Gem Diamonds Limited (GEMD) Earnings Call Transcript & Summary

March 17, 2022

London Stock Exchange GB Materials Metals and Mining earnings 87 min

Earnings Call Speaker Segments

Operator

operator
#1

Good afternoon, everyone, and thank you for joining us for the Gem Diamonds 2021 Annual Results Presentation. <<operator_script>> Kindly be aware that this session is being recorded. At this point, I'll hand the conference over to Mr. Clifford Elphick, our CEO. Sir, the floor is yours.

Clifford Elphick

executive
#2

Thanks, and good morning, everyone, and thank you for joining us. Janine, if we could move to Slide #3, the 2021 in review page. These are the top-line figures. We'll go through the components of this page in detail. But in brief: a solid revenue figure, healthy EBITDA. Carats recovered was encouraging, strong EPS. We faced some challenges with our safety record over the year, but we were able, encouragingly, to get on top of it. We halted operations for a day so everyone could refocus, and I'm glad to report that we finished in a reasonable position. Mike will discuss the financial position later, but it's good to have cash on the balance sheet. In the bottom left-hand corner, the business transformation. This is the final time we'll be mentioning it. But we had set a goal of $100 million in revenue increase and savings, and I'm happy to say we came in slightly ahead of that target. On dollars per carat, we'd rather be above $2,000, but even so, $1,835 average per carat. We hold the highest dollars-per-carat record among kimberlite mines. And this was a solid outcome. It allowed us to declare a dividend once more, a touch better than previously, and it's very satisfying to return capital to our shareholders.

Clifford Elphick

executive
#3

Moving on to Page 4. As you'll notice, our annual report came out at the same time as these results today. There are three main pillars — strategic priorities, with the strapline there, unearthing unique possibilities. But these are the three main pillars we operate under. Extracting maximum value from operations — we're constantly trying to optimize and maximize our operating model. And those three points there — waste dumping, new fines XRT, and adoption of the short-term mine plan within the longer-term framework — are things we always examine to try and get better results. Diamond damage — we've put a lot of time into making sure the plant feed was stable. Considerable work has gone into the data set that we've built up over the years, analyzing and assessing and looking at when we get our best results. And it's all about stability in the plant. We've been evaluating a number of different technologies with a view to smoothing out what goes to the plant and also to producing a head feed that will let us advance the work being done on trying to find a solution to identify diamonds within kimberlite. And that is — the surface miner trials fall into that bucket of R&D work that we've done.

Clifford Elphick

executive
#4

The surface miner turned in a few solid results. The specific unit we had wasn't suited to the job. Even so, we discovered that with steady feed, we could achieve an 11% gain when it came to oil pricing through the plant. That gave us the confidence to push further. We're working with another provider now. And Phase 2 of the surface miner trials is going ahead. So far, as much as we've modeled, it's producing intriguing results, and here I'm referring to the business transformation overall. Operating responsibly and keeping our social license to operate is vitally important, and it grows more important all the time. A great deal of time and effort goes into it. I noted that we needed a specific focus on our safety campaign. That entire process and its planning have matured over the years. We're proud of what we've achieved. That said, we did experience some slippage. And I'm happy to report that we succeeded in pulling it back. Every stakeholder we engage with, be it the community, be it the host government, be it the diamond industry itself, all these various constituents in our industry demand considerable effort, management, and input.

Clifford Elphick

executive
#5

And a whole team is accountable for this: myself, Glenn Turner, Brandon, and Michael Michael, the CEO in-country. So we put a lot of effort into this. And I'm glad to report that by now we have a lengthy track record of consistent behavior and consistent performance. And so at this point, things are in relatively good shape. Our CSI investment strategy is always based on the community needs. We did during COVID, during the hard lockdowns of 2020 and 2021. This had fallen behind as far as our normal rate of investment is concerned. And so it's pleasing that we were able to -- as we moved out of the back end of the hard lockdown of COVID, we were able to get this back on to the normal sort of levels of investments and manage this in our normal way. The tailings management is big issue. We have made a very big effort here. We'll talk about that in some detail. And then the UN SDGs, we've done a lot of work there and made significant progress. And again, Brandon will talk in some detail about that. Increasingly, and it's highlighted by the sanctions, which have now been placed on ALROSA's diamonds, increasingly the origins of the diamonds is becoming a factor.

Clifford Elphick

executive
#6

So there are a couple of initiatives we've got underway here. The first one involves a partnership with the GIA — that's the Gemologists Institute of America, the widely recognized and top grading authority in our industry. We have more than 500 diamonds that have received origin reports. That then travels alongside the rough through our sales process, and our customers, our clients, genuinely value this, and it's a real help to them. So we're putting a lot of effort into that. We've also taken things a step further. We're looking at and taking part in a new technology — a kind of fingerprint technology — and we're in the process of assessing it. All of this comes together with a blockchain recordkeeping process. So I believe all of you will have noticed — whether it's De Beers and <<inaudible>> — that being able to prove precisely where a diamond originated is growing more important and creates added value. Looking ahead, on climate change, we're evaluating where we stand, what we're doing, what we should be doing, and how we get there. And a great deal of work has gone into that. On the debt refinancing, solid work was completed. Michael and his team got it all into decent shape.

Clifford Elphick

executive
#7

So I'm glad to report that all of that is now finished. We're always on the lookout for ways to grow. And while there isn't any big item to announce on that front, we've lifted our target, and we're searching outside our own area — past Lesotho's boundaries — for deposits that are well-known and well understood. The grade and value of the diamond content are known. So we're evaluating a number of options. We're not under instructions to pull any triggers, but I'd just say it's something we do on an ongoing basis. In this presentation, we'll talk at some length about long-term mine planning and how we optimize our assets. A range of initiatives has allowed us to bring more ore into our operations. And that has given us the chance to think a bit differently about the long term. We'll go into that with you in some detail. If we could move to Slide #5. Let me tell you about the diamond market. Right now, the Russian invasion of Ukraine doesn't appear to be going to plan from Russia's perspective. And it's likely to be somewhat more drawn-out than the Russians perhaps originally intended. But the impact of sanctions has been that ALROSA's goods aren't welcome in the market.

Clifford Elphick

executive
#8

You might have noticed that major purchasers of goods—whether that's Signet, LV, Tiffany, or others—are all emphasizing to their supply chains that they won't purchase any of ALROSA's goods. Naturally, ALROSA will probably move its goods via China, and a portion of those goods could very well return to the market. Still, the near-term effect, in my view, would be a meaningful scarcity of goods for a brief window. As I mentioned, those goods will likely find their way into the market. And with the shortage, prices will probably face some upward pressure. We're actively selling goods right now. By the end of next week, or the week after, we'll be in a position to assess how our goods are affected. But recently, there has been robust upward pressure on prices. There's nothing else on the global economic backdrop that I wish to discuss. You can read it there. Regarding the diamond market, demand was certainly very strong all through 2021. And especially, sales at year-end—during the Thanksgiving, Christmas, and New Year stretch—were extremely strong.

Clifford Elphick

executive
#9

Also, a great deal of inventory got worked down, and replenishing those low stock levels took place sooner and continues now. On margins, we saw some expansion. And I'd say the diamond market — the key takeaway for me there is that the diamond market came out ahead. Due to COVID lockdowns, the trouble with traveling, and uncertainty, a sizable pile of capital accumulated, and a portion of it went into the diamond market. We definitely reaped the rewards from that. In the right-hand column, as you can see, we've broadened our viewing operation to Dubai. This — Dubai, you'll remember, has now opened its doors to Israeli diamond buyers. They can get there without much trouble. And a lot of Indian clients would rather go to Dubai than to Antwerp. So through displaying the goods in Dubai, we're seeing a notably larger crowd attending our viewings. After that we bring them back to Antwerp and finish the sale there, with online bidding. But with the goods sitting in Dubai, a sizable number of additional clients — people who otherwise would never lay eyes on the goods — do get to see them. And that extra competition has definitely helped us up to now.

Clifford Elphick

executive
#10

We certainly examine a few of the downstream value alternatives open to us. This is more of a present theme in the water than a deliberate strategy. We're exploring possibilities. And in fact, several of the major brands have been talking with us about supply agreements. But just as a reminder, our obligation is to obtain the best price we can by selling goods on international markets through tenders. That's among the conditions of our mine operating agreement. So we need to work with the government to secure their approval for any longer-term or medium-term supply agreements. And they are sympathetic to this. But as of now, we haven't signed any agreements. Price recovery continuing into 2022. That certainly was true in January and February. It's unclear what effect the war in the Ukraine will have over the medium and longer term. Hopefully, there's no major problem for us. But we shall see in the fullness of time. I'm going to hand over to Brandon to deal with the next few slides.

Brandon de Bruin

executive
#11

Thanks, Clifford, and good morning, everyone. Climate change has been a key area of focus for the group. And in 2021, we adopted the TCFD recommendations and set out a 3-year road map toward full adoption. The end goal is to establish and carry out a suitable decarbonization strategy. And in the table that follows, you can see the 3-year plan that culminates in Phase 3 in 2023. We've taken a science-based approach to defining and setting our decarbonization goals. And in 2021, we finished a climate change scenario analysis. That analysis pinpointed climate-related risks and opportunities for the group. The table below, as I mentioned, lays out our road map. Phase 1 in 2021 — we completed it and hit all our targets there. We're now advancing to Phase 2, which ultimately means defining our decarbonization targets, and then on to Phase 3. And I'm also pleased that bringing in Rosalind Kainyah has strengthened our Board's ESG expertise. And if you turn to the next slide, our climate strategy considerations. Climate change affects our strategy, operations and financial planning, and it ties directly to our three strategic priorities — which Clifford has walked through — namely: getting maximum value from operations; operating responsibly and preserving our social license to operate; and getting ready for our future.

Brandon de Bruin

executive
#12

Several resource efficiency programs we put in place during 2021 have led to lower fossil fuel use as well as cuts in carbon emissions and costs tied to mining. We'll get into this a little more shortly, with a prime illustration being the shortening of waste haulage distances, which brought down operating costs in line with our goal of maximizing value while simultaneously cutting our carbon emissions. The climate change work we are carrying out would guarantee that we can pinpoint risks related to climate change and manage and mitigate them effectively and efficiently. If we turn to the following page, moving on to safety for the year. As Clifford noted, during the first half of the year we did see a number of rises in incidents and safety incidents. And we are not alone in the industry on this. We observed that throughout the mining industry and it seemed to reflect the lag effect of COVID and the impact that has on the workforce. This led to our all injury frequency rate rising slightly from 2020 to 0.93% and pretty much in line with 2019. And although I'm pleased to report that once again we had 0 fatalities, it is unfortunate that we experienced 6 LTIs during the year, which again pushed our lost time injury frequency rate up to 0.24.

Brandon de Bruin

executive
#13

After the rise in incident frequency we saw during H1, as Clifford noted, we halted operations as a Stop for Safety — following that Stop for Safety campaign and the many initiatives we rolled out after consultations and meetings with the workforce. And through putting a number of those initiatives in place, we managed to bring the safety culture at Letšeng up to a level where H2 showed a clear improvement, and that has carried into this year. I'm also glad to say that we experienced no major significant environmental incidents and no major or significant social incidents. Moving to the COVID slide, thank you. On COVID-19, I'd call this a major success for the group, and especially at Letšeng. We managed to navigate our way through three waves of COVID over the year: in January, in June, July, August and then once more in November. And by applying our protocols the way we had the year before during the lockdowns and tweaking them appropriately, we kept operations going without interruption in 2021, safely and responsibly. The big win was the vaccination campaigns we conducted on site, and particularly at Letšeng, educating our workforce about the vaccines and the benefit of receiving them.

Brandon de Bruin

executive
#14

And I'm really happy and proud to report that the team performed extremely well in that area. At Letšeng, we're now at 99% fully vaccinated. As part of our ongoing support for communities and our workforce, we donated 20,000 vaccines over the year, along with a new 4x4 ambulance, 17 oxygen concentrators, and various PPE and food supplies for our communities. Our wide-scale screening and testing carried on. In 2021 alone, we ran close to 31,000 tests, screening employees and visitors at the site and in transport on the way there. The cost impact per employee now comes to LSL 17,000 per employee. And that's for the safety — COVID-19 safety measures. If we turn to the next slide — actually, let me just pause there. This is our dairy project and the milk produced from it, which is one of our CSI projects. We're proud to say it's running very well, and we visited it a couple of weeks ago. Moving on to our CSR overview for 2021: an important work stream this year was updating our community needs analyses, which has informed our next 5-year CSR strategy. We've also been working quite hard to make sure we integrate the 6 UN SDGs we've adopted.

Brandon de Bruin

executive
#15

As Clifford noted, during 2021 we managed to catch up—not just finishing and rolling out our 2021 CSR projects, but also making up ground on 2020 projects that had been held back mainly because of COVID restrictions and, in addition, localized flooding, which stopped us from reaching our communities since roads had been washed away. In that respect, we also managed to rebuild infrastructure that those localized floods had destroyed. That covered footbridges and roads. Throughout the year we carried on with our best practice work, including the successful trials of our bioremediation plant. And <<inaudible>> from those trials, which <<inaudible>> was extremely successful. And we intend to build a full plant by the end of this year. Keeping our dams safe is a priority. And as Clifford noted, we have aligned ourselves with the Global Industry Standard on Tailings Management for our tailings and storage facilities. And I'm glad to report that every report and <<inaudible>> we have received from internal and external consultants has declared our dams safe, well managed, and monitored. We take pride in having retained our ISO 14001 and our ISO 45001 for the seventh consecutive year, as well as our FTSE4Good status for the third consecutive year.

Brandon de Bruin

executive
#16

On the right, that picture shows our egg production project—finished early this year—along with a few farmers from that region. Now to business transformation. Clifford has discussed this, and I'd just like to add something important regarding this target: we've been extremely successful at hitting the target we set, our 4-year target scheduled to conclude on 31st December 2021. We surpassed the $100 million, delivering more than USD 110 million in benefits to the group across that period. Our BT initiatives are embedded. That's precisely why we carried it out across a 4-year period. And we'll keep delivering value as we monitor these consistently, ensuring their sustainability and also implementing some new CI initiatives. You'll see that in 2021, our actual benefit from the BT target came to $31 million. Turning to our operations review. Overall, 2021 was a good year, though certainly not without its challenges. As I mentioned, operations dealt with three waves of COVID-19 during the year, along with extreme weather conditions, including an excessive amount of rain—the most we've seen since I can remember, at Letšeng in particular. Nevertheless, as mentioned before, we managed to keep operating in an uninterrupted, safe and responsible manner.

Brandon de Bruin

executive
#17

Let's move on to waste mining fairly quickly. The waste mine tracked with the mine plan, and it was adjusted for the lower ore volume processed across the year, at 19 million tonnes, though on a like-for-like basis that's below 2019. On waste mining we feel comfortable, and no bottlenecks are causing us concern. The steeper slope approach has worked well at the Satellite pipe, which Clifford referenced, and I'll come back to that later when we discuss our long-term mine plan — the Satellite pipe has seen real success there. We're now also aiming to roll out that same steeper slope strategy at our Main pipe as we go forward. That's work we'll be examining this year. Ore tonnes treated in 2021 came to 6.2 million tonnes, which is above 2020 — though 2020 was an anomaly, with up to 6 weeks of shutdown during the hard lockdowns at the start of COVID. But comparing like-for-like with 2019, we were lower than 6.7 million tonnes. The ore tonnes treated took a hit mainly from the COVID-related difficulties you saw in supply chain management, skills availability, and lost shifts. That affected not just our tonnes treated but our mining production too.

Brandon de Bruin

executive
#18

On top of that, we needed to lower the fee paid to our PCA so that our aging PCA can keep operating for the long term, given that we're starting construction of a new PCA this year as part of the project. We also cut the feed rate, and that had an effect on feed going to the plant too. Then, near the end of Q3, a major jaw crusher broke down, and dealing with it and getting it running again cost roughly 14 days of downtime. On carats, at 115,000, that matches the grade we expected from the ore we treated. Let's go to the next slide, please. Turning to 2021, our key priorities and important projects — as Clifford said earlier, we've put substantial effort into examining the stability of our rate, the feed rates, and the production moving through the plant. We've brought in an advanced process control system. Results in Plant 1 have been very positive, and we'll be ready to move on to Plant 2. Clifford brought up the surface miner trials, which wrapped up in Q3 last year, and we're looking at running more trials in 2022 with equipment that's better matched. From that, we expect to see some very positive results as well.

Brandon de Bruin

executive
#19

Those efforts to contain and cut costs are ongoing. We keep this under constant review. One meaningful example that added value was the step we took to shorten the distances we haul waste. That initiative is delivering roughly $2 million each year going forward by cutting haulage across our businesses, which brought down both waste haulage expenses and diesel use. We've also examined efficiency measures around electricity and water — managing peak demand, recycling water, capturing runoff, and lowering — sorry, reducing the water our plant consumes through recycling. At this point, more of the water we use is recycled than fresh. That was a strong initiative, and it was rolled out over the past few years. On the resource ore drilling program, we were able to push it forward despite tough conditions. Out of the 24 drill holes we targeted, just 4 are still wet for space in the Main pipe, and those will be finished in Q2. Our large diamond recoveries, while largely in line with our 13-year average, are lower than we'd like — we certainly would have wanted more plus-100 caraters, particularly after our record-breaking year last year in 2020, when we sold 16 plus-100 caraters, something we hadn't seen before, along with 29 60-100 caraters.

Brandon de Bruin

executive
#20

We did experience a solid uptick in our 10-60 caraters. That said, clearly we would want to see a greater share of the biggest diamonds moving forward. Final item is a brief update on the revised long-term mine plan. As Clifford noted, the strong work we have observed and the highly encouraging outcomes from optimizing our mine plan — across short, medium and long term — along with putting steeper slopes into practice at the Satellite pipe, have produced a substantial boost in ore availability at our Satellite current cutback, roughly 6 million tonnes relative to our 2019 plan. That has stretched the life of the current cutback, Cut 5 West at the Satellite pipe, out to 2025, while under our 2019 plan it finished in 2023. This in turn lets us push back the start of the following cutback at Satellite pipe to 2024. The upshot is a meaningful cut in waste across the coming 2 years, bringing our waste in 2022 and '23 down to 11.5 million tonnes per annum, with plans to ramp up in 2024 to 24 million tonnes per annum as Cut 6 West comes in. Ore mining stays flat at 6.8 million tonnes starting in 2024.

Brandon de Bruin

executive
#21

As you'll see for 2023 — and there's a slide on the following page — ore treatment declines in 2023. The reason is that our existing third plant is being demobilized this year, and we intend to build a replacement third plant for commissioning in 2024, which will lift our ore production by an additional 1 million tonnes per annum once again. Meanwhile, over the course of the year, we also finished a conceptual preliminary underground study aimed at quick access to the Satellite pipe. The initial results indicated a positive trend — enough for us to take a look and weigh a tradeoff between proceeding with Cut 6 West, the next cutback at the Satellite pipe, or instead moving underground. That will be assessed over the course of this year, following a feasibility study. We'll update the market once that information becomes available. Next slide. This simply depicts what I've been talking about — our waste profile and ore profile for life of mine, assuming Satellite Cut 6 West starts in 2024. And as I said, this will be examined over the next 12 to 18 months while we evaluate the underground option against the Cut 6 West cutback.

Brandon de Bruin

executive
#22

Thanks, Clifford. I’ll turn it back over to you for sales and marketing.

Clifford Elphick

executive
#23

Thank you, Brandon. On this slide, you'll find additional specifics regarding sales in 2021. Looking at the bar chart at the bottom, our average dollar per carat is slightly below last year's level. My sense is that the main reason is we recovered just 6 stones of more than 100 carats, versus our long-term norm of 7 or 8. Yet that compares with the prior year, when we had roughly 15 to 17. So where plus-100 caraters are concerned, it wasn't a strong year. In the 10-to-60 carat range, though, we genuinely had a strong year. I've mentioned the Dubai viewings as well as the market's ongoing recovery. On the following page, there are some photos of lovely diamonds we recovered. In the bottom right-hand corner, a small pink diamond. It fetched roughly $120,000 per carat, which is truly meaningful. We have seen extremely high prices for blues and for other pinks. So demand for these rare colors is clearly there. To give a sense of scale, look at the bottom left-hand corner: a 65-carat white diamond, a stone of genuinely top quality. As you can see, there isn't too much breakage, and a good yield comes out of it.

Clifford Elphick

executive
#24

That diamond went for roughly $47,000 per carat. For context, at the market's lowest point, we were selling goods of this kind at around $38,000 to $30,000 a carat. And the top price we've ever gotten for diamonds like these was $62,000 to $63,000 per carat. So there's still ground to cover before we reach the very highest profits. Thank you. Mike, we'll now move on to the main portion of this presentation.

Michael Michael

executive
#25

Thanks, Clifford, and good morning to everybody. I'll walk you through a few important items on the income statement. As you can see, revenue for 2021 came in at $201.9 million. That figure reflects the $1,835 per carat that Clifford referred to, applied to the roughly 109,000 carats we sold over the course of the year. Compare that with $1,908 per carat in the prior year — a bit higher on price, but with far fewer carats, down 10% at around 99,000 carats. On royalty and selling costs, we pay the regulatory 10% rate in Lesotho, and that accounts for most of the royalty and selling costs. There are also some selling costs tied to our offices in Belgium <<inaudible>> and, of course, in Dubai too. Cost of sales of $113 million reflects normal operations. Measured in local currency, however, we landed within our cost expectations. That said, the rand strengthened during the year, which affected our U.S.-reported costs. That is the reason, in dollar terms, it ended up above what we had thought and anticipated. On COVID-19 costs, Brandon discussed the work on COVID and how we maintained our protocols and processes and ensured everyone's safety throughout the year. In 2021, those costs totaled $700,000, and similarly, in the prior year, that cost was $1 million.

Michael Michael

executive
#26

But we did incur an extra $2.9 million of cost in 2020, mostly because of the shutdown and that closed period while we were locked down. Corporate expenses came in at $8.9 million, which is still under our goal of keeping costs below $10 million. Of that figure, $8.2 million is baseline costs, and $700,000 relates to certain projects we took on during the year — projects that in the prior year, during COVID, we neither started nor did any of. Those costs were also affected by the rand being stronger against the dollar, which is what produced the $8.9 million. On a pleasing note, we finished with $57 million in EBITDA. That carries through to profit before tax of $46 million once depreciation is deducted, along with our finance costs for the year and then certain noncash items, being FX losses and gains that we identify as noncash items. Income tax of $15.6 million reflects the taxes in Lesotho. The Lesotho rate is 25% on operating activities there. Our effective rate stands at 33%, higher because we don't raise any tax assets on our corporate costs in the U.K. and South Africa. Attributable profit was $18.5 million before costs for Ghaghoo. $3.7 million was incurred during the year.

Michael Michael

executive
#27

Just over $2 million of that was the actual cash cost — $2 million and a bit — and that's lower than the prior year's $3.3 million. We put in a fair amount of effort to bring down our care and maintenance spend, even though we had a process underway to dispose of the assets. Slightly more than $1.4 million of that figure is a noncash write-down on some older inventory held in the operation, which we decided to impair. Attributable profit came in at $14.8 million, and earnings per share before the discontinued operation worked out to USD 0.132 per share. That's based on 140.3 million shares in issue. Clifford referred to a dividend of $0.027, and I'll go into that in more detail a few slides from now. Turning to the cost analysis, as you'll see — and picking up from Brandon's slides — we lifted production by 15%, reaching 6.2 million tonnes this year. On overall aggregate local currency costs, we incurred ZAR 1.2 billion, which was also 15% higher than last year. So that flowed straight from the volume increase. As a result, we ended up with a unit cost per tonne treated that was very similar.

Michael Michael

executive
#28

For the third plant operator, costs came in at LSL 15.53 per tonne. That figure rests on the revenue we bring in from production at that third plant operator. So it stayed pretty much in line with our revenue profile for the period. Direct cash costs likewise landed at nearly the same level, LSL 201 per tonne, before noncash accounting charges. You'll notice the decline from LSL 118 last year down to LSL 70 per tonne this year. Waste amortization largely drives those costs — we account for it according to the ore mix we treat during the year, plus inventory movements, diamond inventory, and movements in our stockpile. We ended up building some stockpile at year-end, given higher production requirements and volumes over the period. That brought our cost down, along with strong production in the final quarter of the year, mainly in the last month, which left us with extra carats on hand at year-end. As a result, a reduced cost came through. So total operating costs stand at LSL 271 against LSL 320, 15% lower than last year.

Michael Michael

executive
#29

The exchange rate, as I said, came in stronger. For the year, our average was LSL 14.79 compared with LSL 16.47. That gave us an all-in cost, total operating costs for the year, of $18.38 in U.S. dollar terms. On waste tonnes mined, you'll notice that rose 20% as well, by volume, reaching 18.7 million tonnes. That total cost came to LSL 815 million in local currency, or rands at a 1:1 equivalent, which was likewise up 20%, matching the volume. And once more, you can see that on a unit basis it was fairly in line with the prior year. Again, in dollar terms that was affected by a different exchange rate, and we ended at $3 a tonne per waste mined. Let me then turn to the financial position. There are a couple of points to highlight here too. Despite the movement in the rates used during the year, our closing exchange rates at year-end — December '21 — stood at LSL 15.96. That compares with LSL 14.69. So this also affected the closing balances at the end of the year and would have brought some of those balances down, really owing to a difference in the exchange rate.

Michael Michael

executive
#30

A few things worth pointing out, though. On current assets, you'll notice deferred item climbed to $35.3 million from $32.4 million. That ties back to what I mentioned earlier about inventory rising — both stockpile and diamond inventory — which drove that figure up. For income tax receivable, there's a refund of $1.2 million sitting there. I'll get into tax on the next slide when I cover cash movements. That refund follows a payable of $11.9 million on the very bottom line last year, which got settled during the year. So tax movement, or tax cash flow, swung significantly over the period. Right below that, in the liability section, the first line is interest-bearing loans and borrowings: $11 million versus $16 million. We repaid part of the workshop facility, and of that $11 million, $2 million is still outstanding on the workshop facility, which is a term loan. It gets settled by September of this year. The remaining facility liability there is the $9 million revolving credit facility at the corporate office, drawn down at year-end.

Michael Michael

executive
#31

Turning to noncurrent liabilities, those came in at $13.3 million compared with $14.4 million. That line represents our environmental provisions. The change in that balance was mostly a result of the various exchange rates, which you can see as well. Moving on to cash management, we've got two graphs on this slide. The graph in the top right-hand corner simply shows how our corporate cost has moved across the period. It was a little above last year, though that included some budget costs. We remain happy with the overall value and with the downward trend over the longer term. On the cash side, we finished the year holding $31 million of cash. Once you factor in those liabilities, or the drawdowns I referred to, our net cash position stood at $21 million. Clifford noted earlier in the presentation that we completed our debt refinancing. That was a significant project for us. We consolidated all of our facilities under one process. We added a new lender. RMB has now come in alongside Standard Bank and Nedbank in our lending group. We kept a $30 million facility at the level of our corporate office. And we succeeded in raising our facilities at Letšeng from LSL 600 million, which includes a general banking facility of LSL 100 million, to LSL 850 million.

Michael Michael

executive
#32

So it was pretty satisfying to get that done. That gives us $83 million in total facilities, and $32.3 million of that is sustainability-linked loans, meaning that depending on specific KPIs and targets, we'll receive a lower rate on the targets we've set concerning carbon footprint and certain water quality KPIs. Available facilities stood at $74 million at the end of the period, after accounting for the drawdown. I'd like to walk everyone through a few points on the waterfall. There, you'll see Letšeng generated predominantly $115 million in cash flow. That's before waste investment, shown in the next column, of $65 million. The following column, $24 million, refers to tax, and as mentioned on the earlier slide, $12 million of that was tied to a 2020 tax obligation that was settled in March this year. The remaining $12 million was taxes paid for this year, which left us with a small refund and meant all our tax obligations for 2021 were settled. Corporate costs, which we discussed, the $8.9 million includes some depreciation costs. That related to the corporate office.

Michael Michael

executive
#33

When it comes to dividends to NCIs — that means our noncontrolling interests — the government of Lesotho holds 33% at Letšeng. That money went out when we pulled roughly LSL 400 million in dividends from Letšeng. We also put more into working capital. As I noted, our inventory rose, both stockpile and diamond inventory. Because of that, $6 million went into it. Investment in PPE came to $4 million, which is fairly low. On capital spending, there wasn't much capital involved there. A portion of that — in fact the majority — was the X-ray sorting Brandon mentioned earlier. Dividends paid to shareholders happened in June last year. After AGM approval, the dividend we paid was $0.025 at that time. Then the Ghaghoo cost, as mentioned, came to $2 million in cash flow terms, and we finished the year at $31 million. One important thing — I'd like to pause briefly on the dividend slide. At yesterday's Board meeting we proposed a dividend of $0.027. That's an increase from $0.025 the prior year. But importantly, this marks a second consecutive year in which we've been able to pay a dividend. The total dividend will be circa $3.8 million, based on the 140 million shares in issue.

Michael Michael

executive
#34

That works out to a yield of just under 4%, based on the current share price right now. Under our timetable, the last date for registration is the 19th of May, the record date falls on the 20th, and this is subject to approval at the AGM. The same applies to the final dividend — we do need AGM approval for it. Our AGM has already been scheduled for the 8th of June. After that, we need a record in order to process the payment, so payment is set for the 21st of June. When it comes to the dividend policy and keeping our capital repayment plan in place, the annual cash dividend review rests on cash resources, on free cash and the earnings generated, and importantly, on the capital projects needed booked to guidance. On the next slide, you'll see that some additional capital is coming through this year. So we've factored that in when determining the dividend to be paid this year. As for special dividends, we'll consider them if there are any significant diamond recoveries. Unfortunately, there weren't any significant ones last year. We did have 6 plus-100 carats. But those weren't what we classify as significant. And so they didn't warrant any consideration for a dividend. Importantly, though, a share buyback program is being considered.

Michael Michael

executive
#35

We hold authorization through the next AGM to start that program. And we'll examine it more closely in due course as part of consideration within our capital repayment policy. Then the final slide — I won't go into too much detail. It covers our 2020 guidance. That guidance rests on the mine plan Brandon has discussed and laid out regarding how we move forward. One important thing, though, the final point on capital: you'll see $25 million to $30 million is forecast for next year — or for this year, I should say. That figure is higher than our initial expectation. A couple of new projects have come into it. The new PCA Brandon also mentioned accounts for part of that capital. We're working on finalizing term loan finance for it. That will ease any cash flow requirements connected with it. In addition, the underground studies currently under consideration have been incorporated into these costs as well. And so it comes in slightly higher than what we considered previously. Clifford, may I hand things back to you for 2022 focus areas?

Clifford Elphick

executive
#36

Yes. Thanks, Mike. So what are we concentrating on this year? One thing getting a lot of attention is our mine plan and our pit slope angles. Obviously, that shapes where we're headed over the medium term. So we need to complete our core drill program once we have room at the bottom of the pit. That's going to happen fairly soon. Following the business transformation, we shifted to a continuous improvement program. It's brought some wins, but not the level of success we're after. So we're stepping up how much focus and attention we put on it. And I think we're shifting more toward a mentoring and coaching approach for our management and supervisory staff. I believe that will bring about a really significant cultural change going forward. Our primary crusher has run for a very long time. And it's something we're worried is approaching the end of its life. So we have a project in place to replace it. Alluvial Ventures, who operate our contracting plant, are about to be overtaken by the growing size of the pit. And we've had a very good relationship with them over the years.

Clifford Elphick

executive
#37

However, the facility they run is a low-technology one. That provides an opportunity for us to bring the most up-to-date thinking to bear when it comes to the change-out. We are also designing — and are quite far along with — a smaller facility, though a high-technology one. Under the second column, the bioremediation plant is, I believe, the item worth emphasizing. We have conducted some pilot plant trials, and those went well. Our results at extracting nitrates have genuinely been good. As a result, we are now working toward incorporating this permanently into our operations. Turning to the right, to the future, I have discussed downstream value. And we continue to press ahead on the technology front, be it another surface miner, or recovery techniques and extraction techniques. We have several smaller projects underway. And while these are all interesting and headed in the right direction, I have to say that, from a CEO's perspective, it is quite frustrating how much time is needed to deliver the kind of step change advances one would hope for. The underground feasibility study, along with the tradeoffs we have referenced, is important and interesting work, and it will see a great deal of progress over the course of the year.

Clifford Elphick

executive
#38

The decarbonization strategy, climate change, and the direction mining companies must take and the areas they must push into are clearly a major subject and a costly one for us. We do not think that small, poor nations such as Lesotho receive proper support for this essential transformation, which must occur. Therefore, we are advancing this conversation with the British government especially, urging it to come to Lesotho's aid. And hopefully we can identify a path through which the entire country will be assisted, and in particular our business will not be forced to bear entirely by itself the costs that are approaching. So that is that. I am very glad to take whatever questions you may have. So I will hand things back to the operator and await any questions you would like to pose to us.

Operator

operator
#39

<<operator_script>> The first question comes from Richard Hatch at Berenberg.

Richard Hatch

analyst
#40

Thanks for the presentation, and congratulations on a solid set of numbers. I have a couple of questions. Could you perhaps walk us through your thinking on the longer-term throughput outlook for Letšeng as AV rolls over from June, and then you mentioned the potential to put in a new plant? What is the thought process regarding what your throughput could be at Letšeng? And how much do you think it would cost to construct that plant? That's the first one.

Brandon de Bruin

executive
#41

Yes. Richard, this is Brandon. Regarding our AV plant — as you know well, AV has been with us for many years, in terms of <<inaudible>> and other technology. The new cutback on the Main pipe at Cut 4 West, which comes after the AV plant, is still in place. So that plant would either need to be relocated or, as we mentioned, decommissioned. That has opened up the chance to consider new options. We have several tenders and providers involved, and AV is one of them. We're currently working through that process for building a new plant. On that, you'll remember AV produces roughly 900,000 tonnes annually, 0.25 million. We intend to add a new third plant producing approximately the same, at just over 1 million tonnes a year. We're still examining the costing. As for timing, we'd like it commissioned by the start of 2024, so within 18 to 24 months.

Richard Hatch

analyst
#42

All right, so between now and then, does that mean throughput is going to drop as AV rolls? Or do you keep going with AV? Or must it halt since the pit expands into the area where it's currently working?

Brandon de Bruin

executive
#43

Correct, that's the second one. It must cease by the close of June, which allows us to begin the reduction at Cut 4 West soon after. Following that, demobilization takes roughly 2 months. So you're exactly right. And in the plan I submitted, you'll notice somewhat lower tonnes this year, since AV plant is only available through June. Then next year too, with no output from the third plant, so in the plan you'll see '22 and '23 carrying somewhat fewer tonnes. After that we build up to approximately 6.8 million tonnes starting in 2024.

Richard Hatch

analyst
#44

Alright, got it. That's fine. And apologies if I overlooked this, but is that plant fairly capital-intensive to build or not? Could you give something like a rough order of magnitude on approximately what you think it might cost?

Brandon de Bruin

executive
#45

No, it isn't especially intensive. We're also seeking to fund it through various means as well. So it doesn't demand a huge amount of capital. That said, from a funding standpoint, we're considering many alternatives — whether we provide the financing ourselves, whether we construct it ourselves, or whether a third party puts up the money across the years of their on-site production contracts.

Richard Hatch

analyst
#46

Alright, and then regarding the medium-term capital profile, Mike — could you give us some sense of what CapEx will look like over the medium term? Obviously this year the PCA has come in, and that's a fairly substantial capital outlay. And I guess that carries you through to end of life, I suppose. What does CapEx look like for '23 and '24? I guess you have your views on this additional plant that could be added. But is there anything else in there that's lumpy that we should be thinking about? Or should sustaining CapEx still hover around that $10 million mark?

Michael Michael

executive
#47

Richard, so the PCA likely will see some capital flowing in during 2023, so a portion of that will be there. You mentioned that capital will be coming in for the third plant. And obviously, how we finance that is going to have an impact. Probably, in the short to medium term, we would be taking those two significant capital items at roughly the $10 million mark. Over the last 2 years, we've significantly dropped all capital. So there have been delays, although not to the detriment of the operation. I mean, we may need to make sure that we haven't had capital savings that would impact us in other areas. But I would say that probably $10 million to $12 million in the next couple of years would be sufficient.

Richard Hatch

analyst
#48

My apologies — are you asking about the sustaining figure, or is that the total?

Michael Michael

executive
#49

That covers everything.

Richard Hatch

analyst
#50

All right. Okay. And apologies if I overlooked this, but regarding the underground — what are your thoughts there? I mean, when will we hear more about it? Are you thinking along the lines of access, discussion of mining methods and volumes and the like? Where do things stand on that, just in terms of where your thinking is right now?

Brandon de Bruin

executive
#51

Yes, Richard, that is precisely the thing we're focused on at present. As for the conceptual study, it was carried out and finished during the previous year. We are now progressing toward the feasibility stage. Regarding our method, we are essentially there, and we would like to investigate further as part of the feasibility study. And over roughly the coming 12 to 18 months, we'll be looking at updating the market on those volumes. All of that will emerge from the feasibility study and be based on the method we use, both the initial method and as we proceed <<inaudible>>.

Richard Hatch

analyst
#52

Understood. My final question concerns the market—it feels as though it is rising quite aggressively. A few of your rivals have indicated that prices have climbed somewhere in the region of 30%-plus so far this year. At the upper end, when you examine those bids and watch them come in for your lots, how close are things at the top, roughly, between the first bid and the second? Is it fairly tight? Or are you observing in certain cases a really substantial gap separating the first from the second? Or is this just an attempt to gauge how eager the midstream is to secure goods when they genuinely want them? And how much further do you believe prices can grind upward, to your earlier point, the top <<inaudible>>

Clifford Elphick

executive
#53

What I mean is, there's a tremendous amount of rivalry when it comes to purchasing these goods, since supply is limited. Now and then — actually, in the majority of instances — the bids, meaning the first, second, third, fourth and fifth ones, tend to sit within a very tight bracket of each other. Every so often, though, someone will offer an unusually high price, and you can tell that this buyer genuinely requires that particular diamond and is prepared to pay for it. Usually this happens when they already have a buyer lined up and, say — just to give an example — they've got one earring and they need a second one to match. Or with a necklace they're making for a customer, they're lacking what you might call the central, the principal stone. In those cases you can see that the customers are paying up. They want certainty that they'll secure the goods, and they're pretty much paying above market. But we have — for any individual item, we can receive 60 bids. So the situation is extremely, extremely competitive. And while — I mean, I noticed that one of our — one of the other mining companies recorded something like a 40% rise in its average dollar per carat during the last sales, which took place not long ago.

Clifford Elphick

executive
#54

We haven’t observed 40% on a tender-on-tender comparison, but on a like-for-like basis we’ve definitely seen something in the region of 20%, 25%. Then, just to give you a sense of it again, our best-quality white goods — that’s our bread and butter — are currently in the range of roughly $47,000 to $50,000 per carat. In 2011, the top price we received for those was $62,000 a carat. So I think there’s still some distance to go. And hopefully it continues, and the problems in Ukraine don’t create difficulties for our business. If we can answer some of those questions from David Penman, yes — prices, the ’22 tenders: we’ve had 1 tender so far that went well, very well. As I said, we were up somewhere around 20%, 30%. Our second tender is busily taking place right now. We’ll close it in a couple of weeks’ time. There’s a great deal of interest. In terms of the viewing, we’re completely overbooked. So I think we should see strong prices there. How is the Ghaghoo price set progressing? And Brandon, would you like to answer that?

Brandon de Bruin

executive
#55

Yeah, just a quick update following what we announced before — last year we got a lot done with Botswana Diamonds on the government approvals side, and we did receive those for the site we purchased. Sadly, Vast, the funding partner, wasn't able to close the deal. With Botswana Diamonds, we're well along with a new financing partner. And we're hoping that at the next <<inaudible>> we'll have a clear path forward on it.

Clifford Elphick

executive
#56

Then David, regarding your question about clearance for underground mining—yes, we're actually quite far along on that front. A conceptual study has been completed, and we're currently transitioning into the next stage, which leads us toward the feasibility study. Prior to reaching that point, Board approval is required for us to commit the capital, since these studies naturally involve costs. We're also carrying out some tradeoff studies comparing underground against the next cut. So that's the path we're on. Michael Wolf, why would you say the share price has declined while rising within the diamond market? Yeah, look, I believe the diamond industry is genuinely unloved. I don't think Petra Diamonds is delivering higher share price growth. I mean, you need to consider our Board—we've consistently examined how we stack up against our peer mining companies. And I think across the past 2 years, we've likely performed somewhat better than them, factoring in opportunities and investment at Lesotho as well. Share buyback—yes, a share buyback has been considered. I believe Michael mentioned that. And clearly, it represents the best use of cash. The company is underpriced. So I think you can expect to see something on that front quite soon.

Clifford Elphick

executive
#57

And what about D&A for the year? Mike, would you like to take Kim's question?

Michael Michael

executive
#58

Yeah, Kim, on depreciation — it should stay at roughly the same level we currently have on the income statement. I believe that figure was $8.5 million. Then as for the mining mix affecting amortization and the waste amort write-off, this year it came in at around $45 million, $46-odd million. That reflects a mining mix with about 3-plus million tonnes of Satellite material running through. You should expect a very, very similar cost to come through in the new year.

Clifford Elphick

executive
#59

So, the sales process — I believe we've already discussed that. And AV, we've covered it. If business transformation weren't there, what would the financial results look like? Will Hillen, I think we probably need to model that out, right?

Michael Michael

executive
#60

Right, I think a lot of different pieces go into that. Keep in mind the business transformation delivered cost savings. So that $100 million isn't purely cost savings — additional revenue would have been part of it. Other efficiencies would have been in there too, to put it very simply. I suppose the assumption would be that, in theory, we'd have $100 million less cash on the balance sheet over 4 years.

Clifford Elphick

executive
#61

Will Hillen, you ask why we'd bother looking beyond Lesotho. Well, the reason is that if you happened to find something like a Jwaneng, that would plainly benefit everyone. So I think that settles it. Our large diamond recoveries matched the average. No two diamonds are alike, Will Hillen, and say you recover a 910-carat stone — that's $40 million. $40 million makes a huge difference from — so let's call it a very — this isn't the kind of diamond mine comparable to a Liqhobong, where the run of mine — whatever you recover doesn't matter, it's essentially a widget factory. Letšeng isn't that. Its ore body is far more unusual. And sometimes — I mean, I believe our best dollar per carat went past $4,000. That was in 2011, wasn't it? Yes, 2011. So that year was truly extraordinary. So I think that covers it. As for the effect of Argyle closing, I think it's indeed 20 million to 30 million carats removed from the market. And you'd have seen how the — that well-known jaws of the crocodile graph is now spreading apart.

Clifford Elphick

executive
#62

We discussed this at length before, and it never seemed to materialize. Now, though, it is happening. I'm not sure whether you've gone through the Bain report, Will Hillen, but if you haven't — it's an excellent source on the diamond industry. In that report, they've laid out what will probably unfold on the production side going forward, along with how many mines are either shutting down or going deeper, and what's occurring with overall supply. And I believe Argyle's closure has genuinely been behind some of Petra's — the rise in Petra's goods, though they aren't at that low level of roughly $30 per carat goods, it's $70 per carat and above, it's the same kind of category, not identical, obviously, but the same kind of category. And that has — that truly has been a major effect of Argyle shutting down. Is there room to bring effective tax rates down? Mike, would you like to take that one?

Michael Michael

executive
#63

Yes, Will Hillen. And yes, in theory that's right — if you were able to get every one of your costs into Lesotho, then you would bring the tax rate down. That said, we simply have to keep in mind that as a U.K. listed company on the LSE, this structure carries its own listing obligations. Roughly 30%, 40% of our costs are in fact U.K. costs, driven by our listings. So those costs wouldn't flow through. So we've examined that as well. We do attempt to evaluate ways we can effectively lower our tax obligations. But sadly, we can't relocate our entire U.K. operation just to reach South Africa -- to Lesotho.

Clifford Elphick

executive
#64

Michael, how would you respond to a private shareholder about the 50% decline in the share price across a 5-year span? I'm a large shareholder myself. And my disappointment matches yours. Given the valuations — for a company like ours, with $50 million in EBITDA, generating cash — I find the valuation quite staggering, to put it mildly. We pay a dividend. This marks the third dividend we've paid, and the second one in a row. Another shareholder asked whether a share buyback might be a better use of capital. A number of our shareholders favor a dividend, since they feel equal treatment of all shareholders serves everyone's best interests, and there is clearly merit in that view. At the same time, we've seen cases where miniscule volumes have caused the share price to drop dramatically. So a combination of a share buyback and a dividend is, we believe, probably the best approach to protecting the share price for all shareholders. And to have that buyer of — should I say, a buyer of last resort for small volumes, we really hope this will have a significant impact.

Clifford Elphick

executive
#65

And then, Ashley, how much variation in grade do you expect for 2022 compared with 2021?

Brandon de Bruin

executive
#66

Yeah, I’ll take that one. So the grade you’ll see in the guidance we’ve given is approximately just around 2, which aligns with a comparable mining mix where roughly 3 million Satellite tonnes go through the plant. Some K6 material is coming through, and that has a higher grade. So because of that, it will be around the 2 mark.

Clifford Elphick

executive
#67

And second, regarding the cash management side, which items won’t recur in 2022? I mean, some projects are finished and won’t carry through. Mike, would you like to go into detail?

Michael Michael

executive
#68

Yes, I can take that one. So I think the most significant shift is going to be the capital spending on waste, $65 million, on the slide we showed, tied to roughly 18 million, 19 million tonnes of waste. We're planning on 11 million tonnes. For the current year's guidance, that's 10 million to 12 million. And costs are going to rise. It has risen to LSL 51 to LSL 53, so it's nearer to just under $3.50, and the reason is lower volumes. So you'll strip out roughly $25-odd million — $25 million to $30 million out of that $65 million. And then the other cash flow that won't happen this year is we paid $24 million in tax, which again was essentially 2 years of tax, and we'll really only see 1 coming through. So that ought to halve to around $12 million. And then obviously, our biggest driver — or one of the drivers Brandon mentioned was looking at the sale of Ghaghoo, so those cash flows wouldn't be running through. Beyond that, the remainder is very, very old standard.

Clifford Elphick

executive
#69

Moving on to the third point, Ashley, regarding the buyback: yes, we genuinely think the company is significantly undervalued. By any measure you look at, we hold a solid resource base. We believe our cost control is good. Our benchmarks are set higher — whether that's governance standards. We've put in serious effort to eliminate wasteful spending. And it's really hard for us to understand why the business isn't valued or appreciated more. We've considered whether there's a Lesotho discount — whether operating in a small African nation is grounds for penalizing the business. I think there is — having a single asset in a single geography is a real factor, but over the past 4 or 5 years we've tried extremely hard to take part in a form of consolidation in which one management team could run 3 or 4 assets. Sadly, we've never managed to reach terms with any of our competitors on a basis that would work for our shareholders. So we haven't been able to resolve that issue — put differently, the problem of having more than one ore body.

Clifford Elphick

executive
#70

Sure, we do believe the stock is undervalued. We are working hard to try to do something about that. And Michael, I think that also speaks to your point. Thank you. Right. Any other questions that we haven't covered at the top, Mark? 8 years, 100 — yes, same point. It's a genuine problem. And frankly, it's unacceptable. None of us like watching our capital decimated. And we'll do our best. We have just finished a strategy session in which we examined this, with significant input from our banks and merchant banks, trying to pull apart the reasons behind it. I think the share buyback process, along with the dividend, ought to have an impact — to have a buyer, not a buyer of last resort, but to have a company putting its money where its mouth is, so to speak; I think that is going to have an impact, I hope so. All the academic studies suggest it should. But you don't really know until you've been doing it for a while. There are some practical limitations. Stock exchange rules only permit you to spend a certain amount of money and buy a certain amount of volume on any particular day, so it isn't quite the overall solution I would like, because I'd like to be more aggressive.

Clifford Elphick

executive
#71

We're somewhat limited, but we're definitely going to put in a solid effort. Right. Does anyone else have a question? Or are we — thanks, Matt. Capital costs for waste ought to come down. Okay, just to make sure, what is it — $25 million to $30 million, that's maloti, correct?

Michael Michael

executive
#72

No, that's not right. We actually have $65 million. You're asking about the drop in waste. So we'll have roughly 11 million tonnes of waste at a cost of about — yes, 11 million tonnes versus 18 million tonnes. And the cost will be roughly LSL 53 per tonne, which works out to around $3.50 per tonne. And that comes to, I believe, about $35 million compared with $65 million.

Clifford Elphick

executive
#73

Yes, the $30 million in savings is right. All right. Does anyone else have a question? Or may we start wrapping up? Right. Thank you, everyone. We'll call this meeting closed. Should any further questions come to mind that you haven't thought of just now, please send them our way. We're glad to engage either through e-mail or over the phone. We'd be very happy to talk through any of these subjects further. Many thanks.

Operator

operator
#74

Thanks a lot, sir. Everyone, that brings this event to a close, and you're free to disconnect at this point.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Gem Diamonds Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Gem Diamonds Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Gem Diamonds Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.