What were the key takeaways from Freeport-McMoRan Inc.'s July 23, 2026 earnings call?

In the second quarter of 2026, Freeport-McMoRan Inc. (FCX) reported significant progress in operational performance, particularly with the Grasberg ramp-up and increased production in the Americas. Revenue for the quarter was driven by favorable copper prices and improved operational efficiency, leading to a 65% increase in consolidated net income compared to the same period last year. Management maintained a positive outlook, expecting copper sales to increase by over 20% in the second half of 2026, while also noting a slight decrease in average unit net cash costs to approximately $1.90 per pound, down from prior guidance of $1.95 per pound.

What topics did Freeport-McMoRan Inc. cover?

  • Grasberg Ramp-Up Progress: Freeport reported that production rates at the Grasberg Block Cave mine doubled during the quarter, from an April average of 34,000 tons per day to 69,000 tons per day in June. Management stated, "The Grasberg team has great morale and enthusiasm as it continues to execute exceptionally well."
  • Increased Copper Production Guidance: Management indicated that copper sales are expected to be over 20% higher in the second half of 2026 compared to the first half, driven by higher volumes at Grasberg and U.S. operations. They noted, "We expect a large increase in second half sales volumes driven by higher volumes at Grasberg and our U.S. operations."
  • Cost Management Improvements: Freeport's average unit net cash cost for 2026 is now estimated at approximately $1.90 per pound, slightly below the previous estimate of $1.95 per pound. Maree Robertson stated, "Our current estimate for 2026 average unit net cash cost approximates $1.90 per pound, slightly below the April estimate of $1.95 per pound."
  • Shareholder Returns: The company returned $600 million to shareholders in the first half of 2026, including approximately $200 million in share repurchases. Management emphasized their commitment to returning cash to shareholders while investing in growth projects.
  • Bagdad Mine Expansion Plans: Freeport is nearing an investment decision for a major expansion of the Bagdad mine, with preliminary capital estimates around $4.5 billion, which is approximately 30% above the estimate prepared in 2023. Kathleen Quirk mentioned, "We expect to be in a position to move towards a final decision in the second half of this year."

What were Freeport-McMoRan Inc.'s July 23, 2026 results?

  • Average Unit Net Cash Cost: $1.90
  • Shareholder Returns: $600 million
  • Bagdad Mine Expansion CapEx: $4.5 billion

Freeport-McMoRan's strong operational performance and positive outlook for copper demand position the company favorably for future growth. The successful ramp-up at Grasberg and strategic expansions in the Americas are key catalysts. However, investors should monitor regulatory developments in Indonesia and potential cost escalations related to expansion projects.

Earnings Call Speaker Segments

David Joint

executive
#1

Thanks, Regina, and hello everybody on this morning's call. It's great to have you join us for the Freeport conference call. FCX published its operating and financial results for the second quarter of 26 earlier today. You can find the press release from today along with supplemental schedules and slides on our website, fcx.com. We're streaming today's call live over the Internet, and anyone is welcome to tune in by going to our website homepage and selecting the webcast link for this conference call. Besides analysts and investors, members of the financial press have also been asked to join today's call. Later today, a webcast replay will be posted on our website. Before we get into our remarks, we want to remind all of you that certain of our comments on this call and today's press release involve non-GAAP measures and forward-looking statements. And actual results could differ materially. We ask that you review the cautionary language in our press release and slides, as well as the risk factors outlined in our SEC filings, all of which can be found on our website. Joining me on the call today are Richard Adkerson, Chairman of the Board; Kathleen Quirk, President and Chief Executive Officer; Maree E. Robertson, Executive Vice President and Chief Financial Officer; and other senior members of our management team. Richard is going to give some opening remarks, Kathleen and Maree E. will walk through our slide materials, and after that we'll open up the call for questions. Richard?

Richard Adkerson

executive
#2

Thank you, David, and I appreciate all of you being here with us today. It's a pleasure to share FCX's results for the second quarter. One word captures them: Progress. Our shareholders at Freeport keep gaining from the strategy we've followed for a long time — one built around our leading position in copper and a portfolio of assets with long lives and proven records in operational excellence, project development, and capital allocation. Copper is what electricity requires. As electrification spreads across the globe, what we produce will be needed more than at any point before. Freeport stands especially well placed to expand as the market expands going forward. Members of our team will speak with you today about the tremendous strides we made during the second quarter throughout our worldwide operations. In particular, the successful execution of the Grasberg ramp up, along with the robust operational execution and financial results delivered in The Americas. With our large scale, long life production and our appealing growth pipeline, Freeport is positioned extraordinarily well. Remaining foremost in copper stays our aspiration. Kathleen and I traveled to Jakarta and a mine site in Papua during June. My trips to Indonesia have happened regularly since 1988. Every visit inspires me — both because of what Freeport has accomplished in Papua and in Gresik, and because of how the Republic of Indonesia has grown and advanced through the years. What lies ahead for Indonesia and for PT Freeport Indonesia is the best. I feel blessed and proud to have witnessed personally and taken part in this growth and progress. Everyone in our Freeport Global family takes pride in the dedication and meaningful progress our team in Papua has shown in ramping up the Grasberg Block Cave Mine. Spirits and enthusiasm run high on the Grasberg team as it keeps executing exceptionally well in gaining access. We anticipate continued progress on the Grasberg recovery and look forward to finalizing our mine rights extension with the government of Indonesia, allowing Freeport to keep creating benefits for every stakeholder in the decades ahead. We also take pride in the clear progress the Americas team is making by applying modern, innovative technology to boost production and reduce cost, producing rising profits from our mature mines; it is genuinely impressive, and once more, what lies ahead is the best. Kathleen Quirk, our CEO, will now lead our discussion.

Kathleen Lynne Quirk

executive
#3

Okay, thanks Richard, and I appreciate everyone joining the call today. On this call, we'll go over how we performed in the second quarter and bring you up to date on what we're doing, our projects, and the appealing outlook ahead. You'll hear about the efforts our teams are making around the world to create value. The strides we've taken to bring back safe and sustainable output at scale at Grasberg, the push forward on operational excellence and new technology efforts in the US, and movement on possibilities for an exciting new period of organic growth. Beginning on slide 3, here are the second quarter highlights. Copper sales and unit cash costs came in above what we had forecast; we made consistent headway on the Grasberg ramp up, and along with supportive metal prices, that produced sizable margins, cash flows and earnings. The results show how strong and varied our portfolio is, with our U. S. Mining operations delivering 2.4x more operating income in the first half of 2 thousand 26 than in last year's first half, with strong conversion to the bottom line; a 65% rise in our consolidated net income for the first half of 26 versus last year's first half shows this even more clearly. Our Grasberg ramp up plans remain on schedule, and along with ongoing initiatives and greater production in the Americas, we're set up for future growth in volume and margin. We're moving ahead on our future growth options with a set of projects underway to scale output from our innovative leach initiatives. We're close to an investment decision on a major expansion of our Baghdad mine in Arizona; and we're furthering our regulatory work in Chile for a significant expansion at our El Abra mine. During the quarter, we raised our ownership in Cerro Verde by opportunistically buying Cerro Verde shares on the open market, bringing total purchases across an approximate 2 year period to over $300 million and lifting our ownership by 2% to over 55%; beyond that, we gave back $600 million to shareholders in the first half, including roughly $200 million through share repurchases. Our financial position is still solid and the markets for our products look favorable. That gives us a strong base to invest in value enhancing growth while also returning cash to shareholders. On slide 4, we restate our continuing priorities. They focus on our pursuit of growing shareholder value. Disciplined execution of our plans, including our ramp up progress at Grasberg, realizing the value of our Americas Leach opportunity, embracing new technologies to boost performance, and investing in profitable growth will let us create substantial value in our business. Our team is dedicated to making these initiatives succeed, committed to getting past challenges as they arise, and unwavering in our pursuit of excellence in everything we do. Moving to the copper markets, on Slide 5. As a top worldwide provider of copper, Freeport holds a strong strategic position and gains from the metal's vital and ever more significant function within the global economy. Because of its outstanding thermal conductivity, copper is the metal of electrification, and electrification is accelerating across the globe. Around the world, demand for copper should climb across many uses, among them the enormous needs of the power grid to enable new technologies. Through June, year to date, LME copper prices averaged $5.93 per pound. On the LME yesterday, it settled at $6.30 per pound, roughly a 12% gain since the beginning of the year; within the US, COMEX copper right now trades at about a 2% premium over LME pricing. When we talk with customers throughout the US, they keep telling us about strong copper demand and order books tied to AI data centers and the associated energy infrastructure, plus better demand from the auto sector, which is more than compensating for softness in private construction. Fresh reports from China, the biggest copper consumer on earth, show sustained strength in copper demand linked to power grid and electrical infrastructure, along with sizable exports of Chinese manufactured goods that contain copper. Inventories that are visible in China keep shrinking toward multiyear lows, while exchange inventories held outside the US are extraordinarily tight. Looking ahead, it is evident that the market will need extra copper supplies to satisfy rising demand. And at Freeport, we hold a valuable, geographically varied portfolio of copper assets and are strategically well placed for the long term, with large scale production, long live reserves and resources, and a portfolio of low risk brownfield expansion opportunities to serve a growing market. Now I will turn to the operating highlights by geographic region, which can be found on slide 6. Beginning with The US, we are achieving important and tangible progress in raising mining and processing rates. Our equipment reliability metrics are getting better, with a key example at Morenci, where second quarter mining rates came in 30% above the average achieved over the last 5 years, a great accomplishment. Maintaining those higher mining rates will lead to improved copper production over time, and we expect copper production to increase in the coming quarters. Our innovative leach initiative keeps showing promise, and a number of projects are underway. Targeting meaningful potential to scale. The deployment of our first internally developed additive is delivering results, and we plan to field test 2 additional high potential additives in the coming quarters. Pilot testing at Morenci is in progress, where we are testing heated solution, leaching solution in our existing stockpiles. We know that raising temperatures in our stockpiles will boost recoveries, and our work is centered on finding the most effective engineering and cost solution to achieve this. We remain encouraged by the ability to achieve further scale in the near term and unlock our long term path to 800 million pounds per annum from this initiative. Additionally, we keep finding ways to bring new ideas into our routine mining operations, and we recognize considerable worth in deploying new technologies to improve how we perform. In South America, results were favorable, since the team successfully managed limitations at both the mine and the mill. Even with those difficulties, extraction and processing volumes for the quarter came in above what we had anticipated, and our sales and cost results were marginally stronger than the projections we had at the start of the quarter. At Alabra, the site we run in Chile together with Codelco, a great deal is happening right now, including an expansion of the leach pad, plus intentions to carry out trials in the latter half of 26 involving heated stockpile injections aimed at boosting leach recoveries. We are happy with how discussions have gone with the Chilean government after we filed our environmental impact study in March for a major expansion at El Abra, and we keep moving that effort forward; we are delighted to share that the ramp up of the Grasberg Block Cave mine showed consistent advancement across the second quarter. As the chart makes clear, output rates at the Grasberg Block Cave grew twofold over the quarter, rising from an April average of 34 thousand tons per day to an average of 69 thousand tons per day in June. Improvements to the material handling system supporting our automated rail system remain on track. And we keep pushing ahead with preparations to restart production at Block 1 South in 2027.

Kathleen Lynne Quirk

executive
#4

There are additional initiatives we're pushing forward to bring risk down. Consistent with our April 8 update, we're still targeting district-wide production at approximately 65% of full capacity, with a grade of 0.580%, by the midpoint of 2027, and then hitting full capacity before 2027 ends. The team is doing exceptional work getting the phase ramp up operational in a way that's both safe and efficient, and we continue to reduce risk across the plans while strengthening our confidence in the longer-term outlook. After signing a memorandum of understanding with the Indonesian government earlier this year to prolong our operating rights for the resource's lifetime, we submitted a formal extension request in June, consistent with the conditions set out in that MOU. If that license gets official approval, it would ensure we can keep running at a large scale without interruption, reinforce our ability to pursue future expansion, and generate enduring advantages for the numerous stakeholders of Freeport Indonesia. Turning to slide 7, where we cover growth. Consistent with what we've said about market fundamentals, it's obvious that more copper supply is needed, and Freeport is in an excellent position to provide that additional supply thanks to a robust pipeline of organic growth. What benefits us is a collection of projects that can be developed from resources Freeport already knows about, located in places where we've long operated and have deep experience. Several of these projects have been advanced far enough that a route toward later, more developed phases is now visible. The Americas segment is moving into an expansion phase. In both the near term and the medium term, we see opportunities to grow our leach operations and to increase production at the Baghdad mine in Arizona by more than twofold. Over a longer horizon, we have growth in the Safford Lone Star District, as well as a promising project at El Abra in Chile. Regarding the Grasberg rights extension we spoke about earlier, it will open up additional opportunities further out in time. Every one of these efforts is a brownfield undertaking. They leverage the infrastructure we already have, our skilled teams, and the ties we've built with important stakeholders and communities. That lets us move ahead more quickly and with reduced risk compared with a greenfield project. We're using creative approaches to drive up efficiency, bring down both cost and capital intensity, and trim the time it takes to get our projects done. A strong illustration of putting new technologies to work so we get the most value out of what we already have is the innovative reach initiative, which offers high potential at low cost. Because the Leach initiative requires so little capital, it ranks among the more appealing projects in our sector when it comes to investment returns. We went over what came out of the existing additive we're currently testing. We also expect more outcomes to show up over the next few quarters, driven by the additional additives we're putting into use as well as heated leach solutions. Those will help us hit our near-term scaling targets and lay out the route to much greater leach output down the road. Right now we're completing the investment case for a significant build-out at our Baghdad mine in Northwest Arizona, and we think we'll be ready to head toward a final call during the back half of this year. This project offers a substantial resource located within an operation that's already up and running, opportunities to realize economies of scale, and a supportive tax and fiscal framework here in the US. We've given this project a careful, thorough review. It has the potential to make Baghdad the second-largest copper mine in the entire US, with only our flagship Morenci mine ahead of it. Beyond that, we've put a number of steps in place to lower the risk involved in executing the project. Our figures for capital costs aren't locked in yet. While engineering work continues, we're working hand in hand with vendors and contractors to double-check those capital cost figures and bring the economic evaluation up to date. That review is still underway, but the early signals, based on how the market looks right now, suggest capital of about $4.5 billion. That comes in around 30% above the estimate we assembled back in 2023. The increase reflects escalation in commodities and labor, changes to what the project covers, and revised figures associated with added engineering. Because we improved how we run things, this project can still stand on its own with copper priced at $4 a pound. That figure sits far under what the market shows today. We have a lot of upside over the long haul if copper markets stay strong. Just to remind everyone, nothing major stands in the way on the permitting side. A great deal of planning and preliminary work is already behind us, so we could wrap up the project within 3 to 4 years. Studies continue in the Safford/Lone Star district. This has us quite enthusiastic. To weigh the best ways to expand and develop, we've kept pushing to make the most of the sizable untapped resource we own in an established US mining district, located close to the Morenci Mine. Over at El Abra, there's a major chance for us and our partner Codelco to build out a sizable expansion. The resource base there is substantial — combined copper reserves at El Abra come close to matching the big footprint we hold at Cerro Verde. Officials in Chile are excited about this undertaking and are collaborating with us so the permit gets reviewed promptly. With this project, we're in a strong spot to take El Abra from its current status as a fairly modest producer and turn it into a meaningful piece of Freeport's overall portfolio. Once again, the underlying idea here is a mine that's already up and running in a jurisdiction with low risk. Turning to Indonesia, we likewise have the advantage of a sizable resource base, plus many years of experience and a solid record of success. We're still making headway on the Coochin Liar project over in Indonesia, which helps us keep production costs low and sustain output for the long haul in the Grasberg district, and extending the mine's life creates even more chances for growth down the road. Now on slide 8, we get into how Freeport stands as America's copper champion — a big chunk of our reserves, resources, and future expansion sits right here in the United States. The company is a key American copper producer and easily the biggest player in the U.S. copper market, with a successful track record stretching all the way back to the late 1800s. We're pushing hard on a set of efforts aimed at strengthening our US operations via innovation, automation, and putting money into expanded facilities; our goal is to bring on additional production at low incremental costs so that profitability and resilience improve for our US business. In a sector where it can take over 10 years to develop something, our US operations sit in a strong position, with the possibility of a 60% rise in copper output across the years ahead. Our team feels quite good about these chances—they amount to a meaningful value driver for Freeport. Beyond that attractive growth picture, recent results in our US business have been clearly strong. It came in as the biggest earnings contributor across the portfolio on a year-to-date basis. That underscores how our US business is exposed to favorable copper markets, along with the strength of Freeport's diversified portfolio amid a wide range of market conditions. I'll hand the call over now to Maree E., who will go through the financial outlook, and after that we'll take your questions.

Maree E. Robertson

executive
#5

Appreciate that, Kathleen. Turning to Slide 9, we lay out a three-year projection covering sales volumes for copper, gold, and molybdenum. That outlook stays largely in line with what we gave you back in April. As we progress through 2026, we anticipate a significant step-up in second-half volumes, powered by stronger output at Grasberg along with our US operations. In the reference materials on Slide 20, you'll find that copper sales for the second half should come in more than 20% above the first half, while gold sales should be over 65% greater. Looking at 2027, we're projecting annual copper sales rising by over 20% versus 2026, with gold volumes up by more than 50%. Further growth is anticipated in 2028 across both copper and gold. Our teams continue to prioritize disciplined execution of our plans worldwide, including the phased ramp-up at Grasberg, which is progressing well, plus growing volumes in the US. During last quarter's call, we covered the cost pressures hitting our business tied to the Middle East conflict, along with volatility in oil and related products, as well as sulfur and acid. Although markets are still volatile, our present estimate for 2026 average unit net cash cost sits at about $1.90 per pound. That's a touch under the April estimate of $1.95 per pound, as higher byproduct credits outweigh other unit cost increases. Combining our projected volumes with our cost estimates, Slide 10 presents modeled results for EBITDA and cash flow across a range of copper prices, from $5 to $7 copper. These modeled results rely on the average of 2027 and 2028 using current volume and cost estimates, while holding gold flat at $4 thousand per ounce and molybdenum flat at $30 per pound. Annual EBITDA would land between roughly $13 billion per annum at $5 copper and $20 billion at $7 copper. Operating cash flows would run from about $9.5 billion per year at $5 to $15.5 billion at $7 copper. On the right side, we show sensitivities to various commodities. You'll notice we are highly leveraged to copper prices, with every $0.10 per pound change equating to roughly $390 million in annual EBITDA across the 2027, 2028 periods. We also carry exposure to gold prices, where each $100 per ounce change in price approximates $105 million in annual EBITDA. For molybdenum, which has displayed significant price strength in recent months, each $1 per pound change approximates $85 million per annum. Thanks to our long-life reserves and large scale production, we are well positioned to generate substantial cash flow to fund future organic growth and cash returns under our performance based payout framework. Slide 11 lays out our current forecast for capital expenditures in 2026 and 2027. Our 2026 capital remains consistent with our prior forecast, and 2027 capital expenditures are estimated at $4.8 billion. That's approximately $300 million above the April estimate, reflecting investments in upgraded mining equipment and revised cost estimates. Looking ahead, we anticipate discretionary projects will come in at around $1.6 billion for 2026 and $1.9 billion for 2027. About half of that ties to the Kucing Liar development as well as the LNG project at Grasberg. The remainder covers tailings acceleration and other infrastructure supporting the Baghdad expansion, upgraded mining equipment, and capitalized interest. This discretionary category represents the capital investments we're making in new projects, which, per our financial policy, get funded from the 50% of available cash that isn't distributed. These are value enhancing initiatives, and you can find them detailed on slide 27 of our reference materials. These estimates leave out projects still awaiting completion of final studies and board approvals, including the Baghdad 2x expansion project. We keep managing capital expenditures carefully and will keep deploying capital strategically toward projects offering the best return and risk reward profile. Last, on slide 12, we restate our financial policy priorities: a strong balance sheet, cash return to shareholders, and investments in value enhancing growth projects. Our balance sheet is solid, with investment grade ratings, robust credit metrics, and flexibility within our debt targets to execute on our projects. We face no significant debt maturities during 2026, and we have substantial flexibility for funding the 2027 maturities. Given our strong balance sheet and significant cash flow generation, we hold substantial resources to invest in future growth projects prudently whilst returning cash to shareholders. Since adopting our financial policy in 2021, we have distributed $6.3 billion to shareholders, through dividends and share purchases. And we have an attractive future long term portfolio that will enable us to continue to build long term value for shareholders. Our global team is focused on disciplined execution, profitable growth, and long term value creation. Thank you for your attention.

Kathleen Lynne Quirk

executive
#6

We will now turn to questions.

Lawson Winder

analyst
#7

Thanks, operator, and good morning to Richard and Kathleen. I appreciate the call, and Maree too. It's great to hear from all of you. Nice work on a strong quarter and the advances at Grasberg. If I could begin with Baghdad, I appreciate the extra detail and the extra guidance. You mentioned upfront CapEx that's expected to run somewhat above the 2023 estimate, but you're still targeting an incentive price near $4 per pound. Are there offsetting benefits on the operating side that would balance out that larger CapEx? Also, should a decision on this project be expected in 2026, or should we assume that spending begins in 2027?

Kathleen Lynne Quirk

executive
#8

Thanks, Lawson, and I appreciate your kind remarks. We're putting in extensive effort on the Baghdad project so that we can bring it before our board and pursue final approval during this year's second half. As I said, we've been doing substantial work with our vendors and suppliers to truly pin down the capital cost estimates. We're moving forward and seeking firm bids. We've been engaged with the contract labor organizations that will provide the construction labor, defining the rates and incentives to ensure we attract the best people to this operation — it's a highly competitive construction labor market in this region at the moment, with activity coming from everything including semiconductors, data centers, and so on, plus power generation. So we're doing considerable work to ensure we have solid estimates of what labor will cost and what each of the various components will cost. We've adopted certain approaches to find ways to be more efficient through off-site labor and some prefab work, and we've therefore done a great deal of thorough work on how to carry out the project. Alongside that, we've also been developing the operating plan and working hard to consider the future of Baghdad as not being what a typical project would have been previously, but rather how we can examine the operating model and introduce new technologies; we've already, as you know, deployed the autonomous trucks there. This mine is going to be fully autonomous; we're reviewing other parts of the operating model to gain efficiency. So we've been working on that, working on our operating plans. We've also been examining the throughput from this concentrator and how it could affect our ability to extract more from the existing plans for expansion; and so we've optimized the operating plans. For every input cost, we rely on the long-term markets, and even at $4 copper — which is well below where it sits today — this remains a highly attractive project: it covers the cost of capital and gives us exposure to a very large resource. That will make Baghdad far more resilient, with much lower costs, and a modern facility that carries us forward for decades. As costs come down, the resource grows. So we aren't only advancing the resource; we also have the chance to keep expanding it as we move ahead. There are therefore many attributes that, through the work we've done on this project, we've come to recognize: the operating model can deliver additional efficiencies, and that is improving the economics and helping offset the higher capital cost. That is very helpful. Thank you so much.

Katja Jancic

analyst
#9

Hello, and thanks for letting me ask. Looking at the Grasberg mine plan, it appears copper and gold output dips somewhat in 2028. Could you explain what's behind that?

Kathleen Lynne Quirk

executive
#10

Sure. Across those 5 years, things look much the same as what we showed in April. We did see somewhat lower grades during 2028 versus the earlier forecast. However, when it comes to operating rates and the plans, those remain extremely similar, though sequencing timing shifted somewhat in that 2028 period. All right, thanks. Thank you, Katja.

Carlos de Alba

analyst
#11

Yeah. Thanks. Morning to everyone. Richard, Kathleen, and Maree E. Regarding Grasberg, congratulations on filing that formal extension request. Could either Kathleen or Richard tell us where things stand on scheduling and what comes next, with the goal of hopefully landing a final deal? And anything you can share about possible terms under discussion?

Kathleen Lynne Quirk

executive
#12

All right. The terms had already been settled and bargained through a memorandum of understanding. So back in February we put our signature on a memorandum of understanding alongside Indonesia's government, and the president observed it. Those terms had been bargained and given the green light at that point; thus, what got filed in June is the official request matching what had been settled in February. So the mines — we handed it to the Energy and Mines Ministry, which follows a procedure for examining these extension requests. A regulation passed a while back permits life of resource extensions for integrated companies. And naturally, with our new Indonesian smelter now finished, PTFI counts as a fully integrated producer, supplying refined copper both inside Indonesia and internationally; so this fits with the regulations, and we anticipate that the MOU terms will end up being the terms under the new license. On scheduling, we're putting in serious effort to answer whatever questions the Energy and Mines Ministry raises. Every one of us shares the goal of finishing this promptly. It matters greatly, and the government understands this, that we need adequate time to plan ahead, so we secure the license extension and can start reviewing possibilities that let us keep going past 2041, delivering large scale output with major advantages flowing to the government, which holds 51%, and after 2041 our share will exceed that. Beyond that, we also hand over considerable taxes and benefits to the local community; so everything lines up around how beneficial and important this is. And so we'll move through the regulatory steps as fast as possible, though no fixed deadline exists for completing it. Still, we're pushing extremely hard to finish it this year.

Richard Adkerson

executive
#13

Carlos, back in June, when we traveled to Indonesia, to Jakarta, and afterward to the job site — that was one amazing day. Among all the occasions I've visited over there, by the time that day wrapped up, I considered it among the finest we've ever experienced. I was able to hold one-on-one discussions with the president and with numerous among his closest senior advisors. The president, whom I've been acquainted with since the 1990s, struck a very constructive and supportive tone. He completely grasped the necessity of completing this, along with the consequences should it not be completed. Plus, he places heavy emphasis on international relations, and believed that finishing this would do a great deal to build strong, positive ties involving Indonesia and the United States; so every indication looks favorable. As Kathleen mentioned, this process has to be worked through. Yet everyone recognizes this is something essential and advantageous for all the stakeholders — not merely shareholders, but also the government, the workforce, the community, and Papuans whose economy depends so greatly on PTFI's operations. So we came away from those meetings feeling quite good, and at this point we simply need to push through the process. And in Indonesia, at times that requires time. That's reasonable. Many thanks, Richard and Kathleen. Thank you, Carlos.

Timna Tanners

analyst
#14

Hey, good morning. Hi there. Would you mind sharing a little additional detail about buying that stake in Cerro Verde, and is there room to do considerably more along those lines? How do you weigh those acquisitions? How do you balance them against returning capital to shareholders going forward?

Kathleen Lynne Quirk

executive
#15

There's a fairly modest public float for Cerro Verde that trades openly. So whenever such chances come up, that's a matter we take a serious look at; naturally, the asset itself is outstanding. Freeport would have interest should opportunities emerge at sensible valuations to keep raising our position, yet there's a ceiling on what we're able to do, and not much tends to come onto the market. So we'll simply need to stay opportunistic regarding it. This means putting money into a business we already hold and run, and the economics on our stake acquisitions have proven appealing so far. It doesn't truly affect the buybacks at the FCX level. We're carrying on with that program, which rests, as Maree E. mentioned, on performance—we examine cash flows and give back 50% of available cash to shareholders via dividends as well as share repurchases; but we're quite happy to hold a bigger piece of Cerro Verde and would want to own additional portions if chances present themselves. Okay. That's useful. Thanks a lot.

Nicklaus Cash

analyst
#16

Hey everyone, thanks a lot for letting me ask. I was curious about Freeport and how the Grasberg ramp-up is going — I believe the first-quarter guidance had something around an average of 60 thousand per day for the back half of 26, and you came out of June at roughly 69 thousand tons per day. So I'm just wondering what's behind that — has the mix between wet and dry draw points gotten better, and is there room for that 60 thousand average for the second half of the year to go higher?

Kathleen Lynne Quirk

executive
#17

Thanks, Nicklaus. Mark Jerome Johnson is also on the line, and he can add to what I say. As far as the back half of this year goes, it matches the guidance we gave in April. We did finish June averaging 69 thousand tons per day out of the Grasberg Block Cave, and our guidance assumes 60 thousand to 65 thousand, plus or minus, during the second half. What's happening in that period is that we're right now wrapping up the work in 1 of the shoot galleries tied to this spilminator effort, the chute regulator we're installing, which gives us flexibility to handle particular ore types. After that we'll move to a different area in the second half to finish that maintenance or those upgrades. So in the second half, some of our output will come online as the current work wraps up, and some output will come offline while that work gets done. So from June onward we'll be roughly at a steady state while we finish these projects upgrading the material handling system, and then once we're into 2027, with that work done earlier in the year, we bring on production from Block 1 South, which adds output in 2027. On conditions, they're good at Grasberg; back in April we discussed wet and dry, and things have gone as we expected, though some draw points that were wet in April have turned dry as we've had more activity and movement in the cave from production. Also, you read plenty about wet conditions in Chile, but conditions have been dry in Indonesia; so our wet-to-dry ratio has gotten better over the quarter, and these upgrades we're making give us a more robust plan over the longer term to handle any type of material. Alright, this is an investment we're making for the long haul, though there will be some downtime tied to it. During the second half — and all of that is baked into our guidance, and it lines up with what we aimed for back in April — that work is progressing quite nicely. And since we're discussing this, Maree, perhaps you could share a bit more, building on my comments, and also talk about our efforts around risk mitigation and how we're moving toward resuming production in block 1.

A. Cory Stevens

executive
#18

Okay, Nicklaus — picking up from what Kathleen covered so thoroughly, the areas where we're installing that new technology we proved out about three months ago are the shoot galleries. There's one located in CG44, and 9 shoots are contained within that site. Over the next 3 years, it stands as one of our bigger production zones. When that job is finished — and we expect to have it done before this year is out — we'll see an increase in output associated with it. Somewhere around 25 thousand to 30 thousand tons per day come out of the CG44 area. So getting that done will represent a step change, and following that, in 2027, we have ongoing construction related to continuing to roll out these shoots — 2.73 thousand as well. On mitigation, we've made progress. A number of drill holes have been successfully put into the old pit bottom. Together with drier conditions, the pit bottom is essentially dry; we know the rain will come back at some point; as Kathleen said, El Nino is going to be the driver for our part of Indonesia. There's a new drill we've talked about before; commissioning is underway right now. It's on site. Drilling should get started within the week on that. A second drill, same model, shows up in August. Our plan with this new rig: while the current drilling approach might deliver 5 to 10 meters per day with core drilling, we expect this new machine to hit well above 100 meters per day because of its larger diameter; so it will be crucial to our ability to keep up with any water buildup at the pit bottom. So that work is coming along well. We've started a new drainage gallery that runs along the north side of the pit bottom. It's outside the cave, but it gives us additional access for drilling as well as other opportunities to remove any material accumulating at the pit bottom. And then we're advancing on a couple of others — we're looking into the possibility of putting in a surface slurry pump, with work ongoing; that one is more toward late 2027; so all of this is happening at the same time; we've made good progress on all of it. At the same time, we're busy in the PB-1 area, finishing the cleanup, restoring the shoot gallery, reinstalling the spilminator shoots in CG-21, which takes care of a large share of PB-1 South. So that's still on schedule as well; all of it is quite positive. The government holds 41%. Thanks very much.

Analyst

analyst
#19

Thank you. Good morning to Kathleen, Richard, and Maree, and congratulations on the strong second-quarter result. I wanted to ask about the guidance for the year. It seems there's been some reorganization and sequencing, perhaps at certain mines, since sales came in below prior expectations for Q3. A 750 for the third quarter; and it appears that gets made up in Q4. So maybe you could discuss the timing there. Front.

Kathleen Lynne Quirk

executive
#20

Right. Thanks, Orest. So in Q3, we expect production to run significantly above sales. The bulk of that sits in Indonesia, where we're beginning to ship concentrate from the mine site. We've been shipping to 1 smelter, and during Q3 we'll begin shipping to the new smelter, and building up that inventory enough to run the new smelter consistently will take some time; so as we worked through the actual operating plans of the smelter and the timing of refined copper sales, we've got some timing adjustments between Q3 and Q4. But we do expect to build some inventory in Q3 and make up part of that in Q4. Okay. Can I ask a follow-up. On cash costs, you did lower the full-year guidance slightly even though, obviously, gold prices have come in a bit lower, I guess, and we're saying the expectation is 4 thousand. But regarding the impacts from energy, diesel, and the Strait of Hormuz issues, any changes there versus what you discussed in Q1? As Maree E. mentioned earlier, you know, the situation remains volatile when it comes to diesel prices. We're assuming prices fairly close to what we saw in Q2; so we adjusted it modestly in terms of the forward assumption; but it's pretty similar to what we had in Q2. There are also some effects from sulfur and acid that we're rolling through. But in 2026, we don't have much asset that we bought on a spot basis. So that impact isn't significant; but we will, you know, we will be exposed to the oil markets. I know they're up today and we'll keep monitoring that. But the average is pretty similar to what Q2 was, which was elevated, you know, compared to earlier this year. Just to comment on acid, while you see the impact of sulfur and acid in our operating cost, we also benefit from Freeport's position as a fully integrated producer. So in our revenues, we're getting the benefit of selling acid as well. That gives us an offset, though it isn't always visible. So that's a benefit on our side, since we effectively hold a hedge against soft acid through our substantial smelter operations.

Liam Fitzpatrick

analyst
#21

Morning, Kathleen, and everyone else on the call. I've got 3 questions about your U. S. operations that I'm hoping will be quick. First off, Baghdad — could it possibly get government grants or incentives of some sort to help cover the CapEx budget? Number 2, regarding opportunities to grow smelting and refining, given how in-country processing assets keep gaining importance, are you exploring any options to add smelting and refining capacity past Baghdad and your leaching operations? Then for my third and last one, on the leaching side, how confident are you in hitting that 300 million-pound run rate by the close of this year? And is the right way to think about it as incremental volumes, or will lower production somewhere else in the asset base create some offsets? Thank you.

Kathleen Lynne Quirk

executive
#22

Thank you, Liam. On the incentives question for Baghdad, you begin with the reality that the fiscal regime here in The US is quite attractive. Compared with other countries. That's part of why, if you consider a mine such as Baghdad, we pay no royalties. The reason is that we hold the land and fee. And our tax position in The US is attractive. Once we work through the NOLs, the effective tax rate here in The US ends up substantially below what other countries have. So that genuinely assists with the economics by reducing the financial burden coming from royalties and taxes; as far as incentives go, one item we keep pursuing is the possibility, since Freeport is an integrated producer again, here in the US, we operate a smelter in Arizona, 1 of 2 smelters running in The US. Under certain incentives under 45 x, we would qualify for a 10% production tax credit The initial step involved getting copper designated as a mineral, and that was accomplished several months ago, and we appreciate the administration's work on that. The following step now would be having it placed into the treasury regulations, which would let copper conform to the critical minerals list. And be included in this 45 x credit, which comes to roughly $500 million a year; and so that would be a big help with our investment plans in The US, letting us keep reinvesting things like these production tax credits into our US business. So we keep working and talking, and there are some proposed bills in congress to accomplish this. We keep working on it. And that would be a really attractive way for us to, you know, make significant strategic long term investments in The US. As for the smelter question, right now, we process either through the smelter or through our leach processing all of the copper that we produce in The US. From time to time, we've done some exporting of concentrate, though the volumes have been minor; basically, whatever we turn out gets processed either via the smelter or through leaching. Should a Baghdad expansion move forward, there's a chance we'd explore possibilities, and we've already been examining chances to grow the Liam smelter, which is operating and performing very well. So we'll assess whether that's a sensible move for us. You know, there are certain benefits tied to the smelter and to logistics. Plus having that extra acid. These are synergies that flow back into our operations. So we're taking a serious look — I mean, a rigorous look — at that possibility too. Then the third question concerns the goal for growing the leach opportunity. You know, right now we're at roughly 200 plus or minus per day. By the close of this year, we'll reach a run rate of 300. Where we stand today reflects a great deal of effort we've put into tactical execution, and into adding incremental pounds via the operational processes we've been rolling out. We've been putting in extra irrigation lines. We've been applying technologies for targeted drilling to inject solutions. But the upcoming stage — and it's a truly thrilling stage — of opportunity stems from the innovation efforts we've been pursuing. I brought up the additive work along with the heat work, and those two items will let us achieve greater scale and then map out the route to genuinely a new copper mine, in the way it appears. So Corey Stevens is on the line, and his team is tackling this; it's one of the most thrilling things we're doing as a company. And, perhaps, Corey, you might offer just a bit more detail on what we're doing to gain scale in this really enjoyable and appealing Leach Innovation opportunity.

A. Cory Stevens

executive
#23

Yes, thank you, Kathleen. The base tactics—what we refer to as leaching—have become more developed as we keep advancing that leaching through installing drip lines alongside helicopters, or by improving our raffinate injection methods using feedback loops together with better censoring and analytics. We're even reshaping some piles, which lets us reach zones that previously couldn't be leached, giving us a solid base. Then comes the additive effort layered on top. Our Gen-1 additives are now being deployed. The initial outcomes exceed what we anticipated, and we're continuing to track that. Yet we aren't standing still. Gen-2 additives, which we think deliver several times the effectiveness of Gen-1, are already sourced, and we have 4 targeted demonstration piles throughout the portfolio—a couple at Morenci, 1 in New Mexico, plus another pile at El Abra. So we're quite enthusiastic about that, and the early Gen-1 results give us solid assurance on this front. Beyond that, we mentioned certain heat projects, and the pilot at Morenci is proceeding. We're in the last stages of building something closer to a demonstration commercial unit, which will begin in the second half of this year at El Abra. El Abra reacts strongly to temperature, so we're eager there; we're certain there will be lessons as we proceed, but the team is actively and dynamically working through every possible permutation of what might occur and what changes we could make; that will lay the groundwork going forward on those fronts for the next wave of heat as we enter the following phase. We also have geothermal drilling underway at Morenci that might contribute a significant quantity of extra heat as we fine-tune those recipes. There are additional tactics being pursued at the smaller sites. This creates options to weigh further so-called rehandle chances, where we can relocate older piles to handier spots for heating and/or additives, and then below cutoff grade opportunities; so, as we evaluate expansions or certain major projects like Safford, how do these fresh lessons factor in and either add incremental value or substitute for the capital you'd otherwise spend on more conventional approaches. So all of that is underway. Thanks, Corey. Okay. Bye. Thank you. Appreciate the detail.

Bill Peterson

analyst
#24

Thanks, and congratulations on the quarter. I'm not certain this is the ideal way to ask, but for Richard, I suppose: what are the expectations regarding any kind of shift in the Section 232 copper rulings? Get the President — Freeport is genuinely advocating one direction or another, since there are likely pluses and minuses. Could you discuss how this could help the US footprint, including how much in NOLs is left, and then any effects on the wider market? Thank you, Bill.

Kathleen Lynne Quirk

executive
#25

So we, along with the rest of the market, keep watching and waiting for decisions in February, as you're aware, Bill. Last year's decision was to examine it once more regarding copper cathodes. Examine it once more for the possibility of placing a tariff on cathodes, through a phased approach starting in 2027. No decision has come on that matter. You've observed the situation where a great deal of copper has flowed into the US in expectation that something could be arriving, yet there hasn't — it hasn't been decided yet. And as I said earlier, when you consider inventories beyond the US, it has produced an extremely tight, extremely tight market condition, especially in the heavy consuming regions across Asia. So everybody is tracking the situation closely. Regarding how it would affect Freeport, if a tariff exists and if a premium exists, every one of our US sales is priced on the Comex. And so, you know, we could find ourselves able to obtain a higher price for copper on our US sales than we get internationally, but we'll need to know, we'll need to see. And you can look at the breakout of our US sales, and that's an area that's expanding. Right? I mean, that's an area that's expanding when it comes to this work we're doing on mining rate improvements and also on this leach initiative; so Freeport would be a major beneficiary of it for our US business. Regarding the NOLs, we have roughly just under $6 billion of net operating losses that we can apply against our US income. You can likely see in the results that we began to pay — be subject to a minimum tax in the US this year. And it's, you know, a fairly small effective rate. It's somewhere in the 6% to 7% range, and we'll pay that — you don't take NOLs against that tax. But we do expect in the years ahead for the NOLs to begin being used as we at current markets; and yet we'll have multiple years of being able to use those NOLs. Thanks, Kathleen.

Bob Brackett

analyst
#26

Morning. It really stands out to me that the Morenci mine rate climbed 30% during Q2. Could you explain what mine rate means in this context for you? Also, what could that mean for copper sales down the road, or what takeaways from there might you use elsewhere?

Kathleen Lynne Quirk

executive
#27

Thanks, Bob. This has been something we've focused on for many years. When the pandemic hit, we dealt with significant workforce turnover. Because we had fewer people working and faced limitations, we deliberately reduced the mine rate. Since then, getting that rate back up has been a labor-intensive, ongoing effort spanning several years. A mix of things has aligned to reach about 900 thousand tons per day of material mined at the site; that's well above what we've managed over the past 5 years. It's a big achievement, but it's taken plenty of effort and attention, plus leveraging technology to boost efficiency and improve our equipment and asset health, since everything ties together with shovels. All the machinery needs to function as it should. At this stage, the availability of our current equipment is far greater than before, our maintenance efforts are delivering better results, and we're seeing less unexpected downtime, which we're targeting. Still, it's truly thrilling, and we must keep it going. That's our key point: these practices have to become standard, and we have to maintain them daily. So it's an ongoing effort. Corey, do you want to chime in about the progress and what lies ahead?

A. Cory Stevens

executive
#28

Yes, Kathleen. It's been quite exciting, and the way we describe it among ourselves is that our attention is on people, process, and technology — it's not one versus the other. No technology answer will ever be the ultimate fix. I mean, a great deal of hard effort is involved; we noted that the labor workforce is stable, but at this point the team is stepping up, and there's a lot of leadership and coordination happening; we've centralized certain activities. Around the mine work, so that we can have expertise in the right place and give insights to the field folks, enabling them to make better decisions rather than having to handle the 20, 30 things they must handle during a shift. They receive these insights while the shift is underway and can make the right calls as they proceed. Then we're layering additional technology on top of that to bring another level of sophistication, so that when one piece of equipment breaks down, alright, what's the best option for moving to a different area? One other thing probably worth noting that will add some wind to the sales is that during the second quarter, we began transitioning a number of trucks to a higher capacity 400 ton ultra class truck; that will keep going through the rest of this year. We have plans to add an additional 20-plus trucks next year in the same fashion. And so, as we've been able to demonstrate operating excellence and we get better tooling, we expect even better results as we move forward and work through the volumes we want to work through.

Bob Brackett

analyst
#29

That one's pretty clear-cut. Thanks a lot. Moving on to my next question: we're getting close to the moment when the formal permit for the Grosberg extension comes through. Once that happens, it's our cue to head back and start exploring. Could you share a bit about how you're thinking about exploration strategy in that area once all of this is finished?

Kathleen Lynne Quirk

executive
#30

Absolutely, there are specific targets we're pursuing below the Deep MLZ as an extension. That's really exciting. We've drilled there before. We'll pick that work back up. Still, it's an exciting prospect for us. Then there's another prospect tied to the fact that our resources extend beyond 2041. The resources we have right now. Consider the Coochin Liar project, for instance — that property could continue producing for many years beyond 41. So that gives us a way to really make the most of existing operations beyond 2041. This district, you know, hasn't been thoroughly explored in a very long time, and we've just been adding extensions that could fit within the 2041 window. But an extension is going to open up a completely new frontier for us. With additions to existing ore bodies, like Deep MLZ, like Fuchsin Liar, so it's a — and because that infrastructure is already there, infrastructure, it looks appealing from an economic standpoint. And with Section 232 in play, that only strengthens the case. That one's pretty clear-cut. Thanks a lot.

Richard Adkerson

executive
#31

I believe Kathleen's remarks made this pretty evident, yet since we held no rights past 2041, nothing has been reported by us as reserves past 2041. Even though we're aware the current resources are going to stretch past that point, and we actually started on some of this sooner while gaining ground with the government during our negotiations; some extension exploration work has gotten underway, and that's 1 of the things we continue telling the government regarding how important it is to finish this as fast as we can, so we can figure out what those resources actually are, since that's going to shape every one of our future plans for processing, tailings control, and everything along those lines. So there's 1 item labeled the Grasberg District ever since it was initially found back in 1988. It has consistently ended up larger than any of us involved with it expected it would be; which is exactly why we're eager to see whatever else is sitting out there, and this extension is going to provide the capability to do exactly that.

Daniel Major

analyst
#32

Hello, yes. Most of what I wanted to ask has already been covered, but there are 2 things I'd like to raise quickly. First, you mentioned some additional spending within the 2028 CapEx tied to work at Baghdad tailings and getting ready for the expansion. Does that extra amount sit on top of the 4.5 billion CapEx guidance, or does it fall to some extent inside it? That's part one; then part two, regarding the North American business. You had previously given a target of $2.50 per pound for operating costs in 2027. Does that estimate still hold?

Kathleen Lynne Quirk

executive
#33

On your first question, what our figures include for Baghdad CapEx is the work already underway, and we will keep going to finish the new tailings facility; this is work we pulled forward so we'd be positioned to carry out the expansion, yet it would have been needed regardless with the assets we already have, given how much reserves sit there. It would be needed down the road; so it's captured in our CapEx forecast. What isn't captured in the forecast yet is — and this is still pending, you know, a final decision — the CapEx for the project when it comes to constructing the concentrator and associated infrastructure? So once the project gets approved, that would be added to the existing projects, you know, added to the existing CapEx. We have considerable capacity to cover it from cash flow. We expect that, and we've been sort of planning toward it for quite a while, and our balance sheet is in great shape too. As for the target in the US, we still have a target of $2.50. Per pound. Today's market conditions, with energy prices along with sulfur and acid prices, are pulling that opportunity somewhat out of reach for us in 2027, but we keep working on it. Corey has discussed some of the efforts we're making on automation and technology improvements. To strengthen our basic mining practices, build more efficiency, the Leach initiative with scale, will go a long way toward helping us, since that costs much less than our roughly $3 average in The US; so it remains a target. it's still something we believe is achievable. Right now, it is it is it is not something, with current markets, that we can achieve in 27; but we keep working on things within our control that will let us bring the cost down; and that incremental leach is, is 1 that will be a big driver for us. Orest. Thank you.

Brian MacArthur

analyst
#34

Hello, good morning, and thanks for letting me ask. Many of them have already come up. Could we return to the Baghdad expansion and everything discussed regarding the incentive price — have your molybdenum assumptions in those economics been revised? If yes, which molybdenum price are you applying? My second question, also about molybdenum: you're a major producer of it, and interest keeps growing; primary operations appear to be generating somewhat more. Could you perhaps discuss what opportunities exist there? And the other incentive price matter — you've mentioned the NOL somewhat. In that updated incentive price for Baghdad, are we assuming a substantial amount of NOLs? To phrase it another way, if you set the NOLs aside and change nothing else, would Baghdad move forward regardless?

Kathleen Lynne Quirk

executive
#35

I'll address the second part of that first. We look at this both on a pre-tax and post-tax basis. Ultimately, what matters is the after-tax view, leaving the NOLs out. Even so, the project holds up — at an incentive price of $4, the economics work. So no, this does not hinge on the NOLs, though it certainly benefits from the tax treatment we get in The US. Mining there faces a relatively low effective tax rate compared with the other jurisdictions in which we run operations. On the moly price, we typically work with ranges. As for that $4 scenario, the assumption was a $20 moly price. The current price is significantly above that level, though we'll still be using $20 for moly. What was the second half of your question, Brian? Broadly speaking, with moly performing better, you have a primary molybdenum operation that we don't discuss much, but I'd assume it's contributing a decent amount. Could there be an opportunity to capture more value from Climax and Henderson? At Climax, we do have that capability. As you're aware, that mine has the potential to yield additional moly. We also possess a considerable amount of byproduct moly. And as you mentioned, this Baghdad mine contains substantial byproducts. Sierrita, which ranks among the lowest-grade copper operations, is also one of our cheapest; indeed, it's the lowest-cost mine in The US, aided by its considerable moly output. So through El Abra, we'll have moly plus a new project. Thus, byproduct moly, you know, flows directly to the bottom line; that's something we're focused on too. However, we do retain some optionality thanks to our large Climax operation. Orest. Thank you. And perhaps just one final question. If every one of these projects clears your investment thresholds, it seems like, you know, bad Baghdad, a call could be made perhaps within this year, then maybe 2 or 3, 4 years before it's actually being produced. So that puts output in early 2030. With El Abra, you sort of work your way through permitting. That points to 2033. For Safford/Lone Star, there's still stuff you need to secure, and you mentioned production happening in the 20 thirties. Will Safford and El Abra's schedules ultimately line up at the same point? And if that happens, would you be at ease constructing both simultaneously, or would they wind up as more of a sequential pair, purely as a matter of managing large projects from a peer standpoint? One thing we're aware of, Brian, is that inside the Freeport organization, whenever we concentrate on a project and direct resources toward it, our execution is exceptionally strong. Exceptionally favorable. You know, a lesson that's been picked up gradually is that taking on too many simultaneously, not only financially, but purely in terms of execution, turns it into a bigger challenge. Even so, we're currently getting organized regarding assigning resources to Baghdad and assigning resources to El Abra. The Safford opportunity, as Corey mentioned, has us genuinely enthusiastic since we'll be able to apply certain lessons from this leech work to it. Consequently, Safford's flowsheet could differ from the rest, possibly not be — you might end up with a smaller concentrator and rely mainly on leaks. So we're enthusiastic about, you know, what it could accomplish, though we're still deep in the middle of evaluating it. Permitting for the Safford opportunity is tighter compared with what exists in Chile; therefore, in theory, Safford could present an opportunity at roughly the same moment as El Abra. Yet our real emphasis is on pinning down the opportunity and afterward examining what's sensible, how these items should be sequenced, how we resource them, how we carry them out with maximum efficiency. Still, the effort underway now is aimed at truly locking in the value along with the option opportunity and gaining a clearer grasp of it. Orest. Many thanks for all that detail. That's quite useful. Thanks, Brian.

Christopher LaFemina

analyst
#36

Hello Kathleen, Maree, and Richard. I appreciate you fitting me in at the end here. I actually have 2 quick items. First, regarding the new smelter over in Indonesia, I understand the insurance proceeds came through during the prior quarter, but does any work remain outstanding before the repairs are finished, or is everything set to run at full capacity? That is my first question. Secondly, Kathleen, you walked through earlier how copper sales will vary from one quarter to the next across 2026, and some of that relates to stockpiling at the smelter. You have revised your guidance substantially on a quarterly basis; my question is whether your internal forecasts for copper production, as opposed to sales, on a quarterly basis have shifted since the close of last quarter. Put differently, have your production projections stayed the same, with the story being more inventory buildup at the smelter, which explains why sales are slipping? Or is something also going on with the production side? Thanks.

Kathleen Lynne Quirk

executive
#37

All right. Regarding the smelter, every bit of work that was required on the new smelter has been finished; in fact it began operating last year. We wrapped up all of that work in the first part of 2025, and operations had begun during 2025 prior to the September event. So up to now it has been running in standby mode. We have used that time to thoroughly go through and finish whatever remained from the main project, run tests, train our teams, and as a result that smelter is fully ready to go. I am eager to get started. On the production side there truly are no pluses and minuses to speak of. As for Grasper, production really has not changed at all, but our shipping plan and operating plan for the smelter differ, and it takes time to move material through the smelter and then sell the refined sales. So what you see on sales is actual refined copper sales, while our production looks very much like what we discussed in April. Perfect. Thank you.

Kathleen Lynne Quirk

executive
#38

Alright, we're grateful to all of you for joining and for your questions. Should anything else come up, don't hesitate to get in touch with David, and we're eager to share updates on how things are going down the road.

Richard Adkerson

executive
#39

Thanks, everyone, for participating Onward and Upward.

Operator

operator
#40

Everyone, that brings today's session to a close. We appreciate each of you for being here. You're welcome to hang up now.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Freeport-McMoRan Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Freeport-McMoRan Inc. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Freeport-McMoRan Inc. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.