Ivanhoe Mines Ltd. (IVN) Earnings Call Transcript & Summary
August 15, 2022
Earnings Call Speaker Segments
Operator
operatorHello, everyone, and welcome to the conference call on Ivanhoe Mines' financial results for Q2 2022. This call is being recorded today. I'll now hand things over to Matthew Keevil, our Director of Investor Relations and Corporate Communication. Matthew, please go ahead.
Matthew Keevil
executiveThank you, operator. Good day, everyone. I’m Matthew Keevil, Director of Investor Relations and Corporate Communication at Ivanhoe Mines. It’s a pleasure to welcome all of you to our conference call for the second quarter of 2022. Today’s event will conclude with a question-and-answer session. Questions may be submitted through the Q&A box on the webcast page or via the conference operator using your phone line. Because of time constraints, it’s unlikely we’ll get to every question. We apologize if time runs short; our IR team will make an effort to gather the questions for follow-up. Before we start today, I want to remind everyone that this event will include forward-looking statements involving risks and uncertainties that could cause actual results to differ materially from those in the forward-looking statements. Details of the forward-looking statements are included in our August 15th press release as well as via SEDR and our website at www.ivanhoemines.com. It is now my pleasure to introduce Ivanhoe Mines’ Founder and Co-Chairman, Robert Friedland.
Operator
operatorRobert, we've got you linked up. Nothing is coming through from your side. It's possible you've muted yourself by accident.
Robert Friedland
executiveYes, and many thanks. I appreciate everyone joining this call. Ivanhoe Mines has just completed a very strong quarter, which highlights how fundamentally important it is in mining to hold a Tier 1 ore body positioned at the lowest end of the global cost curve. It was an outstanding quarter, driven mainly by the fact that we are producing green copper in the Congo using low-cost hydroelectricity. We identify several factors that leave us highly optimistic about what lies ahead. We welcome any comparison with competing operations anywhere else in the world. So with that, I want to hand things over to a very, very, very capable operating team, Marna and David, who will walk you through all the details, and later in the call I'll return to take questions. Thank you very much. Marna?
Marna Cloete
executiveThank you, Robert, and good afternoon everyone, speaking from a Johannesburg that is very challenging. During 2022's second quarter, we hit several important milestones on the path toward becoming a major diversified mining company. Among these: Kamoa-Kakula declared commercial production at our Phase 2 ahead of schedule; changeover and equipping of Shaft 1 at the Platreef project was completed; and in June, Ivanhoe and Gécamines approved the development budget at the Kipushi project. At Kamoa-Kakula, Phase 2 ramp up is continuing, and we anticipate reaching 450,000 tons of production by the second quarter of 2023 following completion of the debottlenecking program, with market global reach combined proper. Early commissioning of Phase 2 let us tighten the low end of guidance and lift our production guidance to a range of 310,000 tons to 340,000 tons of copper and concentrate for 2022. While ramping up, Kamoa-Kakula turned out a record 32,877 tons of copper in July — an annualized production rate of 387,100 tons of copper, which is significant given that vice to it were commissioned in April. Expansion to Phase 3 is under way. It will raise copper production to 600,000 tons per annum by Q4 in 2024.
Marna Cloete
executiveFunding for this expansion is going to come from cash flows as well as joint venture facilities. Shortly, David van Heerden, our CFO, is going to walk you through the quarterly numbers. Still, it may be worth noting at this point that during the second quarter we did see C1 cash costs rise. Cash costs per pound of favorable copper produced came in at $1.42 per pound, against $1.21 per pound and $1.28 per pound in the first quarter of 2022 and the fourth quarter of 2021, respectively. That increase was mainly attributable to logistic charges; and Alex Pickard, our VP Corporate Development, will go through a number of initiatives currently underway aimed at bringing these charges down. We do expect somewhat elevated cash costs in the third quarter. We're off the chip reduce in the fourth quarter wanting to Lualaba Copper Smelter returns online in early September of the scheduled maintenance dispose this coming quarter and the cost saving initiatives start yielding results. We therefore reiterate our C1 cash flows guidance for Kamoa-Kakula of $1.20 to $1.40 per pound for the calendar year 2022 and expect our crash cost to be at the upper end of guidance for the year. Environmental, social and governance remain at the heart of what we do.
Marna Cloete
executiveAlso, during May we were proud to release our sustainability report for the fifth year running. Our membership in the United Nations Global Compact came about in June through Ivanhoe, and we stay dedicated to honoring the 10 principles that form the foundation of that initiative. We recognize how much gender diversity matters, along with diversity of every kind, yet especially so in the DRC, where female representation throughout mining had been falling behind. Group-wide goals for gender inclusion have been put in place by us. We are equally dedicated to making sure local employees drawn from the areas surrounding our mines make up the majority of our workforce. To get there, world-class training centers have been set up by us so that employees from local communities can be capacitated. Since we recognize that our mines cannot employ everyone, we likewise place considerable emphasis on enterprise and supplier development, aiming to bring these local businesses into our supply chain and to build capacity for sustainable business operations that last past the life of our mines. At a moment when the world faces substantial deflationary pressures, especially where fuels are concerned, we count ourselves lucky that within the DRC our spending on refurbishing hydropower facilities already in existence delivers improved fuel inflation and also lets us reach our vision of becoming a green metal producer.
Marna Cloete
executiveI'll now pass things over to David van Heerden, our Chief Financial Officer, who will walk you through the results for our second quarter. David, the floor is yours.
David van Heerden
executiveThanks, Marna, and hello to everyone who's joined us on the call today. The second quarter of 2022 marked yet another period of outstanding operational achievement at Kamoa-Kakula. That said, the results took a hit from the copper price drop late in the quarter as well as inflationary pressure, and we'll get into both of those in a bit more detail shortly. This call is, of course, only a high-level overview of our quarterly results, and the presentation ought to be read alongside the quarterly financial statements and MD&A covering the three and six months ended June 30, 2022. In only its fourth quarter since commercial production began, Kamoa-Kakula sold close to 86,000 tons of payable copper in concentrate, which generated quarterly revenue from contracts receivables of $699 million prior to a negative remeasurement of $205 million at period end. Higher diesel prices and other factors, combined with constrained trucking capacity — made worse by the sharp rise in terms produced by Kamoa-Kakula — pushed cash costs upward. Even more significant, though, Kamoa-Kakula managed to sell 1,000 tons more than the payable copper it produced during the quarter. The drop in Kamoa-Kakula's EBITDA to $286 million for the quarter stemmed mainly from the remeasurement of sales, which I'll walk through in more detail now on the next slide, where we focus on a closer look at Kamoa Holding's joint ventures profit.
David van Heerden
executiveContract receivables revenue, booked using the average copper price in the month of sale, reached as much as $699 million in Q2 versus $467 million during Q1, and that gain came from Phase 2 production. Q1 sales were remeasured at the end of March using a copper price of $4.69, whereas the realized copper price in Q2 came in at $4.34 per pound. On top of that, the outstanding balance of provisional price sales will be remeasured at the end of June at a copper price of $3.79 per pound, and together these produced a negative mark-to-market of $205 million in Q2. For the second quarter, Kamoa-Kakula's cost of sales totaled $217 million, or $1.15 per pound of payable copper sold, versus $1.08 in the first quarter; after deducting G&A, operating profit for the second quarter of the year was 253 million and Kamoa-Kakula's EBITDA was $286 million. Kamoa holding recorded a finance cost of $66 million in Q2, mainly interest on the shareholder loans from Ivanhoe infusion plus interest on Kamoa-Kakula's equipment financing facilities. Deferred tax was $57 million in the quarter, alongside a current tax expense of $5 million. The non-controlling interest of $27 million reflects the profit attributable to the DRC government's 20% interest in the Kamoa-Kakula mine complex, which leaves a profit of $100 million attributable to the joint venture partners, with Ivanhoe's share equaling $50 million for Q2.
David van Heerden
executiveMoving on to Ivanhoe's consolidated results for Q2, the chart on Slide 6 begins with that final item, showing Ivanhoe's $50 million share of profit from the Kamoa joint venture for the quarter. On top of that, Ivanhoe brought in $35 million of interest income from Kamoa Holdings during the second quarter. Every one of those shareholder loans was advanced to the joint venture. Over the quarter, the Company put $10 million toward the Kipushi project, $4 million toward Western Foreland exploration, and $4 million toward general and administrative expenditure. Costs incurred at the Platreef project by the industry to bring that project to commercial production are therefore capitalized as development costs in property planting equipment. The $184 million gain on the fair valuation of the financial liability in Q2 reflects the change in, and the deemed fair value of, the conversion feature attached to the $575 million, 2.5% convertible senior notes that Ivanhoe closed in March of 2021. That conversion feature is an embedded derivative financial liability, and its fair value shifts mainly because of fluctuations in our share price. The gain, then, comes from the decline in Ivanhoe's share price between the end of March and the end of June this year.
David van Heerden
executiveIn Q2, Ivanhoe recorded a finance cost of $10 million tied solely to interest on the convertible notes at an effective interest rate. Shareholders of Kipushi have agreed to the development plan, and the development budget has been approved in line with the Kipushi 2022 feasibility study. It has become probable that future taxable profit will be generated by the Kipushi project, against which its unused tax losses and unused tax credits can be offset. So in June of this year we recognized the deferred tax asset that had not previously been recognized, resulting in a gain of $114 million. Those items together ultimately add up to Ivanhoe's second-quarter profit of $352 million. Cash cost per pound of payable copper produced and delivered to China came to $1.42 per pound in the second quarter, compared with $1.21 per pound in the first quarter of this year. Second-quarter cash cost per pound of payable copper was higher mainly because logistics charges for transporting Kamoa-Kakula's copper products rose 42%. And as Marna said, we will go into our cost reduction initiatives in a bit more detail later in this call.
David van Heerden
executiveWe additionally observed higher mining costs, driven by elevated diesel prices along with other increased prices for consumables, and also from drawing on certain surface stockpiles, which ship at a somewhat higher average rate. Our balance sheet is strong, and we are well positioned to support developing and growing our projects, with $507 million in cash and cash equivalents on hand and consolidated working capital of $530 million. Our liabilities total $734 million, and $775 million of that relates to the 2.5% convertible notes, with those only due in 2026 and possible earlier redemption. Our forecast spend for 2022 is $251 million on Platreef of Kipushi and continued exploration on the Western Foreland and recovery rates. And all operating and capital expansion cost at Kamoa-Kakula are expected to be funded from copper sales and facilities at Kamoa. Later this quarter, we also expect to receive the secondary payment on the Platreef streams, which at that time will add a further $225 million to our cash position. I will now hand over to Alex Pickard, Vice President of Corporate Development; and Marna to provide a brief update on the development project.
Alex Pickard
executiveThank you, David, and greetings to everyone joining the call from London, where it's quite warm and humid. I'll walk you through the main operational results for Kamoa-Kakula and the Western Foreland covering the second quarter. Kamoa-Kakula delivered yet another outstanding operational quarter, and the standout accomplishment was the highly successful ramp-up of Phase 2. It's worth drawing attention to how remarkable the timeline for this ramp-up was. The plant was commissioned on March 21, just before the close of the first quarter, and by April 8 — a bit more than two weeks afterward — we had declared commercial production. In the initial month of production, in fact during the first two weeks of production, the Phase 2 concentrator was already routinely surpassing its design throughputs while reaching near design recovery of 86%. The operations team has kept up this trajectory, as you can see from the record production month of close to 32,900 tons of copper achieved in July. That's close to 400,000 tons on an annualized basis. Consequently, we have raised the lower end of our production guidance from 290,000 tons to 310,000 tons while also keeping the upper end of the guidance at 340,000 tons, and we expect to be comfortably within this range.
Alex Pickard
executiveThe debottlenecking initiative at Kamoa-Kakula is coming along nicely too, and we anticipate finishing it in Q2 of next year, which will lift production capacity to roughly 450,000 tons of copper. Alongside that, mine optimization plans are underway at Kakula, aimed at higher mining rates so we can match the expanded plant capacity of 9.2 million tons once debottlenecking is done. During the period when this ramp up and underground material handling capacity is being built at Kakula, some material will come from the stockpile, which carries a somewhat lower yet still quite healthy grade of 4% to 5%, and later this year we will aim to move back toward 6% copperhead grades. The remarkably strong production ramp up at Kamoa-Kakula meant we sold a considerably larger volume of copper products, mainly copper concentrate, but also blister copper under the Alltel smelting agreement at the neighboring Lualaba Copper Smelter. The charts on the right hand side put this in context: we recorded a rise of more than 70% in the absolute volume of concentrate dispatched during the quarter. Digging into these figures a bit more, you will notice that the volume dispatched for local treatment actually fell, as the Lualaba Copper Smelter was shut for scheduled maintenance.
Alex Pickard
executiveAnd we expect that to carry on through Q3 as well, so overall we'll be shipping out a bigger amount of concentrates before that smelter comes back online. So, as both David and Marna mentioned earlier, the upshot of this was a substantial rise in cash costs on our logistics line of about 42% during Q2. That comes partly from the strain those extra volumes put on trucking capacity, along with some trouble scaling up customs clearing processes and congestion at the DRC–Zambia border, but regional elements are also contributing, like the halted port operations in Durban from flooding and diesel prices climbing worldwide. Kamoa Copper is collaborating very closely with CITIC and Zijin, its off-take partners, and with the DRC government to tackle these problems. And we already have plans ready that involve making more trucking capacity available, assisting the DRC government in enhancing customs clearing administration, and we're also very glad to report that a second import-export border crossing linking the DRC and Zambia has now opened at Sakania, supplementing the earlier single crossing at Kasumbalesa, which had been the bottleneck.
Alex Pickard
executiveOn shipping, we're currently exporting through 4 ports across Africa, and that gives us considerably more flexibility, with the possibility of adding a 5th at Lobito in Angola, where a concession was recently awarded. Last, returning to the broader cost picture, we anticipate a step change improvement when our onsite direct blister smelter comes online, and we've conservatively estimated that it can cut costs by 10% to 20%. The primary effect comes from a significant reduction in unit volumes moved of over 50%, which also takes in the Phase 3 volumes, and beyond that, the smelter produces valuable byproducts through sulfuric acid sales, which currently fetch a high price in the DRC copper belt. Moving on now to our Phase 3 expansion plans, we're well advanced with the 5 million ton per annum mining concentrator expansion, and it remains on track for the end of 2024. The graphic on the right hand side illustrates where the Phase 3 concentrator will sit, near the new box cuts and declines being opened up at the Kamoa 1 and 2 mines, both of which are progressing well. In June, we placed orders for key equipment, including ball mills, crushers, flow cells and filters for the plant.
Alex Pickard
executiveRegarding that state-of-the-art 500,000 ton per annum director blister smelter I brought up earlier, we began earthwork at the sites during the quarter, and in June we also ordered the furnaces along with other equipment with long lead times. That project, too, is moving along very nicely. Everything here dovetails with the work at Inga II, where we signed up the EPC contractor in April, and upgrading Turbine 5 is now underway, which will deliver a critical green power source for all of our expansion plans. We are in the process of finishing a prefeasibility study that pulls all of these Phase 3 projects together along with the optimization work under way at Kakula, and this will give up-to-date cost guidance by the end of the year. Turning to exploration, at the Western Foreland we returned to field exploration during the second quarter, which came after the usual close of the rainy season. Our airborne gravity and electromagnetic surveys across the whole 2,400 square kilometer land package are almost finished, which enables much better targeting over an extremely large area. During the quarter, we have been drilling extensions to the existing Makoko discovery situated to the West of Kakula, as well as regional stratigraphic drilling in the north and far south west portions of the license package.
Alex Pickard
executiveEven so, we've got far more drilling scheduled across the whole season, which includes 50,000 meters in shallower zones and as much as 45,000 meters of deeper regional drilling. So we're really eager to see the results that come from that. With that update done, I'll hand things back to Marna now to go over the remaining projects.
Marna Cloete
executiveThank you, Alex. If we look at Platreef to begin with, after the shaft equipping and changeover were finished and lateral development got underway in the second quarter, our underground work is concentrated on the waste passes at the 750-meter, 850-meter and 950-meter labels, and 200 meters have been completed on the 950-meter label. Lateral development at the 750-meter and 850-meter labor is set to begin in the third and fourth quarter. In August 2022, we finished building the 26-meter concrete each to collar at the 10-meter diameter shaft 2, which sits on the critical path for the future expansion of Phase 2. We intend to carry on with construction of the 103-meter-tall headgear shaft 2, since this will provide optionality to bring forward the 5.2 million ton per annum mine at Platreef. Construction of a 5 megawatt solar plant is scheduled to start in the third quarter, with commissioning expected in 2023. Expenditure for the remainder of the year comes to $129 million, and as David mentioned earlier, we intend to draw the remaining $225 million of the $300 million stream facility in the third quarter, which will fund our ongoing efforts at Platreef. Then, returning to the DRD, in June, Ivanhoe and Gécamines approved a development budget for Kipushi that was consistent with the published feasibility study we released earlier this year.
Marna Cloete
executiveWe’ve already begun some early works, and those consist of preparatory underground work. That is going to allow the project to be finished on the timelines we planned. Prepayment is happening for long lead orders, and preliminary construction activity is now in progress. We expect that discussions around financing will wrap up inside the next three months, and after that, full construction activities will be able to begin. Ivanhoe is well along on our journey toward becoming a leading supply of critical meters for the green energy, clean energy transition. With our Tier 1 assets at various stages of development, we are well positioned to realize our vision. I’ll now hand back for today’s Q&A session. Thank you.
Matthew Keevil
executiveThanks, Marna. At this point we'll open things up for questions and answers. Just a reminder: if you'd like to ask something, please send it in through the Q&A box located in the bottom left corner of the webcast page. Within the time we have left, we'll try to get to as many questions as we can. Operator, let's start by going to the conference line so we can take anyone there who has a question waiting. Thank you.
Operator
operatorThanks. <<operator_script>> Our first question comes from Lawson Winder at Bank of America. Go right ahead.
Lawson Winder
analystEven though it's only a hiccup in what is otherwise a pretty remarkable ramp up for a new mine, I did want to focus on cash costs and the cash guidance for 2022. Marna, you commented that cash costs in Q3 '22 would be slightly elevated. It would really help to get some clarity from you on whether you meant higher versus Q2, or just elevated versus guidance, or what exactly you might mean by that. That would be very helpful. Thank you.
Marna Cloete
executiveThanks, Lawson. Perhaps I could begin, and David, please feel free to chime in. Our expectation, I believe, was that we would trend below the guidance we currently have, but we do anticipate trending a little above guidance for Q3 purely because of the new Lualaba Copper Smelter going through scheduled maintenance. And since the measures we're putting in place—the ones Alex is referring to—will need a bit of time before they bear fruit. We're all speaking with customers and authorities, and as Alex said, we're adding trucking capacity. All of that will ease the pressures on our logistical charges. We also believe fuel prices will soften, and that shipping charges and rates will come down. So we think all of those will culminate in lower results during Q4, but we do expect Q3 to be sort of in line with what we saw in Q2.
Lawson Winder
analystNow, regarding the logistics costs you’re trying to eliminate — at this point, do you have a sense of what share can realistically be removed, and how much may stick around? Perhaps at least in percentage terms, until the smelter is ready to go. David, would you like to take a guess?
David van Heerden
executiveI'm glad to weigh in here. Going back to where we were in Q1, once every one of those measures is in place—that doesn't strike me as unrealistic. Beyond that, there are more items we're examining: we're reviewing the balance we strike between corporate recoveries and concentrate trade, simply to determine where the sweet spot lies, and that clearly carries a logistics charge and impact specifically. It comes down to locating that sweet spot and ensuring we get the most value. So yes, there are several things under review, but essentially the Q1 levels are not unachievable—though some work remains to get there.
Alex Pickard
executiveAnd perhaps I could piggyback on that point too, David. The logistics market across the African continent is intensely competitive, and we do anticipate a response driven by market forces—particularly since online freight rates over the last 2, 3 years have risen, in all likelihood, by over 50% when it comes to actual trucking costs. That has happened as considerably more volumes have come online from Kamoa-Kakula and other operations. Yet naturally, with those costs sitting so high and trucking operators likely earning fairly reasonable profits at present, it will definitely attract new entrants—and that forms part of the initiative Marna referred to, namely that we are working to help new trucking operators enter and react to market dynamics, pulling those costs down toward a more normalized level. So I believe there is an opportunity from that standpoint as well.
Lawson Winder
analystThanks, Alex. And if I could just add a follow-up — clearly, that smelter has great potential to bring your costs down dramatically. And to eliminate these logistics problems entirely. You're now aiming for year-end 2024 on that. When you consider the path to getting it started up, what items are on the critical path? And could that timeline potentially be accelerated?
Robert Friedland
executiveMaybe I'll give that a try, Lawson. The real bottleneck at the smelter is power, honestly. So that's the work we're carrying out at Inga II to get Turbine 5 up and running, until that power from Turbine 5 becomes available. Ramping up a smelter when you can't ensure a steady power supply to it isn't something you'd really want to do. So that's essentially what our Q4 2024 guidance rests on. Naturally, we'll seek every avenue to finish those works at Inga faster if we can, but we also don't want to be repaired on realistic.
Operator
operatorOur following question comes from Andrew Mikitchook at BMO Capital Markets. Go ahead, please.
Andrew Mikitchook
analystHello, and good morning or good afternoon, depending on where you're dialing in from. I have just a couple of quick questions. I was hoping we might get a bit more commentary, broadly speaking, on your CapEx and on all that experience with ordering long lead time equipment — whether that's tracking, at least in general terms, with what had been expected or budgeted, and also on the availability and timeline for this equipment generally, across your projects, since I think you likely have broader experience and exposure than perhaps other parts of the market do, and I'm sure investors would be interested in hearing your sense of how that looks?
Alex Pickard
executiveDavid, would you like to handle this one, or should I…
David van Heerden
executiveSure, I’m glad to start on that, and please chime in as well—thanks for the question, Andrew. When it comes to our present CapEx costs, the inflation pressures we’re experiencing aren’t the same as those affecting OpEx and consumables. That said, logistics obviously cuts both ways, so there’s a modest effect on deliveries, particularly regarding what has been bought for Kamoa and for Kipushi. And in South Africa, given how the South African rand has weakened, I think that has worked somewhat to our advantage. As a result, we aren’t currently seeing an increase in U.S. dollars for our capital and expenditure, so that’s a positive on that front for now. But—and I’d also like to mention that the Platreef and Kipushi studies were, of course, finished at the start of this year. So those cost estimates remain fairly up to date, and we will nonetheless update the market if we believe we are deviating materially from our current studies, though that isn’t the situation right now. Perhaps, Alex, you could add a little on Kamoa regarding the prefeasibility survey.
Alex Pickard
executiveYeah. Thank you, David. So clearly, we’re not able to get into the details on the figures until everything is assembled into a single package, and obviously several different pieces feed into that — the mine concentrator, the smelter, and the power all coming together. But as we’ve noted, Andrew, I mean, we did put through orders in June, so pricing has been locked in for some fairly substantial equipment items, including key components for the mill. And I think as we sit here today, the costs on any of those components don’t particularly concern us. And there are indications that the broader market is softening. And regardless, I think we’re quite confident that we have the funding secured, both through cash flow and through Kamoa-Kakula itself, along with the ability to raise facilities at the Kamoa level.
Andrew Mikitchook
analystThanks. David, if you're still on the line, could you give us a quick comment on how the repayment schedule for the development expenses on Phase 1 and 2 is likely to play out? And when would we start to see more meaningful cash taxes payable rather than deferred tax?
David van Heerden
executiveSo Andrew, that’s — in that respect we likewise owned our West entry in the states where we are, and especially at Kamoa-Kakula, likely using up our tax assets quite fast. And so we do expect to have more substantial tax expenditure, and rather than deferred tax, cash tax expenditure beginning as soon as next year.
Andrew Mikitchook
analystAlright, that matches what was said earlier. Thanks a lot. I’ll step aside and let other people ask questions. Congrats on a strong quarter.
David van Heerden
executiveAppreciate it, Andrew.
Operator
operatorAt this point, there are no additional questions coming in by phone.
Matthew Keevil
executiveThanks, operator. Now we’ll turn to questions from the web. As always, a few of them are repeats, so we’ll likely combine some and direct them to the right members of management. We’ll begin with one for Robert, and it’s a pretty common question in our inbox today. Robert, after BHP’s recently announced bid to acquire OZ Minerals, the copper M&A market is clearly picking up somewhat. People want to hear your view of that market and how Ivanhoe might fit in with its M&A focus?
David van Heerden
executiveOkay, copper doesn’t grow on trees, and without a huge rise in demand for copper metal, we won’t get clean air, we won’t make a meaningful climate impact, and we won’t be able to act on this so-called Inflation Reduction Bill. And the policy reaction to recession is inherently reflationary. The global response to Russia’s invasion of Ukraine is leading to demilitarization of the world’s militaries. The Germans haven’t had an army worthy of the name since World War II — even the Dutch are raising their defense budgets. So on both the military side and the greening-of-the-planet side, there is astronomic demand for copper metal. The most bullish scenario is that the capital markets are scared to invest. Building copper mines takes a decade or two. And very few of them can legitimately claim to be Tier 1. The BHP 32% premium price minerals is the case in point. One could argue whether that’s actually a Tier 1 company or not in terms of its assets, but the bid was rejected. And more recently, a 32% premium for Turquoise Hill in Mongolia — an asset that I know better than anyone — was also rejected as unfair by an independent committee of the directors.
David van Heerden
executiveSo, whether you're a sovereign wealth fund, a major mining company, or a big manufacturer or consumer of copper, and you're after a Tier 1 asset — you can tally every possible acquisition on fewer than one of your hands, and you don't need both of them. And then, in what's sort of an anaerobic environment — that's one lacking oxygen — for a lot of the juniors. The pipeline is under stress, and we don't see meaningful copper entering production. To sustain 3% GDP growth across the next 22 years, the world essentially needs copper output to double. That recent S&P study led by Dan Yergin contains stunning statistics that everyone ought to read. We see financial markets run by computers and algorithms, yet they've really got their heads stuck firmly in the sand like ostriches, with no grasp of our industry. I recently passed a day with senior management at one of the largest copper traders in the world, and we see an incipient trend recommend in 2024, 2025, as demand for copper metal explodes and as inventories drop to virtually nothing. We also see reductions in legal costs on the way, reductions in shipping indexes on the way, and we see interest rates being cut in China.
David van Heerden
executiveSo I believe we're sitting almost exactly at the ideal point, where holding copper assets makes a lot of sense at this stage of the cycle. Our fundamental position could not please us more, given that we emit very little greenhouse gas. You've all witnessed some dramatic rises in capital expenses across mining. But when our copper mine achieves 10 times the grade of your copper mine, we consume a 10th of the steel, a 10th of the electricity and a 10th of the hydrocarbons. So this is precisely the message I've been sharing with all of you. When circumstances get tough and you enter an anaerobic stretch of mining, that is precisely the moment to build. We want to construct a mine while the world is in this phase. We want to build your mine while China's supply chain seeks to expand. And in fact, right now is an excellent moment to purchase steel and fabricated goods from China — truly a perfect moment. So we believe our timing is correct, pointing toward a very, very bright future at the bottom of the world cost curve starting in 2024, in a set of conditions that will endure for decades.
David van Heerden
executiveAnd for our children and grandchildren, if a greener planet is what you want, half goes to our management team, who are reinventing mining — that's an unprecedented level of input from women, and an unprecedented level of benefits for the communities that host our efforts. And regarding exploration potential, not only in the Congo but in South Africa as well, I can assure you our teams are well enhanced. So with that, I think that's a good enough answer to your general question. And I think all of you listening to this call, it's very important to remember to buy on red days, so that you can sell when the days turn green. Thank you.
Matthew Keevil
executiveThanks, Robert. And looking at the time, I believe there's room for one more. Marna, this one is fairly high level for you too. Given how well the Company has done in building and commissioning Phase 1 and Phase 2 of Kamoa-Kakula, which knowledge and skills do you intend, or have you intended, to pass along so that Phase 3, the smelter, and also the Platreef project get built and commissioned on schedule and within budget?
Marna Cloete
executiveThanks, Matt. What I'd say is that people and planning are what success hinges on, and the key is keeping things simple — try to standardize designs wherever you can, and stick with the same contractors and suppliers when they've performed well. At Kamoa-Kakula, we ran a handful of lessons-learned reviews once Phase 1 and 2 were finished. We did pinpoint some shortcomings, and we're busy rectifying them, as well as adjusting our plans for carrying out Phase 3 — which we intend to do the same way at Platreef and Kipushi, drawing on all those lessons from Kamoa and applying that same formula.
Matthew Keevil
executiveThanks very much, Marna. We're basically at the one-hour mark now. That brings us to the end of this call on Ivanhoe Mines' second quarter 2022 financial results. Appreciate everyone joining us today, and we hope to talk with you again before long. Once more, should any questions remain that we didn't get to today, feel free to contact our IR team. Many thanks again.
Operator
operatorEveryone, that brings us to the end of today's call. Thank you for joining us. You can go ahead and disconnect at this point.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Ivanhoe Mines Ltd. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Ivanhoe Mines Ltd. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ivanhoe Mines Ltd. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.