K92 Mining Inc. (KNT) Earnings Call Transcript & Summary
November 16, 2026
Earnings Call Speaker Segments
David Medilek
executiveThanks, operator, and I appreciate everyone joining us for K92 Mining's call on our 2026 third-quarter financial results. We hope things are going well for you and your families. Joining me are Justin Blanchet, our Chief Financial Officer, and Rob Smillie, VP, Exploration. As a lot of you know, on October 1 I stepped into the CEO and Director roles, succeeding John Lewins. I want to acknowledge John's contribution to K92's growth over more than ten years. I've served on K92's leadership team since 2019, and I'm pleased to steer the company through the next phase of growth ahead. Getting more output out of our operations without compromising safety, and bringing our growth projects in on plan through disciplined execution on both the operational and project sides, sit at the top of my list — alongside advancing the sizable exploration upside we have. Responsible operation remains a firm commitment, as does partnering closely with the communities that host us and with the government of Papua New Guinea; what we are concentrating on is ensuring that the success we achieve translates into enduring value for shareholders, employees, our communities and Papua New Guinea. Once management has finished its comments, we will take questions from the line. Because forward-looking statements will be made on this call, we ask you to review the cautionary notes and risk disclosure in our MD&A and on Slide 2 of the webcast presentation; unless otherwise noted, please also remember that all dollar amounts discussed on the conference call are in United States dollars. We begin with safety, K92's top priority. The chart on the left shows that our total recordable injury frequency rate, or TRIFR, has remained far under the average reported by members of the International Council on Mining and Metals, a group that includes many of the largest mining companies in the world. Starting in 2023, we placed a stronger focus on safer behaviors and managing risk proactively, and our TRIFR has continued to improve alongside that effort. As the chart on the right illustrates, we have substantially expanded hazard identification and risk assessments, and we have also concentrated on raising their quality. Such activities serve as key leading indicators of strong safety results. Meanwhile, we keep enhancing our safety technology systems and our facilities. We completed the full rollout of SkyTrust, our cloud-based platform for safety and compliance management, earlier this year. That has improved how we handle incidents, inspections, audits, injury management and the wider range of occupational health and safety documentation. In addition, we are building a new training center for underground mining that will complement the service facilities we already have. These things are going to reinforce both the classroom and hands-on preparation that new hires receive prior to starting in their positions. What we're ultimately aiming for hasn't changed at all: zero harm throughout our entire workforce. Another key component of our safety strategy is being ready for emergencies. I'm happy to point out how well our team did at the 2026 National Emergency Response Challenge, hosted by the Mineral Resources Authority and held late in October. We took first place in 3 categories — hazmat, team safety and Best Captain — and came in second for Best Team overall. Those outcomes show how strong our emergency response capabilities are, along with our training and teamwork. I'd like to congratulate the entire team on this outstanding accomplishment. Turning now to our broader commitment to responsible mining. Our focus remains on delivering lasting benefits to the communities in Papua New Guinea that host our operations. A central element of that effort is the economic contribution we keep growing, and K92 is still one of the top taxpayers in the country's mining industry. Following the close of the quarter, in October we made our third corporate tax installment, amounting to PGK 231 million, which lifts corporate tax payments for 2026 to a total of PGK 758 million. As of the end of October, taxes and royalties paid or accrued in 2026 came to PGK 991 million, and we expect that number to exceed PGK 1 billion by the time the year ends. These contributions highlight the substantial economic benefits that K92 provides to Papua New Guinea. We're also committed to long-term community partnerships in Papua New Guinea. We were very pleased to announce not long ago that K92 is a major, foundational partner of the PNG Chiefs as they get ready for their historic entry into the National Rugby League competition. Rugby League runs deep in Papua New Guinea and in the communities where we work. Our support has grown from grassroots development led by Rugby League legend and K92 team member Marcus Bai to partnerships with the PNG Hunters and the Goroka Lahanis, including backing for women's Rugby League. We're staying with the PNG Chiefs all the way to 2031 — a long-term partnership that keeps us focused together on community engagement, youth development, and opening up opportunities for Papua New Guinea, while also deepening ties with our staff and the communities we serve throughout PNG. Now on operating performance: we're glad to share that this was another strong quarter, and the standout was a major milestone — since we declared commercial production in February 2018, we've now produced more than 1 million gold equivalent ounces. That figure speaks to K92's extraordinary growth story, one powered by exploration wins that were turned into one production expansion after another, all delivered through solid operational and project execution. In Q3, we produced 49,776 gold equivalent ounces. That consisted of 46,063 ounces of gold, roughly 1.95 million pounds of copper, and 55,746 ounces of silver. Compared with Q2, gold equivalent production rose about 8%, and it was our second-best quarterly production figure ever. Just as important, we hit this while setting major records in mine development, ore mined, ore processed, and total tonnes mined. This quarter shows the beneficial effect of the new Stage 3 process plant, the continued ramp-up of our second mining front, and the underground infrastructure investments we've made over the past several years. For the quarter, on a byproduct basis, we recorded cash costs of $936 an ounce gold and all-in sustaining costs of $1,441 per ounce gold. On a co-product basis, the figures were cash costs of $1,144 per ounce gold equivalent and all-in sustaining costs of $1,608 per ounce gold equivalent. The chart shows that since early 2023, all-in sustaining costs have stayed meaningfully above cash costs, which reflects K92's substantial investment in the Stage 3 expansion. We expect costs to come down once the expansion is finished and the operation reaches steady-state production. It's worth noting that although those levels are elevated for the time being, K92 remains within the bottom half of the industry's AISC curve — a reflection of the strong quality of the Kainantu Gold Mine and the cost discipline the company continues to prioritize. Turning to processing, Q3 set a record for total tonnes processed, up 11% from Q2 and 82% against Q3 2025, and it marked the third complete quarter during which every bit of material passed solely through the new plant, which continues to perform very well. Gold recoveries averaged 94.1% and copper recoveries 94.9%, each exceeding the parameters set out in our updated definitive feasibility study, and gold recoveries have now topped the study parameter for a 10th quarter in a row. Physicals advanced significantly in the third quarter. As mentioned earlier, we achieved record tonnes processed. Material mined in total reached a record 485,812 tonnes, which is 14% higher than Q2 and 37% higher year-over-year. Ore mined likewise set a record at 252,744 tonnes, representing a 66% increase over the third quarter of 2025. In September 2026, we noted that ore tonnes mined equated to an annualized rate of 1.13 million tonnes per annum. Accordingly, we are already progressing quickly toward the Stage 3 run rate tonnage of 1.2 million tonnes per annum. During the quarter, mine development hit a record 3,486 meters, which is 41% higher than a year earlier. That averages out to 1,162 meters each month—about 16% more than the 1 kilometer per month that Stage 3 expansion development calls for. In July, we set a monthly development record of 1,220 meters, surpassing the Stage 4 expansion's monthly requirement of 1,200 meters. Notably, we posted these results before several key enablers were in place, such as commissioning of the Phase 4 primary ventilation upgrade, and before we add another development jumbo later this year as planned. Lower Kora, our second mining front, kept ramping up over the quarter, and the third front, over at Twin Incline, produced its first stope ore in September. As for what's ahead, we continue to anticipate that Q4 will be the year's strongest quarter for production, backed by a planned stoping sequence with higher grades, rising mining rates, and additional gains in ventilation and material handling. Our 2026 production guidance of 190,000 to 225,000 ounces of gold equivalent is reaffirmed. At this point I'll pass the call to Justin Blanchet, our Chief Financial Officer, who will go over our financial results.
Justin Blanchet
executiveThanks, Dave, and good morning, everyone. K92's revenue for the third quarter came in at $176.5 million, versus $177.5 million in Q3 2025. We sold 41,587 ounces of gold during the quarter at an average selling price of $4,236 per ounce, compared with 45,006 ounces sold in Q3 2025 at an average price of $3,361 per ounce. As of September 30, 2026, gold in inventory, including concentrate and dore, stood at 12,511 ounces, which is 3,286 ounces higher than at the end of June. Cost of sales for the quarter was $64.7 million, versus $43.8 million in Q3 2025. Excluding noncash items, cost of sales came to $49.3 million, compared with $35.5 million in the prior year. Higher cost of sales largely reflected unprecedented underground mining and processing volumes associated with ramping up the Stage 3 expansion, as ore mined climbed 66% and ore processed jumped 82% versus the prior year. Depreciation and depletion increased as well, reaching $14.5 million versus $7.1 million in Q3 2025, following the new Stage 3 process plant's start of commercial production on January 1, 2026. Cash flow from operating activities, before working capital changes, came to $72.5 million this quarter, down from $101.8 million in Q3 2025. At September 30, 2026, K92 held a record $389.9 million in cash and cash equivalents, alongside working capital of $425.9 million and net cash of $355.4 million. That compares with $349.4 million as of June 30. We made another $5 million repayment on the Trafigura credit facility during the quarter. By September 30, $35 million remained outstanding, and $60 million was still accessible. Our gold put option program also continued, providing downside protection for 10,000 ounces each month at a strike price of $3,500 per ounce through December 2026, while leaving room to benefit from higher gold prices. In July, the operating subsidiary we have in Papua New Guinea made its first dividend payment of roughly $100 million to K92 Mining Inc. Dividends in Papua New Guinea are subject to a 15% withholding tax. About $15 million was withheld and paid, and that amount sits in our current tax expense for the quarter. Our accounting also shifted because of the first dividend. Through the prior quarter, we hadn't recorded withholding tax on earnings retained in Papua New Guinea, since we were reinvesting in the expansion and paying down internal loans. With those internal loans now fully repaid and dividends expected to continue being paid in Canada, IFRS calls for us to record a 15% dividend withholding tax on all the retained earnings accumulated, regardless of whether they've been distributed. That catch-up shows up as the $90.3 million deferred tax expense in Q3. Here are the key points. First, it's noncash. Regarding that $90.3 million, no payment has been made; it's carried on the balance sheet as a deferred tax liability, and it only turns into something payable once dividends are distributed, at that same 15% rate. On top of that, this represents a one-time catch-up tied to earnings from a previous year, and we don't expect another adjustment of that size. Going forward, withholding tax will be accrued each quarter on the new Papua New Guinea earnings, although it won't affect cash flow until a dividend is paid. Third, the deferred tax expense has no effect on our cash costs, all-in sustaining costs or operating cash flow. We ended the quarter with cash of $389.9 million, which is a record for us, after paying about $15 million in dividend withholding tax. To put it plainly, we earned $96.3 million before tax in the quarter. The net loss we reported, $39.5 million, or $0.16 per share, comes from this one-time accounting catch-up. If you set aside that charge and a small loss on our gold put options, adjusted net earnings were $52.5 million, or $0.21 per share. As Dave mentioned, Kainantu produced 46,063 ounces of gold, roughly 1.95 million pounds of copper and 55,746 ounces of silver during the third quarter. Our sales came to 41,587 ounces of gold, about 1.91 million pounds of copper and 53,575 ounces of silver. When you look at it on a byproduct basis, cash costs landed at $936 per ounce, while all-in sustaining costs were $1,441 per ounce. In Q3 2025, those figures stood at $694 and $1,254, respectively. The increase is largely driven by a lower head grade — 6.1 grams per tonne of gold, down from 10.7 grams per tonne — plus higher operating costs from ramping up throughput for the Stage 3 expansion, during which ore mined rose 66%. Partly offsetting these pressures were higher byproduct credits. With all-in sustaining costs at $1,441 per ounce, that came to roughly 1/3 of the $4,236 realized gold price, giving us a margin of about $2,800 per ounce — which really reflects our cost discipline and the quality of the Kainantu Gold Mine. As the Stage 3 expansion ramp-up is almost finished, we anticipate that economies of scale will bring unit costs down, and we are still well placed to meet our 2026 guidance ranges for cash cost and all-in sustaining cost. I'll now turn the call back over to Dave, who will provide an update on our growth projects.
David Medilek
executiveThanks, Justin. I'll now provide an update on the Stage 3 and 4 expansions, as well as the key infrastructure projects underpinning our production growth. In our view, these Stage 3 and 4 expansions will fundamentally transform K92 into a Tier 1 mid-tier gold producer. With the Stage 3 expansion, we support a processing rate of 1.2 million tonnes per annum and average annual output of roughly 300,000 gold equivalent ounces at run rate. Stage 4 should lift average annual production beyond 400,000 gold equivalent ounces at run rate, and commissioning of the expanded plant is targeted for late 2027. The Stage 2A plant, with a capacity of 600,000 tonnes per annum, has been sitting idle and offers extra capacity for future growth past Stage 4. By September 30, roughly 98% of the growth capital for the Stage 3 expansion had been spent or committed, and the project is still within budget. In late October, we were delighted to welcome a sizable group of analysts and investors for a thorough two-day site visit to the Kainantu Gold Mine, so they could witness the significant transformation taking place there firsthand and also highlight Papua New Guinea's mining-friendly jurisdiction. Above ground, the tour featured stops at the new state-of-the-art Stage 3 process plant, with a capacity of 1.2 million tonnes per annum, as shown in the image. The operating tailings filter plan — this is part of the paste fill circuit and ancillary infrastructure, which includes the new workshop and power station. The two also gave an overview of the haul road upgrades leading to the underground portal. A helicopter tour covered our exploration sites and provided aerial views of the operation, and participants viewed an extensive selection of drill core from the many exciting deposits we are currently drilling. During the underground tour, the group saw several key enablers firsthand, including the high-speed twin incline, internal ramp and material pass, as well as the primary fans operating during file commissioning. During that trip, there was also an extensive tour of the paste plant being built underground, plus a development phase of high grade? I'm happy to say the main ventilation fans have now been fully commissioned and are running. A milestone will be covered in greater detail later on in the presentation. On the whole, we feel the visit was a great chance to show how large our infrastructure spending is, how much progress we've made so far in growing the operation, and the operating strengths that underpin K92's coming growth phase. As the long section shows and as the site visit made clear, the underground mine has been substantially transformed. Both of the twin inclines wrapped up during 2024, and the internal ramp system followed in Q1 of 2026. Finishing the first material pass in Q3 of last year and the second one in June 2026 has already delivered a sizable lift to our underground material handling capacity. The third material pass remains on schedule to come online before the year is out. Excavation for a fourth pass is also expected to finish by year-end, with that pass starting operations in Q1 2027. Another crucial enabler for the Stage 3 and 4 expansions — Stage 4 especially — will be the paste fill system delivery, which brings more flexibility in sequencing and better stoping performance: less dilution, lower waste rehandling, greater mining recoveries and reduced TSF demand. On this slide we've included a number of images to show just how significantly some of these key enabler projects are paying off. Beginning with the twin incline, the picture at top left shows the incline we acquired from Barrick, which handled every production stoping tonne until not long ago. The image beside it shows one of the new inclines we finished, allowing trucks 50% bigger and speeds far quicker. Late in January we finished the internal ramp, so that all of the mining friends can now connect to the twin incline, which is highly productive. As the image makes clear, this was a deal for the crews, with the banner reading, we are one mine. Prior to that, we ran 2 separate crews and fleets — one for the lower mine and one for the upper mine, respectively. Today we're far more efficient as 1 mine. As the prior slide showed, most of the resource lies above the twin incline, handing us a substantial gravity advantage that we're capitalising on by installing material passes. We've got two material passes in operation right now — one handling ore, the other handling waste — and they're already delivering that gravity benefit. As we mentioned on the last slide, two additional passes should be commissioned before long. In the lower-left image, you can see a truck being filled at a sublevel close by, driven a brief distance, and then dumping its load straight into the ore pass. At this pass, the material drops about 350 meters in vertical descent. After that, it gets loaded onto trucks within the twin incline. So as the visual shows, having these separate ore and waste passes means material can now travel from the upper part of the mine down to the main haulage infrastructure with greater efficiency. To reiterate what I mentioned before, we are really happy to share that the Phase 4 primary ventilation upgrade has been running at full operation since late October. In this drone footage, it's clear that a considerable amount of air is being pushed through the ventilation chamber even when the fans operate at 50% capacity. These 2 big primary fans took the place of a number of smaller, less-efficient fans that had been spread out across the mine before, forming the primary ventilation circuit. The new setup pulls fresh air into the mine at the twin incline and the old incline, and it sends air out to surface via the new Puma vent incline. That's a major milestone for the operation. We are addressing airflow constraints so that reentries after blasting happen more efficiently, traffic moves more smoothly, and we can operate a greater number of working areas. This capacity enhancement exceeds by a wide margin what the present stage IV expansion and life of mine call for, accommodating 600 cubes per second of air flow, and it leaves headroom to raise total air flow past 700 cubes per second. The fans come equipped with variable speed drives, allowing them to operate at reduced speeds for power savings ahead of being stepped up progressively as the mine expands and ventilation demand increases. Over the quarter we achieved considerable advancement on the surface haulage road and river crossings, completing the Kokomo and Kasisi River crossings. With the Baipa crossing finished in April, all three crossings can now handle traffic, and the Stage 3 haul road is essentially finished. The leftover Stage 4 upgrades—covering targeted road straightening, realignment and better gradients—are still set to wrap up by year-end. Thanks to these major Stage 3 haul road investments, surface haulage payload has risen from roughly 20 tonnes to 60 tonnes, bringing faster haulage cycles, cheaper unit costs and less congestion, which backs the greater material movement rates needed for the Stage 3 and 4 expansions. Five of the 8 new 60-ton Volvo trucks have arrived on site, with the remaining 3 due for delivery this quarter; this fleet is being brought in progressively, with expected benefits towards the end of the year and into early next year.
David Medilek
executiveBeyond finishing several infrastructure enablers for the expansion, more mine development keeps opening new mining fronts. Stopin g began in April at Lower Kora, our second mining front, and it kept ramping up through Q3. September brought another key milestone as well: first stope ore arrived from our third mining front in the Twin Incline area. With paste fill coming in, we expect to grow to 4 mining fronts in 2027. Notably, given the big jump in lateral development rates across the past 3 quarters, including a record month in July that beat the Stage 4 expansion development requirement of 1,200 meters per month, we intend to open existing and new sublevels more quickly to create more operational flexibility. With one more jumbo added this quarter and key enablers delivered, development should ramp up further in 2027, with a target of 1,400 meters per month. We also have significant equipment upgrades in progress this year, as the table on the left shows, with 25 new major equipment units set to arrive between late last year and the end of 2026. Counting replacements of older units plus new additions, our overall fleet will grow by 16 units. That sizable fleet investment makes sure we have enough capacity beyond the Stage 3 expansion. On the production side, 4 new loaders joined the fleet this year, made up of 2 additional units and 2 replacements, and a large Sandvik 621i loader is due in Q4. A new explosive charging unit arrived on site during the quarter and is now running, and a new long-hole production drill was commissioned in late April. Two new underground haul trucks remain on track to join the fleet by year-end. A new development jumbo and a cement-agitated truck are also due toward the end of the year, further growing the underground fleet and our development capability; we additionally have 3 new Sandvik 422i development jumbos on order, arriving in the first half of 2027, to replace older units and further improve development reliability and fleet availability. As noted before, we are also close to unlocking higher underground and surface haulage productivities through the gradual introduction of the new 60-ton Volvo haulage fleet. Supporting infrastructure stays a key part of our expansion program. We're happy to report that the new maintenance facilities are finished and have been handed over to operations. As you can see, it is a world-class facility, featuring dedicated heavy machine rebuild center facilities to handle our growing equipment fleet. As previously reported, the Phase 2 power station expansion wrapped up in May, lifting prime power capacity from 10.7 megawatts to 15.3 megawatts. That supplies the capacity needed for the Stage 4 expansion plus extra standby power to support operational reliability. Ever since we commissioned that new power station in October 2025, the operation has experienced very few power interruptions at either the process plant or the underground mine, which really shows how well these upgrades are working. We've made considerable headway on the surface paste fill filtration plant, the surface storage facility and the underground paste fill plant packages, and together those make up the paste fill circuit; this video shows a filter press discharging filter cake as a filtration cycle wraps up at our surface tailings filtration plant. That plant is operational now, with production optimization still ongoing, and it marks an important milestone in delivering our overall paste fill system. At last month's analyst and investor site tour, those attending got to watch a complete filter press cycle for themselves. When the underground paste fill system reaches full operation, roughly 60% of tailings are expected to be redirected underground, which will materially cut the capacity needed for surface tailings storage. Filter tailings will be turned into paste fill for backfilling stopes, which improves ground stability and supports higher mining rates as we keep ramping up production. Over at the surface paste binder blending area and filter cake storage facility, structural, mechanical and piping works wrapped up in Q3. The electrical and instrumentation installations that remain are moving toward commissioning this quarter. At the underground paste plant, every major piece of equipment is now in place, including the silo hopper, the paste and colloidal mixers on the 1205 level, both paste pumps and the paste hopper on the 1170 pump chamber level. The remaining civil, structural, mechanical and electrical works, along with the paste reticulation installations, are continuing to move forward, with commissioning targeted to begin late this quarter; we were glad to showcase the rapid progress in these areas during the analyst and investor site tour, where we visited the 3 levels that make up the underground paste fill plant system; to sum up, the third quarter was another significant stretch of progress across the Stage 3 and 4 expansions, with the Phase 4 ventilation upgrades, the Stage 3 expansion haul road upgrades and the maintenance workshops all now carrying a green checkmark. As you can see, most of our major infrastructure projects are now finished or close to finished, which puts us in position to capture the benefits of these investments through higher production rates, greater operating flexibility and improved cost efficiencies. Importantly, as these projects shift from construction into operation, we expect them to help deliver continued production growth and increased free cash flow generation. I'll now hand things over to Rob Smillie, VP Exploration, for an update on our exploration activities.
Rob Smillie
executiveThanks, Dave. Long-term growth at K92 still rests heavily on exploration. Our programs remain centered on expanding the Kora and Judd vein systems, advancing Arakompa, and evaluating grassroots targets with significant promise throughout our district-scale land package. At present, seven underground rigs are drilling at Kora and Judd surface, five surface rigs are active at Arakompa, one is working at the newly established Judd North area, and a contractor rig is operating at Wara. An additional surface rig is undergoing rebuild for scheduled deployment at <<inaudible>> during Q1 2027, which takes our total fleet, counting this rig, to 15. We've also placed orders for two additional underground rigs and two more surface rigs, scheduled to arrive in 2027, which brings our fleet to 19 rigs in total. That significant increase in mine development rates is strategically important for exploration as well, because it enables us to gradually establish new underground drilling platforms for resource expansion drilling. At Kora, drilling continues to move forward simultaneously across multiple fronts along more than 2.5 kilometers of drill-defined strike. From the Twin Incline, we're targeting Kora Deeps, Kora North Deeps and Kora South Deeps, while a separate program run from the 1205 level drill drive is testing Kora South. At Kora Deeps, drilling targets down to 500 meters RL over the next 12 months, building on thick high-grade mineralization intersected below the twin incline. Results keep delivering strong dilation zone intercepts, and greater drill density is extending and improving how we understand the high-grade zones. Importantly, drilling has also outlined a substantial high-grade copper zone south of Kora across both the K1 and K2 veins, with copper grades rising at depth in K1. The consistency of these high-grade intersections, including multiple intercepts above 4% copper, is especially encouraging and points to development of a significant copper gold corridor extending towards the A1 porphyry target. Since Kora remains open along strike, up dip, and at depth, we believe there is substantial room for further resource expansion; we plan to publish revised mineral resource and reserve estimates for Kora and Judd late in the first quarter of 2027. Similarly, at Judd, drilling continues to test the Judd South and Judd Deep systems, which are still vastly drilled, and the defined strike length at Judd has increased by over 130% since the end of 2021. Deep drilling at Judd is advancing from the Twin Incline, aiming down to 500 meters RL during the coming 12 months, while drilling at Judd South is also ongoing. We're pleased to report that during the third quarter, surface drilling also kicked off at Judd North, aimed at testing a potential extension spanning more than 800 meters along strike and 250 to 500 meters down-dip. Highlights from earlier work in this zone include 20 meters grading 14 grams per tonne gold equivalent over 12 meters true thickness, plus 3 meters at 15 grams per tonne gold equivalent over 2 meters true thickness. The Judd system is still largely underexplored and remains open in every direction. Among the most exciting opportunities in our portfolio is Arakompa, located about 4.5 kilometers from the Kainantu process plant. Arakompa contains high-grade vein mineralization, wider bulk-tonnage mineralized zones, and a porphyry target that is starting to emerge. In the update we gave for June 2026, and as those lengthy sections make clear, we presented assay results covering 33 holes from the surface diamond drill program — part of the 100 holes we've disclosed so far. Thanks to that campaign, our picture of the AR1 and AR2 high-grade loads has widened considerably, and it demonstrated meaningful potential for resource scale along with strong uplift. A high-grade zone at AR1 stands out, reaching as much as 400 meters along strike and up to 300 meters vertically, with an average of 9.47 grams per tonne gold equivalent across 4.3 meters true width. We likewise enlarged our bulk tonnage zone by a substantial margin, and two results lead the way: 99 meters at 2.9 grams per tonne gold equivalent, together with 105 meters at 2.26 grams per tonne gold equivalent. The June results further included significant porphyry step-out intersections that followed discovery hole KARD 0065. Highlights were 1,251.2 meters at 0.3% copper equivalent, 800.7 meters at 0.33% copper equivalent, and 494 meters at 0.35% copper equivalent; these holes came in out of potassic alteration, which gives encouraging vectors toward a potentially higher grade core. Given how significant this target is, we've allocated a second rig to speed up porphyry drilling. Since our last update, an additional 23 holes have been completed. The maiden resource for Arakompa is targeted for late 2026 or the first quarter of next year. We look forward to providing an update in due course. This chart shows just how fast Arakompa has advanced — from a mere 2 holes reported in February 2024 to 100 holes in the most recent release. With every press release, the mineralized footprint has kept expanding, and the growing density of drill infill is making our geological model stronger through each drilling phase. We keep seeing significant upside from the high-grade veins, the bulk tonnage zones, and the porphyry target emerging to the south. In our view, Arakompa is a meaningful opportunity for K92's future resource growth and possibly for additional production sources across the wider Kainantu district. Now moving to Mati Maswan. Here's a near-mine target we're treating as top priority, sitting right next to ML 150, no more than 1.6 kilometers from where we currently mine, and it has never been drilled before. What matters here is that the mineralization sits in northwest trending faults that run parallel to Kora and Judd, hosted in the same Bena sediment, and we've mapped 4 potential gold lodes within those faults, each 2.5 kilometers long. Over the past 2 years we ran a systematic soil sampling and trenching program to define our drill targets. Artisanal workings already there point to strong vein thickness in the area, and we're extremely excited to drill test it, with the start scheduled for Q1 2027. The fact that we have an undrilled target with high prospectivity, Mati Maswan, sitting within two kilometers of our existing mine workings shows we have only begun to tap what Kainantu can really deliver. Over at Wara, roughly 10 kilometers to the southwest of Kora and Judd, our inaugural scout drilling campaign is now in full swing. Right now we are putting vein targets to the test — targets that trenching allowed us to pinpoint — and during this quarter we completed 10 holes. The scale of the system at Wara, along with its location, is what has us excited, because it sits on the very same regional structural corridor that is home to Kora, Judd and Arakompa. Our service work has defined an epithermal vein system over roughly 3.5 by 3.5 kilometers, and it stays open along strike toward the northeast and the southwest. A number of rock chip samples ran above 20 grams per tonne gold, and the best of them came in at 26.3 grams per tonne. Right now we are testing how those veins persist beneath the surface. On the whole, we stay highly encouraged by how large and how varied the exploration opportunities are throughout our land package, which covers more than 830 square kilometers. Looking ahead to 2027, we're keen to expand our exploration programs further, increasing our combined and service exploration fleet from 15 simultaneously operating rigs to 19. David, I'll now return the call to you for your closing remarks.
David Medilek
executiveThanks, Rob. To sum up, K92 posted yet another quarter of robust operating and financial results, with output coming in as our second highest ever at 49,776 gold equivalent ounces, several operational records set and a record cash balance of $389.9 million, which further fortifies the business as we move forward with the Stage 3 and 4 expansions; we also hit a major milestone by producing over 1 million gold equivalent ounces since commercial production started in February '18. That operating momentum is highly encouraging, and we are pleased with how key infrastructure projects were delivered in the quarter and with the swift progress on the remaining key projects. Going forward, we anticipate the fourth quarter will be our strongest production quarter this year, and we stay confident in our full year production guidance of 190,000 to 225,000 ounces of gold equivalent. Exploration keeps moving ahead across both near mine and regional drill programs, and we look forward to sharing updates in due course. Throughout our business, we stay focused on safety, on supporting our communities and on delivering sustainable benefits for our stakeholders. With that, operator, we are glad to open the line for questions. Thank you, operator, and thanks to all of you.
Fanming Zeng
analystMy first question concerns capital allocation. Given that Stage 3 CapEx is 98% spent and Stage 4 is either a low CapEx extension or production is ramping up, how should we think about 2027 spending priorities across Stage 4, our growth projects, exploration versus return on capital?
David Medilek
executiveYes. Thank you very much, Timing, for the question. You're absolutely right that the Stage 3 expansion spend is largely behind us, 98% spent or committed. I think the spent figure is close to 96%, and we are tracking very, very much in line with the guidance we put out at the beginning of the year, in terms of the Stage 4 expansion capital. I'll talk about 2026 first. We did provide guidance. What I do expect is that you'll see a slight underspend relative to guidance, because we did defer the Powerline project, and we brought forward the Stage 4 power plant upgrade instead. As for 2027, what I'd say is that we are currently in the budgeting process. So I don't want to give you guidance at this point until we have an approved budget.
Fanming Zeng
analystAnd I’ve got one more question about our tailings capacity. I notice the EIS submission has shifted to Q1. Could you remind me how many months of capacity are left in our current tailing facility at the throughput we’re running now? And do you see any risk when it comes to the tailings versus our ramp-up in throughput?
David Medilek
executiveYes; so with our existing tailings capacity, there are several lifts that still need to be completed. And as shown in our integrated development plan, that carries us through until mid 2029. So the EIS you’re referring to relates to the Baipa tailings facility, which is a new tailings facility. And we’re actually aiming to have that approved and built ahead of what the existing tailing billings facility requires, because depositing the tailings in that new facility actually becomes cheaper for us than the existing facility. .
Alex Terentiew
analystLook, after I visited the site last month and saw for myself the substantial work that has been done, I really don't have a lot of questions, but there are 2 small ones I do have. First, just on Q4, you're saying it will be our strongest quarter of the year, and that matches my numbers. But could you give us a bit of color? Is it a mix of both throughput and grades, or one or the other? I know in Q3, I believe you had record throughput, and I'm just trying to gauge for Q4 whether you'll still be running the mill full out, or do you think you can go back to some of your badging like you did before but put through higher grades?
David Medilek
executiveYes. Thanks Alex. So on Q4, we certainly expect an upward progression in terms of the physicals. We do see it as the strongest quarter, driven by a combination of higher physicals and also a higher-grade stoping sequence, and that positions us for what we see as the strongest quarter of the year.
Alex Terentiew
analystAll right, great. So perhaps for Wara and Mati Maswan — Robert, you touched on part of this in your remarks, but I apologize if I missed it. Could you give us a bit of a breakdown on the schedule for the work planned at these targets? I know we discussed them fairly extensively during the site tour as well; but for Mati Maswan and Wara specifically, just Q1, Q2 — when do you expect drilling to begin there, what cadence of drilling do you foresee, and when might we begin seeing results from those 2 targets.
David Medilek
executiveYes. I'll jump in on that, since Rob is in an area with poor comms right now. For Mati Maswan, we're aiming to be there in Q1; pad construction has actually already begun. And as you can probably tell from the profiling in the conference call, we're quite excited. There's some really good surface sampling, really good trenches, and we also have confirmation in terms of the strong mineralization that some of the artisanals are mining. As for Judd North, we have a rig on it that arrived in September. There are plans to bring in another drill rig there. There are also plans for a rig at what we call Arakompa North, which is a northern extension of Arakompa, which you would have seen at the site visit — pad construction is currently underway to set up that site. So what you're going to see from us, and as you saw from Rob's comments, is that we're certainly ramping up the drill rigs, and we're ramping the drill rigs where we'll be drilling multiple high priority targets concurrently, which I think is quite exciting; and then alongside that, there is increased activity in terms of the underground, which is certainly going to benefit from the increased development rates, which is opening up more drilling out forms in more areas.
Operator
operatorSince no one has any questions, that brings the question-and-answer portion and today's conference call to a close. You're free to disconnect your lines now. Thanks for joining us, and enjoy the rest of your day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete K92 Mining Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to K92 Mining Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in K92 Mining Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.