Ivanhoe Mines Ltd. (IVN) Earnings Call Transcript & Summary

February 26, 2024

Toronto Stock Exchange CA Materials Metals and Mining earnings 59 min

Earnings Call Speaker Segments

Operator

operator
#1

Good day, and thanks for being with us. I'd like to welcome everyone to the Ivanhoe Mines Ltd. conference call and webcast covering 2023 Q4 and full-year financial results. Right now, everyone joining is in a listen-only mode. Once the speaker finishes presenting, we'll open things up for questions and answers. If you'd like to ask something during that portion, simply press Star 11 on your phone. An automated message will then confirm that your hand is raised. Should you wish to remove your question, just hit Star 11 once more. At this point, I'll turn the conference over to Matt Keevil, our Director of Investor Relations and Corporate Communications. Matt, please go ahead.

Matthew Keevil

executive
#2

Thanks, Operator, and good day to all of you. I'm delighted to have you join us for Ivanhoe Mines' conference call covering the fourth quarter and full-year 2023 financial results. My role here is Director of Investor Relations and Corporate Communications. Joining us on today's line from Ivanhoe Mines are Robert Friedland, our Founder and Executive Co-Chairman; Marna Cloete, President; David van Heerden, Chief Financial Officer; Mark Farren, Chief Operating Officer; Steve Amos, Executive Vice President Projects; and Alex Pickard, Senior Vice President Corporate Development and Investor Relations. Today's event will wrap up with a question-and-answer session. Questions can be submitted through the Q&A box on the webcast or via the conference operator on your phone line. If you have follow-up questions, or if we didn't get to your question during the call, please reach out to our IR team directly. Before we begin, we'd like to remind everyone that forward-looking statements will be part of today's event, and these involve risks and uncertainties that could cause actual results to differ materially from those in the forward-looking statements. You can find details of the forward-looking statements in our February 26th news release, as well as on SEDAR+ and at www.ivanhoemines.com. I'll now hand things over to Ivanhoe Mines Founder and Executive Co-Chair Robert Friedland for some opening remarks.

Matthew Keevil

executive
#3

Robert, you have the floor.

Robert Friedland

executive
#4

To all our shareholders and stakeholders worldwide, I'd like to say welcome to this conference call where we'll discuss the results for our annual period. Following roughly 28 to 30 years of work, it's a great pleasure to report that more than 20,000 people are now employed directly by Ivanhoe Mines, and there's plenty for us to cover on this call. So without any further delay, I'll hand things over to Marna Cloete, our President, who will get us started. Thank you, Marna.

Marna Cloete

executive
#5

Thank you, Robert. Perhaps a short introduction is in order. I've spent 17 years with this company, and I'm approaching 18. The image you see before you shows our Phase 3 plant at Kamoa-Kakula, which is set to be commissioned in June. Once again, we're ahead of schedule. I believe we told the market previously that Phase 3 would be ready in Q4 of this year, and our team has delivered yet again. We're certainly becoming smarter as we go. It's always my privilege to begin with the highlights. Matt, if you could bring up the highlights for us quickly. From the Kamoa-Kakula standpoint, I think we truly had an outstanding year. We delivered once more. We faced some challenges. We did leave some copper on the table, largely because of grid instability. Mark Farren will walk you through all the plans we have in place to make sure we tackle these grid stability issues in the DRC. We've issued our guidance for this year. Our plan is to produce 440,000 to 490,000 tons of copper. As I said a moment ago, this is largely because we are once again ahead of schedule with commissioning our third plant at Phase 3.

Marna Cloete

executive
#6

Building five major capital projects simultaneously is no small feat. I believe our team may be the only one worldwide doing this, and credit for that goes to the amazing individuals we have throughout the organization. For me personally, 2023 was likely among my hardest years. We devoted considerable time to plans, tackling problems, and ensuring we deliver to the market what we promised. We're thrilled that in 2024, Kipushi will also come into production. In the second quarter, the mine looks quite tidy. Mark and Steve will walk you through our development plans here shortly. On the statistics front, we produced more than 390,000 tons of copper during 2023. We sold nearly 376,000 tons. The gap between those figures is essentially what remained in inventory and at the Lualaba Copper Smelter. We generated $2.7 billion in revenue, with EBITDA of $1.68 billion. Our cash cost landed in the mid-range of our guidance. We're also releasing guidance for this year. David van Heerden will cover our C1 guidance a bit later in the presentation.

Marna Cloete

executive
#7

And naturally, it's always a thrill to hear Robert share the wins we've had on the exploration front. With Kitoko, we believe we've landed yet another one. Our team is genuinely energized by what's showing up in the Western Foreland. Let's move to the following slide. Given that we operate in mining, I'd note that safety sits at the heart of everything we do. This line of work carries danger by its very nature. Even so, as you're able to observe, across each of our 3 major projects, our safety figures continue to decline, and we sit comfortably under the industry average — a number that makes us quite proud. We put in hard effort on this daily to foster a zero-harm culture throughout our organization. On to the next slide. This is a topic that gets me quite excited. The DRC is, as a matter of fact, a copper superpower that is rising. In my view, the DRC stands ready to pass Peru and become the world's number two copper producer. In 2023, the DRC accounted for 11% of copper mined globally. This really is the green metal of tomorrow. It's the place to be located. It's prime real estate. It's where you'd want to purchase your next home. We held an election in December.

Marna Cloete

executive
#8

President Félix Tshisekedi won reelection to a second term of five years. We were there for the inauguration. We are quite enthusiastic about what lies ahead for the country. We see considerable backing from all the superpowers around the globe to make sure the DRC enjoys stability. On a project level, so to speak, from an ESG standpoint, we treat what we do with great seriousness. We engage with our communities every single day. And we have also highlighted the Center of Excellence we launched last year, which is going to be a tertiary educational institution in the DRC. And then last but not least, and Alex will speak to this a bit later, is the Lobito Atlantic Railway Corridor. That has truly created a new gateway for getting our product to market. At present we are running trial shipments. We have reserved substantial capacity on this corridor. And we are monitoring this project, building strategic partnerships with the developers to make sure we can move our product. This will also make certain that our carbon footprint is even lower than it is today. So with that as a bit of a lead-in, I will now turn things over to David van Heerden, our CFO, to walk you through our annual results for 2023.

Matthew Keevil

executive
#9

Thanks, Marna. Good day to everyone who's joined us on the call today. Matt, if we move to the following slide, Kamoa-Kakula posted record annual revenue for 2023, at $2.7 billion. That figure reflects a weighted average realized copper price of $384 per pound. Revenue climbed from the $2.4 billion recorded in 2022. We delivered strong EBITDA of $1.7 billion, at a very healthy margin of 62%. Turning to the next slide on Kamoa-Kakula's unmatched cash flow generation, 2023 marked the third year in a row of outperformance at Kamoa-Kakula. On the left-hand side you can see EBITDA growth across those three years, while the graph on the right shows cash generated by operations, after excluding non-cash working capital. This makes it clear that, following an initial Phase 1 and Phase 2 investment of just over $2 billion, Kamoa-Kakula has returned $3.5 billion of cash in only 13 months. Just before we move to the next slide, I want to offer a helpful clarification: cash from operating activities was the same in 2022 and 2023. That is a coincidence, not a mistake. Moving on to Kamoa-Kakula's annual EBITDA waterfall, the waterfall shows that the move from 2022 to a 1.7 EBITDA in 2023 equates to 22% year-on-year EBITDA growth, driven principally by our increased production.

Matthew Keevil

executive
#10

The 2023 results also got a boost from the higher realized copper price that year, once provisional pricing is combined with prices ultimately realized, and cost inflation partly offset that. If we go a bit further into cost on the next slide, Kamoa-Kakula once again hit guidance, with 2023 finishing exactly at the midpoint of our initial 2023 guidance. Q4 2023 cash cost is slightly higher because of generator power used and the intermittent power affecting production, as draws were taken from the stockpile, which impacted the grade milled during the quarter. Looking ahead on the next slide, our cash cost guidance for 2024 is $1.50-$1.70 per pound of payable copper. Even with the temporary elevated cash costs, Kamoa-Kakula would still be well-placed on the global cash cost curve. The 2024 guidance is affected by the earlier commissioning of Phase 3, both because of the additional backup generation allowed for in the guidance due to the Phase 3 concentrator coming online before Inga II and because of the slightly lower grade expected to be fed through the Phase 3 concentrator. Completion of the on-site smelter, on schedule for commissioning in the fourth quarter of 2024, is expected to drive a decrease in average cash cost over the first five years post-completion from 2025 onwards.

Matthew Keevil

executive
#11

Moving on to the following slide, Matt, if we could. On the left-hand side you'll see that Ivanhoe's EBITDA has risen 23% compared with a year earlier. If we strip out the effect of the convertible notes revaluation and the deferred tax income from Kipushi that was recognized in 2022 from our profit, then normalized net profit for 2023 came in at $388 million. That represents a 30% increase over the $298 million recorded in 2022. With Phase 3 construction at Kamoa running ahead of schedule and Kipushi starting its ramp-up within just a few months, 2024 looks set to be yet another year full of record results. Let's advance to the next slide, please. Our capital expenditure during 2023 was effective — something clearly demonstrated by our projects sitting on or ahead of schedule and every one of them tracking on budget. In 2024, we will keep up our industry-leading investment growth. We have been busy arranging facilities for each of our projects, with $400 million of in-country facilities drawn at Kamoa-Kakula, the $150 million senior tech facility signed for Platreef in December 2023, and financing for Kipushi that we expect to be finalized in Q2 this year. On a 100% basis across our projects, we invested almost $2 billion in growth during 2023 alone. That figure is set to rise further in 2024.

Matthew Keevil

executive
#12

The money we put to work in 2023 and are putting to work now is already producing genuine growth, starting as soon as this year. If we turn to the next item. We closed out the year in a very solid financial position, holding $574 million in cash with very little current debt. The $1.2 billion of non-current debt we carry consists mainly of the $800 million tied to the convertible senior notes maturing in 2026 and potentially redeemable early in April 2024. Our net debt-to-EBITDA ratio is extremely small, which positions us ideally for the coming stage of growth in our growth story. At this point I'll turn things over to Alex Pickard, our Executive Vice President, Corporate Development and Investor Relations, who will begin the Operations and Project Update presentation.

Alex Pickard

executive
#13

Thanks, David. Hello, everyone on the call. As Marna said, we've got the whole team here to walk you through the tremendous strides we're making across our operations and our projects. So without further delay, let's go to the next slide. Kamoa-Kakula delivered yet another excellent operational year. As Marna noted, we turned out 393,500 tons of copper, which fell inside our guidance range. We're particularly happy with that result, I think, considering the power stability constraints we face in the DRC. Mark will give you far more detail on our power work, which is a really key focus for this year. In a sense, we truly view that production as unfinished business. With consistent power availability, we believe our copper output might have been as much as 40,000 tons or more higher. That's a very encouraging sign for when we do resolve that issue. Naturally, we finished the debottlenecking project at Kamoa earlier in the first quarter. The Phase 1 and 2 concentrators have since demonstrated the capability to run above a capacity of 10 million tons per annum on a clean run. Another positive is that our recoveries have come in above design, at 87%.

Alex Pickard

executive
#14

To some degree, that also mirrors how stable the power supply is. There is room to push things further. Steve Amos will walk you through Project 95, which we are launching and which we are very excited about, aimed at lifting those recoveries much higher. Then, to restate our guidance range for the year: 440,000 to 490,000 tons of copper in concentrate. That accounts for the Phase 3 mill being commissioned early. From the copper we produce at Phase 3, we will sell a share of the concentrate that arrives ahead of the smelter. We will also stockpile a portion to feed that smelter once it is available in the fourth quarter. With that, I will hand over to Mark Farren, our Chief Operating Officer, to take you through the power initiatives in the DRC.

Mark Farren

executive
#15

Thanks, Alex. Yeah, so power — I mean, over the past year especially, it's been something of a thorn in our side. And like Alex, I believe we've left roughly 40,000 to 50,000 tons of copper on the table owing to power. These are short-term issues, rarely — if you take it, if we put the whole thing in context. I'll begin on this first line regarding what we've done about backup power. Then I'll walk you through the longer-term initiatives we've undertaken and that we're following through on. So in the short term, we've decided to build enough generating capacity on site, which is obviously very expensive. And it's diesel. So it's not exactly clean either. But it's to lower the risk and ensure we have full redundancy within this year to run Phase 1, Phase 2, and Phase 3 under any conditions. That decision we made last year. And if you look at these dates over here, you'll see that by July, we'll have 128 megawatts. And by December, January, we'll have 210 megawatts of diesel on site. So under any conditions, we can run the three phases, the three concentrators, and the three mines.

Mark Farren

executive
#16

A complete 100% blackout from load shedding is highly improbable. That said, it has occurred before. And we do need to manage it. Let me advance to the next slide, which is arguably more significant. So in terms of our longer-term efforts, we have determined that Inga is a project we must finish. We selected a single turbine — the G25, a large unit rated at 178 MW. That project was chosen 2 years ago. It is now in execution. We will swap out that turbine and bring it into commission by Q4 of this year. That adds 178 MW to the grid. As part of this effort, we had to carry out a comprehensive study stretching from Inga all the way to the gate where our power feeds into the mine. That covers roughly 1,700 km across various areas to assess. We have found stability problems in the grid — the same grid — across the entire route from Inga to us. Through this work, approximately $200 million in upgrades are required to ensure that grid becomes stable and reliable. That work is currently in execution.

Mark Farren

executive
#17

We're partnering with the state utility to carry out these projects. So that project ought to be finished in 12 to 18 months. We've also got additional power lined up from Zambia. Getting that power organized has taken us a while. We're pleased to report that an agreement was signed today — a long-term one. Short-term agreements will come after that, ramping up the power from Zambia, and that gives us a clean hydropower source for our mine in stages, beginning at 15 MW and rising to roughly 100 MW this year. A longer-term plan calls for reaching 150 MW. Beyond the work we're currently doing to stabilize the grid and the added power from Inga and Mwadingusha that's already done, we'll be able to bring another 150 MW into that same grid. It will be stable. That comes on top of the capacity work I mentioned to you earlier — installing diesel generation as a backup. Overall, I think, looking at where power is headed this year, in 2024, we'll be able to stabilize power and ensure we have enough for Phase 1, Phase 2, Phase 3, and for our smelter.

Mark Farren

executive
#18

We're focused on how we'll expand the business across the coming couple of years. Additional power initiatives are coming to ensure we establish stability and sufficient energy to support the projects ahead. Yeah. So this matters a great deal to us, since we're taking this mine from the 400,000 tons we achieved last year up to probably 500, and beyond going forward, 600, potentially 800,000 tons of copper that we need to produce within the next four or five years. That's entirely within our control. Power has been something of a thorn in our side, but we're addressing it. And we've assigned, I think, the strongest project team to this, working together with SNEL, the local power utility. And I believe it will be carried out properly within this year. So that covers power. I'm going to ask Steve to say a few words about where we stand with Phase 3, Steven. Steve serves as our Executive Vice President of Projects. He's been with me. We've worked alongside him for at least 10 years. All these projects you see that are on time and on budget, that's basically thanks to Steve.

Mark Farren

executive
#19

Steve, could you give us some detail on Phase 3?

Stephen Amos

executive
#20

Okay, thank you, Mark. Hello, everyone. I believe Mark, Marna, and Alex have each mentioned that Phase 3 is progressing quite nicely. As a matter of fact, we're now as much as 4 months ahead of the planned timeline. So we've become quite skilled at this kind of work by now. Over on the mining side, we're occupied with getting the mine pad ready along with the run of mine that will feed the plant. There's a mobile crusher at the sites. We're currently hauling everything by truck from Kansoko, roughly a kilometer or two from here. We're assembling a sizable stockpile in advance of the plants. In all likelihood next month, we'll commission the surface conveyors. Those surface conveyors will carry the run of mine from the mine essentially over to the plants. Our plan is to accumulate 20,000-odd tons of stock before commissioning takes place for the plants. And there's ample time available for that. We have a number of months in which to do it. Then June, yes, we feed the plants first, all of it into the mill over the course of June. And after that, I'd say, once everything is inside the mill, it's entirely a matter of ramp-up. With Phase 1, we performed very well. We brought the plants up to speed within 3 months. On Phase 2, we did even better.

Stephen Amos

executive
#21

We brought the plant up in 2 weeks. So Phase 3 should deliver something good, in my expectation. Our track record, I think, kind of demonstrates that we'll reach steady state fairly fast. From the picture, I think you can see that mechanical completion and all equipment installation are done. We're busy with the last bit of electrical installation, cable pulling, etc., etc. Some of the substations have been energized, and we're busy pumping a couple of motors to get things moving quite quickly. Next, please, Matt. Sorry. On my side it hasn't changed. Oh, there we go. Sorry. Yes. Okay. So there's a bit of a lag. Okay. So this is something quite exciting. We call it Project 95. And the reason for Project 95 is that the objective, and there are 2 fronts to it, is to raise copper recovery from the current 88-odd to 95%. We've been working on this for about 6 months now. So a lot of work has been done in the lab. And the lab work is nearing completion. The 2 aspects to this are, firstly, modifying the existing Phase 1 and Phase 2 plants, additional regrind capacity, a Flash Float, a couple of other odds and sods to improve recovery from 88 to 95.

Stephen Amos

executive
#22

As I mentioned, the test work is nearly finished and the results look very encouraging. Since this is an operating brownfield site, the way we'll carry it out is much like the debottlenecking work we did during planned shutdowns. We'll perform all the construction within planned shutdowns. We'll complete the tie-in during those shutdowns. That way, there will be minimal impact on existing production. The second part of this concerns the current arisings — the tailings we're generating now — along with the tailings sitting in the tailings dam. So what we've also done over roughly the last six months is design a process that lets us take those tailings, regrind them, and achieve around 60%-70% recovery from that feed into the new plant. That's a greenfield standalone plant. And that effectively lifts recovery to 95%. We believe there are about 30,000 tons per annum in those current arisings, plus what's in the dam, and then some additional recovery from the modifications to the existing plants. Everything is on track. Probably around April, we'll have some basic engineering. We'll have a cost-budget estimate. We'll obtain approval. And we'll fast-track this as soon as we can.

Stephen Amos

executive
#23

Moving on to the smelter now, Matt — thanks. It's state-of-the-art, with capacity of 500,000 tons per annum, using Outotec direct-to-blister technology — the largest direct-to-blister smelter anywhere in the world. Emissions and environmental legislation are all world-class, following IFC and World Bank principles. So there's absolutely zero pollution going into the atmosphere from this smelter. This has been a massive job — it's in a completely different league compared with a concentrator. We're bringing 73,000 tons of equipment in from abroad, right into the heart of Africa. Roughly 50% is already on site at present, and about another 25,000 tons is on its way. So things are looking good. It's great when you can actually see the equipment sitting on site, particularly in the middle of Africa. We're confident about our Q4 2024 startup, with commissioning in Q4 2024. There's also a significant drop in cash costs — we estimate around 20%. And with this, just think about it yourself: shipping 50% of the copper out of the country rather than shipping 100% of the copper out of the country cuts your transport in half. On top of that there are taxes and a TC that come with it, plus a significant amount of asset production, which is kind of the commodity in the DRC, since the bulk of copper producers leach oxide with acid and make copper through solvent extraction and electrowinning.

Stephen Amos

executive
#24

Let's go to the next slide, Matt. And I believe it's Alex's turn now.

Alex Pickard

executive
#25

Yes, thanks, Steve. So at the end of the year we made a landmark announcement: we began trial shipments of copper concentrate from Kamoa-Kakula along the Lobito Rail Corridor. The Lobito Corridor is a project that the U.S. government, along with the European Union and the G7, has backed very publicly. And the good news is that shipments so far have been a big success. A one-way journey has taken us just eight days, which is under one-third of the time needed for the alternative, exporting by truck through Durban or Dar es Salaam. And obviously that reflects the shipment moving by rail, but also the overall distance involved. It's nearly half the distance of the trip to Durban. So ultimately, what this should mean is that shipping costs will certainly come down over time. But it's also important to note that the CO2 emissions tied to rail transportation are much lower. At Kamoa-Kakula, we're very fortunate when it comes to the grade we have and the hydropower. We already have the lowest CO2 emissions of any major copper mine. Those are set to fall by approximately half once the smelter is commissioned and the logistics burden is reduced, as Steve mentioned.

Alex Pickard

executive
#26

And shipping via the Lobito Corridor is going to cut that down even more. As for what comes next at Lobito, we recently put pen to paper on a reserve capacity agreement with the Lobito Consortium, which Trafigura leads. That deal covers shipping as much as 240,000 tons of copper product. Starting next year, that copper product will mostly be 99.7% anode produced by the smelter. Lastly, it's worth flagging that the Lobito Corridor runs right through the Western Forelands exploration licenses. So it's going to matter a great deal both for building future mining operations and for exporting copper products. That probably leads nicely into the next slide. Turning to exploration across the group, we said late last year that we had quadrupled drilling in the Forelands from 2024 to 19 million. Beyond that, we're starting to drill the Mokopane Feeder Project, which sits next to Platreef, and we're also doing early-stage exploration on our new licenses in Angola. As a group, what Ivanhoe Mines strongly believes in is driving the highest possible return on capital for our shareholders. I think we've shown that across every one of our projects, Kamoa-Kakula included, which this team effectively built on exploration.

Alex Pickard

executive
#27

So we’re expecting the drill bit to create enormous value during this year. Late last year, we announced the success already achieved with the first copper resources at Makoko and Kiala, and those are already significant on a global scale. We’re advancing them into more of a study phase. And then, naturally, we also announced our Kitoko discovery, which our founder, Robert Friedland, will now describe far better than I’m sure I can.

Robert Friedland

executive
#28

Okay, everyone on this call — exploration is really the lifeblood of mining as an industry. I wanted to take a few words to explain why the Congo has so rapidly become equal to or larger than Peru as the world's second-largest copper producer. These are sedimentary copper deposits. They share quite a lot of similarities with oilfield geology, actually. They occur in basins. I wouldn't describe it as a bathtub, but perhaps the shape of a bird feeder. In this case, the basin measures roughly 150 to 175 kilometers in length and 25 to 40 kilometers in width. If you could picture that as a giant bathtub or bird feeder, very shallow. If you filled that bathtub with layers of sand of different colors — if you filled your bathtub with two inches of red sand, then two inches of green sand, and two inches of blue sand, gradually laying these sands inside the basin — the original discovery of copper at Kamoa was in a particular sand on the basin's eastern side. We were astonished that we had an ocean of 3% copper. The second copper discovery was Kakula, much higher grade, 4.5%-5.5% copper, and an ocean of it. These flat-lying deposits, when you find them, they can be many, many kilometers long.

Robert Friedland

executive
#29

These can extend 10 or 15 kilometers in length and 10 or 15 kilometers in width. They are extremely consistent. They sit there much like a potash mine or an oilfield. So it is quite remarkable that, when we headed to the western side of the basin at a relatively shallow horizon, we encountered Makoko in sands that resemble the sands hosting the original Kamoa discovery, roughly 30 kilometers to the east. And then, over time and with continued drilling, Makoko grew to about 11 kilometers long. It remains open. And we discovered a second Makoko, stacked in the manner of distinct layers within a layer cake. And through additional drilling, we progressed deeper and deeper into the basin. And we eventually identified two stacked new horizons named Kitoko, which means beautiful or gift in the local languages. The deepest hole we have drilled all the way to the bottom of the basin is returning over 11% copper, right at the basin's bottom. This has never occurred before across this enormous target area. This is an entirely new horizon. As of today, it is approximately 2 kilometers open and open in all directions. It is nearly flat-lying, yet it is open up dip and along strike in virtually every direction and open down dip too, with a very, very shallow dip, as we have shown in numerous cross-sections.

Robert Friedland

executive
#30

Kitoko’s metallurgical traits, visible in this image, are nearly the same as Kakula’s. Bornite and chalcocite—the highest-grade copper minerals—show up there, and they appear in huge amounts. Then, to confirm that the first discovery hole, which came in above 11%, wasn’t just luck, we recently inserted a wedge into that hole and drilled outward from it, and once more we hit the same horizon at well above 11% copper. So it is consistent. It is real. It is open in every direction. And it demonstrates that the land position can generate several further Kakula-type discoveries. I believe those of us in the geology community who grasp sedimentary copper think we might keep locating more deposits of this kind for generations. The biggest value we can create for shareholders is to bring in additional drill rigs. Right now we have 7 rigs operating. Very soon we will have 2 more running. That is even though we are in the rainy season. Years ago, we would have halted drilling during the rainy season. This one, though, has us genuinely excited. The rainy season will be over in another 2 or 3 months.

Robert Friedland

executive
#31

Even so, we will definitely have nine drill rigs operating on this ground. That will generate substantial value, since Ivanhoe Mines holds this land along with a handful of joint venture partners owning minority stakes. This enormous area truly represents a very promising future for us. If a reason ever existed to take interest in what we're doing to address the worldwide copper shortage that's approaching—whether for electrification or national security—this is the place where you'll find it. In this Western Forelands region, there's brand new railroad service running directly to that port in Angola. And it's all downhill, incidentally. Within the Western Forelands, we sit at 1,400 to 1,600 meters in elevation. Obviously, we're headed to the Atlantic Ocean, which is at sea level. As those trains travel toward the seacoast, they'll actually be able to produce electricity on the way down. Over the past 20 years, we've gained an enormous amount of knowledge. We understand how to construct mines in this area. Hydroelectric power has already been built out. Being close to an operating mine gives us every advantage, letting us accomplish everything faster, more quickly, at lower cost, and better than we managed before.

Robert Friedland

executive
#32

Therefore, the destiny of Ivanhoe Mines and copper is to be found in the Western Forelands. And I'm pleased to report that, when it comes to our annual results, our team is as enthusiastic as can be. That is the reason we have increased our exploration budget by four times this year, bringing it to roughly $90 million. With that said, I believe I will now hand things over to Mark Farren, so he can share our fresh thinking and our fresh plans for speeding up production at the biggest combined precious metals and base metals mine on earth, which is Platreef. So, Mark, over to you.

Mark Farren

executive
#33

So we went from one great mine over to the other. And I realize the PGM space is somewhat the ugly sister to the bull market it's experiencing at the moment. But let's discuss Platreef a little, just a bit about how the actual ore body looks first, before I get into the phases. So the ore body — what makes this one different is that it's 20 to 25 meters thick, versus the rest of the Bushveld Complex, which averages about 1 meter thick, and with the same grades, the same grades. So you're still looking at your 4 to 5 grams per ton, 4E, plus enormous nickel and copper credits. So you have roughly 0.3% nickel, which sets it apart enormously from anything else given the thickness of this ore body, which makes it entirely unique and suited to mechanization and automation throughout the ore body. I spent about 23 years at Anglo Platinum. I can tell you right now, speaking for myself, this is the best ore body in the world, no question. It has the grade. And it has the thickness compared to anything else. So what we did is we began with a phase one, which we refer to as a baby mine.

Mark Farren

executive
#34

It's a test mine. It's simply a setup we've assembled, involving a concentrator that Steve will walk you through in a moment, so we can get ourselves going and gain an understanding of the ore body. As we get moving on phase one, we've asked how we can speed up development of this mine. How can we speed this development up and bring phase two, along with a meaningful level of production, in as early as possible? That big shaft you can see behind us in the picture is essentially the phase three portion. It's an enormous shaft. It will be capable of hoisting 8 million tons a year. For phase one and two, we've tried to use them to optimize what we have within the footprint before this enormous shaft is in place. Phase one and two combined will give us the potential to hoist 3 million tons and therefore process 3 million tons rather than the 1 million tons odd that you're going to get out of phase one. The work we've done really now is to be able to speed up phase two and then also begin looking at phase three. At the end of the day, we'll have at least a 10 million ton operation running there, which is over 1 million ounces of 4E and huge credits of nickel.

Mark Farren

executive
#35

On the timing side, a PEA and an FS will both be finished. The phase two FS should be done by mid-year — quarter three at the latest — along with a PEA for the 10 million ton case that we're currently working on. And even as we discuss these items, we're already in execution mode. A great deal of work is underway right now to de-risk phase two and phase one and to speed up development of the mine. Another point worth mentioning, I think, is that we needed to place a portion of the offtake. For phase one, that placement has gone to Northam. And for phase two, we've been able to place a big chunk with Sibanye. We have terms for that — very favorable terms in the South African market. Further downstream, we'll be working as a joint investment alongside other big players in South Africa on some in-house beneficiation. So all in all, I think, when you look at what we hold — the best platinum ore body in the world, accelerated development, and first quartile — Alex, if you could just show the Q1 cost position, or where it's headed, on the next slide. From that next slide you'll see it is actually going to be the best placed, lowest cost producer in the world.

Mark Farren

executive
#36

That comes down to the fact that this ore body lends itself well to mechanization and automation. The ore body is extremely thick. Its grade is very high. Nothing comparable to this ore body exists anywhere else in the world. I am certain of that, since I have spent a very long time in that space. Okay. Let's proceed. Steven, will you continue? Please provide an update on the construction and where things stand.

Stephen Amos

executive
#37

Yes. Matt, if you could advance to the following slide. So regarding the concentrator build, we're roughly 80% done. This plant will be cold commissioned in August this year. After that, we'll begin starting the plants up on run of mine H1 next year. What you're looking at is the phase one plant. The phase two plant is going to sit next to this one. It'll be comparable in size to Kamoa phase one, giving a total of 4 million tons of run of mine treatment, phase one plus phase two. That should deliver roughly half a million ounces of 3E plus gold along with about 10,000 tons of nickel production. The mine footprint also has room for the phase three concentrators. Perhaps I could just add that we've recently secured water for the mine. We redid a water treatment plant called Masodi a few km away from the mine. And we're now receiving clean water for the mine. And our connection to the Eskom grid is imminent. We've just constructed a 28-kilometer line from a Borutho substation onto the mine. So everything going well at Platreef. Focus on phase two and phase three. Thanks, Matt. That's all from me.

Stephen Amos

executive
#38

Moving to the following slide, please. At this point, I believe Mark takes it from here.

Marna Cloete

executive
#39

Now it's my turn to speak.

Stephen Amos

executive
#40

Apologies, Marna.

Marna Cloete

executive
#41

Sure, no problem. So perhaps a quick word on Kipushi first. We said earlier last year that we had agreed the terms for offtake. But it caught us off guard how attractive the conditions were that we could secure locally for financing. As of today, we have closed an $80 million facility with one of the banks in the region. Another facility with a local bank is very near to being finalized. Beyond that, we have also opened talks with several offtake partners. Those talks are close to wrapping up. A prepayment component tied to the offtake will be part of it. And the overall facilities we intend to raise for Kipushi would come to roughly somewhere between $100 million and $200 million, to help with working capital. We are also getting ready to take on logistics for Kipushi ourselves. So we have established our own logistics company. Logistics will be managed in-house by us, on delivery-at-port terms with the offtakers. Moving to the next slide, I think Mark will briefly cover the mining that is happening at Kipushi right now. Then Steve will walk you through the project update.

Mark Farren

executive
#42

Thanks, Marna. Yeah. So the underground at Kipushi is, if you're into mining, a really lovely mine. It uses long-hole stoping. The ground conditions are fantastic. It's been completely de-risked. We've already opened up seven levels for the long-hole open stoping. And we've built a stockpile on surface, which people might find amusing. I mean, low grade — we're calling it 22%, 220,000 tons of ore, which at 22% we call low grade. The mine's grade averages 35%. So as zinc ore bodies go, it's a fantastic one. And it's well set up. Again, Steven will speak to you. We're ahead of schedule on the concentrator. The mining footprint is ready to go. And I don't believe there's any major risk that there will be at Kipushi. Steven, do you want to talk a little bit about the concentrator?

Stephen Amos

executive
#43

Yes. Mark, could you advance to the next slide, please, Matt? Yeah. So we're really enthusiastic about Kipushi. At Kipushi, we've changed the landscape entirely. It genuinely looks superb. We're running a touch ahead of schedule — roughly the same timeline as Kamoa — commissioned in June, and we're currently occupied with the final electrical installation plus energizing the substations. The process is extremely straightforward. I mean, if you take a quick look, the entire plant has five float cells — very easy metallurgy. And the design throughput is 800,000 KTPA. But I think what we'll likely do is a debottlenecking exercise and raise that quite substantially. Still, everything looks good for Kipushi. No problems at all. Really enthusiastic about Kipushi. Thanks.

Marna Cloete

executive
#44

I appreciate it.

Robert Friedland

executive
#45

My apologies. Operator, please proceed.

Operator

operator
#46

Ladies and gentlemen, just a reminder that to ask a question, you press star 11 on your phone and then wait for your name to be announced. If you'd like to withdraw your question, press star 11 once more. Please hold while we put together the Q&A roster. The first question is from Andrew Mikitchook at BMO Capital Markets. Your line is open.

Andrew Mikitchook

analyst
#47

Morning, and congratulations on all the updates packed into this press release and on the hard work behind them. Looking ahead, once that power comes in from Zambia and Inga, along with the on-site backup power and the rail, do you see any chance this leads to some rethinking or optimization of the mine plan for Kamoa phases one, two, three, and I suppose four?

Mark Farren

executive
#48

Yes, absolutely, Andrew. What we're doing now — and it will be announced over the next couple of months — is the same thing you saw with phase one and two. For phase three, we'll also do debottlenecking. And I think we can probably tweak up that production on all three concentrators to. It's a 7 we call it 14, but it's probably going to end up being 16 or 17, plus all the recovery work that we're doing. And that's a few extra megawatts. And that gives us a little bit of time to get stability into the grid. And then time, phase four. Phase four when we want to. And I think it's in about 2 or 3 years' time we need to start executing. So no risk, I don't think, short term. But power is the issue that we need to just get over the line with.

Andrew Mikitchook

analyst
#49

Alright. And my second question is about exploration. It's clearly quite encouraging that Kitoko is seeing further progress. What sort of timeline should investors anticipate for updates and for moving this forward at the usual torrid Ivanhoe pace?

Mark Farren

executive
#50

Robert, would you like me to take care of that?

Robert Friedland

executive
#51

Classic relentless Ivanhoe speed. So, we discovered 50 million tons of copper — the highest grade, and the biggest copper mine located anywhere on earth in recent memory, no question. We don't plan to slow that down at all. We've got every possible reason to locate additional copper across the Western Forelands. So we're discussing 500, 600, 700, 800 thousand tons of copper annually on our original joint venture ground. That sits on 400 sq km. And we're now into designing and developing new production at Makoko and Kitoko. So off we go. Drilling will continue. And should it grow larger, we'll simply bring in more drill rigs and carry on. As I mentioned earlier, this will move faster than before. When we began 25 years ago, the DRC Congo was a very different place from what we have now. Now, we've got 4G wireless. We've got a new international airport. We've got fantastic access. We've got a brand new railroad running downhill to the ocean. We're going to have too much electrical power rather than not enough. I suppose a good way of putting that is we don't really face a copper shortage. We can find copper faster than we can build the concentrators to bring it to market.

Robert Friedland

executive
#52

Concentrators can be constructed by us more quickly than smelters for producing copper metal. Around the globe, no copper company is expanding at a quicker pace than ours, and we mine ores of the highest grade while emitting the least global warming gas for each unit produced. Why would we stop? We have 20,000 people working there. In the Congo, the median age of a person is under 19 years. The workforce is fantastic. The backing from the government for our training programs, our environmental programs, and our ESG programs has no equal. So I believe the only thing left is to get you out there, Andrew. You can stand at the drill rig and watch this core arrive from the Kitoko discovery. And even though I'm a grandfather, I have to tell you, discovering something like that is as exciting as anything you accomplish in life, even for any geologist. A lot of geologists go through an entire lifetime and never come close to a discovery such as Kakula or a Kitoko. So we're going to put the pedal to the metal and help the Congo reach its rightful position as the biggest producer of copper worldwide. Without a doubt, that is achievable. The power line we brought in from the Inga dams is capable of carrying 900 megawatts.

Robert Friedland

executive
#53

We produce nearly 400,000 tons of copper using 78 MW. When you pair the planet's highest-grade copper ore bodies with hydroelectric power, you end up with truly green, long-life power. That's unbeatable. So thank you, Andrew, for your enthusiasm and interest, and for your support over the years. Let's extend that to everyone at BMO. BMO has been a big supporter of all our efforts, especially since we're talking to you today from the BMO conference. As a matter of fact, in roughly 15 minutes I'm due to head downstairs and deliver a speech. Thank you, Andrew.

Andrew Mikitchook

analyst
#54

All right. No — thanks, Robert. I’ll be signing off too and passing the mic along to somebody else. Thank you.

Marna Cloete

executive
#55

Thanks. Just a quick reminder, everyone: to ask a question, please press star 11. We'll now wait for the following question. Lawson Winder of Bank of America Securities is next in the queue. Your line is open.

Lawson Winder

analyst
#56

Much appreciated, operator. Morning, Robert and everyone. Thanks for the update today—great as usual. I just had a question about those temporarily elevated cash costs and what 2025 looks like. In the prior quarter, you had a 20% cut compared with, I believe, the midpoint of the 2023 guidance. That would suggest roughly $1.15 per pound. I just want to confirm my figures are about right.

Robert Friedland

executive
#57

Sure, let me try to address that, since I think there's a lot of confusion out there. To date, we've built 78 megawatts of hydroelectric capacity. The good news here is also the bad news. We've gotten this concentrator completed at least six months sooner than the timeline we shared with you last year. I can't name anyone else who is constructing tier one mines ahead of schedule. Can you? So with the concentrator commissioning in June, we'll need to burn diesel for six months until the Inga dam is online. So we won't be burning diesel once the Inga dam comes online. And we've just announced — we signed an agreement today with Zambia to import hydroelectric power. So this power constraint, this limiting factor, is disappearing. So once the smelter is operating and the Angolan railroad is operating, we save roughly $0.20 per pound on transportation costs, because we're moving half the volume, shipping 99% copper rather than shipping 50% copper. That halves the cost per pound. We're going to get the benefit of sulfuric acid. The price of sulfuric acid leasing is very high in the Congo. As the copper price rises, the price of sulfuric acid in the Congo rises as well.

Robert Friedland

executive
#58

There's a leverage benefit here, since everyone is clamoring for sulfuric acid for their oxide copper operations. At present, the Congo uses 6 to 7 million tons of sulfuric acid annually. That figure, however, is climbing. So our smelter might be able to supply 10% of the Congo's needs. That's why I believe the pricing we've assumed for sulfuric acid sales is quite conservative. So with 100% hydropower running and three mills operating beyond their nameplate capacity, I think $1.15 is a completely realistic target. I'd put it at $1.10-$1.30. And the middle of that range could be $1.20 or $1.15. That seems right to me. Would anyone else on our team care to weigh in? Yeah?

Mark Farren

executive
#59

That's right, and that covers it.

Robert Friedland

executive
#60

Right, and Mark is on the same page. That target makes sense. In dollar terms it sits right at the lowest point of the global cost curve, yet on the measure of greenhouse gas emitted per unit of copper it is also at the very bottom of that worldwide curve, and for that we will command a premium. We have no doubt at all that clean copper will earn us a premium. That show is coming soon to a theater near every one of us.

Lawson Winder

analyst
#61

All right, I really appreciate that background. I’d also like to say congratulations on securing the deal with Sibanye. It’s good that there’s potential for it to grow. What are you considering regarding the alternatives for treating what’s left of the phase two concentrate from Platreef? And could a base metal refinery be something Ivanhoe might construct later on? Or is the matte that’s been proposed the way to avoid needing to do that? Many thanks.

Robert Friedland

executive
#62

Marna and Mark, could you speak a bit—without naming anyone—about what those conversations regarding moving further downstream are actually like?

Mark Farren

executive
#63

I'll bring Alex in here. But when it comes to phase two, Alex, I really don't think we'd take that risk. Do you want to pick it up from there?

Alex Pickard

executive
#64

Mark, I completely concur. For phase two, particularly since we have adjusted the scale to fit within that hosting capacity of 4 million tons, it's clear to us that the South African market will have room for that concentrate. Beyond that, our focus is really on a joint venture partnership for downstream processing, which aligns more with phase three. Once shaft number two—that massive facility—is available to us, we can raise processing capacity as high as 10 million tons per annum. At that stage, we would be either the largest PGM mine or among the very largest, as well as a major producer of nickel and copper. That is what ends up being the constraint when it comes to base metal refinery capacity in South Africa.

Andrew Mikitchook

analyst
#65

What we're considering is possibly, well, either constructing a greenfield facility or, even better, repurposing an existing brownfield site in South Africa — and there are plenty of strong candidates there — which could deliver meaningful savings in time and CapEx. Then the concept is that we'd turn out a nickel matte. So that's roughly 50% nickel by content, PGMs included. And that product then becomes far more marketable on the international stage to a range of different refineries.

Mark Farren

executive
#66

We believe phase two is behind us now. After that, phase three is clearly the decision point we have to make. Right.

Lawson Winder

analyst
#67

All right, many thanks to everyone.

Marna Cloete

executive
#68

Thanks. I’m confident there are no more follow-up questions. At this point, I’d like to hand the call back to Matt.

Mark Farren

executive
#69

Much appreciated, Operator. We're nearing the top of the hour, so I believe this is a good place to end things. As Robert said, he needs to dash off to deliver his keynote speech here. So we'll conclude today's session. I want to express my thanks to all of you for being with us. Should you have any questions that went unanswered during the call, please get in touch with the IR team — Matt, Alex, and myself. We'd be glad to track down those answers for you. We're anticipating a very exciting 2024. Thanks once more for being with us. We can close it out, Operator.

Operator

operator
#70

That brings us to the end of today’s conference call, everyone. We appreciate all of you for joining in. You’re welcome to disconnect at this point.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Ivanhoe Mines Ltd. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Ivanhoe Mines Ltd. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ivanhoe Mines Ltd. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.