Golar LNG Limited (GLNG) Earnings Call Transcript & Summary
August 10, 2023
Earnings Call Speaker Segments
Karl Fredrik Staubo
executiveHi everyone, and thank you for tuning in to Golar LNG's Q2 2023 earnings results presentation. Karl Fredrik Staubo here, CEO of Golar LNG, and joining me is Eduardo, our CFO. Prior to starting the presentation, please take note of the forward-looking statements shown on slide 2. Our company overview appears on slide 3. As a focused FLNG player, we have two FLNGs: Hilli, currently operating in Cameroon, and Gimi, which is on the verge of delivery and will kick off a 20-year contract with BP. Key shifts in our asset portfolio this quarter included upgrading our FLNG conversion candidate, divesting the LNG Carrier Gandria, and picking up the LNG Carrier Fuji. Compared with the other vessel, Fuji offers significantly greater storage, has fewer years behind her, and loses less to boil off, which makes her a stronger fit for the Mark II FLNG conversion we have planned at 3.5 MTPA. An option to turn the Golar Arctic into an FSRU had been held by Snam of Italy. That option expired in July, so we are evaluating other paths for her, among them a charter over the long term or selling the asset. Among our investments are Avenir LNG, which operates in the small-scale LNG Carrier segment, and Macaw Energies, a business established with Golar acting as sponsor that pursues small-scale land-based liquefaction and gas monetization using proprietary technology, and which is presently being built. When it comes to independent, proven FLNG companies, Golar stands alone worldwide. Turning to slide 4, we'll walk through how we expect cash flow to grow in the near term, plus the additional earnings we could capture by recontracting the Hilli and possibly a Mark II FLNG. On the operational side, the Hilli keeps posting the best uptime in the market, delivering yet another quarter at 100% economic utilization. Under its current arrangement, the vessel serves Perenco in Cameroon through July 2026, and we anticipate robust earnings from the unit, helped by commodity-linked earnings terms that keep getting more attractive. That said, right now the ship is running at just 58% of its nameplate capacity. We believe there's meaningful room to lift capacity utilization while also securing better earnings when the Hilli is re-chartered. When we signed the present agreement, our FLNG technology hadn't yet been proven, and the fact that Hilli is the first FLNG available anywhere in the world keeps driving more customer interest in that vessel past the life of the existing deal. Gimi, our second FLNG, is nearly ready to leave Seatrium's yard in Singapore and begin a 20-year contract with BP. As Gimi moves out of CapEx and starts producing earnings, our free cash flow generation will get a substantial boost, and once delivery happens we also see considerable room to optimize the debt facility tied to Gimi. A Mark II vessel at 3.5 MTPA is what our contemplated third FLNG would be. Should we place an order during 2023, delivery would come in late 2026, with operations beginning in early 2027. Adding a Mark II unit would take our overall liquefaction capability up to 9 million tons yearly, compared with roughly 5.5 million tons currently — a gain of approximately 70%. So we've identified three triggers for cash flow at this company. First, Gimi gets delivered and starts up in the second half of this year, which moves that vessel's cash flow out of CapEx and into earnings. Second, we recontract Hilli with better capacity utilization as well as improved operational margin. Third, we place the order and secure a charter for a Mark II FLNG. As the bottom part of the table illustrates, beginning in early 2027, we'll have up to 322 MMBTU available to charter. Given tariffs in line with what's competitive in today's U.S. export market, that capacity translates to about $1 billion in earnings. That said, our FLNG technology makes it possible to monetize stranded gas reserves that would otherwise stay undeveloped. So we think substantially higher liquefaction margins—margins that ought to be achievable—are within reach; right now we're in talks with over six separate gas resource owners across various geographic locations, centered on West Africa, regarding potential FLNG deployment, and every one of those offers meaningfully better economic terms than the charters we have today. Now to slide 5 and the quarter's highlights. Hilli kept up its 100% economic uptime, and our 97th cargo has now been offloaded. We're happy to confirm the improved terms for the Hilli financing are finalized, cutting the debt margin and lengthening the amortization profile and facility duration. Gimi stands at 97% technically complete, and we anticipate sail away in September of this year. On the business development side, we've broadened further the MOU we signed with NNPC in April, which will now be advanced through a heads of terms laying out the contractual framework for jointly developing specific gas fields toward possible FLNG deployment. Commercial opportunity development is also moving ahead beyond Nigeria, including negotiations on commercial terms with gas resource owners and engagement with governments in possible countries of operation; worth noting is that the complexity of offshore gas development shapes how long it takes before any binding terms for incremental FLNG work can be announced. Under corporate and other, Eduardo will address most of that afterward in the presentation, but consistent with our Q1 guiding, we've declared a quarterly dividend of $0.25 for Q2 as well. In the quarter we also used roughly $30 million of the $150 million buyback program announced in May, and we've acquired and canceled approximately 1.4 million shares. We stay committed to boosting shareholder returns as our earnings keep growing. Let's now move to a business update, beginning with Gimi on slide 7. As noted earlier, the vessel is 97% complete, and we expect sail away from the shipyard in September. System handover is in progress and final testing is ongoing. Talks tied to specific pre-commissioning contractual cash flows are still underway through arbitration. Even so, the expectation is that this won't have a wider impact on the 20-year contract we hold with BP. Moving to slide 8, now that Gimi has been delivered, the cash outflows tied to that vessel are beginning to convert into earnings. Work on building Gimi started in 2019, and it fell behind schedule owing to COVID's impact both at the shipyard and among sub-suppliers. Golar holds two key assets, which means until this point about half of the balance sheet hadn't been producing cash flow. As Gimi transitions from CapEx into cash flow, and with Hilli's commodity earnings climbing, we expect earnings to keep growing in the years ahead. All of this comes prior to any possible final investment decision on a Mark II, which would drive additional profit in future years. If you look at slide 9, we've broadened our partnership with NNPC, adding a heads of terms that was signed in Abuja on August 1st. Under those heads of terms, a commercial framework is laid out for developing recognized gas resources located in Nigeria. Beyond our talks with NNPC, we are likewise advancing possible FLNG deployment alongside four independent owners of gas resources in Nigeria. Alongside what's happening in Nigeria, we observe comparable activity involving over five possible FLNG deployment chances in additional West African nations, where commercial negotiations are underway right now with gas resource owners, plus government engagement in the potential countries where we'd operate. Our top priority stays the same: first recharter Hilli before reaching FID on a Mark II FLNG, and after that lock in the charter for that vessel. Shifting to slide 10 and what we accomplished during the quarter on a Mark II. Like we mentioned earlier in this call, we've upgraded the vessel we're looking at for FLNG conversion — we picked up Fuji and let go of the LNG carrier Gandria. On top of that, we've made real progress with lenders in China on a debt package that could go up to $1.5 billion, and it doesn't require a charter to go through.
Karl Fredrik Staubo
executiveWe have kept collaborating with the shipyard in order to bring more certainty to both the schedule for building and the costs involved; our pre-FID commitments have been raised to roughly $400 million, achieved via long lead items, engineering efforts, plus the Fuji acquisition we already mentioned. As was hinted at, should we reach FID on that project during this year, delivery will happen by the close of 2026. Moving to slide 11, we observe solid long-term basics underpinning LNG pricing. Looking at the macro picture, even though gas prices have normalized, that hasn't dampened the keen appetite for locking in future position. Buyers in Asia are busy signing long-term SPAs, and as the graph on the left shows, 2023 looks set to end up nearly matching 2022 when it comes to contracted volumes. Back in 2022, we hit the highest level ever recorded. What this ongoing purchasing interest produces is a climate of escalating prices, and the middle graph illustrates how long-term deals are priced against Brent, presently sitting in a band of 12.5%-13.5% of Brent. Even so, shorter-term agreements have reportedly been struck at between 16% and 20% of Brent parity. So we agree with the stance taken by big players like Shell and BP, namely that LNG demand will stay strong over the long haul, since it provides an answer to the energy trilemma confronting the world right now. That means balancing energy security, affordable energy access, and achieving this sustainably. That's among the things we aim to capture on land via Macaw Energies, which we'll go into more detail about on slide 12. Macaw is advancing as planned, aiming for first operations during 2024. Commercial and technical work continues, while we build commercial momentum together with clients across the U.S. and South America. On top of that, the company is already positioning itself to secure gas for its liquefaction technology, with multiple talks underway involving gas suppliers. To seize the market opportunity Macaw embodies, we are reviewing options that would enable growth beyond the commitment Golar has already made. I'll now pass the call to Eduardo, who will walk us through the Q2 results.
Eduardo Maranhão
executiveThanks, Karl, and good morning, everyone. I'm quite pleased to share an update on how the group performed in the second quarter of 2023. Turning to slide 14, I'd like to take you through some of the financial highlights for the quarter. Total operating revenues reached $78 million, representing a 5% increase over the first quarter of 2023. Since Brent and TTF prices eased during Q2, our total FLNG tariffs came in at $99 million, down 10% versus the previous quarter. FLNG tariff is an important non-GAAP metric, comprising all revenues generated by liquefaction services, including realized gains on oil and gas derivatives. For this quarter, we anticipate that this item will swing back to a positive figure, thanks to stronger Brent and TTF pricing. On top of that, our adjusted EBITDA came in at $83 million, essentially matching what we saw in Q1, even though commodity-linked fees contributed less, which I noted earlier. Corporate and other adjusted EBITDA got a boost from reduced expenses associated with the Tundra development agreement that wrapped up in May; during this quarter, net income reached $7 million, marking a substantial gain over Q1. That amount consists of $72 million in non-cash items overall, including $77 million in unrealized losses tied to oil and gas derivatives, $10 million in unrealized gains on our interest rate swaps, and a $5 million impairment related to the Gandria sale. We continue to have a robust liquidity position, at nearly $1 billion of liquidity. This comprises cash on hand along with other receivables stemming from the unwinding of our TTF hedges earlier in the year. Our contractual debt totaled slightly under $1.2 billion, which left us at a net debt position of $190 million. Now, moving to slide 15, I'd like to give a recap of our historical earnings from Hilli. On this chart, you can see the portion of Hilli's adjusted EBITDA that belongs to us. The tariff, as shown here, consists of three primary pieces. First, there's a fixed tolling tariff of $34 million, which came in at the same level as the prior quarter. Second, we have a Brent-linked fee of $15 million for this quarter, which is lower than the 18% recorded in Q1. Third, there's a TTF-linked fee of $30 million, also a decrease from the $37 million we saw last quarter. As I noted earlier, we anticipate that stronger oil and gas prices will help lift tariffs through the remainder of 2023. Now, if you look at slide 16, it shows that our exposure to TTF prices continues for the rest of 2023, spanning August through December. To illustrate the way this could boost what we earn, each dollar-per-million-BTU shift in TTF pricing should bring us roughly $1.4 million more during 2023. Looking at 2024 through 2026, that figure rises to $3.2 million for each dollar of TTF prices. Take a simple case: should TTF prices come in at an average of $15 per million BTU next year, that tariff by itself ought to generate about $48 million for us. On top of that, with Brent, every $1 per barrel increase beyond $60 per barrel contributes $2.7 million. As we talked about on the May call, we were able to negotiate and finish amending the Hilli debt facility on better terms, with a lower margin plus longer tenor and amortization schedule; those changes should free up roughly $75 million in extra cash through the end of the existing contract in mid-2026. The new terms took effect at the end of June and are now in force. Moving to slide 17. Our balance sheet is still solid, and we have a lot of flexibility to support progressive shareholder returns while also funding our FLNG growth program. If we look at liquidity at this moment, including the cash we expect to receive from TTF hedge receivables, it adds up to almost $1 billion. That amount is enough to cover all the development and equity requirements for the Mark II FLNG build. Beyond that, several alternatives exist that might increase our liquidity even more to support further expansion. One example is a potential refinancing of the existing debt facilities tied to both Hilli and Gimi, which, if we chose to pursue it, could unlock a significant amount of equity. As shown on the earlier slide, the free cash flow that Hilli produces—more than $200 million annually—completely supports the dividend and buyback program as it stands today. Once Gimi begins operations, those figures will rise further, creating the potential to increase shareholder returns down the line. During this quarter, a dividend of $0.25 per share was declared by us, with August 21st set as the record date and payment expected on or around August 29th. Following the May announcement of our $150 million buyback program, $30 million has been deployed to repurchase 1.4 million shares at an average price of approximately $21. As a result, by the close of June, 160 million shares were outstanding. At this point, I'll hand the call over to Karl for some closing remarks.
Karl Fredrik Staubo
executiveThanks, Eduardo. Now let's look at slide 19, where we pull everything together. On the left side, you can see strong earnings growth coming out of the assets we already own, as Gimi shifts from CapEx into generating cash flow, along with a bigger future lift from the commodity-linked earnings tied to Hilli. As the graph shows, every bar sitting above that green line — which marks total debt service — amounts to free cash flow to equity. Down on the bottom left, the pricing looks attractive at EV per million tons of yearly liquefaction capacity, now roughly $680 million per ton, which is about half what it would take to build current shore-based liquefaction projects in the U.S. Up on the top right, our balance sheet gives us the room to keep growing the company. Cash right now is approximately $1 billion, with total net debt at a touch under $200. We've begun returning capital to shareholders via quarterly dividends and a $150 million buyback program, and $30 million of that was used in Q2; our plan is to distribute a growing share of free cash flow to equity among our shareholders, while putting our balance sheet capacity to work on FLNG growth projects — specifically Mark II FLNG, which carries 3.5 MTPA of capacity; and on the bottom right, there's an illustrative CapEx to EBITDA multiple, dependent on margin per MMBtu along the x-axis, against what that CapEx to EBITDA multiple would look like if we deploy at a range of different rates. With over 300 MMBtu of liquefaction capacity available starting in 2027, we think we're in a strong position to monetize stranded gas reserves, especially in West Africa, though we're also in discussions about other geographic regions. That wraps up our Q2 earnings presentation. Thanks for joining us, and we'll turn the call over to the operator now for questions.
Benjamin Nolan
executiveOkay, hi there, and thanks — greetings to Eduardo and Karl as well. I've got a couple of questions, and hopefully that works. Starting with the Nigeria transition: when you shift things from a memorandum of understanding over to a heads of terms, I'm trying to get a handle on how significant a step that actually represents, and in your view, how near does a heads of terms bring you to an executed contract? Are we, in your judgment, substantially closer to a binding definitive agreement, or is it more like, you know, I'm not really sure. Perhaps you could put that in context for me.
Karl Fredrik Staubo
executiveHello, Ben, and I appreciate you asking that. There isn't a manual for repairing an FLNG unit. Golar stands as the sole independent FLNG supplier globally, and we've completed 2 contracts—1 with Perenco, another with BP—and each had a distinct character. Still, the process as it unfolds in our continuing talks with an NNPC begins with executing an MOU to free up resources, especially on NNPC's end. After those resources were freed up in late April, and through a number of gatherings in London plus in Nigeria, we jointly crafted a framework—a commercial framework—for the development of named resources. That commercial framework was subsequently agreed upon, and that is what has been committed to via the heads of terms. When the heads of terms get signed, a further workstream opens up, especially for NNPC, to direct additional resources toward advancing these projects. Since every FLNG project has its own character, offering guidance on precisely when, in what manner, or how substantial is hard, yet things are definitely moving in a favorable direction.
Benjamin Nolan
executiveAlright, that's useful. Now for my next question, you mentioned the Mark II. Should you manage to land a contract for that asset prior to the year's close, it would be ready in 2027. Meanwhile, you describe the Hilli as essentially at the front of the queue. I'm simply wondering whether you consider it sensible to believe that a Mark II contract could be signed before this year ends while keeping to that roughly 2027 schedule?
Karl Fredrik Staubo
executiveLet me be clear on this: should we decide to extend or recharter Hilli, we'd move forward with Mark II even without a contract in hand. Seeing contracts on both Hilli and Mark II isn't necessary. Given everything sitting in our pipeline, I'd say our confidence keeps growing — both about getting Hilli rechartered and about securing a favorable charter for Mark II. The only thing left is making sure the risk reward stays balanced before we commit roughly $2 billion in CapEx.
Benjamin Nolan
executiveAll right. Yet I suppose what you're suggesting is, by the time this year wraps up, you wouldn't consider that to be, that would be excessive. Is that a fair way to put it?
Karl Fredrik Staubo
executiveThat's what we're working towards, yes.
Benjamin Nolan
executiveYeah. Okay. All right, I appreciate it. Thank you, guys.
Chris Tsung
analystThank you, Ben.
Chris Robertson
analystHello, and a good morning and good afternoon to you, Karl. What I have is a follow-up on what Ben asked. When we consider the possible scope of work alongside NNPC, could there be an opportunity to put both Hilli and the Mark II asset to work with them?
Karl Fredrik Staubo
executiveWithin that country, the gas available to them is more than sufficient for multiple FLNGs to be deployed. That's right.
Chris Robertson
analystAll right, that clears it up for me. Thanks. Now, regarding those five additional nations, or organizations, that you're currently in talks or discussions with — do they all, I suppose, have a national oil company involved, or might some international oil companies also be part of the assets under consideration?
Karl Fredrik Staubo
executiveCorrect, though the primary emphasis is on NOCs, and a few of them additionally involve IOCs.
Chris Robertson
analystAll right, that's excellent. Many thanks. I'll hand things over.
Chris Tsung
analystHi there, good afternoon to Karl and Eduardo. How's it going? Fine, thank you. I wanted to continue on those NNPC items and the additional ventures you have going on in West Africa. Will every one of those be structured as tolling arrangements, or are they integrated? And as a related point, what level of ownership should Golar be expected to hold? Would that be something like 100%, or might there be some NOCs, or perhaps IOC partners, joining in?
Karl Fredrik Staubo
executiveAll right. None of the ventures we are currently pursuing involves a set fee of the type that Gimi has. Each one is either completely integrated or a set fee combined with commodity exposure, closer to how Hilli works, though with an even greater degree of commodity exposure. The rationale behind our preference for arranging the charters this way is our observation that achieving stronger project economics becomes considerably simpler when upside and downside are shared alongside the IOCs — or, rather, the NOCs, my mistake. Provided this is tied to very liquid global price benchmarks like Brent, TTF, JKM, or comparable ones, we are able to hedge away that kind of pricing risk through the paper market at any time, and that is precisely our aim. Regarding.
Chris Tsung
analystAll right, that's intriguing.
Karl Fredrik Staubo
executiveEach project is different. In most cases, Golar keeps ownership of the FLNG. The NOC continues to hold the upstream and gas treatment. Both sides aim for the leanest possible economics on that portion, and after that we split the gas offtake pricing, which gets you essentially the same outcome. For a few of them, there's discussion about having economics spanning the value chain too. Should that happen, the resource definitely has to be large enough to charter the vessel for its remaining life, be it Hilli or a Mark II.
Chris Tsung
analystAll right, that's helpful, thanks. I just want to make sure — does the BP contract for Gimi begin in the first quarter of next year, when the vessel shows up at the site, or does it depend on the first-time-zero commissioning cargo being produced? I'm just trying to get a sense of things from what I've been hearing on, you know, the BP and Kosmos earnings calls.
Karl Fredrik Staubo
executiveRegarding that project, I'd say Golar's aim is to get the FLNG delivered, and to get it delivered safely to the site at the hub. We aren't assuming risk or responsibility for any other portion of the infrastructure. The way the contract mechanisms are set up, cash flow to Golar will occur once we commence or reach the site, no matter what status those other portions of the infrastructure are in. That said, it's fair to note that everyone involved has an incentive to get the project operational as quickly as possible; beyond delivering the FLNG, we aren't actively involved in any other portion of the project.
Chris Tsung
analystYes. That's clear, no problem. I appreciate it. I'll hand things off now.
Karl Fredrik Staubo
executiveThanks to everyone for joining the call. I wish you a good day, and I look forward to talking with each of you again very soon. Thank you.
Operator
operatorThat conclude the conference for today. Thank you for participating. You may all disconnect.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Golar LNG Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Golar LNG Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Golar LNG Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.