revise forward-looking statements for new information; this call will also reference non-GAAP measures that we consider important when assessing how our business performs, among them adjusted EBITDA, adjusted gross profit and adjusted gross profit margin. You can find a reconciliation of these non-GAAP measures to the most comparable GAAP measure in our earnings materials on the Investor Relations website. After our prepared remarks, our team will hold a question-and-answer session. Thank you so much. I'll now hand the call over to Julian.
Julian Jose Marquez
executiveThanks, Chris, and a warm welcome to each of you who has joined the call today. Let's move to Slide 4. I'm going to give you an update today on how far we've come in generating new order intake and growing our backlog — during this quarter, both reached record heights. I want to cover how our business is growing, and that growth comes from two places: solid demand among the customers who form our foundation, plus rapid expansion within the data center segment. Out of that segment, we secured our first orders and contract awards, and together they totaled $850 million. My belief is that the momentum we've generated across recent months will keep going in the quarters to come, driven by the distinctiveness of what we offer and by our team's proven, long-standing capacity to deliver on what customers need. After my comments wrap up, Ahmed will take everyone through the quarter's financial results and share how we see the remainder of the year shaping up. Let's start with the top-line highlights from the third fiscal quarter. To start, we booked $1.44 billion in orders this quarter — almost three times the $509 million signed during the same stretch a year ago. Next, among that record intake was our inaugural agreement with a data center developer, valued at $300 million. In July, an additional $550 million of business was awarded to us by one of the hyperscalers mentioned in last quarter's discussion, spanning several data center locations. Also, we ended the period with a record backlog of $6.4 billion, reflecting 14% growth versus the second quarter and over 30% growth compared with the third quarter of last year. Finally, total liquidity stood at roughly $860 million at quarter's end, matching what we had anticipated. Next, Ahmed is going to walk through how we did financially in Q3 in a moment, though our top line took a hit because shipments we had anticipated slipped, a consequence of bringing two freshly contracted production sites up to speed. As a result, for 2026 we're bringing down the midpoint of our outlook for both revenue and adjusted EBITDA, to $3 billion and negative $10 million, respectively. This cut is not something we accept lightly, and we've put changes in place aiming to make sure we meet the rising demand in our market. I'll lay out that plan in greater depth shortly. Let's move to Slide 5, where you'll find additional specifics about our order intake. We've got $2.7 billion in orders booked for Q3 of this year at this point, which puts us 80% above what we saw during the same period a year ago, and roughly 90% of that figure comes from utilities and IPPs. When it comes to Q4, we're anticipating yet another record-breaking quarter for orders, and based on where demand stands and how we're positioned competitively, there's good reason to believe this strong momentum carries into the quarters ahead. If you'll flip to Slide 6, I'll walk through how things are going with our data center customers. During our call last quarter, we shared that we'd secured 2 master supply agreements with hyperscalers, and that news elevated how other prospective data center customers view us. All told, our data center pipeline grew to 16 gigawatt hours — an increase of over 35% versus the second quarter. Projects in that pipeline are now a blend drawn from hyperscalers as well as data center developers. During the quarter, together with a developer, we booked a $300 million order for a behind-the-meter project. The customers were sent to us by one of the hyperscalers we have been working with. For this customer, the sales cycle unfolded much faster than in our traditional market segment — just 3 months passed from lead to order. We continue to see that the developer segment is focused on speed to power solutions, and we are glad to be in a position to serve their needs. Quality in power solutions is still top of mind for our hyperscaler clients, and that's yet another space where our delivery capabilities really shine. Back in July, we were happy to land roughly $550 million in awards tied to one of our MSAs. Those haven't turned into purchase orders at this point, and we anticipate they'll be added to our signed orders tally over the next few months. There's a project pipeline among these data center customers that we feel we're in a strong position to compete for, and we're eager to grow our relationship with them soon. Now, if you'd flip to Slide 7, I'll walk through backlog and pipeline growth. Two of the last four quarters delivered all-time-high order totals, and that has strengthened our backlog, giving us a solid foundation for revenue growth in fiscal '27. Roughly $2.2 billion out of the $6.4 billion in backlog we held as of June 30 should turn into revenue during fiscal '27. For comparison, the revenue coverage we had for fiscal year '26 as of June 30, 2025 stood at $1.5 billion. Now for our pipeline. We closed the quarter at $33.1 billion, up $1.6 billion from the prior quarter. After accounting for pipeline that converted into orders during the quarter, that works out to $3 billion in fresh opportunities. The share of our pipeline originating from the U.S. keeps climbing. In the market versus prior years, the primary factor was the data center segment. Slide 8 will give you the specifics regarding how our supply chain is being scaled. Our supply chain capacity has been growing so that we can satisfy robust product demand, which our backlog's increase demonstrates. Around the world, newly secured larger manufacturing sites under contract should boost our capacity while also providing the quality level customers anticipate. Ramping production at two of those new plants accounts for a significant portion of why we raised this year's revenue outlook. Within the United States, we will serve as off-taker for a newly built, fully automated Houston factory whose projected yearly capacity is 15 gigawatt hours. Construction on the new facility has slipped by several months, the result of construction delays along with problems involving the automation equipment. We began limited production this quarter, and the manufacturer is working to resolve the remaining issues. Full production levels at the facility should be reached in the first quarter of our fiscal '27. It's worth noting that this contract manufacturer has been our main enclosure supplier out of Vietnam, and that site is very similar to the new plant in Houston. We believe the experience and knowledge they offer will be an asset as this factory moves toward operating at full capacity. At this point, our new plants abroad have completed their ramp-up, and we're delivering product to customers on a delayed schedule since the first output fell short of the quality standards we set. We put fixes in place, and we've gone back to shipping top-tier products to projects worldwide. Because producing on time, consistently, and at high quality matters so much to our business, we made organizational adjustments recently to create tighter direct oversight of and accountability for what we're able to produce. As we shared today, Roman Lewsen is taking over leadership of our supply chain, while Peter Williams will focus on product, and both of them will report straight to me. Roman's present role is Chief Enterprise Operations Officer, and he comes with over 20 years of worldwide leadership experience from Siemens, where he occupied senior operational and business leadership positions covering supply chain, manufacturing, and business transformation. Roman will oversee a group of managers who have joined us during the last few months and who carry deep experience and capabilities in supply chain and manufacturing.
Julian Jose Marquez
executiveI have faith that this fresh leadership group is going to reinforce both our supply chain and our manufacturing operations so we can satisfy rising demand for what we sell. Alongside what we already provide for domestic sales, we anticipate that the Houston facility is going to boost how much domestic content we can produce each year by a substantial margin relative to where we stand today. After that site is completely operational and integrated into the supply chain we have now, we anticipate having enough capacity to fulfill the project backlog we currently hold, plus the confidence to keep up with U.S. market growth. For specifics on the ways we stand apart in today's market, please go to Slide 9. Over a remarkably brief stretch, we have managed to grow our backlog and break into the new and significant data center customer segment. Fluence now has both new and returning buyers who value our sophisticated product designs, our industry-leading energy density, and our emphasis on total cost of ownership. Beyond those points, our proprietary software stack, which includes our operating system, is built so that customers can optimize their solution across its lengthy lifespan and conduct monitoring from a distance. Such capabilities can boost availability and prolong the life of what we offer for customers across every use case. When it comes to data center customers in particular, our operating system's capacity to efficiently assist with smoothing loads and managing low voltage periods has driven fresh awards and orders. < > has been winning more favor on the orders front this year, making up 75% of our orders year-to-date. A key appealing aspect of Smartstack is how we built it as a product platform that can be upgraded as time goes on. In the quarter, we unveiled the first iteration, SmartStack 10, which raises the density of every unit from 7.5 megawatt hours up to 10-megawatt hours. Being able to enhance what SmartStack offers over time, quickly and efficiently, lets us respond fast to changing customer requirements, and that holds value for Fluence as well as for our customers. In closing, we think we possess the correct product and the correct team to succeed in this fast-expanding market; with our initial data center awards contributing to a record backlog and a global supply chain that keeps getting bigger to support future growth, we are dedicated to delivering for customers and generating long-term value for shareholders. Having said that, I will hand the call to Ahmed so he can go over our financial results and our outlook for the remainder of this year.
Ahmed Pasha
executiveHello, everyone. Our quarterly results were indeed disappointing, yet the difficulties we faced stemmed mainly from delays in construction and production start-up at newly built manufacturing capacity, along with the scaling of new products. Actions have been taken to resolve these problems and sharpen execution, and we are now on track with our revised production plan. What matters greatly is that these investments reinforce our global supply chain and put us in a position to serve our expanding backlog. Once these new facilities get past the initial ramp-up stage, we think Fluence will be better situated to achieve profitable growth and build shareholder value. Let's begin on Slide 11. Our Q3 2026 revenue came to $650 million, which is 8% higher year-over-year. That figure fell roughly $90 million short of what we outlined during the previous quarterly call. The gap stemmed mainly from production delays at 2 new contract manufacturing facilities that are presently ramping. Output at the encloser manufacturing facility located in Houston slipped by a quarter because of construction and automation delays. That facility has started limited production and should reach full production levels during the first quarter of fiscal 2027. The second problem arose at 1 of our 2 new facilities in China, where initial production of SmartStack components failed to meet stringent standards and needed rework. That facility now produces consistently to our standards and reached full production in the fourth quarter. Although we anticipate collecting the revenues tied to the Q3 projects that were delayed, the slower ramp-up squeezes the time line for fourth quarter production, shifting part of the deliveries previously planned for 2026 into fiscal 2027. Our Q3 adjusted gross profit captures the lost margin from the revenue shortfall plus an approximately $15 million costs tied to new product rollout and production delays; on top of that, we booked $15 million loss on a planned battery supply agreement, the bulk of which related to a single project. Even with that upfront cost, this arrangement locks in long-term supply and attractive pricing, boosting our capacity to serve rising demand and price future orders more confidently. Let's move to Slide 12 for our fiscal 2026 guidance. Our outlook has been revised to capture our updated expectation for production through the close of this fiscal year. To be more specific, we anticipate revenue between $2.9 billion and $3.1 billion, with a midpoint of $3 billion. The roughly $400 million decrease relative to the earlier midpoint stems largely from manufacturing ramp-up delays that shifted revenue recognition into 2027; regarding EBITDA, we now anticipate adjusted EBITDA ranging from negative $30 million to positive $10 million, with a midpoint of negative $10 million, versus our earlier midpoint guidance of $50 million. Although there are a number of pluses and minuses compared with what we told you before, 2 things account for most of that $60 million decrease: roughly $44 million in margin we lose because about $400 million of revenue moves to 2027, plus $15 million tied to the proposed long-term battery supply agreement we went over earlier; and we still expect annual recurring revenue to reach about $180 million by the close of fiscal 2026. Let's go to Slide 13 for news on where we stand with liquidity. We closed the third quarter with roughly $863 million in total liquidity, and that figure includes about $365 million of total cash. As we told you on the previous call, we anticipate total liquidity getting back to the $900 million mark by the close of the fiscal year, powered by how we deliver on the project backlog built into the guidance. The takeaway is that our liquidity keeps covering our near-term working capital requirements, especially as we head into the quarter that brings the most revenue. As for what we need in 2027, we feel good that the liquidity we have now leaves us in a strong spot to succeed. Still, as Julian pointed out, the orders we expect to bring in are hitting new peaks, and backing that expansion could call for another $300 million to $500 million of working capital across the next year. We'll stay disciplined and seek financing only when we can clearly see a path to profitable growth and value for shareholders. To wrap up, we still have plenty of work ahead, but demand is holding up well, our backlog keeps expanding, and we're making the moves required to sharpen our execution and underpin profitable growth over the long run; with that, I'll hand the call back to Julian.
Julian Jose Marquez
executiveAppreciate that, Ahmed. I'd like to wrap up by highlighting a few main points. To start, the momentum in orders is still going strong. Our intake for the third quarter, the record $6.4 billion in backlog we hold, plus that first order from the data center developers — all of it demonstrates how well our product strategy and sales push are working. As things stand, we anticipate orders hitting another record during this year's fourth quarter. Next, more manufacturing capacity. New contract manufacturing capability is being brought online both in the U.S. and overseas, and we've restructured the organization under fresh leadership to improve how we execute. Third, what we offer in products. By combining SmartStack's density, safety and reliability metrics with our software and controls abilities — enabling quick response, smooth flow and remote operation — we've secured a leading position to satisfy rising demand across the varied customer segments we serve. To sum up, we're setting up this company for continued profitable growth and for delivering value to both our customers and our shareholders. George, before you get a chance to ask, I truly want to say sorry for the technical glitch this morning — we'll sort out what caused it — but we'd been waiting in the hall for some time, and while you were waiting too, we weren't connected. So apologies for that, everyone; we genuinely appreciate and value the time you give us, and we realize it was somewhat of a waste of time. But George, good morning.
George Gianarikas
analystPerhaps to start, could you give us a bit more detail on the production delays and walk through what's actually going on at the facility?
Julian Jose Marquez
executiveYes. Great. So, as you're aware, we're scaling the company, and with that comes expanding our production capacity. In line with that, we added 2 new manufacturer groups — one focused on the international market, and one focused on the U.S. market. For the international market, we're partnering with contract manufacturers that are reputable, well-known, and seasoned. As you know, one of these manufacturers builds our SmartStack for international markets. Another one of those manufacturers produces our parts — the components that sit on top of the skids we have; and the first production run had some quality — it wasn't passing our stringent testing, and we had to push production back significantly to make sure we brought production in line with our quality standards. That resulted in significant delays that have been significant; but since then, we've fully resolved it, and now we're producing, and they're working full time. We're fully ramped up; they're doing a great job, but we won't be able to recover the full amount of the volumes we had — we lost during the quarter — during the year. So that's that case; and we feel confident, and we're seeing it today, that they can meet our quality and our volumes going forward, and it will really position us well to serve the international market with a competitive product. The U.S. is a bit different. In the U.S., we're building a full facility with our contract manufacturer that operates out of Vietnam. That same one is standing up fully automated facilities, an improved version of the one we have in Vietnam, fully automated — a lot more automated because of the U.S. labor cost in some way, but a fully automated system; and they ran into construction delays, where the construction delays were then we got delays related to the utility connection. And because of that — we've been running the plant on generators, and that meant we had to manage — we couldn't do all the work in parallel. That meant some of the automation took longer than. And it's the same thing as these delays got stuck on one another, there was a point where it was clear that we will not — we were not going to be able to recover the volumes for '26 and that we had to move volumes to '27. That facility is ramping up, it's producing today. It will connect to the grid in the next couple of weeks. The issues are being resolved. And as I said, this is very much a sister company to the one that's in Vietnam. Thus, we have confidence that the output targets we've established for ourselves during this quarter are going to be achieved, and that the problems we've pinpointed have been given adequate resources and have been fixed. So our confidence level is high regarding this. On a broader note, I'd mention that this plant is going to give us an edge in the American marketplace that, in our view, plays a very significant role in our approach within the U.S. market. It's going to let us manufacture 15 gigas of goods made entirely in the United States, with completely automated integration. Therefore, we're genuinely pleased about what we're set to get. That said, we are facing the holdups that, regrettably, we were unable to completely sort out in time.
George Gianarikas
analystAnd as a quick follow-up, could you give us an update on the commercial momentum you've seen lately in data centers? In particular, how would you describe the competitive landscape, plus your win rates and the deals you've been involved in? And which key factors set you apart and drive those wins?
Julian Jose Marquez
executiveYes. That's a really excellent question. I'd say — why do we come out on top? We come out on top thanks to the density, the safety, and the reliability of Smartstack when it's paired with our operating systems, which enable highly efficient load management and extremely strong response times for low voltage ride through. So it comes down to a mix of the technical side — our operating systems — and our enclosures, meaning our delivery equipment, which are both safe and reliable. That's the reason we win. On the whole, it's been extremely strong. It isn't — and we're quite pleased with the momentum we've gained; this is much better than what we had planned, and we're extremely confident that as that industry expands, it will play a significant role. Another thing that's interesting for us is that we're now looking beyond just the U.S; most of the activities we have and the contracts we've signed to date come from there, but we're also examining some of our markets to — working with certain hyperscalers and some of those same developers to support them in additional markets, and I believe that will position us — our global footprint will assist us in capturing that demand on a more global basis.
Brian Lee
analystI'd like to ask about the increase in battery cell costs. It seems this involves a supplier located abroad, but could you share a bit more information? Is there any connection here to the new ownership at AESC? Or perhaps you could just take us through what is shifting that affects expenses? Also, will this weigh on your procurement and costs in fiscal 2028 too?
Julian Jose Marquez
executiveYeah. Excellent question. No, this relates to the international market — it's an international matter; it has nothing to do with AESC. And we signed a long-term agreement covering not just supply but also a degree of technological alignment regarding how the batteries will function in our modules and how we collaborate moving ahead. It's a contract with a longer horizon that we think will place us in a strong position for '27 and '28 and beyond. That said, we were required to record a charge on one project we had that was being provided by the same customer, which, as the deal was restructured, we had to take. So that's the situation. But the project's NPV is considerably greater than the charge we are recording. So we made the decision to record the charge and proceed. That's the story. I believe that we — as our growth has carried on, we think that aligning our technological road map with that of our < > suppliers is essential to our success over the longer term.
Brian Lee
analystYeah, that's reasonable. All right, and now perhaps one thing about the conversion cycle, since — whenever you check Slide 7, clearly there's been significant backlog expansion over the last 2 years, plus considerable pipeline growth, particularly during the last 2 quarters. So you've got substantial top-of-funnel momentum as you enter fiscal '28. Clearly, certain operational difficulties are causing problems when it comes to hitting expectations this year. Yet what's the right way for us to consider the conversion cycle given these unprecedented backlog levels, along with the effect from those data center and hyperscaler bookings? Any indication of how soon we ought to begin seeing these become P&L impact? Plus does it vary from the backlog conversion cycles you've had historically?
Julian Jose Marquez
executiveWell, like you mentioned, we're beginning — only beginning with data centers. Therefore we possess no — we possess restricted proof points regarding what it is. What proof points we do possess show they operate on a far quicker conversion cycle. There's the deal with the developer; we got it signed from lead to contract within under 3 months, which is incredibly quick, and they'll likewise experience a really quick conversion cycle moving forward. Thus we think those are going to help speed up our conversion cycle. Our typical — the remaining 90% today, or our other segments, operate on the identical conversion cycle of approximately a year to 18 months that we'd previously had. So like you're aware, we recognize revenue, meaning revenue recognition happens based on the program's milestones. And I'd say within an 18-month span, we recognize the complete revenue, with a portion recognized quite fast since we recognize milestones as we proceed with executing the project. It's not as if everything occurs right at the end.
Julien Dumoulin-Smith
analystA few items, and I'll be quick, just to go back over this. First, you said something regarding how fast the VTM has been moving — the prospective buyers for VTM. Could you say a bit more about what you expect in terms of the pace of added bookings going forward tied to some of those agreements? And could you also say a bit more about who these buyers are, given that, clearly, during the prior quarter, we mentioned a few specific ones. VTM might involve a range of various types of counterparties too. Could you describe the character of those counterparties? And I have one brief follow-up.
Julian Jose Marquez
executiveSure; previously, our discussion centered largely on hyperscalers. And at this point we have — the hyperscalers have come aboard into — that was our strategy, approach the hyperscalers since we recognize that is the gateway for the developers. And what we have observed with the develop — and a shift has occurred when you speak with hyperscalers, chiefly speed to power, chiefly quality of power solutions. That is what they aim to invest in, extremely technical evaluation, extremely deep comprehension. When we speak with the developers, it is chiefly speed to power. And what we have observed is that the need — the developers are — I would say, I am not sure at minimum what we have observed so far are in much more of a rush than hyperscalers are; thus we view that market as far more active, and we view those activities, particularly progressing from leads to pipelines to orders more rapidly. So that is what we can state is what we have observed up to now. The pipeline at present, hyperscalers hold the bulk, yet the developers make up the expanding portion that is functioning right now.
Julien Dumoulin-Smith
analystGot it. That's great. And then, if I could just ask briefly — I noticed a remark in here regarding strategic expenses, specifically from recently. I'd really like to know how you're approaching things on the strategic side for the company, and whether there's anything worth pointing out there. I'm not sure, maybe on the expenses for the quarter? Is there anything in particular we ought to keep an eye on as participants?
Julian Jose Marquez
executiveWe are — this is — what we're doing is — we're constantly out in the market, and we're constantly examining it. So, as you're aware, earlier in the year, we considered AESC as a possibility, and a portion of those costs relate to the AESC review along with all the analysis that has to be performed for the AESC review. So there's nothing to announce.
Julien Dumoulin-Smith
analystUnderstood. Still weighing other options when it comes to procurement?
Julian Jose Marquez
executiveWe're looking at — a great deal of our time is going into examining — holding conversations with every battery capacity provider out there and speaking with them. There's honestly nothing to discuss right now, yet that's where our hours are going, since we perceive a chance to collaborate more closely with U.S. battery manufacturers.
Dylan Nassano
analystI just wanted to verify something — regarding how far-reaching those manufacturing plant delays you're experiencing are, how much, if anything, are they affecting the hyperscaler MSAs and the orders you're referring to in this discussion?
Julian Jose Marquez
executiveYeah. No, not in any way. What we're dealing with involves agreements already in place that were signed 1 year, 1.5 years back, and they have no connection whatsoever. They're standard agreements — ordinary contracts that include some tough segments. So there's no impact at all on the MSAs of the contracts we're currently signing with data centers.
Dylan Nassano
analystUnderstood. All right, so perhaps it would be useful if you could reset the baseline for us regarding how many MSAs there are. My understanding is that last quarter it was 2; and precisely how many hyperscalers does that figure cover? Also, could you make it clear — you've got the first order worth $300 million, and then the $550 million that was awarded — do both of those come from one hyperscaler? Or are they from 2 separate hyperscalers?
Julian Jose Marquez
executiveWe currently hold 2 MSAs, each with a different hyperscaler. Because we're engaged and collaborating with these hyperscalers, they pass along referrals to developers who work on their behalf. And at present, as I mentioned, with our pipeline and our efforts, a great deal of our time goes to developers as they keep doing substantial work alongside the hyperscalers. Yet they have a pipeline demanding extremely fast turnaround. Regarding the agreements we entered into, the $300 million contract was signed with a developer that one of the hyperscalers holding an MSA with us referred to us; so that agreement involved a developer constructing a data center for one of the hyperscalers, and we will supply our equipment for it. Then there's — with one of the hyperscalers, a tender came up, we were awarded the $550 million, we sold it, and right now we're finalizing every last technical detail so it can be turned into backlog, which ought to happen over the next few months. And we keep striving to engage additional hyperscalers, and with both hyperscalers we're working with, we see several projects, in the U.S. as well as internationally, that we will supply — that we will seek to bid on, and we'd like to serve them using our products.
Vikram Bagri
analystFirst off, I'd like to inquire about the margins. A bigger competitor of yours mentioned pressure on margins within storage. So I'm curious how you view that 10% to 15% margin target. You've got backlog turning into $2.2 billion in the coming year, and $2.8 billion the year after; that means quite far-out backlog right now. Is there any difference — does margin vary as you examine that backlog across the short term, the medium term, and the long term? Are you seeing those same pressures that your competitor brought up?
Julian Jose Marquez
executiveWhat's true is that we remain very comfortably inside that 10% to 15% band. Looking at what we posted this year, once you strip away certain one-time items from the year, we'd have landed near the 12% figure we told the market to expect; therefore we have confidence. Nothing in our backlog or in fresh orders suggests otherwise — both align with the 10% to 15%. That pressure which the other major vendor said they were experiencing is not something we grasp; perhaps something about their cost structure differs. Going forward, the central challenge for this company is scale; that's what it comes down to. The difficulties we're facing as we grow relate to scale, and scale fuels competitiveness — likely with our rivals, since some already have scale, they're encountering different problems, whereas for us, they aren't < >.
Vikram Bagri
analystUnderstood. So you mentioned scale, and that connects loosely to what I want to ask next; guidance for the upcoming fiscal year will be discussed on the following call. What I'm curious about is the mechanism — how do you approach putting that guidance together? For fiscal '27, there's $2.2 billion of backlog. Should we think of 85% coverage as the correct framework? Or does it need to link to capacity that's being brought online, how much of it you're able to bring online, capacity from the supplier side, and/or ought the 85% coverage be greater? On a related note, it's very encouraging to see the executive management changes aimed at improving execution. What particular changes will Roman and Peter implement over the next 12 months? Since you work with contract manufacturers, their control over operations is relatively limited. So what kinds of changes will the new team make to guarantee on-time deliveries?
Julian Jose Marquez
executiveI'll take your second question first. The reason I'm bringing Roman in to lead our manufacturing and supply chain is his deep transformation background and his work in supply chain and manufacturing — he has a great deal of transformation experience. As you scale a company, one thing you come to realize, and we're moving to a very different scale, is that a transformation is needed: your systems and your processes have to transform to match the new scale. That's the work he's doing. Our suppliers are very good. Our manufacturing partners are great. So this isn't a strategic change — it's execution. That's his focus, on delivering. Peter has been leading SmartStack's development. So I believe he'll keep making sure that development of SmartStack continues; and for '27 and beyond, the key thing is to keep integrating our software and our hardware so that we can give customers something much more stringent than what we've had historically. That's what these 2 groups will do — transform our manufacturing, which doesn't mean changing suppliers, it just means making sure our processes, our systems, our planning match our larger scale, and keep developing Smartstack and our platform and keep strengthening the link between the two; so very happy. And your first question concerned the...
Ahmed Pasha
executiveCoverage.
Julian Jose Marquez
executiveRegarding coverage — my position hasn't changed: 85% remains the correct figure, within that 80% to 90% band. That's how we see it. Obviously — and this is something we've learned — with new facilities, even when a plan is in place, even when a hedge and a contingency are built in, here's what happened: our hedging ran out — we exceeded the hedge — and then the contingency also got exceeded, and that's the point where a problem turns into a real problem. So when it comes to new facilities that are on the way, chances are we'll hedge them for next year. That said, no nonclosure facilities are anticipated by us. Nor do we anticipate any significant fresh manufacturing capacity coming from that which would back our revenue in 2027; therefore my confidence is high that in 2027, coverage of 80% to 90% will prove to be the correct level, though we'll certainly keep examining it as we go.
Justin Clare
analystI'd like to inquire about the guidance. Given the updated revenue and adjusted EBITDA figures, it appears fiscal Q4 gross margin might come in at approximately 12%, somewhere in that vicinity. Could you shed some light on what's assumed for the gross margin in Q4? Also, do any expenses tied to the new products or the fiscal Q3 production delays carry over into fiscal Q4?
Ahmed Pasha
executiveOf course. Justin, it's Ahmed here. Based on the guidance we talked about, I believe the implied gross margin for Q4 is around 11%. If you compare midpoint to midpoint, it's slightly lower. And yes, we've factored in extra costs we might face given the outlook as we see it today. There are lots of puts and takes, but on balance, we're fairly confident that once those added delay-related costs are accounted for, we'll hit the guidance we provided, according to the outlook we have right now.
Justin Clare
analystUnderstood. All right, that's useful. Now, regarding the supply chain, I'd like to hear your thoughts on how the FCC's inverter limits might affect things. I'm aware that you can source inverters from a supplier based in the U.S. Do you have any exposure when it comes to procuring inverters from China? Also, I'm just interested whether domestic sourcing that meets compliance requirements might give you an edge competitively, given that your customers are somewhat reevaluating their reliance on imported inverters.
Julian Jose Marquez
executiveIn the U.S., we deal exclusively with inverters that aren't Chinese — largely manufactured in the U.S., with a portion brought in from Europe. So our belief is that no impact will hit us at all. That's been our approach from that point onward. We do observe that those inverter restrictions will likewise expand in Europe, that this will occur there too, and we anticipate it and we're striving to keep going — in Europe — we utilize a combination of Chinese and non-Chinese, yet we're striving to prepare for a completely European solution serving the European market. Our perspective on the market, from day 1 when we began, is that additional technological restrictions will emerge around this technology as it keeps expanding and takes on a bigger role within the grid.
Christine Cho
analystAll right. I'd like to begin by discussing the $1.44 billion in orders booked during this quarter. Of that total, $300 million came from the behind-the-meter project, while the remaining $1.1 billion represented your standard front-of-the-meter project. Regarding that $1.1 billion, how should we break it down between the U.S. and international markets? Also, when it comes to the $850 million award involving the hyperscaler or data centers as a group, does EPC factor into those? Is there any distinction to be drawn between the developer and the hyperscaler? And should we take it that both of these projects run for 2 hours?
Julian Jose Marquez
executiveYes. When it comes to the data centers, they run for 2 hours, which is something we typically don't provide, and in the market, offerings below 2 hours essentially don't exist. So every market sits at 2 hours. There's no meaningful distinction regarding the technical specifications, and margins are largely in line as well. I'd note that developers, who tend to be smaller firms, are nimbler and — and are able to reach decisions much more quickly, so their conversion rate is considerably quicker. So I'd characterize our present perspective on this as — it's a segment that's still emerging, as you're aware. So we're picking up certain things as we go along, yet feeling quite positive about it; as for the $1.1 billion that isn't data center related, by and large the U.S. remains the place where we're gaining the most ground. I'd put the figure at roughly 60 to 40, with 60% from the U.S. and 40% from international markets. That isn't to say this will be the pattern going forward. It was a quarter featuring a great deal of activity in the U.S. and only limited activity internationally.
Christine Cho
analystAll right. Then only a small administrative point. According to the 10-Q, certain IEEPA refunds existed. Was any portion of that reflected in COGS? Or instead was it allocated toward inventory?
Ahmed Pasha
executiveCorrect. I believe that ties to what I mentioned regarding the puts and takes. We do have a certain IEEPA refund. My sense is it comes to slightly more than $10 million, yes, which we have recorded year-to-date.
Christine Cho
analystSo we should expect to see additional ones come through in Q4, is that right?
Ahmed Pasha
executiveThat's correct, a few...
Julian Jose Marquez
executive< > since a portion of it is recorded right away, while another portion ends up in inventory. And my understanding is that once that inventory turns into revenue, you then record it gradually.
Chris Dendrinos
analystI suppose I really don't want to keep hammering away at this, but I'll follow up just a bit more on what Rob asked regarding the guidance. Still, when I look at what the outlook is for the rest of the year, it's a pretty wide range, simply because of how much time is left. So what's behind that range in the guidance? I'm really just trying to get a feel for how much confidence you have in the path of execution from here on out.
Ahmed Pasha
executiveYeah. No, that's a reasonable question. I don't believe you should read too much into it. Honestly, I think when it comes to execution, there's still some work for us to do there. So we felt it was prudent to provide guidance in case there are any incremental costs we may have to incur as we ramp up our operations; so that's really what's driving that wider gap compared to the revenue guidance we gave. So EBITDA guidance is wider than what you'd expect. So the only thing that reflects is additional costs that we may incur. So that's really the underlying driver.
Ameet Thakkar
analystPerhaps I'll just pick up where Chris left off, but approach it somewhat differently. When I consider the midpoint of your fiscal year 2026 guidance as it stands, it seems to suggest roughly $1.4 billion in revenue for 4Q. If I examine how revenue recognition works and what the implied ASPs look like, it comes out to something like, say, 235. That appears to point to about 6,000 megawatts of recognized revenue. So — are you expecting a significant share of what gets recognized in 4Q to involve EPC? I recall that certain European contracts you had previously carried fairly appealing implied ASPs, since EPC work was part of them. Does that hold true for 4Q? And I have one more brief follow-up.
Ahmed Pasha
executiveNo, I wouldn't say so — the bulk of that sits in the U.S., and it's primarily the deliveries we have under our domestic content.
Julian Jose Marquez
executiveAnd what I'd say is that, for this quarter, we've already manufactured and completely brought together about 50% of what has to be done during the quarter. So we have confidence we'll reach those figures. Obviously, as I mentioned, we're increasing output in Houston, and we think we've got that situation managed. Yet with any increase in production, there are always factors we can't foresee right now, which explains the broader range. But nothing that's out of step with our capabilities. We've already done it. Those units are already aboard vessels heading where they're supposed to go, or on trucks heading where they're supposed to go. So our sense is the guidance remains solid.
Ameet Thakkar
analystGot it. Then, if you could sort of assist us in sort of — it appears that the total megawatts you've deployed stayed the same compared with the previous quarter. And I believe they're only up roughly, I think, 8% or 9% since the start of the year — or as of the close of last year. I mean, I think the cumulative deployed megawatts figure is something like 7.4 gigawatts, I think at year-end, versus 6.8. But revenue, clearly, on a percentage basis, is somewhat stronger. Could you just sort of help us grasp when every one of those megawatts actually gets deployed?
Julian Jose Marquez
executiveIn our metrics, what we mean by deployed megawatts is projects that have hit substantial completion. Our revenue recognition takes place much earlier, with the bulk of our revenue coming when we hand the equipment over at the site and title transfers. So that's the source of the disconnect you're seeing. So we use — under our definition, delivery comes after substantial completion, whereas revenue recognition is tied to transfer of title, which happened a quarter later. So down the road this will turn into what we refer to as delivered products. I realize it causes confusion, since our competitors count delivery as actually delivering to the site instead of substantial completion, and we likely should change our definition so it lines up better with how revenue recognition is defined.
Ahmed Pasha
executiveThat represents the completion percentage.
Julian Jose Marquez
executiveRight, Amit — so there's a mismatch there. Anyway, thanks to all of you for being here. And once more, we truly want to — we apologize for running behind because we ran into technical problems; that's genuinely disruptive for everyone on the line, and we promise it won't happen a second time. And we appreciate very much the time you've given us and the questions you've asked.
Operator
operatorThis concludes today's meeting. You may now disconnect.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Fluence Energy, Inc. transcript — plus 133,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Fluence Energy, Inc. earnings transcripts and 133,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Fluence Energy, Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.