Good day, ladies and gentlemen, and welcome to Hindustan Zinc's Second Quarter FY 2026 Earnings Conference Call. Please be reminded that every participant line will be in listen-only mode, and once the presentation wraps up, you'll have a chance to ask questions. If you require assistance at any point during this call, just signal an operator by pressing star, then zero on your touch-tone phone. Kindly be aware that this conference is being recorded. I'll now turn the conference over to Ms. Raksha Jain, Director of Investor Relations at Hindustan Zinc. Thank you, and over to you, ma'am.

Raksha Jain

executive
#2

Thank you, operator, and good evening, ladies and gentlemen. We appreciate your joining us today to discuss the Second Quarter and Half-Year Results of FY 2026. During this call, we will refer to our investor presentation, which is available on our company's website. Please note that the Safe Harbor Clause mentioned on slide two of the presentation covers today's entire discussion. With us today are our CEO, Mr. Arun Misra, and CFO, Mr. Sandeep Modi. Management will be discussing the operational and financial updates for the quarter, followed by a Q&A session. Now, I would like to invite Mr. Arun Misra to present the results. Over to you, sir.

Arun Misra

executive
#3

Thank you, Raksha. Good evening, everyone, and thanks for being with us today for the Second Quarter and Half-Year FY 2026 results briefing. This year has been extremely eventful for Hindustan Zinc so far — whether it's record mine metal output, the lowest production cost seen in recent years, ambitious CapEx plans, or ESG practices recognized around the world — all of which strengthen the company's strong path toward sustainable long-term growth and its position of global leadership. During this quarter, we were privileged to become the first Indian company to earn the prestigious membership of the International Council on Mining and Metals, a global industry body that unites leading mining and metals companies and associations to enhance sustainable development performance across this sector. As the first new member of the council since 2021, Hindustan Zinc now belongs to an exclusive global league of 26 companies recognized for excellence in responsible mining. With this inclusion, it becomes imperative for us to further deepen our commitment to sustainability across all dimensions outlined under the Sustainability Goals 2030. On the safety front, I am happy to share that we have kept operations fatality-free during the year, which reflects our strong commitment to high standards of safety culture.

Arun Misra

executive
#4

As we move forward on decarbonization, we signed two MOUs with GreenLine Mobility Solutions Limited. The first is to deploy 100 EV trucks for concentrated movement, which makes it India's first commercial-scale initiative of its kind, and the second is to expand the LNG net truck fleet for finished goods logistics. In this quarter, we also released our FY 2025 Sustainability Reporting suite, which includes the Sustainability, TNFD, and Climate Action Reports, offering comprehensive and transparent disclosures that underscore our commitment to strong governance and accountability. Our CSR initiatives continue to create meaningful impact, spanning seven thematic areas and positively touching over 2.3 million lives. Last quarter, we signed an MOU with the Rajasthan Heritage Authority to develop the heritage corridor at Poonchhari Ka Lauta, with a CSR commitment of INR 85 crore over three years. The project will preserve and promote local culture and heritage, including restoration of historical sites and buildings, along with developing botanical gardens and supporting infrastructure. This quarter also witnessed the second edition of India's most beautiful, the Vedanta Zinc City Half Marathon, which saw participation from nearly 7,000 runners across the globe, all supporting the noble cause of Run For Zero Hunger. Coming to the market update, in the broader macroeconomic backdrop, global growth continues to navigate a phase of softness and elevated uncertainties.

Arun Misra

executive
#5

Major institutions are now projecting worldwide GDP expansion of 2.5%-3% for 2025 — a bit below what was previously expected, given escalating trade frictions, swings in commodities, and tighter policy in several key economies. Even with that softer demand backdrop, the non-ferrous metals space has shown considerable strength. Take zinc: prices have hardened over the last few months, and in October LME zinc moved past the $3,000 per ton threshold and has kept trading above it, helped by low inventories and fresh consumption from galvanizing and infrastructure. Lead has held firm as well, with solid battery demand and constrained supply upstream providing support. Silver, for its part, has posted a powerful rally, reaching new highs and underscoring how it functions both as an industrial input and as a store of value. Domestically, India remains a standout, keeping up robust momentum. GDP grew roughly 7.8% in quarter one FY 2026, and major agencies expect full-year expansion of 6.5%-6.8%. That strong showing reflects resilient private consumption, continued capital expenditure, and supportive government measures — together creating a favorable demand tailwind for zinc, lead, and silver offtake. This positive commodity backdrop ties directly into Hindustan Zinc's strength as a leading integrated producer of zinc, lead, and silver.

Arun Misra

executive
#6

Zinc and lead prices staying consistently firm are still underpinning steady profitability in our base metals division, and the silver rally that's underway is delivering meaningful upside — especially as we push forward with our long-term strategy to grow silver output from 700 tons today to 1,500 tons via our 2x growth CapEx programs. Turning to operations, the company posted its strongest second quarter and first-half mine metal production ever, along with the lowest zinc cost of production in five years for those same periods, which drove record second quarter EBITDA of INR 4,467 crores and profit after tax of INR 2,649 crores. Zinc cost of production in the quarter came in at $994 per ton, a 7% year-on-year improvement, helped by renewable energy usage, stronger byproduct realizations, and input commodity prices that have eased. At the half-year mark, COP was $1,002 per ton, 8% better year-on-year, supported by improved metal grades, greater byproduct sales, softer input commodity prices, and increased consumption of domestic coal and renewable energy. Refined metal production for the quarter was 246,000 tons, and sellable silver production reached 144 metric tons. Silver has jumped to an all-time high of roughly $50 per troy ounce. As India's sole integrated silver producer, with about 40% of profits coming from silver, we're uniquely placed to take advantage of this cycle.

Arun Misra

executive
#7

As we look forward, we've updated our guidance for FY 2026 refined metal to 1,075 ± 10,000 tons per annum, and for silver to 680 tons ± 10 tons per annum, taking into account reduced plant availability and lower silver input in the first half of the year. Our growth projects are moving forward according to plan. In the second quarter, we commissioned a 160,000 tons per annum Roaster at Debari and finished the de-bottlenecking of the cell houses at Dariba Smelting Complex. De-bottlenecking at Chanderia Lead-Zinc Smelter remains on track for completion in quarter three FY 2026, to be followed by the Lead Silver Recovery Plant using hot acid leaching technology in quarter four FY 2026. These projects will support higher refined metal and silver output in the years ahead. In addition, to accelerate the company's growth in step with the nation's prospects, EPC partners have been finalized for the previously announced projects: the 250,000 tons per annum integrated metal capacity expansion, expected to be completed by second quarter FY 2029, and India's first 10 million ton per annum zinc tailing reprocessing plant, expected to be completed by fourth quarter FY 2028. Looking forward, in a relatively tepid global growth environment, our integrated operations, cost discipline, and commodity leverage positions leave us well placed to deliver strong earnings.

Arun Misra

executive
#8

Looking ahead, the market should anticipate that upside potential will persist, provided demand stays firm and inventory levels remain healthy. Zinc, in our view, will keep trading within a resilient band; lead will continue to find support from battery and industrial demand; and silver may well hold onto additional gains — all of which could fuel incremental margin expansion over the coming quarters. Our top priority is making sure our growth projects are executed on time and reinforcing Hindustan Zinc's standing as a sustainability-driven global leader in the future. Our ESG commitment stays clear and simple: it is guided by ICMM principles and grounded in global practices. By diversifying strategically and investing with discipline, we are well positioned to deliver sustainable growth and create long-term value for our shareholders. With that, I will now pass things to Sandeep, who will walk us through the financial performance.

Sandeep Modi

executive
#9

Thank you, Mr. Misra, and a very good evening to everyone. Global growth is still moderate given policy tightening and geopolitical uncertainty, but commodity markets have proven resilient. Zinc and lead prices have strengthened as supply has tightened against industrial demand. Silver is trading at record highs, above $50 per ounce, backed by robust industrial demand from solar, electronics, and the green energy transition. With our consistent operational excellence and cost leadership position, Hindustan Zinc is well placed to capture this upcycle. As the world shifts toward a low-carbon future, Hindustan Zinc stands in the right business at the right time — a compelling choice for investors looking for exposure to India's precious metal primary producer company. It is a sustainability growth story at a time when zinc prices have also been at their peak from October until now in this financial year. India remains a bright spot, with GDP growth of between 6.5%-6.8% envisaged in FY 2026, supported by resilient private consumption, consistent capital expenditure, and a strong policy push. This robust domestic momentum is translating into a constructive demand tailwind for zinc, lead, and silver offtake. It is prudent to note that in the first half of the year, we contributed around INR 8,400 crore to the national exchequer, of which INR 2,500 crore went to the state of Rajasthan, reflecting our continued role as a significant economic partner to both the state and the nation.

Sandeep Modi

executive
#10

Before turning to the financials, I'm happy to report that we've released our fifth integrated annual report, together with the digital annual report for FY 2025, which has been hosted on a green-powered server for the third year in a row. Our GenAI chatbot has this year developed into a Zincky featuring real-time voice interaction and improved accessibility features, text-to-speech among them, and it's available on our website. Now to the numbers: we posted record second quarter revenue from operations of INR 8,549 crore, a 10% rise sequentially, fueled by higher commodity prices, a stronger dollar, and better byproduct realization, partly offset by lower production. In the quarter, we logged our highest-ever second quarter EBITDA of INR 4,467 crore, up 16% sequentially. This result was supported by our five-year lowest second quarter zinc cost of production, excluding royalty, of $994 per ton, made possible by higher byproduct realization and softer input commodity prices. Those factors helped us maintain our industry-leading EBITDA margin of around 52%. Consequently, we posted profit after tax of INR 2,649 crore, up 19% quarter-to-quarter, which reflects the strength of our operations and favorable market conditions. For the first half of the year, we delivered our second-best financial performance, with EBITDA of INR 8,328 crore, up 3% YoY, and PAT of INR 4,883 crore, an increase of 5% over last year.

Sandeep Modi

executive
#11

Excluding royalty, our zinc cost of production came in at an outstanding $1,002 per ton — the lowest first-half figure we've seen in 5 years. On top of that, we posted a record return on capital employed of roughly 65% for the trailing 12 months. Starting from the first quarter, we've kept delivering zinc CoP under the guidance we originally set. Accordingly, we're lowering our cost guidance for the full year to approximately $1,000 per ton, which puts us well ahead of the FY 2027 target we had set earlier. With more growth projects now approved, our growth capex guidance for this year is expected to fall within $350 million-$400 million. That covers every growth initiative currently underway — fertilizer, the hot acid leaching plant, smelter de-bottlenecking, and the new 250 KTPA integrated smelter expansion at Debari, along with India's first zinc tailing reprocessing plant at Rampura Agucha. I'm also happy to report that Hindustan Zinc has joined the Nifty 100 and Nifty Next 50 indices, effective 30 September 2025. That milestone speaks to our growth journey, our resilience, and our consistent performance, and it highlights how committed we are to building long-term value for all our stakeholders and for the nation. To sum up, this quarter shows sustained resilience and operational excellence, powered by cost leadership and disciplined execution.

Sandeep Modi

executive
#12

As we move into the next phase of growth, our attention stays on getting the most out of metal recovery, growing silver production, and completing high-return projects, while using technology, innovation, and sustainability to generate value. Given India's robust economic momentum and green transition, Hindustan Zinc is positioned well to build sustainable value and pursue responsible growth. With that, I'll now turn things over to the operator for Q&A. Thank you.

Operator

operator
#13

Thanks a lot, sir. Ladies and gentlemen, we're moving on now to a question-and-answer session. If you'd like to ask a question, you can press star and one on your touch-tone phone. Should you want to drop out of the question queue, just press star and two. We ask that everyone use only handsets when posing a question. Ladies and gentlemen, we'll pause for a moment while the question queue assembles. Please press star and one to ask questions. Our first question comes from the line of Amit Lahoti from Emkay Global. Please go ahead.

Amit Lahoti

analyst
#14

Appreciate the chance to ask. My questions concern silver. First off, is the plant currently operating in lead mode or in zinc-lead mode? Since the pricing economics favor lead mode.

Arun Misra

executive
#15

No, no. The plant continues to operate in zinc-lead mode, since what we're doing is adjusting our approach somewhat from the earlier one under which, for silver, we ran in lead mode only. Our approach now is to run in zinc plus lead mode, though we're using up the bulk of the concentrate arriving from SK Mine, which is high in silver. This should also be viewed together with the silver grade the mine is turning out. The current silver grade isn't very high — it sits at roughly 90 ppm. So the benefit we'd get from lead mode wouldn't be as large as it was previously. Therefore it makes sense to operate in zinc plus lead mode while getting the most out of SK Mine concentrate, so that we at least produce all the silver we can under present conditions.

Amit Lahoti

analyst
#16

All right, so with the 680 tons we've guided to for silver, the required pace in the back half is steep, since output during the first half ran somewhat behind. So how do we plan to hit that figure? And do we have line of sight to producing, let's say, 800 tons of capacity within a year or two?

Arun Misra

executive
#17

Right, right. So here's what we did in H2: we moved resources away from other mines over to SK Mine, and on top of that we gave incentives to the contractors and the workmen there, all to make sure we go after those stocks with the high silver content and get them produced in H2, so we capture the biggest benefit from silver while prices remain elevated. That's the shift you'll be seeing in the numbers as we continue to deliver. H2 is going to produce the numbers that get us to the guidance we've released today, and we're very confident in it.

Amit Lahoti

analyst
#18

All right. So could we get to 800 tons in, let's say, FY 2027? Is that a goal?

Arun Misra

executive
#19

That's the goal, since by then the current Fumer will be completely stabilized. We'll have that with acid leaching from jarosite to recover a certain amount of silver. We'll also have the new 250 KTPA plant coming in from that point. Plus, it will be built together with Fumer. So it might not be 800 ton, but certainly from 700 ton on average to 750 ton seems achievable.

Amit Lahoti

analyst
#20

Alright, thanks.

Operator

operator
#21

Thanks. Our next question comes from Manav Gogia at YES Securities Limited. Your line is open.

Manav Gogia

analyst
#22

Yes, hello there, and good evening to everyone — I appreciate the chance to speak. To start, let me congratulate you on those strong results. My first question is about the 250 KTPA project, which carries a cost of roughly INR 12,000 crores. On top of that, we now have a tailings project of INR 3.8 crores coming up. So how do we expect CapEx to take shape over the coming couple of fiscal years — early 2027 and 2028?

Arun Misra

executive
#23

Let me just make a small correction there: the cost for that 250 KTPA smelter now stands at INR 12,000 crores. It's a smelter expansion at my mine, along with a brand-new concentrator plant. That portion of the project comes to INR 12,000 crores. As for your second question, on that 250 KTPA smelter, we've already begun work on the ground, and we're finalizing the technology — the cell houses for this smelter will be 240 kiloamp cell houses, versus the earlier ones at 200 kiloamps — and we're also looking at building in the inherent ability to de-bottleneck and lift capacity further with a marginal CapEx investment. Once we stabilize production at that 250 KTPA, we'll be able to de-bottleneck further.

Sandeep Modi

executive
#24

And Manav, there's a bit here as well. I believe you were also asking about how capital allocation, or CapEx, is going to look over the coming three to four years. So beyond this INR 16,000 crore, roughly 20% will fall in this year, or about 50% will come next year, with the remainder the year after that. That's typically how CapEx tends to flow. At the start you make the advances and mobilization advances, so 20%-25% this year and 55%-60% next year, and then what's left lands in FY 2028.

Manav Gogia

analyst
#25

Thanks. For FY 2026, our growth CapEx is $350 million-400 million. What would the total be for that year, including maintenance CapEx?

Sandeep Modi

executive
#26

No, that figure refers to growth CapEx. Maintenance CapEx should come in at roughly $400 million.

Manav Gogia

analyst
#27

Understood. Sure, sir. So my second question, in a moment, comes back to the tailings project. I just wanted to know what sort of refined metal output are we looking at from this 10 million tons of the tailings project that we are setting up?

Arun Misra

executive
#28

Out of that 10 million tons project — the tailings one we're looking at — we should end up producing roughly 100 KTPA of zinc metal.

Manav Gogia

analyst
#29

So the only thing that comes out of this is zinc?

Arun Misra

executive
#30

We’ll also include zinc, along with a small but proportional amount of lead as well.

Sandeep Modi

executive
#31

The concentrate holds roughly 25 tons of zinc.

Manav Gogia

analyst
#32

Yes, yes, thank you, sir. So I just have one last question. Could you tell me what the average mining grade was for this specific quarter?

Sandeep Modi

executive
#33

7.4%.

Manav Gogia

analyst
#34

7.4%. So in Q1 it was 7.53% earlier, right?

Arun Misra

executive
#35

However, this time it came in at 7.53% as well. We had anticipated 7%, though we might end up at 7.4%.

Sandeep Modi

executive
#36

You should also look at it year over year. The quarter a year ago came in at 7.3%.

Manav Gogia

analyst
#37

Understood, understood. Of course. I'll rejoin the queue. Thanks very much.

Sandeep Modi

executive
#38

I appreciate it.

Operator

operator
#39

Thanks. We’ll take the next question from Pallav Agarwal at Antique Stock Broking. The line is yours — please go ahead.

Pallav Agarwal

analyst
#40

Good evening, sir. I'd just like to get a sense of the renewable energy proportion this quarter, and what it could be by the end of FY 2026?

Sandeep Modi

executive
#41

For this quarter, renewable energy came in at 19%, and as we mentioned earlier, the exit rate ought to be 25%.

Pallav Agarwal

analyst
#42

Sir, and would this be among the factors keeping our cost CoP down?

Sandeep Modi

executive
#43

As we mentioned before, for each 2% rise in renewable energy, my power cost drops by 1%, which cuts total cost by $1.5 per ton. That's one of the main drivers. Beyond that, coal costs in general have been easing too, and that's also giving us a hand on overall power cost.

Pallav Agarwal

analyst
#44

Yes, sir. And is there any particular reason depreciation is coming down quarter over quarter? Mined metal production is roughly the same. So on a sequential basis, we have seen a decline in depreciation.

Sandeep Modi

executive
#45

Right. At first, it went down on the amortization side. I’ve got 2% for depreciation and amortization. So basically we have the lower figure, and it depends on the mine development cost per meter, since we’ve applied the instant cost effect. Because of that, our mine development rate per meter was reduced. And so, as a result, the amortization cost went up.

Operator

operator
#46

Sorry to cut in, sir — your voice is breaking at the moment.

Sandeep Modi

executive
#47

Can everyone hear me?

Operator

operator
#48

Sir, could you say that final sentence again? We didn't catch it clearly.

Sandeep Modi

executive
#49

Pallav, depreciation and amortization is made up of two components — depreciation, and amortization. Depreciation has gone up as the Roaster and the de-bottlenecking CapEx have been capitalized, but we saw a benefit on the amortization side, since that expense is a function of the mine development rate per meter. So that was genuinely consistent with amortization expenditure having come in lower.

Pallav Agarwal

analyst
#50

Yes, sir. And regarding net debt, we've observed a sequential decline. So do we still anticipate potentially finishing with a net cash position by the close of FY 2026?

Sandeep Modi

executive
#51

We ought to be at net debt. It should stay flat, considering that we've changed our growth CapEx guidance from $350 million up to $400 million. As mentioned before, pre-growth CapEx ought to come in at our figure of $1.1 billion-$1.2 billion. Once you factor in the growth CapEx investment along with overall sustaining, we should be producing those numbers. On that basis, net debt or net cash should be flat.

Pallav Agarwal

analyst
#52

Sure, sir. So finally, I mean, at this point I think we're getting back to a CoP under $1,000. So one thing, clearly, is the growing share of renewable power. That's bringing down the power and fuel cost. And I think as well, perhaps in the second half, our grades ought to get better too. So would that play a part as well in bringing CoP down?

Sandeep Modi

executive
#53

Right, so the CoP we should be looking at for the Q4 exit is roughly 950 to 975.

Pallav Agarwal

analyst
#54

Alright. Understood, sir. Thank you very much.

Sandeep Modi

executive
#55

I appreciate it.

Operator

operator
#56

Thanks. We’ll take our next question from Sumangal Nevatia at Kotak Securities. Go ahead, please.

Sumangal Nevatia

analyst
#57

Yes, thanks for the opportunity. Since this is the first question: regarding our hedging policy, historically we have from time to time hedged and sold some volumes forward. So given today's spike in zinc and silver prices, where do we stand? Are we considering hedging certain volumes? And mainly, could you restate what our strategy is?

Sandeep Modi

executive
#58

Just to make it clear, right now our zinc hedge — or open hedging position — stands at 87 KTPA, at an average price of $2,872. That's where the hedged position sits as of today. And on silver, we've hedged 131 tons at an average price of $37 per tranche. So the strategy stays the same: if prices spike and we see it's better than our internal business plan, then we can hedge some portion accordingly. That gives us balanced margin on the hedged position, which is 10%-20%. The remaining 80% stays as open exposure. So that's something we're thinking about putting the strategy in place for.

Sumangal Nevatia

analyst
#59

Third, is that for the second half of FY 2026?

Sandeep Modi

executive
#60

For FY26, in the second half — that's what I was saying. The open quantity comes to 131 tons of silver, along with 87 KTPA of zinc.

Sumangal Nevatia

analyst
#61

So that's the hedged amount, correct — not the open amount?

Sandeep Modi

executive
#62

That is the open quantity—that is exactly my point.

Sumangal Nevatia

analyst
#63

Alright.

Sandeep Modi

executive
#64

For the second half, we are up. Open refers to the hedged quantity that remains open — still to be opened. Subtract whatever we will produce and -131, and it stays open.

Sumangal Nevatia

analyst
#65

Correct. Got it. Yes, sir. So the second question concerns volumes. Right now, in practice, our capacity stands at roughly 1.18 or 1.28. At what point are we able to reach those volumes? With all our projects now in place, is it possible for us to get there at some point in FY 2027, next year, which would mean high or early double-digit growth in volumes?

Arun Misra

executive
#66

Next year we’ll surely see growth of 1.1 million tons plus. You see, the reason we put up the new Roaster was to create that availability of calcine and let other Roasters go down whenever needed, so there would never be a calcine shortage. But the delayed commissioning of R6 has hurt calcine availability in H1, and that shows in the result. In H2, though, we are projected on the calcine side. We’ve also de-bottlenecked our Dariba cell house by raising current capacity from 200 kiloamps to 210 kiloamps. And this month we’ll do the same thing at Chanderia. Together, that gives us an additional 25 KTPA of production over the earlier base of 1040 or 1080 KT. So altogether, next year we are absolutely positioned correctly to achieve more than 1.1 million tons of metal. We could have achieved it this year too if Roaster 6 commissioning had not been delayed.

Sumangal Nevatia

analyst
#67

Got it, sir. Got it. And just one final question from me. Is anything like our previously planned strategic moves — such as buying Zinc International or separating the business into zinc, lead and silver — still on the table at this point, or over the near to medium term?

Arun Misra

executive
#68

No. Buying Zinc International is completely off the table, since that would amount to a direct attempt at expansion, and on their own they are going to turn into a one million ton player, while we too are working to move from one million tons up to two million tons, so as things stand, we have no additional room to take in any more zinc capacity from anywhere else in the world — that is the first point. Second, regarding the demerger, our view remains that it is the correct process, and we will pursue it wherever it needs to be pursued, because, as you can appreciate at present, with silver prices as raging as they are today, had we been demerged into a zinc, lead, and silver company, the net valuation would have been considerably better than it is now.

Sumangal Nevatia

analyst
#69

Got it, sir. Thanks, and best of luck.

Arun Misra

executive
#70

Thanks.

Operator

operator
#71

Thanks. Our following question comes from Raashi Chopra at Citigroup. Your line is open — go right ahead.

Raashi Chopra

analyst
#72

Thanks. I was hoping you could clarify a couple of the responses you gave. Regarding CapEx, you said the split between the two projects is INR 12,000 crores for one and INR 3,800 crores for the other. The way it lands would be 20% this year, 50% next year, with the remainder after that. Have I got that right?

Sandeep Modi

executive
#73

On the whole, that's accurate.

Raashi Chopra

analyst
#74

Regarding fiscal 2026, you said capital expenditure for growth would be $350 million-$400 million. That figure includes the 20% we're discussing, correct?

Sandeep Modi

executive
#75

Yes.

Raashi Chopra

analyst
#76

And on maintenance CapEx — you mentioned $400 million?

Sandeep Modi

executive
#77

Correct.

Raashi Chopra

analyst
#78

Okay, so regarding that hedged position of 131 for silver, what's the—I didn't catch the price it mentioned—and for the 87 KTPA of zinc, what prices apply? Let's start with that.

Sandeep Modi

executive
#79

Zinc is hedged at $2,872 per ton, and silver is hedged at $37 per tranche.

Raashi Chopra

analyst
#80

And what was the renewable share for this quarter, sorry?

Sandeep Modi

executive
#81

19%.

Raashi Chopra

analyst
#82

So that's the same as what we saw in the first quarter?

Sandeep Modi

executive
#83

Yes. So that figure will go up as wind capacity is added over the course of this quarter.

Raashi Chopra

analyst
#84

And that 70% target you mentioned in the presentation — when does that apply?

Arun Misra

executive
#85

For fiscal 2028 — in FY 2028, that figure reaches 70%.

Raashi Chopra

analyst
#86

And my final question is this: how much domestic coal was there? In this quarter, what share did domestic coal account for?

Sandeep Modi

executive
#87

This quarter came in at 58%, and for the first half as a whole it was roughly 52%.

Raashi Chopra

analyst
#88

Understood. Thanks.

Operator

operator
#89

Thanks. Our next question comes from Pavan Kaware at Nayan M. Vala Securities. Your line is open.

Pavan Kaware

analyst
#90

Hello there, and good afternoon. My question concerns the forward outlook for 2027 and 2028 regarding metal production and zinc metal. Is there any guidance available on that?

Sandeep Modi

executive
#91

Apologies, we weren't able to hear you.

Operator

operator
#92

Mr. Kaware, apologies for cutting you off, sir. Mr. Kaware, we're picking up quite a bit of background noise on your line. Would you mind shifting somewhere quieter and then asking your question?

Pavan Kaware

analyst
#93

Hi there. Can you hear me?

Operator

operator
#94

We can hear you, but there's quite a bit of background noise coming through together with your voice, and we're unable to make out what you're trying to ask.

Pavan Kaware

analyst
#95

Does that make sense at this point? Hello?

Operator

operator
#96

Yes. Go ahead.

Pavan Kaware

analyst
#97

My question was about the outlook for 2027 and 2028. Have we calculated that on the refined metal productions?

Arun Misra

executive
#98

No, no — you're referring to FY 2027 and 2028. We can't provide that outlook at this point. We do our business plan first, and after that we'll put out guidance for next year. At that point, you'll find out.

Pavan Kaware

analyst
#99

Do you have any rough figures you could share regarding manufacturing?

Arun Misra

executive
#100

No, no, no. Like we mentioned, the only thing I’m able to say is that this year we aimed to produce 1.1 million tons. If the Roaster commission hadn’t been delayed, we would definitely have hit that. So that means the Roaster is now commissioned, and next year those figures ought to be reachable. As for what our guidance will be next year, we’ll only be able to tell you next year.

Pavan Kaware

analyst
#101

All right. And when it comes to debottlenecking silver, does refined metal capacity go up at all?

Arun Misra

executive
#102

Roughly 25,000 tons of metal production capacity is involved.

Pavan Kaware

analyst
#103

Is that measured yearly?

Arun Misra

executive
#104

We'll go with annual.

Pavan Kaware

analyst
#105

On an annual basis, and that includes zinc and lead.

Arun Misra

executive
#106

That's just zinc. Debari falls under zinc.

Pavan Kaware

analyst
#107

Thanks. That's all I have to say.

Operator

operator
#108

Thank you. A quick reminder for everyone on the line: please press star and one if you'd like to ask a question. Ladies and gentlemen, since no more questions have come in, I'll now pass the conference to Ms. Jain for her closing remarks. Thank you, and over to you, ma'am.

Raksha Jain

executive
#109

Thanks, Operator, and thanks to all of you for being with us today. Consistent with our dedication to the highest transparency and disclosure standards, full reporting tools can be found on our website. We'd very much welcome any feedback or suggestions you might have that could help us improve our reporting further. If you have any follow-up questions or need more information, please don't hesitate to contact the Investor Relations team. Thank you.

Operator

operator
#110

Much appreciated. Much appreciated, members of the management team. That brings this conference to a close on behalf of Hindustan Zinc. We're grateful that you joined us, and at this point you can disconnect your lines. Much appreciated.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Hindustan Zinc Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Hindustan Zinc Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Hindustan Zinc Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.