K92 Mining Inc. (KNT) Earnings Call Transcript & Summary
August 13, 2024
Earnings Call Speaker Segments
Operator
operatorAppreciation for holding. I’m the conference operator, and I’d like to welcome everyone to K92 Mining’s conference call on financial results for the 2024 second quarter. Please note that everyone joining is in listen-only mode and that this conference is being recorded. Following the presentation, there will be a chance to ask questions <<operator_script>>. At this point I’ll hand the conference over to David Medilek, President and COO. Please proceed.
David Medilek
executiveThanks, operator, and thank you all for joining us for K92 Mining's conference call on our 2024 second quarter results. We hope you and your families are doing well. Joining me on the line are John Lewins, Chief Executive Officer and Director, and Justin Blanchet, Chief Financial Officer. I'd also like to remind everyone that following management's remarks, we'll hold a Q&A session. Since we'll be making forward-looking statements during this call, please refer to the cautionary notes and risk disclosure in our MD&A and on Slide 2 of the webcast presentation. Also, please keep in mind that unless otherwise noted, all dollar amounts discussed on this conference call are in United States dollars. Now, I'll hand things over to John for an overview.
John Lewins
executiveThank you, David, and welcome everyone. We begin with safety, K92's number one priority. At the end of the second quarter, K92 marked a major achievement with zero lost time injuries recorded over the last 12 months. Over this period, two independent safety audits were conducted. From these audits, a number of actions were identified and many actions have been taken and completed. Safety technology on site has been enhanced, including the introduction of in-cab monitoring and proximity and collision avoidance system with more systems planned for the future. Culturally, there's also been multiple positive leading indicators. For several consecutive quarters, there has been a significant increase in job safety assessments to reinforce our safety mindset and a number of safety warnings from our in-cab monitoring system has actually significantly reduced. Changes to personnel have been made where required, resources have been and are being expanded for safety and training. As stated on previous conference calls, we take the increased lost time injury frequency rate in 2023 very seriously, while also noting that historically K92 has operated with one of the best safety records in Papua New Guinea and the broader Australasia region, as shown in the chart. I'd like to reiterate that K92 relentlessly pursues our goal of achieving zero harm amongst our workforce.
John Lewins
executiveK92 was very happy to announce its 2023 sustainability report back in June. This report expands on earlier editions, strengthening what we disclose on ESG and how we align with the global frameworks of SASB and TCFD. It underscores K92's firm dedication to ESG and to the people and the country of Papua New Guinea. That covers our emphasis on hiring and developing local content, with roughly 94% of our workforce being Papua New Guinean nationals, including a majority drawn from our local communities. It also reflects our solid commitment to backing the local economy, including 24.5 million of expenditure to local support joint ventures and procurement of 105 million incurred in Papua New Guinea, which represents 56% of our total procurement for the mine; our delivery of significant benefits to the country with $26.8 million of taxes and royalties paid plus $0.8 million in direct community investment; and our commitment to combating climate change with a mission reduction target set for 2030. So K92 takes great pride in the positive impact it is having on the prosperity and development of Papua New Guinea, and we encourage you to read our report found at www.K92mining.com. In May 2024, K92 reached a major milestone with the commencement of its inaugural infrastructure tax credit scheme project to upgrade the <<inaudible>> road.
John Lewins
executiveThis 6.6 million project—which includes $0.5 million for general administration tied to the project itself as well as other ITCS projects—should be transformational for a lot of our communities, giving them reliable and efficient sealed road access to the main road network. It also creates plenty of opportunities for our community, such as more trade and business development. That picture on the right shows a groundbreaking ceremony attended by the Honourable Simon Tear, Governor of Eastern Highlands Province, and K92's VP Government and Community Affairs, Philip Samar. The project is funded through a tax credit scheme, with as much as 2% of assessable income to be allocated by K92 toward government-approved community projects and deducted from future corporate tax payable. It's a great program. We're proud to be involved, and we look forward to positively transforming infrastructure in our local communities through this project and many others ahead. Turning to operational performance. In the quarter, the Kainantu Gold Mine produced 24,347 ounces gold equivalent. As we announced previously, output for the quarter was affected by the temporary suspension of underground operations for roughly a month beginning in mid-March, following a Form 29 issued by the Mineral Resources Authority of Papua New Guinea relating to a non-industrial fatal incident that happened on site, and this had a significant impact on March and April production, since underground operations had to be re-ramped up and processing stockpiles had to be rebuilt from scratch.
John Lewins
executiveFor the quarter, we processed 95,582 tonnes at a head grade of 8.5 grams per tonne, with a cash cost of $919 an ounce and an all-in sustaining cost of $1,510 an ounce. As the chart notes, all-in sustaining costs have stayed elevated over the last few quarters while the company keeps investing considerably in the Stage 3 expansion, especially in 2024, and costs are expected to come down considerably once that expansion is delivered. I think it's important to highlight that before the non-industrial incident, Q1 was on track to be one of our strongest quarters on record, and there are a lot of positives to take from that going forward. Operational performance in May and June was strong. And as we outlined in our operational guidance earlier in the year, the second half of the year is expected to be our strongest. We reiterate our 2024 operational guidance. In terms of key operational quarterly physicals, K92 has shown over several years that it can sequentially expand the operation, with physicals in the first half of the year clearly affected by the temporary suspension of underground operations that hit in March and then in April.
John Lewins
executiveFor the first six months of the year, the process plant remained a significant operational strength. Multiple monthly, weekly, and daily throughput records were achieved at the process plant during Q1 — surpassing 2A throughput by 35%, 57%, and 75%, respectively — which clearly shows that when supplied with tonnes from the mine, it performs extremely well and offers considerable optionality moving forward. Those records also underscore the potential of the Stage 3 process plant, designed using the same throughput parameters as the Stage 2A process plant, to greatly exceed its 1.2 million tonnes per annum nameplate design. Records for metallurgical recoveries were set by the process plant in Q2. As the bar charts show, gold and copper recoveries came in significantly above both 2023 and Q1 2024 and, importantly, above the assumptions in our integrated development plan. Further recovery upside is expected once the Stage 3 process plant now under construction is delivered, given its more optimal design. I'll now hand things over to our Chief Financial Officer, who will cover our financial results.
Justin Blanchet
executiveTurning to the figures, that was $2,246 versus 28,141 ounces, with an average selling price of $1,883 in the prior year. As of June 30, 2024, inventory held 4,968 gold ounces, covering both concentrate and doré — a rise of 3,291 gold ounces from March 31st, driven by the timing of sales. In Q2 2024, cost of sales came in at $27.7 million versus $29.2 million a year earlier, or $19.4 million against $21.8 million once non-cash items are excluded. The decrease in cost of sales stems mainly from lower variable costs, such as consumables and haulage tied to throughput, which fell relative to 2023. Cash flow from operating activities before working capital changes during Q2 2024 reached $17.3 million, compared with $16.2 million in the prior year. At June 30, 2024, cash and cash equivalents stood at $71.1 million, and we spent $29.8 million on expansion capital during the quarter. Our working capital balance was $91.7 million, and net debt on the balance sheet was $38.9 million. In June, K92 set up two credit facilities with Trafigura — called a loan in the financial statements — allowing borrowing of up to $120 million, with an accordion feature permitting an increase to $150 million.
Justin Blanchet
executiveBy June 30th, K92 had pulled $40 million from the loan and has drawn another $20 million since then, for $60 million altogether. Nothing restricts the remaining $60 million available under that loan. In addition, the $20 million of restricted cash on the balance sheet that serves as security for the loan is able to become unrestricted on January 1, 2025, which gives us access to a further $80 million. As John noted in the second quarter, the Kainantu Gold operations turned out 21,661 ounces of gold, 1,246,639 pounds of copper and 26,754 ounces of silver, equal to 24,347 ounces of gold equivalent. We sold 19,064 ounces of gold, 898,578 pounds of copper and 18,467 ounces of silver. Cash cost came in at $919 and all in sustaining cost at $1510 per ounce of gold, both well under the $2,246 per ounce price at which we sold. Our second quarter cash cost per ounce rose to $919 from $597 in 2023. That rise reflected a higher cost of sales stemming from expenditures made during the temporary suspension, which were charged directly to cost of sales, along with smaller amounts of development and fewer byproduct credits. It is worth noting that cost will face downward pressure through economies of scale as operations ramp up and the Stage 3 expansion is finished.
Justin Blanchet
executiveI'll hand things over to John now so he can pick up the remainder of the presentation.
John Lewins
executiveThanks, Justin. Starting with the exploration and growth section, we'll open with an update on the Stage 3 and 4 expansions, which are set to fundamentally transform K92 into a Tier 1 mid-tier producer by sequentially raising output to 300,000 ounces per annum and then to 470,000 ounces gold equivalent per annum. Importantly, this transformation is happening near term, with commissioning of the Stage 3 process plant planned for Q2 2025. Delivery of the Stage 4 expansion remains on track, targeting late 2026. As at the end of July, 57% of Stage 3 and 4 growth capital has been either spent or committed. And as a reminder, the process plant is the largest growth capital package, and that was awarded in July 2023 on a lump sum fixed price basis, which significantly de-risked the project for K92. Both the Stage 3 and 4 expansions are fully financed from existing cash, cash flow and credit facilities. In June, we announced the establishment of $120 million credit facilities with Trafigura, upsizing from the previously announced $100 million. In addition to this, there's an accordion feature to increase the aggregate amount under the credit facilities to $150 million, well positioning K92 with not only significant liquidity for Stage 3 and 4 expansions but also enabling the potential to add significant value through exploration during this construction period, which I'll discuss later in the presentation.
John Lewins
executiveLike Justin mentioned, by the close of Q2 we had pulled $40 million from these facilities, plus another $20 million after quarter end. There are no restrictions on the $60 million that remains available to draw under the loan, and on top of that there's $20 million of restricted cash that becomes accessible starting January 1, 2025 — giving us $80 million in total available liquidity. At the same time as the credit facility closed, we also finalized our new off-take agreement with Trafagura, our off-take partner since operations began. This new off-take arrangement and the upsized credit facilities strengthen the solid long-term relationship we have with Trafagura. The off-take is an innovative structure, locking in competitive terms on metal spot prices, favorable payment arrangements, and better metal payabilities. Later this year, we intend to update our integrated development plan to capture these improved off-take terms as well as our considerably larger mineral resource, which grew by nearly 50% once depletion from the latest economic study is taken into account. On the Stage 3 construction side, we'll start with a 3D animated flyover of the process plant design covering the full circuit, with the dry end of the circuit shown in the distance and the wet end up in the foreground.
John Lewins
executiveThe flowsheet is a standard single-stage crush, SAG, ball setup, using gravity and flotation recovery to generate doré plus a gold-copper concentrate. We’re now getting much nearer to the plant itself, beginning with our single-stage jaw crusher’s crushed product, which then goes to a surge bin, with additional material over the stockpile reporting to a dead stop-up. Reclaimed crushed ore then reports first to the SAG mill, and the discharge from that reports to the ball mill. The mill product goes through gravity and flotation recovery, yielding doré from the gravity circuit and a copper-gold-silver concentrate from flotation. The recovery approach is the same proven methodology used in the Stage 2A expansion, though with a more optimized design that includes inline analysis, which we expect will deliver better metallurgical recoveries. Given that the Stage 2A plan significantly outperformed the throughput model, we have designed this new plant to be expandable—able to add additional flotation and filtering capacity, for instance—which provides sufficient room for cost effective upgrades and increased throughput. We’ll now pivot to recent drawn footage of the construction site. For those of you who were on the last webcast conference call, which was in May, you’ll certainly appreciate the considerable progress that has been made.
John Lewins
executiveMore than half of the civil works have been finished at this point, and mechanical installation is scheduled to begin in September. Beginning in the primary crusher area, the raft foundation for the jaw crusher has been poured, and crews are now working on the walls. The workers you see on the right are assembling steel panels that will support wall erection across the various concrete lifts. The crusher is substantially oversized, and that matters for expansions down the road. Moving to the crush or stockpile reclaim area, the raft foundation has been placed and the walls are going up. In the grinding area, you can see this section has advanced the furthest, since the other areas carry lower priority under our construction schedule. Over on the far side is where the ball mill will go, with the feed-end pedestal and jacking cradles finished. Concrete work is presently forming the motor end of the bearing. Nearest to us is the spot for the SAG mill, where the raft foundation has been poured and form work for the mill is in progress. On the right-hand side, concrete for the cyclone tower raft foundation will be poured imminently, and on the left-hand side the excavations for the mill discharge hopper are complete as well.
John Lewins
executiveOn the flotation circuit, the raft's been poured and the pedestals lifted. We've finished the first layer of backfill and compaction. A lot of work has been done at the tailings thickener. Every pedestal has been poured, and the team is now taking off the formwork. The concentrate thickener footings are poured, the pedestals are poured, and we're at the backfilling stage. The last part of the circuit ranks lowest in priority, with wall footing work underway for the concentrate, flotation and storage sheds. Earlier this month we hit a major milestone when the SAG and ball mills arrived at site. The photo on the left shows a ball mill shell and ends along with the SAG mill ends. The SAG mill shell is in country and will be hauled to site imminently. Plenty of other process plant long lead items are on site now too, as the photo shows — the float cells, concentrate thickener, tailing thickener, ball mill feed chute, mill girth gears, and mill components such as the motors. Long lead items for the process plant are running ahead of the construction schedule. We're really excited about the stepped-up process plant construction activity, which is picking up considerable momentum, and we look forward to giving further updates on process plant construction in due course.
John Lewins
executiveRegarding the paste fill plant, we've achieved considerable headway. Front-end engineering design work is essentially finished. A large number of the long lead items have been ordered, among them the live bottom feeders, paste mixers, filter presses and pumps. Efforts toward awarding the construction contract are quite far along. Activity on the other ancillary construction packages — the power station, haul road upgrades, camp upgrades, warehouse, maintenance facilities, and so on — is likewise progressing nicely. In addition to the Stage 3 and 4 expansion surface works, several near term major infrastructure upgrades that will fundamentally transform the underground mine are being implemented. The twin incline, which appears in the image on the right, is essentially finished. It can run trucks that are four times faster and roughly 50% bigger than the ones we use today. It will also do away with double handling at the mine portal and let us haul material straight to the process plant. As part of the expansion, we're likewise installing a series of ore and waste passes so gravity can be used efficiently to link the main plant with the highly productive twin incline infrastructure. And as this video shows, the raised bore rig is up and running, currently boring at a 5 metre diameter raise to improve ventilation in the main mine.
John Lewins
executiveThe advance rates for the raised bore vertical development have come in ahead of what we budgeted, and that's really encouraging. The raise is nearly finished, which is another milestone as we reshape the underground mine's infrastructure for the Stage 3 and 4 expansions. The waste and ore pass system will be the focus of the second raise plan. These different infrastructure upgrades, together with the tripling of mining fronts in 2024, as this slide shows, are positioned to fundamentally transform both the mine and the business into a Tier 1 mid-tier producer in the near term. Turning to exploration, we're drilling the Kora, Kora South, Judd and Judd South vein systems, as well as the Arakompa vein system. K92 reported 140 holes at Kora, Kora South, Judd and Judd South on 6th of May. These results keep showing that this is a world class deposit with meaningful upside for growth ahead. At Kora, the results found a new potential dilatant zone to the south past the resource, expanded and upgraded a large high grade zone marked by the big ellipse with the dashed black line above the mine workings, and extended high grade mineralisation to the south through underground step-out drilling. An important highlight is that exploration to the south keeps hitting high grade copper, as annotated on the K-2 long section, with multiple significant step-out intersections approaching 4% copper, along with high gold.
John Lewins
executiveThese intersections have pushed the high grade copper zone farther south, and they keep validating our thesis that copper grades will be high and possibly rising as we continue drilling south toward the A1 porphyry. Judd has turned in some striking drill results as well, among them a vertical extension of a high grade zone at the J1 vein — the one marked by the big dashed black-line ellipse — with several intersections above one ounce per tonne. As with Kora, those results matter a great deal because they sit directly above the main mine workings, which positions us well to mine that area in the near to medium term for the Stage 3 expansion. The Judd results also hit high grade mineralisation in a step-out hole 300 metres to the north, in an area where essentially no drilling has taken place, highlighted by KODD0055 returning 9.85 metres and 7.85 gram per tonne gold equivalent near surface. Then, on the 10th of June, K92 announced its second batch of drilling results at Arakompa, covering nine holes. Arakompa, shown on the map at right, sits roughly 4 to 4.5 kilometres from the process plant — closer than Kora and Judd. Historically, Arakompa has seen limited drilling, just 18 holes, mostly shallow, totalling only 1.8 kilometres drilled.
John Lewins
executiveThe first drilling results we got back were excellent, and the second batch was even better. We cut a substantial amount of high-grade material, and that includes KARDD0011, which came in at 3.7 metres grading 42.35 grams per tonne gold equivalent. KARDD0009 returned 6.7 metres at 14.35 grams per tonne gold equivalent. And KARDD0006 came in at 12.6 metres at 19.87 grams per tonne gold equivalent. These high-grade loads sit inside a broad mineralised corridor that has been overprinted by porphyry-style mineralisation. That gave us a number of bulk intersections, with an average reported true thickness of 67 metres. Among the highlights, KARDD0006 returned 94.4 metres at 3.14, KARDD0011 returned 86.6 metres at 2.12, and KARDD0010 returned 66 metres at 2.1 grams per tonne gold equivalent, and that hole also ended early in mineralisation. Importantly, as the image on the right shows, Arakompa's target size is very large. So far we have defined a strike length of more than 400 metres, and K92 has drill tested only 20% of the 150 to 225 metre wide corridor along strike. Beyond expanding the deposit along strike, Arakompa has meaningful potential at depth, as the long section image on the left shows, and it also has meaningful potential within the 150 to 225 metre corridor, where the corridor's full width has not yet been drill tested, as the cross section on the right shows.
John Lewins
executiveWe're happy to say that exploration work at Arakompa keeps speeding up. As you can see in the footage we drew up very recently, four drill rigs are now running at Arakompa. At the start of the year, we had a single drill rig. When we held our Q1 conference, two rigs were drilling. And thanks to the strong results we've seen — very strong results, in fact — we've now got four rigs drilling. The rig we've zoomed in on is our fourth drill rig in operation. It sits further toward the east than the other pads, which gives us a somewhat different vantage point for targeting that very wide mineralised corridor. Drilling conditions at Arakompa have been good. The rock is competent, penetration rates remain productive, and they're even faster than what we see at Kora and Judd. We intend to announce a maiden resource at Arakompa by Q1 2025 and look forward to giving updates on Arakompa in the near term. With that, operator, we'd like to begin the Q&A section. Thank you.
Operator
operatorThanks. At this point we'll move into the question-and-answer portion <<operator_script>>. Our first question is from Ovais Habib at Scotiabank.
Ovais Habib
analystCongratulations on a solid quarter, and it's genuinely encouraging to see the expansion moving along nicely too. I have a couple of questions for you, John. First, the second half is projected to be notably stronger than the first half. What will be behind that — mainly grade, throughput, or a mix of the two? Any detail you can share on that would be great.
John Lewins
executiveNow, turning to the second quarter — actually, the second half. During our first half, even though we faced some considerable difficulties, as we mentioned, I'd still say it ranks as our equal second-best opening six months ever. In fact, Q1 came in slightly ahead of budget. For the latter six months, we anticipate throughput rising substantially as the mine continues to ramp up. So the main driver will be more tonnes going through the plant. That said, I believe there's also a slight uplift in grades.
Ovais Habib
analystAnd then, Justin, on that point—when it comes to boosting mining rates, obviously your ventilation raise has begun to move forward. How far along is it toward completion? And am I right in assuming that's what will drive your faster development and mining rates?
Justin Blanchet
executiveOvais, you've got that right. For us, ventilation matters a lot when it comes to expanding the underground operation. That raise bore should break through early in September, I believe. So that's going to be our first raise — roughly 300 metres, with a 5 metre diameter. Broadly speaking, on the progress there, we've been getting more metres per day than we had budgeted. So we're fairly pleased about that. And so at the end of the quarter, we'll have that new ventilation in place — that interim ventilation, since it is an interim step — which should be operating by the end of the quarter, early next quarter. And as you're aware, there's a site visit scheduled for October, and those who are actually making the trip will get to see it and hopefully feel it too, while underground.
Ovais Habib
analystAnd so John, I mean, regarding the ventilation, I mean, this was basically supposed to be done by the end of Q4. So things are moving along really well on the start, as well as how quickly you expect it to be finished then?
John Lewins
executiveWe're at the interim stage here. There's another step still ahead of us — the PUMA incline — and the plan is for that to come down, break down so we can break through, in late Q4 to early Q1, then be up and running in Q1 of next year. That's our long-term ventilation solution, and that's where we're installing two 2-megawatt fans with variable speed — and that ventilation, as things stand right now, covers the life of mine.
Operator
operatorStephen Soock from Stifel has the next question.
Stephen Soock
analystI'll second what Ovais said — congratulations on a strong quarter. It started out rocky, but the results were great. My question leans more toward the plant construction side. If you could shed a bit more light on what sits on the critical path for building the plant. I realize it's a fixed package, but timelines clearly matter there. So what has to get done to ensure it's online by the end of Q2 and fully operational through Q3 next year?
John Lewins
executiveThe primary critical path item is basically the SAG mill and the ball mill, which is usually the situation—not always, but typically when you're building plants. When it came to lead times for the mills, the mill package had the longest one. And as you saw in the presentation, the mills have arrived on site except for the SAG mill shell, which is going to be moved up from the port late this month to site, and that's our critical path. And at the moment we're on track to have that finished and be able to begin commissioning by the end of the second quarter. After that, flotation would probably come next as the following critical area. At this point, I'd say we're fairly comfortable with what we're seeing there. I mean, clearly steel work—a great deal of steel work—is beginning to arrive as well, now that designs there have been finalised, et cetera. And then, naturally, there's the ramp-up of the underground. I suppose the other aspect that was pointed out is that right now our existing plant is capable of doing far more tonnes than 600,000 tonnes per annum, and for the new plant that's a significant positive as well.
Operator
operatorAndrew Mikitchook from BMO Capital Markets has the next question.
Andrew Mikitchook
analystI have just a couple of quick questions. I found that video quite instructive for showing how the plant site is progressing. Would it be fair to say the excavations are more or less all finished, at least the majority of them? So for the civil excavation work, is that timeline risk and those surprises now behind you?
John Lewins
executiveYou're right, Andrew, and that's a — it's a really good thing to zero in on, since it can throw up surprises and so on. So yes, all of that has now been finished, and that covers piling too, where we've had to carry out some piling, and so forth.
Andrew Mikitchook
analystAnd then I believe the phrasing in the press release essentially said the contractor has finished mobilizing. And I think the precise language was that you handed the site over to them. So that's also a significant timeline point — they're on-site, they've got their people there, and they're committed to carrying all of this out, right?
John Lewins
executiveThat's right. It turns into a crucial handover date for the site. So at the moment, they are on site, and their civil subcontractor is on site as well. The steel work subcontractor is expected to mobilize — to begin mobilizing, I believe, by the close of this month, with erection getting underway in September.
Andrew Mikitchook
analystAnd then this is my final question. John, I couldn't write quickly enough while you were talking and answering that earlier question about the paste backfill plant. Could you run through the timeline on that once more? I believe that once it's locked in, it would be one of the major pieces in moving from 57% completed and committed up to a considerably bigger figure. So please take us through it one more time.
John Lewins
executiveThe paste fill plant comes in at just above $50 million, making it, as you correctly pointed out, a very substantial share of our total capital. Long lead items for that have already been ordered — filters, pumps, mixers, et cetera. Right now we're wrapping up the tender documents so they can be issued for the construction work. That covers, of course, the contractor who'll build the process plant, but other parties will be bidding on it too. Commissioning won't begin until Q3 of next year. You really need your process plant to be fairly stable before attempting to commission the paste fill. If not, instability carries over into your paste fill, and that's not ideal, since paste fill, as you're aware, needs stability to perform at its best. That said, our design actually provides greater flexibility than a standard plant would, in that we produce a filtered product, take it underground and repulp it, which gives you more flexibility between the two plants.
Andrew Mikitchook
analystThen, regarding timing, is it fair to think we'll see this shift from tendering to locked in before year end?
John Lewins
executiveDefinitely. Our expectation is that the contract gets awarded in the next quarter, at the start of it…
Andrew Mikitchook
analystWas that during Q4?
John Lewins
executiveAbsolutely.
Operator
operatorOur following question is from Alex Terentiew at Ventum Financial.
Alex Terentiew
analystIt's really encouraging to see solid progress at Arakompa. As you mentioned, there are now four drills operating — four of them — so that's clearly got you excited, and a maiden resource is on the way. My question, though, is whether you can shed some light on what comes next on the permitting and mining side, or the licensing needed, to get ore from Arakompa hauled into the mill. Given that it's such a highly prospective target, I'd imagine getting it into a potential mine plan sooner rather than later would be better. So could you take me through how that process would work?
John Lewins
executiveSo at the moment, clearly, this sits within our EL. Right now, our intention is to file a mining license application next year that would cover Arakompa, Maniape, Mati, plus the Kora and Judd South areas where they stretch past the current mining lease. As I recall, the maximum area permitted for a mining lease is roughly 60 square kilometers. We already have a layout and a design for the mining lease we're after, and it aligns with that requirement. We've also begun talks with the MRA and, in fact, with government about submitting that application. Work has already started, including mapping of communities and people, since that's a key part of the process too. The communities we'd typically deal with for an extended mining lease are largely already within the existing mining lease — perhaps a few extra people, but mostly those already there, though there will be some additions as well. This is a mining lease application. It isn't a special mining lease, and it isn't an expansion of the mining lease, since under the legislation currently in force, there's no capacity to expand a mining lease.
John Lewins
executiveThat said, I would point out that just last week the MD of the MRA emphasized that the government—the government's intention is to amend the act so that mining leases can in fact be expanded. Should that happen before we lodge the application, we would then consider expanding the mining lease instead of submitting a new application. As things stand, though, we are proceeding on the assumption that it would be a new mining lease. From an information standpoint, the difference isn't enormous. There is, however, a view that expanding a mining lease would be faster than securing a new mining lease. Realistically, if you put it in in '25, you'd expect a mining lease granted in late '26, '27, and until that point you really wouldn't be able to begin mining in any case, because as things stand right now, we mentioned 400 metres, 500 metres of strike length at Arakompa. Yet at surface, we've mapped this over roughly 1.7 kilometers. At this stage we don't know what depth extent we're dealing with. And we'll progressively drill deeper and deeper, as well as along strike.
John Lewins
executiveAnd obviously, we're deploying a lot of rigs to this so we can get a genuine picture of what we're dealing with as fast as we can. But I'd kind of note, if you look at Kora — and keep in mind we had underground access there — we've now been at Kora for seven years. We've drilled — I can't recall whether it's 600 holes or something like that. It's a huge quantity of holes that have been drilled to bring us to the sort of resource we have now. And I think we're sitting at 2.4 million or thereabouts in measured and indicated, plus another 4.7, I think, in inferred. And overall, I think the total comes close to 8 million ounces once you factor in what we've already mined. So it will be — we believe, multiple years of drilling out of this deposit. And we certainly see it having a similar strike length to what we see at Kora and Judd, or similar potential strike length as we see at Kora and Judd. And so there'll be a heck of a lot of drilling, and a lot of that drilling will come from underground. Potential access is similar to the Kora type model, in that you're coming in the side of a mountain and going up into your deposit.
John Lewins
executiveRealistically speaking, the soonest you'd likely be able to consider it is '27. That's where the new plant's capacity and its potential to reach Stage 4 without needing to restart the existing plant really matters, since obviously that leaves you with an idle plant sitting there, capable of 600,000 tonnes per annum or whatever that figure happens to be, which you could deploy for something like Arakompa. Apologies for the lengthy reply — we've certainly given this plenty of consideration, I can assure you.
Alex Terentiew
analystOkay, that's excellent. It matters a lot for the next stage, so I'm grateful you laid it out so clearly.
Operator
operatorThat brings us to the end of the queue — no more questions remain. With that, the question-and-answer portion is finished. I'll now hand the conference back to John Lewins, who may have some closing remarks.
John Lewins
executiveOkay, thank you, Brenda, and thanks for being with us on this latest quarterly update. In a lot of respects, we feel this could be the most significant quarterly results presentation we've had, because our transformation of the Kainantu Mine is now quite far along, with Stage 3 implemented and the operation very much moving toward delivering what we've, I suppose, been pointing to and committing to for several years — taking it to Tier 1 status as a producing mine and a long-life mine. When you're there on-site — and some people will be on-site in October — you'll witness enormous progress toward that goal, both below ground and above ground, and we observe that progress every day. It's genuinely exciting to watch. I've just spoken at the PNG Investment Conference in Brisbane, something the government actually asked us to do, since we are currently the largest investor in Papua New Guinea. So we receive considerable recognition and considerable backing from the government for that. Turning to operations, this first half of the year was unquestionably difficult. And even so, we actually delivered, I believe, an equal second-best first half of the year that we've had.
John Lewins
executiveAnd we're in a strong position—well set up—to hit plus 70,000 ounces in the second half of the year. Obviously, we're sitting in a very positive price environment, and we're doing that while we're constructing, which is really positive for us in terms of cash flow and obviously in terms of ramping up production—perfect timing to be seeing that strong price environment. On exploration, we're obviously extremely excited by Arakompa. We began the year with one rig there. Now we've got four. More results will come soon. But as you'll have seen from the first batch of results—the first two batches we put out—it's a really exciting prospect, and it's one of a number of high-grade prospects we intend to be drilling over the next couple of years. We spoke about Maniape, which sits just next to Arakompa. And certainly next year, we see ourselves beginning to drill at Maniape and potentially Mati as well. So we're also looking at the first quarter of next year to bring out that first resource at Arakompa. And again, for us, very exciting times.
John Lewins
executiveWe’re eager to share the operational results we’re seeing and to let people see them for themselves — to see what’s happening with our construction of Stage 3 and what’s happening with exploration through the site visit we have planned in October — and then, obviously, to share that in our next quarterly results. So thanks again, everyone, for joining us on this call, and we look forward to the next one. Thank you very much.
Operator
operatorThat brings us to the end of today's conference call. Your lines can be disconnected now. Thanks for joining us, and we hope the rest of your day goes well.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete K92 Mining Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to K92 Mining Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in K92 Mining Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.