Good morning, and welcome to Hut 8's Third Quarter 2026 Financial Results Conference Call. Joining us today are our CEO, Asher Genoot; and our CFO, Sean Glennan. Following the presentation, we will open the line for questions. This event is being recorded and a transcript will be made available on our website. In addition to the press release issued earlier today, our full quarterly report on Form 10-Q is available at hd.com on our EDGAR profile at sec.gov and on our SEDAR profile at sedarplus.ca. Unless otherwise indicated, all figures discussed today are in U.S. dollars. Certain statements made during this call may constitute forward-looking statements within the meaning of applicable securities laws. These statements reflect current expectations and are subject to risks and uncertainties that could cause actual results to differ materially. Certain key risks are detailed in our Form 10-K for the year ended December 31, 2025, and our other continuous disclosure documents. Except as required by law, we assume no obligation to update or revise any forward-looking statements. During the call, management may reference non-GAAP measures such as adjusted EBITDA. A -- we believe these metrics alongside GAAP results provide valuable insight into our performance. Reconciliations of GAAP and non-GAAP results are included in the tables accompanying today's press release available on our website. I'll now turn the call over to Asher.

Asher Genoot

executive
#2

Thank you, Mark, and good morning, everyone. Over the past year, we have contracted 949 megawatts of IT capacity under long-term AI data center leases with our Pasta investment-grade companies, representing approximately $27 billion of contracted revenue, realizing that revenue and the returns that we underwrote against it requires 3 disciplines. First, the quality of the power and the contracts that we originate; second, our execution in delivering what we have contracted and third, our rigor in financing. Those are the 3 principles we outlined for investors in May. And my remarks this morning will address each in term origination, delivery and financing. Sean will then review the results in detail. Before I turn this quarter, I want to step back to the premise behind all 3 measures because it explains why we sequence them in that order. AI is delivered as software, but it is produced by physical infrastructure, power, land, transmission, buildings, cooling, equipment and the people who operate them. The next generation of compute will be constrained not only by chips, but also by that infrastructure. And of everything that infrastructure requires, powers a scarce input. That is why we are a power first company. the input that is hardest to secure is the 1 we secure first. We developed the discipline of building within that constraint in Bitcoin mining, which required us to operate power dense compute to manage cooling and uptime and to procure and build quickly. AI is the largest opportunity we have yet encountered to apply that same discipline. Securing power, however, only earns the right to build, converting it into contracted revenue depends on how efficiently we build, and that is the second part of what defines Hut 8. I'm convinced that the infrastructure behind AI can be built better than it is being built today. faster at a lower cost and without compromising on quality. Many of today's data centers resemble natural blocker programs, remarkable engineering, a complex, expensive slope to deliver. And frankly, this is the mold that Regabatin Beacon Point Phase I follow. This approach makes sense when the buildout is small, but will not work at the multi-gigawatt scale at which I expect honey to build. Our future builds before I start with a different question, what each system must do and how it should be designed and delivered a thinking bills from there with the aim of improving speed and cost efficiency with quality held as a constant, not the variable. We have done this before, Vega, a Vicor mining facility, we designed in-house with direct liquids a chip cooling was built in under 6 months. We believe we can apply the same approach to our future builds, and we believe that our ability to rethink builds to be more cost efficient in shortened delivery times while maintaining quality through innovation will differentiate HUD with customers. With that as context, I will turn to the quarter beginning with origination, which is where the power is secured. For investors origination is a measure of whether we control sufficient pallet on terms that support attractive commercialization opportunities to continue converting our pipeline into leases comparable to those at River Bend and Beacon Points. We originate through 3 channels, and we advanced each throughout the quarter. The first is front of the meter greenfield development. Our pipeline now includes more than 6.4 gigawatts under diligence and under equity. Capacity under exclusivity, the stage at which we have secured a defined path to ownership increased by approximately 1.3 gigawatts during the quarter as existing projects advance and new projects were originated. PL alone does not answer the question investors ask most often about that pipeline, which is how geographically diversified is it? This quarter, we are providing a breakdown of our front-end the meter greenfield pipeline by geography. The largest shares are in MISO, PJM and Sure. Less than 5% is in ERCOT. That distribution reduces our regulatory and price exposure in any single market. It does not, however, diminish the value of our existing Texas interconnect, which we believe has become more valuable as Arcos revised interconnection process has lengthened the time required to secure approvals for new interconnections. The second channel is behind the meter development. which allows us to unlock power and accelerate delivery where traditional grid time lines are constrained and which builds on years of experience developing and operating such projects. We are actively evaluating opportunities across our campuses. Consistent with our disciplined approach, however, we do not include that capacity in our reported development pipeline until a contract is executed. River Bend illustrates that point. Beyond the current phase under construction, we continue to develop the site. We have cleared 184 acres for campus expansion and are advancing site preparation now. So that construction can begin promptly once the next phase commercialize and approvals are secured. The third channel is corporate development in which we acquire powered assets. Our approach here is the 1 that produced Beacon point where we secured the power, underwrote the site on Bitcoin mining as its initial use and applied our greenfield development capabilities to advance the site and convert it into an AI data center campus. This quarter, corporate development yield another opportunity as we entered into a definitive agreement to acquire from affiliates of Poland to energized data center sites in West Texas with up to 230 megawatts of utility capacity upon full energization subject to final power approvals and infrastructure development. Second, delivery. Each lease we sign obligates us to deliver capacity by a contracted date and the lease revenue begins only on delivery. For investors, delivery is, therefore, the measure of whether the capacity we have contracted begins generating rent on the date to which we committed, and it is our central operating priority. Construction at Regabatin Beacon Point Phase 1 remains on track to meet our delivery targets and both projects are funded entirely at the project level. At River Bend, more than 1,200 people are on site. Structural steel, roof decking and building foundations are complete on all 4 data halls. The slab at Data Hall 1 is also complete, and the remaining 3 Data Halls will follow through year-end. Roofing and precast wall panels have also been installed at Data Hall with the remaining halls expected to follow through by mid-December, reducing the exposure of inferior electrical mechanical work to weather-related disruptions. We expect to energize a substation in phases and equipment installation has done in Data Hall 1, starting with Vertiv IT power skids and smart run overhead modulars. At Beacon Point Phase I ground improvements are approximately 95% complete, building foundation work and underground utilities installation are underway. The steel erection is scheduled to begin this month. We have also begun foundation work for the substation. For Beacon Point Phase 2 civil design in surveying are underway. We also amended the Beacon Point Phase 2 lease with our customer, extending its term from 15 to 17 years. The extension serves both parties. For our customer, it secures capacity over a longer horizon, which reflects the durability of demand for power. For Hut 8, it adds 2 years of contracted revenue for lenders to underwrite, which should help offset potentially higher financing costs as we look to finance Phase 2. The amendment applies to Phase 2 only. Phase 1 remains on its existing terms and the construction and financing framework for the campus is unchanged. Delivery also depends on the support of the communities in which we build, which we treat as a precondition of development rather than as an obstacle to be managed. River Bend demonstrates what is required to conserve power first approach into a real project, power, transmission, land, construction partners and community alignment would come together in the right order. That is what more than 300 investors, analysts, media, government stakeholders and community members saw when they visited River Bend last month. I joined Governor, Jeff Landry of Louisiana and leaders from Anthropic, Entergy Louisiana, Broadcom, Ferdman Jacobs to discuss the future of American AI infrastructure, and those discussions reach one conclusion, demand, supply, delivery and policy are inseparable. Sound technical plans matter, but durable products are built transparently in partnerships with the people who live and work nearby. In Louisiana, that partnership has taken specific form. We are investing approximately $60 million in a new water well and nearly 8 miles of water infrastructure. None of which will be used to cool a data center and which will be transferred to the parish at no cost for local taxpayers and can serve more than 4,000 households and 200 local employers. We also made a $10 million payment in Luitaxes, bringing tax revenue to West Bellician Parish 1 year earlier than it otherwise would have arrived, supporting local government, schools and law enforcement including $7,000 stipends for school employees in each of the next 2 school years and payments up to $8,000 per eligible share of office personnel. A beacon Point in Texas. The commitments differ in form, but not imputable. We are funding the electrical upgrades that our campus requires that those costs are not shifted to residential rate payers, and the campus users closed loop pooling design to minimize local water demand. Across both phases, we anticipate approximately 1,900 construction jobs and more than 200 permanent positions supported by partnerships with local educators and workforce organizations. We make these commitments because we believe a successful project must create lasting value, not only for our customers and shareholders, but also for communities that host it. We uphold this philosophy by investing in the infrastructure, workforce and partnerships that allow our projects and the communities around them to grow together. Third, financing. For investors, how we finance our projects is a measure of our ability to limit risk to the parent balance sheet and avoid dilution for existing shareholders. Two of the main questions we've been asked this quarter is directly to that point. How are our current builds progressing? And might we need to issue additional equity to support them? The answers are straightforward. We remain on schedule, and we do not expect to issue additional equity to support River Bend or Beacon Point. River Bend and Beacon Point Phase 1 are funded through completion with investment-grade project bonds of $3.25 billion for River Bend and $4.25 billion for Beacon Point Phase 1, each nonrecourse to Hut 8. We were able to raise investment-grade financing for both projects through a comprehensive approach to risk mitigation. Operating in Bitcoin mining taught us how quickly markets can change. and inflation and interest rate expansion are present realities. We cannot control the market, but we can control we secure in advance in how we contract. We work from first principles to understand what every component must do and what is your cost. At River Bend and Beacon Point Phase 1, all long lead equipment has been ordered and all major contracts have been signed. Locking in the largest components of costs ahead of further market movement. Risk mitigation extends beyond procurement. Our principal Equipment and Construction Partners, Verdan Jacobs are investment-grade counterparties. Comprehensive insurance coverage is in place at both sites, providing an additional layer of protection against covered losses that could affect the projects and in turn bondholders, and the triple net lease structure makes tenants responsible for operating expenses, taxes and insurance, which further supports this framework. A measure of the strength of our financings is that both bonds have traded well in the secondary market. That matters because capital has become scarcer across today's markets and we believe scarcity produces a flight to quality. Investor interest in future issuance remains strong. In a tighter market, we believe contract quality and the flexibility to access multiple debt capital markets gives us a competitive advantage. And as we evaluate financing for future projects, we will start from first principles with a clean slate, taking the lowest cost of capital and the highest free cash flow yield on a risk-adjusted basis. How we originate, how we deliver and how we finance also answers the most direct question investors ask. What will drive the stock. We believe execution is how we create long-term shareholder value. We do not manage to the daily share price, we managed the delivery of Reverend and Beacon Point into the conversion of our pipeline into contracted projects because those are the outcomes within our control. The same long-term focus governs how we allocate capital. Every decision is evaluated against a single criteria, whether it creates long-term shareholder value. Alongside investing in growth, that criteria allows us to opportunistically create shareholder by repurchasing our shares, and we believe the stock trade at a discount to intrinsic value. We have acted on that conviction since last quarter by repurchasing approximately 3.3 million shares for approximately $250 million funded with about 3,100 Bitcoin from our balance sheet. The repurchase met our criterion because we believe our shares do not fully reflect the value of the revenue we have contracted and the power capacity that we control. funding it with Bitcoin rather than with cash, preserve liquidity and continued the reduction in parent level Bitcoin exposure that we described in February. Underneath those measures is a simple proposition, we are builders, and we believe the AI era will award the company that bring power and compute online faster, more cost efficiently and without compromising on quality. That is the company we are building. The revenue we have contracted will be realized the way it was secured by starting with power, underwriting carefully, preserving flexibility and delivering. Those principles govern the 3 measures I have described and those measures are how we expect to be judged in the quarter's end. We believe they are the foundation of an enduring generational business at the intersection of Energy & Technology. With that, I will turn the call over to Sean.

Sean Glennan

executive
#3

Thanks, Asher. The financial story this quarter has 4 main components. First, the operating platform remains resilient. Revenue was $71.1 million for the third quarter compared with $83.5 million in the prior year period, while adjusted EBITDA increased to $33 million from $30.5 million. That result reflects the contribution from additional operating capacity and a disciplined approach to costs. Despite the sale of the Power North portfolio in February, a decline in average revenue per Bitcoin mined and the planned runoff of business are no longer central to our strategy. Second, the GAAP result was heavily affected by the fair value remeasurement of digital assets. We reported net income of $189.5 million of which $131.1 million was attributable to Hut 8. That result included a $413.8 million gain on digital assets, reflecting the increase in the price of Bitcoin during the quarter. Help investors assess operating performance alongside these price movements, which supplement our GAAP results of adjusted EBITDA, a non-GAAP measure and our segment results. Adjusted EBITDA should be considered together with and not a substitute for GAAP net income. Third, we continue to maintain cost discipline even as we scale the company. While we are making major investments to scale them to the company we want to become, we are doing so judiciously. The rigor around spend decisions has not changed since I started 2 years ago when the company was in more of a start-up phase. Compared with the prior year period, G&A, excluding stock-based compensation per megawatt of development pipeline has declined even as our development pipeline has nearly doubled. And last, but arguably most important, the balance sheet and capital position of the company remains strong. We have fully funded 2 construction stage projects. We have ample liquidity to meter obligations until our data centers begin generating cash flow and that liquidity is now further supported by the $1.07 billion revolving credit facility that we closed in September, which provides low-cost, flexible, nondilutive capital. And we have confidence in the availability of capital for strong projects underpinned by robust contracts and thoughtful risk mitigation. Let me walk through the operating business. Compute revenue was $68.4 million in the third quarter compared with $70 million in the prior year period. Headline revenue was broadly stable because the decline in average revenue per Bitcoin mine was largely offset by an increase in Bitcoin Mine, reflecting additional operating capacity at Vega and the reenergization of Thrum Hiller. That result demonstrates the enterprise's ability to scale revenue across a range of external environments. Compute cost of revenue increased to $28 million from $22 million primarily because we were operating more capacity and incurring the associated electricity costs. The increase track the increase in production, not a deterioration in operating efficiency. The important point is that we are producing more Bitcoin from a larger operating footprint, again, demonstrating the ability to scale in a cost-conscious manner. AI cloud revenue also increased during the quarter as new customer contracts came online. That growth was partially offset by the sale of the traditional cloud business in August. Power. Power revenue was $1.3 million in the third quarter compared with $8.4 million in the prior year period. The decline was primarily the result of the sale of the Far North portfolio in February. It is therefore a portfolio composition effect, not a deterioration in the remaining our business. which generates revenue primarily from managed services contracts, digital infrastructure. Digital Infrastructure revenue was $1.4 million in the third quarter compared with $5.1 million in the prior year period. The decline primarily reflects the termination of the Vega colocation agreement after American Bitcoin exercised its purchase option for the miners of website, together with the customer churn in the legacy GPU infrastructure business. The current digital infrastructure results do not yet reflect a contracted lease revenue from River Bend and Beacon Point. That revenue begins when the relevant capacity is delivered. The financial model is therefore moving through an intentional transition. The legacy revenue base is no longer the main growth driver. While the larger contracted infrastructure revenues remain tied to delivery milestones. Adjusted EBITDA was $33 million compared with $30.5 million in the prior year period. We use this measure to evaluate operating performance after excluding the effect of fair value remeasurement of digital assets and other onetime or noncash items. As always, adjusted EBITDA should be considered alongside GAAP results. not in place of them. Reported general and administrative expense was $99.6 million compared with $25.9 million in the prior year period. approximately $64.7 million of this quarter's G&A was stock-based compensation, including the effect of onetime long-term incentive awards. The quarter also included professional fees and approximately $6.2 million of incremental salaries and benefits as we added people to support energy origination, corporate development and other growth functions. Excluding noncash costs, the cash G&A was $34.8 million, which compares with $24.8 million last quarter and $19.5 million from a year ago. We do not view all of that spending as recurring corporate overhead. A meaningful portion reflects the cost of building the organization required to originate, finance, construct and operate multiple large campuses in parallel. At the same time, the cash component is real, and we are holding those investments to a clear standard. They must support one or more of the following outcomes over time, more high-quality power origination, faster project conversion a lower cost of capital, better execution or stronger operating leverage. The balance sheet requires an important distinction between corporate liquidity and project restricted capital. At September 30, 2023, we had approximately $156.9 million of cash, $3.6 billion of restricted cash and cash represents, and $2.8 billion of restricted short-term investments. The restricted balances are principally proceed from the River Bend and Beacon Point financings. Eldon project accounts for construction, debt service reserves and other specified project purposes. They are not excess corporate cash. Hut 8 also has about 1,361 unencumbered Bitcoin on the balance sheet as of November 1. The company had approximately $7.6 billion of consolidated loans, not cable and other financial liabilities. Approximately $7.5 billion of that amount relates to the River Bend and Beacon Point project financing. Those obligations to a project subsidiaries are secured by the applicable project assets and accounts and our nonrecourse to Hut 8's parent company. Each project is designed to service its own debt from its own contracted lease cash flows. The quarter also included $105.5 million of interest expense and $51.8 million of interest income. The interest expense reflects the construction period carried on the River Bend and Beacon Point financings. The interest income was generated by investing unused project pros and restricted short-term investments to partially offset that carry. We accepted that construction period interest cost because the projects are fully funded upfront. The parent level financing architecture is separate and quite simple. In September, we added a $1.07 billion senior secured revolving credit facility to support corporate liquidity, development need and letters of credit. No borrowings were outstanding under that facility as of September 30, 2026. This facility gives us committed capacity without requiring us to draw debt before we need it. We also simplified the parent capital structure during the year. The CO2 note converted into equity, a corn-based facility was refinanced with the Bitcoin collateralized Dalkon x term loan at a lower coupon and the remaining TCRC secured promissory note was repaid in October. We are also planning to retire a Falcone term loan edible to maturity in April 2027. The objective is straightforward, maintain parent level flexibility as financing to the asset that generates the cash flow and avoid using corporate equity where project-level capital is available on better terms. During the quarter, we sold approximately 954 Bitcoin or $74.8 million and used those proceeds to repurchase 953,802 shares for $74.7 million. Subsequent to quarter end, we repurchased additional shares under the $250 million program. In total, we repurchased approximately 3.3 million shares for approximately $250 million funded with approximately 3,100 Bitcoin. Those repurchases converted a portion of the strategic declines into equity head of price, we believe does not reflect the contracted revenue and power capacity controlled by the company. They also continue the reduction of the parent level exposure that we have described previously. Our Board has also authorized an increase in our share repurchase program from $250 million to $1 billion. We view this as a long-term program that gives us the flexibility to act when opportunities arise over the coming years. We will be patient and judicious in how we deploy it, that we maintain liquidity to run our business and pursue opportunistic growth. Stepping back and these should evaluate Hut 8 through 3 layers. The first is the solid footing of the current operating platform. For the quarter demonstrated increased bitcoin production, a growing AI cloud contribution and adjusted EBITDA above the prior year period despite lower revenue. The second is the contracted infrastructure platform, where River Bend and Beacon Point are being funded and delivered through project-level structures tied to long-duration customer commitments. The third is the development platform where we are advancing however, opportunities while preserving flexibility on the application, the customer and the financing structure. Our financial objective is not to maximize headline growth at any cost. It is to convert scarce power into financeable, contracted infrastructure while protecting parent level liquidity and limiting unnecessary dilution. If we execute against that standard, the financial profile should evolve from a business with Bitcoin driven volatility and construction period carry toward one with a larger base of contracted infrastructure cash flows.

Asher Genoot

executive
#4

Before we transition to Q&A, let me address what is likely to be the first question. The outcome of the governor's race in Texas and its implications for Beacon Point. We reset the election outcome and the support -- and support the governor elect in a hostess called for legislative guardrails. We also expect Texas to remain a business-friendly state and recognize the benefits that data centers bring to global communities through tax revenue and jobs. As we discussed earlier in the context of Beacon Point and River Bend, our focus is on building responsibly with local communities in mind, a commitment that we believe aligns with Governor hoses objectives. We do not believe the results change the outlook for Beacon Point, which as a late-stage project is well positioned. For Beacon Point Phase 1, our baseload designation remains subject to Governor Abbott audit. We believe we are well placed in that process and anticipate an unconditional classification on December 17. And which will provide a clear path to energizing the full gigawatt at Beacon Point with 700 megawatts expected in the first quarter of 2027. With that, happy to take questions.

Operator

operator
#5

[Operator Instructions] Your first question comes from the line of Ryan Gravett with UBS.

Ryan Gravett

analyst
#6

Ash, I did want to just follow up on your closing remarks there, just given the election outcome last night. Anything you can share in terms of various other permits required for both Phase 1 and Phase 2 at Beacon Point. And then maybe 1 for -- anything you can share in terms of expected timing for project financing at Phase II of Beacon Point? And if the election outcome changes that time line at all?

Asher Genoot

executive
#7

Thanks for the question, Ryan. In regards to the build, we're primarily focused on the December 17 time line. When we think about TCQ, when any permissive diesel generators, there are paths to be able to design around that use the best system as an alternative back source. And so those are the kind of the primary focuses for us as we continue to progress and develop the project. Sean, I'll pass it to you.

Sean Glennan

executive
#8

Yes. So we -- the sort of timing that's right in front of us doesn't really change the -- we expect to get back from the audit results on December 10th and then have those be finalized on December 17th. And those remove largely the sort of remaining items ahead of us to get going on the financing for Beacon Point 2. There are a lot of different ways that we can see to finance that. Obviously, we've addressed the -- and tapped the investment-grade bond market. And we think there are a number of other avenues around that exists too. So we feel really confident about the ability to get that done. In our minds, the path is the same as it was before. And so we look forward to executing on that.

Operator

operator
#9

Your next question comes from the line of Eric Luebchow with Wells Fargo.

Eric Luebchow

analyst
#10

I'm curious, given everything going on in terms of higher labor costs, more upfront investment in the site in terms of utility deposits. What are you seeing in terms of your build cost, not just for Beacon Point and River Bend. But as you look at your power pipeline today, are you seeing build costs move into the low to mid-teens on a dollar per critical load megawatt basis? And do you think that you have enough pricing power to kind of maintain or even improve your development yields as you build out the next phase of your pipeline?

Asher Genoot

executive
#11

Appreciate the question, Eric. I'll answer that in 3 parts. Part 1 is origination. Part 2 is the development in EPC and Part 3 is the commercialization and lease rates. For Part 1, in regards to origination, you're right, a lot of utilities now ask for more upfront collateral kayak payments to make sure that the infrastructure upgrades or energy supply that's committed to doesn't affect rate payers. And we've been supportive of that since day 1, and that's the same structure that we've had at River Bend and Beacon Point in paying for those QIAGupgrades and any collateral that's necessary. And so as we continue to develop our approach remains similar, which is we don't put large development capital at risk in the pursuit of commercialization. We stay disciplined in the origination process. which makes it difficult, more difficult to originate, but we found opportunities where we are able to do so, able to bring customers along for the process with us and be able to continue to develop the sites that have -- that we have conviction in. As our balance sheet continues to grow, we obviously will be working on more sites across our pipeline. As you see this quarter, we had another 1,300 megawatts of sites go from energy under diligence to energy under exclusivity, which means we're diving deeper into those sites. We're spending more resources in developing those projects. And so we really think about it as a percentage of overall development capital as we continue to scale that we can increase to develop those sites. But we are spending, call it, hundreds of thousands or single-digit millions up front in these developments and not tens of millions or hundreds of millions of dollars, really when the collateral requirements come, we're deeply engaged with the end user during those moments in time. In regards to everyone has heard labor rates have gone up, you have supply chain rates that have changed. And as we've continued to build over the larger of a decade here, the focus has been how can we control our destiny. Well, we can't control our macro conditions of overall capital markets of overall cost of labor equipment, et cetera. What we can control is how do we design the infrastructure to be able to drive additional efficiency to try to offset those changes and those increases that you had mentioned. And so if we can ruthlessly focus on learning from the build that we have today, designing from first principles driving efficiencies in the design, which ultimately drive efficiencies in the supply chain and equipment you need to purchase, which ultimately drives efficiencies in the construction and the amount of hours we need to construct a data center those are things that are in our control and that we have conviction and confidence that we continue to build towards. So that is our offset against these macro conditions that you mentioned, and I chatted about earlier in my prepared remarks on how want to build a scalable, repeatable model like the Raptor photos of the Tesla engine that I'm sure many people have seen during Iteration 1, 2 and 3 are SpaceX versus kind of a bespoke build every single time that is expensive and costly and time intensive. And then the last 1 is in terms of lease rates. We've always approached the market from a perspective of signing leases that we believe are fair and kind of middle of the fairway market from a lease rate perspective and our shareholders and our investors have been happy with the structuring and the returns on those deals. So the way that we think about it is if market costs on average across the industry go up, therefore, lease rates would move in proportionately with that because many folks work on a more yield on cost basis. And so we'll charge market-based rents, meanwhile, focus on driving ruthless efficiency within our execution EPC stack to construct and hold costs on construction, which could, in turn, actually increase the yield on products that we're developing, if revenues go up and we're able to maintain costs.

Operator

operator
#12

Your next question comes from the line of Bryan Baratian with ROTH Capital Partners.

Bryan Baratian

analyst
#13

I have to 2. One is as we -- in the face of the election and looking to what I think is one of the most interesting things is River Bend expansion, where you have a gap of IT capacity to expand there. How can we think about what the structure looks like with regard to ultimate counter party. I know the River Bend site Day, the Head of Computed Anthropic was there, and it all seemed very positive. But would we expect to see similar to your other leases the same level of investment-grade equity support that was both across River Bend and Beacon Point with different tenants? Or like how are you thinking about structuring that?

Asher Genoot

executive
#14

Is there a second one? Or you want me to...

Bryan Baratian

analyst
#15

Yes, you can start with the first, and then I'll do the second, it's separate.

Asher Genoot

executive
#16

Okay. Sounds great. We're very excited for and we have been for quite some time in her so with the market. There's been a good amount of work that has been done believe that there's actually more than a gigawatt of gas available on the pipelines that run through the property and have been working towards being able to actualize and realize the continued expansion of that campus. When we look at the commercialization, obviously, I can't speak to any deals that we haven't announced yet. But we continue to stay focused on the credit quality of our -- and offtake relative to the investment in CapEx and the capital we ultimately need to raise we're pretty open. I was on a call with a non-AI lab, non-investment-grade counterparty yesterday, someone we admire a lot in the business that they've created, we were open. We said, look, it's very hard for us to tell our shareholders and our Board to go and build infrastructure for folks that don't have the credit that supports the ability to bring on the financing that we brought on historically to be able to build and execute these projects at scale. And so I don't want to speak to any deals that aren't announced yet, Bryan, but overall, maintaining balance sheet, maintaining credit profile of our cash flows continues to be a core focus of the business and 1 that shareholders have asked us for as well.

Bryan Baratian

analyst
#17

Awesome. And the next 1 is, as we think about the existing footprint of opportunities that you have, I know American Bitcoin is running north of 400 megawatts of capacity. I guess in the face of the election that happened today, -- how are you? Or if you can provide any color on thinking about potential brownfield opportunities as it relates to the existing footprint there? Or is the focus just going to continue being on greenfield development?

Asher Genoot

executive
#18

When you look at our pipeline that we've announced the development pipeline is almost 8 gigawatts with a total of about 8.6 gigawatts in terms of our overall pipeline overview. That is 1 out of 4 buckets of the ability to commercialize and realize additional TCV. That bucket is our greenfield origination bucket. The second 1 we have is the behind-the-meter generation bucket, which I chatted about more so in your first question in River Bend and other sites that we have. The third 1 is M&A through our corporate development team. There continues to be very interesting opportunities and growing opportunities in a world where capital becomes more constrained and flows to proven operators. And then the fourth is brownfield opportunities as well on existing campuses. So we continue to look at all 4 of those, continue to originate across all 4 which gives us a strong conviction that outside of the publicly disclosed pipeline with 3 other pipelines with dedicated teams looking at opportunities there.

Operator

operator
#19

Your next question comes from the line of George Sutton with Craig-Hallum.

George Sutton

analyst
#20

Asher, I found it interning that your energy capacity under diligence came down, but your capacity under exclusivity went up. Can you just give us a sense of -- that just sounds like a more focused way to go to market. Is that the way to read that?

Asher Genoot

executive
#21

That's exactly right. The way to think about our pipeline, it's a funnel. You start top of funnel more wide. And as you get deeper and deeper in more resources get allocated more time gets committed to sites. We closing the aperture. And so at every stage, the requirements get higher and higher as we continue developing those sites. And so we have kind of clear guardrails before projects pass from 1 stage to another, and we dedicated additional resources to it. So you see a transition from capacity and the diligence exclusivity through quarter-over-quarter.

George Sutton

analyst
#22

Just 1 quick question on -- when we watched you bill Vega. That was just simply a better mousetrap at the time really shortening delivery times and lowering costs. When you look at the application of these kinds of principles to the AI development. Can you just give us a sense of how significant can those deltas be in your view and maybe looking out a couple of years?

Asher Genoot

executive
#23

Very significant we've done more than a couple of hours in recent months at Vega sharing our design lost in abilities. It's actually pretty interesting because before we started building a River Bend and Beacon Point, we had self-engineered designed a lot of our own infrastructure in GC all of it. So Vega that campus you not only see the first principle of design pathology, but you see the components in which we designed and contract manufactured everything from tight skids to the PDU, the switch gears and so forth. As we enter the AI space, the big thing that we were building was credibility for end-user tenants to trust that we can build this infrastructure stack. So we hired some of the largest GC equipment suppliers in the world to help build that credibility and help execute. As we've executed for these end users, we've built that credibility. And in those discussions, we started talking about our origination where we came from the capabilities that we really haven't been able to tap into on these projects because we haven't been able to use first principle, it's design from the ground up how this infrastructure stack would work. And so opened a slew of conversations as people think about this capacity as people think about this capacity on earth and space, how do you drive more efficiency, more speed, and so there is a next chapter there, George, that I alluded to in my prepared remarks, but we believe the skill sets and the philosophy that we built in a world where we were able to build infrastructure without constraints will be coming to light as well.

Operator

operator
#24

Next question comes from the line of Ben Sommers with BTIG.

Benjamin Sommers

analyst
#25

I wanted to just ask a bit about the capacity that you guys moved under exclusivity, says that you're looking across multiple regions there. So anything you want to highlight in particular regions of interest as we expand the power portfolio?

Asher Genoot

executive
#26

Yes. So when you look at the overall pipeline, 1 big asset we've received from investors was the understanding the pipeline and the makeup of that pipeline, we share the megawatt numbers, but we didn't share how many sites those were. We didn't share what regions they were kind of made up of. And so as you look through the disclosure this quarter, we shared kind of the ag size per site. We also shared the makeup of what ISO those sites are. And I think for most people that will see that we're very diversified the thing that causes that diversification is we actually have teams dedicated to different regions to specialize in those regions and to dive deep within them as well. As we continue to scale, we have our greenfield origination team. We have our corporate development team. And so we're looking at projects across the board. And as we think through the election cycle yesterday as well, diversification, I think, is increasingly important to be able to navigate through any policy or market volatility that may come up, and we feel confident that, that diversification today.

Operator

operator
#27

Next question comes from the line of John Todaro with Needham & Company.

John Todaro

analyst
#28

And congrats on a quarter down here. I guess just going back to Texas and the election in your comments around ERCOT in the December approval schedule. Just wondering if you could frame up the confidence in that Maimi would be -- maybe it gets pushed out and you get new directives from a governor but you guys are obviously closer in Texas and with those regulators. So just wondering on the framing of ERCOT confidence for the December approvals.

Asher Genoot

executive
#29

Going into the elections, we spoke to a lot of our consultants and lobbyists in regards to the different outcomes of the election how is effective. I think the thing that is really important is from day 1, we've focus on building responsibly. And so even when the audit process came out, we were confident there because we had already answered the questions from the PUC that came out that were voluntary. Similarly here, we believe the mindset is not don't build net new investments into the state, but more so, how do we build responsibly. And so based on the current progress and being a very mature project that's financed, and the ways in which we're building, we feel confident in working with the governor elect and anything that she needs in terms of continuing to progress and invest into the state.

Operator

operator
#30

Your next question comes from the line of Patrick Moley with Piper Sandler.

Patrick Moley

analyst
#31

So I just had one, Asher, you said that your -- you felt the shares didn't fully reflect contracted revenue and controlled power. So could you maybe just share how you frame intrinsic value internally? Is that an NOI multiple? Is it some of the parts or something else? And then at what point do you think you could look to fund repurchases with cash or the revolver rather than Bitcoin given that the stack has -- I think it sits a little under $700 million now.

Asher Genoot

executive
#32

Thanks for the question, Patrick. So it is really a triangulation on intrinsic value because many people look at the company and value it differently. So the first methodology is we look at the sum of the parts. -- what are the 2, 3 contracts that we've announced across the 2 projects. So that's River Bend, Beacon Point 1, Beacon Point 2. What is both the net present value of those contracts are doing but also how do we think about the tap rates in different market scenarios that we'll be able to sell those products and what they should be trading at. So that's existing projects. Then we have conviction over the funnels that we have, whether that be the greenfield funnel that we disclosed publicly, the behind the meter funnel, the corporate development funnel, the new opportunities we're looking at in the brownfield funnel as well. And so that creates the kind of growth of where we believe the company can go and we apply a discount factor to different products at different stages. And so if we look at -- I mean, where we're trading today, we're not even trading at the value of all 3 agreements, needless to say, even 2 of our contracts. And so we believe that we're trading even -- I mean, today, even more so compared to when we were in the 70s, a discount to the value of the existing agreements if they just come online and start operating on these triple-net structures. Then we have all the growth that we have in plan and put aside gigawatts that we have in our pipeline nearing 10 gigawatts of opportunities even for to execute another 1 or 2 sites that would increase the value of the company substantially. And so that's how we've thought about intrinsic value of the company. Now as we think about kind of what stage we're at in the market and how do we think about shareholder buybacks. The market has obviously had some negativity over the recent weeks. And so even though we may be trading under intrinsic value, we are focused now to make sure that we maintain capital preservation and optionality because there might be interesting buying opportunities that never came up before because things were too expensive. And so we don't plan to continue to buy aggressively as we want to reserve that cash. In our revolver, we also don't plan to use a revolver share buybacks. Really, we thought it was a really nice way to respond to investors over the last 2 years, which the main question we had around balance sheet was how long do you plan on holding Bitcoin for? You're an AI company now you don't get value for your Bitcoin at all. Why to hold on the balance sheet. And as we looked at where the markets were relative to our share price in Bitcoin price, frankly, we had a lot more conviction in the depreciation of our stock relative to where Bitcoin Price was as well. And so we swapped exposure from Bitcoin to Hut 8 shares and initiated those buybacks.

Operator

operator
#33

Your next question comes from the line of Logan Hannan with Northland Capital Markets.

Unknown Analyst

analyst
#34

Just 1 from us today. Can you provide some additional color around the new 230 megawatts acquired in West Texas in regard to how you're thinking about that opportunity? And maybe clarify where that site sits in Bath and the remaining permits and approvals needed there?

Asher Genoot

executive
#35

Happy to do so. So we were part of a bankruptcy. It was kind of a day job in 2022. We were part of many bankruptcies where we acquired assets during the downturn in the crypto market and we were able to acquire many infrastructure projects, whether that be full acquisitions, taking on managed services agreements or being planned for as to spin out new companies like Ionic. And so it was a very informative journey in our lives and when we were part of this bankruptcy auction, it was a little bit of a day job who back then, we grew almost 10x during that period of time as a company. And so building during market downturns, we see as really interesting opportunities to grow because things are really cheap. It's never as ideal to build when things are expensive. It's always much more exciting to build at a lower cost basis. And so I think this was the first opportunity in the market that allowed for that. We've been patient. We felt like at some point, the opportunities like this would come up and 1 of them did come up. So we pursue that opportunity. That site is located -- those 2 sites are located within driving distance of our Salt Creek campus in West Texas. You have sites there in power for the bigger mining sites that were there that are energized right now that are energized, they don't have miners there that were hashing because through the bankruptcy, those hosting clients left. And so we visited those sites last week, and we are working through the closing conditions now and look to close by end of the year.

Operator

operator
#36

Your next question comes from the line of Richard Choe with JPMorgan.

Richard Choe

analyst
#37

I just wanted to ask, like, as you've gone through this deal with a leading AI company, how is the change orders and the engineering change? And how has Hut kind of been able to maximize your ability to address those needs because I think the ability to build these large-scale AI data centers is underappreciated. I'm just wondering the challenges that you've been faced with and how you've handled them?

Asher Genoot

executive
#38

I appreciate the question, Richard. I'll answer that question from 2 mindsets. Current status quo of the products we're building and net new approach towards building that I've talked about a bit on this Q&A in the prepared remarks. And I'll go through a little bit of a kind of flow chart of the different areas in which you move through them. So the first thing is a change order comes in. And that change order may be driven by insurance need, be driven by customer needs, whatever it may be. And if you look at the say, like, River Bend, there are a lot of counterparties involved, right? Our ultimate -- our tenant is fluid stack then you have entropic as the end user. You have Broadcom and Google, who are part of kind of the credit profile. We have Jacobs as RGC. There's subcontractors Verde. So there's a lot of parties in the mix in here. So any change order kind of have to run through the system and through all of these various parties in many instances. And so the first question is, when a change order comes in, is that a change order that is necessary or not is the first question, right? So there's a discussion around what is the ultimate thing that is trying to be solved for? And is this the best way to solve for it or not? The easy thing is say, okay, you gave me a tenant change order -- this is the time the schedule impact that we've received from Jacobs, here you go. Thank you and want to pay it or not. We think that starts on a very big creep situation where things creep up because you just take it for gossip. And so we start with kind of challenging the first principle, working together across all of the partners and saying, what is the ultimate that we're solving for? And is there a more efficient way to do it without impacting scheduling costs. because ultimately, scheduling costs, if we didn't do that, just get passed through to the tenant, but we want to drive infrastructure coming online as quickly as possible. So then if we get to a place where a change order is necessary, whether it be change in requirements, change design, whatever maybe that causes that, then the question is, what can we do to be able to minimize the impact of that change order? And once you get to that final kind of answer, everyone's aligned on this is the changeover that's necessary and this is the impact that it has, then there's kind of a slew of questions that arise. The contracts currently have it so change orders need to be paid back in cash, reimbursement cash the impact applies to the lease kind of peruse whatever the impact is and you get a fee on top of that for managing the process. There's obviously increasing questions from end users, which is, hey, can you rentalize this rather than it being just a CapEx reimbursement that we pay for, can you rentalize this or not? So I think when you think about that, there's really kind of multiple ways saying about that. One is there ample ability within the budget to be able to rentalize it, that is within the financing guardrails that we have built forwards and the continues that we've put in place of. So the great, you get more yield on the capital stack that you have. The second is if that doesn't exist, can you use external capital or additional kind of funding in order to do so and we've seen that in other parts of the market as well. And if you look at it from an individual investment, depending on what kind of yield on cost has agreed to on the rentalization it could be really interesting depending on your balance sheet position, your willingness to take on that return on investment. Obviously, right now, we're investing into these projects and have pretty good structures, LTCs and so forth. And so that bar is pretty high. But overall, that's how we would think about in bucket 1, which is kind of the current regime with many counterparties and really these bespoke unique solutions. And there's a lot of engineers involved in people have different opinions and kind of drive and that causes design changes. The second bucket is going back to kind of first principles, Vega and so forth, which is what is the thing that we're trying to solve which is bring on reliable compute at speed and at scale. And so there is a second kind of camp in which we've been having a lot of discussions around, which is -- can we get a line from a leadership perspective within Hut 8 or tenant end users, et cetera, that we align on the thing that we need to build. And if we're able to build it really quickly, we don't allow for that many changes along the way because those are the things that really slow down in Hill project. And in that scenario, I mean, you're building much more like a SpaceX where you're building speed, you don't have as many cooks in the kitchen making decisions and you have kind of a set thing that everyone is aligned on upfront and then you sprint at getting that infrastructure stack online. And so Richard, I hope that was helpful. I'm walking through kind of like status quo of the industry? And then how do you actually bring those in, so then you're not on call talking about kind of those impacts? And then it requires a certain type of partner philosophy and conviction and confidence in the ability to build the first principles.

Richard Choe

analyst
#39

That's great. And honestly, I think the problem is people don't realize how this is a problem at scale that you need to engineer for and everyone just thinks it's easy to build, and it shows the level of detail that is needed to deliver this amount of capacity at scale.

Asher Genoot

executive
#40

I'll give you an example. If we go a little bit more granular, we had a request to change some of the lineups because there was a different chipset in design that was going in. And at first, when we kind of asked for those requests. -- the thing that came back was the impact on schedule and costs that we believe was too high. And so we really go deep with our equipment vendors and GCs. We said, what is driving this? Because if everything is passed through as a developer, we can just pass it through the end user and say, this is -- you asked me for a change order, this is what we got back and this is a change. But as we think about like the importance is trying to bring on compute quickly, and we can't do this across all the board, but there we -- the big reason was having to go and change basically the cable trade that have to pull more cable across the facility in the short months we're able to get them into the actual TPUs. And so we looked at it, we said, okay, why do we have to actually increase the size? What did you go reengineer all of those skis, why do we have to increase the sizing? Is there a way to do that in the field. So we're able to save on schedule and cost. And we're able to reduce that cost impact by over 90% by just challenging and focusing on how do we engineer this in a better way. And so Richard, many of those situations come across alongside large builds and being able to navigate and manage through those with your end users and a diverse is critical.

Operator

operator
#41

Your next question comes from the line of Chris Brendler with Rosenblat Securities.

Christopher Brendler

analyst
#42

I just wanted to see if there was -- any way to think about Louisiana versus Texas, given the election results. No change with the governor in Louisiana. I know that it seems like a very supportive community when we were down there last month. But how should we think about your sort of future expansion plans in relation to the election results?

Asher Genoot

executive
#43

For the folks that had the opportunity to come to our River Bend first-look ceremony, the governor was there, the local community was there. We're very proud of the relationships that we've built and the support that we've garnered throughout the state, and the adoption we've had in Hoda's ability to build responsibly. And so we're big fans of Louisiana. We were before people even focus and looked at Louisiana, we were left out of rooms 2, 3 years ago when we talked about Louisiana. There's a lot more focus today, but we continue to double down and focus on the state and are very proud of the work that we've done and are excited to continue to invest in continued growth in the state as well.

Christopher Brendler

analyst
#44

And then just a quick follow-up on the sort of buyback/capital needs question. free understand the balancing act there, but how do you view the current bitcoin balance in relation to the cash needs? And it just feels like not quite the right time to me to be sort of leading into a buyback. So -- just love a little more color on how thinking about your cash vision over the near term given market conditions.

Asher Genoot

executive
#45

Really appreciate the question. I'll start with the buyback itself and talk about our liquidity position. So in regards to the buyback, we've increased the buyback not necessarily to buy immediately, but to hold that optionality when we first announced a $250 million buyback that was almost 2 years ago or so at this point. And we really only initiated that in the recent quarter. And so we just sat on that opportunity. So similarly here, expanding the buyback is less around we want to go buy billion shares immediately. As I mentioned, kind of liquidity and being able to invest in opportunistic moments is critically important and especially in these market conditions. So we don't expect to go in immediately go buy shares off the back of this increase, but rather just leave it on the shelf as an additional tool that we have. our overall liquidity, if we think about on the parent level and across the projects, is over $7.7 billion, and that's across our Bitcoin, the cash we have, the restricted cash we have on the project level that finance those projects, and the revolver that we put in place as well in the availability along that revolver. So we are excited and confident with that access to that capital that we have on our balance sheet and our bank accounts. We also have 0 recourse debt at this point on our balance sheet as well. And so the increase of the share buyback is to have on the shelf and not to implement immediately because we believe that cash will be king as we navigate through this current volatility.

Operator

operator
#46

Your next question comes from the line of Nick Giles with B. Riley Securities.

Nick Giles

analyst
#47

Maybe just a question for Sean. Curious on how the way you're approaching structuring any future debt deals has evolved since your last raiser. Can you just give us a sense for some of the alternatives you're exploring or any kind of features of a debt offering that you might be considering today that weren't as logical, say, 6 months ago?

Sean Glennan

executive
#48

Yes. Thanks, Nick. Appreciate the question. So look, I don't think we actually view how we approach financing any differently from the way we did the last 2. We start with a clean slate every single time. We say, what is the asset we have, what are its attributes and what do we think is the financing that it deserves. We obviously also take a look at the market environment, how are different markets performing, where is their most depth of capital where do we see the most liquidity and best pricing. And then we also think about what's going to increase the free cash flow yield of these projects on a risk-adjusted basis as we talked about in the prepared remarks. So I don't think the approach actually changes at all. Looks like everything we do at the company from a first principle perspective. We have been preparing for the financing for Beacon Point 2, which I think is kind of what you're alluding to for a while. And we have, I think, really great solutions that we're going to bring to bear. Some of those might involve things we've done before, but they don't necessarily but we've been working pretty tirelessly to make sure that we have a great path. I think we've got a lot of kudos for the prior financing we've done, and we're not resting on our laurels. Like we have a very, I think, clear path on what we want to do, how we want to finance and that is going to -- a couple of things aren't going to change. One, recourse to the parent. And two, we're going to try to minimize as much refinancing risk as we can. So again, approach doesn't change. I think some of the instruments and tools we use might, but we'll keep that for the day when we finally -- we do announce our financings because we don't want to obviously fall on any transactions.

Operator

operator
#49

Your next question comes from the line of Dylan Heslin with Lucid Capital Markets.

Unknown Analyst

analyst
#50

On the Beacon Point Phase 2 lease amendment from 15 years to 17 years. Could you just provide a bit more color on how you're looking at that? Like it seems like you mentioned higher financing cost. Is that an interest rate look through? Or is that a potential combination of like both the flowing into a higher bond stuff that you need and less interest rates? And does that still mean -- like that to your amendment still doesn't eat into any of the extensions, correct?

Asher Genoot

executive
#51

That's right. That's exactly right. It doesn't lead into any of its extensions and really it was a holistic discussion over the site. And I think there's a big question that folks have asked, which is if there are changes in market conditions, how does that -- how do the tenants respond to that? And at the end of the day, the data center costs are still relatively small to the overall compute economics and the value of those economics. And so for us, I think this is a signal and a sign that whether it be through tenure rates, et cetera, that tenants understand market conditions and are willing to support to make sure infrastructure gets built.

Operator

operator
#52

Your next question comes from the line of Brett Knoblauch with Cantor Fitzgerald.

Brett Knoblauch

analyst
#53

I just want to hit on Texas one more time. Obviously, kind of the outcome we were expecting. When we read through maybe the incoming governor stands on data centers. It doesn't feel like you'd actually like super against them. It's not a hard line, no data centers. It seems like she is in line with the rest of the country and once kind of center operators that pay for grid infrastructure, order infrastructure to save rate payers, local communities to have kind of a say in what's happening. How different do you view the Texas landscape today versus yesterday? Is it more of the same. Should we assume that most tenants now are going to be looking outside of Texas. Just any additional color would be helpful. Really appreciate it.

Asher Genoot

executive
#54

I agree with you, Brett. We believe that this infrastructure is an American initiative, it is not right or left. And which over side you're on, making sure that citizens don't get impacted in their day-to-day lives in terms of their energy, their water, their status quo of their lifestyle is critical. And the way that we've been building has been in that -- with that mindset and that approach, right? If you look across the states in our development pipeline, I mean, there are states before last night that had Democratic leaders within those states, and we've continued to explore and continue to push forward on those developments of those projects because we believe we have a program that's focused on building responsibly. And so as a result, in Texas, we don't actually think this changes much of what the governor elect is looking to do because we're very supportive to make sure that citizens are protected while America is building this critical infrastructure. And so we're excited to work alongside her and her administration to make sure that Texas can lead the front as well in terms of building the infrastructure and having these investments going to the state responsibly. So my perspective is similar to your spread, and we continue to focus on that foundation regardless of people have asked for it or not.

Operator

operator
#55

That concludes our question-and-answer session. I will now turn the call back to Asher Genoot for closing remarks.

Asher Genoot

executive
#56

As we have built this business, we've always understood that periods of rapid infrastructure growth come with volatility. And there will inevitably be peaks and troughs driven by both broader macroeconomic conditions, but also industry dynamics. And what has always mattered to us is building a business that cannot only withstand these cycles, but also continues to grow and execute through them. And that is why we've been so deliberate in strengthening our balance sheet structuring our business thoughtfully and building a foundation design for long-term success. So as I shared last quarter, our excitement and conviction in the business we are building remains as strong as ever. We know there will be challenges along the way, but we're confident in our ability to navigate through them, overcome them and emerge stronger. And I reminded our team in our last town hall with Warren Buffett's famous observation that the market is a voting machine in the short term and a weighing machine in the long term. We can't control short-term market conditions, but we can control how we execute, how we allocate capital and how we build this company. And our focus remains on what has always mattered most, executing on our commitments delivering for our customers and building a business that can compound value through every market cycle. We believe the opportunity ahead of us is extraordinary, and we remain as committed as ever to realizing it. Thank you all for being with us today.

Operator

operator
#57

Ladies and gentlemen, that concludes today's call. Thank you all for joining. You may now disconnect.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Hut 8 Corp. transcript — plus 259,000+ transcripts from 13,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Hut 8 Corp. earnings transcripts and 259,000+ others is available through the EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Hut 8 Corp. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.