Ivanhoe Mines Ltd. (IVN) Earnings Call Transcript & Summary

March 8, 2022

Toronto Stock Exchange CA Materials Metals and Mining earnings 58 min

Earnings Call Speaker Segments

Operator

operator
#1

Hello, and welcome to the conference call on Ivanhoe Mines' financial results for Q4 2021. This call is being recorded today. Right now, I'd like to hand things over to Mr. Bill Trenaman, Vice President, Investor Relations. Sir, please go ahead. The floor is yours.

Bill Trenaman

executive
#2

Thank you, operator, and greetings to all of you. I'm delighted to have you join us for Ivanhoe Mines' conference call covering Q4 and year-end 2021 financial results. A question-and-answer session will close out today's event. Questions may be submitted through the Q&A section on the webcast page or via the conference operator on your phone line. Because of time constraints, we probably won't get to every question today. We apologize in advance if time runs short, though our IR team will work to gather all questions for follow-up. Before we get started, please be aware that forward-looking statements will be part of today's event, and these involve risks and uncertainties that might cause actual results to differ materially from those in the forward-looking statements. You can find details of the forward-looking statements in our news release issued earlier today. I'm now pleased to present the first segment of today's call: a brief introductory message from our Co-Chairman and Founder, Mr. Robert Friedland. Robert, the floor is yours.

Robert Friedland

executive
#3

I want to thank everyone for joining us today, on International Women's Day, for our quarterly and year-end financials. I do have to point out that it's rather bittersweet that women rarely star wars, but are suffering from one tonight, and of course, the conflict going on in Ukraine is causing a lot of human rights violations and massive volatility in the markets. So it's hard to set that aside in one's mind when we talk to you about our 25 or 30-year journey to reach these excellent results, as we keep building the largest, highest grade, most rapidly growing copper mine in our industry, along with other significant projects in platinum, palladium, nickel and zinc. I'd like to keep my opening remarks very short and go directly into the highlights, and then see if there is anything I can contribute when we get to the question-and-answers. So with that, I'd like to turn this over to Marna Cloete, our President. Marna?

Marna Cloete

executive
#4

Thank you, Robert. This past week I had the privilege of spending a substantial amount of time with Robert. And I have to say, he has an almost uncanny ability to view the world from a million miles away as a pale blue dot and to predict how the actions we take today might shape our world a number of years down the road. And that is typically why followers take a long position when investing in these ventures; in my mind, there is no copper mine anywhere in the world today with the potential of Kamoa-Kakula. And let's not begin speculating about the potential success of Ivanhoe's true passion — adding value through the drill bit. Alex will touch on our exploration efforts later in this presentation. Today, we proudly present our fourth quarter results, and I'm always fortunate to present the executive summary as a kind of benefit spoiler alert on what is to come during the rest of the presentation. Kamoa-Kakula produced a total of 106,000 tonnes of copper and concentrate in 2021, significantly exceeding our initial 2021 production guidance range of 80,000 to 90,000 tonnes, as well as the increased guidance of 92,500 to 100,000 tonnes for 2021. We promised to hone our forecasting ability as the project matures and operational parameters become more predictable.

Marna Cloete

executive
#5

Beyond that, the Phase 2 concentrator at Kamoa-Kakula remains on schedule to start up in April of this year, and that will double Kamoa-Kakula's nameplate milling capacity throughput to 7.6 million tonnes of ore per annum. We also have a debottlenecking program underway that will expand processing capacity at our Phase 1 and Phase 2 concentrators by 21%, bringing the combined total to 9.2 million tonnes of ore per year. That debottlenecking program is expected to lift copper production from Kamoa-Kakula's first two phases to more than 450,000 tonnes per year by the second quarter of 2023. This will make Kamoa-Kakula the fourth largest copper producer in the world. It's remarkable when you consider that we only began producing in the middle of last year. But before we dive into our quarterly financials, I'd like to briefly remind you about our ESG credentials. And just before this call, I received an e-mail from one of our valued investors saying that the safety statistics featured on this slide are actually among the most impressive statistics of today. And I tend to agree with him. Across all our projects, our operational teams have put in a tremendous effort to strengthen our culture of safety. And you can see this on the slide in front of you, of that—if it takes the minute to that.

Marna Cloete

executive
#6

Right now, MSCI has us at level A, and we're aware of the many ESG indices out there and how they could affect our reputation. We're actively working to improve our ratings. Ivanhoe Mines strongly believes in stakeholder capitalism, and our partnership with local stakeholders proves that. Through our community and entrepreneurial development programs, we operate at the grassroots level all the way to our government and community shareholder structures. We believe every stakeholder should gain from our mining activities. We showed this commitment early on, even while our projects were still in exploration. Our carbon agenda matters greatly, and at Kamoa-Kakula we're aiming to become the first net zero emitter — carbon emitter among top-tier copper mines. The DRC has plenty of water, and every size of our mine, including our smelter, will run on hydroelectric power. At our Platreef project in South Africa, we're very excited to receive our electric fleet imminently. I think all our mining executives have already driven to Platreef to wait for the delivery. And none of our achievements would be possible without our people. We commend the resounding efforts of our diverse workforce, who worked tirelessly behind the scenes to advance our vision.

Marna Cloete

executive
#7

At this point I'll pass things over to our Chief Financial Officer, David van Heerden, who will walk you through the financials for the quarter.

David van Heerden

executive
#8

Thank you, Marna, and hello to everyone who's on the call today. Since Q4 2021 was just the second quarter of commercial production at the Kamoa-Kakula mining complex, my focus will be on the results we achieved in the quarter, and I'll compare those with Q3 2021 rather than with the fourth quarter of 2020. Our MD&A, of course, contains the detailed comparison of the three and 12 months ending December 31, 2021 against the same period in 2020. Without question, the standout item in the fourth quarter is the outstanding production performance at Kamoa-Kakula. Payable copper sold during Q4 came to more than 53,000 tonnes, which was 28% higher than the 41,490 tonnes of payable copper sold in Q3 2021. That greater volume of tons sold, combined with stronger average prices in Q4 and the re-measurement of contract receivables as at December 31, all helped drive a 43% rise in revenue, to $489 million, for the fourth quarter. C1 cash cost came in at $1.28 per pound of payable copper delivered to China for the fourth quarter, though I'll say more about cash cost on a later slide. EBITDA at Kamoa-Kakula for the fourth quarter reached $358 million, climbing by a massive 53% thanks to higher revenue and a lower cost per pound.

David van Heerden

executive
#9

On this slide, you can see how those highlights I just went through came together to produce profit at the Kamoa Holding joint venture, and how that ultimately flows through to Ivanhoe's share of the profit attributable to the joint venture partners. Revenue for Q4 2021 of $489 million includes a re-measurement of contract receivables of $30 million at the end of December, reflecting the effective mark-to-market at a copper price of $4.40 per pound. Kamoa-Kakula's cost of sales for Q4 2021 came to $131 million in total, or $1.12 per pound of payable copper sold, while cash cost — C1 cash cost per pound of payable copper produced — was $1.28 per pound. After deducting general and administrative expenditure, operating profit for only the second quarter of commercial production was $348 million, with EBITDA of $358 million. Kamoa Holding recorded a finance cost of $56 million in the fourth quarter, principally interest on <<inaudible>> as well as interest on Kamoa-Kakula's equipment finance facility and the short-term facilities available under the off-take agreements. Of the $93 million tax expense, $5 million represents minimum income taxes payable equal to 1% of revenue, while the remaining $88 million is deferred tax and does not represent a cash outflow.

David van Heerden

executive
#10

The reason for this is that development and expiration expenditure incurred since inception can be offset against taxable income, and for tax purposes Kamoa is able to amortize these over the first two years after commercial production begins. The non-controlling interest of $40 million reflects the profit attributable to the DRC government's 20% interest in the Kamoa-Kakula mining complex, which leaves $158 million of profit attributable to the joint venture partners. Ivanhoe's share, which equals $78 million for the fourth quarter. If we move to Ivanhoe's consolidated results for Q4, the chart and the slide deck begin with a last slide that ended with Ivanhoe's share of profit from the Kamoa joint venture of $48 million versus $78 billion for the quarter. In addition, Ivanhoe earned interest income of $26 million from Kamoa Holding in the fourth quarter of 2021 on the shareholder loans advanced to the joint venture. Over the quarter, the company spent $10 million on the Kipushi project, $6 million on the Western Foreland exploration and $11 million on general and administrative expenditure. Costs incurred at the Platreef project are necessary to bring the project to commercial production and are therefore capitalized as development cost in property planting equipment.

David van Heerden

executive
#11

In Q4, Ivanhoe recorded a finance cost of $11 million tied to interest on the convertible notes, calculated at the effective interest rate. The $89 million loss from fair valuation of the financial liability during the fourth quarter reflects the movement and the deemed fair value of the conversion feature tied to the $575 million convertible notes that Ivanhoe closed in March 2021. That conversion feature is an embedded derivative financial liability, and its fair value shifts mainly because of swings in our share price. So the loss stems from Ivanhoe's share price rising between the end of September 2021 and the end of December. With the stream facilities completed in December, a large portion of Platreef project Phase 1 capital costs is now fully funded, and we also have the excellent results from the Platreef feasibility study. It is now considered probable that future taxable profit from the Platreef project will be available against which the unused tax credits can be applied. Consequently, Ivanhoe Mines recognized in the fourth quarter the deferred tax asset that had previously gone unrecognized, producing deferred tax income of $74 million for the period. Those four items I mentioned add up automatically to Ivanhoe's profit of $48 million for the three months ending December 2021, and total profit before the loss on fair value of the financial liability and the deferred tax income came to $63 million for Q4 2021.

David van Heerden

executive
#12

For Kamoa-Kakula's second quarter of commercial production, the cash cost for each pound of payable copper delivered to China came in at $1.28 per pound, which is lower than the $1.37 per pound recorded in Q3 2021. That decline was driven largely by the mine's fixed operating cost being distributed across higher copper output from Phase 2, with Phase 1 production running above steady-state design throughput. The most significant improvements were seen in mining cost per pound, along with support services and G&A. For 2022, our guidance on cash cost ranges from $1.20 to $1.40 per pound of payable copper. We are confident the downward trend will persist as additional copper production from the Phase 2 concentrator is expected to push the cash cost per pound even lower. Over the longer term, we continue to evaluate projects such as the smelter, which could enhance cash cost by 215%. C1 cash cost is, of course, a non-GAAP measure, and a reconciliation from cost of sales to cash cost appears on Page 42 of our MD&A. Our balance sheet is strong, and we are well-positioned to advance the project further, with $608 million in cash and cash equivalents on hand and consolidated working capital of $655 million as of the end of December.

David van Heerden

executive
#13

That figure rose from the end of September through when we received the first stream prepayment of $75 million. Our $841 million in debt is mostly tied to the 2.5% convertible notes, which don't come due until 2026, though they could be redeemed earlier. For 2022, our full cost spend is $315 million across Platreef, Kipushi, ongoing exploration on the Western Foreland, and overheads. We also anticipate getting the second stream prepayment for 2022 — $225 million — later this year. At the Kamoa-Kakula mining complex, the plant capital expenditure for 2022 will be funded from cash flows generated by the joint venture, specifically for accelerating Phase 2, and it also covers $52 million for the debottlenecking program that Marna mentioned earlier, which will boost processing capacity at the Phase 1 and Phase 2 concentrators by roughly 21%. The other Phase 2 expansion group also provides for upsizing certain infrastructure and speeding up underground development so we can optimize for Phase 3. We've additionally included direct early works expenditure on Phase 3, along with the plant smelter, which will be updated once the prefeasibility study is complete. At the Platreef project, the plant capital expenditure for 2022 will support continued development toward completing its first phase, currently scheduled for the third quarter of 2024, and will also allow construction of the shop two head frame to continue, preserving optionality for potentially bringing Phase 2 forward.

David van Heerden

executive
#14

Now that the Kipushi feasibility study is finalized and we’ve agreed on the development plan, our expectation is to move ahead with ordering long lead items and carrying out other construction work once the revised and signed joint venture agreement, along with the financing agreements, are in place. Also worth noting: the loans Ivanhoe has advanced to the Kipushi project came to $528 million at the end of December, and then at Platreef as well, Ivanhoe had — has funded $655 million to Platreef, repayable to Ivanhoe, plus $277 million in vendor lines to the — to our partners. At this point I’ll hand things over to Alex Pickard, our Vice President, Corporate Development; and Marna, to give a brief update on developments across our projects.

Alex Pickard

executive
#15

Thanks, David, and hello to everyone joining us today. Starting with Kamoa-Kakula Phase 1 and Phase 2, the Phase 1 mine and processing plant kept up outstanding performance throughout the quarter and into the opening months of 2022. As Marna said, we came in above our production guidance, and that guidance was raised twice during the quarter, with more than 105,000 tonnes of copper produced in the first seven months by itself — an incredible accomplishment for the Kamoa team. Lately the processing plant has been running at a capacity above 18,500 tonnes of copper each month, and we're also glad to report copper recoveries sitting above design, at roughly 87% to 88%. We look forward to first production from Phase 2 in about one month from today, and we expect a smooth ramp-up at Phase 2 that draws on what we learned from Phase 1. Given how the crushing and grinding circuits performed in particular during Phase 1, we've identified a $50 million debottlenecking campaign to run over the next 12 months, which will push combined Phase 1 and Phase 2 production beyond 450,000 tons before Phase 3 comes into production shortly after that. Turning now to Phase 3.

Alex Pickard

executive
#16

We're now moving full speed ahead with the expansion, and we're opening up mining access to the Kamoa ore bodies, which will be ramped up to supply the Phase 3 expansion. By the end of 2024, we expect to commission a considerably bigger concentrator situated near the existing Kansoko mine. Alongside that will come a direct-to-blister smelter with a capacity of 500,000 tons per annum — the largest such facility in Africa. As David mentioned, we anticipate that this smelter project will further enhance the cash cost position across the Kamoa-Kakula operation. All of this, naturally, depends on power, and we are now mobilized and working toward refurbishing turbine 5 at the Inga II dam, which will be timed to coincide with the commissioning of the plant. That will supply sufficient power for Phase 3 and beyond. We'll be giving the markets a comprehensive update on the development plan at Kamoa-Kakula, with an updated PFS anticipated in the third quarter. Turning now to the Western Foreland: we're extremely excited about the opportunity we have across our 2,500 square kilometer land package, which Ivanhoe Mines owns 100%. That's roughly seven times bigger than the land package holding all of the Kamoa-Kakula resources we have today.

Alex Pickard

executive
#17

In 2021, we got the groundwork done — building roads and infrastructure, and running geophysics and geochemical analysis over the expanded license package. For 2022, we have an initial budget of $25 million. That covers a targeted drill campaign, which will kick off in full during the dry season — expected next month — with more than 90,000 meters of drilling planned across the Western Foreland licenses over the course of the year. That budget, though, is always subject to expansion. I'll now hand things back to Marna for an update on Platreef.

Marna Cloete

executive
#18

Thanks, Alex. It's been a pretty busy quarter for us, with two feasibility studies published in a single quarter. So our technical team is really worn out. But in South Africa, we've been persistently grinding away at turning our dreams into reality at our world-class Platreef Project. In February, we announced the phenomenal results of this independent feasibility study. And first production at our Phase 1 mine is planned for the third quarter of 2024. But our ambitions go much higher, and at the same time we'll keep developing Shaft 2 for commissioning in 2027, so we can speed up the Phase 2 expansion to 5.2 million tons per annum. That's alongside bringing Phase 1 into production. We've also locked in a stream, as David mentioned, of $300 million. And we're currently negotiating a senior debt facility that could be extended further to cover development past Phase 1. But that's just an introduction. I'll ask Alex to walk us through the project economics.

Alex Pickard

executive
#19

Thanks, Marna. Before I start, I want to note that the complete findings from our 2022 feasibility study can be found in the press release we issued last Monday, and they will shortly appear in the technical report filed on SEDAR and posted on the Ivanhoe Mines website. As Marna said, the first phase of production at the Platreef mine is now fully funded and being built, and that phase consists of a mine and concentrator with a capacity of 700,000 tons per annum, turning out roughly 110,000 ounces of PGMs in concentrate — merely the opening step for this remarkable mine. Meanwhile, we are equally determined to push the Phase 2 expansion at Platreef ahead as quickly as we can via Shaft 2, and once that happens Platreef will rank among the biggest PGM operations anywhere in the world, with output near 600,000 ounces of PGMs, while also standing as a world-class source of sulfide nickel and copper. Platreef is an unusually large and thick ore body that lends itself to a mining method that is both highly productive and highly safe. Because of that, together with the base metal endowment we hold, we anticipate Platreef will rank among the lowest cost producers globally, at roughly $500 an ounce, versus today's basket price of more than $2,500 an ounce.

Alex Pickard

executive
#20

On the overall economics side, we believe Platreef shows outstanding returns, considering it's a mine meant to last multiple generations given its remarkable scale and cost structure. Platreef has a unique mineral endowment, with a great deal of scalability past what the feasibility study covers. And we think that at today's copper price — sorry, at today's commodity price environment, it is significantly undervalued inside the Ivanhoe Mines portfolio, as the NPVs and IRRs we present here at spot prices show. I'll hand it back to Marna, who will walk you through the Kipushi update.

Marna Cloete

executive
#21

Thanks, Alex. So while our team was focused on getting Kamoa-Kakula into production over the last two years, those of us based elsewhere weren't just sitting idle — we spent a great deal of time in Congo working alongside our partners Gécamines to put together a unique partnership agreement aimed at bringing Kipushi back into production. And we were really excited to announce the results of that term sheet, or rather the agreement, that we reached with Gécamines. The stage is now set for us to return this mine to production within 24 months of the construction decision. At present, our joint venture teams are actively pursuing financing alternatives for developing the projects, and the team on the ground has already begun some early works, with zinc trading at record highs and inventory at historic lows. The Kipushi project has the potential to be restored to its former glory, only wearing a new coat made of zinc instead of copper. So with that as an introduction, may I ask Alex to please also walk us through the project economics for Kipushi that we recently published? Thanks, Alex.

Alex Pickard

executive
#22

Thanks, Marna. Once more, the complete findings from our 2022 feasibility study on Kipushi were only released a few days back, both on our website and via SEDAR. When you compare Kipushi with Platreef and Kamoa-Kakula, it's a fairly straightforward project — what it really needs is bringing the existing underground mining infrastructure back into service, plus building a modest processing facility on the surface with a capacity of 800,000 tons per annum. As Marna noted, that work can be completed within two years of the construction decision being taken. Even with that modest scale, we may have exceptionally high grades at Kipushi, roughly 35% zinc in situ. Consequently, we would still rank among the world's largest zinc producers, at more than 240,000 tons per annum. A further advantage of those remarkable grades is low cash costs — at $0.65, Kipushi will sit in the first quartile of the industry. Beyond that, the capital cost is unusually low for a mine of this size, since we benefit from a substantial amount of existing underground infrastructure that the KICO team has recently refurbished. So I think it's fairly evident that Kipushi offers exceptional economics at consensus prices, and even more so at current prices, where we see an NPV of close to $3 billion and an IRR after tax of over 80%.

Alex Pickard

executive
#23

We're really looking forward to pushing this project ahead as quickly as we can. Now I'll hand things back to Marna for her closing remarks. Thanks.

Marna Cloete

executive
#24

Thank you, Alex. We hear this question often: what comes next for Ivanhoe Mines? You have a great deal on your plate. I suspect some would question whether we were capable of it. These days, when we go to conferences, we carry ourselves with real pride thanks to what we accomplished at Kamoa-Kakula. I believe the credibility is now firmly established, and we are extremely enthusiastic about what our team will deliver at Platreef and Kipushi mix. Our exploration geologists stand in a league of their own. They are the very same geologists we deployed at Kamoa-Kakula, and I believe — no, I know — Ivanhoe Mines will become the world's next diversified major miner with a difference. We are responsible miners who care about the communities that listen to us and work alongside our partners. We are excited about the change we bring to the jurisdictions where we operate, and it is easy to do so given the type of ore bodies we are developing. I am very excited about our fourth quarter results, almost moving into our first quarter results for this year. Thanks for joining today. I will now hand back to the operator to open the line for live Q&A.

Marna Cloete

executive
#25

I appreciate it.

Bill Trenaman

executive
#26

Okay, so we’re waiting for the operator to open the lines for phone questions. This is Bill Trenaman, and I’ll put forward a few of the questions that came in through the webcast. Robert, I think this one is probably best answered by you. We’ve received a lot of questions about Western Foreland, and the gist of them would be: do you think Western Foreland will move forward as a joint venture or on a stand-Ivanhoe basis?

Robert Friedland

executive
#27

It's a bit past midnight in Singapore right now, and Western Foreland could easily fill a week's worth of conversation, though for the time being I believe it's wiser for us to hold back and observe what we turn up. Fair to say we have received approaches from quite a few major industry players as well as sovereign wealth funds. They are extremely keen to partner with us as we develop Western Foreland, and it has become clear that when you look at it through an ESG lens, the sensible location on this planet for copper mining is the Democratic Republic of the Congo. It matters a great deal that the ordinary onlooker grasps this point: the geology of the copper we have found in Western Foreland resembles an oil field far more than it does free copper. The biggest mineral discovery anywhere in the world was the Ghawar oil field, found in Saudi Arabia's Eastern Forelands. And in truth, the geology we see in the Western Forelands of the Congo is strikingly close to the setting of a substantial sedimentary oil field. So this is a basal level event. To form a Kakula ore body, essentially four critical components must come together.

Robert Friedland

executive
#28

If three of those four components line up, the result starts to look more like a Kamoa ore body. Given just how large this project is, a great deal of infrastructure work is needed. Right now, we are carrying this project entirely as an initiative led by Ivanhoe Mines. Naturally, we do not negotiate in public. There is a very real possibility that we will add a partner to develop this project at any point, but at present, as we complete the fundamental work and keep looking at expanding our land holdings in certain areas, we are doing this completely on our own. I hope that answers your question, Bill.

Bill Trenaman

executive
#29

Appreciate that, Robert. Operator, would you mind opening the line for us now? I think there are a few analyst questions coming in by phone. Thanks.

Operator

operator
#30

Yes. Thank you. Thanks a lot, sir. <<operator_script>> We'll go to the next — our first question comes from Lawson Winder at Bank of America Securities. Your line is open. Please go ahead.

Lawson Winder

analyst
#31

Yes. Good morning, good afternoon, good evening. Thanks for the update. And congratulations on a remarkable first year at Kamoa-Kakula. I'd like to ask about the cash cost guidance. So it's noted in the release through 2022, C1 cash costs are expected to decline from the Q4 2021 level of a $1.28. And I mean, that stands out as remarkable to me as it implies, you're already expecting cash cost to be at the lower half of the 2022 guidance of a $1.20 to a $1.40. And so I just appreciate to get your thoughts on the extent to which Kamoa-Kakula is experiencing any cost inflation and whether beating the low end of the 2022 to cash cost guidances within the realm of possibility at this point? Thanks very much.

David van Heerden

executive
#32

Hello, Lawson. David van Heerden here. I really do believe that hitting the bottom end of the cash cost range is something we could achieve, and we're quite hopeful about getting there. We're also very confident that we'll be quite near it later in the year. On the subject of cost inflation, we've seen some lost inflation that's factored into how we've framed our guidance range. I wouldn't call it material, and it's certainly not material for Kamoa-Kakula. That said, with the recent rise in fuel prices and so on, we do expect that to have an effect on Kamoa-Kakula, but we remain confident about getting very close to the low end of that range.

Lawson Winder

analyst
#33

All right, that's great considering the time limit. I'll stop there. Thanks a lot.

Operator

operator
#34

Our following question comes from Andrew Mikitchook at BMO Capital Markets. Your line is now open, so please proceed.

Andrew Mikitchook

analyst
#35

Thanks so much, and well done on a strong finish to 2021. My question is probably for David and the finance team. You've already noted, I believe, that you expect cash flows from Kakula and Kamoa to cover costs — both expansion and sustaining — at that mine for the other two principal assets, Platreef and Kipushi. When we look at the total 2022 guidance for those figures, what share of those costs should we expect will be covered by the financing that has already been announced or is being pursued?

David van Heerden

executive
#36

Hi Andrew. Regarding Platreef, the money we anticipate getting from the stream — would we expect that to be more than what we spend this year? So part of it would clearly be there for the 2023 spend. And we're working on locking in funding for the rest of the Phase 1 capital, and also continuing to work with senior lenders on the Phase 2 expenditure. For Kipushi, we're working on funding solutions there too. We do expect to spend a fair amount of this year's expenditure ourselves. But as I said earlier, those funds will in effect be provided by Ivanhoe as a loan to Kipushi. And so we'll fund 100%, but fund it to Kipushi as a loan at LIBOR plus, with an interest rate of LIBOR plus 6%, and hopefully be able to secure funding and time for Kipushi to be funded from a financing facility from next year onwards.

Andrew Mikitchook

analyst
#37

Perhaps, David, just as a brief follow-up: is it fair to say there would be a modest draw on the cash balance at the corporate level, stemming from the issues we discussed plus other corporate costs, though probably not a significant one? Would that be a fair characterization?

David van Heerden

executive
#38

Absolutely, Andrew, that’s a fair point. By the close of this year, we anticipate cash balances will be above $500 million. And that figure doesn’t include any funds coming in from Kamoa-Kakula at all. So it will likely end up higher.

Andrew Mikitchook

analyst
#39

Excellent. I’ll open it up so others can ask their questions. Once more, congratulations, and many thanks.

Operator

operator
#40

Orest Wowkodaw from Scotiabank has the next question. Your line is open, so please proceed.

Orest Wowkodaw

analyst
#41

Hello, and good morning. I suppose it's good evening for those of you abroad. Regarding the debottlenecking initiative at Kamoa-Kakula, your release mentions raising throughput for Phase 1 and Phase 2 to 9.2. So I'm wondering how we ought to view the ultimate throughput at this point — once Phase 3 comes into the picture, do you expect the combined throughput to get above 19 million tons, or am I just curious what the actual final figure could be when we factor in Phase 3 here?

Alex Picard

unknown
#42

Maybe I can handle that one, Orest. This is Alex speaking. Thanks for asking. So, you know, that's a fair point you're making, and it'll be covered to some degree in the Q3 PFS, which will essentially lay out the broad development plan for Kamoa-Kakula. I mean, regarding the phases past Phase 1 and Phase 2, as you mentioned, we'll reach what, 9.2 million tons per annum. We've stated that Phase 3 is going to be larger than either of those Phase 1 and Phase 2 sizings. But we'll return to you on just how much larger it will be. On the broader picture, another element we need to factor in here is the copper price. I think at the time we assembled a 19 million ton per annum plan, we were assuming a $3 copper world. And right now we're in a considerably more bullish copper price setting. So from where we sit, we'd want to keep growing Kakula larger and quicker. And if you consider your reserves and resources from roughly a $4.50, $5 copper standpoint, it clearly rises very, very substantially.

Alex Picard

unknown
#43

So the Kamoa-Kakula joint venture has resources well beyond what's needed to supply a larger concentrator facility. That said, I believe we'll stick with our current approach — advancing in bite-sized chunks, module by module, with the team focused on opening new mining areas starting with the highest-grade ones and commissioning concentrators that rely on essentially the same technology and the same process flow sheet as Phase 1 and Phase 2, though possibly at somewhat larger sizes.

Orest Wowkodaw

analyst
#44

Appreciate that, Alex. So does that mean we should expect that past Phase 3, we'll be hearing about Phase 4 and Phase 5 at some point later on?

Alex Picard

unknown
#45

Right, so this PFS is going to include that. It won’t simply end at Phase 3, though obviously Phase 3 is what we’ve sort of committed to as of today. Those later phases could end up larger down the road — similar to the call we made in moving from Phase 2 to Phase 3, which didn’t necessarily mirror what was in our previous PEA, but we reached that decision given the market conditions we’re seeing right now.

Orest Wowkodaw

analyst
#46

Much appreciated. That works great.

Operator

operator
#47

Greg Barnes from TD Securities has our next question. Your line is open, so please proceed.

Greg Barnes

analyst
#48

Yes. Thanks. This one’s for Alex too, about the Western Foreland exploration project this year. You may have covered it already, Alex, but I didn’t catch a figure for the planned drilling meterage—and where do you see that heading, even into 2023?

Alex Picard

unknown
#49

Yes, so Greg, I did mention that overall there’s 90,000 meters of drilling. Roughly 50,000 of those meters consist of shallow drilling—so under 150 meters. That’s really about drilling out the targets that we’ve—or I should say the highest-priority targets that we identified through the geophysics and geochem work we did in 2021. And then there’s another 40,000 meters of more stratigraphic drilling, which is essentially testing the furthest reaches of the Western Foreland license in terms of the underlying stratigraphy, looking for those key ingredients to find a Kamoa-Kakula.

Greg Barnes

analyst
#50

So Alex, are those specific targets you're zeroing in on — one, two, three — or do you actually have a lot more of them, past four or five?

Alex Picard

unknown
#51

No, I mean, you always have a lot of targets. And we rank them by priority in terms of what excites us most, but what's great now is that before last year, our targeting was always constrained because we lacked the infrastructure to necessarily get to the most interesting spots based on the geological data. But now we've got that spine road that crosses the whole license package. It makes it far simpler to bring drill rigs in and test some of those higher priority areas.

Greg Barnes

analyst
#52

All right, thanks, Alex.

Operator

operator
#53

Dalton Baretto from Canaccord has the next question. Your line is open — please go ahead.

Dalton Baretto

analyst
#54

Thanks a lot. Appreciate it, guys. This one might be for Robert. There's been a bit of noise lately surrounding Tenke Fungurume, along with a dispute pitting Gécamines against China Moly. So I'm curious how much of this is really an asset-specific matter rather than something broader in nature, and second, with that recent Kipushi deal — the staged transfer of ownership over to Gécamines — to what degree does that shield Kamoa-Kakula from any state-related disputes? Thank you.

Robert Friedland

executive
#55

Okay, first off, we have zero disputes with the state, and we create our own reality, because we are the absolute leader in the Democratic Republic of the Congo when it comes to treating our local and national stakeholders with the utmost respect, and because we hire women and young people and empower them, and because our ESG scores are so high, we have no disputes with the state. We expect that to continue. In fact, we're very pleased with the support we've received from the governor of Lava province, the new Prime Minister of the country — Prime Minister Sama — backed by the President's office, all the way through the government from top to bottom. I'd remind you that the Kamoa-Kakula license is held by Ivanhoe Mines. We are the landlord. We acquired that land under the 1905 mining law. We stated it and acquired it. We don't have a landlord; the issues around Tenke Fungurume aren't mine to comment on, beyond pointing out the obvious: Tenke Fungurume does have a landlord, that landlord is Gécamines, and it's not unusual for landlords and the people who rent from them to have their disputes, but it's certainly not a national issue.

Robert Friedland

executive
#56

Politically, the country has undergone quite a few shifts, and every one of them has been an improvement, as we have witnessed the adoption, or the solidifying, of Félix Tshisekedi's forward-looking course toward wiping out corruption and bureaucracy in government step by step, yet in a very genuine way. And if you look back over history, having been present there since 1996, the advancement in the Congo's business climate has simply been tremendous. And the proof of that is that everyone on the planet wants to be there. Old disagreements over which deals were struck in earlier times are not unfamiliar resources to revisit — colonial-era assets such as Tenke Fungurume have existed for 100 years, and there is a somewhat opaque record of what happened, or at least ample space for debate — but Kamoa-Kakula was a completely blank slate. We came into the country holding 50,000 square kilometers of exploration ground. Nobody had ever disturbed that land, which lay beneath 20 meters or 30 meters of sand blown in from the Kalahari desert. A 20-year exploration campaign was needed to locate this deposit, or network of deposits, which in fact stands as the biggest and highest-grade copper-bearing system across the whole Copperbelt, which extends into Zambia as well.

Robert Friedland

executive
#57

So I think it's pretty widely recognized that our deep, long-standing commitment — one that stretches back decades — is what led to this discovery and then to this remarkable, clean-sheet design of a mine, and it stands as a kind of beacon for foreign investment in the country, drawing interest from practically everyone. It would be difficult for you not to think of, or be unable to name, one of the major mining companies that has phoned us with congratulations and astonishment at how quickly this mine was brought on and how well it was brought on. Kakula was only discovered a little more than five years ago. And so we never could have accomplished that without a supportive government. Believe me. You'll see other mines in Chile, for instance, that are five or 10 years behind schedule and have suffered enormous cost overruns. You've witnessed that same phenomenon in Mongolia — just absurd cost overruns and delays in comparison. And so I think the Congolese people are the last thing you need to worry about. And certainly any disputes involving other, other operations are entirely irrelevant. I might add that Barrack sort of bet their future on the development of a magnificent gold asset in the Northeast.

Robert Friedland

executive
#58

And once again, Mark Bristow’s team has created their own reality. They went into a much tougher location and constructed a spectacular mine. So I think you create your own reality in the developing world, and what sets other mines apart is genuine rather than optical commitments to the ESG characteristics that have become so fundamental to all investors. So there is nothing in our history that bears any relation whatsoever, any issues. And thank you for grooming.

Bill Trenaman

executive
#59

Thanks, Robert. We have quite a few questions coming in on the webcast about a supplemental or additional listing for Ivanhoe Mines, given how extremely strong the share price performance has been over the past year. I’m not sure — Robert, Marna, or Alex, do you want to handle this? Could you give some color on what Ivanhoe’s plans are going forward?

Robert Friedland

executive
#60

I don't believe we truly want to speculate in public about where we'll list or when, or why of course, or that it means the possibility that the previous Ivanhoe mines, which went into Mongolia, was listed under the New York Stock Exchange. That is certainly a possibility in the future, but I don't think it's appropriate to have a selected disclosure on that subject. At the moment Americans can easily buy our shares on a secondary listing in the United States, and we have shareholders all over the world and there's liquidity building in the shares as the market compensation increases, but it is certainly possible that we'll seek additional listings.

Bill Trenaman

executive
#61

Thanks. This is perhaps something for Alex or David — could you give us an idea of when shareholder loan repayments from Kamoa-Kakula might come in 2022, and how much they could total?

Alex Picard

unknown
#62

I’m glad to address that, Bill, though I don’t believe we ought to give a specific dollar figure. As you know, it depends heavily on where copper prices go. What I can tell you is that no repayments will occur, at minimum not before Phase 2 reaches full capacity. After that point, it’s clear to anyone that Phase 1 is currently generating EBITDA at a run rate of roughly $350 million to $360 million. With Phase 2, there’s a chance to double those earnings. When you set that against our capital commitments, you can see there should, hopefully, be a certain amount — but it will only materialize once Phase 2 has entered production, and we really can’t say today how large it will be.

Bill Trenaman

executive
#63

Thanks, Alex. I believe we can take one or two additional questions prior to finishing up. A few inquiries have come in along comparable lines regarding Platreef, in light of the dramatic swings we've seen in copper and the other commodities that Platreef is going to produce. Could there be any opportunity to accelerate Platreef's output so as to take advantage of some of these extraordinary commodity prices currently in front of us?

Robert Friedland

executive
#64

We’re accelerating Platreef. For 25 years we’ve been pushing ahead as quickly as we can to discover and develop the biggest precious metals development project anywhere in the world. Questions like these always kind of make me smile, and it truly matters to go there in person and grasp the sheer scale of what we’re discussing. Imagine descending an elevator shaft that will measure 10 meters across, going down to a reef whose thickness matches an eighth story building, and then watching that reef stretch on for mile after mile after mile — all of it fully mechanized, with nobody lifting anything heavier than a pencil. You’d be in an air conditioned cab, beneath a hanging wall that is rock solid and very safe — essentially a rock factory. This requires a great deal of work, a great deal of development work. So the wonderful thing about phasing these projects is that we’re genuinely involved, lifting up our labor force and training them to a very high standard. They’re turning into at least dental technicians, if not dentists. So you begin by training people at the baby mine, just as you had training wheels on your bike, and once you’re stable, you scale up.

Robert Friedland

executive
#65

Today we announced our plan to speed up Shaft 2. Of course, the nickel price has gone hyperbolic. I think that's kind of a one or two day phenomenon, but nickel is a very, very important metal for the future, as are our platinum and Palladium. So the longer we have sustained high metals prices, the greater the many of options we have to further accelerate the project. I'd like everyone on this call to understand that the Platreef goes basically forever. There's about 150 million ounces of metal drilled off in various categories, but it's still open in every direction. And there are numerous other nickel phase mineralized bodies that are much closer to surface. So if the nickel price remains very sustained, we think probably we have the largest nickel endowment on a planetary basis at the Northern Limb of the Bushveld around our holdings. We actually have work that's been done by our geological team, contrasting the nickel endowment in area of being greater than <<inaudible>> So it's always possible to seek more Shafts. If a sovereign wealth fund wants to get involved, if unconventional investors come forward, we could seek a number of Shafts, but right now we like working in a steady modular fashion, a fast track on Phase 1, get everybody underground and show them that we're in production and then develop the first, super large mine.

Robert Friedland

executive
#66

And we need to view this against the backdrop of the ongoing expansions at Kamoa-Kakula as well as bringing Kipushi into production. Naturally, once you begin modeling this out, there are enormous cash flows potentially on hand down the road to expand these mines into a world-class major mining company. And at present we are either the biggest junior mining company on the planet, or we are the smallest major mining company on the planet. We favor the ladder, and we would ask everyone to keep their eyes on Platreef. It is, it is quite rare to find a polymetallic ore body, because as you are well aware, not all metals move in tandem. Lately palladium has gone crazy, north of $3,000 an ounce, or nickel has gone crazy. And perhaps platinum stays comparatively quiet going forward. It could be platinum that catches up, or perhaps the gold in the deposit or the copper in the deposit. Essentially you hold a self-hedged portfolio of metals at Platreef, and a lot of people ask me, what is my favorite discovery or favorite project? Without question, the world's largest precious metal system, Platreef, is the best project I have ever seen. It simply requires more capital and requires more time to get a hundred year Tier 1 mine up and running.

Robert Friedland

executive
#67

But once it’s up and running, it will be a treasure for our kids and grandchildren. And we really encourage every one of you to come and have a look at it. We’ll be doing the Endava conference, which I think takes place in May this year. And soon after that, we’ll pick a handful of institutional investors to visit Platreef and Kamoa-Kakula. So if that interests you, I’m <<email_hidden>>, and you can get in touch with Bill Trenaman, and we’ll figure out how to show you the scale of these operations — it’s really substantial — and then you’ll see why worthwhile things take a bit of time.

Bill Trenaman

executive
#68

Thank you, Robert. I felt that was an ideal note on which to close this call. I also want to express appreciation to every shareholder, analyst, and investor who took part today. We look forward to giving you regular updates as we keep growing into what Robert called the next world-scale diversified mining company. And thank you. I am <<email_hidden>>. Please don't hesitate to contact me via email or phone, and we'll address any questions we weren't able to get to for you today. So thank you. And I wish each of you a good morning, good afternoon, or good evening,

Operator

operator
#69

That brings us to the end of the call for today. We appreciate everyone for joining us. You can go ahead and disconnect at this time.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Ivanhoe Mines Ltd. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Ivanhoe Mines Ltd. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ivanhoe Mines Ltd. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.